Professional Documents
Culture Documents
Standardized Work
Department: Die Maint revision
Position: All
Heating steels before and after Welding date: 11/7/2018
Prepared By:
MFG Proc No 249 Rev Level 000 file:///conversion/tmp/activity_task_scratch/562926672.xlsx date of last revision: 14Feb17
UNCONROLLED IF PRINTED
Checked By:
MFG Proc No 249 Rev Level 000 file:///conversion/tmp/activity_task_scratch/562926672.xlsx date of last revision: 14Feb17
UNCONTROLLED IF PRINTED
Standardized Work
Department: Die Maint revision
Position: All
Ball Lock Punch Retainer date: 4/13/2020
Prepared By:
Checked By:
WIP Measurement/ Quality Check Safety
Setting
Approved By: # details revision date Name
MFG Proc No 249 Rev Level 000 file:///conversion/tmp/activity_task_scratch/562926672.xlsx date of last revision: 14Feb17
UNCONTROLLED IF PRINTED
Standardized Work
Department: revision
Position: date:
Prepared By:
MFG Proc No 249 Rev Level 000 file:///conversion/tmp/activity_task_scratch/562926672.xlsx date of last revision: 14Feb17
UNCONTROLLED IF PRINTED
Standardized Work
Department: Die Maint revision
Position: All
Checking a Ball lock Retainer date: 14-Apr-20
The second step to removing a ball lock retainer. When flat checking the retainer
#3 Remove the bolts and dowel pins and flat check make sure to paint check for
the retainer and check for damage. 80% flatness.
MFG Proc No 249 Rev Level 000 file:///conversion/tmp/activity_task_scratch/562926672.xlsx date of last revision: 14Feb17