Maintenance Scheduling
1 25 November 2016
DEFENISI & CAKUPAN
MAINTENANCE SCHEDULING
A short definition of maintenance planning and scheduling:
Planning decides what, how and time estimate for a
job. Scheduling decides when and who will do the job. Planning
of a job should be done before scheduling a job. There are two
main types of maintenance: preventative maintenance (routine)
& corrective maintenance.
Maintenance Scheduling
2 25 November 2016
SERVICE PERIODIC MAINTENANCE
Maintenance Scheduling
3 25 November 2016
PM CHEK & BACKLOG MANAGEMENT
Backlog
Suatu kegiatan preventive maintenance
dengan melakukan identifikasi dini gejala-
gejala kerusakan, membuat scheduling
Daily Inspection or PM Check
perbaikan yang tepat agar tidak Suatu kegiatan preventive maintenance
mengganggu kegiatan operasi alat. dengan melakukan pengecekan unit
(add oil, add radiator, greasing dump
body, check propeller shaft & steering,
make part recommendation)
Kerusakan ?
Maintenance Scheduling
4 25 November 2016
MANFAAT BACKLOG MANAGEMENT
Maintenance Scheduling
5 25 November 2016
FLOW PROCESS BACKLOG
Application : Prosedure Pelaksanaan Maintenance - PM Daily, Periodic Service & Backlog System - unit FMC
PM Crew Radio Operator PS Crew & Backlog PPIC Dept / Mgr Support
Tdk
Lengkap
Check &
Input ke program Parts
Analisa by
3 Excel Service-EMR 5a Report : Parts Dept
Spv
Olah data EMR & Backlog & kapan
Catat dgn lengkap 7
SR, Time Down & up Entry Backlog Items diperlukan
6
Time Up, Comp yg
rusak/leak/retak dgn
jelas, plus PN yg rusak
Maintenance Scheduling
6 25 November 2016
EFFECTIVE BACKLOG MANAGEMENT
BACKLOG MANAGEMENT
INSPECTION
& PREPARATION PLANNING EXECUTION EVALUATION
VALIDATION
Maintenance Scheduling
7 25 November 2016
EFFECTIVE BACKLOG MANAGEMENT
INSPECTION
&
VALIDATION
UPDATE
SUMMARY
KEBERSIHAN BACKLOG
• Scheduled • Update
Washing FREKUENSI VALIDASI Backlog
CHECK SHEET
• Sarana status
• Man Power
• Pengisian check sheet
• Daily Check • Job instruction Tgl, HM, Inspector,
• Sched. Service • Detail Task List P/N, Qty
• Unit Down • Format Check sheet • Cross check backlog
• Unit stand by
sebelumnya & Saat
inspection selanjutnya
Maintenance Scheduling
8 25 November 2016
EFFECTIVE BACKLOG MANAGEMENT
PREPARATION
PART TOOLS/SARANA
OVH/EXCHANGE FABRICATON
• Check Stock
• Raise SO • Check tools avail.
• Material
• Monitor Status • Check Stock • Bay workshop utk
• Kawat las
• Coordination • Raise SO/ SR/ IO pengerjaan khusus
• Welder
with Part Dept • Speed up • Check avaib.
• Procedure Fab
comp OVH Sarana/support
• Consumable
• Coordination with
CRC
Maintenance Scheduling
9 25 November 2016
EFFECTIVE BACKLOG MANAGEMENT
Weekly meeting
PLANNING coordination
DURATION
PLAN SERVICE
CREATED WCS
Maintenance Scheduling
10 25 November 2016
EFFECTIVE BACKLOG MANAGEMENT
Backlog
Sched Replacement
comp/parts
Additional Backlog
Tools Avaibility
Equipment support
Maintenance Scheduling
11 25 November 2016
EFFECTIVE BACKLOG MANAGEMENT
EXECUTION
PREPARATION FINAL
INSPECTION
RECEIVING
INSPECTION
• Preparation CONTROLLING
• Pre release
sebelum unit JOB DISTRIBUTION Inspection
di down kan • Check additional
(see WCS) Job diluar WCS • Control Job
sesuai WCS
• Supervisi dan • Review Progress
distribution job • Update WCS status
(target job & safety)
Maintenance Scheduling
12 25 November 2016
EFFECTIVE BACKLOG MANAGEMENT
EVALUATION
• Deviasi HM
• Deviasi Duration • List backlog finish • Buat activity plan untuk
• Hambatan/kendala • List Backlog pending perbaikannya sesuai
• Additional Backlog hasil evaluasi plan PS &
• Duration Backlog VS actual
• Hambatan/Kendala
Maintenance Scheduling
13 25 November 2016
GENERAL OVERHAUL PROGRAM (GOH)
Standar Overhaul Component:
* Overhaul Engine
* Overhaul Transmission
* Overhaul Drop Box (Gear Box)
* Overhaul Differential (Front, Middle & Rear)
* Small Component Recondition (Compressor, Propeller
Shaft, Alternator, Starter Motor, Cylinder Dump/ Hoist,
Boom Cylinder)
Maintenance Scheduling
14 25 November 2016
GENERAL OVERHAUL PROGRAM (GOH)
Maintenance Scheduling
15 25 November 2016
GENERAL RESPONSIBILITY OF
PLANNER
Adapun yang menjadi tanggung jawab planner adalah:
1. Menyusun daily and weekly plan untuk pekerjaan maintenance (PM, Service, Overhaul)
2. Manjalankan aktivitas health planning (daily inspections, electronic downloads,
scheduled oil sampling, lubrication and top-up oils, monitoring of application and operating
practices, monitoring equipment)
3. Membuka work orders untuk planned work
4. Membuat plan budget untuk parts, consumable, component overhaul
5. Memastikan manpower planning
Performance measurement yang digunakan untuk mengukur kinerja planning antara lain :
1. Service accuracy
2. Backlog ageing
3. Planning efficiency
Planning menjadi jembatan antara strategy dan operation, dimana planner bertanggung
jawab untuk memastikan bahwa kegiatan yang sudah di-setup oleh strategy bisa terlaksana
oleh operation. Kata lain dari planner yang mudah dipahami adalah event organizer. Target
dari planning efficiency adalah 80% downtime & cost dari maintenance activity.
Maintenance Scheduling
16 25 November 2016
FOCUS & TARGET OF
MAINTENANCE SCHEDULING
Fokus dari planning dalam melaksanakan tugasnya adalah efisiensi, dimana dengan planning yang
berkualitas dan informasi yang akurat proses pekerjaan bisa terlaksana sesuai dengan alokasi waktu dan
biaya.
Maintenance Scheduling
17 25 November 2016
Thank you