Company Sequence
Symbol Number
“Mirah Ganal (start from 001)
Energy”
Facility Discipline
Codes Symbols
(Appendix – 1) (Appendix – 2)
Drawing piping number 001 for Early Condensate Delivery (ECD) Phase Kerendan Facility
in Muara Bakah Refinery Project, Mirah Ganal Energi
4. Revision Index
Each document shall be issued with a letter revision index shall be as follow:
- Rev. A, B, C, …. document process for review and approval
- Rev. 0 means documents “Approved for Bid” (AFB) / “Approved for Construction” (AFC)
- Rev. 1,2, 3, … revised of AFB/AFC documents (Re-Issued)
The document code shall appear only in the footer of narrative documents (not in the main
document number block) and in the Revision box of documents.
Revision history / track start from A until document approve shall be written in a column part of
document cover. When the document has revision 0, will be started from 1,2,3…
5. Document Status
The following DOCUMENT status are existing during the detail engineering or Construction phase:
Issued for Review IFR (A)
Issued for Approval IFA (B)
Approved for Bid / Construction AFB / AFC (0)
Re-Approved for Bid / Construction Re-AFB / Re-AFC (1)