Standard Work Instruction Sheet

Process Name Part Number Customer Demand Takt Time (sec per piece) Prepared By

Standard WIP Date

Quality Time
SWIP =
Work Description Key Points

Minutes

Seconds
- Go, no-go Safety =
Check - Safety

Gage
No.

- Ease Quality =

Total Manual Cycle Time


Standard Work Instruction Sheet
Process Name Part Number Customer Demand Takt Time (sec per piece) Prepared By
625 43 C. Nelson
Small Steel Machining I-12345 Net Operating Time in sec Standard WIP Date
27,000 5 20-Dec-10
Quality Time
SWIP =
Work Description Key Points

Minutes

Seconds
- Go, no-go Safety =
Check - Safety

Gage
No.

- Ease Quality =
1 Pick up material Verify part number and scan barcode 4
2 Turn OD Visual No gloves while operating lathe 9
3 Grind Face Visual Use alignment fixture 5
4 Mill groove Visual Check bit each morning for wear 9
5 Gauge Caliper 8
6 Pack Bend knees when lifting 4

Total Manual Cycle Time 39