Professional Documents
Culture Documents
Team:
Sukhoi
A Report
On
At
By
Team SUKHOI
Team Leader Under the Guidance of
a) Thus with the suggested techniques along with the sustainable continuous improvements, the
Division has saved Rs. 1, 82, 59,200/- (Rs. One Crore Eighty Two Lakhs Fifty Nine
Thousands Two Hundred) per year as compared with the old existing set up.
b) The Overall cycle time of coupling in jig has been reduced to 14 days from existing 30 days
(i.e. reduced by 54%)
List of Illustrations
Hindustan Aeronautics Limited, Nasik Division was established in 1964 for license
manufacturing of MiG 21FL aircrafts & K-13 Missiles. Since then the Nasik Division is engaged
in manufacturing and overhaul of Russian origin aircrafts under license like MiG-21FL, 21M,
MiG-21 BIS and MiG-27M. The ongoing project is manufacturing of SU30MKI aircraft under
license manufacturing from Russia.
Under the license manufacturing, the SU30 project is under taken in 4 phases to cater the
absorption of manufacturing technology in progressive manner as below...
Phase – I : Flyway series (Direct Purchase from Russia)
Phase – II : Installation and equipping onwards (Looming done by HAL)
Phase – III : Structural Assembly onwards (Pre-coupling and further assembly done by HAL)
Phase – IV : Raw Material Series Production (Complete indigenization)
Over the period of time, as compared to original Contractual production plan with Indian Air
Force (IAF), the supply of SU-30 MKI aircrafts to IAF is behind schedule by 36 aircrafts as on
March 2015. The present rate of production is not able to meet the customer demand. There is
still a difference of 36 aircrafts in planning and actual delivery to IAF. This is attracting huge LD
charges against HAL. In order to compensate the backlog, the production rate of aircraft from
the Division has to be enhanced up to 14 aircrafts per annum specially from sub assembly
complex.
The whole aim of this project is to either eliminate or to minimise this gap so as to achieve the
required rate of production through reduction in TAKT time by implementing various new and
worldwide accepted management techniques and capacity enhancement. The implementation of
the suggestions and recommendations of this project will result in reduction of LD charges. Sub
assembly is the area where we can augment the capacity and increase the direct production rate.
Hence it was necessary to identify such critical stages which contribute majorly in increasing the
cycle time of sub-assemblies. The sub assembly complex consists of 5 different major shops.
1. Front Fuselage shop 4. Air Intake Assembly shop
2. Centre Fuselage shop 5. Wing Assembly Shop
3. Rear Fuselage shop
The Critical path of Sub assembly complex shows that Centre Fuselage assembly is critical as
shown in fig 1.
The work content and criticality in terms of inter jig requirements involved in Centre fuselage
assembly was more as compared to other Fuselage assemblies. Hence, Centre fuselage assembly
is taken for project study and analysis (Fig 2)
(Note: Due to confidentiality issues some of the data and values cannot be disclosed in this
report)
Centre Fuselage is the aircraft’s main load carrying structure. The design of the wing centre section
includes two fuel tanks; Tank No 1 and Tank No 2, and two wheel well bays. The Tank No 1 is
located between frame No 18 and 25 and Tank No 2 is located between frame No 25 and 34. The
wheel well bay on port and starboard side provide accommodation for main wheels after retraction
of landing gears. The main landing gear legs are attached to the bottom side of beam provided inside
the tank No 2. The engine air intakes and air ducts are attached to the bottom panels of wing center
section.
The Centre Fuselage Assembly involves six main stages as below…
a) Tank 1 Assembly : Structural assembly of Tank 1 parts and small assemblies
b) Tank 1 Equipping : Assembly and Testing of pipelines, accumulator, etc
c) Tank 2 Assembly : Structural assembly of Tank 2 parts and small assemblies
d) Tank 2 Equipping: Assembly and Testing of pipelines, accumulator, etc
e) Tank 1 & Tank 2 Coupling : Joining of Both Tank1 & 2, its off jig work and Airbrake suiting
f) Testing : Airtightness and fuel testing with PPU installation
The work content in Centre Fuselage assembly and employee distribution is as shown in fig 3 &
4 respectively.
Tank II Equipping
Tank II
Equipping, 4 Tank I & II Coupling
Testing
Tank II, 14
Tank I
Equipping, 5
Figure 4: Number of employees per stage
The Avg Cycle time required for completion of all the tasks in coupling in jig was 30 days (fig 5)
30
Avg Cycle time: 30 days 24 24
25
20 20
20
15
10
5
0
1st A/C 2nd A/C 3rd A/C 4th A/C 5th A/C 6th A/C 7th A/C 8th A/C 9th A/C
Number of Aircraft
All the tasks are distributed equally among employees based on SMH. With this we come to
know non value adding activities, time consuming and critical activities. The study is mainly
concentrated on these two aspects of shop for improvement. In Fig 6 all tasks oc coupling in jig
are mapped.
13-14 mm
1.1.3 Since this is contractual obligation, we have taken approval from OEM Designer
before implementing.
1.2 Phase II:-
1.2.1 In this 2nd phase, balanced milling operation is started after completion of
Fastening/coupling of tank-1 with centre section of wing on joint (Activity 10)
1.2.2 In this phase we are removing balance material of about 1.5 to 2 mm followed by
reaming of parting plane (Activity 19 & 20)
1.2.3 Only 1 operator (each on LH & RH) are allotted for doing milling task. At the
same time the other partner operator is engaged in doing other activity in parallel.
1.3 Reaming and spot facing activities were also splitted into two activities.
Figure 10: Gantt chart of Coupling in jig activities after splitting milling tasks only
Figure 11: Gantt chart of Coupling in jig activities after complete improvement
3. Provision of Bin trays has eliminated the non-value adding activity. Now the activity can be
done in 15-20 mins instead of indirect 1 day.
4. Shifting of testing procedure has again reduced the cycle time to 1 day instead of 2-3 days.
5. The increase in moral and enthusiasm among employees due to ease and standardization of
work procedure has increased the learning factor rapidly. Due to parallel and effective work
distribution, more tasks are getting completed in time.
6. Thus overall effect all these improvements and changes in all respect has resulted in
reduction in cycle time of coupling in jig to 13-14 days over the period of time (i.e. reduction
by 5%)( Fig 12)
7. The total Takt time of coupling in jig has been reduced to 38 days from 111 days i.e
reduction by 68 % and is maintained further. Thus the improvements are standardized and
sustained for longer production run.(fig 13)
3rd A/C
4th A/C
5th A/C
6th A/C
7th A/C
8th A/C
9th A/C
2nd A/C
SB-178
SB-179
SB-180
SB-185
SB-186
SB-187
SB-188
SB-189
SB-190
SB-191
SB-192
SB-193
SB-194
SB-195
SB-196
SB-201
SB-202
SB-203
SB-419
Figure 12: Total Cycle time after improvement
80 69
55 55
60 50 48 48
43 45 45 41
39 35 36 38 38
40 28 32 31 30
19 23
20
Avg Takt time after improvement 38 days
0
1st A/C
3rd A/C
4th A/C
5th A/C
6th A/C
7th A/C
8th A/C
9th A/C
2nd A/C
SB-178
SB-179
SB-180
SB-185
SB-186
SB-187
SB-188
SB-189
SB-190
SB-191
SB-192
SB-193
SB-194
SB-195
SB-196
SB-201
SB-202
SB-203
Annual savings (12 AC per year) = Rs. 1, 82, 59,200/- per year
identifying the value adding activity and non-value adding activity either eliminating or reducing
The Cycle time and Takt time of coupling in jig has been drastically reduced and made the jig
non critical. Similar type of tools can be applied to other stages of Center fuselage assembly so
as to reduce overall cycle time and Takt time of Centre Fuselage Assembly. The HAL
Management has appreciated efforts by letter in fig 14.