The document summarizes the responsibilities of different contractors involved in the Bhopal Metro Rail Project Package BH-06 related to traction power supply. It outlines that the traction and power supply contractor will be responsible for designing, supplying, installing and terminating the auxiliary transformer and associated equipment at the depot. It also specifies that the depot contractor will be responsible for designing and providing a comprehensive protection system in coordination with the traction and power supply contractor and providing connection terminals and space for cable/bus duct termination. Both contractors will collaborate on protection devices, current transformers and status monitoring of equipment.
The document summarizes the responsibilities of different contractors involved in the Bhopal Metro Rail Project Package BH-06 related to traction power supply. It outlines that the traction and power supply contractor will be responsible for designing, supplying, installing and terminating the auxiliary transformer and associated equipment at the depot. It also specifies that the depot contractor will be responsible for designing and providing a comprehensive protection system in coordination with the traction and power supply contractor and providing connection terminals and space for cable/bus duct termination. Both contractors will collaborate on protection devices, current transformers and status monitoring of equipment.
The document summarizes the responsibilities of different contractors involved in the Bhopal Metro Rail Project Package BH-06 related to traction power supply. It outlines that the traction and power supply contractor will be responsible for designing, supplying, installing and terminating the auxiliary transformer and associated equipment at the depot. It also specifies that the depot contractor will be responsible for designing and providing a comprehensive protection system in coordination with the traction and power supply contractor and providing connection terminals and space for cable/bus duct termination. Both contractors will collaborate on protection devices, current transformers and status monitoring of equipment.
Item Description Depot Contractor(s) No. Supply Contractor d. Shall coordinate for suitable approach road to ASS, TSS and RSS.
e. Shall arrange material
handling equipment at their own cost.
f. Should ensure height of
the rolling shutters is adequate for pushing in the tallest equipment.
6. Connection Shall coordinate and provide Shall design, supply, terminate
(cable / bus duct) suitable terminals on the and install cable/bus duct from from Transformer secondary side of Aux. transformer secondary to MDB to MDB Transformer for facilitating cable/bus duct connection Shall provide necessary cable trays / support.
7. Protection system Design:
Shall design a comprehensive protection system in coordination with Depot Contractor. Construction: Construction:
a. Shall design and provide a. Shall coordinate and provide
all protective devices for details of protection design Auxiliary Transformer used for low voltage system. protection. b. Shall supply and install CTs in b. Shall coordinate and MDB panel as per the provide details of CTs to requirement given by Traction be installed in MDB for and Power supply contractor. various protections e.g. differential, REF protections to c. Shall provide potential free Depot Contractor. contacts for power SCADA connection by Traction and c. Display of Status of LV Power supply Contractor for ACB in MDB on display of LV ACB in MDB to
Attachment – 8 to Corrigendum – 2, Date: 10.11.2021 Page 36 of 80