Sr. No. Description Make PROCUREMENT STATUS DELIVERY DATE DELIVERY DATE REMARK
DELIVERY
AT WTE AT SITE
DATES
A.     MECHANICAL EQUIPMENT
1 Centrifugal Pumps with motor Xylem Done on 24.09.2021 15.11.2021 15.11.2021
2 High Pressure Pumps with motor Xylem Done on 24.09.2021 15.11.2021 15.11.2021

MECH
MOTOR
MOTOR MAKE - ANICAL
3 Dosing Pumps Milton Roy Done on 06.10.2021 12.11.2021 12.11.2021 CONFIGUR
HINDUSTAN OPERA
ATION IE2
TED

4 Motors Siemens Done on 24.09.2021 05.11.2021 05.11.2021


5 Air Blower- Twin Lobe Type Everest Done on 24.09.2021 10.11.2021 10.11.2021
6 Air Blower-Centrifugal Type WTE Done on 06.10.2021 30.10.2021 10.11.2021
7 LDPE/HDPE Tanks Arun Plast Done on 06.10.2021 20.11.2021 30.11.2021
8 RO FRP Pressure Vessels Pentair Done on 27.09.2021 27.10.2021 27.10.2021
9 Ball Valves- Metallic Aira Done on 05.10.2021 15.11.2021 15.11.2021
Ball Valves- Non Metallic (MOC
10 Astral Done on 05.10.2021 30.10.2021 30.10.2021
-PP/PVC)
11 Solenoid Valve Aira Done on 05.10.2021 15.11.2021 12.11.2021
12 NRV Intervalve Done on 05.10.2021 15.11.2021 12.11.2021
13 Butterfly Valve Metallic Aira Done on 05.10.2021 15.11.2021 12.11.2021
14 Globe Valve Aira Done on 05.10.2021 15.11.2021 12.11.2021
15 Bag Filter Pratham/ Gopani Done on 15.10.2021 20.11.2021 20.11.2021
16 Cartridge Filter Pratham/ Gopani Done on 15.10.2021 20.11.2021 20.11.2021
17 UF Membrane Dow Done on 27.09.2021 30.10.2021 25.10.2021
18 RO Membrane Dow Done on 27.09.2021 30.10.2021 25.10.2021

19 Resin Thermax Done on 18.10.2021 10.11.2021 05.11.2021

20 Gear box (for agitator) Bonfiglioli Done on 24.09.2021 30.10.2021 30.10.2021


Sheets and Pipe ordered on
21 Fabricated Items WTE 20.10.2021 20.10.2021
29.09.2021
INSTRUMENT LIST
Order will be release on
1 Pressure Gauges H-Guru 10.11.2021 10.11.2021
22.10.2021
2 pH, Conductivity, ORP, Transmitter Emerson Done on 05.10.2021 05.12.2021 05.12.2021
3 DPT/PT ABB Done on 05.10.2021 20.11.2021 20.11.2021
Pressure Switch/Differential Pressure
4 Switzer Done on 05.10.2021 15.11.2021 10.11.2021
Switch
5 Level Gauges Pune techtrol Done on 15.10.2021 25.11.2021 25.11.2021
6 Level Switches Pune techtrol Done on 15.10.2021 25.11.2021 25.11.2021
7 Flow Indicator-Rotameter Aster Done on 05.10.2021 30.10.2021 30.10.2021
8 Flow Transmitter (Emag) Eureka Done on 05.10.2021 30.11.2021 30.11.2021
9 Pneumatic Actuator Aira Done on 05.10.2021 15.11.2021 15.11.2021
10 Flow Switch Scientific Devices Done on 05.10.2021 22.11.2021 15.11.2021
11 Calcium Hardness Online Meter Microset Instrumentation and Control Done on 18.10.2021 20.11.2021 25.11.2021
C. ELECTRICAL COMPONENT
1 MCCB/MPCB Siemens Done on 05.10.2021 05.11.2021 25.10.2021
2 Indicator Teknic Done on 05.10.2021 30.10.2021 22.10.2021
3 Selector switch Teknic Done on 05.10.2021 30.10.2021 22.10.2021
4 Push Button Teknic Done on 05.10.2021 30.10.2021 22.10.2021
5 Contactor Siemens Done on 05.10.2021 05.11.2021 25.10.2021
6 LT Power Cable RPG/Polycab Done on 05.10.2021 20.11.2021 30.10.2021
7 LT copper control Cable RPG/Polycab Done on 05.10.2021 20.11.2021 30.10.2021
8 Signal and Instrument Cable Polycab Done on 05.10.2021 20.11.2021 30.10.2021
9 Terminal Box Connectwell Done on 05.10.2021 30.10.2021 25.10.2021
10 MCC Panel box WTE Done on 05.10.2021 10.11.2021 30.10.2021
11 Cable Glands Comet Done on 05.10.2021 30.10.2021 30.10.2021
12 Cable Lugs Comet Done on 05.10.2021 30.10.2021 25.10.2021
13 Logic Controller Siemens Done on 05.10.2021 05.11.2021 10.11.2021
14 Relay card Trinity Done on 05.10.2021 30.10.2021 30.10.2021
15 Cable tray WTE Done on 05.10.2021 10.11.2021 10.11.2021
16 LPBS WTE Done on 05.10.2021 25.10.2021 25.10.2021
EXPECTED
UPDATE AS ON UPDATE AS ON
Sr. No. Description Make PROCUREMENT STATUS DELIVERY DATE REMARK
26.10.2021 10.11.2021
AT SITE
A.     MECHANICAL EQUIPMENT
DATE TO
Revised delivery
1 Centrifugal Pumps with motor Xylem Done on 24.09.2021 30.11.2021 CONFIRM BY
date-30.12.2021
PURCHASE
DATE TO
Revised delivery
2 High Pressure Pumps with motor Xylem Done on 24.09.2021 20.12.2021 CONFIRM BY
date-30.12.2021
PURCHASE

3 Dosing Pumps Milton Roy Done on 06.10.2021 20.12.2021 28.10.2021 Received at WTE

4 Motors Siemens Done on 24.09.2021 07.12.2021 28.10.2021 Received at WTE

5 Air Blower- Twin Lobe Type Everest Done on 24.09.2021 07.12.2021 10.11.2021 Received at WTE

In Transit,
6 Air Blower-Centrifugal Type WTE Done on 06.10.2021 07.12.2021 30.10.2021 Delivery Date -
12.11.2021
7 LDPE/HDPE Tanks Arun Plast Done on 06.10.2021 07.12.2021 25.11.2021 25.11.2021
8 RO FRP Pressure Vessels Pentair Done on 27.09.2021 20.12.2021 MARCURAS 20.11.2021
9 Ball Valves- Metallic Aira Done on 05.10.2021 07.12.2021 15.11.2021 27.10.2021
Ball Valves- Non Metallic (MOC ORDER
10 Astral Done on 05.10.2021 07.12.2021 27.10.2021 15.11.2021
-PP/PVC) PENDING
11 Solenoid Valve Aira Done on 05.10.2021 20.12.2021 15.11.2021 30.10.2021
ORDER
12 NRV Intervalve Done on 05.10.2021 30.11.2021 27.10.2021 15.11.2021
PENDING
ORDER
13 Butterfly Valve Metallic Aira Done on 05.10.2021 30.11.2021 27.10.2021 15.11.2021
PENDING
14 Globe Valve Aira Done on 05.10.2021 20.12.2021 MARCURAS 15.11.2021
15 Bag Filter Pratham/ Gopani Done on 15.10.2021 20.12.2021 MARCURAS 15.11.2021
16 Cartridge Filter Pratham/ Gopani Done on 15.10.2021 20.12.2021 MARCURAS 20.11.2021
17 UF Membrane Dow Done on 27.09.2021 20.12.2021 30.10.2021 20.11.2021
18 RO Membrane Dow Done on 27.09.2021 20.12.2021 20.11.2021 30.10.2021
19 Resin Thermax Done on 18.10.2021 07.12.2021 20.11.2021 30.10.2021
READY MATERIAL
20 Gear box (for agitator) Bonfiglioli Done on 24.09.2021 07.12.2021 30.10.2021 TO DISPATCH BY 10.11.2021
NEXT 2 DAYS
MS PLATE -
Sheets and Pipe ordered on SHEEL AND
21 Fabricated Items WTE 07.12.2021 30.10.2021
29.09.2021 PIPE 125NB
PENDING
INSTRUMENT LIST 20.10.2021
Order will be release on
1 Pressure Gauges H-Guru 07.12.2021 15.11.2021
22.10.2021
DATE TO
2 pH, Conductivity, ORP, Transmitter Emerson Done on 05.10.2021 20.12.2021 CONFIRM BY 10.11.2021
PURCHASE
3 DPT/PT ABB Done on 05.10.2021 20.12.2021 30.10.2021 PI RECEIVED 05.12.2021
DATE TO
Pressure Switch/Differential Pressure
4 Switzer Done on 05.10.2021 07.12.2021 CONFIRM BY 20.11.2021
Switch
PURCHASE
5 Level Gauges Pune techtrol Done on 15.10.2021 07.12.2021 30.11.2021 15.11.2021
6 Level Switches Pune techtrol Done on 15.10.2021 07.12.2021 30.11.2021 25.11.2021
7 Flow Indicator-Rotameter Aster Done on 05.10.2021 20.12.2021 MARCURAS 25.11.2021
DATE TO
8 Flow Transmitter (Emag) Eureka Done on 05.10.2021 20.12.2021 CONFIRM BY 30.10.2021
PURCHASE
9 Pneumatic Actuator Aira Done on 05.10.2021 07.12.2021 15.11.2021 30.11.2021
DATE TO
10 Flow Switch Scientific Devices Done on 05.10.2021 07.12.2021 CONFIRM BY 15.11.2021
PURCHASE

11 Calcium Hardness Online Meter Microset Instrumentation and Control Done on 18.10.2021 20.12.2021 30.11.2021 22.11.2021
C. ELECTRICAL COMPONENT 20.11.2021
1 MCCB/MPCB Siemens Done on 05.10.2021 07.12.2021 RECEIVED
2 Indicator Teknic Done on 05.10.2021 07.12.2021 RECEIVED 05.11.2021
3 Selector switch Teknic Done on 05.10.2021 07.12.2021 RECEIVED 30.10.2021
4 Push Button Teknic Done on 05.10.2021 07.12.2021 RECEIVED 30.10.2021
5 Contactor Siemens Done on 05.10.2021 07.12.2021 RECEIVED 30.10.2021
6 LT Power Cable RPG/Polycab Done on 05.10.2021 07.12.2021 RECEIVED 05.11.2021
7 LT copper control Cable RPG/Polycab Done on 05.10.2021 07.12.2021 RECEIVED 20.11.2021
8 Signal and Instrument Cable Polycab Done on 05.10.2021 07.12.2021 RECEIVED 20.11.2021
9 Terminal Box Connectwell Done on 05.10.2021 07.12.2021 RECEIVED 20.11.2021
10 MCC Panel box WTE Done on 05.10.2021 07.12.2021 RECEIVED 30.10.2021
11 Cable Glands Comet Done on 05.10.2021 07.12.2021 RECEIVED 10.11.2021
12 Cable Lugs Comet Done on 05.10.2021 07.12.2021 RECEIVED 30.10.2021
13 Logic Controller Siemens Done on 05.10.2021 07.12.2021 RECEIVED 30.10.2021
14 Relay card Trinity Done on 05.10.2021 07.12.2021 RECEIVED 05.11.2021
15 Cable tray WTE Done on 05.10.2021 07.12.2021 RECEIVED 30.10.2021
16 LPBS WTE Done on 05.10.2021 07.12.2021 RECEIVED 10.11.2021
17 PANEL TESTING WTE NA NA 12.11.2021 25.10.2021
SR NO. DESCRIPTION MAKE PROCUREMENT STATUS DELIVERY STATUS

A.     MECHANICAL EQUIPMENT

Delivery date to confirm by purchase team


1 Centrifugal Pumps with motor Xylem Done on 24.09.2021
EOD
High Pressure Pumps with Delivery date to confirm by purchase team
2 Xylem Done on 24.09.2021
motor EOD
Material Ready at vendorOtstanding
3 Dosing Pumps Milton Roy Done on 06.10.2021
payment to done
2 Motors Received at WTE and 02 Motors
4 Motors Siemens Done on 24.09.2021
deliver at Degasser vendor

5 Air Blower- Twin Lobe Type Everest Done on 24.09.2021 Received at WTE

Under Blower and Motor assembly, Purchase


6 Air Blower-Centrifugal Type WTE Done on 06.10.2021
team to confirm the delivery

100 Litre - 200 Litre, 500 Litre, 1500 Litre,


7 LDPE/HDPE Tanks Arun Plast Done on 06.10.2021 20KL Tank…. Dates to confirm by purchase
team by EOD

8 RO FRP Pressure Vessels Pentair Done on 27.09.2021 Marcuras to confirm by EOD

9 Ball Valves- Metallic Aira Done on 05.10.2021 Purchase Team to Confirm by EOD

Ball Valves- Non Metallic


10 Astral Done on 05.10.2021 Purchase Team to Confirm by EOD
(MOC -PP/PVC)

11 Solenoid Valve Aira Done on 05.10.2021 Purchase Team to Confirm by EOD

12 NRV Intervalve Done on 05.10.2021 Purchase Team to Confirm by EOD

13 Butterfly Valve Metallic Aira Done on 05.10.2021 Purchase Team to Confirm by EOD

14 Globe Valve Aira Done on 05.10.2021 Purchase Team to Confirm by EOD

15 Bag Filter Pratham/ Gopani Done on 15.10.2021 Marcuras to confirm

16 Cartridge Filter Pratham/ Gopani Done on 15.10.2021 Marcuras to confirm

Material ready at vendor, Delivery Date -


17 UF Membrane Dow Done on 27.09.2021
25.11.2021
Material ready at vendor, Delivery Date -
18 RO Membrane Dow Done on 27.09.2021
25.11.2021

19 Resin Thermax Done on 18.10.2021 Purchase Team to Confirm by EOD

20 Gear box (for agitator) Bonfiglioli Done on 24.09.2021 Received at WTE

Sheets and Pipe ordered on


21 Fabricated Items WTE
29.09.2021
MULTI GRADE FILTER 1
21.1 WTE Under fabrication - Welding
WITH FRONTAL
MULTI GRADE FILTER 2
21.2 WTE Under fabrication - Welding
WITH FRONTAL
ACTIVATED CARBON FILTER
21.3 WTE Under fabrication - Welding
1 WITH FRONTAL
ACTIVATED CARBON FILTER
21.4 WTE Under fabrication - Welding
2 WITH FRONTAL

21.5 SOFTENER 1 WITH FRONTAL WTE Under fabrication - Dish end, Shell Pending

21.6 SOFTENER 2 WITH FRONTAL WTE Under fabrication - Dish end, Shell Pending

21.7 DEGASSER TOWER WTE Under fabrication - Welding

21.8 DEGASSER SUMP WTE Blasting

21.9 BRINE PREAPARTION TANK WTE Blasting

22 BRINE DOSING TANK WTE Blasting

22.1 Inter connecting Pipe WTE Production team to confirm by EOD

22.2 Pump Skid WTE Production team to confirm by EOD

22.3 RO Skid and Piping Marcuras Marcuras to confirm


22.4 UF Skid and Piping Marcuras Marcuras to confirm

22.5 CIP Skid and Piping Marcuras Marcuras to confirm

INSTRUMENT LIST

Order will be release on


1 Pressure Gauges H-Guru 05.12.2021
22.10.2021
pH, Conductivity, ORP, Material ready at vendor, need to do PI
2 Emerson Done on 05.10.2021
Transmitter payment

3 DPT/PT ABB Done on 05.10.2021 Delivery Date - 24.11.2021 By Vendor

Pressure Switch/Differential
4 Switzer Done on 05.10.2021 Received at WTE
Pressure Switch

5 Level Gauges Pune techtrol Done on 15.10.2021 Delivery Date progressively by 07.12.2021

6 Level Switches Pune techtrol Done on 15.10.2021 Delivery Date progressively by 07.12.2021

7 Flow Indicator-Rotameter Aster Done on 05.10.2021 Marcuras to confirm by EOD

8 Flow Transmitter (Emag) Eureka Done on 05.10.2021 Delivery Date progressively by 07.12.2021

9 Pneumatic Actuator Aira Done on 05.10.2021 Purchase Team to Confirm by EOD

10 Flow Switch Scientific Devices Done on 05.10.2021 Received at WTE

Calcium Hardness Online Microset Instrumentation


11 Done on 18.10.2021 Delivery Date progressively by 07.12.2021
Meter and Control

C. ELECTRICAL COMPONENT

1 MCC Panel box WTE Done on 05.10.2021 Received at WTE

2 Cable Glands Comet Done on 05.10.2021 Received at WTE

3 Logic Controller/HMI Siemens Done on 05.10.2021 Received at WTE

4 Cable and Cable tray WTE Done on 05.10.2021 Received at WTE