1. Tracks Completion
Dates of Important
Metrics.
2. Identifies Red
Issues during the
APQP Process.
3. Displays Valve
Completion Status.
Why Change?
30 30
Da Da
OLD ys ys
PPAP Run at
Contract Rate Valve
Valve
ed R@R
1rst
Valve A Valve B Saleable Completion
Tool Required Start First MRD Deadline
Date Production (-15wks) (-8wks )
(Approx -120 to -78 Part Required
wks) (Approx -
APQP SQE to adjust to 38wks)
Sourced
Kick Off match Tool
Construction Start
Enhanced 30
Da
30
Date
Da
ys ys
OLD
30 30
Day Day
s s
Contracte Run at
Valve B PPAP Valve Rate Valve
d Valve A Powertrain Powertrain R@R
Powertrain P Release Design Purchase Completion
Freeze Parts (PP) Deadline
PPAP
APQP
Sourced
Kick Off
Enha 30 30
nced
Da Da
ys ys
19 Tasks/Categories
1 Question per Task
Red/Yellow/Green
Defined Answers
Answers Locked at
“Locked Date”
Enhanced Valve Question
Type
21 Elements/Categories
4-6 Questions per Element
Red/Green
Answers based on SQE
Judgment
Answers can be updated
anytime
Pop-Up detail of question
Comment area for each
question
Last person to update
captured
Red or Green
Current System: Answers are Limited to a “Pre-Defined” Red,
Yellow, or Green selection
GREEN 1. Complete
2. On Track
3. Not Complete but have a low risk plan that meets
program dates
Elements
Elements are groupings
of questions.
2. Non Completed SRVs due prior to the change date will Automatically
be Exempted
Review
Due Date
Status
Red Issues
Group #
Purpose: Provide a
status of the SRVs for
the selected SQEs,
Programs, or
Suppliers.
3 Display Options
Drilldown to detail
Question Status (1 of 2)
Question Status (2 of 2)
Date Tracker
Date Tracker
What is the difference between the actual GM1927-11 APQP Valve Assessments versus the
APQP SRV’s Template?
With the APQP SRV’s Template, we have the target date for each task and we can perform a
review every week in where at least 5 to 9 tasks can be reviewed it to ensure completion, doing
so, we will avoid any open item during the SRV review date, we will know since week -106 if
some tasks from the SRV1 are not complete instead of week -76.
With the APQP SRV’s Template, we are following the APQP task by task and not just doing a
"check list" during the SRV review date.
APQP SRV’s Template
Pros
• Living document, adding new programs daily, weekly, monthly.
• Clear vision of when the SRV tasks must occur.
• Standardized planning for SQEs and suppliers.
• Review and complete all SRV tasks on time.
• Aware about missing or incomplete SRV tasks before SRV review
date.
• Complete knowledge about the current status for any program.
Cons
• Manual updates.
Q&A
Thanks
Electrical SMT