You are on page 1of 10

Case Study

Determining the Probability of Project Cost Overruns


Peter E. D. Love1; Xiangyu Wang2; Chun-pong Sing3; and Robert L. K. Tiong4

Abstract: The statistical characteristics of cost overruns experienced from contract award in 276 Australian construction and engineering
projects were analyzed. The skewness and kurtosis values of the cost overruns are computed to determine if the empirical distribution of the
data follows a normal distribution. The Kolmogorov-Smirnov, Anderson-Darling, and chi-squared nonparametric tests are used to determine
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

the goodness of fit of the selected probability distributions. A three-parameter Frechet probability function is found to describe the behavior of
cost overruns and provide the best overall distribution fit. The Frechet distribution is then used to calculate the probability of a cost overrun
being experienced. The statistical characteristics of contract size and cost overruns were also analyzed. The Cauchy (< A$1 million), Wakeby
(A$1 to 10 million, < A$101 million) and four-parameter Burr (A$11 to 50 million) tests were found to provide the best distribution fits and
used to calculate cost overrun probabilities by contract size. Ascertaining the best fit probability distribution from an empirical distribution at
contract award can produce realistic probabilities of cost overruns, which should then be incorporated into a construction cost contingency.
DOI: 10.1061/(ASCE)CO.1943-7862.0000575. © 2013 American Society of Civil Engineers.
CE Database subject headings: Australia; Construction costs; Probability; Project management.
Author keywords: Australia; Cost overrun; Distribution fitting; Probability; Probability distribution.

Introduction To assume that the aforementioned factors are the primary con-
tributors to cost overruns neglects the underlying complexity asso-
The ability to make accurate cost predictions is critical to successful ciated with the design and construction process (Love et al. 2012).
project delivery. In an attempt to assess the likelihood of cost As more information about a project’s requirements, specifically
overruns and put in place mechanisms to reduce their impact, those of a client, becomes available during the design process,
several techniques have been espoused (Jahren and Ashe 1990; the budget that is established during feasibility is modified.
Birnie and Yates 1991; Attala and Hegazy 2003; Flyvbjerg At the contract award, the expected cost to a client can be affirmed
2008; Bhargava et al. 2010). Despite the application of such and a reliable reference point can be established for determining a
techniques as well as the adoption of innovative organizational project cost’s overrun. From this point, factors contributing to
and managerial practices, cost overruns in projects remain a cost overruns include material and labor shortages, price inflation,
pervasive problem (Hester et al. 1991; Ibbs and Allen 1995; Love rework, change orders, site access, unexpected site conditions,
2002; Bhargava et al. 2010). Cost overruns have been attributed and unforeseen events (Arditi et al. 1985; Semple et al. 1994;
to the occurrence of optimism bias or strategic misrepresentation Chang 2002; Knight and Fayak 2002; Gkritza and Labi 2008;
during the formation of a project’s budget (Flyvbjerg 2007a, b). Love et al. 2011). Such causes may not have been considered
Optimism bias is the demonstrated systematic tendency for at the award of contract and typically arise during construction.
people to be overly optimistic about the outcome of planned With a sufficient data set of projects, however, the probability
actions (Kahneman et al. 1982; Lovallo and Kahneman 2003). of a cost overrun from a contract’s award can be determined
This includes overestimating the likelihood of positive events and (Jahren and Ashe 1990; Birnie and Yates 1991; Gkritza and
underestimating the likelihood of negative events. Alternatively, Labi 2008).
strategic misrepresentation is the planned, systematic distortion A cost overrun can be classified as a “random continuous var-
or misstatement of fact; it is essentially lying (Jones and iable” because it can take an infinite range of values (Jahren and
Euske 1991). Ashe 1990). Typically, the probability density function (PDF) of a
normal (otherwise known as Gaussian) distribution has been used
1
to determine project cost overruns (e.g., Flyvbjerg 2007b). A nor-
John Curtin Distinguished Professor, School of Built Environment,
mal distribution is symmetric about its mean value and therefore
Curtin Univ., GPO Box U1987, Perth, WA 6845, Australia (corresponding
author). E-mail: p.love@curtin.edu.au cannot be used to accurately model left- or right-skewed data.
2
Professor, School of Built Environment, Curtin Univ., GPO Box Even if cost overrun data are symmetric by nature, it is possible
U1987, Perth, WA 6845, Australia. E-mail: x.wang@curtin.edu.au that they are best described using heavy tailed distribution models
3 such as a Cauchy. Fitting an empirical distribution to data can
Senior Lecturer, School of Built Environment, Curtin Univ., GPO Box
U1987, Perth, WA 6845, Australia. E-mail: chunpong.sing@curtin.edu.au be a difficult task considering the array of statistical distribution
4
Associate Profesor, School of Civil and Environmental Engineering, choices that are available. The selection of an inappropriate statis-
Nangyang Technological Univ., Singapore. E-mail: CLKTIONG@ntu tical distribution can produce incorrect probabilities, which can
.edu.sg adversely affect decision making and therefore lead to negative
Note. This manuscript was submitted on August 11, 2011; approved on
January 31, 2012; published online on April 28, 2012. Discussion period
outcomes. In addressing this shortcoming, this paper uses data
open until August 1, 2013; separate discussions must be submitted for in- derived from 276 completed Australian construction and engineer-
dividual papers. This paper is part of the Journal of Construction Engi- ing projects to determine the “best fit” distribution so that a realistic
neering and Management, Vol. 139, No. 3, March 1, 2013. © ASCE, probability of project cost overruns from contract award can be
ISSN 0733-9364/2013/3-321-330/$25.00. determined.

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013 / 321

J. Constr. Eng. Manage. 2013.139:321-330.


Cost Overruns Table 1. Descriptive Statistics for Cost Overruns
Statistic Value
The term cost overrun is often referred to as a budget increase, cost
increase, or cost growth. A cost overrun should, however, be Sample size 276
distinguished from cost escalation, which is used to express an an- Range 328.35
Mean 12.22%
ticipated growth in a budgeted cost due to factors such as inflation.
Variance 426.54
A lack of a standard definition juxtaposed with the inappropriate Standard deviation 20.65
distribution models has contributed to the formulation of inaccurate Coefficient of variation 1.689
cost overrun probability forecasts. Nijkamp and Ubbels (1999), Standard error 1.243
Flyvbjerg et al. (2002), and Odeck (2004), for example, defined Skewness 5.549
a cost overrun as the difference between forecasted and actual con- Excess kurtosis 60.25
struction costs. In this instance, the budget at the decision to build is
used as the reference for determining the overrun that may be
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

incurred (Fig. 1). Actual construction costs (Acv ) are defined as Flyvbjerg et al. (2002) revealed that there was a significant differ-
accounted construction costs at the time of project completion. ence between the mean cost overruns for different project types
An alternative definition and reference point for determining a cost but not for geographical location. Conversely, however, Odeck
overrun have been provided by Rowland (1981), Hinze et al. (2004) observed that project type did not influence the level of cost
(1992), and Zeitoun and Oberlander (1993), who suggested that overrun incurred.
it is the difference between the original contract value (Ocv )
(i.e., contract award) and Acv at practical completion. The discrep-
ancy between definitions presented has contributed to significant Cost Overrun Determination
variability in the cost overrun percentages that have been reported In Fig. 1 the project development process is identified along with
in the normative literature. the reference points that are used to determine a cost overrun. As
Table 1 provides a summary of studies that have examined cost noted previously, between the budget to contract award (between
overruns in construction and engineering projects. The Auditor Activities A and H), which is denoted as the Ocv , estimating
General of Sweden (1994), for example, revealed that the average accuracy can be affected by an array of factors such as process char-
cost overrun for eight road projects was 86%, with a range of −2 to acteristics and knowledge, the degree of project definition, incen-
182%. In contrast, Odeck and Skjeseth (1995) examined 12 toll tives for accurate estimation, and human judgment and bias. Project
projects and found the average cost overrun to be 5%, with a range costs, however, increase either by changing their character or
of −10 to 170%. In a further study undertaken by Odeck (2004), a changing the economic and institutional environment in which
mean cost overrun of 7.9% and a range of −59 to 183% was re- they develop. Distinguishing between the factors that increase
ported for 420 road construction projects. For bridges and tunnels, project costs and those that affect the accuracy of estimates is
Skamris and Flyvbjerg (1996, 1997) found the cost estimates from pivotal to determining an accurate cost overrun probability. The
the decision to build to actual completion experienced a cost percentage increase from the estimate when the decision to build
overrun of 50 to 100% (Table 1). is made to contract award needs to be determined and separated
Issues relating to project types and their influence on cost from a cost overrun analysis. When this is done, an appropriate
overruns have been examined and are subject to ongoing debate. contingency at the decision to build can be determined and used

Fig. 1. Project development process: determination of cost overrun

322 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013

J. Constr. Eng. Manage. 2013.139:321-330.


to ensure a higher degree of estimating certainty about the expected (2008) has assumed that projects of the same type experience sim-
construction costs at contract award. ilar degrees of optimism bias and cost overruns, which is contrary
When large infrastructure projects, for example, are announced, to the findings reported elsewhere (e.g., Love 2002; Odeck 2004;
governments customarily inform the public of the projects’ ex- Love et al. 2009).
pected budget. An air of skepticism pertaining to the budgeted cost In the case of FSH and Perth Arena, the initial estimates were
prevails within the public domain as it is widely accepted that the unrealistic because their scope had not been well defined and
forecasted costs will increase. From the time when a project is fully understood. Furthermore, during the design process of the
budgeted and announced to the actual commencement of construc- FSH, its size increased by 44% as a consequence of a demand
tion may take years and therefore leave the project susceptible to for additional single beds and clinical facilities. Similarly, in the
cost increases. Furthermore, depending on the size and complex- case of the Perth Arena, major issues contributing to its cost in-
ity of the project, its physical construction can also take several crease were design costs (þA$7 million), changes to the building’s
years. The Fiona Stanley Hospital (FSH), currently under construc- design (þA$55 million), the inclusion of fit-out and transition to
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

tion, in Perth, Western Australia (WA), is the state’s largest social operation (þA$42 million), and an underground car parking
infrastructure project ever. In 2004 it was originally budgeted at facility (þA$34 million). Clearly, without a defined scope, any
A$420 million, and after 4 years of planning and design a revised budget that is formulated at the decision to build would be inaccu-
budget of A$1.76 billion was established. Before construction had rate and subject to changes. Consequently, using the initial budget
even commenced the project had overrun its original budget by as a reference point to determine a cost overrun is misleading and
320%. In 2010 the WA auditor general concluded (WA Auditor will naturally lead to an overinflated value that does reflect a
General 2010a, p. 5): project’s new characteristics and changed scope. With this in mind,
the use of the contract award can provide an ameliorated point
: : : the opening date is between three and a half and four of reference for determining cost overruns and therefore can allow
years later than originally planned. In common with other for apples-to-apples comparisons.
capital projects, the original estimates were unrealistic and
were not based on a good understanding of what this major
Costs and Project Size
project would involve. Better definition of the requirements
of the hospital has resulted in scope changes which have Research has suggested that the likelihood of a cost overrun in-
increased forecast costs, and delayed the opening. creases with contract size and complexity as well as the number
of change orders (Rowland 1981; Hinze et al. 1992). Specifically
The revised budget did not include the essential fit-out needed to change orders. The change-order rate is defined as the “ratio
run a working hospital. However, construction and building works between the dollar amount change of change orders and award
accounted for only A$755 million of the revised 2008 budget. amount” (Jahren and Ashe 1991, p. 548). Rowland (1981) found
Other major budgeted items included escalation due to inflation that as the change-order rate increased, contract size increased,
(A$431 million), professional fees (A$186 million), and a contin- whereas Randolph et al. (1987) revealed that as the change-order
gency (A$110 m). rate decreased, contract size increased. Jahren and Ashe’s (1990)
The Perth Arena project currently being constructed has been examination of 1,576 construction projects found that a cost over-
subjected to a significant cost overrun. With an original bud- run rate of 1 to 11% is more likely to occur on larger projects than
get of A$160 million established in 2005, it was expected to be smaller projects as managers typically have longer periods of time
fully operational by 2009. Poor governance and significant to rectify cost-related issues and therefore keep cost overrun rates
changes in scope have resulted in significant cost and schedule low. Likewise, Odeck’s (2004) research showed that larger over-
blowouts, and when completed the total estimated cost is expect- runs were experienced in smaller projects. This suggests that larger
ed to exceed A$500 million (i.e., more than a 200% increase). projects may be better managed and that longer completion times
In 2010 the WA auditor general concluded (WA Auditor General provide an opportunity to make adjustments to facilitate cost con-
2010b, p. 5): trol (Jahren and Ashe 1991; Vidalis and Najafi 2002; Odeck 2004).
To improve cost control, there is a need to put in place strategies to
On current estimates, it will cost $483 million, more than prevent those factors that cause cost overruns from occurring. It
three times the original estimate of $160 million. The Arena is beyond the scope of this paper to examine the causes of cost
is scheduled to open almost three years later than originally overruns. A detailed review of the subject matter can be found in
planned, in November 2011 rather than January 2009. Insuf- Frimpong et al. (2003), Ashan and Gunawan (2010), Bhargava
ficient scoping and planning meant that both the original cost et al. (2010), Jergeas and Runwanpura (2010), and Love et al.
estimate and opening date were unrealistic. Key decisions on (2011, 2012).
the project during contract negotiations have altered the
planned allocation of risks between the state and contractor,
increased the risks to the state, and led to project delays and Research Approach
cost increases. These decisions were made without systematic
or sufficient analysis of their impact, consideration of alterna- The data set presented in Love et al. (2009) for Australian con-
tives, external scrutiny or legal advice. struction and engineering projects is used to develop “best-fit”
statistical distributions so that probabilities for cost overruns at
According to Flyvbjerg and Cowi (2004), inaccurate budgets contract award can be determined. For the purpose of clarity,
of this nature are a result of optimism bias. As a result, reference the method of data collection and dataset characteristics will be
class forecasting was developed to mitigate the risk of optimism presented again.
bias that may arise during the formulation of a budget (Flyvbjerg
and Cowi 2004; Flyvbjerg 2007a, 2008). This approach does not
Questionnaire Survey
try to forecast specific uncertain events that will affect a particular
project but instead places a project in a statistical distribution of The questionnaire survey developed for the study reported in Love
outcomes from the class of reference points. Essentially, Flyvbjerg et al. (2010) was used to extract cost overrun information as well as

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013 / 323

J. Constr. Eng. Manage. 2013.139:321-330.


that relating to rework costs and causes. Stratified random sampling Procedure
was used to select the study sample from the telephone directory Descriptive statistics such as the mean (M), standard deviation
Yellow Pages for the various regions of Australia. Two main ben- (SD), and interquartile were calculated. A one-way analysis of vari-
efits can be derived from using a stratified sample: ance (ANOVA) was used to determine if cost overruns significantly
1. It can ensure that adequate and representative respondents varied between construction and engineering projects and original
within each subgroup under study are acquired. contract value at a 0.05 significance level. Probability density func-
2. It ensures that respondents within the same group are tions (PDFs) were developed using EastFit 5. A PDF for a continu-
homogeneous. ous distribution can be expressed in terms of an integral between
Before the sample size for the main study could be determined, a two points:
pilot survey was completed with 30 building and 20 civil engineer-
ing contractors. Because the survey of building contractors was Zb
undertaken first, it was considered to be reliable; it was then used fðxÞdx ¼ Pða ≤ X ≤ bÞ ð1Þ
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

to pilot the civil engineering sample. The firms sampled comprised a


design and engineering consultants, project managers, and contrac-
A cumulative distribution functions (CDF) was also produced.
tors. The rationale was to test the suitability, clarity, and compre-
For theoretical continuous distributions the CDF is expressed as a
hensibility of the questionnaire and measure the response rate.
curve and denoted by
Participating firms were contacted by telephone and informed of
the research aims and objectives and informed that all responses Zx
would remain strictly confidential, though generalizations of the FðxÞ ¼ fðtÞdt ð2Þ
findings would be made available to all participants. −∞
Upon participant consent, questionnaires were mailed to the
sample, with a stamped addressed return envelope enclosed. Par- The empirical CDF, which is displayed as a stepped discontinu-
ticipants were invited to critically review the questionnaires’ design ous line and dependent on the number of bins, is represented by
and structure by adding comments onto the document itself in order 1
to provide constructive feedback. Comments received were posi- Fn ðxÞ ¼ · ½Number of observations ≤ x ð3Þ
n
tive, and therefore the questionnaire remained largely unaltered
for the main surveys, although a few minor layout changes were The PDF, CDFs, and distribution parameters (α, β, γ, μ, k, m,
made to increase clarity. A total of 25 responses were received σ, ξ) for continuous distributions such as beta, Burr, Cauchy, error,
in the building project pilot survey, giving an 83% response rate. Gumbel max/min, Johnson SB, normal, and Wakeby were exam-
ined using the maximum-likelihood estimate method. Using
For the civil engineering project survey, a total of 17 responses
StatAssist 5.5, the best-fit distribution was then determined using
were received, giving an 85% response rate. These high response the following goodness-of-fit tests, which measure the compatibil-
rates were obtained because prior consent to support the work was ity of a random sample with a theoretical probability distribution:
obtained from all survey participants. • Kolmogorov-Smirnov statistic (D): based on the largest vertical
In the main survey, 420 and 300 questionnaires were distributed difference between the theoretical and empirical CDF:
to design consultants, contractors, and project managers for build-  
ing and civil engineering projects, respectively. Because no funda- i−1 i
D ¼ max Fðxi Þ − ; − Fðxi Þ ð4Þ
mental changes were required to either of the pilot questionnaires, 1≤i≤n n n
they were added to the samples. For the building and civil engineer-
• Anderson-Darling statistic (A2 ): a general test to compare the fit
ing projects, 161 and 115 responses were received, respectively,
of an observed CDF to an expected CDF. The test provides more
which represents a total consolidated response rate of 36% for both
weight to a distribution’s tails than does the Kolmogorov-
surveys, which is within an acceptable range for a survey with Smirnov test. The Anderson-Darling statistic is defined as
industry practitioners (Alreck and Settle 1985).
1X n
A2 ¼ −n − ð2i − 1Þ · ½InFðxi Þ þ Inð1 − Fðxn−1þ1 ÞÞ
Data Reliability n i¼1

Data reliability relates to the data source and the identification of ð5Þ
the position held by the respondent completing the questionnaire • Chi-squared statistic (χ2 ): determines if a sample comes from a
(Oppenheim 1992). Therefore, it was critically important that only population with a specific distribution. The chi-squared statistic
selected senior personnel who had sufficient knowledge and expe- is defined as
rience about the procurement processes associated with a project
answered the questionnaire. From the total responses gathered, X
k
ðOi − Ei Þ2
χ2 ¼ ð6Þ
133 respondents provided information relating to their individual Ei
i¼1
job position and title, and it was revealed that most respondents
held senior positions within their organizations. Based upon this where Oi is the observed frequency for bin i and Ei is the
finding the direct mailing to individuals in organizations seemed expected frequency of bin i calculated by
to have achieved its objective of reaching senior staff that plays
a significant role in construction project management. In addition, Ei ¼ Fðx2 Þ − Fðx1 Þ ð7Þ
because, in accordance with the study design, questionnaires were
mailed to organizations in different states in Australia, the risk of Here F is the CDF of the probability distribution being
duplicating projects was minimized. tested, and x1 and x2 are the limits for bin i.

324 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013

J. Constr. Eng. Manage. 2013.139:321-330.


The foregoing goodness-of-fit tests were used to test the null To demonstrate the spread of a data set, the percentage of cost over-
(H0 ) and alternative hypotheses (H1 ) that data set H0 follows run for the sample is plotted against Ocv (Fig. 2). It can be seen in
the specified distribution and that data set H 1 does not fol- Fig. 2 that smaller projects experienced considerably larger cost
low the specified distribution. The hypothesis regarding the distri- overruns than the two projects that were greater than $300 million.
butional form is rejected at the chosen significance level (α) if the An ANOVA test was used to determine if there were significant
statistic D, A2 , χ2 are greater than the critical value. For the pur- differences between the cost overruns experienced in the construc-
poses of this research, a 0.05 significance level was used to evaluate tion and engineering projects (p ¼ 0.05). The analysis revealed
the null hypothesis. The p-value, in contrast to fixed α values, is that there were no significant differences between the cost overruns
calculated based on the test statistic and denotes the threshold value experienced between construction and civil engineering projects
of significance level in the sense that H 0 will be accepted for all [Fð1; 274Þ ¼ 0.611, p ¼ 0.41]. Previous analysis of this data
values of α less than the p-value. Once the best-fit distribution was set revealed that project cost overruns did not vary with procure-
identified, the probabilities for cost overruns were calculated using ment and tendering methods and project types (Love 2002; Love
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

the CDF. Then, to simulate the sample’s randomness and derive et al. 2009, 2010). Therefore, generic probabilities for determining
cost overrun probabilities, a Mersenne twister, which is a pseudor- the occurrence of project cost overruns based upon the best-fit
andom number generating algorithm, was used to generate a probability distribution were calculated.
sequence of numbers that approximated the sample to 1,000
(Matsumoto and Nishimura 1998).
Distribution Fitting: Probability of Cost Overruns
The construction and engineering data sets were combined, and the
Results best-fit probability distribution was examined using the goodness-
of-fit tests Kolmogorov-Smirnov and Anderson-Darling. The re-
Data from a total of 276 construction (n ¼ 161) and civil engi- sults of the goodness-of-fit tests revealed that a three-parameter
neering (n ¼ 115) projects were obtained. In the case of con- (3P) Frechet distribution provided the best fit for the data sets
struction projects, these ranged from banks to hospitals and hotels. (Table 3).
For the civil engineering sample, these ranged from tunneling to A Frechet is a form of generalized extreme value distribution
road construction and sewer treatment plants. The summary statis- (GEV) that is used as an approximation to model the maxima
tics reveal that the mean Ocv was A$23,142,486 (SD ¼ A$41;171; of long (finite) sequences of random variables (Coles 2001).
772; minimum ¼ A$132;347; maximum ¼ A$390 million), and the The parameter α is a continuous shape parameter α > 0, β > 0,
mean Acv was A$25,455,372 (SD ¼ A$45;090;928; minimum ¼ and γ is a continuous location parameter, where γ ≡ 0 yields
A$136;671; maximum ¼ A$420 million). the two-parameter Frechet distribution. The domain for the 3P
To better understand the makeup of the sample, an examination Frechet distribution is γ < x < þ∞. The PDF is expressed as
of respondent stratification, geographical dispersion, and company  αþ1   α 
α β β
turnover was completed for the civil engineering sample. In terms fðxÞ ¼ exp − ð8Þ
of respondent stratification, 45% were design consultants (archi- β x−γ x−γ
tects, quantity surveyors, and structural, mechanical, and electrical
The CDF is expressed as
engineers), 31% were contractors, and 24% comprised project
 α 
managers. With regards to geographical dispersion, organizations β
were situated across the states of Victoria (45%), New South Wales fðxÞ ¼ exp − ð9Þ
x−γ
(17%), Queensland (27%), South Australia (9%), and WA (2%).
In Table 2 the descriptive statistics for the cost overruns that The parameters for the Frechet (3P) were found to be
were incurred in the sampled projects are presented. The mean α ¼ 10.158, β ¼ 90.215, and γ ¼ −84.29. Figs. 3 and 4 present
overall project cost overrun for the sample was 12.22% the PDF and CDF based upon the calculated distribution parame-
(SD ¼ 20.65) of Ocv . Means were also determined for the two ters. The calculated probabilities of a cost overrun are presented in
groupings of project type, construction and civil engineering, Table 4. The probability of a cost overrun of greater than 10% is
and were found to be 12.22% (SD ¼ 24.22%) and 11.76% 47%. Delimiters were also used to provide probabilities of cost
(SD ¼ 13.76%), respectively. For construction projects the maxi- overruns within ranges. The probability of a project experiencing
mum cost overrun was 244% and the minimum was −84%
(i.e., cost underrun), which results in a range of 328%. For the civil
engineering projects sampled the maximum cost overrun was 109% 0.56 % Cost Overrun Frechet (3P)

and the minimum was 11%, which results in a range of 98%.


Probability of Cost Overrun

0.48

0.4
Table 2. Percentiles for Project Cost Overrun
0.32
Percentile Value 0.24
Minimum −84.29 0.16
5% 0
10% 1.02 0.08
25% (Q1) 2.96 0
50% (median) 8.16
75% (Q3) 15.14 -0.08
90% 30.54 -40 -20 0 20 40 60 80 100 120
95% 40 Percentage of Cost Overrun
Maximum 244.06
Fig. 2. Frechet 3P: PDF for cost overruns
Note: Q1 = first quarter; Q3 = third quarter.

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013 / 325

J. Constr. Eng. Manage. 2013.139:321-330.


Table 3. Goodness-of-Fit Tests for Construction and Engineering Projects
Sigma Kolmogorov-Smirnov Anderson Darling Chi-squared
Distribution type N α level (D) critical value (A2 ) critical value (χ2 ) critical value
Frechet 3P (construction 276 0.2 0.064 1.374 11.03
and engineering projects) 0.1 0.073 1.928 13.362
0.05 0.081 2.50 15.507
0.02 0.091 3.289 18.168
0.01 0.098 3.907 20.09
Cauchy <A$1 m 14 0.2 2.748 1.374 1.642
0.1 0.3141 1.928 2.705
0.05 0.348 2.501 3.841
0.02 0.389 3.289 5.411
0.01 0.417 3.907 6.634
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

Wakeby A$1 to A$10 million 131 0.2 0.0937 1.374 N/A


0.1 0.1068 1.928 N/A
0.05 0.1186 2.501 N/A
0.02 0.132 3.289 N/A
0.01 0.142 3.907 N/A
Burr (4P) A$11 to A$50 million 101 0.2 0.1067 1.374 8.558
0.1 0.1216 1.928 10.64
0.05 0.1351 2.501 12.59
0.02 0.151 3.289 15.03
0.01 0.162 3.907 16.81
Cauchy A$51 to A$100 million 17 0.2 0.250 1.374 3.218
0.1 0.286 1.928 4.605
0.05 0.317 2.501 5.991
0.02 0.355 3.289 7.824
0.01 0.380 3.907 9.210
Wakeby >A$100 million 17 0.2 0.295 1.374 1.642
0.1 0.338 1.928 2.705
0.05 0.375 2.501 3.841
0.02 0.419 3.289 5.411
0.01 0.449 3.907 6.634

1 a cost overrun of between 1 and 5%, for example, is 16% (Fig. 3).
0.9 Cost Frechet 3P The likelihood that a project will exceed a mean cost overrun of
0.8
Overrun
12.22% is 60% [Pðx < x1Þ ¼ 0.60].
Probability of Cost Overrun

0.7
0.6
Project Size
0.5
0.4
An ANOVA was also used to determine if the cost overruns varied
0.3
with different Ocv ðp ¼ 0.05Þ. The homogeneity of variance as-
sumptions was violated for cost overrun comparisons; hence the
0.2
results of a t-test with equal variances not assumed are reported
0.1
(p ¼ 0.05). There were no significant differences for Ocv and
0
project cost overruns tð272Þ ¼ −1.21, p ¼ 0.289. Fig. 4 shows
-80 -40 0 40 80 120 160 200 240
a scatterplot of Ocv and the percentage of cost overrun that occurred
Cost Overrun
on each project. It can be seen that as Ocv increases, the cost over-
Fig. 3. Frechet 3P: CDF function for cost overruns run decreases. Table 5 indicates that construction projects greater
than A$1 million saw a mean cost overrun of 24.90%. For civil
engineering projects, the largest cost overrun of 14.01% occurred
in the smallest contract range, A$1 to A$10 million.
1
% Cost Overrun Cauchy While the data set was comparable in size to those of other stud-
Probability of Cost Overrun

0.8 ies that have examined cost overruns (e.g., Flyvbjerg et al. 2002),
the number of projects within established Ocv ranges is small for
0.6

0.4
Table 4. Generic Discrete Probabilities for Project Cost Overruns
0.2 Probability of cost overrun (%) PðX < X1Þ PðX > X1Þ
0 5 0.32 0.67
10 0.53 0.47
-0.2
0 100 200 300 15 0.69 0.31
Percentage of Cost Overrun 20 0.8 0.2
25 0.87 0.13
Fig. 4. Cauchy: PDF for construction projects less than A$1 million 30 0.91 0.09

326 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013

J. Constr. Eng. Manage. 2013.139:321-330.


   −1
Table 5. Generic Range of Probabilities for Project Cost Overruns x − σ2
fðxÞ ¼ πσ 1 þ ð10Þ
Probability of a cost overrun between PðX1 < X < X2Þ σ
1 and 5% 0.16
5 and 10% 0.2 The CDF is expressed as
10 and 15% 0.16
15 and 20% 0.11  
1 x−μ
20 and 25% 0.07 FðxÞ ¼ arctan þ 0.5 ð11Þ
25 and 30% 0.05 π σ

For the contract ranges A$1 to A$10 million (Table 7) and less
each of the project classification types. Construction and engineer- than A$101 million the best-fitting distribution was a Wakeby
ing projects were combined to create a large data set to determine (Table 7). This form of distribution is also a GEV. The parameters
of a Wakeby, α, β, γ, δ, and ξ, are all continuous. The domain for
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

the best-fit distribution for each range of cost overrun experienced


within a range of Ocv classifications. Only construction projects
had contract values less than $1 million; therefore, this category
was not combined with the engineering sample. Only two con- 0.44
% Cost Overrun Cauchy
0.4
struction projects exceeded A$200 million. As a result, these two

Probability of Cost Overrun


0.36
projects were combined into an Ocv classification of more than 0.32
A$101 million. The best-fit probability distribution for each range 0.28
of Ocv classifications was examined using the goodness-of-fit 0.24
tests: Kolmogorov-Smirnov, Anderson-Darling, and chi-squared 0.2
0.16
(Tables 6–8).
0.12
For projects greater than $1 million an unbounded Cauchy dis- 0.08
tribution with parameters σ ¼ 4.31, μ ¼ 3.47 was identified as the 0.04
best-fit solution (Table 6). A distribution of this nature has a pos- 0
-10 -5 0 5 10 15 20 25
itive excess kurtosis and is leptokurtic. It also has an acute peak Percentage of Cost Overrun
around the mean (that is, a lower probability than a normally
distributed variable of values near the mean). With this distribution Fig. 5. Cauchy: PDF for construction and engineering projects
σ is a continuous scale parameter (σ > 0) and μ a continuous A$51–$100 million
location parameter. The domain for this distribution is expressed
as −∞ < x < þ∞. All the critical values were accepted at the
nominated α level. The probability of cost overruns was then 1
determined using the Cauchy PDF function at the cost overrun % Cost Overrun Wakeby
Probability of Cost Overrun

levels identified (Fig. 5). 0.8

The probabilities derived for cost overruns are presented in 0.6


Table 8. For example, the probability of a project with an Ocv
0.4
of less than A$1 million experiencing a cost overrun of less than
25% is 93%. Alternatively, the probability of incurring a cost over- 0.2
run of more than 25% is 7%. Construction and engineering projects 0
with an Ocv within the range of A$51 to A$100 million were also
-0.2
found to possess a Cauchy distribution with parameters σ ¼ 2.95,
μ ¼ 4.303 (Fig. 6). -150 -100 -50 0 50 100 150
Using the Cauchy PDF, probabilities for cost overruns within Percentage of Cost Overrun
the range A$51 to A$100 million are also presented in Table 8.
The Cauchy PDF is defined as Fig. 6. Wakeby: PDF for construction projects A$1–$10 million

Table 6. Project Cost Overruns by Project Type and Contract Value


Ocv Standard Mean percentage Overrun standard
Project type Project size N Mean Ocv deviation overrun (%) deviation
Construction <A$1 million 14 A$513,546 A$344,668 24.90 64.81
A$1 to A$10 million 70 A$3,874,368 A$2,830,183 10.30 17.10
A$11 to A$50 million 60 A$21,860,966 A$10,099,633 12.90 16.77
A$51 to A$100 million 12 A$66,883,333 A$15,062,888 9.03 11.24
A$101 to A$200 million 6 A$162,666,666 A$22,339,800 13.79 16.68
>A$200 million 2 A$376,000,000 A$19,798,989 9.09 1.98
Subtotal 161 A$25,521,927 A$51,957,899 12.56 24.44
Civil engineering A$1 to A$10 million 61 A$8,136,604 A$3,464,888 14.01 17.11
A$11 to A$50 million 43 A$24,906,930 A$10,487,326 8.49 13.84
A$51 to A$100 million 7 A$77,285,714 A$12,499,523 7.90 10.80
>A$101 million 4 A$165,250,000 A$25,051,613 9.10 11.90
Subtotal 115 A$22,092,965 A$33,897,118 11.76 13.76
Total 276 A$24,093,193 A$45,275,566 12.22 20.65

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013 / 327

J. Constr. Eng. Manage. 2013.139:321-330.


Table 7. Discrete Probabilities for Project Cost Overruns by Contract A four-parameter (4P) Burr distribution, which is a right-
Value skewed distribution, was found to be the best-fit distribution for
Contract Probability of contract ranges of A$11 to A$50 million (Table 8). The Burr dis-
value cost overrun (%) PðX < X1Þ PðX > X1Þ tribution has a flexible shape and controllable scale and location.
<A$1 5 0.64 0.36 It is sometimes considered an alternative to a normal distribution
10 0.81 0.19 when data demonstrate positive skewness. The parameters of the
15 0.88 0.12 (4P) Burr are all continuous: k is a shape parameter (k > 0), α a
20 0.91 0.09 shape parameter (α > 0), β a scale parameter, and γ a location
25 0.93 0.07 parameter (γ ≡ 0 yields the 3P Burr distribution). The distribution
30 0.94 0.06 parameters for the A$11 to A$50 million projects were found
A$1 to A$10 5 0.32 0.68 to be k ¼ 0.17857, α ¼ 42.483, β ¼ 67.778, γ ¼ −66.723 (Fig. 8).
million 10 0.57 0.43 Using the 4P Burr PDF, probabilities for cost overruns within the
15 0.73 0.27
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

range A$11 to A$50 million were calculated and are presented in


20 0.82 0.18
25 0.88 0.12 Table 8. The (4P) Burr PDF is expressed as [Eq. (13)]
30 0.92 0.08
A$11 to A$50 5 0.36 0.64
million 10 0.61 0.39 Table 8. Range of Probabilities for Project Cost Overruns by Contract
15 0.76 0.24 Value
20 0.85 0.15 Probability of a cost
25 0.89 0.11 Contract value (A$M) overrun between PðX1 < X < X2Þ
30 0.93 0.07
A$51 to A$100 5 0.57 0.43 <A$1 1 and 5% 0.27
million 10 0.84 0.16 5 and 10% 0.21
15 0.91 0.09 10 and 15% 0.07
20 0.94 0.06 15 and 20% 0.003
25 0.95 0.05 20 and 25% 0.002
30 0.96 0.04 25 and 30% 0.001
>A$101 million 5 0.31 0.69 A$1 to A$10 million 1 and 5% 0.23
10 0.51 0.49 5 and 10% 0.25
15 0.68 0.32 10 and 15% 0.15
20 0.8 0.2 15 and 20% 0.09
25 0.87 0.13 20 and 25% 0.06
30 0.91 0.09 25 and 30% 0.04
A$11 to A$50 million 1 and 5% 0.25
5 and 10% 0.25
10 and 15% 0.19
this distribution is expressed as ξ ≤ x if δ ≥ and γ > 0, ξ ≤ x ≤ 15 and 20% 0.08
þα=β − γ=δ if δ < 0 or γ ¼ 0. The distribution parameters for 20 and 25% 0.05
the range A$1 to A$10 million were α ¼ 1833.9, β ¼ 42.444, 25 and 30% 0.03
γ ¼ −10.698, δ ¼ 0.15, ξ ¼ −42.405, and for more than A$51 to A$100 million 1 and 5% 0.34
A$100 million they were α ¼ 389.57, β ¼ 14.917, γ ¼ 4.8036, 5 and 10% 0.27
δ ¼ 0.3951, ξ ¼ −20.972. The probability distributions for each 10 and 15% 0.06
of the contract ranges are presented in Figs. 6 and 7. 15 and 20% 0.03
20 and 25% 0.01
Using the Wakeby PDF, the probabilities for cost overruns
25 and 30% 0.001
within the ranges A$1 to A$10 million and less than A$101 million >A$101 million 1 and 5% 0.14
are presented in Table 8. The Wakeby distribution is defined by the 5 and 10% 0.2
quantile function (inverse CDF): 10 and 15% 0.17
15 and 20% 0.11
α γ 20 and 25% 0.07
xðFÞ ¼ ξ þ ð1 − ð1 − FÞβ Þ − ð1 − ð1 − FÞ−δ Þ ð12Þ 25 and 30% 0.04
β δ

0.48
% Cost Overrun Wakeby 0.64 % Cost Overrun Burr (4P)
0.4
Probability of Cost Overrun

0.56
Probability of Cost Overrun

0.32 0.48
0.24 0.4
0.16 0.32
0.08 0.24
0.16
0
0.08
-0.08 0
-0.16 -0.08

-40 -20 0 20 40 60 0 50 100


Percentage of Cost Overrun Percentage of Cost Overrun

Fig. 7. Wakeby: PDF for construction and engineering projects less Fig. 8. (4P) Burr: PDF for construction and engineering projects less
than A$101 million than A$11–$50 million

328 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013

J. Constr. Eng. Manage. 2013.139:321-330.


αkðx−y α−1
β Þ
Conclusion
FðxÞ ¼ α kþ1
ð13Þ
βð1 þ ðx−y
β Þ Þ Two different viewpoints exist with regard to the point at which a
cost overrun is determined. Within the infrastructure and transport
The CDF is expressed as [Eq. (14)] literature, cost overruns are invariably calculated from the decision
    to build. In contrast, within the construction and engineering man-
x − y α −k
FðxÞ ¼ 1 − 1 þ ð14Þ agement literature, cost overruns are determined from contract
β award. When the decision to build is used as the reference point,
reported cost overruns can be phenomenally high and alarmist to
The identified statistical distributions were used to determine
the general public. Between the decision to build and contract
realistic probabilities for cost overruns in construction and engineer-
award a project’s nature and scope can change dramatically to
ing projects from contract award. Such probabilities can be used
the extent that an entirely different facility may be commissioned,
to determine an appropriate allowance for a construction cost
rendering cost overrun comparisons unrealistic.
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

contingency.
Using the contract award as the reference point, cost overruns
from 276 construction and engineering projects were calculated.
The research revealed a mean cost overrun of 12.22%. No signifi-
Cost Contingency cant differences for cost overruns were found among procurement
method, project type, and contract size. The empirical distributions
A contingency can be defined as “the amount of funds, budget or
for the cost overruns were found to be non-Gaussian. Nonparamet-
time needed above the estimate to reduce the risk of overruns of
ric goodness-of-fit tests were used to select the best-fit probability
project objectives to a level acceptable to the organization” (Project
distribution. A three-parameter Frechet probability function was
Management Institute 2008). Most projects will experience cost
found to provide the best overall distribution fit to calculate the
increases between the decision to build and the contract award.
probability of cost overruns. As a line of inquiry, the statistical
A design contingency is typically allocated for changes during de-
characteristics of contract size and cost overruns were also
sign for factors such as incomplete scope definition and estimating
analyzed. The Cauchy (<A$1 million), Wakeby (A$1 to 10 million,
inaccuracy (e.g., Clark and Lorenzoni 1985). As a project becomes
<A$101 million), and four-parameter Burr (A$11 to $50 million)
more defined, the design contingency is absorbed into the budget
were found to provide the best distribution fits and were therefore
for specific cost elements (Gunhan and Arditi 2007). Any unre-
used to calculate cost overrun probabilities by contract size. It is
solved design issues at the time of contract award should be incor-
suggested that distribution fitting of empirical distributions is nec-
porated into the construction contingency (Gunhan and Arditi
essary to produce reliable and realistic cost overrun probabilities
2007). At the initial budget stage, a contingency of 30 to 50%
and, as a result, improve decision making.
should be allowed for incomplete scope and 5 to 10% for estimat-
ing inaccuracies (Clark and Lorenzoni 1985). Thus, as a rule of
thumb, a 35 to 60% design contingency should be added to the References
initial budget estimate figure. In the case of FSH and Perth Arena,
for example, the cost increase prior to contract award far outweighs Alreck, P. L., and Settle, R. B. (1985). The survey research handbook,
the suggested design contingency. Predicting the cost overrun from Richard D. Irwin, Homewood, IL.
the decision to build to contract award relies exclusively on a large Arditi, D., Tarim, G., and Gurdamar, S. (1985). “Cost overruns in public
data set, so the empirical distribution of cost overruns can be used projects.” Int. J. Project Manage., 3(4), 218–224.
Ashan, K., and Gunawan, I. (2010). “Analysis of cost and schedule perfor-
to determine the best-fit statistical distribution for probabilistic
mance of international development projects.” Int. J. Project Manag.,
analysis. 28(1), 68–78.
A construction contingency is used for changes that may occur Attala, M., and Hegazy, T. (2003). “Predicting cost deviation in
during the construction process. Under a traditional lump sum con- reconstruction projects: Artificial neural networks versus regression.”
tract based on bills of quantities (BoQs), scope and design are sup- J. Constr. Eng. Manage., 129(4), 405–411.
posed to be fully defined and developed. As a result, Clark and Auditor General Sweden (1994). Riksrevisionsverket. Infrastrukturinves-
Lorenzoni (1985) suggest using a contingency value of 3 to 5% teringar: En kostnadsjämörelse mellan plan og utyfall i 15 storre
(Clark and Lorenzoni 1985). In practice, complete drawings and prosjekt innöm Vägverket og Banverket, RVV, 23, Stockholm, Sweden.
BoQs are generally not available when a project goes to tender Bhargava, A., Anastasopoulos, P., Labi, S., Sinha, K. C., and
(Rowlinson 1999). A similar situation arises when nontraditional Mannering, F. L. (2010). “Three-stage least squares analysis of time
and cost overruns in construction contracts.” J. Constr. Eng. Manage.,
methods are used to deliver projects. The present analysis revealed
136(11), 1207–1218.
that there was no statistical difference between the extent of cost Birnie, J., and Yates, A. (1991). “Cost prediction using decision/risk
overrun experienced and procurement method used. From the fore- analysis methodologies.” Constr. Manage. Econ., 9(2), 171–186.
going analysis, it is suggested that a construction contingency value Chang, A. S.-T. (2002). “Reasons for cost and schedule increase for
in excess of the average cost overrun of 12.22% be used to deter- engineering design projects.” J. Manage. Eng., 18(1), 29–36.
mine known unknowns (i.e., identifiable risks). For example, de- Clark, F. D., and Lorenzoni, A. B. (1985). Applied cost engineering, Marcel
sign errors and omissions contained within contract documents Dekker, New York.
have been found to contribute as much as 50% of a project’s cost Coles, S. (2001). An introduction to statistical modeling of extreme values,
overrun (Love et al. 2009). From a client’s perspective, design er- Springer, Berlin.
rors and omissions are identifiable risks and should be accommo- Flyvbjerg, B. (2007a). “Policy and planning for large scale-infrastructure
projects: Problems, causes, and cures.” Environ. Plann. B Plann. Des.,
dated within a contingency. The probabilities derived from the
34(1), 578–597.
statistical distributions provide the basis to monitor and reassess Flyvbjerg, B. (2007b). “Cost overruns and demand shortfalls in urban rail
project costs. Identifying the key factors contributing cost overruns and other infrastructure.” Transp. Plann. Technol., 30(1), 9–30.
from contract award and assessing their likelihood of occurrence Flyvbjerg, B. (2008). “Curbing optimism bias and strategic misrepresenta-
can enable clients and contractors to implement appropriate risk tion in planning: Reference class forecasting in practice.” Eur. Plann.
management strategies. Stud., 16(1), 3–21.

JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013 / 329

J. Constr. Eng. Manage. 2013.139:321-330.


Flyvbjerg, B., and Cowi. (2004). Procedures for dealing with optimism Love, P. E. D., Edwards, D. J., Watson, H., and Davis, P. R. (2010).
bias in transport planning: Guidance document, UK Department of “Rework in civil engineering projects: Determination of cost predic-
Transport, London. tors.” J. Constr. Eng. Manage., 136(3), 275–282.
Flyvbjerg, B., Holm, M., and Buhl, S. (2002). “Underestimating costs in Matsumoto, M., and Nishimura, T. (1998). “Mersenne Twister: A 623-
public works projects: Errors or lie?” J. Am. Plann. Assoc., 68(3), dimensionally equidistributed uniform pseudo-random number genera-
279–295. tor.” ACM Trans. Modell. Comput. Simul., 8(1), 3–30.
Frimpong, Y., Oluwoye, J., and Crawford, L. (2003). “Causes of delays and Nijkamp, P., and Ubbels, B. (1999). How reliable are estimates of infra-
cost overruns in construction groundwater projects in developing structure costs? A comparative analysis, Faculty of Economics, Busi-
countries: Ghana case study.” Int. J. Proj. Manage., 21(5), 321–326. ness Administration and Econometrics, Free Univ., Amsterdam, the
Gkritza, K., and Labi, S. (2008). “Estimating cost discrepancies in highway Netherlands.
contracts: Multistep economic approach.” J. Constr. Eng. Manage., Odeck, J. (2004). “Cost overruns in road construction: What are their sizes
134(12), 953–962. and determinants?” Transport Policy, 11(1), 43–53.
Gunhan, S., and Arditi, D. (2007). “Budgeting owner’s construction Odeck, J., and Skjeseth, T. (1995). “Assessing Norwegian toll roads.”
contingency.” J. Constr. Eng. Manage., 133(7), 492–497.
Downloaded from ascelibrary.org by UNIV OF OKLA LIBRARIES on 03/27/13. Copyright ASCE. For personal use only; all rights reserved.

Transportation quarterly / Eno Foundation for Transportation,


Hester, W. T., Kuprenas, J. A., and Chang, T. C. (1991). “Construction 49(2), 89–98.
changes and change orders: Their magnitude and impact, Source docu- Oppenheim, A. N. (1992). Questionnaire design, interviewing and attitude
ment 66.” Construction Industry Institute, Univ. of Texas, Austin, TX. measurement, Pinter, London.
Hinze, J., Selstead, G., and Mahoney, J. P. (1992). “Cost overruns on State Project Management Institute. (2008). A guide to the project management
of Washington construction contracts.” Transportation Research of knowledge (PMBOK), 4th Ed., Project Management Institute,
Record 1351, Transportation Research Board, Washington, DC, 87–93. Newton Square, PA.
Ibbs, C. W., and Allen, W. E. (1995). “Quantitative impacts of project
Randolph, D. A., Rajandra, K., and Campfield, J. J. (1987). “Using risk
change, Source document 118.” Construction Industry Institute, Univ.
management techniques to control construction costs.” J. Constr.
of Texas, Austin, TX.
Eng. Manage., 3(4), 314–324.
Jahren, C., and Ashe, A. M. (1990). “Predictors of cost-overrun rates.”
Rowland, M. (1981). “The causes and effects of change orders on the
J. Constr. Eng. Manage., 116(3), 548–552.
construction process.” Master’s thesis, Georgia Institute of Technology,
Jergeas, G. F., and Runwanpura, J. (2010). “Why cost and schedule over-
Atlanta.
runs on mega oil sands projects?” Pract. Period. Struct. Des. Constr.,
Rowlinson, S. (1999). “A definition of procurement systems.” Procurement
15(1), 40–43.
systems: A guide to best practice in construction, S. Rowlinson and
Jones, L. R., and Euske, K. J. (1991). “Strategic misrepresentation in budg-
P. McDermott, eds., E & F Spon, London, 27–53.
eting.” Journal of public administration research and theory : J-PART,
1(4), 437–460. Semple, C., Harman, F. T., and Jergeas, G. (1994). “Construction claims
Kahneman, D., Slovic, P., and Tversky, A. (1982). Judgment under uncer- and disputes: Causes and cost/time overruns.” J. Constr. Eng. Manage.,
tainty: Heuristics and biases, Cambridge Univ. Press, Cambridge. 120(4), 785–795.
Knight, K., and Fayak, A. R. (2002). “Use of fuzzy logic for predicting Skamris, M. K., and Flyvbjerg, B. (1996). “Accuracy of traffic forecasts and
design cost overruns on building projects.” J. Constr. Eng. Manage., cost estimates on large transportation projects.” Transportation Re-
128(6), 503–512. search Record 1518, Transportation Research Board, Washington,
Lovallo, D., and Kahneman, D. (2003). “Delusions of success: How opti- DC, 65–69.
mism undermines executives’ decisions.” Harvard Bus. Rev., 56–63. Skamris, M. K., and Flyvbjerg, B. (1997). “Inaccuracy of traffic forecasts
Love, P. E. D. (2002). “Influence of project type and procurement method and cost estimates on large transportation projects.” Transport Policy,
on rework costs in building construction projects.” J. Constr. Eng. 4(3), 141–146.
Manage., 128(1), 18–29. Vidalis, S. M., and Najafi, F. T. (2002). “Cost and time overruns in highway
Love, P. E. D., Cheung, S. O., Irani, Z., and Davis, P. R. (2011). “Causal construction.” Proc., 4th Transportation Specialty Conf. of the
discovery and inference of project disputes.” IEEE Trans. Eng. Canadian Society of Civil Engineering, Canadian Society of Civil
Manage., 58(3), 400–411. Engineering, Montreal, QC.
Love, P. E. D., Edwards, D. J., and Irani, Z. (2012). “Moving beyond opti- Western Australia Auditor General. (2010a). “Fiona Stanley Hospital
mism bias and strategic misrepresentation: An explanation for social project, Report 5.” 〈www.audit.wa.gov.au/reports〉 (Jul. 18, 2011).
infrastructure project cost overruns.” IEEE Trans. Eng. Manage., Western Australia Auditor General. (2010b). “Planning and Management
59(4), 560–571. of Perth Arena, Report 1.” 〈www.audit.wa.gov.au/reports〉 (Jul. 18,
Love, P. E. D., Edwards, D. J., Smith, J., and Walker, D. H. T. (2009). 2011).
“Congruence or divergence? A path model of rework in building Zeitoun, A., and Oberlander, G. (1993). Early warning signs of project
and civil engineering projects.” J. Perform. Constr. Facil., 23(6), changes, Source Document 91, Construction Industry Institute, Univ.
480–488. of Texas, Austin, TX.

330 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE / MARCH 2013

J. Constr. Eng. Manage. 2013.139:321-330.

You might also like