Professional Documents
Culture Documents
XIII MISCELLANEOUS
A. TEMP. PROJECT SIGNBOARD (1.2X1.2M
1 unit 1,500.00 1,500.00
PLYWOOD)
II. EARTHWORKS
A. EXCAVATION
Quantity = 170.4 Cu.m.
I.Direct Cost
Employ 4 Laborers
2 days
I. EARTHWORKS
A. EXCAVATION
Quantity = 245.3 Cu.m.
3,040.00
TOTAL 59,280.00
1. FOOTING
Vol.1 32.81 cu.m
2. COLUMN
Vol. 9.26 cu.m
3. TIE BEAM
Vol. 2.33 cu.m
4. FRAMING BEAM
Vol. 11.65 cu.m
4. ROOF BEAM
Vol. 7.89 cu.m
V. ROOFING WORKS
A. Materials UNIT QTY. U-COST AMOUNT
RIB TYPE G.I ROOFING SHEETS LM 295.00 480.00 141,600.00
50mm X 50mm X 5mm ANGLE BAR pcs. 50.00 588.00 29,400.00
16mm DIA SOGROD pcs. 10.00 200.00 2,000.00
8mm GUSSET PLATE pcs. 8.00 485.00 3,880.00
TECKSCREW box/es 16.00 495.00 7,920.00
WELDING ROD SETS 6.00 780.00 4,680.00
TURN BUCKLE 189,480.00
branches: 3@
20amp a. Total Material Cost P 143,610.00
B. Labor
1 Const. Foreman @ 500.00 /day x 10
3 Mason @ 400.00 /day x 10
2 Laborers @ 300.00 /day x 10
SUMMARY
I. Materials
II. Equipment
III. Labor
IV. ESTIMATED DIRECT COST
` B. Labor
1 Const. Foreman @ 500.00 /day x 21
3 Carpenter @ 400.00 /day x 21
4 Helpers @ 300.00 /day x 21
SUMMARY
I. Materials
III. Labor
IV. ESTIMATED DIRECT COST
Qtty= 146.70 SQM
UNIT QTY. U-COST AMOUNT
pcs 408 120.00 48,960.00
pcs 24 60.00 1,440.00
kg, 21 120.00 2,520.00
bag 16 260.00 4,160.00
box 22 250.00 5,500.00
62,580.00
days 5,000.00
days 12,000.00
days 3,000.00
20,000.00
62,580.00
-
20,000.00
ESTIMATED DIRECT COST 82,580.00
TOTAL 82,580.00
UNIT COST 562.92
TOTAL ITEM COST 82,580.00
days 10,500.00
days 25,200.00
days 25,200.00
60,900.00
248,750.00
60,900.00
ESTIMATED DIRECT COST 309,650.00
TOTAL 309,650.00
UNIT COST 580.68
TOTAL ITEM COST 309,650.00
TITLE: PROPOSED TWO (2) STOREY MIX USE BUILDING
OWNER: MR. ROMEL D. CIANO
LOCATION: MA. CLARA, DIFFUN, QUIRINO
UNIT
ITEM & DESCRIPTION SUBTOTAL LABOR COST@ TOTAL COST
QTY UNIT COST 35%
DIRECT COST
BUILDING & MAT COST 2,205,643.46
LABOR COST 529,354.43
GRAND TOTAL 2,734,997.89
I.Direct Cost
a. Labor Cost
Total Cost
Unit Cost
TOTAL COST
= P 62.50
= P 306.25
P 368.75
368.75
368.75
25.81
59.18
45.37
130.37
499.12
51.35
C. Gravel Bedding
Material
Gravel = 12.2 x P 560
Equipment
Dump Truc = 1 P 1,183.0 x 1
I.Direct Cost
a. Total Material Cost
b. Labor Cost(35%)
c. Equipment
Total Cost
Unit Cost
TOTAL COST
= P 6,809.60
= P 65.65
= P 287.34
P 352.99
= P 1,183.00
P 1,183.00
6,809.60
352.99
1,183.00
7,162.59
476.67
1,323.34
1,014.56
2,814.57
9,977.16
820.49
III. CONCRETE WORKS
1. FOOTING
Vol.1 = (1.5x1.5x0.35)x6 +Vol.2 =
(1.2x1.2x0.30)x11 5.16 cu.m
2. COLUMN
Vol. = (0.25*0.40*8*17)+(0.20*0.20*1) 8.54 cu.m
3. TIE BEAM
Vol. = 0.2mx0.30mX73m = 4.38 cu.m
4. FRAMING BEAM
Vol. = 0.2mx0.30mX73m = 4.38 cu.m
4. ROOF BEAM
Vol. = 0.2mx0.30mX73m = 4.38 cu.m
I.Direct Cost
a. Total Material Cost 178,218.30
b. Labor Cost(35%) 62376.405
240,594.71
II. Indirect Cost
a.Contingency (7%) 12475.281
b. Net Profit (15%) 37960.4979
c. 10% VAT 29,103.05
79,538.83
A=62.94*2+81.72*2=289.32-
277.75 sq.m.
11.57=277.75*2=555.50
I.Direct Cost
a. Total Material Cost 70,962.28
b. Labor Cost(35%) 24,836.80
95,799.07
II. Indirect Cost
a.Contingency (7%) 4,967.36
b. Net Profit (15%) 15,114.96
c. 10% VAT 11,588.14
31,670.46
L.S. = 95.6
I.Direct Cost
a. Total Material Cost 67,620.00
b. Labor Cost(35%) 23,667.00
91,287.00
II. Indirect Cost
a.Contingency (7%) 4,733.40
b. Net Profit (15%) 14,403.06
c. 10% VAT 11,042.35
30,178.81
I.Direct Cost
a. Total Material Cost 37,440.00
b. Labor Cost(35%) 13,104.00
50,544.00
II. Indirect Cost
a.Contingency (7%) 2,620.80
b. Net Profit (15%) 7,974.72
c. 10% VAT 6,113.95
16,709.47
Total Cost 67,253.47
Unit Cost 425.01
VII.ROOFING WORKS
I.Direct Cost
a. Total Material Cost 220,800.00
b. Labor Cost(35%) 77,280.00
298,080.00
II. Indirect Cost
a.Contingency (7%) 15,456.00
b. Net Profit (15%) 47,030.40
c. 10% VAT 36,056.64
98,543.04
A.PANEL DOOR
Wooden Panel Door = 4 sets 8,000.00 /set 32,000.00
(2.1x0.9m)
I.Direct Cost
a. Total Material Cost 32,000.00
b. Labor Cost(35%) 11,200.00
43,200.00
II. Indirect Cost
a.Contingency (7%) 2,240.00
b. Net Profit (15%) 6,816.00
c. 10% VAT 5,225.60
14,281.60
A. Materials
Flat Latex White
Flat Latex (cream)
Sanding Paper #120
Sanding Paper #220
Paint Roler w/ pan
Paint Brush #4
Paint Brush #2
` B. Labor
1 Const. Foreman @ 500.00 /day x 18
2 Painter @ 400.00 /day x 18
2 Helpers @ 300.00 /day x 18
Qtty= 708.89 sq.m.
days 9,000.00
days 14,400.00
days 10,800.00
34,200.00