Ministry of Public Works

Procurement Directorate
Projects of International Procurement Department
Sonbola 1391 (September 2012)

Completed Projects
Project
Project Name Funding Project Starting Closing Paid
S. No Length in Contractor Consultant Work Progress Work Status
& Location Source Cost Date Date Amount
km
Road MPW
Government
Construction of 37 Million Abad Rahaan Director of 323231155. Remaining work
1 124 of Hoot 1385 Hoot 1387 100%
Torghundi, USD Pars Iran Herat & Eng. 145 USD 11km
Afghanistan
Herat Province Kahingi
Project from
Government 1390/1/30 1390/7/30 Khybar Rasooli Eng. Zahir
Aftash Bridge, 455 mtr 3812349 Project Handed
2 of April 19, May 28, Construction from Kunduz 100% 100%
Kunduz Asphalt Afghani Over
Afghanistan 2011 2011 Company Region
Province
Internal Roads Government 3.7 1388 Saratan Haji Khail MPW
Guarantee
3 Pitching of 10.4 km of Million January 1391 Construction Director of 100% 100%
Condition
Shahra-beg Afghanistan USD 23, 2010 June 2011 Company Samangan
Over work was
100%
send for
German Completed
Internal Roads Government 1.45 1389 MPW procurement to
1388 Afghan Khail 1294280.81 with 5 faults
4 Pitching of 2.2 of Million February Director of ARDS where the
May 27, Construction USD but the
Shebarghan Afghanistan USD 27, 2010 Ghor tenders are in the
2009 Company company has
evaluation
been notified
process
Road Pitching
Government 1388 1389 Directorate From Directorate
of Farza District 2 Million Directorate of
5 10 of October March of Project 100% of Transport &
of Kabul USD Kabul Zone
Afghanistan 2010 2012 Building Infrastructure
Province
Eng. Wais
Pitching of
Government 6.1 1388/8/1 Ilyas Wais from MPW’s
Shebarghan 1386/1/16 Guarantee
6 17.5 km of Million March 27, Construction Survey & 100% 100%
City’s Internal April 2007 Condition
Afghanistan USD 2009 Company Engineering
Road
Directorate
7 Road repair of 132 km Government 1.35 1388 1389 Cinderella Eng. Fridoun 100% Guarantee
Pulikhumri to of Million December June 2011 Director of Condition
Sher Khan Afghanistan USD 2009 MPW in
Bandar, Kunduz Kunduz
Road Sonbola Eng. Fridoun
Government 1387
Construction of 4934454 1390 Director of Guarantee
8 30 km of March 10, Badghis 100% 100%
Baharak to USD September MPW in Condition
Afghanistan 2009
Khwaja Ghar 2011 Kunduz
Project of Government 17575722 1390/5/27 1391/5/27 Al-Hoti Eng.
Guarantee
9 Rubat to Juz- 1.929 km of .15 February February Construction Mohammad 100% 100%
Condition
Sang Qala Afghanistan Afghani 2012 2013 Company Qasim

Underwork Projects
Fundin
Project Name & Length of the Project Starting Closing Paid
No g Contractor Consultant Work Progress Work Status
Location Project in Km Cost Date Date Amount
Source
Gover
Second Phase of nment MPW A panel is
2.5 Million 1390/11/1 2268052.6
1 Herat City Roads 7.2 km of 1389/6/16 Ferdous Jawad Director at 100% assigned for the
USD 6 USD
Construction Afghan Herat primary takeover.
istan
Gover
A panel is
Road Construction nment Badghis MPW
4.19 Saratan assigned for
2 of Khan Abad to 17.3 of Qaws 1387 Contraction Director of 100%
Million USD 1391 takeover of 2.3
Musa-Zai Afghan Company Kunduz
km.
istan
On
1388/9/30
the first
handover
Gover was taken Engineer A panel was
Road Construction nment 1386 place and Fridoun assigned for
1359405 1357104
3 of Khuwja Khar to 16 km of December the second Ferdous Jawad Director of 100% primary takeover,
USD USD
Dasht Qala Afghan 31, 2007 handover MPW in but have not yet
istan was due Kunduz reported.
after 6
month of
the above
date
Gover On Engineer Due to the design
Road Construction
nment 1387 1388/9/30 Fridoun change the work
of Dasht Qala to 2020352 1593551
4 24 km of December the first Ferdous Jawad Director of 65% was delayed. Also
Khuwaja USD USD
Afghan 31, 2007 handover MPW in the availability of
Bahaudine
istan was taken Kunduz & fund was limited
place and Eng. Khair on that year
the second Mohammad therefore the
handover from Survey progress of work
was due & Project was delayed by
after 6 Design the company
month of Directorate
the above
date
On
1388/9/30
Eng. Fridoun
the first
Director of
handover
MPW in
Gover was taken
Road Construction Kunduz &
nment 1387 place and
of Khuwja 2146712 Eng. Sayed 1347364
5 19 km of September the second Ferdous Jawad 50%
Bahaudine to USD Akbar USD
Afghan 20, 2008 handover
Yangi Qala Construction
istan was due
Manager for
after 6
Takhar
month of
Province
the above
date
Despite
Eng. Sayed disagreement on
Gover
Akbar the project’s build
Construction of nment 1387 Hoot 1390
4529688 Khan Shreen Construction 2674938.21 design in 1389, a
6 Yangi Qala to Cha 30 km of September March 59%
USD Khan Manager at USD new section was
Ab Afghan 20, 2008 2012
Takhar added and the
istan
Province work is in
progress
Despite
disagreement on
Gover Eng. Sayed
Road Construction the project’s build
nment 1391/7/1 Raouf
of Duo Rahi 9734187.8 December Mohammad 7596093.01 design in 1389, a
7 44 km of September Director of 80%
Khawja Khar to USD 31, 2007 Naeem Sons USD new section was
Afghan 2012 MPW in
Rustaq added and the
istan Takhar
work is in
progress
Overwork of the
Gover
1389/10/2 project has been
nment Saratan Haji Khail Director of
Pitching of Farah’s 6.7 Million 0 6479669.2 send to the
8 12.58 km of 1391 Construction MPW in 95.7%
inside Roads USD February USD committee of
Afghan June 2012 Company Farah
2011 procurement
istan
directorate
Gover
1389/11/2 Construction
Pitching of Mazar- nment 1390/11/2 Ghulam Rasool
12.3 5 Manager of 6370171.1
9 e-Sharif inside 19.915 km of 5 Construction 51.73%
Million USD September MPW in USD
roads Afghan May 2012 Company
2011 Mazar
istan
Gover
Road Pitching of Sonbola
nment 1.76 Sawr 1392 Afghan Korea Project
Gardanwal to 1390 958136558
10 st 40 km of Million January Construction Design 38.68%
Chegh-cheran 1 January Afghani
Afghan Afghani 2013 Company Engineers
phase 2012
istan
Gover
1390/10/1 1391/10/1
Pitching of Mazar- nment Directorate
297 Million 4 4 20111658.7
11 e-Sharif inside 15 km of Elyas Wais of MPW in 10%
Afghani January January 5 Afghani
roads Afghan Balkh
2012 2013
istan
Design of 20km
has been
Road Pitching of Saudi 38.78 February February Eng. Sayed 5.8 Million Not yet
12 52 km Cinderella completed and
Armak to Laman Arabia Million USD 2012 2013 Mujtaba USD reported
the work is still in
progress
Gover
First Phase of nment 1390/8/11 1391/8/11
76607770 NRAP 13298127.1
13 Manara to Qareeia 8.495 km of August August Cinderella 17.4%
Afghani Engineers 7 Afghani
Noqra, Herat Afghan 2011 2012
istan
nd Gover
2 Line Road
nment Elyas Wais A group of
Construction of 577 Million 86755916
14 26.6 km of 1391/1/16 1392/7/16 Construction MPW 3.7%
Qalai Moradbeg to USD Afghani
Afghan Company engineers
2 Sarake Bagram
istan
Gover Design problem
Asphalting of Ahda
nment Nawi Sahak was solved with
to Haska Meena, 150682556 NRAP Not yet
15 16.732 km of --- --- Construction 0 NRAP and from
Nangarhar Afghani engineers reported
Afghan Company 1391/6/8 work
Province
istan has started
Gover
Project of
nment Badghis, Hobi Work has started
Ghuriyaan District 496929430 NRAP 10% pre- Note yet
16 27.59 km of 1391/4/21 18 months Lemnia and in the phase of
of Herat Province, Afghani engineers paid reported
st Afghan Chenai mobilization
1 phase
istan
Project of Gover Badghis, Hobi Newly contracted
488735990 NRAP 10% pre- Note yet
17 Ghuriyaan District 30 km nment 1391/4/21 18 months Lemnia and and the work has
Afghani engineers paid reported
of Herat Province, of Chenai started in the
st
2 phase Afghan phase of
istan mobilization

Under Bidding Projects

1 Dara Kaihan Road 19km At the process of announcement (Budget Problem)

nd
2 Project for the 2 Phase of Manara to Qarya Noqra, Herat 9.54km Tenders at the evaluation process (Budget Problem)
Province
3 Road Pitching of Khenjan to Andarab 13.140km Tenders of the companies has been send to ARDS committee for review (Budget
Problem)
4 Project for inside city road of Taliqan 50.075km Tenders of the companies has been send to ARDS committee for review (Budget
Problem)
5 Project for inside city road of Zarang, Nimroz Province 10km Tenders of the companies has been send to ARDS committee for review (Budget
Problem)
6 Mazar-e-Sharif Ring Road 17km Tenders of the companies has been send to ARDS committee for review (Budget Problem
for the year 1392)
7 Lata-Band Road Project 25.49km Has been send to ARDS for announcement

8 Road Project for inside city of Ghazni 10.42km Budget problem for the year 1392

9 Road Project for Trinkot 20km Budget problem for the year 1392

10 Pavement and drainage Project for Badgis province Survey and design not available but have kept the Directorate of Project Design in the
picture
11 Ring Road of Shebarghan 15.069km Has been send to ARDS for announcement