Professional Documents
Culture Documents
ISSN: 2278-0181
Vol. 2 Issue 12, December - 2013
1. INTRODUCTION
Figure 1 A map of Dar es Salaam City
Reinforced concrete is widely used in the
construction of buildings and several other types of
This paper discusses the challenges of the
structures in Dar es Salaam due to its relatively
quality of reinforced concrete building construction
lower cost of construction, non-availability of other
in Dar es Salaam and recommendations on how to
durable materials, and the strength and protection
improve the quality of reinforced concrete
concrete structures provide against natural disasters
buildings are presented.
and aggressive weather conditions. Reinforced
concrete being a fabricated material, its properties
are much dependent on the procedures adopted 2. CONSTRUCTION REGULATORY
during design and construction. Most of the AUTHORITIES IN
reinforced concrete constructions in Dar es Salaam DAR ES SALAAM
are of in-situ concrete which is labor intensive. It
has been observed that sometimes the desirable Construction regulatory authorities involved in
qualities in terms of strength, serviceability, and regulating construction activities in Dar es Salaam
protection are not achieved particularly when are the Engineers Registration Board, the
appropriate quality control measures are not Architects and Quantity Surveyors Registration
adopted during design and construction. Board, Contractors registration Board, Public
In Dar es Salaam, about 98% of storeyed Procurement Regulatory Authority (for public
buildings are constructed using reinforced concrete, constructions), and the Municipal Councils
and Rubaratuka (2011) established that there are
several cases where reinforced concrete structures
is ensured that a constructed facility will have an professional experience and construction practices in
acceptable service life to function as per intended their regions of application. These codes are
use without significant maintenance cost. regularly revised and updated as and when more
information becomes available regarding materials,
4. INVESTIGATION OF THE design procedures, and construction practices.
QUALITY OF REINFORCED Therefore, the safety, strength, and durability levels
stipulated in a code can be achieved only if the
CONCRETE BUILDINGS recommended design and construction provisions of
the codes and standards have been applied
Investigation of the quality of reinforced concrete judiciously. Partial application of these provisions
buildings in Dar es Salaam involved the following may not yield the intended quality in the constructed
methodology: (i) review of designs of constructed facility.
reinforced concrete buildings, (ii) determining the In the absence of a national code of practice, the
quality of concrete ingredients and steel design and construction of most of reinforced
reinforcement at different construction sites, and (iii) concrete structures are carried out using foreign
assessment of construction technology and codes, namely British Standards, which in some
determining the quality of constructed structural cases are not directly applicable to our conditions. In
components of the building. most cases, designs of structural components are
carried out using material and load partial safety
5. CHALLENGES OF THE QUALITY factors which depend on certain conditions
OF REINFORCED CONCRETE prevailing in the countries of the origin of respective
BUILDINGS codes and standards which are not the same as in
Tanzania. For example, some of the partial safety
Investigations carried out for designs of selected factors for materials and loadings for British
reinforced concrete buildings, and constructed Standards (BS 8110-1-1997) and South Africa
buildings in Dar es Salaam have established the Building Standards (SABS 0100-1 & SABS 0160-
RT
following main causes for unsatisfactory quality of 1989) are shown in Table 1 below.
reinforced concrete buildings: (i) design
deficiencies, (ii) unsatisfactory quality of concrete Table 1: Comparative partial safety factors
IJE
It has been observed that design details provided the provided concrete covers are inadequate as a
for reinforced concrete building structural members result premature deterioration of structural
are inadequate especially for connections of beams, components has been observed.
columns and foundations. For some projects, soil
investigation is not carried out as a result design of 5.2 Quality of Concrete Ingredients
foundations is based on assumptions which do not
take into account the appropriate soil conditions. While in many projects the cement used comply to
Some buildings are constructed without expansion the required standards as shown in Table 3,
joints, foundation beams, etc. For some buildings, sometimes the quality of water, fine and coarse
aggregates used is not satisfactory.
Depending on the source, water used for corrosion which eventually affects the strength and
construction, contains chloride to a slight degree of durability of reinforced concrete buildings.
aggressiveness (slightly less than 300 mg/l.
IJE
Sample Yield Stress (N/mm2) Tensile Stress (N/mm2) ft/fy Elongation (%)
1Y8 512.9 591.5 115 25
2Y8 509.6 588.3 115 25
1Y12 553.2 637.3 115 18
2Y12 557.6 641.7 115 18
1Y16 573.3 670.1 117 19
2Y16 570.2 675.5 118 20
1Y20 611.0 684.0 112 19
2Y20 611.5 688.0 113 17
1Y25 595.1 658.1 111 13
2Y25 596.6 659.8 111 13
REQUIREMENTS FOR TENSILE TEST BS 4449:1997
Steel GR 460 Specified characteristic strength 460 N/mm2 ≥ 110 ≥12
5.3.1 Batching and Mixing 0.5) is normally used hence resulting to production
of permeable reinforced concrete with a lower
It was observed that at many construction strength [2].
projects, the mix design is not carried out as a result Mixing of concrete ingredients is also not
concrete produced is variable and do not attain the adequately carried out and sometimes small concrete
required design strength as shown in Table 5. Lack mixers are used leading to production of concrete
of proper supervision at the construction sites has which is not uniform and with variable strengths as
resulted to batching not being carried out correctly shown in Table 5.
as a result concrete with high w/c ratio (greater than
RT
5.3.2 Form and False works widely used in Dar es Salaam. In many projects,
form and false works are not designed and erected
For concrete to harden and achieve the required properly (see Figure 4) as a result they deform, get
shape, form and false works plays a vital role. To distorted hence affecting the alignment of concrete
minimize the cost of form and false works, wooden members and concrete cover as shown in Figure 5.
props and planks of different sizes and strength are
(a) (b)
Figure 4 Timber formwork for building construction
To avoid such defects, proper erection of
(a) (b)
Figure 5 (a) Deflected reinforced concrete slab (b) Reinforced concrete slab with inadequate concrete cover
in Figure 6.
s Salaam revealed that concrete is poured instead of most recommended wet curing is not fully adhered
being placed. Further, it has been established that to as shown in Figure 9 where columns are partially
lack of compaction equipment/vibrators lead to covered by sacks hence resulting to non uniform
compaction being carried out using timber pieces curing.
hence resulting to inadequate compaction and
concrete members with voids, honeycomb (see
Figure 7) which are permeable.
It has been established that most of the labourers Investigations carried at different construction
involved in concrete works do not have relevant sites in Dar es Salaam, have revealed that some
knowledge, experience and skills for concrete works supervising consultants do not provide adequate
as a result the constructed concrete members do not supervision as a result some contractors are not
have adequate concrete cover as shown in Figure 8 adhering to design specifications as well as to good
for a pad foundation base under construction. construction practices. Figure 10 shows a building
which was still under construction but already
loaded prematurely with cement sand blocks.
REFERENCES