This document outlines the responsibilities for different contractors working on the Bhopal Metro Rail Projects Package BH-06. It contains an interface matrix that assigns one of four levels of responsibility - Responsible, Accountable, Consulted, or Informed (RACI) - to various contractors for civil works, electrical and mechanical systems, lighting, drainage, fire safety, and equipment rooms for each of the metro lines - Purple Line (underground and elevated) and Red Line (elevated). The civil works contractor takes the lead role (is Responsible and Accountable) for most interface work while the other contractors (railway system, track work, rolling stock) are informed or consulted on issues relating to their scope of work
This document outlines the responsibilities for different contractors working on the Bhopal Metro Rail Projects Package BH-06. It contains an interface matrix that assigns one of four levels of responsibility - Responsible, Accountable, Consulted, or Informed (RACI) - to various contractors for civil works, electrical and mechanical systems, lighting, drainage, fire safety, and equipment rooms for each of the metro lines - Purple Line (underground and elevated) and Red Line (elevated). The civil works contractor takes the lead role (is Responsible and Accountable) for most interface work while the other contractors (railway system, track work, rolling stock) are informed or consulted on issues relating to their scope of work
This document outlines the responsibilities for different contractors working on the Bhopal Metro Rail Projects Package BH-06. It contains an interface matrix that assigns one of four levels of responsibility - Responsible, Accountable, Consulted, or Informed (RACI) - to various contractors for civil works, electrical and mechanical systems, lighting, drainage, fire safety, and equipment rooms for each of the metro lines - Purple Line (underground and elevated) and Red Line (elevated). The civil works contractor takes the lead role (is Responsible and Accountable) for most interface work while the other contractors (railway system, track work, rolling stock) are informed or consulted on issues relating to their scope of work
Package BH-06 Volume III – Employer’s Requirements
APPENDIX IV PROJECT INTERFACE MANUAL
Interface RACI Matrix
Civil Works Contractor
Railway Track Rolling Type Scope of Services / Works System Work Stock Purple Red Depot Purple Line Contractor Contractor Contractor Line Line Underground Elevated Elevated
A Civil Works Tunnel Sections
1 Electrical & Mechanical (E&M)
a. Low voltage electrical distribution Interface 1 Lead
b. Lighting Interface 1 Lead
c. Lightning protection Interface 1 Lead
d. Station HVAC Interface 1 Lead
e. Drainage system Interface 2 Interface 2 Lead
f. Fire fighting Interface 1 Lead
g. Plumbing Interface 2 Lead
Rooms for Railway Systems
2 Interface 1 Lead equipment
Volume III – Project Interface Manual Page 1 of 10