Checklist for the SET of Electrical Drawings (SEC Drawings)  Parcel No.  
S.No.  Description  Yes /No / 
Incomplete
1.  Is the List of Drawings along with AUTOCAD soft copy of drawings attached. Yes/No
2.  Is the Keyplan shows the KAFD-Main Sub-stations locations from which the Power Yes/No
Supply to be fed for the concern Parcel and the cable routings upto the Parcel
Boundary.
3.  Is the submitted drawing (i-e Site Setting Out Plan) have the Key / Scale (1:100). Yes/No
4.  Are the submitted drawings have enlarged details in scale (1:50). Yes/No
5.  Are the Level Height of Ground Floor from sub-Road / Main Road is indicated. Yes/No
6.  Are the Municipality / KAFD coordinates shown on the drawings. Yes/No
7.  Is the SEC Room shown on Basement -1 (As per client requirement) Yes/No
8.  Is the Site Setting Plan shows the required Eectrical MAN-HOLE for cable pulling to Yes/No
the building.
9.  Is there any Electrical Man hole within the Parcel Boundary. (If Yes, Is this coordinated Incomplete
with other underground MEP Services.
10.  Are Earth Pits locations shown and coordinated within the Parcel Boundary. If yes, Is Incomplete
the Table for Earth Pit identification numbering available.
11.  Are the (2+1) Nos. x Diameter 150 mm uPVC pipes shown from MANHOLE to the Yes/No
Building cable entry point.
12.  Is the Enlarged details for underground cable installation shows the pipe level, Yes/No
distances, cable warning tapes & cable tiles etc.
13.  Are the Enlarged details (Plan showing sections – XX & YY) for RMU Room & the Yes/No
Transformer Rooms shown.
14.  Are the Level Height and Coordinates for SEC cable penetration sleeve shown on Yes/No
drawings.
15.  Are the Architectural plan indicating HV cable trenches / cable ladder / cable trays Yes/No
routings between RMU Room & Transformer Room, along with section showing the
typical horizontal / vertical clearances available for the route.
16.  Are the foundation details drawings for RMUs / Transformers indicated. Yes/No
17.  Are the cable ladder / cable trays installation details shown on the drawings. from Yes/No
cable entry point to SEC Room / Transformer Rooms shown on the drawings.
18.  Are the clear width & depth of cable trench from FFL (Finished Floor Level) of RMU  Yes/No
Room indicated.
19.  Are the full length of cable routings up to the final destination / termination points Yes/No
indicated.
20.  Is the Architectural plan indicating LV Cables route between Transformer Room & Yes/No
Electrical / LV Room.
21.  Is the copy of Load Summary Sheet attached. (Total KWH meters). Yes/No
22.  Is the load intake & metering arrangement indicated clearly within the Electrical Yes/No
Schematic Diagrams.
23.  Is the Method Statement for transportation of RMUs / transformer(s) is included within Yes/No
this submittal.
Note: In case of cable tray arrangement, Minimum clearance of 0.45 mts. is to be maintained
above bed of the cable tray for cable installation.

 
PERVEZ  AHMAD  KHAN    0556 786 222 
   
 
 
Checklist for the SET of Electrical Drawings (SEC Drawings) Parcel No.
S.No.  Description  Yes /No / 
Incomplete
24.  Is the Method Statement for Testing & Commissioning of RMUs and Transformers in Yes/No
accordance with contracts requirements included within this submittal.
25.  Is the calculations supporting the adequacy of natural ventilation for maintaining the Yes/No
ambient temperature inside the SEC Room is included within this submittal.
26.  Is the Total A/C Load + other Motors / Pumps Loads sheets are included within this Yes/No
submittal.
27.  Is the Total Connected Load, Voltage Drop calculations tables are included within Yes/No
this submittal
28.  Are the installations details with diamensions of RMUs and Transformers indicated on Yes/No
drawings considering the maintenance spaces.
29.  Are the Cable Identification table indicates the sizes of cable trays and the nos. of Yes/No
cable runs, sizes of cable trays openings and the approved cable tags.
30.  Are the Electrical Schematic Diagram drawings clearly indicates the Electro- Incomplete
Mechanical Interlockings, Sizes of Cables, ratings of Bus-Bars, Types of Circuit
Breakers, Types of protective relays for Earth fault protections, Over Voltage
protections and Earth Fault protections considering contracts specifications.
31.  Are the Electrical Schematic Diagrams drawings clearly indicates the metering Yes/No
strategy considering Digital Metering.
32.  Is this submittal includes the cost comparision between contracts specified metering Yes/No
and digital metering.
33.  Is the Electrical Schematic Diagrams drawings clearly indicates the types and ratings Incomplete
of Capacitor banks
34.  Is the Electrical Schematic Diagrams drawings clearly indicates the lightning surge Yes/No
protections / thermal protections. If yes, Are the details included in the NOTES on the
drawings.
35.  Is the remote monitoring module is indicated on the drawings, If Yes, Are the Yes/No
reference numbers of BMS Design drawing indicated.
36.  Is the BMS Architectural diagram for monitoring and controlling of Electrical Yes/No
Switchgear included within this submittal.
37.  Are the RMUs Panels diamensional drawings available within this submittal, If Yes, Yes/No
Are the sizes of cut / holes indicated in gland plates.
38.  Are the Lighting / Power / Fire Alarm / Fire Fighting / HVAC / Ventillations services Yes/No
considered within this drawing considering local authorities regulations and standards.
If Yes, Are they coordinated.
39.  Are the RMUs & Transformer rooms Access Control / Security requirements Yes/No
considered.
40.  Are the details of Doors for RMUs Room & Transformers Room available within this Yes/No
submittal.
NOTE: The opening of Doors for RMUs & Transformers Rooms shall be in outside direction. 
 

 