Bhopal Metro Rail Project

Package BH-06

Attachment – 8 to Corrigendum – 2
Volume III, 12.9.8, “Interface between Depot Civil Contractor and Power Supply
Contractor”
Interface between Depot Civil Contractor and Power Supply Contractor

Item Traction and Power


Item Description Depot Contractor(s)
No. Supply Contractor

1. Installation of a. Shall supply & install 33 a. Shall construct cable trenches


132KV, 33KV, kV, 750 V DC cables, ETS for carrying the cables from
750V DC cables, cables, traction cables RSS complex to Depot ASS
ETS, traction and control cables (132KV and OCC ASS and various
cables and cable not in the scope of third rail / return rails in the
control cables. Traction and Power depot area.
supply contractor).

b. Shall provide and install cable


b. Shall co-ordinate and give support infrastructure (metallic
requirements to the Depot brackets, trays etc.) inside the
Contractor for the cable trench / cable duct as per
trench and cable path for requirement.
33 KV, 750V cables,
return cables and control
cables in the Depot area
c. Shall provide suitable opening
and HDPE pipe for carrying
c. Shall co-ordinate with
cables at appropriate locations
Depot contractor for
as per the requirement.
provision of opening and
HDPE pipes of adequate
size to carry the cables at d. Shall take into consideration
appropriate locations the bending radius of cable
and covering of cables at
relevant places.

2. Temporary Power a. Shall co-ordinate with a. Shall provide temporary power


for Installation, depot contractor for as per requirement.
testing & provision of suitable
commissioning. sockets for temporary
power.
b. Shall pay to the depot b. Shall provide suitable meters
contractor for the power for calculating the consumption.
consumption.
c. If temporary power is not
available with Depot

Attachment – 8 to Corrigendum – 2, Date: 10.11.2021 Page 33 of 80