Professional Documents
Culture Documents
FOR
Construction of 220/132kV, 2X160 MVA; 132/33kV, 2X50 MVA GIS at
location (Khumtai) and its associated lines and bay extension
(Package D)
(Design, Engineering, Manufacture, Assembly, Inspection, Testing at Manufacturer’s Works
before Dispatch, Packing, Supply, Delivery at Site, Including Insurance During Transit,
Subsequent Storage, Erection and Commissioning of GIS, Power Transformers with Associated
Switchgears, including Supply & Erection of Substation Steel Structures, Construction of Control
Room Building, Erection And Commissioning of new associated Transmission Lines and all other
Civil Works on Turnkey Basis)
4 PROJECT IMPLEMENTATION
4.12. SPARES
4.12.1 GENERAL
Page 2 of 954
CHAPTER 2: DRAWINGS AND DOCUMENTS
4.13. TRAINING
5.1. GENERAL
Page 3 of 954
CHAPTER 2: DRAWINGS AND DOCUMENTS
5.19. INTERFACING
6.2. LOUVERS
7. 3.1 GENERAL
7.3.7 SUB-CONTRACTORS
7. 4.1 GENERAL
Page 4 of 954
CHAPTER 2: DRAWINGS AND DOCUMENTS
7.6. STANDARDS
7.10. GALVANISING
7.13.5 PADLOCKS
7.13.6 EARTHING
7.13.7 LUBRICATION
7.14.1 CASTINGS
7.14.2 FORGINGS
Page 5 of 954
CHAPTER 2: DRAWINGS AND DOCUMENTS
7.19.1 GENERAL
7.19.7 SECURITY
8.1.1 SCOPE
8.1.3 GENERAL
Page 6 of 954
CHAPTER 2: DRAWINGS AND DOCUMENTS
8.3. SWITCHYARD
Page 7 of 954
CHAPTER 2: DRAWINGS AND DOCUMENTS
Page 8 of 954
CHAPTER 2: DRAWINGS AND DOCUMENTS
ATTACHED A
41 GENERIC ESMP REPORT
ANNEXURE- B
Page 9 of 954
CHAPTER 1: STANDARDS & ABBREVIATIONS
CIRCUIT BREAKERS
IEC-62271-100 - High Voltage Alternating Current Circuit
Breakers
CHAPTER 1: STANDARDS & ABBREVIATIONS
SURGE ARRESTERS
IS-3070(PART2) - Lightning arresters for alternating current
systems Metal oxide lightning arrestors without
gaps.
IEC-60099-4 - Metal oxide surge arrestors without gaps
IEC-60099-5 - Selection and application recommendation
ANSI-C62.1 - IEE Standards for S A for AC Power Circuits
NEMA-LA 1 - Surge Arresters
CUBICLESAND PANELS & OTHER RELATED EQUIPMENTS
IS-722, IS-1248, - Electrical relays for power system protection
CHAPTER 1: STANDARDS & ABBREVIATIONS
Overhead Conductors
Bus hardware and insulators
IS: 2121 - Fittings for Aluminum and steel cored Al
conductors for overhead power lines.
IS-731 - Porcelain insulators for overhead power lines
with a nominal voltage greater than 1000 V.
IS-2486(P1 to P4) - Insulator fittings for overhead power lines with
a nominal voltage greater than 1000V
IEC-60120 - Dimensions of Ball and Socket Couplings of
string insulator units.
IEC-60137 - Insulated bushings for alternating voltages
above 1000V.
IEC-60168 - Tests on indoor and outdoor post insulators of
ceramic material or glass for Systems with
Nominal Voltages Greater than 1000V.
IEC-60233 - Tests on Hollow Insulators for use in electrical
equipment.
IEC-60273 - Characteristics of indoor and outdoor post
insulators for systems with nominal voltages
greater than 1000V.
IEC-60305 - Insulators for overhead lines with nominal
voltage above 1000V-ceramic or glass insulator
units for ac systems Characteristics of String
Insulator Units of the cap and pin type.
IEC-60372(1984) - Locking devices for ball and socket couplings
of string insulator units: dimensions and tests.
IEC-60383(P1 and P2) - Insulators for overhead lines with nominal
voltage above 1000V.
IEC-60433 - Characteristics of string insulator units of the
long rod type.
IEC-60471 - Dimensions of Clevis and tongue couplings of
string insulator units.
ANSI-C29 - Wet process porcelain insulators
ANSI-C29.1 - Test methods for electrical power insulators
ANSI-C92.2 - For insulators, wet-process porcelain and
toughened glass
suspension type
CHAPTER 1: STANDARDS & ABBREVIATIONS
Painting
IS-6005 - Code of practice for phosphating of iron and
steel.
ANSI-Z551 - Gray finishes for industrial apparatus and
Equipment
SSPEC - Steel structure painting council
Fire protection system
Fire protection manual issued by tariff advisory committee (TAC), NFPA and
National Building code 2016 of India
HORIZONTAL CENTRIFUGAL PUMPS
IS: 6595(Part2) - Horizontal centrifugal pumps for clear, cold
water
IS: 9137 - Code for acceptance test for centrifugal & axial
pumps
CHAPTER 1: STANDARDS & ABBREVIATIONS
IS: 1538 - Cast iron fittings for pressure pipes for water,
gas and sewage
IS: 1903 - Ball valve (horizontal plunger type) including
floats for water supply purposes
IS: 2062 - SP for weldable structural steel
IS: 2379 - Color Code for the identification of pipelines
IS: 2643 - Dimensions of pipe threads for fastening
purposes
IS: 2685 - Code of Practice for selection, installation and
Maintenance of sluice valves
IS: 2906 - Sluice valves for water-works purposes (350 to
1200mm size)
IS: 3582 - Basket strainers for firefighting purposes
(Cylindrical type)
IS: 3589 - Electrically welded steel pipes for water, gas
and sewage (150 to2000 mm nominal diameter)
IS: 4038 - Foot valves for water works purposes
IS: 4927 - Unlined flax canvas hose for fire fighting
IS: 5290 - Landing valves (internal hydrant)
IS: 5312 - Swing check type reflex (non-return) valves
(Part-I)
IS: 5306 - Code of practice for fire extinguishing
installations and equipment on premises
Part-I - Hydrant systems, hose reels and foam inlets
Part-II - Sprinkler systems
BS: 5150 - Specification for cast iron gate valves
MOTORS & ANNUNCIATION PANELS
IS: 325 - Three phase induction motors
IS: 900 - Code of practice for installation and
maintenance of induction motors
IS: 996 - Single phase small AC and universal electric
motors
IS: 1231 - Dimensions of three phase foot mounted
induction motors
IS: 2148 - Flame proof enclosure of electrical apparatus
IS: 2223 - Dimensions of flange mounted AC induction
motors
CHAPTER 1: STANDARDS & ABBREVIATIONS
general construction.
ASTM-A234 - Pipe fittings of wrought carbon steel and alloy
steel for moderate and elevated temperatures
ASTM-S181 - Specification for forgings, carbon steel for
general purpose piping
ASTM-A105 - Forgings, carbon steel for piping components
ASTM-A307 - Carbon steel externally treated standard
fasteners
ASTM-A193 - Alloy steel and stainless steel bolting materials
for high temperature service
ASTM-A345 - Flat rolled electrical steel for magnetic
applications
ASTM-A197 - Cupola malleable iron
ANSI-B2.1 - Pipe threads (Except dry seal)
ANSI-B16.1 - Cast iron pipe flanges and glanged fitting.
Class 25,125, 250 and 800
ANSI-B16.1 - Malleable iron threaded fittings, class 150 and
300
ANSI-B16.5 - Pipe flanges and flanged fittings, steel nickel
alloy and other special alloys
ANSI-B16.9 - Factory-made wrought steel butt welding
Fittings
ANSI-B16.11 - Forged steel fittings, socket-welding and
threaded
ANSI-B16.14 - Ferrous pipe plug, bushings and locknuts with
piple threads
ANSI-B16.25 - Butt welding ends
ANSI-B18.1.1 - Fire hose couplings screw thread.
ANSI-B18.2.1 - Inch series square and hexagonal bolts and
screws
ANSI-B18.2.2 - Square and hexagonal nuts
NSI-B18.21.1 - Lock washers
ANSI-B18.21.2 - Plain washers
ANSI-B31.1 - Power piping
ANSI-B36.10 - Welded and seamless wrought steel pipe
ANSI-B36.9 - Stainless steel pipe
Other civil works standards
CHAPTER 1: STANDARDS & ABBREVIATIONS
IS-3025 (Part 1 to Part 48) - Methods of sampling and test (Physical and
chemical) for water and waste water.
IS-4091 - Code of practice for design and construction of
foundations for
transmission line towers and poles.
IS-4111 (Part1 to P5) - Code of practice for ancillary structures in
sewerage system.
IS-4990 - Plywood for concrete shuttering work.
IS-5600 - Sewage and drainage pumps.
National building code of India 2016
USBRE12 - Earth Manual by United States Department of
the interior Bureau of Reclamation
ASTM-A392-81 - Zinc/Coated steel chain link fence fabric
ASTM-D1557-80 - test for moisture-density relation of soils using
10- lb (4.5 kg) rame land18-in. (457 mm) Drop.
ASTM-D1586 - Penetration Test and Split-Barrel
(1967) - Sampling of Soils
ASTM-D2049-69 - Test Method for Relative Density of
Cohesionless Soil
ASTM-D2435 - Test method for Unconsolidated,
(1982) Undrained Strengths of Cohesive Soils in
Triaxial Compression.
BS-5075 - Specification for accelerating Part I
Admixtures, Retarding Admixtures and Water
Reducing Admixtures.
CPWD - Latest CPWD specifications
ACSR MOOSE CONDUCTOR
IS:6745 Methods for Determination of
BS:443-1969 Mass of zinc coating on zinc
IS:8263 Coated Iron and Steel Articles
Methods for Radio Interference
IEC: 437-1973 Test on High Voltage Insulators
NEMA: 107-1964 CISPR
IS: 209 Zinc Ingots BS: 3436-1961
IS: 398 Aluminum Conductors for Overhead
Transmission Purposes
IEC: 209-1966
CHAPTER 1: STANDARDS & ABBREVIATIONS
Part-V
BS: 215(Part-II) Aluminum Conductors galvanized
IEC: 209-1966 Steel reinforced extra high Voltage (400 kV
and above)
IS: 1778 Reels and Drums for
BS: 1559-1949 Bare Conductors
IS: 1521 Method for Tensile Testing ISO/R89-1959of
steel wire
IS: 2629 Recommended practice for Hot dip
Galvanizing on Iron and Steel.
IS: 2633 Method for Testing Uniformity of coating of
zinc Coated Articles.
IS: 4826 Hot dip galvanised coatings On round steel
wires
ASTMA-472- 729
GALVANISED STEEL EARTHWIRE
IS: 1521 Method for Tensile Testing
ISO/R:89-1959 of Steel Wire
IS: 1778 Reels and Drums for Bare Conductors
IS: 2629 Recommended practice for Hot Dip
Galvanizing on Iron and Steel.
IS: 2633 Methods for testing Uniformity of Coating of
Zinc Coated Articles.
IS: 4826 Hot dip Galvanised Coatings ASTM:A 475-
72aon Round
Steel Wires
BS: 443-1969
IS: 6745 Method for Determination BS: 443-1969 of
mass of Zinc Coating on Zinc coated Iron and
Steel Articles.
IS: 209 Zinc ingot BS: 3463-1961
IS: 398(Pt. I to Aluminum Conductors for
BS: 215 (Part-II) P5:1992) overhead transmission purposes.
Lighting Fixtures and Accessories
IS: 1913 General and safety requirements for electric
lighting fittings.
IS: 3528 Waterproof electric lighting fittings.
CHAPTER 1: STANDARDS & ABBREVIATIONS
LT SWITCHGEAR
IS: 8623(Part-I) Specification for low voltage switchgear and
control gear assemblies
IS: 13947(Part-I) Specification for low voltage switchgear and
control gear,
Part 1 General Rules
Part 2 circuit breakers.
Part3 Switches, Disconnectors, and fuse combination
units
Part4 Contactors and motors starters.
Part5 Control-circuit devices and switching elements
Part6 Multiple function switching devices.
Part7 Ancillary equipment
IS: 12063 Degree of protection provided by enclosures
IS: 2705 Current Transformers
IS: 3156 Voltage Transformers
IS: 3231 Electrical relays for power system protection
IS: 1248 Electrical indicating instruments
IS: 722 AC Electricity meters
IS: 5578 Guide for marking of insulated conductors of
apparatus terminals
IS: 13703(part1) Low voltage fuses for voltage not exceeding
1000V AC or 1500VDC
Part1 General Requirements
Part 2 Fuses for use of authorized persons
IS: 6005 Code of practice of phosphating iron and steel
IS: 5082 Wrought Aluminum and Aluminum alloys for
electrical purposes
IS: 2633 Hot dip galvanizing.
TRANSMISSION LINES
The relevant site information relating to these projects and information that
would be required to implement these projects has been obtained and
presented in the “Volume III – BID PURPOSE DRAWINGS, SCHEDULE
OF QUANTITIES AND MISCELLANEOUS DOCUMENTS”. The
important aspects have been detailed out in the DPR along with the relevant
drawings. Bidders can use this information as a basic guide and verify the site
condition physically by visiting the site before bidding.
Location Khumtai
Outdoor temperature 35° C
Maximum outdoor temperature 40° C
Maximum Oil Temperature 60° C
Maximum relative Humidity 86%
Minimum relative Humidity 65%
All the equipment and items offered shall be of any one of the approved makes:
The equipment shall generally be for use in moderately hot and humid
tropical climate conducive to rust and fungus growth unless otherwise
specified.
2.6.12 The present scope of Design, supply, erection and commissioning work
and space for future expansion for 220/132/33kV Khumtai GIS is briefly
detailed as below:
1) SUBSTATION WORK (all electrical and civil works)
to the affected party directly without creating any liability on the part
of AEGCL.
2.7.11AEGCL shall not be responsible for arranging access roads/RoW for
transport of material from roadside to worksites. If the contractor has
to adopt any such arrangements, he may do so with the consent of the
property owners and any compensation in that respect shall be his
responsibility against which no reimbursement shall be made by
AEGCL. The contractor shall take all necessary precautions to cause
no/minimum damage while executing work.
2.7.12Clearing of obstruction falling in the right-of-way to maintain
standards asperIS:5613(Part-3, Section-2),1985 and lopping and
trimming of trees and other overgrowths during check survey or work
execution shall be under contractor’s scope. Arrangement of required
documents, obtaining Govt. department permissions and submission of
necessary fees shall be done by the contractor. AEGCL shall assist in
the official procedures wherever deemed necessary and any statutory
fees incurred by the contractor in obtaining statutory
clearances/permissions at this stage by the contractor shall be
reimbursed in due course of time on submission of valid documentary
evidence.
2.7.13The Acquisition of land for Sub- Stations shall be the sole
responsibility of AEGCL. Whereas the Contractor shall be responsible
for securing the RoW for transmission line works, AEGCL shall assist
the Contractor for getting clearances from Railway, NHAI, Forest,
Water, and other Govt./Statutory bodies. All statutory fees for getting
clearance shall be to AEGCL's account.
2.7.14For settlement of ROW for private lands (including private water
bodies), the clearances shall be extracted by the contractor based on
the RoW notified by the Government. The land compensation amount
shall be settled by the contractor through district revenue officials
based on relevant provision of the GOA guidelines and as per the
mechanism followed by district administration for assessment/fixation
of land compensation. However, the compensation amount will be
paid by AEGCL directly to the landowners on submission of Original
award statement by the contractor to AEGCL against such land, duly
assessed and signed by the concerned officials of District Revenue
Administration. The acknowledgement for receipt of the amount by
the landowner shall be through Non-Judicial stamp paper.
2.7.15For zirat compensation on account of crop damage, plantation damage,
tree cutting etc the assessment shall be done jointly by the contractor
and AEGCL officials in coordination with the district/revenue
officials. Based on this assessment, the zirat payable to the
beneficiaries shall be fixed and the same shall be paid to the
beneficiaries by the contractor through district administration. The
contractor shall then submit the Zirat bills duly endorsed by the
concerned revenue official to AEGCL for reimbursement. The
reimbursement of the compensation shall be made by the AEGCL
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
Note:
The above table describe the technical parameter of various equiments. The contractor shall use
1 this as refernce only.
Any technical parameter mentioned in the literature of each equipments shall deemed to be
2 included.
S. N Drawings
1.0 Single Line Diagram of Complete Electrical System based on the design criteria.
a. Substation layout/plot plan in section and plan indicating EGL, Proposed FGLand top of
plinth/foundation level.
2.0 Cable Sealing Ends for cables above 33kV cables
a. Complete assembly drawing showing plan, elevation and sectional views of CSE
showing the internal construction and incorporating mounting dimensions, overall
dimensions, material of construction, cables joints, SVL, weight, electrical clearances
for installation, details of terminal connections etc.
b. Calculations and General arrangement drawing of the foundations of structure mountings
and structure.
3.0 Lightning Arrestor (33kV and above)
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
a. Complete assembly drawing showing plan, elevation and sectional views of arrester
showing the internal construction and incorporating mounting dimensions, overall
dimensions, material of construction, weight, electrical clearances for installation, details
of terminal studs etc.
b. Ratings and description of special features, if any.
c. Power frequency voltage vs. time characteristic of the arrester.
d. Drawings for Surge counter, grading ring, porcelain bushing, terminal clamp, pressure
release arrangement and rating plate.
e. Guaranteed Technical particulars, type test certificates
f. Calculations and General Arrangement drawing of the foundations of structure
mountings and structure.
4.0 BPI (33kV and above)
a. Complete assembly drawing showing plan, elevation and sectional views of Insulator
incorporating mounting dimensions, overall dimensions, material of construction,
weight, details of terminal studs etc.
b. Guaranteed Technical particulars, type test certificates
c. Calculations and General arrangement drawing of the foundations of structure
mountings and structure.
5.0 Clamps and Connectors (33kV and above)
a. Detailed dimensioned drawings for Clamps & Connectors giving weight, rating, bill of
material including bolts, nuts, washers, etc.
6.0 Earthing details of Substations and Transmission lines including calculations and
layout drawings.
a. Complete DSLP calculation with related drawings.
7.0 Civil Details for switchyard including fencing, officers’ hostels, staff hostel, secutity
barrack, transit camp, RE residence, Store Building, 33kV control room building ,
security gate and all other related civil works.
8.0 Substation HVAC System
Providing Ventilation system of the Exhaust air fans for Ground Floor 400/220/132 KV
a. GIS Room & 33 kV Switch Gear Room, cable trench, Battery Room, Store Room,
Kitchen / Pantry, Lockers & Toilet.
Providing Air Conditioning system for the Conference Room, Admin Room-1, Admin
b. Room-2, Admin Room-3, Battery Room, Digital PLCC Room, SCADA & CRP Room,
Office Room-1 and Office Room-2.
c Providing location for Fresh and Exhaust air Louvers wherever necessary.
9.0 Electrical Substation GA and sectional Layouts of 400/220/132kV GIS showing
locations of various Equipment including, Transformer, cable trenches, Switchgear
Panel, control & relay panels and other allied equipments and associated systems as
listed above.
10.0 GIS (132kV and above)
a. General Arrangement and sectional drawings of overall layout of GIS, terminal
arrangement, bay cross section of individual bays, LCP, PD monitoring system including
all dimensional details, layout and maintenance requirements, details of supports
required for piping and other accessories, cable entry details, Grounding requirements,
etc
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
b. Foundation drawings for all equipment/accessories indicating the grouting details, static
and dynamic loading data and any insert details for supporting structures and other
equipment
c. Gas Section diagram, Guaranteed Technical Particulars.
d. Schematic wiring diagrams & Block interlock diagrams indicating the control and
interlock logic for all equipment/accessories
e. Bill of materials listing equipment designation, make, type, rating, etc. of the various
equipment mounted on the equipment.
f. Type test certificates not older than ten years and submit certificates before award of
contract (if already not submitted).
g. All Routine tests shall be conducted on each equipment.
h. Descriptive and illustrative literature for the equipment
11.0 Relay & Control Panel (33kV and above)
a) Control and relay panel drawing showing plan, front elevation, foundation details, floor
openings, terminal block location, etc.
b) Schematic wiring diagrams
c) Bill of materials listing equipment designation, make, type, rating, etc. of the various
equipment mounted on the panels.
d) Interconnection and external connection wiring drawings - The drawings shall include all
panel to panel interconnections and panel to field external connections to facilitate
external cable connections.
e) Type test certificates & Routine test certificates not older than five years and submit
certificates before award of contract.
f) All Routine tests shall be conducted on each equipment.
g) Descriptive and illustrative literature for the Relays, Instruments, Meters, Annunciators,
Control Switches, etc.
12.0 General arrangement for MRS (Main receiving substation)
a) G A drawing for 33kV & above substation showing GIS, battery/battery charger and
DCDB, PCC, ACDB, 400/220kV, 220/33kV, 220/132kV, 132/33kV Power transformer,
station transformer and cabling, earthing, lighting and lightning protection layouts.
13.0 Bill of quantities for GIS Substation (33kV and above)
14.0 Transformers (33kV above)
a. General arrangement drawing shall indicate the overall dimensions, net weights, quantity
of oil, crane requirements for assembly and dismantling of transformers, and the general
constructional features.
b. General arrangement drawing of the transformer showing plan, front elevation and side
elevation complete with all accessories and fittings, detailed dimensions, cable entries,
earthing terminals, foundation/floor fixing details, jacking pads, crane lift for un tanking,
size of lifting lugs and eyes, clearances between HV terminals, between LV terminals,
between HV and LV terminals, between HV & LV terminals and ground and bill of
materials etc.
c. Valve schedule, Rating, diagram and terminal marking plates, complete with polarity
and vector group.
d. OLTC cabinets: schematic circuit diagram and actual detailed wiring diagram giving
terminal numbers.
e. Bushings Plan, elevation, terminal details, mounting details, make and type number,
current and voltage rating, creepage distances and principal characteristics.
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
e. Type test certificates not older than last five years and submit certificates before award
of contract.
17.0 Battery & Battery charger with DC Distribution Board
a. Dimensioned general arrangement drawings
b. Fully dimensioned general arrangement drawings of battery and battery charger with
elevation, side view, sectional view and foundation details
c. Complete schematic and wiring diagrams
18.0 Cabling system
a. Details of Installation of Cables in Trenches/Tunnels, on cable trays, racks directly
buried etc., at all locations as specified including cable trays.
b. 220 kV, 132kV, 33kV & 1.1kV Cable routing layout inside and outside the Switchyard.
c. Bill of quantities of LT cables, lugs and glands & HT Termination Kits.
d. All Cable termination and mounting Kit Layout drawing.
e. Cable Termination arrangement drawing (33kV & above).
19.0 Earthing & Lightning Protection system
a. Detail calculations of earthing network including step & touch
calculations, main grid calculations.
b. Earthing notes including detail write up and drawings of earthing conductor layout,
equipment & structural earthing, joints, cable earthing, instrument earthing and special
earthing.
c. Details such as material, sizes, etc. of the earth conductor and electrode pits
d. Earthing layout drawing showing routing of main grid inside and outside of Building
with interconnection of equipment earthing to the grid and earth pits
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
b. Conduit layout showing room wise routing of wires from lighting panel to lighting
fixtures, receptacles etc.
c. Internal road Lighting and Area lighting layout with type of mounting details and fixture
details.
21.0 SCADA
a. SCADA Architecture drawings with details
26.0 Drawings for Fire fighting, HVAC, Plumbing, SCADA System and Fire alarm system
27.0 Drawing for pump house (colony & HVWS), water tank, parking shed, Gate, Boundary
wall, Lighting Mast, Fire protection wall for Power Transformers
28.0 Drawings for switchyard cable trenches and Control room cable trenches.
29.0 Layout for switchyard PCC and gravelling.
30.0 Drawing for contour plan and marking the existing HFL with earth filling required at the
substation location.
B) Calculations
All related Power Transformer design calculation details as described in respective
specification.
a. Auxiliary Transformer Sizing Calculations
b. Fault level Calculations
c. Co-ordinated protection study with latest available version of PSSE software.
d. HT & LT cable sizing
e. UPS & Battery Sizing Calculations
f. Switchyard Lightning Protection and Earthing Sizing Calculations
g. Room wise Lighting Calculation as per Lux level given in IS 3646 Part-I.
h. Calculations related to Fire fighting, HVAC, Plumbing, SCADA System and Fire alarm
system
C) Schedules
a. Cable Schedule
b. Protection Relay Setting Schedule
c. Interconnection schedule
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
Note:
1. All other documents listed in the particular specification of each
equipment, but not listed above shall also be submitted.
2. All equipment/ system sizing calculations/ drawings shall be submitted
to the employer for approval whether specifically mentioned or not.
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
GENERAL CONDITIONS
4.1 Responsibility of the Contractor
The Contractor shall also be responsible for the complete design and
engineering of substation and transmission lines, overall co-ordination with
internal and external agencies, project management, training of Employer’s
manpower, loading, unloading, storage at site, inventory management at site
during construction, dismantling, re-erection of installations as per AEGCL
advice, soil testing, handling, moving to final destination, obtaining statutory
authority’s clearance for successful erection, and testing and commissioning of
the substation as per the CHAPTER 2 OF “Volume III – BID PURPOSE
DRAWINGS, SCHEDULE OF QUANTITIES AND MISCELLANEOUS
DOCUMENTS”
The Contractor shall construct the works in compliance with the outline
programme appended to the Bidding Document, and shall submit for the
approval of AEGCL, a detailed programme in accordance with the requirements
of this Specification.
Programme:
1) All activities from the start Date up to commissioning shall be included.
Separate Programme shall be furnished for each of the activities.
2) Earliest and latest occurrence of each activity.
3) Constraints, if any.
The activities for each of the items shall essentially cover time-table for
activities such as placement of order with sub-vendors, Empowering,
submission of drawing, review and approval by the Employer, manufacture,
inspection, delivery, erection and commissioning. All events shall be
represented in a proper in proper sequence of occurrence with due consideration
for inter-dependent activities and all period shall be counted from the start date.
Contractor to follow the ESIA report as per CHAPTER 3 OF “Volume III –
BID PURPOSE DRAWINGS, SCHEDULE OF QUANTITIES AND
MISCELLANEOUS DOCUMENTS”
4.2 Specific exclusions:
The following items of work are specifically excluded from the Contractors
scope of work unless otherwise specifically brought out.
a) Substation site selection
b) Land acquisition for substation
4.3 Interfacial point for line termination at substation
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
The Contractor shall terminate the transmission line along with insulator
hardware and other essential fittings at the substation gantry. The Contractor
shall provide necessary anchoring plates etc.
4.4 Limit of Contract
Whether called for specifically or not, all accessories and work required for the
completion of the work are deemed to be considered as a part of the Bidder’s
scope, unless and until mentioned very clearly as excluded. The scope of work
shall also include all work incidental for successful operation and
commissioning and handing over of works whether specifically mentioned or
not. In general works are to be carried out by the Contractor in accordance with
stipulations in Conditions of Contract.
4.5 Meteorological data
Appropriate meteorological data is given in the CHAPTER 2.
4.6 Soil data
The general characteristics of the soil are given in the CHAPTER 3 OF
“Volume III – BID PURPOSE DRAWINGS, SCHEDULE OF
QUANTITIES AND MISCELLANEOUS DOCUMENTS”. The information
furnished is for reference purpose only. The Contractor shall be required to
carry out soil investigation and related design based on his findings.The same
would prevail for designing of tower foundation of transmission lines also.
4.7 Completeness and accuracy of information
The Contractor shall note that the information provided above and in the
relevant schedules may not be complete or fully accurate at the time of bidding.
For his own interest the Contractor is advised to make site visits and fully
satisfy himself regarding site conditions in all respects and shall be fully
responsible for the complete design and engineering of the substations.
4.8 Drawings attached with Tender Document
The various drawings and schedules provided are a part of the specification and
for information purposes only. These are not necessarily binding on the part of
the Contractor. However, the Bidders shall inspect the site and prepare the
topographic map with proper contour lines. The layout shall be drawn on the
basis of this topographic map. The layout of the substation shall then be
superimposed on the prepared topographic map and the same shall be submitted
to AEGCL for approval. The Drawing provided are enclosed in CHAPTER 1
OF “Volume III – BID PURPOSE DRAWINGS, SCHEDULE OF
QUANTITIES AND MISCELLANEOUS DOCUMENTS”
4.9 Guaranteed Technical Particulars
The Contract Works shall comply with the guaranteed technical particulars
specified or quoted in the bid. All plant and apparatus supplied under this
Contract shall be to the approval of AEGCL.
All plant and equipment supplied under this contract must have been type tested
(as per IEC standard) as specified in the respective specification as on date of
bid opening. And have been in manufacture and satisfactory service at Same or
Higher rated equipments ratings for at least five years for Power Transformers
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
and 7 years for GIS equipments. The bidder shall furnish in his bid the
necessary supporting data in specified formats for consideration during bid
evaluation. If during evaluation noncompliance is identified the successful
Contractor shall be bound to supply the equipment from manufacturers
complying with the stipulated requirements / AEGCL approval renders.
The Contractor shall be responsible for any discrepancies, errors or omissions in
the particulars and guarantees.
The Bidder for his own interest, shall establish the technical responsiveness of
his bid, shall provide all data in appropriate technical data sheets, general/
technical information, literature, and pamphlets etc. along with the bid.
4.10 Compliance with Specification
All apparatus should comply with this Specification. Any departures from the
requirements of this Specification shall be stated in the relevant Bid Proposal
Schedules and will be considered during Bid evaluation. Unless brought out
clearly in the technical schedules, it will be presumed that the equipment is
deemed to comply with the technical specification. In the event of there being
any inconsistency between the provisions of the conditions of contract and the
provisions of this Specification in respect of commercial requirements, the
provisions of the conditions of contract shall take precedence for commercial
matters and the provisions of this Specification shall take precedence in respect
of technical matters. In case of inconsistency between technical specification &
bid proposal sheet, quantities of various items as specified in the bid proposal
sheet shall be considered for quoting however the work shall be executed as
specified in the technical specification. Only brief description is given in the
BPS & the work shall be executed in line with the requirement given in the
technical specification. The manufacturer and places of manufacture, testing and
inspection of the various portions of the Contract Works shall be stated in the
relevant Bid Proposal Schedules.
4.11 Test and Maintenance Equipment
The Contractor shall supply the type and quantity of test and maintenance
equipment specified in the Schedules as part of the contract works.
4.12 Spares
4.12.1 General
The Contractor shall provide the mandatory spares detailed in the Schedules.
Provide a list of recommended spare parts (optional spares) together with their
individual prices, which will be considered forfor evaluation. The Employer
may order all or any of the Optional spare parts listed at the time of contract
award.
Mandatory spares shall be supplied as part of the Works under this
specification. Additional spares (Mandatory) may be ordered at any time during
the contract at the rates stated in the Price Schedule.
4.12.2 Mandatory spares
The Employer has indicated the requirement of mandatory spares in
CHAPTER 2 OF “Volume III – BID PURPOSE DRAWINGS, SCHEDULE
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
The contractor shall impart one-month field training & fifteen days factory
training on GIS equipment for operation and maintenance of GIS substation.
The bidder (in case of not a GIS manufacturer) shall obtain undertaking in the
letter head of the GIS manufacturer from GIS manufacturer in this regard and
shall enclose the same in the bid.
4.13.1. Hardware maintenance
Courses for hardware maintenance shall identify techniques for preventative
physical maintenance and for identification, isolation and replacement of faulty
components. This course shall take place before equipment is delivered to site.
An essential part of the hardware maintenance course shall include highlighting
the philosophy of computer based preventive maintenance and identification of
the various diagnostic/interrogation facilities available. The Contractor shall
supply adequate documented instructions to enable a detailed interrogation and
analysis process to be carried out using the diagnostic software facilities. All
items of hardware to be supplied shall be covered by the course.
4.13.2 Operator familiarisation
This course is intended to familiarise the operators with the system and its use in
substation operation and maintenance inclusive of associated communication
network. The course shall ensure that the control room staff are completely
familiar with all operational and maintenance aspects of the equipment. The
means of obtaining special data, report logs and all other facilities which would
enable the operators to be fully conversant with the system, shall also be
incorporated.
It is envisaged that it will be necessary for the Contractor to run operator
familiarisation courses each of approximately one week in duration at site for
the training of the Employer's staff.
4.13.3 Software management
This course shall comprise two main areas and shall take place at the
Contractor's works before equipment is delivered to site.
I). A formal course on the software detailing the various modules used and
their interaction. The course shall broadly cover the following topics
i. SAS software
ii. Relays software.
iii. Communication software
II). Hand-on-training on editing the database (to incorporate extensions to
the power networks, inclusion of additional analogue/digital signals from
existing equipment, etc.) and generating new logs, alphanumeric displays,
etc.
It is envisaged that the software management courses shall extend for a period
of approximately six weeks.
4.13.4 Installation and commissioning techniques
CHAPTER 2: INFORMATION TO BIDDERS (ITB)
provide suitable office accommodation at each substation site for the sole use by
AEGCL.
4.15 Site Construction Supplies
The Contractor shall provide at his own cost and expense, any site supplies of
electrical energy, water and any other requirements which he may require for
site operation.
All wiring and pipeing etc. for such tackle and for lighting from the point of
supply shall be provided by the Contractor and all such installations shall
comply with all appropriate statutory regulations to which the Employer is
subject.
Wiring shall be of the best quality double insulated flexible cable, suitably
fixed, protected and maintained. All necessary precautions shall be taken to
ensure the safety of every person employed or working on the Site and this shall
include routine inspection of all temporary installations and portable equipment.
The authorized representative of AEGCL may require the disconnection or
alteration of any parts which he may consider unsafe.
As soon as any part or the whole of the Contractor’s installation is no longer
required for the carrying out of the works, the Contractor shall disconnect and
remove the same to the satisfaction of the authorised representative of AEGCL.
The contractor shall be responsible for arranging construction water at his own
cost.
Under no circumstances AEGCL shall arrange water for construction activities.
4.16 Supervision and Checking of Work on Site
All work on site included in the Contract scope of works shall be supervised by
a sufficient number of qualified representatives of the Contractor.
Before putting any plant or apparatus into operation the Contractor shall satisfy
himself as to the correctness of all connections between the plant and apparatus
supplied under this and other contracts. The Contractor shall advise the
authorized representative of AEGCL in writing, giving the period of notice as
specified in the General Conditions of Contract, when the plant or apparatus is
ready for inspection or energization.
4.17 Responsibility for the Running of Plant by Contractor
Until each Section of the Contract Works has been taken over or deemed to
have been taken over under the Conditions of Contract, the Contractor shall be
entirely responsible for the Contract Works, whether under construction, during
tests, or in use for the Employer’s service. The Contractor shall instruct the
Employer’s operating staff in the recommended method of operation of the
plant supplied. Such instruction shall commence prior to the commissioning of
the plant and shall be followed by practical instruction for a period of up to
three months for GIS after the plant is taken over by the Employer. During this
specified period the Contractor shall provide an engineer, on each site that is
taken over, to assist with operation of the plant and to provide on-site training of
the Employer’s operating staff. The training schedule and programme for each
substation shall be submitted to the authorised representative of AEGCL for
approval, three months prior to the substation’s planned completion date. In the
event of any emergency situation arising out of failure/outage of any parts of the
GIS, the contractor shall be obliged to provide service of their competent
personnel for rectification/repair of the problem within 100 (One hundred)
hours. The contactor shall be under the obligation of this stipulation for a
period of 5 (five) years with effect from date of submission of the extended
guarantee. Any work which may be necessary for the Contractor to carry out in
pursuance of his obligations under the Conditions of Contract shall be carried
out with the minimum of interference to the normal operation of the substation.
Work on the Site shall be carried out at such time and during such hours as
AEGCL may require.
4.18 Compliance with Regulations
All apparatus and material supplied, and all work carried out shall comply in all
respects with such of the requirements of all Regulations and Acts in force in
the country of the Employer as are applicable to the Contract Works and with
any other applicable regulations to which the Employer is subject.
The Contractor shall fully inform himself of the requirements of the local Laws,
Regulations and rules in-force in the State of Assam, especially with respect to
local employment laws, licensing requirements, electrical safety rules and
regulations, building regulations and planning procedures.
The Contractor shall be responsible for applying for all necessary licenses;
including Electrical Contractors License, Workman’s Permits and Certificates
of Competency for Supervisors, and local government approvals required for
the contract works and for the payment of all necessary fees associated with
such licenses and approvals.
Correspondence with the Electrical Inspector shall be conducted through the
Authorised representative of AEGCL, but the Contractor shall provide all
necessary information, regarding the contract works, as may be required by the
Electrical Inspector. Additionally, the Contractor shall also follow the minimum
regulations on safety, employee’s welfare, industry etc. as stipulated under the
relevant Clause of this section.
4.19 Maintenance and Clearing of Site
CHAPTER 4: PROJECT IMPLEMENTATION
The placing of materials and plant near the erection site prior to their being
erected and installed shall be done in a neat, tidy and safe manner. The
Contractor shall at his own expense keep the site area allocated to him and also
the erection area of the Contract Works reasonably clean and shall remove all
waste material as it accumulates and as directed by AEGCL from time to time.
4.20 Protection of Monuments and Reference Points
The Contractor shall ensure that any finds such as relics, antiques, coins, fossils,
etc. which he may come across during the course of performance of his works
either during excavation or elsewhere, are properly protected and handed over to
the Employer. Similarly, the Contractor shall ensure that the bench marks,
reference points, etc. which are marked either with the help of Employer or by
the Employer shall not be disturbed in any way during the performance of his
works. If any work is to be performed which disturbs such reference points, the
same shall be done only after these are transferred to other suitable locations
under the direction of the Employer. The Contractor shall provide all necessary
materials and assistance for such relocation of reference points etc.
4.21 Foreign Personnel
If necessary, for the execution of the works, the Contractor shall bring foreign
supervisors for the execution of the Contract at his own cost. The Contractor
shall submit to the Employer data on all personnel he proposes to bring into
India for the performance of the works under the Contract, at least Sixty (60)
days prior to their arrival in India. Such data shall include the name of each
person, his present address, his assignment and responsibility in connection with
the works, and a short resume of his qualifications and experience etc. in
relation to the work to be performed by him.
Any person unsuitable and unacceptable to the Employer, shall not be brought
to India. Any person brought to India and found unsuitable or unacceptable to
the Employer shall be immediately removed from Site and repatriated. If found
necessary, he may be replaced by other personnel acceptable to the Employer.
No person brought to India by the Contractor for the works shall be repatriated
without the consent of the Employer in writing, based on a written request from
the Supplier for such repatriation giving reasons for such an action to the
Employer. The Employer may give permission for such repatriation provided
the Employer is satisfied that the progress of work will not suffer due to such
repatriation. The cost of passports, visas and all other travel expenses to and
from India, shall be to the Contractor's account. The Employer will not provide
any residential accommodation and/or furniture for any of the Contractors
personnel including foreign personnel. Contractor shall make his own
arrangements for such facilities. The Contractor and his expatriate personnel
shall respect all Indian Acts, Laws, Rules and Regulations and shall not in any
way, interfere with Indian political and religious affairs and shall conform to
any other rules and regulations which the Government of India, and the
Employer may establish on them. The Contractor’s expatriate personnel shall
work and live in close co-operation and co-ordination with their co-workers and
the community and shall not engage themselves in any other employment either
part-time or full-time nor shall they take part in any local politics. The Employer
shall assist the Contractor, to the extent possible, in obtaining necessary
certificates and other information needed by the Government agencies.
CHAPTER 4: PROJECT IMPLEMENTATION
Specification for Ready mixed paint, brushing, grey filler, for enamels for use
IS:110 over primers.
IS:280 Specification for mild steel wire for general engineering purposes
IS:304 Specification for High Tensile Brass Ingots and Castings
IS:337 Specification for Varnish, finishing interior
IS:348 Specification for French polish
IS:383 Specification for coarse and fine aggregates from natural sources for concrete
IS:412 Specification for Expanded metal steel sheets for general purposes
IS:419 Specification for putty for use on window frames
IS:428 Washable Distemper-specification
Indian standard unreinforced corrugated and semi-corrugated asbestos cement
IS:459 sheets- Specification
IS:702 Specification for industrial bitumen
IS:710 Specification for marine plywood
IS:712 Specification for building limes
IS:730 Specification for hook bolts for corrugated sheet roofing
Specification for Wrought aluminium and aluminium alloys, bars, rods and
IS:733 sections (for general engineering purposes)
IS:15622 Specification for Pressed Ceramic Tiles
IS:1003 Specification for timber panelled and glazed shutters (Parts 1 & 2)
IS:1038 Specification for steel doors, windows and ventilators
IS:1077 Common burnt clay building bricks – Specification
Code of practice for fixing and glazing of metal (steel & aluminium) doors,
IS:1081 windows and ventilators
Method of test for determination of water absorption, apparent specific gravity
IS:1124 and porosity of natural building stones.
IS:1237 Specification for cement concrete flooring tiles
CHAPTER 4: PROJECT IMPLEMENTATION
IS:1322 Specification for Bitumen felts for water proofing and damp proofing
IS:1346 Code of practice for water proofing of roofs with bitumen felts
IS:1361 Specification for steel windows for industrial buildings
IS:1397 Specification for kraft paper
IS:1443 Code of practice for laying and finishing of cement concrete flooring tiles
IS:1477 Code of practice for painting of ferrous metals in buildings (Parts1 & 2)
IS:1542 Specification for sand for plaster
Specification for bituminous compounds for water-proofing and caulking
IS:1580 purposes
Code of practice for construction of stone masonry : Part 1 Rubble stone
IS:1597 masonry
IS:1659 Specification for block boards
IS:1661 Code of practice for application of cement and cement-lime plaster finishes
IS:1834 Specification for hot applied sealing compound for joints in concrete
Specification for preformed fillers for expansion joint in pavements and
structures (non- extruding and resilient type) : Part 1 Bitumen impregnated
IS:1838 fibre
IS:1948 Specification for aluminium doors, windows and ventilators
IS:1949 Specification for aluminium windows for industrial buildings
Ready mixed paint, air drying, red oxide- zinc chrome, priming –
IS:2074 Specification
IS:2098 Specification for Asbestos cement building boards
IS:2114 Code of practice for laying in-situ terrazzo floor finish
IS:2116 Specification for sand for masonry mortars
IS:2185 Specification for concrete masonry units (Parts 1,2 & 3)
IS:2202 Specification for wooden flush door shutters (Solid core type) : Parts 1 & 2
IS:2212 Code of practice for brickwork
IS:2250 Code of practice for preparation and use of masonry mortars
IS:2338 Code of practice for finishing of wood and wood based materials (Parts 1 & 2)
IS:2339 Specification for Aluminium paint for general purposes, in dual container
Code of practice for painting concrete, masonry and plaster surfaces (Parts 1
IS:2395 & 2)
IS:2402 Code of practice for external rendered finishes
IS:2571 Code of practice for laying in-situ cement concrete flooring
IS:2572 Code of practice for construction of hollow concrete block masonry
Integral cement waterproofing compounds for cement mortar and concrete –
IS:2645 Specification
IS:2690 Specification for burnt clay flat terracing tiles : Part 1 Machine made
IS:2691 Specification for burnt clay facing bricks
IS:2750 Specification for steel scaffoldings
IS:2835 Flat transparent sheet glass
IS:2932 Enamel, synthetic, exterior (a) undercoating, (b)finishing - Specification
Code of practice for laying of asbestos cement sheets - corrugated and (Part 1
IS:3007 & 2) semi-corrugated sheets
IS:3036 Code of practice for laying lime concrete for a water-proofed roof finish
Code of practice of general design details and preparatory work for damp-
IS:3067 proofing and water- proofing of buildings.
Specification for broken brick (burnt clay) coarse aggregates for use in lime
IS:3068 concrete
Specification for bitumen primer for use in water-proofing and damp-
IS:3384 proofing
CHAPTER 4: PROJECT IMPLEMENTATION
5.1 GENERAL
The intent of this technical specification covers the following:
All civil works shall be carried out as per drawings/design provided by the Em-
ployer/Contractor and as per these specifications provided by the Employer. In
case any item is not covered under specification then the same shall be carried
out as applicable Standards and Codes. Any item for which specification is not
provided herein and is not covered under standard specification shall be exe-
cuted as per manufacturer guidelines. All materials shall be of best quality con-
forming to relevant Indian Standards and Codes. In case of any conflict between
Standards/Code and Technical Specification, the provisions of Technical Speci-
CHAPTER 4: PROJECT IMPLEMENTATION
The Contractor shall furnish all designs, (unless otherwise specified) drawings,
labour, tools, equipment, materials, temporary works, constructional plant and
machinery, fuel supply, transportation and all other incidental items not shown
or specified but as may be required for complete performance of the Works in
accordance with approved drawings, specifications and direction of Employer.
All materials including cement, reinforcement steel and structural steel, etc shall
be arranged by the Contractor. All testing required shall be arranged by the con-
tractor at his own cost. The Contractor shall execute the work as per field quality
plan (FQP) attached with this document.
The bidder shall fully apprise himself of the prevailing conditions at the pro-
posed site. Climatic conditions including monsoon patterns local conditions and
site-specific parameters, soil parameters, availability of construction material
and shall include for all such conditions and contingent measures in the bid, in-
cluding those which may not have been specifically brought out in the specifica-
tions.
The scope shall generally cover switch yard structures, including gantries and
equipment support structures and their foundations, cable trenches along with
covers, cable trench crossings of road and rails, sump pits, marshalling box/con-
trol cubicle foundations, switch yard levelling, site clearance, soil investigation,
roads, drains, fencing, gravel filling, transformer / reactor foundations, firewalls,
control room building, other auxiliary buildings, potable water supply, street
light etc. Any other items not specifically mentioned here but required for the
commissioning of switch yard/substation shall be deemed to be included in the
scope of this Specification. The scope shall further cover design, construction for
all civil works at each substation. All civil works shall also satisfy the General
Technical Clauses specified in other sections of this specification and as detailed
below.
g) Trial pits
Trial pits shall be made at two locations as approved by AEGCL. The
trial pits shall be 2 meters square in size extending to (four) meters depth or
as specified by AEGCL. Undisturbed samples shall be taken from the trial
pits as per the direction of AEGCL.
This test shall be carried out to obtain the properties of soil required for
the construction of roads. The equipment and accessories required for
carrying out the test, test procedure, recording of observations and
presentation of results shall confirm to IS 2770 part XXXI. The test
locations of CBR test shall be on the road loc-ations as per GA drawing.
These tests shall be performed on remoulded and undisturbed, soaked and
un soaked samples.
i) Electrical resistivity test.
This test shall be conducted to determine the electrical resistivity of soil
required for designing safety grounding system for the entire station area.
The specifications for the equipment and other accessories required for
performing electrical resistivity test, the test procedure, and reporting of
field observations shall confirm to IS 3043. The test shall be conducted
using Wagner’s four electrode method as specified in IS 1892,
Appendix-B2. Unless otherwise specified at each test location, the test
shall be conducted along two perpendicular lines parallel to the coordinate
axis.
j) Plate load test
Plate load test shall be conducted to determine the bearing capacity and
load/ settlement characteristics of soil at shallow depths by loading a
plane and level steel plate kept at the desired depth and measuring the
settlement under different loads, until a desired settlement takes place or
failure occurs. The specification for the equipment and accessories required
for conducting the test, the test procedure, field observations and
reporting of results shall conform to IS 1888. The location and depth of
the test shall be given by the Contractor and approved by AEGCL.
Undisturbed tube samples shall be collected at 1.0 m and 2.5 m depths
from the natural ground level for carrying out laboratory tests.
The size of the pit shall not be less than five times the plate size and shall
be taken upto the specified depth. All provisions regarding excavation and
visual examination of pit shall apply here.
If the ground water table is at a depth higher than the specified test depth,
the ground water table shall be lowered and maintained at the test depth
for the entire duration of the test. Dewatering shall be at Contractor’s cost.
Unless otherwise specified the reaction method of loading shall be adopted.
Settlement shall be recorded from dial gauges placed at four diametrically
opposite ends of the test plate. The test plate shall be 600 x 600 mm size
and at least 25mm thick. The bottom of the pit shall be levelled before
placing the plate in position for conducting the test.
CHAPTER 4: PROJECT IMPLEMENTATION
A seating load of 70 gm/sq.cm shall be applied and after the dial gauge
readings are stabilized, the load shall be released, and the initial readings
of the dial gauges recorded after they indicate constant reading. The load
shall be increased in stages. These stages shall be 20, 40, 70, 100, 150,
200, 250, 300, 400. 500, 600 and 800 KN per sqm or as directed by
AEGCL. Under each loading stage, record of time versus settlement shall
be kept as specified in IS 1888.
The load shall be maintained for a minimum duration of one hour or
till the settlement rate reduces to 0.02 mm/m. whichever is later. No
extrapolation of settlement rate from periods less than one hour shall be
permitted.
Loading shall be carried out in stages as specified above till one of the
following conditions occurs:
i. Failure of the soil under the plate i.e. the settlement of the plate at
constant load becomes progressive and reaches a value of 40 mm or
more.
ii.Total settlement of the plate is more than 4Omm.
iii.Load intensity of 800 kN/sq.m is reached without failure of the soil.
Backfilling of the pit shall be carried out as per the directions of AEGCL.
Unless otherwise specified the excavated soil shall be used for this purpose.
The quoted rates shall include backfilling.
Dial gauge readings for settlement shall generally be taken at 1, 2, 4, 6,
9, 16, 25, 60, 90 and 120 minutes from the commencement of each
stage of loading. Thereafter the readings shall be taken at hourly
intervals upto a further four hours and at two hours intervals thereafter for
another six hours.
k) Water sample
Representative samples of ground water shall be taken when ground water
is first encountered before the addition of water to aid drilling of boreholes.
The samples shall be of sufficient quantity for chemical analysis to be
carried out and shall be stored in air-tight containers.
l) Laboratory Test
The laboratory tests shall be carried out progressively during the field
work after a sufficient number of samples have reached the laboratory, in
order that the test results of the initial bore holes can be made use of in
planning the later stages of the field investigation and quantum of
laboratory tests.
All samples brought from field, whether disturbed or undisturbed shall be
extracted/prepared and examined by competent technical personnel, and
the tests shall be carried out as per the procedures laid out in the latest
edition of the relevant IS Codes and Standards.
The following laboratory tests shall be carried out:
i. Visual and engineering classification.
ii. Liquid limit, plastic limit and and shrinkage limit.
iii. Natural moisture content, bulk density, dry density and specific gravity.
iv. Grain size distribution.
v. Unconfined compression test.
CHAPTER 4: PROJECT IMPLEMENTATION
Admixtures in concrete shall confirm to IS: 9103. The water proofing ce-
ment additives shall confirm to IS: 2645. Concrete Admixtures/Additives
shall be approved by the owner. Limit state method of design shall be
adopted unless stated otherwise in the Specification. For design and con-
struction of steel-concrete composite beams IS 11384 shall be followed. For
detailing of reinforcement IS 2502 and SP: 34 shall be followed. Cold
twisted deformed bars (Fe= 415 N/sq mm) conforming to IS 1786 shall be
used as reinforcement. Two layers of reinforcement (on inner and outer face)
shall be provided for wall and slab sections having thickness of 125 mm and
above. Clear cover to reinforcement towards the earth face shall be mini-
CHAPTER 4: PROJECT IMPLEMENTATION
mum 50 mm. RCC water retaining structures such as storage tanks, cooling
water basin etc. shall be designed as uncracked sections in accordance with
IS 3370 (Part 1 to IV) by working stress method and shall also be tested for
water tightness at full water level. However, water channels shall be de-
signed as cracked sections with limited steel stresses as per IS 3370 (Part 1
to IV) by working stress method. The procedure used for the design of the
foundations shall be the most critical loading combination of the steel struc-
ture and /or equipment and /or superstructure, and other conditions which
produce the maximum stresses in the foundation or the foundation compo-
nent, and as per the relevant IS Codes of foundation design. The design cal-
culations shall be submitted by the bidder showing complete details of
piles/pile groups proposed to be used. All foundations shall rest below virgin
ground level and the minimum depth of foundation below the virgin ground
level shall be maintained. Design shall consider any sub-soil water pressure
that may be encountered. Necessary protection to the foundation work, if re-
quired, shall be provided to take care of any special requirements for aggres-
sive alkaline soil, black cotton soil or any other type of soil which is detri-
mental or harmful to the concrete foundations. RCC columns shall be pro-
vided with rigid connection at the base. All building sub-structures shall be
checked for sliding and overturning stability during both construction and
operating conditions for various combinations of loads. Factors of safety for
these cases shall be as stated in relevant IS Codes or as stipulated elsewhere
in the Specifications. Earth pressure for all underground structures shall be
calculated using coefficient of earth pressure at rest, coefficient of active or
passive earth pressure (whichever is applicable). However, for the design of
substructures of any underground enclosures, earth pressure at rest shall be
considered. In addition to earth pressure and ground water pressure etc., a
surcharge load of 2T/sq.m shall also be considered for the design of all un-
derground structures including channels, sumps, tanks, trenches, and sub-
structures of any underground hollow enclosure etc., to allow for vehicular
traffic in the vicinity of the structure.
The foundations shall be proportioned so that the estimated total and
differential movements of the foundations are not greater than the
movements that the structure or equipment is designed to accommodate.
The foundation of the transformer and circuit breaker shall be of block
type foundation. Minimum reinforcement shall be governed by IS:2974
and IS:456.
Full earth pressure, surcharge pressure and ground water pressure from out-
side and no water pressure from inside.
Design shall also be checked against buoyancy due to the ground water
during construction and maintenance stages. Minimum factor of safety of
1.5 against buoyancy shall be ensured ignoring the superimposed loadings.
Base slabs of any underground enclosures shall be designed for empty
condition during construction and maintenance stages with maximum
ground water table (GWT).
Base slab of underground enclosures such as water storage tank shall
also be designed for the condition of different combination of pump
sumps being empty during maintenance stages with maximum GWT. Inter-
mediate dividing piers of such enclosures shall be designed considering
water in one pump sump only and the other pump sump being empty for
maintenance.
c) Machine Foundations
All machine foundations shall be designed in accordance to the provisions
of the relevant parts of the latest revisions of IS 2974, IS 456 and IS
2911.The provisions of DIN 4O24 (latest) shall also be followed. All block
foundations resting on soil or piles shall be designed using the elastic half
space theory.
The mass of the RCC block shall not be less than three times the mass of
the machine. Dynamic analysis shall be carried out to calculate natural
frequencies in all the modes including coupled modes, and to calculate
vibration amplitudes. Frequency and amplitude criteria as laid down by the
relevant IS codes and/or machine manufacturers, shall be satisfied.
Minimum reinforcement shall be governed by IS 2974 and IS 456.
CHAPTER 4: PROJECT IMPLEMENTATION
For the foundations supporting minor equipment weighing less than one
tonne, or if the mass of the rotating parts is less than one-hundredth of
the mass of the foundation, no dynamic analysis is necessary. However, if
such minor equipment is to be supported on building structures, floors
etc. suitable vibration isolation shall be provided by means of springs,
neoprene pads etc. and such vibration isolation system shall be designed
suitably.
d) Other Foundations
All foundations shall be designed in accordance with the provisions of the
relevant parts of latest revisions of IS 2911 and IS 456. Type of
foundation system i.e. isolated footing, raft or piling shall be decided based
on the load intensity and soil strata. A minimum three piles shall be
provided in any pile group. Gantry and tower foundations shall be
designed for an additional factor of safety of 1.1 for normal/ broken wire
conditions and for short circuit condition. Circuit breaker foundations
shall be designed for impact loading and shall be strictly in accordance
with the Manufacturer`s recommendations.
e) 220 KV GIS Building - Architectural Drawings are enclosed with the
tender documents. Structural Drawing shall be prepared by the Contractor.
f) 33kV Switchgear & Control Room building– Architectural Drawings are
enclosed with the tender documents. Structural Drawing shall be prepared
by the Contractor.
g) Fire fighting pump house Building & Fire water Tank
h) R.E Residence - Architectural Drawings are enclosed with the tender
documents. Structural Drawing shall be prepared by the Contractor.
i) Officers Hostel/ Transit Camp - Architectural Drawings are enclosed with
the tender documents. Structural Drawing shall be prepared by the
Contractor.
j) Staff hostel - Architectural Drawings are enclosed with the tender
documents. Structural Drawing shall be prepared by the Contractor.
k) Security Barrack - Architectural Drawings are enclosed with the tender
documents. Structural Drawing shall be prepared by the Contractor.
l) Security Booth - Architectural Drawings are enclosed with the tender
documents. Structural Drawing shall be prepared by the Contractor.
m) Open Store Shed - Architectural Drawings are enclosed with the tender
documents. Structural Drawing shall be prepared by the Contractor.
n) Store Building - Architectural Drawings are enclosed with the tender
documents. Structural Drawing shall be prepared by the Contractor
o) Septic Tank and Soak Pit - Drawing to be prepared by contractor on the
basis of specifications provided in the bid document.
p) Roads and RCC box culverts – Drawing to be prepared by contractor on the
basis of specifications provided in the bid document.
q) Drains - Drawing to be prepared by contractor on the basis of specifications
provided in the bid document.
r) Chain link fencing – Drawing enclosed with the bid document.
s) Gate - Drawing enclosed with the bid document
t) Cable trenches - Drawing enclosed with the bid document.
CHAPTER 4: PROJECT IMPLEMENTATION
d) Programme
CHAPTER 4: PROJECT IMPLEMENTATION
The Contractor shall execute the works as per the approved schedule in
accordance with the requirements of this Specification.
e) Inclement weather
PLOYER may at any time withdraw his previously given approval to ob-
taining materials from any maker or supplier should such maker or sup-
plier fail to supply materials of the specified quality or quantity in the requi-
site time.
e) Rejection of materials and workmanship –
EMPLOYER shall at any time have power to reject materials and work-
manship not complying with this Specification or with the approved
Drawings. Materials so rejected shall be immediately removed from site
and replaced by materials of an approved standard at the expense of the
Contractor. Rejected workmanship shall be broken out and replaced by
work of an acceptable standard including the supply of new materials
by the Contractor, at the expense of the Contractor, and without delay.
f) Explosives and Blasting –
All rules under the Explosive Act or other local rules in force shall be fully
observed. All blasting works shall be done in accordance with the stipu-
lation contained in IS 4081. Written approval shall be obtained from
EMPLOYER before explosives are used for excavating foundations in rock
and EMPLOYER may impose conditions for their use. The Contractor shall
be responsible for complying with local regulations concerning the use of
explosives and for the safe-keeping and handling of explosives. Proper
warning shall be given of all blasting operations. During operations in-
volving the handling or use of explosives, the Contractor shall be re-
sponsible for the safety of personnel, Site Works and people or properties
in the vicinity of the site. The Contractor shall make good at his own ex-
pense any damage caused by the use or mishandling of explosives.
5.6 EXCAVATION AND BACKFILL
Excavation and backfill for foundations shall be in accordance with
the relevant Code. The back fill around the foundations shall be com-
pacted according to the specification mentioned for Compaction.
Whenever water table is met during the excavation, it shall be dewatered
and water table shall be maintained below the bottom of the excavation
level during excavation, concreting and backfilling.
When embankments are to be constructed on slopes of 15% or greater,
benches or steps with horizontal and vertical faces shall be cut in the origi-
nal slope prior to placement of embankment material. Vertical faces shall
measure not more than one meter in height.
Embankments adjacent to abutments, culverts, retaining walls and similar
structures shall be constructed by compacting the material in successive
uniform horizontal layers not exceeding 15 cm in thickness, (of loose mate-
rial before compaction). Each layer shall be compacted as required by
means of mechanical tampers approved by EMPLOYER. Rocks larger than
ten centimeters shall not be placed in embankment adjacent to structures.
CHAPTER 4: PROJECT IMPLEMENTATION
Support of excavations
CHAPTER 4: PROJECT IMPLEMENTATION
The Contractor shall be responsible for the stability of the sides of the
excavations. Excavations shall be close timbered or sheeted, planked and
strutted as and when necessary during the course of the work and shall
ensure the safety of personnel working within them. If any slips occur,
they shall, as soon as practicable, be made good in an approved manner at
the expense of the Contractor. Shoring shall not be removed until the
possibility of damaging the works by earth pressure has passed. No
payment for shoring or timber left in shall be made.
Works to be in dry
All excavations shall be kept free from water and the Contractor shall take
whatever action is necessary to achieve this. Pumping, well pointing and
other means necessary to maintain the excavations free from water shall be
at the expense of the Contractor, and carried out in an approved manner.
Backfill
As soon as possible after the permanent works are sufficiently hard and
have been inspected and approved, backfill shall be placed where necessary
and thoroughly consolidated in layers not exceeding two hundred (200)
millimetres in depth.
On completion of structures, the earth surrounding them shall be accurately
finished to the line and grade as shown on the drawings. Finished surfaces
shall be free of irregularities and depressions.
The soil to be used for back filling purposes shall be from the excavated
earth or from borrow pits, as directed by EMPLOYER.
Disposal of surplus
Surplus excavated material not required or not approved for fill or backfill
shall be loaded and deposited either on or off site as directed. The
Contractor shall not delay disposal of surplus material after receipt of
instructions from EMPLOYER. The contractor shall arrange to transport
the excavated earth by mechanical transport, not necessarily on Pucca
roads. The soil so transported shall be stacked and levelled neatly and
dressed. The location for disposal of shall be arranged by contractor at their
own cost and responsibility within 5kM from the site observing necessary
government law and regulation.
Compaction:
The method and equipment used to compact the fill material to a density
that will give the allowable soil bearing pressure required for the
foundations, roads, etc. in each layer of fill material. Each layer of earth
embankment when compacted shall be as close to optimum moisture
content (OMC) as practicable. Embankment material which does not
contain sufficient moisture to obtain proper compaction shall be wetted.
If the material contains an excess of moisture, then it shall be allowed to
dry before rolling. The rolling shall begin at the edges overlaping half the
width of the roller each time and progress to the center of the road or
towards the building as applicable. Rolling will also be required on
rockfills. No compaction shall be carried out in rainy weather.
At all times unfinished construction shall have adequate drainage. Upon
completion of the road's surface course, adjacent shoulders shall be given a
final shaping, true alignment and grade.
CHAPTER 4: PROJECT IMPLEMENTATION
The boundary wall shall be designed based on the soil investigation data.
Salient points to be considered at the time of design:
(1) Random rubble masonry wall for retaining wall as per relevant IS
code.
(3) RCC (1:1.5:3) tie beam: continuous RCC tie beam to be rested on the
RCC pillars below the finished ground level all along the boundary line.
Provision of steel bar: (a) Horizontal 12 mm Ø: 6 Nos. (b) Stirrup: 8 mm
Ø, 150 mm C to C.
(4) Brick works: 1st Class Brick of all along the boundary wall to be
provided. Cement sand mortar of ratio (1:4) to be provided for brick
masonry works. A 50mm height of finished concrete (ratio 1:2:4) shall
be provided on the top of the boundary wall.
(5) BRICK: The brick shall be shall be machine moulded and made
from suitable fly ash, cement, lime, gypsum, etc. They shall be free
from cracks and nodules of free lime. They shall have smooth rectangu-
lar faces with sharp corners and shall be of uniform colour. The bricks
shall be moulded with the frog of 100mm x 40 mm and 10mm to 20mm
deep on one of its flat sides. The bricks shall not break when thrown on
the ground from a height of 600mm
The size of the modular bricks shall be 190 x 90 x 90 mm.
The size of the conventional bricks shall be 250 x 125 x 75mm.
Only bricks of one standard size shall be used on one work. The follow-
ing tolerance shall be permitted in the conventional size adopted in a
particular work. Length +3.0mm, Width + 1.50mm, Height +1.50mm.
The crushing strength of the brick shall not be less than 75.0 Kg / Sq cm.
The average water absorption shall be within 13- 15% by weight. Simi-
larly, the porosity of the fly ash bricks shall be within 12-20%. Neces-
sary test for crushing strength and water absorption shall be carried out
as per IS 3495: (Part I to Part IV) 1976.
b) Design
The buildings shall be designed:
to the requirements of the National Building Code of India. and the stan-
dards quoted therein
for the specified climatic and loading conditions
to adequately suit the requirements of the equipment and apparatus
contained in the buildings and in all respects to be compatible with
the intended use and occupancy
with a functional and economical space arrangement
for a life expectancy of structure, systems and components not less
than that of the equipment which is contained in the buildings, pro-
vided regular maintenance is carried out
to be aesthetically pleasing. Different buildings shall show a uniformity
and consistency in architectural design
to allow for easy access to equipment and maintenance of the equipment
with, wherever required, fire retarding materials for walls, ceilings and
doors, which would prevent supporting or spreading of fire
with material preventing dust accumulation
Suitable expansion joints shall be provided in the longitudinal direc-
tion wherever necessary with provision of twin columns.
Individual members of the building frame shall be designed for the
worst combination of forces such as bending moment, axial force, shear
force, torsion etc.
Permissible stresses for different load combinations shall be taken as per
relevant IS Codes.
All cable vaults shall be located above ground level i.e. cable vaults shall
not be provided as basements in the buildings. The building lighting
shall be designed in accordance with the requirements of relevant sec-
tion.
The building auxiliary services such as air conditioning and ventilation
systems, fire protection and detection systems and all other miscella-
CHAPTER 4: PROJECT IMPLEMENTATION
shutter for trouble free and smooth operation. The rolling shutter with
handle gear operation shall be provided.
h) Finish Schedule
The preliminary indicative finishing schedule is given in subsequent
clauses. However, at the time of detailed engineering, EMPLOYER
reserves the right to alter the finishing schedule and specifications and
such changes shall have no additional financial implication whatsoever to
the Employer.
ii. Walls
Control room buildings shall have framed superstructure. All walls shall
be non-load bearing walls. Minimum thickness of walls shall be 230
mm with 1:4 cement sand mortar. A 50 mm thick DPC shall be
provided at plinth level before starting masonary work.
iii. Plastering
All internal walls shall have minimum 20mm thick 1:4 cement sand
plaster. The ceiling shall have 15mm thick 1:4 cement sand plaster.
1 Interior wall 3P 0778- Soft Light (Easy 7907-Candle Wick (AP 2016P- Lemon balm
Clean) Royale) (Lotus Touch)
2 Exterior wall 2P 0229-Calming Touch 8564- Sweet Dreams 4051- Lightest Peach
(body) (Weather Coat Smooth) (Apex) (Excel)
3 Exterior wall 2A 0232- Cookie Crisp 8645-Rich Chocolate 2798C- Kitty Kat
(border) (Weather Coat Smooth) (Apex) (Excel)
Minimum section for aluminium doors & windows: Main outer size-
127mmX38.10X2mm; Horizontal & verical four track-
122.2mmX31.75mmX2mm; Sliding shutter Horizontal & Vertical-
40mmX18mmX2mm.
All other quarter and hostel buildings shall have factory made wooden
paneled doors with wooden chowkaths of size 150 x 75 mm and
laminate. The thickness of the panel shall be 35mm. Timber to be used
shall be first class Indian Teak wood as per IS: 4021. This shall be of
the best quality and well-seasoned by a suitable process before being
planned to the required sizes. The maximum permissible moisture
content shall be from 10 to 16 percent for timber 50mm and above in
thickness and 8% to 14 % of timber less than 50mm in thickness for
different regions of the country as stipulated in IS: 287. Timber shall be
close grained, of uniform colour and free from decay, fungal growth,
boxed heart, pitch pockets or streaks on the exposed edges, borer holes,
splits and cracks. Flush door shutters of the solid core type with plywood
face panels shall conform to IS: 2202 (Part 1) and with particle
board/hard board face panels shall conform to IS: 2202 (Part 2).
Windows for all building shall be Ivory powder coated aluminum sliding
windows and ventilators of standard sections as required complete as
specified and directed for all levels. All window shall have sliding panel
of mosquito proof net made of carbon fiber.
The window grill shall be made of: outer frame and two (2) intermediate
vertical frame made of 50X25X1.5 mm MS tube, horizontal member
16mm round bar @ 100 mm centre to centre. Finishing with primer and
enamel paint.
Proper locking arrangement with stoppers to be provided on the door
and windows. Care should be taken while designing the grill frame that
the entering of cat should be restricted.
ix. Plumbing And Sanitation
All plumbing and sanitation work shall be executed to comply with
the requirements of the appropriate bye laws, rules and regulations of
the Local Authority having jurisdiction over such matters. The
Contractor shall arrange for all necessary formalities to be met in
regard to inspection, testing, obtaining approval and giving notices etc.
One (1) no. Stainless Steel kitchen sink with Drain board (510x 1040 x
178 mm bowl Depth) for pantry shall be provided.
All fittings, fastener, grating shall be chromium plated.
All sanitary fixtures and fittings shall be of approved quality and type
manufactured by well known manufactures. All ítems brought to site
must bear identification marks of the type of the Manufacturer.
x. Building storm water drainage
The building design shall provide for the collection of storm water
from the roofs. This water shall be collected in junction boxes and
these boxes shall drain to the main drainage system of the station.
100 mm nominial dia uPVC pipe rain water of 6kg shall be provided
to drain off the rain water from the roof. These shall be suitably
concealed with masonry work of cement concrete or cladding
material. The number and size of downcomers shall be governed by
IS:1742 and IS:2527.
All drains inside the buildings shall have minimum 40 mm thick
grating covers and in areas subject to movement heavy equipment
loads, precast RCC covers shall be provided in place of steel grating.
For all buildings, suitable arrangement for draining water collected from
equipment blowdowns, leakages, floor washings, firefighting etc. shall
be provided for each floor.
xi. Plinth Protection
Entire area around the control room building (outside) shall be provided
with PCC paving starting from the building upto 1 mtrs clear distance for
the full length of the building.The above specified PCC paving shall be
with M20 mix grade concrete over suitable under bed arrangement as
specified for other ground floor slab.Above the PCC paving suitable
Cement pavers chequered plate of size as per the standard to be
provided. The colour of the chequered plate shall be fixed over the PCC
paving by using cement mortar and the colour of such plate shall be red.
The cable vault below the main control room shall have 50 mm thick
smooth floor finish units of cement concrete.
Stair case of all type of buildings shall have stainless steel pf 304
grade in hand railing using 50mm dia of 2mm thick circular pipe
with balustrade of size 32mmx32mmx32mm @0.90mtr C/C and
stainless square pipe bracing of size 32mmx32mmx32mm in
three rows in staircase as per approved design and specification,
buffing, polishing.
xii. Illumination Sysytem
The Contractor shall design, supply and install illumination system for
the entire substation. The average illumination level and limiting glare
index for different parts of the substation shall be as follows.
sliding layer of bitumen paper or craft paper shall be provided over the
screed layer to destroy the bond between the screed and the base slab
concrete of the water retaining structures. Bricks having minimum
75kg/sq.cm compressive strength can only be used for masonry work.
Bidder shall ascertain himself at site regarding the availability of bricks
of minimum 75kg/ sq.cm compressive strength before submitting his
offer. Monorails, monorail girders and fixtures shall be provided, wherever
required. Doors and windows on external walls of buildings other than
areas provided with insulated metal claddings shall be provided with a
RCC sun-shade over the openings with 300 mm projection on either side
of the openings. Projection of sunshade from the wall shall be minimum
450 mm over window openings and 750 mm over door openings.
All stairs shall have maximum riser height of 150 mm and a minimum
tread width of 250 mm. Minimum width of stairs shall be 1200 mm.
There shall be provision of staircase to the roof of the building.
Angles of 50x50x6 mm minimum with lugs shall be provided for edge
protection all round cut out and openings in floor slab, edges of drains
with grating covers, edges of RCC cable/pipe trenches with covers, edges
of manholes with covers, edges of precast covers and any other place
where breakage of corners of concrete is expected.
1:3:6 placed over sand filling. The top of PCC shall be up to the formation
level. In case of road cum rail track, 75mm thick PCC of grade 1:1.5:3
shall be placed up to the road level. Suitable drainage system between the
tracks shall be provided.
The rails shall be first quality 52 kg/m medium manganese steel as per
Indian Railway specification T-12-64 and its subsequent revision, joined
together by fish plates as per Indian Railway specification T-1/57, and 27
mm diameter fish bolts.
A pylon support system shall be provided for supporting the firefighting
system by the Contractor.
For design of foundation for transformer refer the weightage of the
transformer indicated in the BPS (civil works)
b) Application criteria
A fire wall shall be erected between the transformers and or the reactors
if the free distance between the various pieces of equipment is less than
10 m, to protect each one from the effects of fire on another.
Fire walls shall also be erected between the transformers, reactors, and
auxiliary services transformers if the free distance is less than ten
meters.
c) Fire resistance
The fire wall shall have a minimum fire resistance of three hours.
Partitions which are made to reduce the noise level of the transformers
shall have the same fire resistance where they are also used as fire walls.
The walls of buildings which are used as fire walls, shall also have a
minimum fire resistance of three hours.
Fire walls shall be designed in order to protect against the effect of
radiant heat and flying debris from an adjacent fire. The column of the
fire walls shall be type be RCC, M20 (1:1.5:3 mix).
d) Mechanical resistance
Fire walls shall have the mechanical resistance to withstand local
atmospheric conditions. If the wall is intended to serve as a support for
equipment such as insulators etc., its mechanical rigidity must be
increased accordingly.
Building walls which act as fire walls shall extend at least one metre
above the roof in order to protect it.
f) Materials
Fire walls may be made of reinforced concrete (M20 grade), fire brick,
concrete blocks or corrugated iron on a steel structure as per the
system requirements. Materials used must conform to the standards of
the National Fire Prevention Association and TAC norms.
All construction joints of cable trenches i.e. between base slab to base
slab and the junction of vertical wall to base slab, as well as from
vertical wall to wall, and all expansion joints shall be provided with
approved quality PVC water stops of approximately 230 x 5 mm size
for those sections where the ground water table is expected to rise
above the junction of base slab and vertical wall of cable trenches.
The covers for the cable trench inside the control room shall be
provided with MS chequered plate with MS angle stiffeners at the
bottom for proper mechanical strength.
b) Excavation
Excavation for cable ducts shall generally be carried out in accordance
with specification.
c) Back fill
Except where ducts are to be encased in concrete, sand is to be packed
and well tamped round the duct until it is covered to a depth of 75 mm
above the upper surface of the duct. Filling above this level is to be with
suitable excavated material free from large stones. In multiple duct runs
the interstices between the ducts are to be filled with sand and
compacted. A cover of 75 mm above the uppermost ducts shall be
maintained. The sand used shall be the same quality as approved for
use in making concrete.
d) Laying of ducts
Telephone and electrical cable ducts shall be laid and jointed in
accordance with the Manufacturer’s instructions.
alternate lines.
f) Cutting of ducts
The Contractor shall carry out any necessary cutting of pipe ducts
according to the requirements of the work. Except where ducts enter the
cable trench at an angle, they shall be cut at right angles to the length of
the duct. The inside edges of cut ducts shall be thoroughly rounded off or
so dressed before being placed in position so that there can be no
possibility of damage to cables from the edges of the ducts. All electrical
ducts entering draw pits shall be provided with suitable bell mouths.
g) Cleaning and testing of ducts
On completion of all electrical cable ducting, two mops of appropriate
size connected one to each end of an iron mandrel shall be passed
twice through each way to clean the conduit and to remove any foreign
matter which may have entered. If any obstruction or other defect be
discovered, it shall be removed or rectified forthwith.
h) Sealing of electrical ducts
As soon as every duct or set of ducts has been proved and its draw
wire material installed, the ends of the cut or its bell mouth where
provided, shall be sealed to a depth of 5 mm with an appropriate sealer,
and a single coat of bitumastic paint shall then be applied over the end
of the ducts and the seal. The length of draw wire installed shall be
such that at least one metre of draw wire extends from each end of each
duct. After the ends of ducts have been sealed the free ends of draw
wires shall be neatly coiled.
i) Concrete cable and pipe trenches
In-situ concrete trenches are to be provided inside and outside the
Substation. The trenches are to have falls in the floor and must be
drained at regular intervals. All trenches must have trench covers
suitable for their location and loading. Any beams or supporting covers
must be as shallow as possible to avoid interfering with the pipes and
cables in the trench. Once the trench covers have been made they are to
be stored and not laid until all trench cabling, piping, etc. is finished.
Any covers laid before this time which become damaged shall be
replaced at the Contractor’s expense. Trench covers and bridging beams
for covers, except where heavy duty, shall be light enough for two men
to lift.
j) Buried cables
Cables are to be laid in neat lines and at suitable levels. Their depth
below ground level will depend upon the voltage associated with the
cables but in all cases the excavation must provide a clear trench.
Sand filling below, around and above the cables will always be
required and protection covers or tiles will be placed in position over
the sand filling before final backfilling to the ground level. The line of
the cable trenches shall be marked with suitable posts as required by
relevant section of this Specification. The installation and maintenance
of high voltaje cable shall conform to IS 1255.
UPVC pipes shall be used below ground level for sewage disposal.
b) Storm Water Drain
Storm Water drainage system shall be provided along both side of
the road as well as surrounding the campus and switchyard .
The Contractor shall obtain rainfall data and design the storm water
drainage system, (culverts, ditches, drains etc.) to accommodate the most
intense rainfall that is likely to occur over the catchment area in one-
hour period on an average of once per ten years. The surfaces of the
site shall be sloped to prevent the ponding of water. The bottom of the
drain should be minimum 600mm wide. The side wall should be minimum
2:1 slope. The maximum velocity for pipe drains and open drains shall be
limited to 2.4m/sec and 1.8m/sec respectively. However, minimum non
silting velocity of 0.6m/sec shall be ensured. Longitudinal bed slope
not milder than 1:500 shall be provided. For design of RCC box culvert
for drains and culverts, IS 456 and IS 783 shall be followed. The Contrac-
tor shall ensure that water drains are away from the site area and shall pre-
vent damage to adjacent property by this water. Adequate protection
shall be given to site surfaces, roads, ditches, culverts, etc., to prevent ero-
sion of material by water. The drainage system shall be adequate without
the use of cable or pipe trenches. For road crossings RCC box culvert
shall be provided. Manholes shall be provided at 30 m intervals, at
connection points and at every change of alignment. All manholes
deeper than 1.2 m shall be provided with galvanized M.S. footrests.
Footrests shall be of 20 mm M.S. square bars. Open surface drains shall
be of RCC (1:1.5:3) type. Design and drawings shall have the approval
of EMPLOYER. For expansive soils, the guidelines of IS 9451 shall be
followed. Suitable expansion joints shall be provided as per standard. In
general, all plant effluent drainage shall be through buried concrete pipes
and all storm water drainage shall be through open drains/pipe drains.
Open storm water drains shall be provided on both sides of the roads
and shall be designed to drain the road surface as well as all the free and
covered areas. Pipe drains shall be connected through manholes at an in-
terval of maximum 30 m. Plant effluents shall be suitably treated by the
Contractor to meet all the prevalent statutory requirements and local pol-
lution control norms and treated effluents shall be conveyed to the storm
water drainage system at a suitable location for their final disposal. Invert
of the drainage system shall be decided in such a way that the water can
easily be discharged above the High Flood Level (HFL) outside substa-
tion boundary at suitable location and approved by EMPLOYER. Pump-
ing of drainage water, if required, shall be provided by Contractor. All
internal site drainage systems, including the final connection and dis-
posal to Authorized representative of EMPLOYER acceptance points
shall be part of Contractor`s scope including all required civil work, me-
chanical and electrical systems. The Contractor shall connect his drain(s)
CHAPTER 4: PROJECT IMPLEMENTATION
The Contractor shall locate the outfall point outside the substation
vicinity and the substation storm drainage must be connected to this
point.
accept an air (smoke) pressure test, provided that the method of testing
is approved by EMPLOYER. Further testing may be called for after
backfilling of trenches to ensure that pipes have not been damaged
during that operation.
iv. Regulations
The regulations and recommendations of any relevant drainage or
sanitary authority shall be fully observed, and the Contractor shall
be responsible for acquainting himself with any such regulations.
After due compaction of the surface of the entire switchyard area shall be
provided with plain cement concrete of 100 mm thickness after proper
compaction, and antiweed treatment having cement concrete ratio 1:3:6.
Care shall be taken for proper gradient for easy discharge of storm water.
As a final surface course minimum 100 mm uniform layers of uncrushed
/crushed broken metals (gravel) of 20 mm. nominal size shall be spread over
the base layer/course. This final surface course shall be applied in all areas of
switchyard exclusive of roadways up to the fenced area. This surface course
shall then be compacted by light roller using 1/2-ton steel roller (width 30”x
dia 24”) and 4 to 5 passes or any other means with water sprinkling as
directed by EMPLOYER. Water shall be sprinkled in such a manner that
bulking does not take place. The 20 mm. nominal size (for both layers) shall
pass 100% through IS sieve designation 37.5 mm and nothing through 16.0
mm. IS sieve.
In areas that are considered by EMPLOYER to be too congested with
foundations and structures for proper rolling of the site base course material
by normal rolling equipment’s, the material shall be compacted by hand, if
necessary. Due care shall be exercised so as not to damage any foundation
structure or equipment during rolling or compaction. EMPLOYER by no
means shall relieve the contractor of their contractual obligations as
stipulated in General and Special Conditions of Contract.
A 125mm mm thick (one and a half brick size) toe wall of Brick with
tie beam with notches shall be provided below all fencing and shall be
minimum 200 mm above and 500 mm below finished ground level. All
exposed surfaces for brick toe wall shall be provided with 15 mm 1:4
cement sand plaster and coated with two coats of e x t e r n a l weather
coat paint. In case if rubble masonry is provided suitable pointing shall be
done.
b) Gates shall be installed in locations shown on drawings. Next to the main
gate, a men gate (1.25 m wide, single leaf) shall also be provided.
Bottom of gates shall be set approximately 40 mm above ground surface
and necessary guiding mechanism (with roller on the bottom of the gate
and fixed guider in the road) shall be fitted to avoid hanging of the main
gate.
Design of the gate shall be as per attached drawing in the BID document.
Gates shall be fabricated with welded joints or other approved methods
to achieve rigid connections.
All culverts and allied structures required for road/rail, drain, trench crossings
etc. shall be designed for class AA loading as per IRC standard.
At the junction of the hard standing and roads due to different thickness of
foundations, precautions shall be taken to ensure that sub-surface drainage
from the hard standing does not have a detrimental effect upon the road foun-
dations.
a) INTER LOCKING CONCRETE BLOCK PAVEMENT (ICBP)
BLOCK ROAD:
The side shoulder of all the roads shall be with kerb stone at two sides. The
kerb stones shall be painted yellow and black alternatively. In case of switch
yard road, the shoulder would be compacted earth 600 mm wide on the sides
of the road. The inter locking concrete block pavement (ICBP) block road
shall have minimum 80 mm thick. Below it 150 mm thick water bound
macadam (WBM) in two equal layers of 75 mm each at the bottom and
minimum 200mm granular sub-base.
5.18FOUNDATION AND RCC CONSTRUCTION
a) General
Work covered under this Clause of this Specification comprises the de-
sign, supply and installation of foundations and other RCC construc-
CHAPTER 4: PROJECT IMPLEMENTATION
c) Aggregate
Coarse and fine aggregate shall conform to the requirements of IS 383-
1970.
Sampling and testing of aggregates shall be in accordance with the
relevant Indian Standard.
Fine and coarse aggregates shall be obtained from the same source and
the Contractor shall ensure that material from the source is known to
have a good service record over a long period of time.
Aggregate shall be hard and dense and free from earth, clay, loam and
soft, clayey, shaley or decomposed stone, organic matter and other
impurities.
d) Storage of aggregates
Coarse and fine aggregates shall be stored on site in bins or on clean,
dry, hard surfaces, and be kept free from all sources of contamination.
Aggregates of different gradings shall be stored separately, and no new
aggregate shall be mixed with existing stocks until tested and approved
by EMPLOYER.
e) Approval of Supplies
As soon as possible after the Contract has been placed the Contractor
shall submit a list giving details of the sources from which he proposes
to obtain concrete and mortar materials. Only materials from approved
sources shall be brought to site, but EMPLOYER will be prepared to
extend his approval to other satisfactory sources of supply which may
be proposed by the Contractor. Approval of a source of supply shall not
imply acceptance of material found not to conform to this Specification
f) Water
CHAPTER 4: PROJECT IMPLEMENTATION
Water used for mixing concrete and mortar shall be clean, fresh water
obtained from an approved source and free from harmful chemicals,
oils, organic matter and other impurities. Normally potable water may
be considered satisfactorily for mixing and curing concrete and masonry
work. Requisite tests to be done if directed by Employer.
For durability the minimum concrete cover to any reinforcing bar shall
be as follows:
Concrete above ground.
Internal faces of slabs 25 mm
Internal faces of beams and walls 30 mm
Exposed faces of slabs, beams and walls 50 mm
All faces of columns and sub-structures 50 mm
i) Grades of concrete
Concrete shall be either ordinary or controlled and in grades designated
M10, M15, M20 and M25 as specified in IS 456 (latest edition). In addi-
tion, nominal mixes of 1:3: 6 or as indicated on drawings, or any other
mix without any strength requirements as per mix design shall be used
where specified. RCC for pile works shall be Design Mix of minimum
grade M-25 and also minimum cement content shall be 400 kg/cum as per
IS:2911.
i) Ordinary concrete
CHAPTER 4: PROJECT IMPLEMENTATION
Ordinary concrete shall be used for all plain cement concrete work and
where shown on drawings in proportioning concrete, the minimum
quantity of cement shall be as specified in Table 15.15.1 of this clause
and the amount to be used shall be determined by actual weight. The
quantities of fine and coarse aggregate may be determined by volume,
but preferably by weight.
The water cement ratio shall not be more than those specified in IS 456.
or allowed by EMPLOYER. Ordinary concrete shall not require
preparation of trial mixes.
Characteristic Compressive
Grade Designation
Strength at 28 days
CHAPTER 4: PROJECT IMPLEMENTATION
M 10 10 N / sq. mm
M 15 15 N / sq. mm
M 20 20 N / sq. mm
M 25 25 N / sq. mm
The strength of concrete given above is the 28
days characteristic compressive strength of 15 cm
cube.
j) Workability
The workability of concrete shall be checked at frequent intervals by
slump test, where facilities exist and if required by EMPLOYER,
alternatively the compaction factor test in accordance with IS 1199
shall be carried out.
k) Mixing of Concrete
Unless otherwise approved, concrete for foundations will be M 20
grade, corresponding to nominal mix of 1:1.5:3 as per IS 456. The
proportions of fine and coarse aggregate, cement and water shall be
as determined by the mix design or according to fixed proportions
in case of nominal mix concrete and shall always be approved by
EMPLOYER. The quantities of the cement, fine and coarse
aggregates shall be determined by weight, the water shall be
measured accurately after giving proper allowance for surface water
present in the aggregate. Water shall be added to make a workable
mix and it is important to maintain the water-cement ratio at its
maximum
value of 0.55 in accordance with the requirements of IS 456.
Water shall not be added to the mix until all the cement and
aggregates constituting the batch are already in the drum and dry
mix for at least one minute. Mixing of each batch shall be
continued until there is uniform distribution of materials and the
mass done for less than 2 minutes and at least 40 revolutions after all
the materials and water are in the drum.
When hand mixing is permitted by EMPLOYER for concrete to be
used in unimportant locations it shall be carried out on a watertight
platform and care shall be taken to ensure that mixing is continued
until the mass is uniform in colour and consistency. In case of
hand mixing, an extra 10% of cement shall be added to each batch
and additional cost due to extra cement will be borne by the
Contractor.
l) Conveying Concrete
Concrete shall be handled and conveyed from the place of mixing to
the place of final laying as rapidly as practicable by approved
means before the initial setting cement starts. Concrete should be
conveyed in such a way which will prevent segregation or loss of
any of the ingredients. If segregation does occur during the transport
of concrete same shall be re- mixed. The requirements to be fulfilled
during transportation are:
No segregation or separation of materials in the concrete, and concrete
CHAPTER 4: PROJECT IMPLEMENTATION
o) Curing of Concrete
In order to achieve proper and complete strength of the concrete, the
loss of water from evaporation should be prevented. Eighty to eighty-
five per cent of the strength is attained in the first 28 days and hence
this 28-day strength is considered to be the criterion for the design and
is called characteristic strength. The concrete after setting for 24 hours
shall be cured by keeping the concrete wet continuously for a period of
10 days after laying.
The curing increases compressive strength, improves durability,
impermeability and abrasion resistance. Failure to carry out
satisfactory curing can lead to cracking in the concrete. This in turn
can lead to salt attack of the reinforcement and consequential
failure of the structure. If cracks occur in a structure which are
severe enough to affect the structure, the Contractor shall cut out
and replace the defective concrete at his own cost. The Contractor’s
attention is, therefore, drawn to this particular aspect of proper and
adequate curing.
p) Construction joints
Construction joints are a potential source of weakness and should
be located and formed with care and their number is kept to a
minimum. When the work is to be interrupted, the concrete shall be
rebated at the joint to such shape and size as may be required by
EMPLOYER o r as shown on the drawings. All vertical
construction joints shall be made with water bars which are rigidly
fixed and shall provide a positive barrier against movement of water
through the joint. Great care shall be taken when placing concrete
around water bars because the space is often congested. Concreting
shall be carried out continuously up to construction joints.
Construction joints, if not described on the drawings, shall be in
accordance with the following:
In a column, the joint shall be formed about 75 mm below the
lowest sofit of the beams framing into it, at the meeting points of
the columns and the raft, and at the point of contraflexure in the
CHAPTER 4: PROJECT IMPLEMENTATION
columns.
Concrete in a beam shall be placed throughout without a joint.
However, if the provision of a joint is unavoidable, the joint shall
be vertical and at the middle of the span.
A joint in a suspended floor slab shall be vertical at one of the
quarter points of the span and at right angle to the principal rein-
forcement.
Additional reinforcements and shear keys shall be provided at the
construction joints.
In forming a joint, concrete shall not be allowed to slope away to
thin edge. The locations of construction joints shall be planned by
the contractor well in advance of pouring and be approved by
EMPLOYER. Construction joints in foundation of equipment shall
not be provided without the approval of Authorized representative of
EMPLOYER.
5.19 INTERFACING
CHAPTER 4: PROJECT IMPLEMENTATION
5.20WATER SUPPLY
The Contractor shall be overall responsible for supply of water within switch
yard for firefighting, drinking purposes, construction purpose and other mis-
cellaneous purposes. The scope is also inclusive of installation of deep tube
well, construction of slow sand filter and ground storage tank, supply
and installation of distribution network pipe lines, supply and erection of
all overhead tanks, staging for OH tank wherever necessary, pipes, fittings
etc. required for the water supply to be taken from the terminal point to the
respective buildings. A scheme shall be prepared by the contractor indicat-
ing the layout and details of water supply which shall subject to the ap-
proval of EMPLOYER before actual start of work. Any extra bore holes re-
quired shall be within the scope of the contractor.
There shall be separate bore wells for the control room building and
colony quarters if required. There shall be pump houses for the bore wells
and approach road to the pump houses shall be provided.
There shall be one RCC type security booth near the main gate,
switchyard gate and as per master plan to be provided as per design and
drawing. The booth shall have also provision of sitting arrangement for
the guests and toilet. The shed shall be provided with telephone internal,
electrical lighting and ceiling fan facilities. There shall be provision of gate
lights. A portion of the shed shall be used for the guest who comes for
visit the sub-station. Adequate no. of aluminium doors and windows are
also to be provided. Necessary paintings as per standard are also to be
done.
5.22CAR PARKING SHED
CHAPTER 4: PROJECT IMPLEMENTATION
Shed for Car parking shall be constructed adjacent to all building depending
upon the space available and the requirement. Each unit for single car parking
shall be of minimum size 5.5m x 3 m with a plinth height of minimum 300
mm. The floor should be completed with pavers block with appropriate base,
which has to be joined with the approach or internal road. Shed structure shall
be constructed using Steel section by TATA of YST 310 Grade or equivalent
with RCC block as base. Shed roofing to be completed with PPGI sheet roofing
with minimum 0.6 mm thickness.
5.25RAINWATER HARVESTING
openings of sizes 0.7X0.7 meter shall be provided in the RCC cover slab
as shown in the drawing. An iron cover made of 5mm thick chequered
plate with hinges shall be provided in the openings. Galvanized M.S. rungs
of 20mm diameter at spacing of 300mm shall be provided in the wall of the
shaft below the opening of the RCC slab to facilitate cleaning of shaft.
A 300mm diameter bore well shall be drilled in the center of the shaft. The
depth of bore well shall be 5.0 meter more than the depth of the sub soil
water.
A 100mm diameter medium duty MS pipe confirming to IS 1161 shall be
lowered in the bore well keeping bail plug towards bottom of bore well.
The pipe shall have 1.58mm holes for 4.0- m e t e r length starting from
1.0 meter from bottom of bore well. Holes of 3.0mm dia. Shall be
provided for a length of 2.0 meter starting from the bottom level of coarse
sand and downwards. The overall length of the pipe shall be equal to the
total depth of the bore well plus depth of shaft.
Gravel of size 3mm to 6mm shall be filled around 100 dia MS pipe in
the bore well. The shaft shall be filled with 500mm thick layers each
from the bottom of shaft with boulders of size 50mm to 150mm, gravel
of size 5mm to 10mm, coarse sand having particle size 1.5mm to 2.0mm
and boulders of size not less than 200mm respectively.
Fire water Tank: This is a lump-sum item. The contractor shall be
required to complete the work in all respect as per requirement. All the
items including excavation, compaction, brick work, roof truss,
corrugated A.C. Sheet roofing, all types of miscellaneous steel internal
and external plastering, painting, etc. shall be deemed to be included
in this lump-sum water tank.
The system design and equipment shall conform in all respects to high
standard of engineering, design and workmanship and shall be capable
of performing in continuous commercial operation in a manner
acceptable to the owner.
5.26.2 STANDARDS :
CHAPTER 4: PROJECT IMPLEMENTATION
5.26.3
5.26.4 I) DEVIATIONS :
Normally the offer should be as per Technical Specification without any
deviation.
II) MODIFICATION:
If any modification felt necessary to improve performance, efficiency
and utility of equipment, the same must be mentioned in the
'Modification schedule' with reasons duly supported by documentary
evidences and advantages. Such modifications suggested may or may
not be accepted, but the same must be submitted along with Pre-Bid
Queries. The modifications not mentioned in Schedule will not be
considered.
The system shall be designed in such a way that the same can be
extended to protect two more 400 KV Transformer / Reactor to
be installed in future. However, design consideration shall be on the
basis of considering only one Transformer/Reactor of highest
MVA/MVAR rating will be on fire at a time. The system shall be
designed to have a suitable pressure and suitable water quantity/hr. at
the farthest transformer/reactor location as per approved layout
drawing.
Each Deluge Valve shall be provided with a local panel for the
purpose of manual electrical operation of the valve. Additionally,
latch is to be provided for local operation.
5.26.6 HIGH VELOCITY SPRAY NOZZLES (PROJECTOR):
Minimum set point of the heat detectors used in HVW Spray System
shall be specified by the Contractor. However, the optimum rating
shall be suggested by the Contractor as per the attainable maximum
and minimum temperature at site.
The whole system will be kept pressurized with the help of air vessel
of adequate capacity and two numbers jockey pumps & motors.
Jockey pump shall take care, if there is any minor leakage. One set of
which shall be provided by the contractor as standby. The pumps and
air vessel with all auxiliary equipment will be located in fire water
pump house.
The outdoor piping for the system in general shall be laid above
ground on concrete pedestals with proper clamping. However, at
road/ rail crossings, in front access of buildings, places where
movement of cranes / vehicles is expected and at any other place
where laying of pipe above ground is not advisable, the pipes shall
be laid underground. Such locations shall be finalised during
detailed engineering and after approval of all relevant substation
drawings.
a) Panel for motor driven fire water One no. to be located in fire water pump house.
pump
b) Panel for two nos. Jockey pump One no. to be located in fire water pump house
CHAPTER 4: PROJECT IMPLEMENTATION
c) Panel for 2 nos. battery charger One no. to be located in fire water pump house
and diesel engine driven fire
water pump
d) Annunciation panel One no. to be located in fire water pump house
e) Annunciation panel One no. to be located in Control room building –
applicable for 400KV Sub Station.
5.26.8.1Panel for motor driven fire water pump shall be provided with :
p
u
s
h
b
u
t
t
o
n
S
e
t
w
i
t
h
s
t
a
r
t
e
r
CHAPTER 4: PROJECT IMPLEMENTATION
i
n
d
i
c
a
t
i
o
n
lamp& thermal O/L relay
c) Indicating lamp with drive ON/OFF : 1 set.
5.26.8.3Annunciation Panel :
a) Indicating lamp showing power supply ‘ON’ and status
indication lamp for each motor.
b) Annunciation windows shall be as follows :
i) Electric motor driven fire water pump running :1
No.
CHAPTER 4: PROJECT IMPLEMENTATION
All the control and annunciation panel shall be subject to all routine
and acceptance tests as per relevant Indian Standard. Routine &
acceptance Test Reports are to be submitted to AEGCL.
All MCCBs, MCBs & Air Circuit Breakers shall be from one of the
following manufacturer’s
complying with technical specification & relevant IS & IEC
a) M/s Siemens
CHAPTER 4: PROJECT IMPLEMENTATION
b) M/s L & T
c) M/s ABB
d) M/s Schneider
c) Jockey Pump
Jockey pump shall start automatically when water pressure in
header fall, below the sets value. Jockey pump shall stop
automatically when the pressure is normal.
The engine shall be provided with fuel oil tank having adequate
capacity to hold sufficient fuel oil for a minimum of six (6) hours
of full load run. The fuel oil tank shall preferably be mounted
near the engine. No. fuel oil tank will be provided by the
AEGCL.
The fuel tank shall be designed in such a way that the sludge and
sediment settle down to the tank bottom and is not carried to the
injection pump. A small sump shall be provided and fitted with
drain plug to take out sludge/sediment and to drain oil. Adequate
hand holes (greater than 80 mm. Size) shall be provided to
facilitate maintenance.
Pipeline carrying fuel oil shall be gradually sloped from the tank
to the injection pump. Any valve in the fuel feed pipe between
the fuel tank and the engine shall be placed adjacent to the tank
and it shall be locked in the open position. A filter shall be
incorporated in this pipeline in addition to other filters in the fuel
oil system. Pipe joints shall not be soldered and plastic tubing
shall not be used. Reinforced flexible pipes may also be used.
The complete fuel oil system shall be designed to avoid any air
pocket in any part of the pipe work, fuel pump,
sprayers/injectors, filter system etc. No air relief cock is
permitted. However, where air relief is essential plugs may be
used.
The fire fighting main motor and standby motor shall be of 3 –phase 400 V
squirrel cage type induction motor and suitable for continuous duty in the
specified ambient temperature of 50°C. Rating of motor shall be decided by
the bidder as per stipulated norms of TAC and fire fighting system
requirement. Calculation of motor rating is to be furnished during detailed
engineering. Motors to be installed outdoor or semi-outdoor shall have hose
proof enclosure and shall be equivalent to IP –55 as per IS:4691. For indoor
type the enclosure shall be dust proof as per IS : 4691. Offered motors shall
be TEFC (totally enclosed fan cooled) type and suitable for full voltage
direct-on-line starting. Starting current at rated voltage shall not exceed six
times of the rated full load current subject to tolerance as per IS:325.
Maximum permissible temperature rise under running condition shall
be as per IS:325.
Motor shall be capable of running at 80% of rated voltage for 5
minutes with rated load commencing from hot condition and able
to develop rated full load torque for 1 second if supply voltage
drop to 70% of rated voltage.
Motor shall be capable of withstanding electro-dynamic stresses
and heating imposed if it is started at a voltage of 110% of the
rated voltage.
Rating plate with all particulars as per stipulation
of IS:325 is to be provided. All routine and
acceptance test reports are to be submitted.
After installation and commissioning at site, the motors along with
the driven equipment shall be subject to tests. If any
abnormality/defects observed during testing, necessary
rectification/replacement to be made free of cost.
The set point shall be selected after giving due consideration for
ventilating air-velocity and cable insulation. The set point shall be
adjustable.
Fire detectors shall be equipped with an integral LED, so that it
shall be possible to know which of the detectors has been operated.
The detectors, which are to be placed in the space above the false
ceiling or in the floor void, shall not have the response indicators
on the body but shall be provided with remote response indicators.
Smoke/heat detector system shall be provided with proper capacity
battery and battery charger for its operation during failure of
power.
5.26.21 GUARANTEE :
Electrical and mechanical characteristics shall be guaranteed by the
bidder. In case of failure of materials to meet the guarantee, AEGCL
shall have right to reject the material. Guaranteed Technical
particulars are to be submitted by the successful bidder during
detailed engineering along with submitted drawings / documents.
However, format for submission of GTP shall be handed over to
intending bidders at the time of sale of tender documents.
SCOPE
This specification covers the general design, materials, construction features, manufacture, shop
inspection and testing at manufacturer’s works, delivery at site, handling at site, installation, testing,
commissioning, performance testing and handing over of split air-conditioners (SAC).
The design, materials, construction, manufacture, inspection, testing and performance of window air
conditioners shall comply with all currently applicable statutes, regulations and safety codes in the
locality where the equipment is to be installed. The equipment shall also conform to the latest
applicable Indian or equivalent standards. Other international standards are also acceptable, if these
are established to be equal or superior to the listed standards. Nothing in this specification shall be
construed to relieve the CONTRACTOR of this responsibility.
CONSTRUCTION FEATURES
CABINETS
The split air-conditioners shall comprise of two components viz. indoor unit (IDU) and
condensing/outdoor unit (ODU), interconnected with refrigerant piping. Indoor unit shall house
air handling fan, cooling coil, insulated drain tray and filter. The unit shall be of heavy gauge
steel, corrosion resistant, finished with synthetic enamel paint and acoustically insulated with
resin bonded fiber glass or equivalent material. Suitable drain connection shall be provided for
removal of condensate collected inside the drain tray under cooling coil. The front panel shall be
decorative type with supply air grille of adjustable type and having adequate return air passage.
The front panel shall be made of plastic or aluminium and shall be easily removable for cleaning
of filter.
The unit shall be suitable for wall mounting and can also be ceiling suspended.
Condensing/outdoor unit shall house compressor and condenser and shall be of heavy gauge
corrosion resistant carbon steel and shall be suitable for mounting in open space (e.g. on terrace
or on outside wall).
COMPRESSOR
The compressor shall be hermetic scroll or rotary and shall be mounted on vibration isolators.
Necessary crank case heaters shall be provided. The power supply to the heaters shall be from an
auxiliary source so as to keep the power available even while the unit is switched off for routine
maintenance.
CONDENSER
The air-cooled condenser shall be with copper tubes and aluminium fins with low noise fan(s).
Speed of axial fan(s) shall not exceed 960 RPM for fan with impeller diameter above 450 mm
and 1440 RPM for fan with impeller diameter 450 mm and less. The impeller shall be statically
and dynamically balanced. Condenser coil shall have anti-corrosion treatment. The casing of the
condensing unit shall be given treatment to withstand harsh weather conditions of the ambient.
FILTER
The air, before it enters the cooling coil, shall be filtered by dry and cleanable type filters. The
filters shall include (either one or more of) anti-dust, deodorization, anti- bacterial and/or
ultraviolet types, as Specified.
Refrigerant piping, fittings and piping joints shall conform to the requirements ANSI B 31.5.
The piping shall be designed for an internal pressure representing the most severe condition of
coincident pressure and temperature expected in normal operation.
Vacuum testing shall be done for medium vacuum of around 40 mm Hg absolute and held with
vacuum pump in operation for at least 4 hours. Thereafter unit shall be sealed and vacuum held
for at least 12 hours. Vacuum break shall be done using refrigerant and pressure raised to
standing pressure in refrigerant cylinder.
ON-OFF thermostat with adjustable setting shall be provided for temperature control. A selector
switch enabling the running of air handling fan alone or fan with cooling shall be provided.
Interlock shall be provided such that compressor can start only after starting air handling fan.
Provision shall also be made to interlock the compressor with air cooled condenser fan motor.
Safety devices such as high/low refrigerant pressurestat (HP/LP) and compressor oil pressurestat
(OP), hermetic motor winding thermostat etc. shall be provided. HP and OP cut out shall be
manual reset while LP cut out shall be auto reset type.
Refrigerant and oil shall be supplied along with the unit. The refrigerant and oil charging shall be
carried out at site. Exposed refrigerant piping shall have anti- corrosive coating.
ELECTRICAL
This controller shall facilitate automatic periodic switching of the units from working to standby
mode in a predefined sequence so that all the units shall be in operation for a defined period of time.
This system shall be required in (N+1) OR (N+2) type combination of working & standby units.
The unit shall be provided with single phase preventers for all motors. Each SAC shall be provided
with three pin Plug and cable.
The indoor and outdoor units shall be pre-wired at the factory and shall be complete with starters for
all motors.
Wiring between indoor and outdoor units shall be carried out at site.
Cordless remote controller shall be provided. Remote controller shall have ON/OFF & temperature
control option.
6.2 LOUVERS
SCOPE
CHAPTER 6: AIR CONDITIONING SYSTEM
This specification covers the general design, materials, construction features, manufacture, shop
inspection and testing at manufacturer's works, delivery at site, handling at site, installation, testing
and commissioning at site of louvers required for fresh air intake and exhaust air outlets for air-
conditioning and ventilation systems.
CONSTRUCTION FEATURES
The louvers shall consist of parallel metallic blades. The louvers shall be provided with fixed type
blades or adjustable opening type blades.
The width and angle of blades shall be such as to minimize the entry of water and snow inside. The
minimum percentage of free area shall be 35% to 37%. The minimum projected width of blades in
horizontal plane shall be 150 mm with the blades inclined at minimum 35 degrees. The blades shall
be overlapping each other with maximum 30 mm height in vertical plane between two blades.
Blades shall be bent back at edges and ridged to provide stiffness and prevent water from travelling
up. Width of one bank of louvers shall be 1000 mm maximum. In case width is more, mullions shall
be provided to restrict width to less than 1000 mm. For adjustable type louvers, mechanism of blade
angle adjustment shall be designed in such a manner that maximum effort required shall not exceed
20 Kgf. The blade linkage rod shall be of cold rolled steel and minimum 8 mm diameter. The
number of blade linkage rod shall be one (1) for every 1000 mm width of louvers or part there-of.
The louvers shall be located at a minimum 350 mm height above the ground or roof level to
minimize the pick-up of dust and the probability of snow piling up and subsequently entering the
louver during winter operation. The louvers shall be located in such a manner that cross
contamination from other exhaust does not occur. Bird screen of 10 mm 2 and minimum 16 G wire
mesh shall be provided on outer face of louvers, wherever the louvers are exposed to atmosphere.
The frame of louver shall have a sill extension of 50 mm to provide drip ledge so that rainwater
drains outside.
The frame of louver shall have suitable framework for installation of filter and damper.
CHAPTER 6: AIR CONDITIONING SYSTEM
for 400 KV
system, 156 KV
rms for 220 KV
system & 92 KV
rms for 132
KV system
8 Minimum 13020 mm 7595 mm 4495 mm 1116 mm
creepage distance
@ 31 mm/KV
9 Min. Clearances
i Phase to spacing 7000 mm 4500 mm 3000 mm 1500 mm
for installation
ii Ground clearances 8200 mm 7000 mm 5000 mm 4000 mm
from lowest live
terminal of
equipment from
ground level
Rated short circuit 63 KA for 50 KA for 40 KA for 31.5
10 current /for three three seconds three three KA for
sec. duration seconds seconds three
seconds
11 System Neutral Effectively Effectively Effectively Effectively
earthing Earthed Earthed Earthed Earthed
Vol-II. The overall responsibility for compliance of ESMP will stand with the
Project Manager with support of Health and safety Specialist. The contractor
is abided to comply with the project specific ESMP which can be issued by
AEGCL to contractor during the complete tenure of project.
Within one month of award of contract the Contractor shall produce a HSE
Plan for the contract and submit for the approval of AEGCL. The HSE Plan
is described in the following sections. The same is to submit to CGM
(PP&D) and ESIA Consultant for approval.
The primary objective of the HSE Plan is for the contractor to demonstrate
that he has the capability to carry out the contract work in a cost effective
manner, giving due consideration to the Health, Safety and Environmental
and Social management of both his own employees, those of the Employer
and anyone who may be affected by his activities and in full compliance with
the ESMP.
Special arrangements shall be made to accommodate for gender-inclusive
engagements and participation of vulnerable people, to ensure the
implementation of the social development and gender relevant features
included in the design of the project, including monitoring of occupational
and community health and safety, community awareness activities,
compliance of core labour standards, prevention of Gender-based violence
(GBV) and Sexual exploitation (SE) risks.
• Working adjacent to, and in the vicinity of, live high voltage overhead
lines
• Working at elevation
• Lifting operations
• Use of explosives
• Use of heavy machinery including cranage, pile rigs and concrete
mixers
• Excavation works
• Work in confined spaces
• Working with insulating oil
• Working with compressed gas
• Rotating machinery
The Contractor should demonstrate his understanding of these hazards by
either proposing specific controls for each of them or by giving supporting
documentation which demonstrates that such controls already exist.
7.5 PROGRESS REPORTING
The Contractor shall submit for approval, within four weeks of the issue of letter
of award, an outline of the design, engineering, material procurement,
production, site mobilisation, man and machine deployment, delivery, erection,
testing, commissioning, and handing over programme as mentioned earlier.
Within a further period of 4 weeks the Contractor shall provide a detailed
programme scheduling the future activities in the form of Bar chart and/or any
other form to be agreed upon by AEGCL. The Contractor shall submit monthly
progress reports to AEGCL office not later than the fifth day of the following
month. The reports shall show clearly and accurately the position of all
activities associated with design, material procurement, manufacture, works
tests, shipping, site erection, testing and commissioning with regard to the
agreed contract programme. In addition to the routine monthly progress report
the Contractor shall also submit to AEGCL by the 25th day of every month, a
man hour schedule for the following month, detailing the man hours scheduled
for that month, skill-wise and area-wise. The preferred format for presentation
of programmes is MS Project version 4.0 or any latest. The programmes and
monthly updates shall be submitted on Email/CD/Hard copy. The design aspect
of the progress report shall include a comprehensive statement on drawing and
calculations submitted for approval. The position on material procurement shall
give the date and details of orders placed and indicate the delivery date quoted
by the manufacturer. If any delivery date has an adverse effect on the contract
programme the Contractor shall state the remedial action taken to ensure that
delays do not occur. The position on manufacture shall indicate the arrival of
material, the progress of manufacture and date at which the equipment will be
ready for transport. Any events that may adversely affect completion in the
manufacturer’s works shall also be reported. All works, tests executed shall be
listed and the test-results shall be remarked upon. Any test failures shall be
highlighted, and the Contractor shall detail the necessary steps taken in order to
CHAPTER 6: AIR CONDITIONING SYSTEM
avoid any adverse effect on the contract completion dates. The despatch of each
order shall be monitored on the progress report giving the date by which the
equipment will be available for transport, the estimated time of arrival on site
and the dates actually achieved.
The site works shall be segregated into civil, mechanical and electrical works
for reporting purposes and each section of the site works shall be monitored
giving the percentage completion and the estimated completion date in
accordance with the contract programme. The number of men working on site,
both labour and supervisory staff, shall be reported together with any incidents
or events that may affect the progress of site works.
Any delays which may affect any milestone or final completion dates shall be
detailed by the Contractor who shall state the action taken to effect contract
completion in accordance with the contract programme.
The contractor shall provide two copies of the progress report to AEGCL office.
All other activities listed in other sections of bid document also shall be
provided.
7.6. STANDARDS
Except where otherwise specified or implied, the Contract Works shall comply
with the latest edition of the relevant Indian Standards, International Electro
technical Commission (IEC) standards and any other standards mentioned in
this Specification. The Contractor may submit for approval, equipment or
materials conforming to technically equivalent National Standards. In such
cases copies of the relevant Standards or part thereof, in the English language
shall be submitted with the Tender. In case of conflict the order of precedence
shall be (1) IEC, (2) IS and (3) other alternative standard.
The supply and erection requirements and procedures to be followed during the
installation of the equipment shall be in accordance with the relevant
Indian/International Standards/Regulations, ASME codes, accepted good
engineering practice, drawings and other applicable Indian codes and laws and
regulations.
Reference to a particular standard or recommendation in this Specification does
not relieve the Contractor of the necessity of providing the Contract Works
complying with other relevant standards or recommendations.
The list of standards provided in the Chapter 1 of this Specification is not to be
considered exhaustive and the Contractor shall ensure that equipment supplied
under this contract meets the requirements of the relevant standard whether or
not it is mentioned therein.
7.7. LANGUAGE AND SYSTEM OF UNITS
The English language shall be used in all written communications between the
Employers, AEGCL and the Contractor with respect to the services to be
rendered and with respect to all documents and drawings procured or prepared
by the Contractor pertaining to the work, unless otherwise agreed by the
Employer.
It is required that danger plates, equipment designation labels or plates,
instruction notices on plant and general substation notices be written in English.
CHAPTER 6: AIR CONDITIONING SYSTEM
Control switch and lamp labels, indicator lamp and annunciator inscriptions
shall be in English only.
The design features of all equipment shall be based on the SI system of units.
7.8. MASS AND SIZE OF PARTS AND QUANTITIES OF OIL
The mass and dimensions of any item of equipment shall not exceed the figures
stated in the Schedules.
Each item shall be labelled to indicate its mass, quantity of oil (if any) and any
special handling instructions.
7.9. GENERAL REQUIREMENTS
7.9.1 Bolts and nuts
All bolts, studs, screw threads, pipe threads, bolt heads and nuts shall comply
with the appropriate national standards for metric threads, or the technical
equivalent.
Except for small wiring, current carrying terminal bolts or studs, for mechanical
reasons, shall not be less than 6 mm in diameter.
All nuts and pins shall be adequately locked.
Wherever possible bolts shall be fitted in such a manner that in the event of
failure of locking resulting in the nuts working loose and falling off, the bolt
will remain in position.
All bolts, nuts and washers placed in outdoor positions shall be treated to
prevent corrosion, by hot dip galvanising or electro galvanising to service
condition 4. Appropriate precautions shall be taken to prevent electrolytic action
between dissimilar metals.
Where bolts are used on external horizontal surfaces where water can collect,
methods of preventing the ingress of moisture to the threads shall be provided.
Each bolt or stud shall project at least one thread but not more than three threads
through its nut, except when otherwise approved for terminal board studs or
relay stems. If bolts and nuts are placed so that they are inaccessible by means
of ordinary spanners, special spanners shall be provided.
The length of the screwed portion of the bolts shall be such that no screw thread
may form part of a shear plane between members.
Taper washers shall be provided where necessary.
Protective washers of suitable material shall be provided front and back on the
securing screws.
7.10 Galvanising.
7.10.1. General
All machining, drilling, welding, engraving, scribing or other manufacturing
activities which would damage the final surface treatment shall be completed
before the specified surface treatment is carried out.
CHAPTER 6: AIR CONDITIONING SYSTEM
7.10.2. Galvanising
All metal surfaces shall be subjected to treatment for anti-corrosion protection.
All ferrous surfaces for external use shall be hot dip galvanised. High tensile
steel nuts, bolts and spring washers shall be electro galvanised to service
condition 4. All steel conductors including those used for earthing and
grounding (above ground level) shall also be galvanised according to IS 2629.
All galvanising shall be applied by the hot dip process and shall comply with IS
2629, IS 2633, IS 4759, IS 1367 or IS 6745.
All welds shall be de-scaled, all machining carried out and all parts shall be
adequately cleaned prior to galvanising. The preparation for galvanising and the
galvanising itself shall not adversely affect the mechanical properties of the
coated material.
The threads of all galvanised bolts and screwed rods shall be cleared of spelter
by spinning or brushing. A die shall not be used for cleaning the threads unless
specially approved by AEGCL. All nuts shall be galvanised with the exception
of the threads which shall be oiled. Surfaces which are in contact with oil shall
not be galvanised or cadmium plated.
Partial immersion of the work will not be permitted, and the galvanising tank
must therefore be sufficiently large to permit galvanising to be carried out by
one immersion.
Galvanising of wires shall be applied by the hot dip process and shall meet the
requirements of IS 2141.
The minimum weight of the zinc coating shall be 610 gm/sq. m. and minimum
thickness of coating shall be 86 microns for all items thicker than 5 mm. For
items of less than 5 mm thickness requirement of coating thickness shall be as
per BS 729. For surface which shall be embedded in concrete, the zinc coating
shall be a minimum of 800 gm/sq. m.
The galvanised surfaces shall consist of a continuous and uniform thick coating
of zinc, firmly adhering to the surface of steel. The finished surface shall be
clean and smooth and shall be free from defects such as discoloured patches,
bare spots, unevenness of coating, spelter which is loosely attached to the steel
globules, spiky deposits, blistered surface, flaking or peeling off, etc. The
presence of any of these defects noticed on visual or microscopic inspection
shall render the material liable to rejection.
After galvanising no drilling or welding shall be performed on the galvanised
parts of the equipment excepting that nuts may be threaded after galvanising.
Sodium dichromate treatment shall be provided to avoid formation of white rust
after hot dip galvanisation.
The galvanised steel shall be subjected to six one minute dips in copper sulphate
solution as per IS 2633.
Sharp edges with radii less than 2.5 mm shall be able to withstand four
immersions of the Standard Preece test. All other coatings shall withstand six
immersions. The following galvanising tests should essentially be performed as
per relevant Indian Standards.
CHAPTER 6: AIR CONDITIONING SYSTEM
• Coating thickness
• Uniformity of zinc
• Adhesion test
• Mass of zinc coating
Galvanised material must be transported properly to ensure that galvanised
surfaces are not damaged during transit. Application of zinc rich paint at site
shall not be allowed.
7.11. Cleaning, painting and topicalization
7.11.1. General
All paints shall be applied in strict accordance with the paint manufacturer’s
instructions.
All painting shall be carried out on dry and clean surfaces and under suitable
atmospheric and other conditions in accordance with the paint
manufacturer’s recommendations.
An alternative method of coating equipment such as with epoxy resin-based
coating powders will be permitted, subject to the approval of AEGCL, and
such powders shall comply with the requirements of IEC 455. The
Contractor shall provide full details of the coating process to AEGCL for
approval.
It is the responsibility of the Contractor to ensure that the quality of paints
used shall withstand the tropical heat and extremes of weather conditions
specified in the schedules. The paint shall not peel off, wrinkle, be removed
by wind, storm and handling on site and the surface finish shall neither rust
nor fade during the service life of the equipment.
The colours of paints for external and internal surfaces shall be in accordance
with the approved colour schemes.
7.11.2. Works painting processes
All steelworks, plant supporting steelworks and metalwork, except
galvanised surfaces or where otherwise specified, shall be shot blasted to BS
7079 or the equivalent ISO standard. All sheet steel work shall be degreased,
pickled, phosphated in accordance with the IS 6005 “Code of Practice for
phosphating iron and sheet steel”. All surfaces shall then be painted with one
coat of epoxy zinc rich primer, two pack type, to a film thickness of 50
microns. This primer shall be applied preferably by airless spray and within
twenty minutes but not exceeding one hour of shot blasting.
All rough surfaces of coatings shall be filled with an approved two pack
filler and rubbed down to a smooth surface.
The interior surfaces of all steel tanks and oil filled chambers shall be shot
blasted in accordance with BS 7079 or the equivalent ISO, and painted
within a period of preferably twenty minutes, but not exceeding one hour
with an oil resisting coating of a type and make to the approval of AEGCL.
CHAPTER 6: AIR CONDITIONING SYSTEM
Miscellaneous
19 Control modules and console inserts Smoke grey 692 Light grey 631
20 Lighting package equipment outside Light grey 631 Light grey 631
21 Lighting package equipment inside Glossy white Glossy
22 Water pipes sea green 217 white
sea green 217
23 Air pipes Sky blue 101 Sky blue 101
CHAPTER 6: AIR CONDITIONING SYSTEM
Colours shall be permanent and free from fading. Labels mounted on black
surfaces shall have white lettering. „Danger‟ plates shall have red lettering on a
white background.
All labels and plates for outdoor use shall be of non-corroding material. Where
the use of enamelled iron plates is approved, the whole surface including the
back and edges, shall be properly covered and resistant to corrosion. Protective
washers of suitable material shall be provided front and back on the securing
screws.
Labels shall be engraved in English. Name plates shall be white with black
engraved lettering and shall carry all the applicable information specified in the
applicable items of the Standards. Any other relevant information which may be
required for groups of smaller items for which this is not possible e.g. switch
bays etc. a common name plate in English and Assamese with the title and
special instructions on it shall be provided.
No scratching, corrections or changes will be allowed on name plates.
All equipment mounted on front and rear sides as well as equipment mounted
inside the panels shall be provided with individual name plates with equipment
designation engraved.
On the top of each panel on front as well as rear sides large name plates with
bold size lettering shall be provided for circuit/ feeder/ cubicle box designation.
All front mounted equipment shall be also provided, at the rear, with individual
name plates engraved with tag numbers corresponding to the one shown in the
panel internal wiring to facilitate tracing of the wiring. The name plates shall be
mounted directly by the side of the respective equipment wiring.
Name plates of cubicles and panels may be made of non-rusting metal or 3 ply
lamicoid. These name plates may be black with white engraved lettering.
The name plate inscription and size of name plates and letters shall be submitted
to AEGCL for approval.
The nameplates of the apparatus shall include, at least, the information listed
below, together with any other relevant information specified in the applicable
standards:
• Concise descriptive title of the equipment
• Rating and circuit diagrams
• Manufacturer's name, trademark, model type, serial number
• Instruction book number
• Year of manufacture
• Total weight (for capacitor racks indicate weight, for capacitors indicate
quantity of liquid)
• Name of the project.
Each measuring instrument and meter shall be prominently marked with the
quantity measured e.g. kV, A, MW etc. All relays and other devices shall be
CHAPTER 6: AIR CONDITIONING SYSTEM
7.14.1 Castings
7.14.1.1. General
All castings shall be true to pattern, free from defects and of uniform quality
and condition. The surfaces of castings which do not undergo machining,
shall be free from foundry irregularities. The castings shall be subject to
NDT, chemical, mechanical and metallographic tests. Details of the same
shall be furnished to AEGCL for review/approval. Magnetic particle
inspection (MPI) test, wherever applicable, shall be carried out in
longitudinal and transverse direction to detect radial and axial cracks.
7.14.1.2. Iron castings
Iron casting material shall be in accordance with ASTM A 126 Class B. A
copy of the ladle analysis shall be sent to AEGCL. Each casting shall have a
test bar from which tension test specimens may be taken. Test specimen shall
be in accordance with ASTM A 370 and tested in accordance with ASTM
E8. The Contractor shall submit his procedures for testing and acceptance for
iron castings for approval by AEGCL.
7.14.1.3. Steel castings
Steel castings shall be manufactured in accordance with ASTM A 27 and
shall be subjected to appropriate tests and inspection as detailed herein.
Copies of mandatory documentation, such as ladle analyses and mechanical
test results, shall be sent to AEGCL. (Non-ferrous casting material and
castings shall be manufactured in accordance with the appropriate ASTM
standards for the material concerned).
7.14.2. Forgings
When requested by AEGCL, forgings will be subjected to inspection in the
regions of fillets and changes of section by suitable method. Magnetic
particle, dye-penetration, radiographic or ultrasonic, or any combination of
these methods may be used to suit material type and forging design.
The testing is to be carried out after the rough machining operation and is to
be conducted according to the appropriate ASTM standards.
MPI test on forging shall be carried out to detect both radial and axial cracks.
Ferrous forgings shall be demagnetised after such tests.
Any indentations which prove to penetrate deeper than 2.5% of the finished
thickness of the forging shall be reported to AEGCL giving location, length,
width and depth. Any indentations which will not machine out during final
machining shall be gouged out and repaired using an approved repair
procedure.
Repair of rotating elements by welding will only be accepted subject to
detailed examination of the proposal by AEGCL prior to the repair being
carried out.
The forging shall be tested for mechanical and metallographic tests as per
ASTM. The details shall be mutually discussed/agreed upon.
CHAPTER 6: AIR CONDITIONING SYSTEM
with the requirements of the ASME “Boiler and Pressure Vessel Code”
Section VIII.
In addition to satisfying the procedural and quality requirements set forth in
the applicable code and/or these Specifications, all welding shall meet the
following requirements for workmanship and visual quality:
• Butt welds shall be slightly convex, of uniform height and shall have
full penetration.
• Fillet welds shall be of the specified size, with full throat and legs of
equal length.
• Repairing, chipping and grinding of welds shall be done in a manner
which will not gouge, groove or reduce the thickness of the base metal.
• The edges of the member to be joined shall expose sound metal, free
from laminations, surface defects caused by shearing or flame-cutting
operations or other injurious defects.
Welded joints subject to critical working stress shall be tested by approved
methods of non-destructive testing, such as radiographic and ultrasonic
examination, magnetic particle and liquid penetration inspection. All
expenses in connection with these tests shall be borne by the Contractor. The
extent of testing shall be as stipulated by the ASME “Boiler and Pressure
Vessel Code”, Section VIII, but without prejudice to the rights of the
Inspector or AEGCL to ask for additional tests,
The arc-welding process to be used and the welding qualifications of the
welders employed on the work shall be used in accordance with AWS
requirements and Section VIII and IX of the ASME (American Society of
Mechanical Engineers) Code, latest edition, as they may apply. All welding
rods shall conform to the requirements of the latest issue of Section It, part C
of the ASME Code.
Gas shielded welding (TIG or MIG) used as appropriate for aluminium,
stainless steel or other material shall be carried out in accordance with the
best commercial practice and the following standard specifications:
• Specifications for copper and copper-alloy welding rods (AWS A5.7,
ASTM B259)
• Specification for corrosion-resisting chromium and chromium-nickel
steel welding rods and bare electrodes (AWS A5.9, ASTM A371)
• Specifications for aluminium and aluminium alloy rods and bare
electrodes (AWS A5.10, ASTM B285).
• Specifications for nickel and nickel-base alloy bare welding filler metal
(AWS A5.14, ASTM B304).
Gas welding will not normally be used in the equipment. When a particular
equipment manufacture requires the use of gas welding, the proposed
process and the welder’s qualification shall be in accordance with AWS
B3.0. Welding of galvanised components will not be allowed in the
equipment. Strict measures of quality control shall be exercised throughout
the Equipment/ Works. AEGCL may call for an adequate NDT test of the
CHAPTER 6: AIR CONDITIONING SYSTEM
work of any operator, who in his opinion is not maintaining the standard of
workmanship. Should this NDT test prove defective, all work done by that
operator, since his last test shall be tested at the Contractor’s expense. If
three or more of these tests prove defective, the operator shall be removed
from the project. A procedure for the repair of defects shall be submitted to
AEGCL for his approval prior to any repairs being made.
7.14.4.3. Welding of pipes
Before welding, the ends shall be cleaned by wire brushing, filing or
machine grinding. Each weld-run shall be cleaned of slag before the next run
is deposited. Welding at any joint shall be completed uninterrupted. If this
cannot be followed for some reason, the weld shall be insulated for slow and
uniform cooling. Welding shall be done by manual oxy-acetylene or manual
shielded metal are process. Automatic or semi-automatic welding processes
may be done only with the specific approval of AEGCL. As far as possible
welding shall be carried out in flat position. If not possible, welding shall be
done in a position as close to flat position as possible. Downward technique
is not allowed while welding pipes in horizontal position, unless permitted
by AEGCL. Combination of welding processes or usage of electrodes of
different classes or makes in a particular joint shall be allowed only after the
welding procedure has been duly qualified and approved by AEGCL. No
backing ring shall be used for circumferential butt welds. Welding carried
out in ambient temperature of 5C or below shall be heat treated.
A spacer wire of proper diameter may be used for weld root opening but
must be removed after tack welding and before applying root run.
Tack welding for the alignment of pipe joints shall be done only by qualified
welders. Since tack welds form part of final welding, they shall be executed
carefully and shall be free from defects. Defective welds shall be removed
prior to the welding of joints.
Electrodes size for tack welding shall be selected depending upon the root
opening. Tack welds should be equally spaced.
Root run shall be made with respective electrodes/filler wires. The size of the
electrodes shall not be greater than 3.25 mm (10 SWG) and should
preferably be 2.3 mm (12 SWG). Welding shall be done with direct current
values recommended by the electrode manufacturers.
Upward technique shall be adopted for welding pipes in horizontally fixed
position. For pipes with wall thickness less than 3 mm, oxyacetylene welding
is recommended.
The root run of butt joints shall be such as to achieve full penetration with
the complete fusion of root edges. The weld projection shall not exceed 3
mm inside the pipe.
On completion of each run craters, weld irregularities, slag etc. shall be
removed by grinding or chipping.
During the process of welding, all movements, shocks, vibration or stresses
shall be carefully avoided in order to prevent weld cracks.
CHAPTER 6: AIR CONDITIONING SYSTEM
both ends of each wire. Ferrules shall fit tightly on the wire and shall not fall
off when the wire is disconnected from terminal blocks. Numbers 6 and 9
shall not be included for ferrules purposes unless the ferrules have numbers
underscored to enable differentiation. (i.e. 6 and 9).
Fuses and links shall be provided to enable all circuits in a cubicle, except a
lighting circuit, to be isolated from the bus wires.
The DC trip and AC voltage supplies and wiring to main protective gear
shall be segregated from those for back-up protection and also from
protective apparatus for special purposes. Each such group shall be fed
through separate fuses from the bus wires. There shall not be more than one
set of supplies to the apparatus comprising each group. All wires associated
with the tripping circuits shall be provided with red ferrules marked “Trip”.
It shall be possible to work on small wiring for maintenance or test purposes
without making a switchboard dead.
The insulation material shall be suitably coloured in order to distinguish
between the relevant phases of the circuit.
When connections rated at 380 volt and above are taken through junction
boxes they shall be adequately screened and “DANGER” notices shall be
affixed to the outsides of junction boxes or marshalling kiosk.
Where connections to other equipment and supervisory equipment are
required the connections shall be grouped together.
The above specification are general guidelines. If specific requirement is
made for individual items, that will supersede the above details.
7.15.2 LV power cabling
LVAC cable terminals shall be provided with adequately sized, hot pressed,
cast or crimp type lugs. Where sweating sockets are provided, they shall be
without additional clamping or pinch bolts. Where crimp type lugs are
provided, they shall be applied with the correct tool and the crimping tool
shall be checked regularly for correct calibration. Bi-metallic joints between
the terminals and lugs shall be provided where necessary.
Terminals shall be marked with the phase colour in a clear and permanent
manner.
A removable gland plate shall be provided by the Contractor. The Contractor
shall be responsible for drilling the cable gland plate.
Armoured cables shall be provided with suitable glands for terminating the
cable armour and shall be provided with an earthing ring and lug to facilitate
connection of the gland to the earth bar.
The above specification are general guidelines. If specific requirement is
made for individual items, that will supersede the above details.
7.15.3 Multi-core cables and conduit wiring
External multi-core cabling between items of main and ancillary equipment
shall form part of the Contract Works and shall consist of armoured multi-
CHAPTER 6: AIR CONDITIONING SYSTEM
core cable with stranded copper conductors PVC/XLPE insulated and PVC
over sheathed complying with the requirements of IEC 227 and 228 as
applicable.
Multi-core cable for instrumentation and control purposes shall be supplied
with 2.5 mm2 stranded copper cores. Multi-core cables for CT and VT
circuits shall be supplied with two by 2.5 mm2 stranded copper cores and the
cores shall be identified by the phase colour.
Where conduit is used the runs shall be laid with suitable falls and the lowest
parts of the run shall be external to the equipment. All conduit runs shall be
adequately drained and ventilated. Conduits shall not be run at or below
ground level.
Multi-core cable tails shall be so bound that each wire may be traced to its
cable without difficulty. All multi-core cables shall be provided with 20 %
spare cores and the spare cores shall be numbered and terminated at a
terminal block in the cubicle. Where cables are terminated in a junction box
and the connections to a relay or control cubicle are continued in conduit, the
spare cores shall be taken through the conduit and terminated in the cubicle.
The dc trip and ac voltage circuits shall be segregated from each other as
shall the circuits to main protective gear be segregated from those for back-
up protection.
The screens of screened pairs of multi-core cables shall be earthed at one end
of the cable only. The position of the earthing connections shall be shown
clearly on the diagram.
All wires on panels and all multi-core cable cores shall be crimped with the
correct size of crimp and crimping tool and will have ferrules which bear the
same number at both ends. At those points of interconnection between the
wiring carried out by separate contractors where a change of number cannot
be avoided double ferrules shall be provided on each wire. The change of
numbering shall be shown on the appropriate diagram of the equipment. The
same ferrule number shall not be used on wires in different circuits on the
same panels.
The Contractor shall provide a two (2) metre loop of spare cable at both ends
of all multi-core cable runs and shall leave sufficient lengths of tails at each
end of the multi-core cables to connect up to the terminal boards. The
Contractor shall also strip, insulate, ring through and tag the tails and shall
also seal the cable boxes. The Contractor shall be responsible for re-checking
the individual cores and for the final connecting up and fitting of numbered
ferrules within all equipment provided on this contract.
The drilling of gland plates, supply and fitting of compression glands and
connecting up of power cables included in the Contract scope of work shall
be carried out under this contract.
7.15.4 Laying and installing of cables
7.15.4.1. General
For cable laying the following shall apply:
CHAPTER 6: AIR CONDITIONING SYSTEM
IS standards.
The running of communications and power cables along the same route shall
be avoided as far as possible. Where this is not possible, they shall be
segregated, the one group from the other. Power and communication cables
shall be laid in separate tiers. For other than directly buried cables the order
of laying of various cables shall be as follows:
• Power cables on top tiers.
• Control/ instrumentation/Communication and other service cables in
bottom tiers.
7.15.4.3. Cable tags and markers
Each cable and conduit run shall be tagged with numbers that appear in the
cable and conduit schedule. The tag shall be of aluminium with the number
punched on it and securely attached to the cable conduit by not less than two
turns of 20 SWG GI wire conforming to IS 280. Cable tags shall be of
rectangular shape for power cables and of circular shape for control cables.
Location of cables laid directly in the ground shall be clearly indicated with
cable marker made of galvanised iron plate.
Location of buried cable joints shall be indicated with a cable marker having
an additional inscription "Cable joint".
Cable markers shall project 150 mm above ground and shall be spaced at an
interval of 30 meters and at every change in direction. They shall be located
on both sides of road and drain crossings.
Cable tags shall be provided on all cables at each end (just before entering
the equipment enclosure), on both sides of a wall or floor crossing, on each
duct, conduit entry and at every twenty meters (20 m) in cable tray/trench
runs. Cable tags shall be provided inside switchgear, motor control centres,
control and relay panels etc. and wherever required for cable identification
when a number of cables enter together through a gland plate.
The price of cable tags and markers shall be included in the installation rates
for cables/conduits quoted by the Bidder.
7.15.4.4. Cable supports and cable tray mounting arrangements in
control room
The control room will normally be provided with embedded steel inserts on
concrete floors/walls for the purpose of cabling in the control room. The
supports shall be secured by welding to these inserts or available building
steel structures. However, in cases where no such embedded steel inserts are
available, the same shall have to secured to the supports on walls or floors by
suitable anchoring.
7.15.4.5. Cable support structure in switchyard cable trenches
The contractor shall fabricate and install cable support structures in cable
trenches. These supports shall be provided at 750 mm spacing along the run
of cable trenches.
CHAPTER 6: AIR CONDITIONING SYSTEM
Cable supports and cable racks shall be fabricated from standard structural
steel members, channels, angles and flats of required size. The fabrication
welding and erection of these structures shall conform to the relevant clauses
of this Specification, in addition to the specification given herein.
7.15.5. Termination of cables and wires
Where cables leave the apparatus in an upward direction the cable boxes
shall be provided with a barrier joint to prevent leakage of cable oil or
compound into the apparatus. Where cable cores are liable to contact with oil
or oil vapour the insulation shall be unaffected by oil.
PVC sheathed cables shall be terminated by compression glands complying
with BS 6121 (or equivalent).
Auxiliary PVC insulated cables shall be terminated with compression type
glands, clamps or armour clamps complete with all the necessary fittings.
Colours shall be marked on the cable box, cable tail ends and single core
cables at all connecting points and/or any positions AEGCL may determine.
Cable boxes shall be provided with suitable labels indicating the purpose of
the supply where such supply is not obvious or where AEGCL may
determine.
All cables shall be identified and shall have phase colours marked at their
termination.
All incoming and outgoing connections shall be terminated at a terminal
block. Direct termination into auxiliary switches will not be accepted.
The above specification are general guidelines. If specific requirement is
made for individual items, that will supersede the above details.
7.16 DEGREES OF PROTECTION
Degrees of protection shall be provided in accordance with IEC 144 and
IEC 529 and be as follows:
• For outdoor applications, IP 55/ IP 65.
• For indoor applications where purpose-built accommodation is provided,
e.g. switch and control and relay rooms in auxiliary plant buildings, IP
41/42.
• Where dust can adversely affect equipment within the enclosure, this
equipment should be separately housed with a degree of protection of IP
51.
• For indoor applications where the equipment is housed in the same
building as that enclosing water and steam operated equipment, the
degrees of protection stated in the previous paragraph shall be up rated to
IP 44 and IP 54 respectively.
Where more severe environments exist, e.g. steam and oil vapour or other
deleterious chemical environments, special measures will be necessary, and
the degree of protection required will be specified separately.
CHAPTER 6: AIR CONDITIONING SYSTEM
The Contractor shall submit a schedule for providing the degree protection to
various control boxes, junction boxes etc. for AEGCLs approval.
The above specification are general guidelines. If specific requirement is
made for individual items, that will supersede the above details.
7.17 SUPPLY VOLTAGE
All incoming supplies of greater than 125V to earth shall have their
termination shrouded by a suitable insulating material.
The auxiliary supply voltages on site shall be as follows:
etc. to provide adequate protection to persons and property. The Contractor shall
be responsible for giving reasonable notice to AEGCL and the owners of public
or private property and utilities when such property and utilities are likely to be
damaged or injured during the performance of his works, and shall make all
necessary arrangements with such owners, related to removal and/or
replacement or protection of such property and utilities.
7.20 EMPLOYER'S SUPERVISION
To eliminate delays and avoid disputes and litigation, it is agreed between the
Parties to the Contracts that all matters and questions shall be referred to the
Employer and without prejudice the Contractor shall proceed to comply with the
Employer's decision.
The work shall be performed under the direction and supervision of AEGCL &
PMC. The scope of the duties of AEGCL, pursuant to the contract, will include
but not be limited to the following:
• Interpretation of all the terms and conditions of these documents and
specifications.
• Review and interpretation of all the Contractors drawing, engineering data
etc.
• Witness or authorise his representative to witness tests and trials either at
the manufacturer's works or at site, or at any place where work is
performed under the Contract.
• Inspect, accept or reject any equipment, material and work under Contract.
• Issue certificate of acceptance and/or progressive payment and final
payment certificates.
• Review and suggest modification and improvements in completion
schedules from time to time.
• Supervise the Quality Assurance program implementation at all stages of
the Works.
7.21 TESTING AND INSPECTION
7.21.1 General Conditions of Type Test.
The Contractor shall carry out the tests stated in accordance with the conditions
of this Specification, without extra charge for such additional tests as in the
opinion of AEGCL are necessary to determine that the Contract Works comply
with this Specification. The tests shall be carried out generally in accordance
with the relevant IEC’s or IS. However, in the absence of relevant regulations in
IEC / IS, other appropriate international standards may be accepted at AEGCL’s
discretion. The specific details of testing and inspection are given in the
appropriate section of this Specification.
The Contractor shall submit Type Test Reports for all equipment excluding GIS
being supplied by him (as per IEC standard) which, shall not be older than five
(5) years, as on date of bid opening for AEGCL’s approval. AEGCL may also
give instruction to carry out Type Tests, routine tests or acceptance tests. No
charges shall be paid by AEGCL for any Type Test.
CHAPTER 6: AIR CONDITIONING SYSTEM
duties. At least ten percent of all personnel assigned to site at any one time shall
be trained for firefighting.
The contractor shall provide sufficient fire protection equipment of the types
and sizes for the ware- houses, office temporary structures, labour colony area
etc. Access to such fire protection equipment shall be easy and kept open at all
time.
7.23 PACKING, SHIPPING AND TRANSPORT
The Contractor shall be responsible for the packing, loading and transport of the
plant and equipment from the place of manufacture, whether this is at his own
works or those of any Contractor, to Site, and for off-loading at site.
All apparatus and equipment shall be carefully packed for transport by air, sea,
rail and road as necessary and in such a manner that it is protected against
tropical climate conditions and transport in rough terrain and cross-country road
conditions. The method of packing shall provide complete protection to all
apparatus and equipment during transport and storage at site in heavy rain. The
method of packing shall provide adequate protection to main items of plant and
those parts contained within and attached without, for transportation.
Precautions shall be taken to protect parts containing electrical insulation
against the ingress of moisture.
All bright parts liable to rust shall receive a coat of anti-rusting composition and
shall be suitably protected. The machined face of all flanges shall be protected
by means of a blank disc bolted to each face.
Where appropriate all parts shall be boxed in substantial crates or containers to
facilitate handling in a safe and secure manner. Each crate or container shall be
marked clearly on the outside of the case to show “TOP” and “BOTTOM”
positions with appropriate signs, and where the mass is bearing and the correct
position for slings. Each crate or container shall also be marked with the
notation of the part or parts contained therein, contract number and port of
destination. It shall be the Contractor’s responsibility to dispose of all such
packing.
Any damage due to defective or insufficient packing shall be made good by the
Contractor at his own expense and within reasonable time when called upon by
AEGCL to do so. Four (4) copies of complete packing lists showing the
number, size, marks, mass and contents of each package shall be delivered to
AEGCL immediately after the material is despatched.
The Contractor shall inform himself fully as to all relevant transport facilities
and requirements and loading gauges and ensure that the equipment as packed
for transport shall conform to these limitations. The Contractor shall also be
responsible for verifying the access facilities specified.
The Contractor shall be responsible for all costs of repair or replacement of the
equipment, including those incurred by the Employer, arising from damage
during transport, off-loading or erection on site, until take-over by the
Employer.
The Contractor shall be responsible for the transportation of all loads associated
with the contract works and shall take all reasonable steps to prevent any
CHAPTER 6: AIR CONDITIONING SYSTEM
highways or bridges from being damaged by his traffic and shall select routes,
choose and use vehicles and restrict and distribute loads so that the risk of
damage shall be avoided. Any cost of claim towards damages, if any, caused to
Bridges and Highways during transportation of the materials shall be borne by
the contractor.
7.24 ERECTION MARKS
Before leaving the Contractor’s Works all apparatus and fittings shall be painted
or stamped in two places with a distinguishing number and/or letter
corresponding to the distinguishing number and/or letter on an approved
drawing and material list. All markings shall be legible; weatherproof tags,
where used, shall be durable, securely attached and duplicated.
The erection marks on galvanised material shall be stamped before galvanising
and shall be clearly legible after galvanising.
7.25 SPECIAL TOOLS & EQUIPMENTS
A complete set of spanners shall be supplied for each station to fit every nut and
bolt head on the apparatus supplied under this Contract, together with all special
tools required for the adjustment and maintenance of the equipment. These tools
shall be mounted in a lockable cabinet at each substation, also to be provided
under this Contract. Eye bolts which have to be removed after use shall be
accommodated in the cabinets.
Spanners and other maintenance equipment provided under the Contract shall
not be used for the purpose of erection of the contract Works.
Any special devices, slings or tackle necessary for the complete overhaul of the
plant shall be handed over to AEGCL in working order on completion of the
Contract.
On delivering any or all of these tools to AEGCL, a signature shall be obtained
from AEGCL’s representative. Any tools not signed for shall be deemed not to
have been delivered.
The above specification are general guidelines. If specific requirement is
made for individual items, that will supersede the above details.
7.26 RUNWAY BEAMS, EYE BOLTS AND LIFTING TACKLE
Runway beams shall comply with the requirements of BS 2853, or its
equivalent, and shall be tested after erection in accordance with this standard
and this Specification. The Contractor shall be responsible for the provision of
the appropriate test certificates which must be in accordance with Appendix C
of BS 2853.
All slings, eye bolts and other lifting tackle provided shall be proof tested to
twice the safe working load and suitably marked with embossed labels to show
clearly the safe working loads.
7.27 EARTHING SYSTEM
Electrical measurements of the subsoil at various depths up to 20 meters shall be
made at the site of each substation in order to determine the layered effects of
the ground from which the effective ground resistivity and hence the expected
CHAPTER 6: AIR CONDITIONING SYSTEM
Earth bars installed directly into the ground should normally be laid bare and the
trench backfilled with a fine top soil. Where the soil is of a hostile nature,
precautions must be taken to protect the earth bar.
All exposed joints shall be at a minimum height of 150 mm above floor or
ground level.
A facility shall be provided on the earth bar run between the equipment and the
base of the structure, comprising a looped copper strip (test link), so as to permit
the attachment of portable earth connections for maintenance purposes.
After installation of the earth system the Contractor shall measure the resistance
of the substation. The method used shall preferably be the "fall of potential"
method, requiring the availability of a local low voltage supply, but other
methods using an earth resistance meter will be acceptable in the event of a
local supply being unavailable.
The fencing of the switch yard also to be earthed by using G.I flats of size
75x10mm to each post and a continuous earth strip of size 50x6mm shall run all
through the fence. The periphery of the switch yard shall be provided with non-
treated earth pit at a distance of 5 mtrs all along the periphery. The size of the
non-treated pit conductor shall be 40 mm dia MS rod of length 3000mm. The
said earth MS Rod to be placed in earth pit as per standard practice and the pit
shall be filled with Bentonite powder mixed with lomy soil at a ratio 1:10. There
shall be provision of watering into the earth pits. A pipe of adequate size should
run all along the periphery and outlets shall be provided to each pit. The pipe
shall be connected to the overhead tank provided on the control room building
and proper water control valve should be provided. Contractor shall prepare a
detail earthing provision considering as per specification and shall obtain
approval from AEGCL and the top of the MS rod shall be welded to the buried
earth mats.
CONTRACTOR shall.
a) Assemble the transformers with all fittings such as bushings, cooler
banks, radiator, conservators, valves, piping, cables boxes, marshalling
boxes OLTC, cooling fans/pumps, etc.
b) Arrange for vacuum and oil filtration of the transformers. Oil filtration
shall be done as per the standard practice. Oil tanker in this effect are to
be used and filtration to be done while the oil is inside the tanker. On
getting the standard value of the oils the same shall be pushed into the
main tank and other portion of the transformer. Final filtration to be
done after entire oil is filled in the transformer. Prior to that vacuum
treatment of the tank of the transformer with the windings are to be
taken up.
c) Provide wedges/clamps to rigidly station all transformers on rails.
d) Connect up the transformer’s terminals.
e) Lay and terminate cables/ conduits between all the accessories mounted
on the transformer tank/cooler and the transformer-marshalling kiosk
and RTCC panels etc.
f) Pre commissioning checks shall be carried out as per relevant standards
and Employer’s instructions.
The CONTRACTOR shall arrange the oil filtration equipment.
Care shall be taken during handling of insulating oil to prevent ingress of
moisture or foreign matter. In the testing, circulating, filtering or otherwise
handling of oil, rubber hoses shall not be used, circulation and filtering of oil,
the heating of oil by regulated short-circuit current during drying runs and
sampling and testing of oil shall be in accordance with the
MANUFACTURER’S instructions and specified Code of Practice.
8.2.2 SWITCHGEAR, CONTROL/ RELAY PANELS
Switchgears and control relay panels/desks shall be installed in accordance
with specified Code of Practice and the Manufacturer’s instructions. The
switchgear panels shall be installed on finished surfaces or concrete or steel
sills. The CONTRACTOR shall be required to install and align and channel
sills which form part of the foundations. In joining shipping sections of the
switchgear/panels /control centers together with adjacent housing or panes
sections provided shall be bolted together after alignment has been
completed. Power bus, enclosures, ground and control splices of
conventional nature shall be cleaned and bolted together, being drawn up
with torque wrench of proper size or by other approved means. Tape or
compound shall be applied where called for by the MANUFACTURER’S
drawings.
The CONTRACTOR shall take utmost care in handling instruments. Relays
and other delicate mechanisms. Wherever the instruments and relays are
supplied separately, they shall be mounted only after the associated control
panel/desks have been erected and aligned. The blocking
materials/mechanism employed for the safe transit of the instruments and
relays shall be removed after ensuring that the panels/desks have been
CHAPTER 6: AIR CONDITIONING SYSTEM
i) The supplier shall install, test and commission the cables. Cables shall be
laid on cable trays and supports, in conduits and doctor or bare on walls,
ceiling, etc. as required. The supplier’s scope of work includes laying,
fixing, jointing, bending and terminating cables. The supplier shall also
supply necessary materials and equipment required for jointing and
terminating of cables. The supplier shall prepare detailed layout drawing
for cable trenches, cable tray layouts for approval by Employer and
construct cable routes strictly according to these drawings.
ii) Sharp bending, twisting and kinking of cables shall be avoided. The
bending radius for various types of cables shall not be less than those
specified by cable manufacturer.
iii) In each cable run, some extra length shall be kept at a suitable point to
enable one or two straight through joints to be made. Should the cable
develop fault at a later date.
iv) Cable joints in the middle of the run for control cables will not be an
accepted.
v) All cable terminations shall be made in a neat. Workmanlike manner.
Terminations shall be made for each type of wire or cable in accordance
with instructions issued by cable manufacturers and the Employer.
vi) Metal sheath and Armour of the cable shall be bounded to the earthing
system of the sub- station.
8.3.1. GENERAL REQUIREMENTS OF INSTALLATION FOR
CONDUITS, PIPES AND DUCTS.
i) The supplier shall supply and install conduits pipes (PVC thick but
flexible suitable for taking inside the roof and walls) and ducts as
necessary for the lighting system. All accessories/fittings required for
making installation complete. Including but not limited to ordinary and
inspection tees and elbows, check nuts, make and female reducers and
enlargers, wooden plugs, caps, squat headed male plugs, nipples, gland
sealing fittings, motion boxes, pull boxes, conduit outlets, outlet boxes,
splice boxes, terminal boxes, glands, gaskets and box covers, saddles and
all steel supporting work shall be supplied. Conduit fittings shall be of the
galvanized one. Flexible metallic conduits shall be used for termination of
connections to equipment such as motors or other apparatus to be
disconnected at periodic intervals.
ii) Conduits (thick and flexible PVC) and accessories shall be adequately
protected against mechanical damage as well as corrosion.
8.3.2. GENERAL REQUIREMENTS OF INSTALLATION FOR
EARTHING AND LIGHTNING PROTECTION SYSTEMS
8.4. SCOPE OF INSTALLATION
i) The supplier shall install steel conductors (GI flats) and braids, as required
for system and individual equipment earthing. All work such as cutting,
bending, supporting, painting coating drilling, brazing/soldering/welding,
clamping, bolting and connection on to structures, equipment frames,
terminals, rails or other devices shall be in the scope of work. All incidental
CHAPTER 6: AIR CONDITIONING SYSTEM
The owner may ask for such additional tests on site as in his opinion are
necessary to determine that the works comply with the specification,
Manufacturer’s guarantee/instructions or the applicable code of installation.
The CONTRACTOR shall carry out such additional tests also.
The CONTRACTOR shall perform operating tests on all switchgear and
panels to verify operation of switchgear/panels and correctness of the inter-
connections between various items of the equipment. This shall be done by
applying normal AC or DC voltage to the circuits and operating the
equipment for functional checking of all control circuits e.g. closing,
tripping, control interlock supervision and alarm circuits. All connections in
the switchgear shall be tested from point for possible ground or short circuit.
Insulation resistance tests shall be carried out by following rating megger:
a) Control circuits up to 220 V : By 500 V Megger
b) Power circuits, busbars : By 5000 Motor
connections for 132 KV. Operated Megger.
c) Power circuits, busbars : By 5000 V Motor
connections above 220 KV. Operated Megger.
The Employer’s authorized representative shall be present during every test
as called for by the EMPLOYER. The CONTRACTOR shall record all test
values and furnish the required copies of the test data to the EMPLOYER.
Electrical circuits and equipments shall be energized or used at nominal
operating voltage only after such reports have been accepted as satisfactory
by the EMPLOYER.
8.6. COMPLETION CHECKS
a) Name plate details according to approved drawings/ specifications.
b) Any physical damage or defect and cleanliness.
c) Tightness of all bolts, clamps and connections
d) Oil leakages and oil level.
e) Condition of accessories and their completeness.
f) Clearances.
g) Earthing connections.
h) Correctness of installation with respect to approved drawings/
specifications.
i) Lubrication Moving parts.
j) Alignment.
k) Correctness and condition of connections.
8.6.1 COMMISSIONING TESTS
CHAPTER 6: AIR CONDITIONING SYSTEM
9.1.0 SCOPE
9.1.1 This section of the specification covers the manufacture, testing at
manufactures works, erection and commissioning of indoor 33 KV, 13
panel switch boards which includes 33 KV circuit breakers with current
transformers, voltage transformers, local controls and instruments &
meters etc. and wired complete with all accessories as specified.
9.2.0 STANDARDS
9.2.1 The switchgear panels shall comply in all respects the requirement laid
down in the latest editions of IEC: 62271-200/100 unless otherwise
specified in this specification.
9.4.7 Plug and socket isolating Contacts for main power circuit shall be silver
plated, of self aligning type, of robust design and capable of
withstanding the specified short circuit currents. They shall preferably
be shrouded with an insulating material Plug and socket contacts for
auxiliary circuits shall also be silver plated, sturdy and of self-aligning
type having a high degree of reliability. Thickness of silver plating shall
not be less than 10 microns
9.5.2 All wires will be continuous from one terminal to the other and, also
will have no Tee-junction enroute. The connections shall be securely
made with the help of connecting lugs duly crimped on to the copper
conductor. The meters and relays shall be mounted in a convenient
position so as to be readily accessible for inspection or repair. The
terminal board provided in the instrument panel of VCBs will be made
of moulded dielectric having brass studs, washers, holding nuts &
locking nuts. All holding nuts shall be secured by locking nuts. The
connection studs shall project 6 mm from the lock nut surface. NO
OTHER TYPE OF TERMINAL BOARD IS ACCEPTABLE. The
panels shall have a degree of protection of IP-52. The leads from
metering CTs shall be directly terminated at TTB & there from at the
KWH meter with a provision to seal TTB and KWH meter. The said CT
leads will be concealed to prevent their tempering enroute. Similarly,
PT leads from secondary box of the PT to TTB & there from to energy
meter including inter panel PT leads will also be concealed to prevent
their tempering. The mode & extent of concealing the metering leads of
CTs & PTs to prevent their tempering (by unscrupulous operating
personnel) will be discussed & mutually agreed upon with the
successful bidder(s). TTB used on the instrument panel should
besuitable for front connections.
9.5.3 Earthing of current free metallic parts or metallic bodies of the
meters/switches mounted on the instrument panel and metal enclosed
switchgear shall be done by a suitably sized copper conductor. Earth bus
made of 25x8 mm bare copper flat will be extended through entire
length of 33 kV switch board with suitable provision to connect it to the
sub-station earth at the extremities. The earthing arrangement will meet
with the requirements laid down in IS: 3427read with its latest
amendment.
9.7.2 The circuit breaker shall be trip free and shall be provided with anti-
pumping device.
9.7.3 The vacuum type circuit breaker shall be draw out type & trip free. The
VCBs shall be suitable for operation from 220 V DC auxiliary supply.
The operating mechanism shall be motor operated spring charged type.
There shall be provision(s) for manual charging of closing spring and
emergency hand trip. The motor used for the purpose will be suitable
for 240 V AC as well as for 220 V DC. The operating mechanism shall
work satisfactorily at 85 % - 110 % of rated supply voltage. The VCB
shall have 4 normally open & 4 normally-closed auxiliary contacts over
& above the ones required for various control & supervision circuits.
9.7.4 The circuit breakers shall have following ratings and characteristics:
(i). Rated voltage: 36 KV
(ii). No. of poles: 3
(iii). Rated current: (a) 2500 Amps for
transformers & Bus section.
(b) 1600 Amps for
outgoing
(iv). Rated frequency: 50 Hz
(v). Rated breaking capacity:
(i) Symmetrical: 25 KA
(ii) Asymmetrical: As per IS: 13118
(vi). Rated breaking capacity: 2.5 times the rated
symmetrical breaking
capacity
(vii). Short time current rating: 31.5 KA for three
second
(viii). Rated voltage of operating device:
220 volts D.C
(ix). Operating mechanism: Motor operated spring
charged independent
spring closing
mechanism
(x). Impulse withstand voltage: 170 KV (Peak)
(xi). One-minute power frequency
withstand voltage: 70 KV (rms)
9.18.0 TEST
9.18.1 All routine tests shall be carried out in accordance with IS:
13118-1991(latest edition thereof).VCB and panel should be type tested
within 5 years of opening of tender from any of the following testing
laboratory: CPRI/ ERDA/ KEEMA/ KERI/ PHELA/ CESI/NABL
accredited laboratory.
9.19. TECHNICAL PARAMETERS
CHAPTER 6: AIR CONDITIONING SYSTEM
Table- (a)
2 No of Poles 3
2 Accuracy class
CHAPTER 6: AIR CONDITIONING SYSTEM
3 Rated Burden
4 Knee point voltage
5 Max. Secondary Resistance
Current Transformers for outgoing
(feeders)
6 Ratio
7 Accuracy class
8 Rated Burden
Current transformers for Bus Section
9 Ratio
10 Accuracy class
11 Rated Burden
POTENTIAL TRANSFORMERS
Rated voltage ratio 33000/110V
No. of phases 3 phases/star-star connected
Rated Burden 100/100/100 VA per phase
(micro-volt)
Corona Extinction Voltage
17 320 - - -
(kV)
18 Operating mechanism
a) Isolator Motor Motor Motor Motor
b) Earth switch Motor Motor Motor Manual
19 Auxiliary voltage
a) Control & Interlock 220V DC 80% to 110%
b) Motor voltage 3 Phase 415V AC 50Hz
c) Heater, lamp & socket Single phase 240 V 50HZ
20 Safe duration of overload
150% of rated current 5 minute
120% of rated current 30 minute
21 Minimum creepage distance of
insulator (mm)
22 Mounting structure Tubular Tubular Tubular Tubular
/ Lattice / Lattice / Lattice / Lattice
23 Operating time Less than 12 secs
24 Insulator Data
a) Bending Strength (kgf) 800 800 800 600
Type: 400 kV 220 kV 132 kV 33 kV
b) Height (mm) 3650 2300 1500 508
c) Bottom PCD (mm) 300 254 184 76
d) No. of holes & hole dia. 8x18 8x18 4x18 4xM12
e) Top PCD 127 127 127 76
f) No. of holes & hole dia. 4xM16 4xM16 4xM16 4xM12
g) Minimum creepage distance 13020 7595 4495 1116
(mm) 25mm/kV
25 Working clearance (live part to 8000 5900 4600 3700
ground) (in mm)
26 Phase Spacing (mm.) 7000 4500 3000 1500
27 Minimum clearances (mm.)
a) Phase to Phase 4000 2100 1300 320
b) Phase to earth 3500 2100 1300 320
c) Sectional clearance 6500 5000 4000 3000
SCOPE
This specification provides for design, manufacturer, testing at manufacturer’s
Works and delivery, supervision of erection, commissioning (if required) of
outdoor station type 400kV/220KV/132KV/ 33KV, 3 phase triple pole (as
mentioned above) Isolator with/ without earth switches, with electrical
interlock, insulators and complete in all respect with bimetallic connectors
arcing horns operating mechanism, auxiliary switches, indicating devices, fixing
detail etc. as described hereinafter.
10.1 STANDARDS
Disconnecting switches covered by this specification shall conform to latest
edition IEC-129/IEC 62271-102 I.S.1813 and IS: 9921, IS-325 and unless
specifically stated otherwise in this specification.
10.2 TYPE
CHAPTER 6: AIR CONDITIONING SYSTEM
The 400,220&132 KV Isolators shall be outdoor type with three phase centre
break type/Pantograph type as required [Single(SI)/ Double(DI)] Isolators
suitable for electrical as well as manual operation and local/ remote operation;
but 33KV Isolators (SI or DI) shall be outdoor type with three phase double
break center rotating manual as well as motor operated type with local
operation. They shall have crank and reduction gear mechanism.
All Isolators offered shall be suitable for horizontal upright mounting on steel
structures. Each pole unit of the multiple Isolators shall be of identical
construction and mechanically linked for gang operation.
Each pole of the Isolator shall be provided with two sets of contacts to be
operated in series and the moving contact blades shall rotate in horizontal plane.
The design shall be such that the operating mechanism with the linkages shall
be suitable for mounting on any of the outer pole ends without much difficulty
and with minimum shifting of parts.
Moving contacts of all isolators shall rotate through 90 deg. from their “fully
closed position” to “fully open position so that the break is distinct and clearly
visible from ground level.
The Isolators offered by the Bidder shall be designed for Normal rating current
for Isolator as follows:
It should suitable for continuous service at the system voltages specified herein.
The Isolators shall be suitable to carry the rated current continuously and full
short circuit current of 63/50/40/31.5 KA for 400/220/132/33 KV respectively
for 3 second at site condition without any appreciable rise in temperature. These
shall also be suitable for operation at 110% rated (normal) voltage. The Isolators
shall be suitable for Isolating low capacitive / inductive currents of 0.7amp at
0.15 power factor. The isolators shall be so constructed that they don’t open
under the influence of short circuit conditions.
The Isolators and earthing switches are required to be used on electrically
exposed installation and this should be taken into account while fixing the
clearance between phases and between phase and earth.
10.3 MAIN CONTACTS
All Isolators shall have heavy duty, self-aligning and high-pressure line type
contacts made of high conductivity, corrosion resistant, hard-drawn electrolytic
copper strips of proper thickness and contact area. Fixed contact should consist
of loops of above copper strips suitable for 4000 Amps, 3150 Amps, 2000
Amps, and 1250Amps ratings for 400kV, 220 KV, 132KV and 33KV Isolators
respectively. The hard dawn electrolytic copper strips should be silver plated
25micron thickness and fixed contacts should be backed by powerful phosphor
bronze/stainless steel springs of suitable numbers. The main contacts should be
preferably of tulip type design. However, the thickness and contact area of the
contact should conform to the drawing approved during type test. Moving
contact with moving arm should be of hard- drawn electrolytic copper of proper
thickness and contact area.
CHAPTER 6: AIR CONDITIONING SYSTEM
These fixed and moving contacts shall be able to carry the rated current
continuously and the maximum fault current of 63/50/40/31.5 KA for
400/220/132/33KV respectively for 3 seconds without any appreciable rise in
temperature. The Isolator blades shall retain their form and straightness under
all conditions of operation including all mechanical stress arising out of
operation as well as under rated short circuit condition.
Fixed guides shall be provided so that even when the blades are out of
alignment by one inch (maximum), closing of the switches, proper seating of the
blades in between contacts and adequate pressure to give enough contact surface
is ensured. Wherever possible, the blades shall be counter balanced by weights
and springs. The contact shall be self-cleaning by the wiping action created by
the movements of the blades. The surface of the contacts shall be tendered
smooth and silver plated (25 micron).
The Isolator shall be self-cleaning type so that when isolators remain closed for
long periods in a heavily polluted atmosphere, binding does not occur. No
undue wear or scuffing shall be evident during the mechanical endurance tests,
contacts and springs shall be designed so that adjustment of contact pressure
shall not be necessary throughout the life of the isolator. Each contact or part of
contacts shall be independently sprung so that full pressure is maintained on all
contact at all times.
10.4 ARCING HORN AND GRADING HORN
Suitable arcing horn made of tinned electrolytic copper which are required for
guiding contacts shall be provided on the fixed and moving contacts of all
Isolators. The contacts shall be of ‘make before and break after” type.
10.5 ELECTRICAL INTERLOCK / MECHANICAL INTERLOCK
The disconnecting switches whenever required shall be with an approved type
electrical interlock for interlocking with the associated circuit breakers and earth
switch. Electrical interlock assembly should be more right in construction and
properly mounted to ensure reliable operation. The design should be such that
the electrical circuit for the interlocking mechanism will only remain energised
during operation of the switches.
10.6. AUXILIARY SWITCHES
All isolators and earthing switches shall be provided with 220VDC auxiliary
switches for their remote position indication on the control board and for
electrical locking with other equipment. The auxiliary switch shall be provided
with a minimum of six auxiliary contacts- 10 normally open and 10 normally
closed and 10 normally open and 10 normally closed for earth switch. Separate
auxiliary switches shall be provided for isolating and earth switches. 6
additional NO and NC contact to be provided as spare in each case.
The auxiliary switches and auxiliary circuits shall have a continuous current
carrying capacity of at least 10 Amps. Auxiliary switches shall not be used as
limit switches. Details of make, rating and type of limit switch shall be
furnished in the offer.
10.7 EARTH SWITCH
CHAPTER 6: AIR CONDITIONING SYSTEM
Line earth switch shall consist of three earthing blades for Isolator which
normally rest against the frame when the connected Isolator is in closed
position. The earthing blades for three phases shall be mechanically linked to a
coupling shaft which shall be capable of being fitted on either side of the
Isolator. The earthing blades shall match and be similar to the main switch
blades and shall be provided at the hinge; with suitable flexible conductors with
terminal lugs for connecting to the station ground bus. The earthing blades shall
be operated by a separate mechanism but shall be mechanically interlocked with
the main switch so that the earthing blades can be closed only when the main
switches are in open position and vice-versa. The earthing blades shall be gang
operated and all the three blades will operate simultaneously.
10.8 OPERATING MACHANISM
The operating mechanism shall be simple and shall ensure quick and effective
1000 operation. The design shall be such as to enable one man to operate it with
nominal effort. The operating mechanism box shall be made out of aluminum
extruded (Aluminum alloy) sections of minimum 3.0 mm thickness. The
operating mechanism shall be strong rigid and not subject to rebound.
The Isolator blades shall be in positive continuous control throughout the entire
cycles of operation. The operating rods and pipes shall be rigid enough to
maintain positive control under most adverse conditions and to withstand all
torsional and bending stresses arising from operation. Operation of the switches
at any speed should not result in improper functioning, in displacement of parts /
machines after final adjustment has been made. All holes in cranks, linkages etc.
having moving pins shall be drilled and fitted accurately so as to prevent
slackness and lost motion.
Provision shall be made for padlocking the operating mechanism of
disconnecting and earth switches in both open and closed positions.
Bearings shall be ball and roller type shall be protected from weather and dust
by means of cover and grease retainers. Bearings pressures shall be kept low to
ensure long life and care of operation.
Each power operated isolator shall be motor driven as well as manually operated
and shall be complete with local / remote selector switch and open / close push
buttons. The function of all control facilitates operating isolators.
Provision shall be made in the control cabinet to disconnect power supply to
prevent local / remote power operation. Limit switches for open and close
positions of re-isolations and earth switches.
All the terminal blocks to be used in the operating mechanism should of stud
type of Poly-amide/Mealmine material of make like Elmex (OAT-6 for non
disconnecting type & OAT –6T for disconnecting type) / connectwell
(Equivalent).
10.9 DESIGN, MATERIALS AND WORKMANSHIP
The live parts shall be designed to eliminate sharp points, edges and similar
corona producing surfaces. Where this is impracticable, adequate shields to be
provided. All ferrous metal parts shall be hot dip galvanized, as per IS 2629.All
metal parts shall be of such materials or treated in such a way so as to avoid
CHAPTER 6: AIR CONDITIONING SYSTEM
Isolator, earthing switches and their operating devices shall be provided with
name plate. The name plate shall be weatherproof and corrosion proof. It shall
be mounted in such a position that it shall be visible in the position of normal
service and installation. It shall carry the following informations duly engraved
or punched on it.
A. Isolator Base
Name: AEGCL
Name of manufacturer –
Order No. –
Type Designation –
Manufacturers serial No. –
Rated voltage –
Rated normal current –
Rated short time current (rms) and duration –
Rated short time peak current (KAP)
Weight
B. Earthing Switch
Name: AEGCL
Name of manufacturer –
Order No. –
Type Designation –
Manufacturers serial No. –
Rated voltage –
Rated normal current –
Rated short time current (rms) and duration
Rated short time peak current (KAP)
Weight
C. Operating Device
Name – AEGCL
Name of manufacturer –
Order No.
Type Designation –
Reduction gear ratio –
AC motor
CHAPTER 6: AIR CONDITIONING SYSTEM
Six sets of the type test report, duly approved by the Purchaser shall be
submitted by the supplier for distribution, before commencement of supply
Adequate copies of acceptance and routine test certificates, duly approved by
the Purchaser shall accompany the dispatched consignment.
The manufacturing of the equipment shall be strictly in accordance with the
approved drawings and no deviation shall be permitted without the written
approval of the purchaser. All manufacturing and fabrication work in
connection with the equipment prior to the approval of the drawing shall be at
the supplier risk.
10.26 INSTRUCTION MANUALS:
Fifteen copies of the erection, operation and maintenance manuals in English to
be supplied for each type of disconnector one month prior to dispatch of the
equipment. The manual shall be bound volumes and shall contain all drawings
and information required for erection, operation and maintenance of the
disconnector including but not limited to the following particulars.
(a) Marked erection prints identifying the component parts of the
disconnector as shipped with assembly drawings.
(b) Detailed dimensions and description of all auxiliaries.
(c) Detailed views of the insulator stacks, metallics, operating mechanism,
structure, interlocks, spare parts etc.
10.27 PACKING AND FORWARDING:
The equipment shall be packed in crates suitable for vertical / horizontal
transport, as the case may be and suitable to withstand handling during transport
and outdoor storage during transit. The supplier shall be responsible for any
damage to the equipment during transit, due to improper and inadequate
packing. The easily damageable material shall be carefully packed and marked
with the appropriate caution symbols.
Wherever necessary, proper arrangement for lifting, such as lifting hooks etc.
shall be provided. Any material found short inside the packing cases shall be
supplied by supplier without any extra cost.
Each consignment shall be accompanied by a detailed packing list containing
the following information:
(a) Name of the consignee.
(b) Details of consignment.
(c) Destination.
(d) Total weight of consignment.
(e) Handling and unpacking instructions.
(f) Bill of material indicating contents of each package.
The supplier shall ensure that the bill of material is approved by the purchaser
before dispatch.
CHAPTER 6: AIR CONDITIONING SYSTEM
APPENDIX – I
(Isolators)
LIST OF SPECIAL TESTS TO BE CARRIED OUT IF DECIDED BY THE
PURCHASER
11.1.0 SCOPE
11.1.1 The brief description of scope of scope covered under this Bidding
Document is furnished below:
a) Design, manufacture, testing at manufacturer’s works and
supply of 800KVA, 500KVA and 250KVA 33/0.415 kV
Auxiliary Power transformers (Energy Efficiency level 3) with
all fittings and accessories as specified.
b) Loading at manufacturer’s works, transportation and delivery at
respective substation sites, including unloading at destination
sites.
c) Erection, Testing and Commissioning.
11.2.0 SERVICE CONDITIONS
11.2.1 The plant and materials supplied shall be suitable for operation under
the climatic conditions mentioned in chapter 2 of this bid document:
11.3.1 Equipment, which have never been type tested, shall not be
accepted. In such cases, a promise or agreement by a bidder to have
the equipment tested after award of a contract is not acceptable.
11.3.2 All Bids must be accompanied by the full Type Test Certificates of
equipment offered. Such type test certificates shall be acceptable only
if,
CHAPTER 6: AIR CONDITIONING SYSTEM
11.3.4 Type Test Reports older than five (5) years on the date of
Technical bid opening shall not be accepted.
ii) IS: 1180 (Part- Outdoor type Oil Immersed Distribution Transformers upto and
1):2014 including 2500 KVA, 33 kV – Specification.
(iii). IS: 335 Specification for Transformer Oil.
(iv). IS: 12444 Specification for Copper Wire Rod
(v). IS:3347 Specification for Porcelain Transformer Bushing.
(vi). IS: 2099 Specification for High Voltage Porcelain Bushings.
(vii). IS: 7421 Specification for Low Voltage Bushings.
(viii) IS: 9335 Specification for Insulating Kraft Paper.
(ix). IS: 1576 Specification for Insulating Press Board
(x). IS: 6600 Guide for Loading of Oil Immersed Transformers.
(xi). IEC: 60076 Specification of Power Transformer Outdoor.
11.5.2 TECHNICAL REQUIREMENTS
11.5.2.1 General
11.5.2.1.1 The Transformers shall be of outdoor, three phase, 50 Hz, oil
immersed, self-cooled and suitable for use in the geographic and
meteorological conditions as given in Clause 11.2.0. The
Transformers shall be suitable for mounting on RCC Pedestal.
11.5.2.1.2 The transformer shall be suitable for continuous operation with a
frequency variation of (+/-) 3% from normal 50 Hz. Combined
voltage and frequency variation should not exceed the rated V/f ratio
by 10%.
11.5.2.2 Core
11.5.2.2.1 The core shall be stacked type of high-grade cold rolled grain
annealed steel lamination having low loss and good grain properties,
coated with hot oil proof insulation, bolted together and to the frames
firmly to prevent vibration or noise. The complete design of core must
ensure permanency of the core losses with continuous working of the
transformers.
11.5.2.2.2 MS channel or plate shall be used on top and bottom. Channel frames
on LV side to be reinforced at equidistance, if holes / cutting are done
for LT lead in order to avoid bending of channel. MS channels/plate
frames shall be painted with hot oil-resistant varnish or paint.
11.5.2.2.3 The maximum flux density in any part of the core and yokes, of each
transformer at normal voltage and frequency shall be such that the
flux density with (+) 12.5% combined voltage and frequency
variation from rated voltage and frequency does not exceed 1.9 Tesla
(19,000 lines per cm2). The manufacturer shall furnish the design
calculation in support of flux density.
11.5.2.2.4 The transformers core shall be suitable for over fluxing (due to
combined effect of voltage and frequency) up to 12.5% without
injurious heating at full load conditions and shall not get saturated.
11.5.2.2.5 No load current shall not exceed 2% of full load current. Increase in
secondary voltage of 433 volts by 12.5% shall not increase the load
current beyond 5%.
11.5.2.3 Winding
CHAPTER 6: AIR CONDITIONING SYSTEM
11.5.2.7.1 The insulating oil shall comply with the requirements of relevant
standards IS 335. No inhibitors shall be used in oil.
11.5.2.8 Transformer Tank
11.5.2.8.1 The transformer tank shall be of robust construction, rectangular
plain tank type and shall be built up of tested MS sheet.
11.5.2.8.2 The internal clearance of tank shall be such that it shall facilitate easy
lifting of core with coils from the tank without dismantling LV & HV
bushings.
11.5.2.8.3 All joints of tank and fittings shall be oil tight and no bulging should
occur during service. The tank design shall be such that the core and
windings can be lifted freely. The tank plate shall be of such strength
that the complete transformers when filled with oil may be lifted
bodily by means of lifting lugs. Inside of tank shall be painted with
varnish / hot oil resistant paint.
CHAPTER 6: AIR CONDITIONING SYSTEM
11.5.2.8.4 The four walls of the tank shall be made of two “L” shaped sheets
(without joints) full welded at the corners from inside and outside of
the tank for withstanding a pressure of 0.8 kg/cm2 for 10 minutes.
11.5.2.8.5 The tank shall be reinforced by welded angle on all the outside
walls on the edge of the tank to form two equal compartments.
Permanent deflection when the tank without oil is subject to a vacuum
of 525 mm of mercury for rectangular tank and 760 mm of mercury
for round tank shall not be more than 5 mm upto 750 mm length and 6
mm upto 1250 mm length. The tank shall further be capable of
withstanding a pressure of 0.8 kg/sq cm (g) and a vacuum of 0.3 kg/sq
cm (g) without any deformation.
11.5.2.8.6 Pressed steel radiators shall be used for cooling. The transformer
shall be capable of giving continuous rated output without exceeding
the specified temperature rise. 4 Nos. welded heavy duty lifting lugs
of MS plate 8 mm thick (min) suitably reinforced by vertical
supporting flat welded edgewise below the lug shall be provided on
the side wall.
11.5.2.8.7 Top cover fixing shall be with Stainless Steel bolts and 6 mm
Neoprene bonded cork gasket conforming to IS 4253 part-II shall be
placed between tank and cover. The bolts outside tank shall have 2
flat washers & one spring washer.
All bolts/nuts/washers exposed to atmosphere shall be as follows:
a) Size 12 mm or below - Stainless Steel
b) Above 12 mm - Steel with suitable finish like electro
galvanized with passivation or hot dip
galvanized.
11.5.2.8.8 Conservator
Oil gauge and the plain or dehydrating breathing devise shall be fixed
to the conservator, which shall also be provided with a drain plug and
a filling hole (M30 normal size thread) with cover. The capacity of a
conservator tank shall be designed keeping in view the total quantity
of oil and its contraction and expansion due to temperature variations.
In addition, the cover of main tank shall be provided with an air
release plug to enable air trapped within to be released, unless the
conservator is so located as to eliminate the possibility of air being
trapped within the main tank.
(i) Oil level gauge with toughened glass with “minimum” and
‘maximum’ marking.
(j) De-hydrating breather.
(k) Pressure Relief device or explosion vent.
(l) One drain cum sampling valve.
(m) One filter valve on the upper side of the tank.
(n) Unidirectional flat rollers.
(o) Inspection hole.
(p) Terminal connectors for HV & LV.
(q) One 33 kV 400 Amps DO Fuse set.
(r) One LT 630 Amps MCCB of make preferably ABB/Schneider
(s) 3 numbers, 30kV Polymeric Lightning Arrestor of make
LAMCO/equivalent
(t) LA holder clamp with provision of earthing in HV side bushings,
3 numbers.
(u) Grounding material & accessories for earthing of transformer
neutral, transformer tank and LA.
11.5.3 TESTING AND INSPECTION
11.5.3.1 Inspection
(a) Physical and dimensional check of transformer tank and
accessories.
(b) Tank crack detection of major strength weld seams by dye
penetration test.
(c) Physical inspection and check of quality of varnish, if used in
core.
(d) Check on completed core for measurement of iron loss and check
for any hot spot by exciting the core so as to induce the designed
value of flux density in the core.
(e) Sample checks for physical properties of the insulating material.
(f) Check for dielectric strength of insulating materials.
(g) Sample check on winding conductor for mechanical properties
and electrical conductivity and on installation covering.
(h) Sample check on insulation paper used for windings for pH value,
Bursting strength, Electric strength.
(i) Check complete transformer against approved outline drawing
provision for all fittings, finish etc.
11.5.3.2 Factory Tests
All standard routine tests in accordance with IS: 1180 (Part-1), 2014
and latest issue of IS: 2026 shall be carried out on each transformer at
Manufacturer’s Works.
In addition to above standard Routine tests, following tests shall also
be carried out as Routine Tests for one number transformer of each
category of each Package:
(a) Temperature-rise test as per IS 2026.
(b) No load current at 112.5% of rated voltage.
(c) Pressure and Oil Leakage test. (on each transformer).
CHAPTER 6: AIR CONDITIONING SYSTEM
Sl.
DESCRIPTION PARAMETER
No.
I II III IV V
1 Rated Capacity, KVA 250kVA 500kVA 800kVA
2 Rated Voltage
(a) HV, kV 33 33 33
(b) LV, kV 0.433 0.433 0.433
3 RATED HV CURRENT 4.3Amps 8.7 Amps 13.99 Amps
4 RATED LV CURRENT 347.8A 695.6A 1071.6 A
Two Winding Two Winding Two Winding
5 Type of Winding
Transformer Transformer Transformer
6 Service Outdoor Outdoor Outdoor
7 No of Phases Three Three Three
8 Frequency, Hz 50 50 50
9 Type of Cooling ONAN ONAN ONAN
10 Impedance at 750 C, % 4.5 4.5 5
CHAPTER 6: AIR CONDITIONING SYSTEM
12.1.0. SCOPE
12.1.1. This Section covers the specifications for design, manufacture,
laboratory testing before dispatch at Station, delivery at site,
erection, testing and commissioning of class heavy duty, gapless
metal (zinc) oxide Surge Arrestors complete with fittings &
accessories for 400 kV, 220 kV, 132 kV and 33 kV systems.
12.2.0. STANDARDS
12.2.1. The design, manufacture and performance of Surge Arrestors shall
comply with IS: 3070 Part-3 / IEC: 60099-4 unless otherwise
specifically specified in this Specification
12.7.0. TESTS
12.7.1. Test on Surge Arrestors
The Surge Arrestors offered shall be type tested and shall be subjected
to routine and acceptance tests in accordance with IS: 3070 (Part-3). In
addition, the suitability of the Surge Arrestors shall also be established
for the following:
- Residual voltage test
CHAPTER 12: TECHNICAL SPECIFICATION FOR SURGE ARRESTER
I II III IV V VI
2 Rated frequency, Hz 50 50 50 50
13.3. STANDARDS:
13.3.1 The IVTs & CVTs shall conform in all respects to high standards of
Engineering, design, workmanship and latest revisions of relevant standards
at the time of offer and the Purchaser shall have the power to reject any work
or material which in his judgement is not in full accordance therewith.
13.3.2. Except to the extent modified in the specifications, the IVTS & CVTs
shall conform to the latest editions and the amendments of the standards
listed hereunder:
Sl.
Standard Ref. No. Title
No.
01 IEC-44(4) Instrument Transformer – measurement of PDS.
02 IEC-60 High voltage testing techniques.
03 IEC-171 Insulation co-ordination.
04 IEC-186 Voltage Transformers.
05 IEC-186(A) Voltage Transformers (first supp. to IEC-186)
06 IEC-270 Partial discharge measurement.
07 IS-335 Insulating oil for transformers and switchgears.
08 IEC-8263 Method for RIV Test on high voltage insulators.
09 IS-2071 Method of high voltage testing.
10 IS-2099 High Voltage porcelain bushings.
Degree of protection provided by enclosures for low voltage
11 IS-2147
switchgear and control.
12 IS-2165 Insulation co-ordination for equipments of 100KV and above.
13 IS-3156 (Part-I to IV). Voltage transformers.
14 IS-3347 Dimensions of porcelain transformer bushings.
15 IS-4146 Application guide for voltage transformers.
16 IS-5547 Application guide for Capacitor Voltage Transformers.
17 IS-9348 Coupling Capacitor & Capacitor Devices.
13.3.3 All the above along with the amendments thereof shall be read and
interpreted together. However, in case of a contradiction between the
Technical Specification and any other volume, the provisions of this
Technical Specification will prevail.
13.3.4. The voltage transformers with the requirements of other authoritative
standards, which ensure equal or better quality than the standards, mentioned
above shall also be acceptable. Where the equipments, offered by the
supplier conform to other standards, salient points of difference between the
standards shall be brought out in the offer. 4 (four) copies of the reference
standards in English language shall be furnished along with the offer.
13.3.5. The supplier is to furnish the standards as mentioned above from Sl.
1 to 17 at their own cost, if required by the purchaser.
13.4. CLIMATIC AND SERVICE CONDITIONS:
13.4.1 Earthquake Incidence:
CHAPTER 12: TECHNICAL SPECIFICATION FOR SURGE ARRESTER
The length of at least 15 mm shall be available on the studs for inserting the
leads.
13.6.1.4.9. Primary earthling link should be provided for measurement of
capacitance & di electric dissipation factor.
13.6.1.4.10. Separate point should be provided
13.6.1.5. Polarity shall be indelibly marked on each primary and secondary
terminal.
13.6.1.6. The IVT shall be vacuum filled with oil after processing and
thereafter hermetically sealed to eliminate breathing and to prevent air and
moisture from entering the tanks. Oil filling and/or oil sampling cocks, if
provided to facilitate factory processing should be properly sealed before
dispatching the IVT. The method adopted for hermetic sealing shall be
described in the offer.
13.6.1.7. The castings of base, collar etc. shall be die cast and tested before
assembly to detect cracks and voids, if any.
13.6.1.8. The characteristics of the IVTS shall be such as to provide
satisfactory performance such as voltage error and phase displacement at
rated frequency shall not exceed the values as per relevant standards at any
voltage between 80% and 120% of rated voltage and with burdens of
between 25% and 100% of rated burden at a power factor of 0.8 lagging. The
error shall be determined at the terminals of the IVT and shall include the
effects of any fuses or resistors as an integral part of the IVT.
13.6.1.9. Inductive voltage transformers shall be designed so as to achieve
the minimum risk of explosion in service. The bidder shall bring out in his
offer, measures taken to achieve this.
13.6.1.10. Primary Winding:
Primary winding of the IVT will be connected phase to neutral with the
neutral point solidly earthed. The arrangement for this shall be included in
the scope of supply. The primary conductor shall be of adequate cross-
section so that the maximum permissible current density shall not be
exceeded even during short-circuit conditions.
13.6.1.11. Secondary Winding:
Suitably insulated copper wire of electrolytic grade shall be used for
secondary windings. The secondary conductor shall be of adequate cross
section so that the maximum permissible current density shall not be
exceeded even during short- circuit conditions. Secondary windings details,
burden & accuracy class are mentioned in Appendix-I. Secondary windings
shall be used for metering, relaying and synchronizing. Each winding shall
comply requirements of both Part-II and III of up-to-date editions of IS-
3156/IEC-186.
13.6.1.12. Core:
Core laminations shall be of cold rolled grain-oriented silicon steel or other
equivalent alloys of low hysteresis and eddy current losses, high
permeability to ensure accuracy i.e. 0.2 accuracy class at both normal and
CHAPTER 12: TECHNICAL SPECIFICATION FOR SURGE ARRESTER
high over voltage. The core material, thickness of lamination, the relevant
graphs showing the characteristics of the core materials shall be submitted
along with the offer.
13.6.1.13. Tank:
13.6.1.13.1. Both expansion chambers and tanks of the IVT shall be made of
high-quality steel / Aluminum and shall be able to withstand full vacuum and
pressure, occurring during transit and thermal and mechanical stresses
resulting from maximum short circuit current during operation. The tanks
along with all ferrous parts shall be hot- dip galvanized as per relevant
standard.
13.6.1.13.2. The metal tanks shall have bare minimum number of welded
joints so as to minimize possible locations of oil leakage. Welding in
horizontal plane is to be avoided as welding at this location may give way
due to vibrations during transport resulting in oil leakage. Supplier has to
obtain specific approval from the purchaser for any horizontal welding, used
in the bottom tank
13.6.1.13.3. Paint inside the metallic housing shall be of anti-condensation
type.
13.6.1.14. Porcelain Housing:
13.6.1.14.1. The housing shall be made up of homogeneous, vitreous
porcelain of high mechanical and dielectric strength, glazing of porcelain
shall be of uniform brown or dark brown colour with a smooth surface,
arranged to shed away rainwater or condensed water particles (fog). The
details of location and type of joint, if provided on the porcelain, shall be
furnished by the Bidder along with the offer.
13.6.1.14.2. The bushings of the IVTS shall conform to latest edition of IS-
2099.The hollow porcelain insulators shall conform to the latest edition of
lS-5621
13.6.1.14.3. The insulators shall be cemented with Portland cement to the
flanges resulting in high mechanical, tensile and breaking strength
13.6.1.14.4. The bushings shall have ample insulation, mechanical strength
and rigidity for the condition under which they shall be used and shall be
used and shall be designed to prevent accumulation of explosive gases and
provide adequate oil circulation to remove the internal heat.
13.6.1.14.5. Cast metal and caps for the bushings shall be of high strength
hot dip galvanized malleable iron. They shall have smooth surface to prevent
discharge taking place between the metal parts and porcelain as a result of
ionisation.
13.6.1.14.6. The insulation of bushings shall be co-ordinated with that of the
IVT such that the flashover, if any, shall occur only external to the IVT.
13.6.1.14.7. Oil level gauge and convenient means of filling, sampling and
draining of oil shall be provided.
13.6.1.14.8. End shields should be provided for distribution of stresses.
CHAPTER 12: TECHNICAL SPECIFICATION FOR SURGE ARRESTER
removable gland plate at the bottom and shall be suitable for accepting the
required number of PVC insulated PVC sheathed, 10 core 2.5 mm² standard
copper conductor cable.
13.6.2.12.6. All terminals shall be clearly marked to facilitate connection of
secondary wiring.
13.6.2.12.7. Secondary fuses or MCBs shall be provided on or adjacent to
each CVT, located such that they are accessible while the primary is live and
shall be provided with labels indicating their function and their phase colours
CVT secondary circuits shall be complete in themselves and shall be earthed
at one point only. A separate earth link shall be provided for each secondary
winding and shall be situated at the CVT. Primary earhing links should be
provided.
13.6.2.12.8. Where CVTs are supplied which are or may be connected to
different sections of the bus bar, it shall not be possible for the CVT
secondary circuits, to be connected in parallel.
13.6.2.12.9. An auxiliary switch or relay shall be provided in each phase of
the secondary circuit of the synchronizing and metering voltage supply
connections to break the circuits automatically as soon as the circuit breaker
is opened.
13.6.2.12.10. To prevent ferro resonance, suitable damping devices shall
provide for connection to the transformer secondaries.
13.6.2.12.11. CVTs shall meet the requirements, given in this section of the
specification.
13.6.2.12.12. The creepage and flashover distances of the high voltage
insulator shall be suitable for the outdoor service conditions, specified in the
schedules.
13.6.2.12.13. The bidder in the offer is to state the suitable
precautions/methods, adopted during design stage of the CVT to avoid the
un-desirable effects due to ferro resonance phenomena. The
precautions/methods include lower level of working flux density in EMU,
greater utilization of the linear portion of the magnetization curve, providing
an air gap in the magnetic circuit, connecting a suitable damping resistance
permanently across the secondary etc.
13.6.2.12.14. It should be stated in the bid offer regarding the steps taken in
the design stage for elimination/minimization of the influence of the transient
response on the behaviour of high-speed relays.
13.6.2.12.15. It shall be ensured by the bidder in the offer that the connection
of carrier, frequency coupling device across the CVT will not affect the
designated accuracy class of the CVT windings.
13.6.2.12.16. The capacitor divider unit shall comply to IS: 9348/1979.
13.6.2.12.17. It shall also be complied in the offer through a calculation
sheet, proving that the designated accuracy class of the CVT (both metering
and protection) are not affected by extreme temperatures, to be encountered
in service conditions (Max. ambient temperature 50º C and minimum -0º
CHAPTER 12: TECHNICAL SPECIFICATION FOR SURGE ARRESTER
13.13 APPENDIX – I.
TECHNICAL REQUIREMENTS FOR 33kV, 132kV & 220kV INDUCTIVE
VOLTAGE TRANSFORMERS & 132kV, 220kV, 400kV CAPACITIVE
VOLTAGE TRANSFORMER.
Sl. 400kV/220kV
Particulars 33kV IVT 132kV IVT 132kV CVT
No. CVT
I II III IV V VI
Single phase, 50Hz, Single phase, Single phase,
Single phase, 50Hz,
oil filled, self- 50Hz, oil Filled, 50Hz, oil Filled,
oil filled, self-
cooled, self-cooled, self-cooled,
1 Type cooled, Hermetically
Hermetically Hermetically Hermetically
sealed, outdoor
sealed, outdoor sealed, Outdoor sealed, Outdoor
porcelain type.
porcelain type. porcelain type. porcelain type.
Nominal
2 33kV 132kV 132kV 400 kV/220kV
system voltage.
Highest system
3 36kV 145kV. 145kV 420kV/245kV
voltage.
4 Frequency. 50Hz± 5% 50Hz± 5% 50Hz ± 5% 50Hz± 5%
System Effectively solidly Effectively solidly Effectively solidly Effectively solidly
5
earthing. earthed earthed earthed. earthed.
Number of
6 3 [single phase] 3 [single phase] 3 [single phase] 3 [single phase]
phases.
(i) Number of 3 [three] 3 [three] 3 [three] 3 [three]
secondary
7 windings.
(ii) Purpose of Protection & Protection & Protection & Protection &
windings. metering. metering. metering. metering.
Rated primary 400/1.732 kV
8 33/1.732kV 132/1.732kV 132/1.732kV
voltage. 220/1.732 kV
Winding-II &III- Winding-II &III- Winding-I- Winding-I-
110/1.732V 110/1.732V 110/1.732V 110/1.732V
Rated
(Protection) (Protection) Winding-II- Winding-II-
9 secondary Winding-I-
Winding-I- 110/1.732V 110/1.732V
voltage. 110/1.732V 110/1.732V Winding-III- Winding-III-
(Metering) (Metering) 110/1.732V 110/1.732V
400kV/1.732:
110V/1.732,
33kV/1.732: 132kV/1.732: 132kV/1.732:
110V/1.732
10 Ratio 110V/1.732 110V/1.732 110V/1.732
220kV/1.732:
110V/1.732 110V/1.732 110V/1.732 110V/1.732
110V/1.732
Winding-I(M)- Winding-I(M)- Winding-I (M)- Winding-I (M)-
100VA 100VA 100VA 100VA
Winding-II(P)- Winding-II(P)- Winding-II (P)- Winding-II (P)-
11 Rated burden.
100VA 100VA 100VA 100VA
Winding-III(P)- Winding-III(P)- Winding-III(P)-
Winding-III(P)-
100VA 100VA 100VA 100VA
12 Accuracy class 0.2/3P/3P 0.2/3P/3P 0.2/3P/3P 0.2/3P/3P
13 Rated voltage 1.2 continuous. 1.2 continuous. 1.2 continuous. 1.2 continuous.
factor at rated 1.5 for 30second. 1.5 for 30second. 1.5 for 30second. 1.5 for 30second.
CHAPTER 13: TECHNICAL SPECIFICATION FOR IVT & CVT
frequency.
Temperature
rise at 1.2 times
the rated
primary
14 As per IEC- 186. As per IEC-186. As per IEC- 186 As per IEC-186
voltage, rated
frequency
& rated
burdens.
Temperature
rise at 1.5 times
the rated
15 primary voltage As per IEC- 186. As per IEC-186. As per IEC- 186. As per IEC-186.
for 30 seconds,
rated frequency
& rated burden.
One-minute
power
frequency dry
650kV[rms]/
16 withstands test 70kV[rms] 275kV[rms] 275kV[rms]
460kV[rms]
voltage for
primary
winding.
1-minute power
frequency wet
withstands test 650kV[rms]/
17 70kV[rms] 275kV[rms] 275kV[rms]
voltage for 460kV[rms]
primary
winding.
1.2/50 micro
second impulse
withstand test 1425kV[peak]/
18 170kV[peak] 650kV[peak] 650kV[peak]
voltage for 1050kV[peak]
primary
winding
One-minute 3kV[rms] 3kV[rms] 3kV[rms] 3kV[rms]
power
frequency
19 withstands test
voltage for - - 10kV[rms] for 10kV[rms] for
(i) Secondary exposed terminals exposed terminals
winding & 4kV[rms] for & 4kV[rms] for
terminals, terminals,
enclosed in a enclosed in a
Between weatherproof box. weatherproof box.
(ii) LV(HF)
terminal
& earth
terminal
Class of
20 ‘A’ ‘A’ ‘A’ or better ‘A’ or better
insulation.
21 Material of the Copper. Copper. Copper for EMU Copper for EMU
conductor of
primary and
CHAPTER 13: TECHNICAL SPECIFICATION FOR IVT & CVT
secondary
windings.
Fault level of
the bus to 31.5kA [rms] for 3 40 kA [rms] for 3 40 kA [rms] for 3 63/50kA [rms] for
22
which PTs will second. second. second. 3 second.
be connected.
Minimum
13020/7595
23 creepage 1116mm 4495mm 4495 mm
mm
distance.
EHV Grade As per EHV Grade As per EHV Grade EHV Grade As per
24 Quality of oil.
IS-335. IS-335. As per IS- 335. IS-335.
Radio
interference
voltage at 1.1
25 500 micro volts. 500 micro volts. 500 micro volts.
times maximum
rated voltage at
1.0 MHZ.
Partial Less than 10 Less than 10 Less than 10
26
discharge level. piccocoulombs. Piccocoulombs. piccocoulombs.
Seismic
acceleration 0.3g. 0.3g. 0.3g. 0.3g.
27
Horizontal – 0.15g. 0.15g. 0.15g. 0.15g.
Vertical –
Accuracy class
of standard
V.T. to be used
during testing
towards
28 determination 0.05 or better. 0.05 or better. 0.05 or better. 0.05 or better.
of ratio errors
and phase angle
errors for
metering
windings.
4400 (for 220kV),
Capacitance 4400 + 10%, 4400/6600 (for
29. -
(Pf) -5% 400kV)
+ 10%, -5%
CHAPTER 13: TECHNICAL SPECIFICATION FOR IVT & CVT
b) The Control and Relay Panels required are for control and protection of
the Power Transformers and Feeders according to requirements. The
supply shall include all accessories, special tools, supporting steels, spare
parts, drawings, relevant software, instruction manuals etc. The panels
shall be supplied complete with all accessories as specified and
completely assembled and all internal wiring completed.
c) The sub-stations shall have automation as per IEC 61850 protocol in Bay
& Station level. The bidder has to supply the C&R panels to match the
requirement of Sub-station Automation System (SAS) as specified in the
subsequent chapter, from the same manufacturer.
e) Design and fabrication of Control & Protection Panels for mounting the
relay and relay assemblies along with all necessary accessories like
switches, indicating lamps etc. and wiring up of the same to provide self
contained and ready to use protection as per this specification.
14.2 STANDARDS:
All equipment and all component parts supplied under this specification shall
conform in all respects to the latest issue of relevant IEC and Indian Standard
Specifications except where specified otherwise in this specification. Equipment
meeting any other authoritative standards which ensure an equal or better
quality may also be acceptable.
The plant and materials supplied shall be suitable for operation under the
following climatic and other conditions as mentioned in chapter 2 of this Bid
document:
iii) Type Test Reports older than five (5) years (for panel and Energy
meter) and older than seven (7) years (for Relays and BCU) on the date
of Technical bid opening shall not be accepted.
14.5.4 In case of Duplex panel, all control functions including BCU and
Energy meters shall be provided in front of the panel. The protective relays and
all other equipment may be provided on the back of panel with swing door
covered with glass door. All type of local communication ports of relays shall
be accessible from front or without opening the panel door. The height & width
of panel shall be as per clause 14.5.3 with restriction of width i.e. 800 mm only.
14.5.5 For 33kV feeder, panel shall be of simplex type and it should
accommodate one 33kV feeder in
a single cubicle and one BCU will control single 33kV feeder.
d) All doors, removable covers and panels shall be sealed all around with
synthetic rubber gaskets Neoprene/EPDM generally conforming to
provision of IS 11149. However, XLPE gaskets can also be used for fixing
protective toughened glass doors. Ventilating louvers, if provided shall
have screens and filters. The screens shall be made of either brass or GI
wire mesh.
e) Panels shall have additional rolled channel plinth at the bottom with
smooth bearing surface. The panels shall be fixed on the embedded
foundation channels with intervening layers of anti-vibration strips made of
shock absorbing materials which shall be supplied by the contractor.
i) All circuits except instrument transformers circuits: 1.5 sq. mm. per
lead.
ii) Instrument transformers circuit: 2.5 sq. mm. per lead.
d) Wire terminals shall be made with solder less clamping type of tinned
copper lugs, which firmly grip the conductor and insulation. Insulated
sleeves shall be provided at all the wire terminations. Engraved core
identification plastic ferrules marked to correspond with panel wiring
diagram shall be fitted at both ends of each wire. Ferrules shall fit tightly
on the wires and shall not fall off when the wire is disconnected from
blocks.
e) Interconnections to adjacent panels shall be brought out to a separate set
of terminals blocks located near the slots or holes meant for taking the
interconnecting wires. Arrangement shall permit easy interconnection to
adjacent panels at site and wires for this purpose shall be provided by the
supplier looped and bunched properly inside the panel.
f) A laminated copy of total schematics is to be fixed on the inside of door.
14.10 PAINTING:
a) All Sheet steelwork shall be phosphated in accordance with IS 6005.
b) Oil grease, dirt and warp shall be thoroughly removed by emulsion
cleaning. Rust and scale shall be removed by pickling with dilute acid
followed by washing with running water, rinsing with slightly alkaline
hot water and drying.
c) After phosphating, thorough rinsing shall be carried out with clean water
followed by final rinsing with dilute dichromate solution and oven drying.
The phosphate coating shall be sealed with application of 2 (two) coats of
ready mixed, stoving type zinc chromate primer. The first coat may be
‘flash dried’ while the second shall be stoved.
d) After application of the primer, two coats of finishing synthetic enamel
paint shall be applied, each coat followed by stoving. The second
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
14.13 EARTHING:
a) All panels shall be equipped with an earth bus securely fixed along with
inside base of the panels. The materials and the sizes of the bus bar shall
be at least 25X4 mm copper. When several panels are mounted joining
each other, the earth bus shall be made continuous and necessary
connectors and clamps for this purpose shall be included in the scope of
supply. Provisions shall be made for extending the earth bus bar to future
adjoining panels on either side.
b) All metallic cases of equipment shall be connected to the earth bus by
independent copper wires of size not less than 2.5 sq. mm. Earthing wire
shall be connected on terminals with suitable clamp connectors and
soldering shall not be permitted.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Frequency : 50 Hz ± 5%
The bidder can also offer meters which can withstand higher variations.
14.15.3 ACCURACY:
The class of accuracy of the meter shall be 0.2s.
14.15.4 POWER CONSUMPTION:
The active and apparent power consumption on each voltage circuit
including power supply of the meter at ref. Voltage, temperature and
frequency shall not exceed the limits as per IS: 14697
The apparent power drawn by each current circuit of the meter shall not
exceed as per IS 14697 of basic current, reference frequency and reference
temperature
14.15.5 STARTING CURRENT:
The meter shall start registering energy at 0.1% of basic current at unity
power factor.
When the voltage is applied with no current flowing in the current circuit, the
meter shall not register any energy and the test output of the meter shall not
be more than 1 pulse per count on no load.
14.15.6 MAXIMUM CONTINUOUS CURRENT:
The maximum continuous current in meters shall be 120% of rated basic
current (Ib) at which the meter purports to meet the accuracy requirements as
per the relevant standards.
14.15.7 CONNECTIONS:
The meters shall be suitable for being connected directly through its terminal
block to
i) Single phase AC auxiliary power supply or DC supply,
ii) Secondary of Voltage Transformers, and
iii) Secondary of Current Transformers.
14.15.8 AUXILIARY POWER SUPPLY:
The meters shall be capable of being powered up with standard 230 volts, 50
Hz AC and 110 volts or 220 volts DC auxiliary power supplies of the
substations so that metering core of PT is not loaded.
14.15.9 TEST TERMINAL BLOCK:
The meter shall be provided with a test blocks for testing without disturbing
the CT and PT secondary connections. Meter shall have digital display.
14.15.10 General & Constructional Requirements
14.15.11 GENERAL:
Metering equipment shall be of draw out type modular metering units with
facility of automatic CT short-circuiting. When a meter is drawn out of its
case, the CT secondary should get short-circuited automatically.
The meter should be housed in a safe, high grade engineering plastic /
polycarbonate casing, and is dust/moisture proof, conforming to IP-55 of BIS
12063 / IEC 529, vermin proof and sturdy.
14.15.12 Terminal Block:
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
The terminal block shall be made out of high grade non-hygroscopic, low
tracking, properly fire resistant, reinforced high grade engineering plastic
and designed according to adequate rating requirement conforming to
relevant standards and having provision for sealing.
14.15.13 Sealing of Meter:
Reliable sealing arrangement should be provided to make the meter tamper
proof and avoid fiddling or tampering by unauthorized persons.
14.15.14 Nameplate Marking of the Meter:
Meters shall have a name plate clearly visible and effectively secured against
removal, indelibly and distinctly marked with all essential particulars as per
relevant Standards.
14.15.15 Quantities to be Measured
The meter shall be capable of measuring and displaying the below mentioned
electrical quantities within specified accuracy limits for poly-phase balanced
or unbalanced loads at all power factors.
The measurements shall be carried out on 3 phase, 4 wire principle within an
accuracy as per 0.2s class of IS: 14697.
(i) Active energy measurement in all four quadrants
(import / export at all power factors). The meter shall compute the
active energy and load import, active energy and load export during
each successive 15/5 minutes block and store it in its memory.
(ii) The meter shall display on demand the 15/5 minutes
Active Energy (import and export shall be displayed in separate
register) for the previous 15 minutes block.
(iii) The meter shall continuously display the average of
the RMS values of the three line to neutral PT secondary voltages as
a percentage of 63.5 volts and display the same on demand.
(iv) The meters shall be able to measure & display the
instantaneous voltages and currents for all three phases instantaneous
average three phase power, instantaneous and average frequency &
power factor. The meter shall be suitable for working under balanced
/ unbalanced loads at all power factor (i.e. zero lag-unity-zero lead).
(v) The meter shall count the number of cycles in PT
output during each successive 15 minute block and divide the same
by 900 to arrive at the average frequency. This shall be stored in the
meter’s memory. The average frequency of the previous 15minutes
block shall also be displayed, on demand in Hz.
(vi) The meters shall measure and display cumulative
active energy, apparent energy, reactive (lag) energy, reactive (lead)
energy in both import and export mode.
(vii) The meters shall also compute the reactive power on
3-phase, 4-wire principle, with an accuracy one class lower as per IS:
14697 and integrate the reactive energy into 8 separate registers, as
given below. One set for the period for which the average RMS
voltage is 103% or higher, and the other for the period for which the
average RMS voltage is below 97%.
Import Reactive Energy (lag) for Voltage < 97%
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
14.19.2 The test output device should have constant pulse rate in terms
of pulse/unit energy and its value should be indelibly printed on the rating
plate.
14.19.3 The device shall be suitable for use with sensing probe used
with test benches or reference standards.
14.20 Display
14.20.1 The meter shall have a minimum 7-digit backlit liquid crystal
display (LCD) with another digit for legend. The minimum character height
shall be 5 mm.
14.20.2 The meter should have facility of auto display mode where all
parameters automatically scroll within the specified time and a manual mode
where the parameters can be read by push button operation. In auto display
mode each parameter shall on display for 10 seconds.
14.21 Real Time Clock
14.21.1 A real time quartz clock shall be used in the meter for
maintaining time and calendar date. The maximum drift shall not exceed -/+
180 seconds per year. The uncertainty of setting initial time shall not exceed +
30 Seconds with respect to Indian standard time.
14.21.2 Facility for adjustment of real time shall be provided through
CMRI/Workstation with proper security.
14.21.3 It shall also be possible to synchronise clocks of all the meters
through GPS clock. All necessary equipment shall be provided to run the auto
time synchronization of all ABT meters through a centrally located GPS clock
available in each sub-station. Off-line time synchronization will not be
accepted.
14.22 Memory
14.22.1 The meter shall have non-volatile memory, so that the
registered parameters will not be affected by loss of power. The non-volatile
memory should have a minimum retention time of 10 years.
14.23 Harmonics Measurement
14.23.1 THD Up to 29th Harmonic shall be measurable that is a
sampling rate of 3000/sec. The meter should be capable of measuring
fundamental energy as well as total energy. Fundamental energy shall be made
available on meter-display and the same only shall be used for billing purpose.
14.24 Self-Diagnostic Feature
14.24.1 The meter shall be capable of performing complete self-
diagnostic check to monitor the circuits for any malfunctioning to ensure
integrity of data memory location at all times. The meter shall have indications
for unsatisfactory/non-functioning/malfunctioning of the following:
i) Real Time and Date
ii) All display segments as per the requirement
iii) Non-volatile memory (NVM) failure indication at SAS
iv) Low battery indication at SAS
14.24.2 While installing the meter, it should be possible to check the
correctness of Current Transformer, Voltage connections to the meter and their
polarity from the functioning of the meter for different voltage injections with
the help of vector/phasor diagrams. For this purpose, suitable software for
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
14.28 RELAYS:
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
14.28.1 General
a) All relays shall conform to the requirements of IS 3231/ IEC 60255/ IEC
61000 or other relevant standards.
b) All protective relays shall be numerical type and communication protocol
shall be IEC 61850. Further, test levels of EMI as indicated IEC 61850
shall be applicable to these relays.
c) Two sets of relevant software for relay configuration & setting,
maintenance etc to be supplied to each station. The numeric relay and
software shall be upgradable.
d) The protective relays shall be suitable for efficient and reliable operation
of the protection scheme described in the specification. Necessary
auxiliary relays and timers required for interlocking schemes for
multiplying of contacts suiting contact duties of protective relays and
monitoring of control supplies and circuits etc. also required for the
complete protection schemes described in the specification shall be
provided. All protective relays shall be provided with at least two pairs of
potential free isolated output contacts. Auxiliary relays and timers shall
have pairs of contacts as required to complete the scheme contacts shall
be silver faced with spring action. Relay case shall have adequate number
of terminals for making potential free external connections to the relay’s
coils and contacts, including spare contacts.
e) Relays shall be suitable for flush or semi-flush mounting with connectors
from rear.
f) All draw out cases or plug in type modular cases will have proper testing
facilities. The testing facilities provided on the relays shall be specifically
stated in the bid. All protective relays shall be with proper online testing
facilities without isolation from TB where inputs viz CT/ PT and DC are
wired. All main relays shall be provided with test plug to test the relay
online & required test handle may be invariably indicated. Necessary test
plug shall be in the supplier's scope of supply and shall be supplied loose.
Unless otherwise specified all auxiliary relays and timers shall be
supplied either in non-draw out cases or plug in type modular cases.
g) All A.C. relays shall be suitable for operation at 50 Hz. A.C. Voltage
operated relays shall be suitable for 110 volts VT secondary and current
operated relays for 1Amp. CT secondary. DC auxiliary relays and timers
shall be designed for 110 volts/ 220 volts DC and shall operate
satisfactorily between 70% and 110% of rated voltage. Voltage operated
relays shall have adequate thermal capacity for continuous operation.
h) All Protective relays, auxiliary relays and timers except the lockout relays
and interlocking relays shall be provided with self-reset type contacts. All
protective relays, trip relays and timers shall be provided with externally/
electrically reset positive action operation indicators provided with proper
inscription. All protective relays which do not have built-in hand reset
operation indicators shall have additional auxiliary relays with operating
indicators for this purpose. Similar separate operating indicators
(auxiliary relays) shall also be provided in the trip circuits of protections
located outside the board such as Buchholz relays, temperature protection
etc.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
i) No control relays that shall trip the circuit breaker when the relays are de-
energized shall be employed in the circuits.
j) All relays shall withstand a test voltage of 2.5 kV, 50 Hz rms. voltage for
one second. In case of static relays, the Clause 14.28.1.l shall be
applicable.
k) Auxiliary seal-in unit provided in the protective relays shall preferably be
of shunt reinforcement type. If series relays are used the following shall
be strictly ensured:
(i) The operating time of the series seal-in unit shall be sufficiently
shorter than that of the trip coil relay in series with which it operates to
ensure definite operation of the flag indicator of the relay.
(ii) Seal - in unit shall obtain adequate current for operation when one or
more relays operate simultaneously.
(iii) Impedance of the seal-in unit shall be small enough to permit
satisfactory operation of the trip coil on trip relays when D.C. supply
is minimum.
(iv) Trip-circuit seal-in is required for all trip outputs, irrespective of the
magnitude of the interrupted current. The trip-circuit seal-in logic shall
not only seal-in the trip output(s),but also the relevant initiation signals
to other scheme functions, (e.g. initiate signals to the circuit-breaker
failure function, reclosing function etc.), and the alarm output signals.
(vi)For the current seal-in method, the seal-in shall be maintained until
the circuit-breaker opens, at which time the seal-in shall reset and the
seal in method shall not now revert to the fixed time duration method.
For this seal-in method, the seal-in shall be maintained for the set time
duration. For the line protection schemes, this time duration shall be
independently settable for single- and three-pole tripping.
i) The printed circuit cards shall be of fibre glass type and the contact
shall be gold plated. All connectors with the connector pegs shall be
through wire wrapping. All solder Joints on the printed circuit boards
shall be encapsulated or covered with varnish.
ii) The components shall be loaded by less than half of their rated values.
The resistor shall be of carbon composition or metal oxide type and
the capacitors shall be plastic film or tantalum type. Stringent
measures including shielding of long internal wiring should be taken
to make relays immune to voltage spikes. Relays must withstand 5kW,
1x150 microsecond, O.5 Joule source energy impulse test or 1.5 MHz
damp oscillations with initial value of 2.5 kV decaying to half the
initial value in 6 microseconds with internal source impedance of 150
ohms.
iii) The supplier shall ensure that the terminals of the contacts of the
relays are readily brought out for connectors as required in the final
approved scheme.
iv) DC /DC converter shall be provided in the solid state protective relays
wherever necessary in order to provide a stable auxiliary supply for
relay operation. Provision of DC cell in the protective relays as
relievable stand-by power supplies will however not be acceptable.
m) Provision shall be made for easy isolation of trip circuits of each relay for
the purpose of testing and maintenance.
n) All protective relays and alarm relays shall be provided with one/two
extra isolated pair of contacts wired terminals exclusively for Employer’s
use.
o) The bidder shall include in his bid a list of installations where the relays
quoted have been in satisfactory operation.
i) Distance Protection (Main I & Main II) of different make for 400KV
and 220 kV lines
ii) Distance Protection for 132 kV lines
iii) Back up directional over current and earth fault relays for 132 kV
iv) Back up non directional over current (3 O/C) and earth fault relays for
33kV lines
v) Integrated Numerical Transformer Protection
vi)Integrated Numerical Transformer Differential Protection as Main –I &
Main-II of different make with non-directional overcurrent and earth
fault function with high set units for power and autotransformers/
reactors.
vii)Reactor Protection as per Clause 14.33.
ii) Relays shall have one no. front RJ45 or USB port (for RS 232 port
Converter to USB shall be supplied for each substation along with
spare) for Local Relay Parameterization and Two nos. rear FO port/
Rear RS485 for connectivity to SAS over IEC61850 protocol
iii) The relay shall have self-communication port monitoring feature and
failure shall generate alarm.
iv) The relay shall have sufficient battery back up to keep the internal
clock running for at least 2 years in absence of auxiliary supply. The
capacitor discharging power is not sufficient and won’t be accepted.
Proper battery back must be provided.
vi) Should have minimum 36 Binary Inputs and 32 Binary Outputs as per
scheme requirement including 30% BI & BO spare.
viii) Shall have front minimum 3 lines LCD display with Alpha numeric
keypad
x) The bidder shall bring out in the bid that the Numerical relays
providing different protection features / application in a single unit if
any one of the application/ features goes out of service the other
feature/application (s) will remain un-effected.
xiii) Must have real time clock for time stamping of events/ disturbances
with time synchronization inputs (GPRS etc.). Time synchronisation
through SNTP compatible.
xiv) The major component cards shall be hot swappable and front or rear
loading.
ii) The relay shall be able to detect any discrepancy found between NO &
NC contacts of breaker.
k) The relays shall have the following tools for fault diagnostics:
i) Fault record (shall be function of IED): – The relay shall have the
facility to store fault records with information on cause of trip,
date, time, trip values of electrical parameters.
ii) Event record (shall be function of IED ): – The relay shall have the
facility to store time stamped event records with 1ms resolution.
iii) Disturbance records (shall be function of IED ): – The relay shall
have capacity to store disturbance records of at least 10 sec.
duration and sampling rate per cycle shall be more than 15.
n) It shall be possible to change the relay setting from the front panel using
the key pads/ Work station of SAS and Laptop.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Main I and Main II Line Differential Protection shall be of two different make
(i.e. from different manufacturers) or of same make with two different
platforms with same specifications.
The relay shall have all the features as per Distance protection relay
over and above following features
B. Remote communication:
a) 1300 nm - multi-mode
OR
the fault, zone-2 shall cover full protected section plus 50 % of the next
section, zone-3 shall normally cover the two adjacent sections
completely. The zones must have independent time settings.
ix) Shall have resetting time of less than 55 milli-seconds (including the
resetting time of trip relays)
x) All the zones shall have setting such that they can detect the fault online
from minimum 0.3 km to 500 km.
xi) The maximum fault current could be as high as 63kA but the minimum
fault current could be as low as 20% of rated current. The starting and
measuring relays characteristics should be satisfactory under these
extreme varying conditions.
xii) The relay shall use the memory voltage for proper directional
discrimination at close in 3 phase fault which shall be based on positive
sequence voltages. The directional discrimination and phase selection
based on negative sequence measurement techniques is not acceptable.
xiii) Have adequate number of forward zones (minimum three) and a reverse
zone. The zone reach setting ranges shall be sufficient to cover line
lengths appropriate to each zone. Carrier aided scheme options such as
permissive under reach, overreach, & blocking and non-carrier aided
schemes of zone 1 extension and Loss of load accelerated tripping
schemes shall be available as standard. Weak in feed logic and current
reversal guard also shall be provided.
xiv) In case the carrier channel fails, one out of the non-carrier-based schemes
cited above should come into operation automatically to ensure high
speed and simultaneous opening of breakers at both ends of the line.
trip as per zone detection. The relay shall be blocked for the set time for
the first PS sensed and remain unblocked for the set time for the
successive PS.
xxi) Be suitable for single pole or three pole tripping. However, relays offered
for 132 kV lines provided with mechanically ganged circuit breakers
single pole tripping need not to be provided.
xxii) Be suitable for both bus PT or Line PT/ CVT supply.
xxiii) Shall have in built Trip circuit supervision facility to monitor both pre-
and post close supervision facilities. An alarm shall be generated.
xxiv) Shall have in built broken conductor detection by way of level detector
or negative sequence measurement.
xxv) Shall have df/dt functions.
xxvi) Shall have multistage under frequency setting options.
xxvii) The sensitivity of the logic shall not be affected during operation under
low load.
xxviii) Shall have a fault locator with an accuracy of ±3%. The display should be
in kilometres and preferably in percentage impedance too. The fault
locator should have built in mutual compensation for parallel circuit.
xxix) Have mutual zero sequence compensation factor setting. The relay shall
have facility to select different group settings to cater for mutual coupling
on account of multi circuit line conditions. The minimum no. of group
should be four.
xxx) Have at least 24 no. of programmable binary input and 32 no. of
programmable binary output contact to cater for DR/SER carrier aided
tripping auto re-closing etc.
xxxi) The relay shall have a built-in auto-reclose function with facilities for
single pole / three pole / single and three pole tripping. It shall be possible
to trigger the A/R function from an external protection. A voltage check
function which can be programmed for deadline charging/dead bus
charging / check synchronising shall be included. However, the relay
shall support independent A/R scheme.
xxxii) Shall have additional features to provide under/ over voltage protection.
xxxiii) Shall have additional features to provide under frequency protection
xxxiv) Shall have memory circuits with defined characteristics in all three phases
to ensure correct operation during close-up 3 phase faults and other
adverse conditions and shall operate instantaneously when circuit breaker
is closed to zero-volt 3 phase fault.
a) GENERAL REQUIREMENTS:
b) FUNCTIONAL DESCRIPTIONS:
1) Differential protection:
The scheme shall have in-built restricted earth Fault (REF) for both
the windings. This function should be provided to maximise the
sensitivity of the protection of earth faults. The REF function should
be a high impedance element. The REF function should be able to
share Current Transformers with the biased differential function. As in
traditional REF protections, the function should respond only to the
fundamental frequency component of the currents. For star/star
transformer, both the windings shall be protected through REF, as
such relay shall have sufficient analogue channels to accommodate the
same.
i) The over fluxing protection shall be built in the relay. By pairs of V/f
and t, it shall be possible to plot the over fluxing characteristics so
that accurate adaptation of the power transformer data is ensured.
ii) In addition, the relay should have a definite time element for alarm.
iii) The relay should monitor all the three phase voltages for calculation
of V/f and should take the highest voltage for V/f calculation.
i) Shall have two stages of thermal overload protection for alarm and
trip condition with continuously adjustable setting range of 100-
400% of rated current and time constant setting range of 1.0 to
10.00sec continuously.
ii) Shall be single pole type.
iii) Shall have a drop off/pick up ratio greater than 95%.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
iv) Shall have separately adjustable time delay relays for alarm having
a setting range of 1to 10 seconds continuously.
i) The relay shall have three stages of definite time over current
protection as backup operating with separate measuring systems for
the evaluation of the three phase currents, the negative sequence
current and the residual current.
ii) In addition, the relay shall have three stages of Inverse time over
current protection operating based on one measuring system each for
the three phase currents, the negative sequence current and the
residual current.
iii) Shall have additional features to provide under/ over voltage
protection.
iv) Shall have additional features to provide under frequency protection.
operation of any one out of two schemes connected to main faulty bus
shall result in tripping of the same.
c) Single bus bar protection scheme shall be provided for each main bus
and transfer bus (as applicable) for 220KV voltage level.
d) Each Bus Bar protection scheme shall
i)Have maximum operating time up to trip impulse to trip relay for all
types of faults of 25 milli seconds at 5 times setting value.
ii) Operate selectively for each bus bar
iii) Give hundred percent security up to 63 KA for fault level for 400 KV ,
50kA for 220 KV and 40 KA for 132 KV
iv) Incorporate continuous supervision for CT secondary against any
possible open circuit and if it occurs, shall render the relevant zone of
protection inoperative and initiate an alarm
v) Not give false operation during normal load flow in bus bars
vi) Incorporate clear zone indication
f). Be of phase segregated and triple pole type. The bus bar scheme may be
Centralized, or Decentralized type and it must accommodate minimum 3
future bays along with tripping relays.
g) Provide independent zones of protection (including transfer bus if any).
If the bus section is provided, then each side of bus section shall have
separate set of bus bar protection schemes
h) Include individual high speed electrically reset tripping relays for each
feeder. However, in case of distributed Bus bar protection, individual trip
relay shall not be required if bay unit is having trip duty contacts for
breaker tripping.
i) Be transient free in operation
j) Include continuous D.C. supplies supervision
k) Not cause tripping for the differential current below the load current of
heaviest loaded feeder. Contractor shall submit application check for the
same.
l)Shall include necessary C.T. switching relays wherever C.T. switching is
involved and have 'CT' selection incomplete alarm
m) Include protection 'IN/OUT' switch for each zone
n) Shall include trip relays, CT switching relays (if applicable) , auxiliary
CTs (if applicable) as well as additional power supply modules, input
modules etc. as may be required to provide a Bus bar protection scheme
for the complete bus arrangement i.e. for all the bays or breakers
including future bays as per the Single line diagram for new substations.
However, for extension of bus bar protection scheme in existing
substations, scope shall be limited to the bay or breakers covered under
this specification. Suitable panels (if required) to mount these are also
included in the scope of the work.
o) In case of distributed Bus bar Protection, the bay units for future bays
may be installed in a separate panel and the same shall be located in
switchyard panel room where bus bar protection panel shall be installed.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
The equipment must be Type tested for Shock, Vibration, Dry heat,
Radiated Emission, Electromagnetic field immunity, Electrostatic
discharge immunity test in a Standard Laboratory. Type test report shall
be submitted along with the bid. Type tests shall be more than five years
as on opening of this bid.
The equipment shall be compliant to IEC 61850 Protocol. It shall also
support the network protocols like NTPv4, SNTP, SNMPv1,2,3, SNMP
Trap, SSH2, Ipv6, DHCP, HTTP (S), eMail, FTP, TELNET and Syslog
The Time synchronisation equipment shall receive the coordinated
Universal Time (UTC) transmitted through Geo Positioning Satellite
System (GPS) and synchronise equipment to the Indian Standard Time in
a substation.
Time synchronisation equipment shall include antenna, all special cables
and processing equipment etc.
It shall be compatible for synchronisation of Event Loggers, Disturbance
recorders and SCADA at a substation through individual port or through
Ethernet realised through optic fibre bus.
Equipment shall operate up to the ambient temperature of 50 degree
centigrade and 100% humidity.
The synchronisation equipment shall have 20 nano second accuracy.
Equipment shall give real time corresponding to IST (taking into
consideration all factors like voltage, & temperature variations,
propagation & processing delays etc.) including communication time for
satellite link to achieve real time signal.
Equipment shall meet the requirement of IEC 60255 for storage &
operation.
The bay unit shall use industrial grade components. The bay level unit,
based on microprocessor technology, shall use numerical techniques for
the calculation and evaluation of externally input analogue signals. These
shall incorporate select-before-operate control principles as safety
measures for operation via the HMI. These shall perform all bay related
functions, such as control commands, bay interlocking, data acquisition,
data storage, event recording and shall provide inputs for status indication
and outputs for commands. These shall be directly connected to the
switchgear. The bay unit shall acquire and process all data for the bay
(Equipment status, fault indications, measured values, alarms etc.) and
transmit these to the other devices in sub-station automation system. In
addition, these shall receive the operation commands from station HMI
and SLDC. The bay unit shall have the capability to store all the data for
at least 24 hours even if there is any power off conditions during the day.
The BCU shall have back up directional & non-directional back-up
protection features in addition to Auto Reclose, LBB, U/O voltage and
Synchronization function. The BCU shall have redundant power supply
card i.e. in case of failure of one source/Card fail, the redundant shall pick
up instantly. Power supply card failure shall generate necessary alarm to
local SCADA.
The BCU must have metering functions like phase current, phase
voltages, active & apparent power, power factor, frequency etc. The
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
The mimic diagram shall indicate the live & dead portion of the Bay.
The BCU shall be capable to generate password for maintenance
shutdown.
One Bay level unit shall be provided for supervision and control of each
400KV, 220KV, 132kV and 33kV bay (a bay comprises of one circuit
breaker and associated disconnectors, earth switches and instrument
transformer). If the 33kV bus section comprises isolator only, then the
isolator shall be controlled from the transformer LV side bay and same is
the case for Bus PT Isolator which shall be controlled by Transformer LV
side BCU. The Bay level unit shall be equipped with analogue and binary
inputs/outputs for handling the control, status monitoring and analogue
measurement functions. All bay level interlocks are to be incorporated in
the Bay level unit so as to permit control from the Bay level unit/ local
bay mimic panel, with all bay interlocks in place, during maintenance and
commissioning or in case of contingencies when the Station HMI is out
of service.
The Bay level units shall be installed in the control and relay panels
located in the control room.
The Bay level unit shall meet the requirements for withstanding
electromagnetic interference according to relevant parts of IEC 61850.
Failure of any single component within the equipment shall neither cause
unwanted operation nor lead to a complete system breakdown.
Input / Output (I/O) modules
The I/O modules shall form a part of the bay level unit and shall provide
coupling to the substation equipment. The I/O modules shall acquire all
switchgear information (i.e. data coming directly from the switchgear or
from switchgear interlocking devices) and transmit commands for
operation of the switchgear.
In addition, it shall be possible to plug a PC laptop on the Bay and get the
full substation operator interface.
The bidder shall provide the redundant managed switched optical Ethernet
communication infrastructure for SAS against PRP architecture. The
necessary switches are provided for communication infrastructure as follows.
14.44.1 One switch shall be provided to connect all IEDs for 1 Bay in
LAN –I and the second optical port of Bay IEDs shall be connected to other
Ethernet Switch in LAN-2. The maximum number of bays may be connected
to these Ethernet Switch shall be two bays for 400KV, 220kV and 132kV.
However, for 33kV, 3 numbers bay may be connected to one Ethernet
Switch in this PRP architecture.
14.44.2 The managed Ethernet switch shall have minimum 20% port
redundancy (Both Fibre & Copper ports).
14.45.5 Acquisition units shall acquire the Disturbance data for the pre
fault and post fault period and transfer them to Evaluation unit
automatically to store in the hard disk. The acquisition units shall be
located in the protection panels of the respective feeders.
14.45.6 The acquisition unit shall be suitable for inputs from current
transformers with 1A rated secondary and capacitive voltage transformers
with 63.5V (phase to neutral voltage) rated secondary. Any device required
for processing of input signals in order to make the signals compatible to
the Fault recorder equipment shall form an integral part of it. However,
such processing of input signals shall in no way distort its waveform.
14.45.7 The equipment shall be carefully screened, shielded, earthed
and protected as may be required for its safe functioning. Also, the Fault
recorder shall have stable software, reliable hardware, simplicity of
maintenance and immunity from the effects of the hostile environment of
EHV switchyard which are prone to various interference signals typically
from large switching transients.
14.45.8 The evaluation unit hardware shall be as described in clause no.
4.0 of section sub-station automation.
14.45.9 Necessary software for transferring the data automatically from
local evaluation unit to a remote station and receiving the same at the
remote station through owner’s PLCC/VSAT/LEASED LINE shall be
provided.
14.45.10 Evaluation software shall be provided for the analysis and
evaluation of the recorded data made available in the PC under WINDOWS
environment. The Software features shall include repositioning of analog
and digital signals, selection and amplification of time and amplitude scales
of each analogue and digital channel, calculation of MAX/MIN frequency,
phase difference values, recording of MAX/MIN values etc. of analogue
channel, group of signal to be drawn on the same axis etc, listing and
numbering of all analogue and digital channels and current, voltage,
frequency and phase difference values at the time of fault/tripping. Also,
the software should be capable of carrying out Fourier /Harmonic analysis
of the current and voltage wave forms. The Disturbance records shall also
be available in COMTRADE format (IEEE standard- Common Format for
Transient data Exchange for Power System)
14.45.11 The Evaluation unit shall be connected to the printer to obtain
the graphic form of disturbances whenever desired by the operator.
14.45.12 Fault recorder acquisition units shall be suitable to operate from
220V DC as available at sub-station Evaluation unit along with the printer
shall normally be connected to 230V, single phase AC supply. In case of
failure of AC supply, Evaluation unit and printer shall be switched
automatically to the station DC through Inverter of adequate capacity
which shall form a part of Distance recorder system. The inverter of
adequate capacity shall be provided to cater the requirement specified in
section sub-station automation clause no. 8.0 and DR evaluation unit.
14.45.13 The acquisition unit shall have the following features:
i) Facility shall exist to alarm operator in case of any internal faults in the
acquisition units such as power supply fail, processor / memory fail etc.
and same shall be wired to annunciation system.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
b) Backup Protection:
The 33kV Feeder Panels shall be provided non directional single/ multi
pole relays as specified in Clause 14.32. One triple pole over current
relays for phase faults and one Earth Fault Relay for Earth Faults with
high set elements shall be provided. Two numbers 33kV feeders shall be
accommodated in a single simplex panel with control on one BCU only.
(b) Bus differential protection: The bus bar protection relays shall be
provided as specified in Clause 14.35.
(b) Bus differential protection: The bus bar protection relays shall be
provided as specified in Clause 14.35.
(b) Bus differential protection: The bus bar protection relays shall be
provided as specified in Clause 14.35, if applicable.
14.48 RELAY MAINTENANCE TOOL KIT
The bidder shall supply a complete maintenance tool kit set. The tool kit
shall have generally current jack, card extender, card puller, required
crimping tool, screw drivers, pliers etc.
The tool kit shall contain test plugs, test leads, clips for maintenance and
testing of relays supplied. Further detailing will be done during detail
engineering.
The Maintenance Tool Kit shall be of Universal type.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
14.49 TESTS
The supplier shall carryout all tests as per relevant standards as all
associated equipment including relays, meters, instruments etc. The
supplier shall submit all that reports to Employer for approval before
despatching the control and relay panels. The Bidder shall also submit
along with the bid type test reports for relays instruments, meters and
other devices of the type and class being offered. Bidder has to submit
KEMA test certificate for Numeric relay on interoperability compliance
of IEC 61850 in general and GOOSE messaging and publishing in
particular along with the bid.
Control and relay panels shall be subjected to the following tests:
B TRANSFORMER PANELS
1 Protection and Relays:
(a) Differential Protection Scheme 2 No. 2 No. 2 No. 2 No.
(b) Restricted Earth Fault 1 No 1 No (overall 1 No 1 No
Protection Scheme (overall REF)
REF)
(c) Back up non-directional over Could be Could be Could be Could be
current scheme for HV side feature of feature of feature of feature of
relay relay relay relay
(d) Back up non-directional over Could be Could be Could be Could be
current and earth fault scheme for feature of feature of feature of feature of
MV/LV Side relay relay relay relay
(e) LBB Protection Scheme. Can be Can be Can be Can be
function of function of function of function of
BCU/IEDs BCU/IEDs BCU/IEDs BCU/IEDs
(f) Over Fluxing Protection 1 Set 1 Set 1 Set 1 Set-
scheme
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
SL.
NO Description 400 kV
XI
400kV, 220 kV and 132 kV Bus Coupler / Bypass and Tie Breaker Panel
SL ITEM RATINGS AND PARTICULARS
NO
220 kV Panel with Main I 132 kV Panel with Main 1 &
& Main II Scheme Transfer
Bus Scheme
XII XIII
(b) Bus Bar differential Main I and Main II cum Applicable, where specified in
protection transfer bus BoQ
(d) Trip Circuit Supervision Supervision for 6 trip coils Supervision for 2 trip coils
Relay for pre and post-closing (2 trip coils per
pole or phase)
(e) DC Supply healthy 2 No. 2 No.
monitoring scheme
(f) AC Supply healthy 1 No. 1 No.
monitoring scheme
(g) High Speed Trip relay 2 No. 2 No.
(h) PT Selection Scheme 1No. Complete Bus PT Not applicable
Selection Scheme (Can be
function of
BCU)
(i) Auxiliary relay, timer relay As required As required
scheme
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
3 Controls/Annunciation/
Statusindication
XIV
B TIE PANEL
(b) Bus Bar differential Redundant (1+1) numerical bus bar protection scheme for
protection each bus system
(c) LBB Protection Scheme. 1 set (if centralised scheme or 1 set bus bar bay unit if
decentralised scheme)
(d) Trip Circuit Supervision Supervision for 6 trip coils (2 trip coils per
Relay for pre and post-closing pole or phase)
3 Controls/Annunciation/Status
indication
Dielectric Withstand IEC60255-5 IEEE C37.90 50 Hz, 1mn, 2kV (CM), 1kV (DM)
Classe 2 :
Acceleration : 2g from 10 (1) to 500Hz
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Classe 2 :
Acceleration : 1g from 10 (1) to 500Hz
Classe 2 : Acceleration : 2g
Displacement : 7,5mm selon axe H
Acceleration : 1g
Displacement : 3,5mm selon axe V
Test Ab : - 25°c / 96 H
Cold Test - Storage IEC60068-2-1 Test Ad :
-40°C / 96h
Powered On at –25°C (for information)
Powered On at –40°C (for information)
Dry Heat Test – IEC 60068-2-2 Test Bd : 55°C / 96h
Operating
70°C / 2h
70°c / 24 H
Dry Heat Test – IEC 60068-2-1 Test Bd :
Storage +70°C / 96h
Powered On at +70°C
Class 3 :
2kV – 5kHz (CM)
Class 3 :
2kV (CM) on shield
Class 4 :
4kV (CM) for information
Class 3 :
1 kV MC
Communication Standards
UCA2:
CASM 1.6 - Common Application Service Models and Mapping to MMS
GOMSFE 0.91 - Generic Object Models for Substation & Feeder Equipment
IEC 61850:
IEC 61850-8-1: Communication networks and systems in substations – Part 8-
1: Specific communication service mapping (SCSM) – Mapping to
MMS(ISO/IEC 9506 Part 1 and Part 2
Telecontrol protocol:
IEC 608670-5-101
IEC 608670-5-104.
Legacy protection protocol
IEC 60870-5-103 International standards – First release 1997-12
MODBUS
Automation Standard
IEC 61131-3
future expandability and this shall excludes data for 3 (three) numbers
future provision bays. The Gateways shall have redundant power cards
It shall include communication gateway, intelligent electronic devices (IED) for
bay control and inter IED communication infrastructure. A model architecture
drawing for SAS is enclosed at the end of this chapter as Annexure I.
Bay level intelligent electronic devices (IED) for protection and control and
the Managed Ethernet Switch shall be provided in the C&R panels
installed in the local control room. Each IED will be directly connected to the
Hot-standby Server PC (HMI) of the Station Automation System through a PRP
Ethernet LAN on fiber optic medium and shall communicate as per the
IEC61850 standard.
The communication gateway shall facilitate the information flow with
SLDC/Remote Control Centre.
The bay level intelligent electronic devices (IED) for protection and control
shall provide the direct connection to the switchgear without the need of
interposing components and perform control, protection, and monitoring
functions.
The Integration of IEC61850 communication based monitoring equipments like
Online Insulating Oil drying system, Digital RTCC Relays etc with substation
automation system shall be carried out and shall be included in the scope of
work.
Further the Gateways shall have licenses sufficient for all the bays covered in
the present scope as well as all the mentioned future bays.
All the numerical IEDs must be fully IEC 61850 compliant and must have the
following features.
operate the system. The operator interface shall be intuitive such that
operating personnel shall be able to operate the system easily after
having received some basic training.
The system shall incorporate the control, monitoring and protection
functions specified, self-monitoring, signaling and testing facilities,
measuring as well as memory functions, event recording and evaluation
of disturbance records.
Maintenance, modification or extension of components may not cause a
shutdown of the whole substation automation system. Self-monitoring
of components, modules and communication shall be incorporated to
increase the availability and the reliability of the equipment and
minimize maintenance.
Bidder shall offer the Bay level unit (a bay comprises of one circuit
breaker and associated isolator, earth switches and instrument
transformer), bay mimic along with relay and protection panels and
Station HMI in Control Room building for overall optimization.
The high-voltage apparatus within the station shall be operated from different
places:
Select-before-Execute
For security reasons the command is always to be given in two stages: selection
of the object and command for operation under all mode of operation except
emergency operation. Final execution shall take place only when selection and
command are actuated.
Command Supervision
Self-supervision
Continuous self-supervision function with self-diagnostic feature shall be
included.
User Configuration
The monitoring, controlling and configuration of all input and output logical
signals and binary inputs and relay outputs for all built-in functions and signals
shall be possible both locally and remotely.
It shall also be possible to interconnect and derive input and output signals,
logic functions, using built-In functions, complex voltage and currents,
additional logics (AND-gates, OR gates and timers). (Multi-activation of these
additional functions should be possible).
EMERGENCY Operation
It shall be possible to close or open the selected Circuit Breaker with ON or
OFF push buttons even during the outage of bay IED.
REMOTE mode
Control authority in this mode is given to a higher level (Remote SCADA) and
the installation can be controlled only remotely. Control operation from lower
levels shall not be possible in this operating mode.
Voltage selection
The voltages relevant for the Synchro-check functions are dependent on the
station topology, i.e. on the positions of the circuit breakers and/or the isolators.
The correct voltage for synchronizing and energizing is derived from the
auxiliary switches of the circuit breakers, the isolator, and earthing switch and
shall be selected automatically by the bay control and protection IEDs.
General
The Protection functions are independent of Bay Control function. The
Protection shall be provided by separate Protection IEDs (numerical relays) and
other Protection devices as per section Relay & Protection.
IEDs shall be connected to the communication infrastructure for data sharing
and meet the real-time communication requirements for automatic functions.
The data presentation and the configuration of the various IEDs shall be
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Status Supervision
Continuous monitoring of switching objects i.e. the position of each
switchgear, e.g. Circuit Breaker, Isolator, Earthing Switch, Transformer
tap changer etc., shall be supervised continuously. Every detected
change of position shall be immediately displayed in the single-line
diagram on the station
HMI screen, recorded in the event list, and a hard copy printout shall be
produced. Alarms shall be initiated in the case of spontaneous position
changes.
The switchgear positions shall be indicated by two auxiliary switches,
normally closed (NC) and normally open (NO), which shall give
ambivalent signals. An alarm shall be initiated if these position
indications are inconsistent or if the time required for operating
mechanism to change position exceeds a predefined limit.
The SAS shall also monitor the status of sub-station auxiliaries. The
status and control of auxiliaries shall be done through dedicated one or
more IED and all alarm and analogue values shall be monitored and
recoded through this IED.
Measurements
Analogue inputs for voltage and current measurements shall be connected
directly to the voltage transformers (VT) and the current transformers (CT)
without intermediate transducers. The values of active power (W), reactive
power (VAR), frequency (Hz), and the rms, Max / Min values for voltage (U)
and current (I) shall be calculated.
The measured values shall be displayed locally on the station HMI and in the
control center. The abnormal values must be discarded. The analogue values
shall be updated every 2 seconds.
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
General
The operator station HMI shall be a redundant with hot standby and shall
provide basic functions for supervision and control of the substation. The
operator shall give commands to the switchgear on the screen via mouse clicks
or keyboard commands.
The HMI shall give the operator access to alarms and events displayed on the
screen. Aside from these lists on the screen, there shall be a printout of alarms
or events in an event log.
An acoustic alarm shall indicate abnormalities, and all unacknowledged alarms
shall be accessible from any screen selected by the operator.
The following standard pictures shall be available from the HMI:
Single-line diagram showing the switchgear status, Pressure values
(wherever required) and measured values (current, voltage, apparent
power, freq & pf) including OLTC Tap Position, WTI, OTI & Analog
set values.
Control dialogues with interlocking and blocking details. This control
dialogue shall tell the operator whether the device operation is permitted
or blocked & Select before Execute.
Measurement dialogues, Statistics & Trends
Bay wise interlock status display and failure of any interlock within the
bay by generating alarm and indication in Interlock diagram window.
Alarm list, station / bay-oriented
Event list, station / bay-oriented
Substation Auxiliaries
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
System status
Printing of sequence of event list, hardcopy and reports. The reports
shall be freely configurable using Crystal Report
List of signals to be configured in SAS is mentioned in Annexure-II of this
chapter.
Event List
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
The event list shall contain events that are important for the control and
monitoring of the substation.
The event and associated time (with 1ms resolution) of its occurrence has to be
displayed for each event.
The operator shall be able to call up the chronological event list on the monitor
at any time for the whole substation or sections of it.
A printout of each display shall be possible on the hard copy printer/Dot matrix
Printer / Line Printer of 132 Column.
The events shall be registered in a chronological event list in which the type of
event and its time of occurrence are specified. It shall be possible to store all
events in the computer for at least one month. The information shall be
obtainable also from a printed event log.
The chronological event list shall contain:
Position changes of circuit breakers, isolators and earthing devices
Indication of protective relay operations
Fault signals from the switchgear
Indication when analogue measured values exceed upper and lower
limits. Suitable provision shall be made in the system to define two
level of alarm on either side of the value or which shall be user defined
for each measurand.
Loss of communication.
Hourly time Stamping
Filters for selection of a certain type or group of events shall be available. The
filters shall be designed to enable viewing of events grouped per:
Date and time
Bay
Device
Function e.g. trips, protection operations etc.
Alarm class
Alarm List
Faults and errors occurring in the substation shall be listed in an alarm list and
shall be immediately transmitted to the control centre. The alarm list shall
substitute a conventional alarm tableau, and shall constitute an evaluation of all
station alarms. It shall contain unacknowledged alarms and persisting faults.
The date and time of occurrence shall be indicated.
The alarm list shall consist of a summary display of the present alarm situation.
Each alarm shall be reported on one line that contains:
The date and time of the alarm
The name of the alarming object
A descriptive text
The acknowledgement state.
Whenever an alarm condition occurs, the alarm condition must be shown on the
alarm list and must be displayed in a flashing state along with an audible alarm.
After acknowledgement of the alarm, it should appear in a steady (i.e. not
flashing) state and the audible alarm shall stop. The alarm should disappear only
if the alarm condition has physically cleared and the operator has reset the alarm
with a reset command. The state of the alarms shall be shown in the alarm list
(Unacknowledged and persistent, Unacknowledged and cleared, Acknowledged
and persistent).
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Filters for selection of a certain type or group of alarms shall be available as for
events.
Object picture
When selecting an object such as a circuit breaker or isolator in the single line
diagram, the associated bay picture shall be presented first. In the selected
object picture, all attributes like
Type of blocking
Authority
Local / remote control
SLDC / SAS control
Errors
etc. shall be displayed.
Control dialogues
The operator shall give commands to the system by means of mouse click
located on the single-line diagram. It shall also be possible to use the keyboard
for command activation. Data entry is performed with the keyboard. Dedicated
control dialogues for controlling at least the following devices shall be
available:
Breaker and Disconnector
Transformer tap-changer
User-authority levels
It shall be possible to restrict activation of the process pictures of each object
(bays, apparatus...) within a certain user authorization group. Each user shall
then be given access rights to each group of objects, e.g.:
Display only
Normal operation (e.g. open/close of switchgear), Shift wise operator’s
pass word for 3 shift in a day.
Restricted operation (e.g. by-passed interlocking)
System administrator
For maintenance and engineering purposes of the station HMI, the
following authorization levels shall be available:
No engineering allowed
Engineering/configuration allowed
Entire system management allowed
The access rights shall be defined by passwords assigned during the login
procedure. Only the system administrator shall be able to add/remove users and
change access rights.
15.11. Reports
The reports shall provide time-related follow-ups of measured and calculated
values. The data displayed shall comprise:
Trend reports:
Day (mean, peak)
Month (mean, peak)
Semi-annual (mean, peak)
Year (mean, peak)
Historical reports of selected analogue Values:
Day (at 15 minutes interval)
Week
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Month
Year
It shall be possible to select displayed values from the database in the process
display on-line. Scrolling between e.g. days shall be possible. Unsure values
shall be indicated. It shall be possible to select the time period for which the
specific data are kept in the memory.
Following printouts shall be available from the printer and shall be printed on
demand:
i. Daily voltage and frequency curves depicting time on X-axis and the
appropriate parameters on the Y-axis. The time duration of the curve is 24
hours.
ii. Weekly trend curves for real and derived analogue values.
iii. Printouts of the maximum and minimum values and frequency of occurrence
and duration of maximum and minimum values for each analogue parameter for
each circuit in 24 hr period.
iv. Provision shall be made for logging information about breaker status like
number of operation with date and time indications.
v. Equipment operation details shift wise and during 24 hours.
vi. Printout on adjustable time period as well as on demand for MW, MVAR,
Current, Voltage on each feeder and transformer as well as Tap Positions,
temperatures (WTIs, OTI) and status of pumps and fans for transformers.
vii. Printout on adjustable time period as well as on demand system frequency
and average frequency.
viii. Reports in specified formats which shall be developed by the contractor.
Disturbance Analysis
The PC-based work station shall have necessary software to evaluate all the
required information for proper fault analysis.
Automatic Sequences
The available automatic sequences in the system should be listed and described,
(e.g. sequences related to the bus transfer). It must be possible to initiate pre-
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
defined automatic sequences by the operator and also define new automatic
sequences.
15.12. GATEWAY
Communication Interface
The Substation Automation System shall have the capability to support
simultaneous communications with SLDC,
The Substation Automation System shall have communication ports as follows:
(a) Two Ports for RCC & State Load Dispatch Centre from each Gateway.
(b) The redundant Gateway shall work as hot stand by.
The communication interface to the SAS shall allow scanning and control of
defined points within the substation automation system. The substation
automation system shall simultaneously respond to independent scans and
commands from employer's control centers (SLDC).
Interface equipment:
The Contractor shall provide interface equipment for communicating between
Substation Automation system and State Load Dispatch Centre (PLCC/ FO).
In case of PLCC communication any modem supplied shall not require manual
equalization and shall include self-test features such as manual mark/space
keying, analogue loop-back, and digital loop-back. The modems shall provide
for convenient adjustment of output level and receive sensitivity. The modem
should be stand alone complete in all respects including power supply to
interface the SAS with communication channel. The configuration of tones
and speed shall be programmable and maintained in non-volatile memory in the
modem. All necessary hardware and software shall also be in the scope of
bidder except the communication link along with communication equipment
between substation control room and SLDC.
Communication Protocol
The communication protocol for gateway to control centre must be open
protocol and shall support IEC 60870-5-101,104 and IEC 61850 for all levels of
communication for sub-station automation such as Bay to station HMI, gateway
to remote station etc.
It shall be capable to perform all functions for entire substation including future
requirements as indicated in the SLD. It shall use industrial grade components.
Processor and RAM shall be selected in such a manner that during normal
operation not more than 30% capacity of processing and memory are used.
Supplier shall demonstrate these features. The RAM, Hard Disk and Bus should
latest and with maximum Values.
The capacity of hard disk shall be selected such that the following requirement
should occupy less than 50% of disk space:
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
1) Storage of all analogue data (at 15 Minutes interval) and digital data
including alarm, event and trend data for thirty (30) days,
2) Storage of all necessary software,
3) 500GB space for EMPLOYER'S use.
Supplier shall demonstrate that the capacity of hard disk is sufficient to meet the
above requirement.
Printer
It shall be robust & suitable for operation with a minimum of 132 characters per
line for Line Printer and Dot Matrix Printer. The printing operation shall be
quiet with a noise level of less than 45 dB suitable for location in the control
room. Printer shall accept and print all ASCII characters via master control
computer unit interface.
The printer shall have in built testing facility. Failure of the printer shall be
indicated in the Station HMI. The printer shall have an off line mode selector
switch to enable safe maintenance. The maintenance should be simple with
provisions for ease of change of print head, ribbon changing, paper insertion etc.
All printers mounted in the control room shall be provided with printer
enclosure. The enclosure shall be designed to permit full enclosure of the
printers at a convenient level. Plexiglas windows shall be used to provide visual
inspection of the printers and ease of reading. The printer enclosures shall be
designed to protect the printers from accidental external contact & each should
be removable from hinges at the back and shall be provided with lock at the
front.
All reports and graphics prints shall be printed on laser printer
One Dot Matrix Printer (DMP) shall be exclusively used for hourly log
printing.
The mass storage unit shall be built-in to the Station HMI. All operational
measured values, and indications shall be stored in a mass-storage unit of CD-
ROM & DVD-ROM with 5GB or more capacity i.e CD Writer & DVD Writer
(Both). The unit should support at least Read (48X), Write (24X), and Re-Write
(10X) operations, with Multi-Session capability. It should support ISO9660,
Rockridge and Joliet File systems. It should support formatting and use under
the operating system provided for Station HMI. The monthly back up of data
shall be taken on disc. The facility of back up of data shall be inherent in the
software.
All the data pertaining to Substation is to store in a system year/ month / day
wise. The daily data is stored in a day file of Particular Month and Year
automatically from 00.00Hrs to 24.00Hrs.
Auxiliary BCU
One BCU shall be put in Station level for monitoring Station Auxiliary Supply
(AC & DC), Battery Chargers, Nitrogen Fire Fighting System, Fire alarm etc.
Furniture required for HMIs, Printers, and Operators etc. The make of furniture
shall be of Godrej or better.
performance and contain basic functions, which shall not be accessible by the
application and maintenance engineer for modifications. The system shall
support the generation of typical control macros and a process database for user
specific data storage. In case of restoration of links after failure, the software
along with hardware shall be capable of automatically synchronising with the
remaining system without any manual interface. This shall be demonstrated by
contractor during integrated system test.
Application software
In order to ensure robust quality and reliable software functions, the main part
of the application software shall consist of standard software modules built as
functional block elements. The functional blocks shall be documented and
thoroughly tested. They form part of a library.
The application software within the control/protection devices shall be
programmed in a functional block language.
Simulation
Simulation tools shall be provided with the system to emulate a missing
equipment on UCA2/IEC61850.
The simulation tools shall be set up by the system configuration tool and be able
to execute scenario defined by the user.
The bidder shall provide each software in two copies in CD to load into the
system in case of any problem related with Hardware/Communication etc.
15.19. TESTS
The substation automation system offered by the bidder shall be subjected to
following tests to establish compliance with IEC 61850 for EHV substation
equipment and specified conditions:
Type Tests:
Control IEDs and Communication Equipment:
a. Power Input:
i. Auxiliary Voltage
ii. Current Circuits
iii. Voltage Circuits
iv. Indications
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
b. Accuracy Tests:
i. Operational Measured Values
ii. Currents
iii. Voltages
iv. Time resolution
c. Insulation Tests:
i. Dielectric Tests
ii. Impulse Voltage withstand Test
d. Influencing Quantities
i. Limits of operation
ii. Permissible ripples
iii. Interruption of input voltage
e. Electromagnetic Compatibility Test:
i. 1 MHZ. burst disturbance test
ii. Electrostatic Discharge Test
iii. Radiated Electromagnetic Field Disturbance Test
iv. Electrical Fast transient Disturbance Test
v. Conducted Disturbances Tests induced by Radio Frequency Field
vi. Magnetic Field Test
vii. Emission (Radio interference level) Test.
viii. Conducted Interference Test
f. Function Tests:
i. Indication
ii. Commands
iii. Measured value Acquisition
iv. Display Indications
g. Environmental tests:
i. Cold Temperature
ii. Dry Heat
iii. Wet heat
iv. Humidity (Damp heat Cycle)
v. Vibration
vi. Bump
vii. Shock
Integrated Testing
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Substation Operation
NORMAL OPERATION
Operation of the system by the operator from the remote SLDC or at the
substation shall take place via industry standard HMI (Human Machine
interface) subsystem consisting of graphic colour VDU, a standard keyboard
and a cursor positioning device (mouse). The coloured screen shall be divided
into 4 fields :
i) Message field with display of present time and date
ii) Display field for single line diagrams
iii) Navigation bar with alarm/condition indication
iv) Real time bus energization status with distinguishable colours i.e. for live &
dead section of SLD.
For display of alarm annunciation, lists of events etc a separate HMI View node.
shall be provided.
All operations shall be performed with mouse and/or a minimum number of
function keys and cursor keys. The function keys shall have different meanings
depending on the operation. The operator shall see the relevant meanings as
function tests displayed in the command field (i.e. operator prompting). For
control actions, the switchgear (i.e. circuit breaker etc.) requested shall be
selectable on the display by means of the cursor keys. The switching element
selected shall then appear on the background that shall be flashing in a different
color. The operator prompting shall distinguish between:-
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
15.22. DOCUMENTATION
The following documents shall be submitted for employer’s approval during
detailed engineering:
(a) System Architecture Drawing
(b) Hardware Specification
(c) Sizing Calculations of various components
(d) Response Time Calculation
(e) Functional Design Document
(f) Clear procedure describing how to add an IED/ bay in future covering all
major suppliers
The following documentation to be provided for the system in the course of the
project shall be consistent, CAD supported, and of similar look / feel. All CAD
drawings to be provide in “dxf” format and also acrobat format.
List of Drawings
Substation Automation System Architecture
Block Diagram
Guaranteed Technical parameters, Functional Design Specification and
Guaranteed availability and reliability
Calculation for power supply dimensioning
I/O Signal lists
Schematic diagrams
List of Apparatus
List of Labels
Logic Diagram (hardware & software )
Control Room Lay-out
Test Specification for Factory Acceptance Test (FAT)
Product Technical Manuals
Application Manuals
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Assembly Drawing
Operator’s Manual
Testing and Commissioning Manuals
Complete documentation of implemented protocols between various
elements
Listing of software and loadable in CD ROM
Other documents as may be required during detailed engineering
Two sets of hard copy and Four sets of CD ROM containing all the as built
documents/drawings shall be provided.
Training offered shall be free of cost to the Employer except the logistic.
On Site Training:
After successful commissioning of the entire SAS, the contractor will impart on-
site training in following areas:
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
The Contractor shall submit the training modules for approval of the Employer.
The training durations mentioned above is tentative only. Actual duration of the
training shall be as per approved training module.
15.24. MAINTENANCE
Outage terms
1) Outage
The state in which substation automation system or a unit of SAS is unavailable
for Normal Operation as defined in the clause above due to an event directly
related to the SAS or unit of SAS. In the event, the Employer has taken any
equipment/ system other than Sub-station Automation System for
schedule/forced maintenance, the consequent outage to SAS shall not be
considered as outage for the purpose of availability.
5) Availability
Each SAS shall have a total availability of 99.98 % i.e. the ratio of total time
duration minus the actual outage duration to total time duration.
system shall be taken over by the employer and then the guarantee period shall
start along with the whole facilities.
15.27. SPARES
Consumables
All consumables such as paper, cartridges shall be supplied by the contractor till
the SAS is taken over by the Employer.
Availability Spares:
In addition to mandatory spares as listed in below for SAS, the bidder is
required to list the recommended spares along with unit prices, which may be
required for ensuring the guaranteed availability of the system. During the entire
guarantee period including the pre-commissioning and commissioning periods,
the successful contractor will have to make available at site his recommended
spares.
Based on the requirement of recommended spares during the entire guarantee
period, the Employer will decide the final list of spares that the Employer will
procure for safe running of the system after the guaranteed period. The
contractor is bound to supply these spares promptly.
i) Station HMI & Redundant Station HMI (in Hot-stand by mode) of Latest
Configuration and Latest OS Software with CD & DVD Multilayer Read, write,
Rewrite with Possible all types of formats, Hard disk capacity of 1TB, Key
Board, Optical Mouse, integrated VGA, Integrated LAN, 25” or More TFT
Monitor (4:3 Screen).
ii) Engineering Station & Disturbance Recorder Work Station (Maintenance
HMI)
iii) Gateways with PLCC/Fibre Optic Modem
iv) Required Inverter/UPS for 3 hour back up
v) List of Printers with / without Printer server
1. Colour Laser Printer– 1 No. (Print, Scan, Fax & Xerox) (For Reports &
Disturbance records),
2. Line Printer - (For Alarms and Sequence of Event recorder)
3. Dot matrix printer Multi sheet paper Model – For log sheets, regular
parameters at 15 min duration).
vi) All interface equipment for gateway to SLDC.
vii) Communication infrastructure between Bay level units, Station HMI,
Printers, gateways, redundant LAN etc. as required. (Armoured FO and Cu
CHAPTER 14: TECHNICAL SPECIFICATION FOR CONTROL & RELAY PANEL
Cables) as required.
viii) BCUs for Sub Station Auxiliaries.
ix) Any other equipment as necessary.
For all the SAS equipment, the power supply unit shall have dual mode i.e.
main & redundant card, in case of any one card fail, the IED/Component of SAS
shall have to switch over to redundant card and to generate alarm for the outage
of the card.
All the type of cables used for LAN (Bay level & Station level) shall be
Armoured type.
The above Architecture is typical. The contractor is to consider the SLD of respective substation for detail
BoQ, particularly for Ethernet Switches & BCUs.
ANNEXURE II
List of Analogue and Digital Inputs/ Outputs for SAS
1. Basic Monitoring requirements are:
o Switchgear status indication
o Measurements (U, I, P,MVA Q, f, sequence components, pf, phase angle, THD & TDD,
Synchrocheck information i.e. ΔF, ΔV, Δφ; Active & Reactive energy)
o Event
o Alarm
o Winding temperature if transformers/ reactors
o Ambient temperature
o Status and display of station auxiliary ac & dc supply
o Status display of transformer fire protection system
o Acquisition of all counters in PLCC panels
o from PLCC or independently by counting the receive/send commands
o Acquisition of alarm and fault record from protection relays
o Disturbance records
o Monitoring the state of batteries by displaying DC voltage, charging current and load current etc
for both 220/110-volt station & communication 48-volt batteries
o Tap-position of Transformer
1) Analogue inputs
o For line R, Y, B phase line currents & R-N, Y-N, B-N phase voltages
o For transformers R, Y, B phase line currents for HV & LV
OTI & WTI
Tap position
2) Digital inputs
o Line bays
Status of each pole of CB
Status of isolator, earth switch
CB trouble
CB operation / closing lock out
Pole discrepancy operated
Trip circuit faulty
LBB operated
Bus bar protection trip operated
Breaker auto reclosure operated
Tie/ transfer breaker auto reclosure operated
AR lock out
Trip transfer sent/ received
Main I / II DPR operated
Directional E/F operated
Fuse failure alarm
PSB alarm
Broken Conductor alarm
Under voltage alarm
SOTF trip
Carrier aided trip
Main I/ II Zone 2/ Zone III trip
Back up O/C or E/F operated
PLCC protection channel I/ II failed
PLCC speech failed
BCU/ BPU failed
o Transformer bays
Standard DR Signal
MAIN-1
(Limited to 16
S.No. Channel Description Characters) 7 characters Triggers COMMENTS
BUSBAR OPERATED
20 (M1/M2) BUSBAR_OPTD BB_OPD Y
MAIN-2
(Limited to 16
S.No. Channel Description Characters) 7 characters Triggers COMMENTS
MAIN/TIE CB POLE
20 DISCREPANCY M/T_CB_POLE_DISC M/T_PLDSC N
25 OPTIONAL
26 OPTIONAL
27 OPTIONAL
28 OPTIONAL
29 OPTIONAL
30 OPTIONAL
31 OPTIONAL
32 OPTIONAL
MAIN-1/2
Main 1
A Configuration of ANALOG CHANNELS
(Limited to 16
S.No. Channel Description Characters) 7 characters Triggers COMMENTS
MAIN1/2 CARRIER
13 RECEIVE MAIN1/2_CARR_REC M1/2_CR N MAIN-1/2
DT RECEIVE CHANNEL-
14 1/2 DT_REC_CH1/2 DTRC1/2 Y
BUSBAR OPERATED
20 (M1/M2) BUSBAR_OPTD BB_OPD Y
MAIN/TBC LBB
21 OPERATED M/T_LBB_OPTD M/T_LBB Y
MAIN-2
(Limited to 16
S.No. Channel Description Characters) 7 characters Triggers COMMENTS
MAIN/TBC CB POLE
20 DISCREPANCY M/T_CB_POLE_DISC M/T_PLDSC N
25 OPTIONAL
26 OPTIONAL
27 OPTIONAL
28 OPTIONAL
29 OPTIONAL
30 OPTIONAL
31 OPTIONAL
32 OPTIONAL
Standardized
S.No. Channel Description Channel Name COMMENTS
DIFFERENTIAL PROTECTION
5 OPERATED DIFF_PROTN_OPTD DIF_OPD Y
IF
23 DTOC OPTD DTOC_OPTD DTOCOPD Y APPLICABLE
29 OPTIONAL
30 OPTIONAL
31 OPTIONAL
32 OPTIONAL
(Limited to 16
S.No. DIGITAL CHANNELS Characters) 7 characters Triggers
DIFFERENTIAL PROTECTION
5 OPERATED DIFF_PROTN_OPTD DIF_OPD Y
HV BACKUP PROTECTION
7 OPERATED HV_B/U_PROTN_OPD HVBUOPD Y
M/T_HV_LBB
DIFFERENTIAL PROTECTION
3 OPERATED DIFF_PROTN_OPTD DIF_OPD Y
7
S.No. Channel Description (Limited to 16 Characters) characters Triggers
DIFFERENTIAL PROTECTION
3 OPERATED DIFF_PROTN_OPTD DIF_OPD Y
DIFFERENTIAL PROTECTION
3 OPERATED DIFF_PROTN_OPTD DIF_OPD Y
DIFFERENTIAL PROTECTION
3 OPERATED DIFF_PROTN_OPTD DIF_OPD Y
8 SPI START, Z1 R PH
9 SPI START, Z1 Y PH
10 SPI START, Z1 B PH
11 SPI START, Z2
12 SPI START, Z3
13 SPI START, Z4
14 SPI START, Z5
15 SPI TRIP, Z1 R PH Y
16 SPI TRIP, Z1 Y PH Y
17 SPI TRIP, Z1 B PH Y
System
30 Diagnosis
(SON) TIME SYNCHRONIZATION ERROR Y
System
31 Diagnosis
(SON) M1 IED UNHEALTHY Y
32 SPI START AR
34 SPI DT SEND CH 1 Y
35 SPI DT SEND CH 1 Y
36 SPI DT RECEIVE CH 1 Y
37 SPI DT RECEIVE CH 2 Y
System
8 Diagnosis
(SON) TIME SYNCHRONIZATION ERROR Y
System
9 Diagnosis
(SON) DIFFRENTIAL IED UNHEALTHY Y
FIRE PROTECTION R PH
51
SPI OPERATED Y
FIRE PROTECTION Y PH
52
SPI OPERATED Y
FIRE PROTECTION B PH
53
SPI OPERATED Y
55
SPI MAIN CB R PH OPEN
System
4 Diagnosis
(SON) TIME SYNCHRONIZATION ERROR Y
System
5 Diagnosis
(SON) DIFFRENTIAL IED UNHEALTHY Y
DIRECTIONAL OVERCURRENT
3
SPI START Y
DIRECTIONAL OVERCURRENT
4
SPI TRIP Y
System
6 Diagnosis
(SON) TIME SYNCHRONIZATION ERROR Y
System
7 Diagnosis
(SON) M1 IED UNHEALTHY Y
WHETHER ALARM TO
SL.NO.
TYPE EVENT/ALARM NAME BE GENERATED
System
5 Diagnosis
(SON) DIFFRENTIAL IED UNHEALTHY Y
TIE CB R PH OPEN Y
44
SPI
APPLICABLE FOR
52 SWITCHABLE REACTOR
SPI REACTOR CB R PH OPEN APPLICATION
REACTOR CB Y PH OPEN
53
SPI
System
1 Diagnosis
(SON) TIME SYNCHRONIZATION ERROR Y
System
2 Diagnosis
(SON) DIFFRENTIAL IED UNHEALTHY Y
21
SPI BUCCHOLZ SPARE PH ALARM Y
1 SPI START Z1
2 SPI Z1 TRIP Y
System
6 Diagnosis
(SON) TIME SYNCHRONIZATION ERROR Y
System
7 Diagnosis
(SON) M1 IED UNHEALTHY Y
WHETHER ALARM TO
SL.NO.
TYPE EVENT/ALARM NAME BE GENERATED
4 System
Diagnosis
(SON) TIME SYNCHRONIZATION ERROR Y
System
5 Diagnosis
(SON) M1 IED UNHEALTHY Y
7
WHETHER
ADDITIONAL
SL.NO. TYPE EVENT/ALARM NAME ALARM TO BE
REMARKS
GENERATED
BLOCK AUTORECLOSE
3 SPI Y
FUNCTION
Y
STATUS 2 AUTORECLOSE IN
PROGRESS
STATUS 3 AUTORECLOSE
Y
SUCCESSFUL
Available in
STATUS 10 AUTORECLOSE
Edition 2 IEDs, not
UNSUCCESSFUL
in Edition 1 IEDs
5 CMD BAY_CB_COMMAND
BAY_CB_OPEN PERMITTED OR
6 SPI
ENABLED
BAY_CB_CLOSE PERMITTED OR
7 SPI
ENABLED
IF BUS EARTH
15 DPI BAY_89AE_ISOLATOR POSITION
SWITCH IS IN
THE BAY FOR
16 CMD BAY_89AE_ISO COMMAND WHICH THE
ASSIGNMENT IS
BAY_89AE_ISO OPEN BEING DONE,
17 SPI CSWI3 SHALL
PERMITTED OR ENABLED
BE USED FOR 89
18 SPI BAY_89AE_CLOSE PERMITTED AE 1, i.e. BUS
OR ENABLED EARTH SWITCH.
FOR BAY SIDE
EARTH SWITCH
(89AE2)
SEPARATE
LOGICAL NODE
CSWI 10 IS
PROVIDED
BELOW
19 DPI BAY_89 B_ISOLATOR POSITION
BAY_89AE 2_ISOLATOR
43 DPI
POSITION USED FOR
SECOND EARTH
44 CMD BAY_89AE 2_ISO COMMAND
SWITCH OF
BAY_89AE 2_ISO OPEN ISOLATOR,
45 SPI
PERMITTED OR ENABLED WHEN BUS
EARTH SWITCH
BAY_89AE 2_CLOSE PERMITTED IS PROVIDED
46 SPI
OR ENABLED
THE LOGICAL NODES FOR ISOLATOR & EARTHSWITCHES FOR 3 PH ICTs &
REACTORS , e.g 89 RR,RR1,RR2 & RE and for 89TR,TR1,TR2,TRE MAY BE ASSIGNED AS PER
AVAILABILITY
System
TIME SYNCHRONIZATION
47 Diagnosis Y
ERROR
(SON)
System
48 Diagnosis BCU UNHEALTHY Y
(SON)
CONDITIONS OK FOR
49 SPI
SYNCHRONIZATION
FOR BCUs
67 SPI BUS VT MCB TRIP Y HAVING BUS VT
INPUT
48 V DC
1. Voltage of 48 V DCDB 1
2. Voltage of 48 V DCDB 2
3. Current from 48 V Battery set 1
4. Current from Battery Set 2
5. Current from 48 V Charger 1
6. Current from 48 V Charger 2
7. Battery 1 Output Voltage
8. Battery 2 Output Volatge
9. Charger Trouble 1
10. Charger Trouble 2
11. Charger 1 on Boost
12. Charger 1 on Float
13. Charger 1 Failure (Float)
14. Charger 1 Failure (FCBC)
15. Charger 2 on Boost
16. Charger 2 on Float
17. Charger 2 Failure (Float)
18. Charger 2 Failure (FCBC)
19. Charger 1 Float Current
20. Charger 1 Boost Current
21. Charger 2 Float Current
22. Charger 2 Boost Current
23. Input MCCB Incomer-1 ON (DCDB)
24. Input MCCB Incomer-2 ON (DCDB)
25. DCDB Bus coupler MCCB OFF
26. DC Earth Fault Relay Operated Sec-I
27. DC Earth Fault Relay Operated Sec-II
28. 415 V AC Supply MCCB-1 Trip
29. 415 V AC Supply MCCB-2 Trip
30. Over Temperature Indication
31. DC Overvoltage and Undervoltage relay operated
32. AC Supply Trouble (Charger)
DG Set
1. DG Set Breaker ON
2. DG Set Breaker OFF
3. Low Lube Oil Pressure
4. High Water Temperature
5. Engine Over Speed
6. Low Fuel in Service Tank
7. Over load Trip
8. Voltage RY, YB and BR
9. Current from DG set R, Y and B
Fire Fighting
1. Zone 1 Fire
2. Zone 2 Fire
3. Zone 3 Fire
4. Zone 4 Fire
5. Zone 5 Fire
Other Signal
1. PLCC Exchange Fail
2. Time Synch. Signal Fail
3. GPS Signal Fail
4. Current from Station transformer
5. Voltage from Station Transformer
6. Isolator Status of Station Transformer
7. Ambient Temperature .
CHAPTER 16: TECHNICAL SPECIFICATIONS FOR 400, 220 & 132KV GIS
400, 220, 132 KV GIS SUB-STATION SYSTEM
GENERAL DESCRIPTION OF GAS INSULATED SWITCHGEAR.
STANDARD SPECIFICATIONS
The switchgear conforms to the following IEC standards:
SWITCHGEAR, GENERAL:
IEC 62271-1: High-voltage switchgear and control gear Part 1: Common
specifications
IEC 62271-203: High-voltage switchgear and control gear Part 203: Gas-insulated
metal-enclosed switchgear for rated voltages above 52 kV Circuit-
breakers:
IEC 62271-100: High-voltage switchgear and control gear Part 100: Alternating-
current circuit-breakers
IEC 62271-101: High-voltage switchgear and control gear Part 101: Synthetic
testing Disconnectors, earthing switches.
IEC 62271-102: High-voltage switchgear and control gear Part 102: Alternating-current
dis-connectors and earthing switches Instrument transformers:
IEC 62271-303: High-voltage switchgear and control gear – Use and handling of
sulphur hexafluoride (SF6)
IEC 61000 Electromagnetic compatibility (EMC)
IEC 60060 High voltage test techniques
IEC 60071 Insulation co-ordination
IEC 60255 Electrical relays
IEC 60265 High voltage switches
IEC 60270 High-voltage test techniques - Partial discharge measurements
IEC 60376 Specification and acceptance of new sulphur hexafluoride
IEC 60480 Guide to checking of sulphur hexafluoride (SF6)
IEC 60529 Degrees of protection provided by enclosures (IP Code)
IEC 60815 Guide for the selection of insulators in respect of polluted conditions
IEC 61869/60044/60185/60186: Instrument transformers
IEC 60364 / 60479 / 60621 / IEEE std. 80/CIGRE 44: Standards for station grounding.
CENELEC/SVDB Pressure vessel code
IEC 693: Seismic Design
CABLE CONNECTIONS:
IEC 62271-209: High-voltage switchgear and control gear Part 209: Cable connections
for gas-insulated metal-enclosed switchgear for rated voltages above 52 kV – Fluid-
filled and dry- type cable-terminations
OUTDOOR BUSHINGS:
IEC 60137 : Insulated bushings for alternating voltages above 1000 V Transformer
direct connection:
IEC 61639 : Direct connection between power transformers and gas-insulated
metal-enclosed switchgear for rated voltages of 72.5 kV and
above.
SURGE ARRESTERS:
IEC 60099-4: Surge arresters Part 4: Metal-oxide surge arresters without gaps for A.C.
Systems
SF6-Gas:
IEC 60480: Guidelines for the checking and treatment of sulphur hexafluoride (SF6)
taken from electrical equipment and specification for its re-use
IEC/TR 62271-303: High-voltage switchgear and control gear Part 303: Use and
handling Of sulphur hexafluoride (SF6)
LOCAL CONTROL CUBICLES:
IEC 61439 -1: Low-voltage switchgear and control gear assemblies Part 1: General
rules EMC.
IEC 62271-1: High-voltage switchgear and control gear Part 1: Common specifications
ENCLOSURE
CENELEC standard mentioned above.
MODULAR DESIGN
Housings and expansion joints together form the pressure-resistant enclosure of the
switchgear. The housings are made of cast or welded aluminium, the expansion joints of
high-grade steel and the covers of steel or aluminium. The switchgear modules are
single-phase or three-phase encapsulated.
The manufacturing and testing of the housings are state-of-the-art technology. Each,
housing is subject to a pressure and gas tightness test and complies with the
requirements of the relevant CENELEC standard.
SURFACE TREATMENT
Steel (covers):
Indoor structure: Hot galvanised or painted
Outdoor structure: Hot galvanised and painted
High-Grade Steel (expansion joints):
Indoor Pre-treatment: none
Paint work: none
Outdoor Pre-treatment: degrease
Paint work: same as housings of cast aluminium
CAST-ALUMINIUM:
Pre-treatment (indoor and outdoor): Sand-blast or degrease alkaline
Internal surfaces (cast-aluminium): Seevenax protective paint RAL 7038 (grey)
Internal surfaces (aluminium wrought alloy): without surface treatment
External surfaces: material description: high-resistant 2-component polyurethane paint
Shade: RAL 9010 (white)
GAS
Gas compartments, monitoring of gas compartments:
• SF6 serves as insulation for the en osure of several separately-sealed gas
compartments
• static filters in all gas compartments – with single-phase encapsulation for each phase
for single phase encapsulation design - absorb moisture and decomposition products; the
filter material is placed in filter bags which are supplied in airtight cans
• all gas compartments are equipped with rupture diaphragms and, if necessary, with gas
diverter nozzles; these nozzles are arranged in a way that, if the rupture diaphragm
bursts, the gas flow is guided away in a direction not unnecessary hazardous to either
personnel or equipment
• the modules of circuit-breakers, voltage transformers, cable connection module and
surge
arresters form separate gas compartments.
• the disconnector gas compartment can contain other device like earthing switch
• the switch operating shafts are supported and provided with lip seals against pressure
and vacuum loss in such a way that during the evacuation process before
commissioning no air can penetrate and no SF6 can escape during operation; the
leakage rate is less than 0.5 % SF6 per year and gas compartment.
• the gas pressure is monitored by density monitors with indication; density monitors are
installed directly at the gas compartment they monitor.
16.1. GENERAL SPECIFICATION
The intent of this specification is to provide the work enumerated to be fully complete in
every detail for the function designated. It is hereby required that the BIDDER, in
accepting the contract, agrees to furnish all apparatus, appliances, material not herein
specifically mentioned or included, but which may be found necessary to complete,
perfect or test any portion of the apparatus or equipment herein specified in a substantial
manner, and in compliance with the requirements implied in this specification and
without extra cost to the PURCHASER/OWNER. The GIS manufacturer should depute
testing and commissioning engineer(s) with necessary HV testing kit of appropriate
rating duly calibrated with calibration certificates.
NOTE: The Bus of the 400kV, 220 KV& 132kV GIS System shall be of Aluminium
Alloy of adequate size and should be capable of withstanding the short circuit current
level of 63kA, 50kA, 40 KA respectively for 3 sec. Care should be taken while designing
the GIS system.
The tender work shall be carried out in accordance with the requirements of this
specification and shall include design, manufacture, supply, testing at the factory,
shipping to site, installation and testing at site and commissioning of the GIS and
associated equipment.
For 400 kV and above voltage class GIS, wherever required, stairs, fixed ladder,
platforms, and walkways for operation and maintenance access to the operating
mechanism and monitoring devices should be provided to permit access. The
structures shall be either aluminum or hot-dipped galvanized steel. All
structures, stairs, platforms, and walkways shall conform to the relevant
occupational health and safety regulations and designed in accordance with the
latest industry standards and guidelines. The platforms and walkways shall have
anti-skid surfaces that can be walked on. Handrails shall be provided where
necessary. The GIS supplier shall provide 3-D arrangement drawing to show the
location of equipment and access to it.
In addition to above suitable portable scissor lift shall be provided for access of
distant portion of GIS installation.
16.3.1.1 SECTIONALIZATION
The switchgear must be sectionalized, with gas tight barriers between sections or
compartments. The sections shall be designed
i) To minimize operational shut down when the gas pressure is
reduced due to Leakage or for maintenance purposes.
ii) To minimize the quantity of gas that has to be evacuated and
recharged before and after maintaining any item of equipment.
Continuous bus lengths without gas segregation shall not be acceptable.
Each section shall be provided with necessary valves to allow evacuation and refill of
gas without evacuation of any other section.
The gas system proposed shall be submitted with the proposal. External fixtures shall be
of non-corrosive material and be capped wherever required.
For the purpose of gas monitoring and maintenance, the GIS shall be provided with gas
density monitoring device along with temperature compensated gas density switch
having two stage contacts in each gas compartment.
Pressure relief devices shall be used wherever required.
16.3.1.18 REPAIR
In case of any internal fault in the bus bar or bus bar dis - connector, circuit breaker,
grounding switches etc., repair works must be possible with at least one busbar in
service. In case of any type of fault in any section of the line bay, transformer bay or bus
coupler bay modules repair works must be possible.
Any failure shall be immediately signaled by the systems inherent self-supervision with
clear description of the nature and the location of this failure. Generally, any failure shall
have impact only on the direct related devices and the rest of the substation shall remain
in normal operation.
16.3.1.19 REMOVAL OF COMPONENTS
The GIS shall be designed so that any component of the GIS can be easily removed. As
minimum flexibility in the layout arrangement, it shall be possible to remove the circuit
breaker with both bus bar remaining in service and it shall be possible to remove the dis
connector of the bus bars, with one bus bar remaining in service.
Service continuity requirement:
The GIS equipment with the given bus switching arrangement is divided into
different gas compartments. During the work such as a fault repair or major
maintenance, requiring the dismantling of a gas compartment for which more
than one compartments may need to be de-gassed. Working conditions, method
statements and procedures are to be furnished by the GIS manufacturer in order
to ensure equipment and operating personnel’s safety and to achieve following
Service continuity conditions to the extent possible:
For One & half breaker bus switching scheme during a fault in CB
compartment, no bus bar and feeder is permitted out of service during
maintenance and repair/replacement.
For Double Main bus switching scheme during a fault in CB compartment, no
bus bar permitted out of service during maintenance and repair/replacement.
During a fault in GIS compartment other than CB compartment, maximum one
bus bar and/or one feeder permitted out of service during maintenance and
repair/replacement.
16.3.1.20 EARTHING OF THE SWITCHGEAR
GROUNDING: The grounding system shall be designed and provided as per
IEEE-80-2000 andCIGRE-44 to protect operating staff against any hazardous
touch voltages and electro-magnetic interferences.
The GIS supplier shall define clearly what constitutes the main grounding bus of
the GIS. The contractor shall supply the entire material for grounding bus of GIS
viz conductor, Clamps, joints, operating and safety platforms etc. The contractor
is also required to supply all the earthing conductors and associated hardware
material for connecting all GIS equipment, bus ducts, enclosures, control
cabinets, supporting structure, GIS surge arrestor etc. to the ground bus of GIS.
The enclosure of the GIS may be grounded at several points so that there shall
be grounded cage around all the live parts. A minimum of two nos. of grounding
connections should be provided for each of circuit breaker, potential
transformers, disconnectors, current transformers, grounding switches, high
speed earth switches, cable terminals, surge arrestors, and at each end of the bus
bars. The grounding continuity between each enclosure shall be effectively
interconnected externally with Copper /Aluminum bonds of suitable size to
bridge the flanges. Subassembly to subassembly bonding shall be provided to
bridge the gap & safe voltage gradients between all intentionally grounded parts
of the GIS assembly & between those parts and the main grounding bus of the
GIS.
Each marshaling box, local control panel, power and control cable sheaths and other non-
current carrying metallic structures shall be connected to the grounding system of GIS
via connections that are separated from GIS enclosures.
The grounding connector shall be of sufficient mechanical strength to withstand
electromagnetic forces as well as capable of carrying the anticipated maximum fault
current without overheating. At least two grounding paths shall be provided to connect
each point to the main grounding bus. Necessary precautions should be under taken to
prevent excessive currents from being induced into adjacent frames, structures of
reinforcing steel and to avoid establishment of current loops via other station equipment.
The enclosure grounding system shall be designed to minimize circulating currents and
to ensure that the potential rise during an external or internal fault is kept to an
acceptable level. The guidelines of IEEE Std. 80-2000 on GIS grounding, especially the
transient ground potential rise caused by high frequency phenomena, shall be taken into
consideration while designing the grounding system for GIS. The manufacturer shall
furnish readily accessible connectors of sufficient mechanical strength to withstand
electromagnetic forces as well as capable of carrying the anticipated maximum fault
current without overheating by at least from two paths to ground from the main ground
bus. The manufacturer shall provide suitable measure to mitigate transient enclosure
voltage caused by high frequency currents caused by lightning strikes, operation of surge
arrester, ph/earth fault and discharge between contacts during switching operation. The
grounding system shall ensure safe touch and step voltages in all the enclosures. The
manufacturer shall provide suitable barrier of non-linear resistor/counter discontinued
SF6/Air termination SF6/HV cable bushing etc. to mitigate transient enclosure voltage.
Online Partial Discharge Monitoring System (Applicable for 765kV& 400 kV GIS)
GIS equipment shall be designed so as to minimize
partial discharge or other electrical discharge. A state-of-
the art Partial Discharge Monitoring system shall be
provided to monitor the entire GIS installation.
An on-line continuous Partial Discharge Monitoring
(PDM) system shall be designed to provide an automatic
facility for the simultaneous collection of PD data at
multiple points on the GIS & its associated GIB ducts
and Voltage Transformers adopting UHF technique. The
data stored shall provide a historical record of the
progress of PD sources and shall identify the areas of
maximum activity.
On-line continuous Partial Discharge Monitoring (PDM)
system shall be capable for measuring PD in charged GIS
environment as EHV which shall have bandwidth in
order of 100 MHz–2GHz with possibility to select a wide
range of intermediate bandwidths for best measurement
results. The principle of operation shall be based on UHF
principle of detection.
The scope shall cover Engineering, supply, installation,
testing and commissioning of partial discharge
continuous monitoring system, with all necessary
auxiliaries and accessories to make a complete system as
per technical specification, including site demonstration
of successful operation. Any items/accessories necessary
to make the system fully functional for the trouble free
online PD monitoring of complete GIS installation shall
be considered as included in the scope.
The PDM system shall be provided with all its hardware
and software, with readily interfacing to the UHF PD
couplers installed in the GIS of present bays and future
bays as shown in SLD plus 20% additional as extra.
Details of this shall be submitted during engineering
stage for approval.
1.1. Documentation
The contractor shall prepare and submit to the employer,
drawings, details that show the GIS design in order for the
employer to verify the equipment conform to the
specifications. The Design Document to be submitted for
review and approval are as follows:
i. Design Review Document as per clause no. 19 of this
specification
ii. Single Line Diagram
iii. Gas Schematic Diagram
iv. GTP-Guaranteed Technical Particulars
GIS layout (Plan and Section) including 3D drawing
v. GIS Component Drawings
vi. Interface modules drawing for GIS extension
vii. Rating and Name Plate Drawing
viii. GIS/LCC Schematics Drawing
ix. Foundation loading plan and detail
x. GIS Support Structure Drawing
xi. GIS platforms and Walkway Drawing
xii. GIS grounding plan and details along with design calculation
for GIS grounding
xiii. GIS key Diagram enlisting and marking each
and every GIS Module clearly and separately
identifiable (indoor and outdoor). This separately
identified module shall be complete along with its
enclosure, gasket and all active parts such as conductor,
conductor joints, corona shield etc.
xiv. Method Statement along with sequential instruction
for dismantling and assembling of all major
components of GIS exhibiting service continuity
requirement
xv. Type Test Reports
xvi. Seismic Analysis Report
xvii. Study report of VFTO generated for GIS installation for 400
kV and above.
xviii. The general arrangement drawing of
interconnecting bus-duct from GIS bay module to
XLPE cable termination end
xix. The general arrangement drawing of Terminal
connection arrangement to connect GIS duct to
SF6/Oil bushing and duct mounting arrangement
details
xx. Gas handling procedure
xxi. The design & construction proposal of the building
along with necessary information, data, and
drawings according to the complete requirements
xxii. Capacity calculation of EOT crane for GIS hall considering a
factor of safety of 5
xxiii. Method statement/ procedure of ON SITE high
voltage testing with PD measurement and Switching
Impulse test
xxiv. Additional CB data to be furnished during detailed
engineering :
a) Design data on capabilities of circuit breakers in
terms of time and number of operations at duties
ranging from 100 % fault currents to load
currents of the lowest possible value without
requiring any maintenance or checks.
b) Curves supported by test data indicating the
opening time under close open operation with
combined variation of trip coil voltage and
hydraulic pressure.
c) Contact Travel: Operating mechanism operating
shaft travel and contact overlap of Circuit
Breaker to be provided
xxv. PD Monitoring System
a) The technical proposal for PDM system along
with detailed design documentation.
b) Data sheet for the UHF couplers.
c) The Sub-station GIS layout as a separate
drawing indicating position of spacers, spread
over of PD sensors with distance, sensor
identification, the detector unit identification
etc., total numbers of offered UHF Sensors
along with attenuation calculation.
d) Guaranteed Technical Particulars & Data Sheet
for various components used in the PDM
system.
e) Electromagnetic compatibility Test Reports.
f) List of critical spares.
xxvi. Installation and Operation & Maintenance Manual
16.3.1.24DESIGN REVIEW
i. Design reviews shall be conducted by Employer; however
the entire responsibility of design shall be with the supplier.
ii. Employer may also visit to the supplier’s works to inspect
design, manufacturing and test facilities.
iii. The design review will commence after placement of award
with the successful contractor and shall be finalized before
commencement of manufacturing activity. These design
reviews shall be carried out in detail to the specific design
with reference of the GIS under the scope of this
specification. Employer reserve the right to waive off the
design review during detailed engineering.
iv. The design review shall be conducted generally following
the, “User Guide for the application of Gas Insulator
Switchgear (GIS) rated voltage of 72.5kV and above” –
CIGRE report No. 125 prepared by CIGRE Working Group
23.10.
v. The manufacturer will be required to demonstrate the use of
adequate safety margins for thermal, mechanical, dielectric,
insulation coordination and vibration etc. design to take into
the account the uncertainties of his design and
manufacturing processes.
vi. The scope of such a design review shall at least include the
following:
d) The breakers are to be re-strike-free. The circuit breakers shall be designed for
high speed single and three phase reclosing with an operating sequence and
timing as specified. The Circuit breaker shall be C2 – M2 class type. Breaker
disposition must be horizontal to provide higher mechanical stability and ease in
maintenance. The operating principle of the breaker shall ensure minimized
dynamic floor loading. Low reaction forces on foundations especially
dynamically, are favourable and considered in the evaluation.
2. Duty Requirements
Circuit breaker shall meet the duty requirements for any type of fault or fault location
also for line charging and dropping when used on 400 KV, 220 kV, 132 KV
effectively grounded system and perform make and break operations as per the
stipulated duty cycles satisfactorily.
The circuit breaker shall be capable of:
i) Interrupting the steady and transient magnetizing current
corresponding to connected transformers.
ii) Interrupting line/cable charging current as per IEC without re-strikes
and without use of opening resistors.
iii)Clearing short line fault (Kilometric faults) with source impedance
behind the bus equivalent to symmetrical fault current specified.
iv) Breaking 25% the rated fault current at twice the rated voltage under
phase opposition condition.
vi) The breaker shall satisfactorily withstand the high stresses
imposed on them during fault clearing, load rejection and re-
energisation of lines with trapped charges.
Pre insertion resister: 765kV/400 kV circuit breakers for line bay (as per the
provisions of bid proposal sheet) shall be provided with single step pre insertion closing
resistors (wherever the requirement of PIR is explicitly specified so ) to limit the
switching surges to a value of less than1.9 p.u for 765kV and 2.3 p.u for 400kV. PIR
contacts should open immediately after closing of main contacts or At least 5 ms prior
to opening of main contacts at rated air/gas pressure where the PIR contacts remain
closed. The resistor shall have thermal rating for the following duties :
vii) Terminal fault : Close.... 1 Min........ Open...... Close Open
2 min........ Close .......
1 Min Open Close Open.
Each of the foregoing supplies shall be made available by the Purchaser at the
terminal point for each circuit breaker for operation of accessories and auxiliary
equipment. Supplier’s scope includes supply of interconnecting cables, terminal
boxes etc. The above supply voltage may vary as below and all devices shall be
suitable for continuous operation over entire range of voltages.
I) AC supply : voltage ± 10% frequency ± 5%
II) DC supply : - 15% to + 10%
3. Constructional features
a) All making and breaking contacts shall be designed to have adequate thermal
and current carrying capacity for the duty specified and to have a life expectancy
(as per relevant standards) so that frequent replacements due to excessive
burning will not be necessary. Provision shall be made for rapid dissipation of
heat generated by the arc on opening.
b) Main contacts shall be first to open and last to close so that there is little contact
burning and wear. Contacts shall be kept permanently under pressure of SF6 gas.
c) Arcing contacts shall be first to close and last to open. These shall be easily
accessible for inspection & replacements.
d) Any devices provided for voltage grading to damp oscillations or to prevent re-
strike prior to the complete interruption of the circuit or to limit over voltage on
closing shall have a life expectancy comparable to that of the beaker as a whole.
e) Breaker shall be so designed that when operated within its specified rating, the
temperature of each part is limited to the values consistent with a long life or the
material used. The temperature shall not exceed the values indicated in IEC
60694 / IEC 62271 under specified ambient conditions.
f) The material used in the construction of the circuit breaker shall be such as to be
fully compatible with SF6 gas decomposition products. All gasket surfaces shall
be smooth, straight and reinforced
4. Breaking capacity
The total breaking time from energizing of the trip coil at rated control voltage to final
arc extinction shall be as short as possible.
The circuit breaker shall be capable of breaking all currents from zero up to the specified
maximum fault current in accordance with the relevant IEC publications. Official test
reports shall be submitted with the tender as evidence that the offered circuit breaker
meets the specific rating.
5. Interrupting Duty:
Circuit breakers must be capable of coping with the interrupting duties produced by the
switching of transformer magnetizing currents, line charging currents, cable charging
currents, capacitor banks, short-line faults and out-of-phase switching duties.
6. Auto-reclosing
The circuit-breakers shall be capable of tripping and re closing according to the specified
duty cycle.
7. Closing devices
All electrically operated closing devices and any mechanism charging motors or devices
shall be suitable for operation at any voltage between 110% and 85% of the nominal
control voltage measured at the device terminals. The breaker shall close correctly when
an electrical closing pulse of 50 ms duration is applied to the closing coil. Closing coil
rating shall be as per GIS manufacturer’s standard.
8. Tripping devices
All electrical tripping devices shall be suitable for operation at any voltage between
110% and 70% of the nominal voltage, measured at the device terminals. Tripping
device tolerance shall be as per IEC/ANSI. An emergency hand tripping (mechanical)
device shall be provided in the operating mechanism. Trip coil rating shall be as per GIS
manufacturers standard
9. Operating mechanism
Spring-Spring/Hydromechanical – spring operating mechanism shall be supplied for
each circuit-breaker. Electric motor for the mechanism shall be DC operated. In case of
failure of auxiliary supply, the mechanism shall have sufficient energy stored to perform
at least a O-CO cycle. Additionally, it should also be possible to operate the mechanism
manually as a safety requirement. (e.g. to ensure that the stored energy has been released
in case of any assembly, maintenance or replacement work)
In order to reduce maintenance work and outage time, pneumatic operating mechanisms
or pure hydraulic mechanism is not be accepted. The mechanism shall be strong and
rigid and shall be suitable for high speed auto re-closing and other duties specified. The
mechanism shall be anti-pumping and trip free under every method of closing.
Low stored operating energy shall be detected as per following operations:
1. start pump motor/spring charge motor
2. block auto-reclosing if stored operating energy is insufficient to complete a break-
make-break operation
3. block closing if stored operating energy is insufficient to complete a make-break
operation
4. block tripping if stored operating energy is insufficient to complete a break operation
Charging of the operating mechanism shall be possible in the event of failure of the
motor drive. The mechanism shall be in a dust and vermin proof box for indoor
installation or in a weatherproof box for outdoor installation. Each breaker shall have
sufficient auxiliary switches all wired to terminals located in the local control cubicle.
Position indicating devices: Position indicators shall be provided to clearly indicate
whether a circuit-breaker is open or closed.
Operation counter: Each circuit -breaker shall be provided with an operation counter
per mechanism to record the number of tripping operations performed.
Discrepancy circuit shall be provided which shall detect pole position discrepancy.
Design of circuit breaker shall ensure that the contacts will not ‘close’ / ‘open’
automatically upon loss of gas pressure. The circuit breaker shall retain and continue to
remain in the position prior to the loss of pressure.
10. Anti pumping
All circuit-breaker mechanisms shall be provided with means to prevent pumping while
the closing circuit remains energized, should the circuit breaker either fail to latch, or be
tripped during closing due to the operation of the protective relays.
11. Position indicating devices
Position indicators shall be provided to clearly indicate whether a circuit-breaker is open
or closed. Each circuit-breaker shall be provided with an operation counter per
mechanism to record the number of tripping operations performed.
12. Controlled Switching Device(CSD):
12.1 765kV & 400KV Circuit Breaker shall be equipped with controlled
switching device with consequent optimization of switching behavior,
when used in:
1. Switching of transformer(from 765kV and 400kV side circuit
breakers only)
2. Switching of shunt reactor
2. Operating mechanism
Electric motor for the driving mechanism shall be DC operated. Mechanisms shall be
arranged (mechanically ganged) so that all three phases of any particular earthing switch
operate simultaneously.
All mechanisms shall be suitable for electrical motor operation to achieve a fully
automatic operation in an unmanned substation. For emergency situations manual
operation shall be possible. Handles or hand cranks shall be provided.
Manual operation shall be prevented if the interlocking system does not allow the
operation of the switch.
The auxiliary energy shall be electrically uncoupled from the motor when the switch is
operated manually.
The mechanisms shall be arranged for locking in the open and in the closed position.
Facilities shall be available to allow the switch to be padlocked in any position.
3. Position indicating devices
External mechanically connected position indicators shall be provided showing
either open or close position.
16.3.2.4 FAST ACTING EARTHING SWITCH
1. General
Fast acting earthing switches shall be located at the busbar and at all external HV
connections of feeders (like HV cable or overhead line). The switching capability shall
be class B (Earthing switches designated to be used in circuits having relatively long
lines or high coupling to adjacent energized circuits) as per IEC 62271-102 Annex C
standard. Furthermore, it shall withstand the full making capability.
The fast-acting earthing switches shall comply with the following general requirements
of fast acting earthing switches and the latest revision of the relevant IEC
specifications.Fast acting earthing switches shall be three pole group operated, with one
motor operated mechanism for three phases. They shall also have facilities for
emergency manual operation and the necessary operating handles or hand cranks shall be
supplied.
Fast acting earthing switches shall be electrically interlocked to prevent the fast-acting
earthing switch from closing on an energized bus section.
All main contacts, male and female, shall either be silver plated or shall have silver
inserts.
Each fast-acting earthing switch shall open or close only due to motor-driven or manual
operation. The switch contact shall not move due to gravity or other means, even if a part
fails. Once initiated, the motor mechanism shall complete an open or close operation
without requiring the initiating contact to be held closed.
2. Operating mechanism
Electric motor for the driving mechanism shall be DC operated. Mechanisms shall be
arranged (mechanically ganged) so that all three phases of any particular fast acting
earthing switch operate simultaneously.
All mechanisms shall be equipped with a motor suitable for operation from the auxiliary
supply, and a set of springs for energy storage and closing. Motors shall be suitable for
operation at any voltage between 85% and 110% of the rated auxiliary voltage.
For emergency situations manual operation shall be possible. Handles or hand cranks
shall be provided, together with all necessary operation rods and rod guides.
The auxiliary energy shall be electrically uncoupled from the motor when the switch is
operated manually. The mechanisms shall be arranged for locking in the open and in the
closed position.
3. Auxiliary switches
Each fast-acting earthing switch shall be furnished with adequate number of electrically
independent contacts at user’s disposal. The auxiliary switches shall indicate the position
of the switch contacts, and shall be independent of the motor operation.
4. Position indicating devices
External mechanically connected position indicators shall also be provided.
16.3.2.5 CURRENT TRANSFORMERS
1. General
The current transformers shall be supplied in accordance with the following general
requirements and the latest revisions of the relevant IEC.
Each current transformer shall be arranged so that the enclosure current does not affect
the accuracy or the ratio of the device or the conductor current being measured.
Current transformer secondary cores shall be terminated to shorting terminal blocks.
It shall be possible to test each current transformer without the removal of gas through
the insulated grounding switches.
2. Position of the Current Transformers and Cores, Ratios and Characteristics.
The number and position of the current transformers relative to the circuit-breakers,
disconnectors and earthing switches shall be as detailed in the single line diagram.
However, there must have possibility of provision of CT on either side of CB.
The rating, ratio, accuracy class etc. for the individual current transformer secondary
cores shall be as PER specification. Where multi-ratio current transformers are required,
the various ratios shall be obtained by changing the effective number of turns on the
secondary winding. However, CT ratio shall be finalized during detailed engineering.
3. Rating and Diagram Plates
Rating and diagram plates shall be as specified in the IEC specification incorporating
the year of manufacture. The rated extended current rating voltage and rated thermal
current shall also be marked on the name plate. The diagram plates shall show the
terminal markings and the relative physical arrangement of the current transformer cores
with respect to the primary terminals (P1 & P2). The position of each primary terminal
in the current transformer SF6 gas section shall be clearly marked by two plates fixed to
the enclosure at each end of the current transformer.
4. Constructional Details:
The current transformers incorporated into the GIS will be used for protective relaying
and metering and shall be of metal enclosed type. The secondary windings shall be air
insulated/Gas insulated with terminals brought out for secondary connection. All the
current transformers shall have effective electromagnetic shields to protect against high
frequency transients.
Each current transformer shall be equipped with a marshalling box with terminals for the
secondary circuits, which are connected to the local control cubicle or CT secondary
terminals shall be directly terminated to the local control cubicle to avoid open circuiting
in marshalling box. The star/ delta configuration and the inter connection to the line
protection panels will be done at the CT terminal block located in the local control
cubicle.
Current transformers guaranteed burdens and accuracy class shall be as per
specifications and are to be intended as simultaneous for all cores. The wiring diagram,
for the interconnections of the three-single phase CTs shall be provided inside the
marshalling box. The current transformers shall be suitable for high speed auto re-
closing. Provisions shall be made for primary injection testing either within CT or
outside.
16.3.2.6 POTENTIAL TRANSFORMERS (PT): Bus PT
1. General
The voltage transformers shall be supplied in accordance with the following general
requirements and the latest revisions of the relevant IEC.
Each voltage transformer shall be an electromagnetic, dry type SF6 –enclosed single
phase unit with the specified ratings. The voltage transformers are to be connected as
shown in the single line diagram. (Refer to Volume III)
Voltage transformers shall be attached to the gas-insulated system in such a manner that
they can be readily disconnected from the system if required for dielectric testing. The
metal housing of the voltage transformer shall be connected to the metal enclosure of the
GIS with a flanged, bolted and gasketed joint so that the transformer housing is
thoroughly grounded to the GIS enclosure. Adequate measures shall be provided to
prevent any unacceptable impact on the secondary control and protection circuits which
might result from very fast transients (VFT) or ferro-resonance.
2. Ratios and Characteristics
The rating, ratio, accuracy class, connection, etc. for the voltage transformers shall be as
per specifications and single line diagram.
3. Rating and diagram plates
Rating and diagram plate shall be provided complying with the requirements of the IEC
specification incorporating the year of manufacture and including turns ratio, voltage
ratio, burden, connection diagram etc.
4. Secondary Terminals, Earthing, MCB's and Fuses
The beginning and end of each secondary winding and all secondary taps shall be wired
to suitable terminals accommodated in the local control cabinet for the feeder bay.
Fuses / MCBs shall be also located in the local control cabinet.
All terminals shall be stamped or otherwise marked to correspond with the marking on
the diagram plate. Secondary terminals shall have permanent marking as identification of
polarity, in accordance with IEC. Provision shall be made for earthing of the secondary
windings inside the terminal box.
The transformer shall be able to sustain full line to line voltage without saturation of
transformer. The accuracy class will be at maximum tap.
5. Constructional Details of Potential Transformers:
The potential transformers shall be located in a separate bay module on the bus and will
be connected phase to ground and shall be used for protection, metering and
synchronization.
The potential transformers shall be of inductive type, non-resistant and shall be contained
in their own-SF6 compartment, separated from other parts of installation. The potential
transformers shall be effectively shielded against high frequency electromagnetic
transients. The voltage transformers shall have three secondary windings.
Potential transformer’s secondary shall be protected by fuses for all the windings. In
addition, fuses shall be provided for the protection and metering windings for fuse
monitoring scheme. The secondary terminals of the PT’s shall be terminated to the stud
type non-disconnecting terminal blocks in the secondary boxes via the fuse.
The potential transformer should be thermally and dielectrically safe when the secondary
terminals are loaded with the guaranteed thermal burdens. The diagram for the
interconnection of the VTs shall be provided inside the marshalling box.
16.3.2.7 SF6 to AIR BUSHINGS
1. General
Outdoor SF6 to air bushings, for the connection between the GIS and overhead lines or
conventional air insulated equipment shall be furnished where specified.
OUTDOOR BUSHINGS:
Outdoor bushings, for the connection of conventional external conductors to the SF6
metal enclosed switchgear, shall be provided where specified and shall conform to the
requirements given in technical specifications. The dimensional and clearance
requirements for the metal enclosure will be the responsibility of the manufacturer and
their dimensions must be coordinated with the switchgear.
Bushings shall generally be in accordance with the requirements of IEC -60137.
2. Insulation levels and Creepage distances: All bushings shall have an impulse and
power frequency withstands level that is greater than or equal to the levels specified for
GIS. The creepage distance over the external surface of outdoor bushings shall not be
less than 31mm/kV.
SF6 to air Bushing shall be of Polymer / composite type and shall be robust and
designed for adequate cantilever strength to meet the requirement of seismic condition,
substation layout. The electrical and mechanical characteristics of bushings shall be in
accordance with IEC: 60137. Polymer / composite insulator shall be seamless sheath of
a silicone rubber compound. The housing & weather sheds should have silicon content
of minimum 30% by weight. It should protect the bushing against environmental
influences, external pollution and humidity. The hollow silicone composite insulators
shall comply with the requirements of the IEC publications IEC 61462 and the relevant
parts of IEC 62217. The design of the composite insulators shall be tested and verified
according to IEC 61462.
3. Mechanical forces on bushing terminals:
Outdoor bushings must be capable of withstanding a cantilever force as per IEC
standard.
4. Interface definition
The flange and conductor connection between bushing and GIS component shall be the
standard of the GIS supplier.
16.3.2.8 SURGE ARRESTORS
The surge arrestors shall confirm in general to latest IEC –60099-4.
Insulation co-ordination and selection of surge arrestor: The contractor shall be fully
responsible for complete insulation co-ordination of switchyard including GIS.
Contractor shall carry out detailed studies and design calculations to evolve the required
parameters locations, energy capability etc. of surge arrestors such that adequate
protective margin is available between peak impulse, surge and power frequency
discharge voltages and BIL of the protected requirement. The locations of surge arrestors
shown in single line diagram is indicative only. If the contractor feels that at some more
locations the surge arrestors are required to be provided the same should also be deemed
included in the offer.
The contractor shall perform all necessary studies and the report shall detail the limits of
all equipment parameters which could affect the insulation co-ordination. The report shall
also detail the characteristics of the surge arrestor and shall demonstrate that the selected
arrestor’s protective and withstand levels, discharge and coordinating currents and
arrestor ratings and comply with the requirement of this specification.
The contractor shall also consider in the studies the open circuit breaker condition, fast
transients generated by slow operation of disconnecting switches. The study report and
design calculations shall be submitted for Owner’s approval.
The surge arrestor shall be SF6 gas insulated metal oxide and gapless type. The metal
housing of the arrestor shall be connected to the metal enclosure of the GIS with flange,
bolted and gasketed joint so that the arrestor housing is grounded through GIS enclosure.
Surge arrestor shall be disconnect-link type and be attached to the gas-insulated system in
such a manner that they can be readily disconnected from the system while the system is
being dielectrically tested.
The surge arrester shall be of heavy-duty station class and gapless (Metal oxide) type
without any series or shunt gaps.
The surge arresters shall be capable of discharging over-voltages occurring during
switching of unloaded transformers, reactors and long lines.
Surge arresters for the 765 kV network shall be capable of discharging of severe re-
energisation switching surges on a 765kV line with surge impedance of 270hms and
capacitance of 13 nF/Km.
765 kV class arrester shall be capable of discharging energy equivalent to class 5 of IEC
for a 765 kV system on two successive operation followed immediately by 50 HZ
energisation with a sequential voltage profile as specified below:
1000 kVp for 3 peaks
910 kVp for 0.1 Sec.
885 kVp for 1 Sec.
866 kVp for 10 Secs.
Surge arresters for the 400 kV network shall be capable of discharging of severe
re- energisation switching surges on a 400 kV, 450 Km long line with surge
impedance of 300 ohms and capacitance of 12 nF/Km and over voltage factor
of 2.3 p.u at the arrestor terminals.
400 kV class arrester shall be capable of discharging energy equivalent to class
4 of IEC for a 400 kV system on two successive operation followed
immediately by 50 HZ energisation with a sequential voltage profile as
specified below:
650 kVp for 3 peaks
575 kVp for 0.1 Sec.
550 kVp for 1 Sec.
475 kVp for 10 Secs.
245 & 145kV class arrester shall be capable of discharging energy equivalent to
class 3 of IEC for 245 kV & 145 kV system respectively on two successive
operations.
The reference current of the arresters shall be high enough to eliminate the
influence of grading and stray capacitance on the measured reference voltage.
The surge arresters are being provided to protect the followings whose
insulation levels are indicated in the table given below:-
Constructional Features
The nonlinear blocks shall be of sintered/infered metal oxide material. These shall be
provided in such a way as to obtain robust construction, with excellent mechanical
and electrical properties even after repeated operations.
The arrestor enclosure shall be vertically or horizontally mounted to suit the layout
of the switchgear as suggested by the supplier and each arrestor shall be fitted with a
Online continuous resistive leakage current monitoring system. The system shall be
provided with an interface to integrate with the substation automation system.
The main grounding connection from the surge arrestor to the earth shall be provided
by the contractor. The size of the connecting conductor shall be such that all the
energy is dissipated to the ground without getting overheated.
Tests
In accordance with the requirements stipulated, the surge arrestors shall conform to
type tests and shall be subjected to routine and acceptance tests in accordance with
IEC document.
Each metal oxide block shall be tested for the guaranteed specific energy capability
in addition to the routine/acceptance test as per IEC-60099.
Test on Surge Monitors: The Surge monitors shall also be connected in series with
the test specimens during residual voltage and current impulse withstand tests to
verify efficacy of the same. Additional routine/functional tests with one 100A and
10 kA current impulse, (8/20 micro sec.) shall also be performed on the surge
monitor.
- The circuit breaker may not be closed if the ear thing switch of
the associated section of bus bar is closed.
- The feeder disconnector may not be closed or opened if the
associated circuit breaker is closed.
- The feeder disconnector may not be closed if the earthing switch is
closed.
On the bus bar:
- cable disconnector can be opened and
earthing switch can be closed only if the
voltage transformer reads zero.
- Cable earth switch can be closed only if cable disconnector is
opened.
- Cable disconnector can be opened only if the associated
circuit breaker is opened.
- The feeder disconnector cannot be closed if the switchgear is closed
and bus bar disconnector is closed.
- The earthing switch of each bus bar may be closed only if all the
bus bar disconnections are opened.
16.3.2.14: ARRANGEMENTS
Wiring
The wiring must be carried out with stranded copper conductors of at least 7 strands.
The size of the conductors shall be suitable enough for the expected usage, but it must
not be less than 2.5 sq.mm. All precautions should be taken to minimize the inductive
and capacity coupling between circuits of especially with the wiring of the AC and DC
circuits. The cable trays shall be designed in such a way that it has at least 20% space for
future usage.
Terminal Blocks
The design of the terminal shall be as per the relevant standards in vogue. The terminals
permitting the direct control of SF 6 surveillance from pressure monitoring devices must
be fitted with test point.
The outgoing terminal connection must be unique and comprises of 2 distinct parts:
- an arrangement for auxiliary voltage supply (alternating or direct current)
- an arrangement for control common.
Worker Safety
All precautions must be taken to ensure an efficient protection against accidental contact
with the live elements.
Degree of protection
The required level of protection shall be established for the enclosures of boxes and
cubicles as per the relevant standards in vogue.
Frame work
The boxes and cubicles shall have metallic enclosures to ensure effective protection
against radio interference. If these enclosures are of non-metallic materials, the screen
shall be connected to the earth to ensure efficient protection.
Cable entrance
Cable glands or grommets shall be provided for cable entry through the lower side.
These cable glands should avoid electrolytic corrosion at the lower side of the box.
Closing devices
A simple handle will be sufficed at the door of the cubicles.The door must open at at
least 120 deg.
Lighting and socket :
Lighting facility at the cubicles shall be activated by opening the door.In each local
control cubicle a single phase 3 pin socket with switch shall also be provided. The
lighting points and sockets should be connected by a circuit separate from other circuits.
Space heaters
In each box and local control cubicle a space heater is required to prevent condensation.
It should be connected by the same separate A.C. circuit as above. The manufacturer
shall indicate the electrical power of each heater.
Earthing of boxes and cubicles
Depending upon the location of boxes and cubicles, the earthing terminal is either linked
to the metal enclosure, or linked directly to the general earth mat by an earthing
conductor of reduced cross – section.
Equipotential connections between boxes, cubicles and doors shall be provided to ensure
that no movable part of the enclosure can, once it is in place, be isolated from the part to
which the earthing terminal is connected.
Voltage transformer
The cable from voltage transformers shall be terminated in the cubicles with removable
fuses and shall be padlocked.
The fuses are connected in such a way that the locking devices forbids access to the cells
corresponding to the conductors from the voltage transformers. The fuse units shall be of
25-amp rating with a 6amp fuse cartridge.
Boxes and cubicles.
Other than stainless steel, all the boxes and cubicles shall be painted with a minimum
one primer coat and one top coat.
Bolts, screws and nuts
In case of stainless steel a diameter of 16mm and above shall be provided.
If the diameter is below 16mm hot galvanized will be allowed and in such case the
thickness of zinc
plating shall be 375 g /sq.m.
All precautions shall be taken:
- to ensure that contacting materials do not cause electrolytic corrosion.
- to avoid water stagnation.
The manufacturer shall specify the measures adopted to ensure the above condition
16.3.2.15: LOW VOLTAGE CABLES & CONTROL CABLES
The Low voltage cables & control cables shall be of 1.1 kV XLPE/PVC insulated
copper tape shielded control cables shall be complied with IEC 60502 and flame
retardant to IEC 60332-1.
16.3.2.16: ACCESSORIES:
SF6 GAS SERVICE CART (SF6 Gas Filling, Evacuating, Filtering, Drying, Pumping
& Storage Plant) The SF6 gas service cart shall be adequate to refill each compartment
between the first or second level of SF6 gas pressure to the rated pressure.
- Check the SF6 monitoring.
- The SF6 Gas Filling, Evacuating, Filtering, Drying, Pumping & Storage Plant
with spares for 5 years Operation.
The plant necessary for filling and evacuating the SF6 gas in the switchgear shall be
supplied to enable any maintenance work to be carried out. This shall include all the
necessary gas cylinders for temporarily storing the evacuated SF6 gas. The capacity of
the temporary storage facilities shall at least be sufficient for storing the maximum
quantity of gas that could be removed from at least one phase of one complete bay. The
minimum capacity of evacuation plant shall be:
(1) 400/220/132kV: Vacuum Pump: 40 M3/Hour (Nominal suction pressure) &
Compressor: 6.5 M3/Hour (Delivery).
The evacuation equipment shall be provided with all the necessary pipes, couplings,
flexible tubes and valves for coupling up to the switchgear for filling or evacuating all
the gases. The gases compartments shall be fitted with permanent non-return valves
through which the gas is pumped into or evacuated from the compartments.
(a) SF6 HANDLING PLANT
The SF6 handling plant shall contain compressors and vacuum pump necessary for
recovering vacuum and filling SF6 gas. It shall be movable with wheels.
It shall allow the storage of SF6 in liquid state in a built – in tank having capacity
sufficient to empty any three adjacent compartment of 400kV / 220 KV / 132kV GIS.
The capacity of compressors and vacuum pumps shall be selected in
such a way for -filling a compartment to the rated pressure within one
hour.
recovering SF6 gas from any compartment to the built in tank from the rated
pressure to 50mb pressure within three hours.
evacuating a compartment from 50 mb pressure to less than 1 mb pressure within
one hour.
The cart shall have the following provisions:
accessories for connections and operation (valves and coupling)
dry type filters, dust and oil traps,
tools and spares for operation and Maintenance,
hand- book for description, commissioning, operation, and Maintenance.
(b) 400kV / 220 KV /132 kV SF6 TEST BUSHINGS: Required for HV testing at the
time of commissioning to be considered by the supplier (Supplier scope but will be
taken back by the supplier after commissioning).
These bushings shall conform to IEC
60137 standard. The design shall
meet the following requirements:
- Minimum creep age distance: 31mm / KV for heavy pollution level according to the
IEC60815 standard.
-The terminal clamp shall be supplied by the GIS manufacturer
16.3.2.17: EARTHING
CONNECTION TO THE GENERAL EARTH MAT:
All metal parts intended which does not belong to a main or an auxiliary circuit, shall be
connected to earth.
The general HDG MS earth flat earth circuit of the substation shall be formed by an
uninterrupted loop which originates form the buried HDG MS earth flat conductor of a
cross section of 900sq.mm (75X12) for 220 & 780 sqmm (65x12) for132 KV & 40
mm dia MS Rod for 400 KV. These loops shall be fixed to the base of the chassis with
the help of an earth riser connection bolted into a hole in the chassis or frame by the
manufacturer of the metal-clad equipment, and situated at 0.30 m above the floor level of
the switchgear. The general earth mat design, the connection device and the bimetallic
plate shall be supplied by the GIS manufacturer. The earth connection from earth pad of
equipment to the general earth mat near shall be provided by the supplier. The continuity
of the earthing circuitsshall be ensured taking into account the thermal and electrical
stress by the current they may have to carry. The riser shall be of copper flat size of
50X10 mm with bi-metallic arrangement to connect from the ground earth mat to
enclosure of the GIS equipment.
EQUIPOTENTIAL EARTHMAT: (below the GIS)
When a fault current flows through the earthing connections into the soil, the enclosures,
linked to the earthing circuits, are carried at the same potential as the earthing mat
conductors but this potential is generally different from that on the soil surface.
In order to ensure the security of personnel, it is necessary to install an equipotential mat
linked to the general earthing mat in the zones where metal enclosures and fixed
accessories are accessible from the floor.
It is also necessary to provide an equipotential earthing mat in the zones where an
emergency mechanical operation or a locking system is accessible from the floor. It is
therefore possible to extend the equipotential mat to allow the operator to carry out his
manoeuvres.
In order to ensure a good equipotential surface, each element of the equipotential mat
must be connected to the general earthing network by the manufacturer.
This mat will be placed on the floor, all around the switch gears. It is not required in
front of the control cubicles.
If it is an oxidizing material, it should be hot dip galvanized.
The manufacturer must provide and specify this equipotential earthing mat. The location
of the equipotential mat should be defined by the supplier for all the GIS and at places
where :
- the enclosures are accessible for the floor.
- Manual operation of apparatus or locking system is located.
Five copies of equipotential earth mat drawings along with design calculations may be
submitted for approval by the successful Bidder.
16.3.2.18: TESTING & COMMISSIONING:
(a) TYPE TEST:
Type tests shall be according to the IEC 62271-203 and other relevant IEC standards.
Copies of the type tests conducted shall be furnished along with the BID failing which
the Bid is liable for rejection. These type tests should have been conducted in a
Recognized independent institution / Laboratory. The type test reports of the
manufacturer or its principal (holding company) shall be acceptable, if the manufacturer
is of international repute.
(b) ROUTINE TESTS:
Routine tests shall be as per the IEC 62271-203 and other relevant standards. The
manufacturer shall provide all the testing equipment required for the site tests.
(c) COMMISSIONING TESTS/ON SITE TESTS AFTER ERECTION:
After erection, and before putting into service, the gas-insulated metal enclosed
Switchgear shall be tested for the correct operation and dielectric strength of the
equipment.
These tests and verifications shall comprise:
(1) Tests to be conducted on the circuit breaker at site at all required operating
sequences
- Measurement of operating time
- Checking of wiring and connections and dielectric checks
- Indications, alarms and interlocks, auxiliary contacts
- Operation at minimum and maximum control supply voltage/pressure
- Operation of anti-pumping device.
(2) Test to be conducted on the Disconnectors at site
- Checking of wiring and connections and dielectric checks
- Indications, alarms and interlocks, auxiliary contacts
- Operation at minimum and maximum control supply voltage/pressure
(3)Other Tests at Site
- Dielectric tests on auxiliary circuits
- Measurement of the resistance of the main circuit
- Measurement of gas condition
- Gas tightness tests
- General verifications
- Tests as per IEEE C37.122.1 clause 4.10.5
- Demonstration of operational compatibility with SCADA
- Mechanical operation tests of circuit breakers, Disconnectors
and earthing switches and high-speed earthing switches
- Insulation resistance measurement
During the on site tests, the supplier shall provide all necessary test facilities and
equipment (such as high voltage test kit) for the switch-gear power frequency tests, i.e.
test bushing or test cable, test adapter, test transformer or resonant test set etc.
16.3.2.19 ELECTRIC OVERHEAD CRANE:
One EOT Crane each for GIS hall of suitable capacity shall be provided for erection &
maintenance of largest GIS component/assembly. The crane shall consist of all special
equirements for erection & maintenance of GIS equipment.The capacity of the crane
shall be sized to lift the heaviest GIS switchgear component crane.
The Crane shall be used for the erection and maintenance of the GIS switchgear
component and all plant installed in the GIS switchgear room .On completion of erection
of the switchgear, the Contractor shall completely service the crane before the Taking
Over Certificate is issued. Crane hook approaches shall be of the minimum possible
dimensions to ensure maximum coverage of the plant area.
The crane(s) shall be capable of lifting and accurately positioning all loads ranging from
full crane rated capacity toat least 10% rated capacity.
The crane shall have minimum speeds under full load of:
Speed
(a) Hoisting 2 meters/minute
(b) Cross Travel 10 meters/minute
(c) Long Travel 20 meters/minute
(d) Creep speed shall be of25% of operating speed
The electric overhead cranes shall be provided with walkways, platforms. Guard hand
rails shall be provided along the bridge rails and on the crab of EOT crane to facilitate
cleaning/maintenance of the crane and to give access to the GIS room high bay lighting
and ventilation duct and grilles. The platform and walkways shall be designed to support
any weight to be imposed upon them during crane overhaul. An access platform shall be
provided together with a guarded ladder on the crane to allow access to the bridge rails.
The crane shall be possible to be operated through the cable, through the pendant control
and which shall be easily accessible from the floor of GIS building and through remote
control device. Manufacturer/contractor shall submit the capacity calculation of crane for
GIS hall considering a factor of safety of 5.
a) The crane for 400kV GIS hall shall have capacity of minimum 10T safe working
load & minimum height of crane have shall be 9.0 meters or as per actual requirement
whichever is higher.
b) The crane for 220kV GIS/132kV GIS shall have capacity of minimum 7.5T safe
working load & minimum height of crane have shall be 8.0 meters or as per actual
requirement whichever is higher. In case the GIS hall is to be extended, the scope of
work also involves extension of EOT crane girders to facilitate movement of EOT crane
in the extended portion of GIS hall.
The following tests should be performed for EOT Crane:
1. The crane shall be tested at manufacturer work under full load and 25 percent
overload of hoisting and cross transverse motions as a routine test.
2. Further the following tests may be done at site after installation of
the crane at site a. Check althea accessories for proper function.
The following tests may be EOT Crane
1. The crane shall be tested at manufacturer work under full load and 25 percent
overload of hoisting and cross transverse motions as a routine test.
2. Further the following tests may be done at site after installation of
the crane at site a. Check all the accessories for proper function
b. No load test
c. Load test as per site conditions.
Constructional details
The double web, box construction crane bridge girders shall be in one piece or in pieces
suitable for transportation if in pieces the design of multi piece construction shall require
the approval of the Engineer in Charge. Cross travel rails shall be fixed to the bridge
girders by clamping only and not welding. Plates, bars, angle sections and where
practicable other rolled sections, used in the load bearing members of structures shall be
not less than 6 mm thickness. The end carriages shall be of double web plate box
construction or I section connected to the girders by welding at top or by large gusset
plates and fitted bolts to ensure maximum rigidity. Drop stops and jacking pads shall be
built-in features. Full length plate form of checker plate of minimum thickness 6 mm
shall be provided along both sides of the crane to ensure easy, safe excess to the crane
crab, travel gears and other parts. Safety railing shall be provided on crane bridges and
crab frame. Foot-walk shall have sufficient width to give 500 mm minimum clear
passage at all points, except between railing and bridge drive where this clearance may
be reduced to not less than 400mm.
Rope Drums
Rope drums shall be of cast steel or fabricated from seamless tubes, conforming to the
relevant Indian Standards. Fabricated rope drums shall be stress relieved before any
machining takes place. The sizing of drum shall conform to IS 3177 Clause 5.
Rope Sheaves
Rope sheaves shall be of cast steel or fabricated from rolled steel plates, conforming to
Clause 6 of IS 3177.
Wire Ropes
The wires shall be hemp cored for all cranes. Ropes shall be of regular right hand lay as
per IS 2266. The rope construction shall be 6 x 37 up to 16 mm diameter and 6 x 36
above 16 mm diameter, with a factor of safety specified as per Clause 5.6.1 of IS 3177.
Hook Block
The sheaves shall be fully encased in close fitting guards fabricated from steel plate.
Smooth opening shall be provided in the guards to allow for free movement of the rope.
Holes shall be provided for oil drainage.
Lifting Hooks
The lifting hook shall be one that will best suit this type of crane and as per IS 3177.
Hooks shall be quality tested by a third-party agency such as SGS or Lloyds.
Track Wheels
Crab/Crane wheels shall be double flanged. Wheels shall be mounted in anti-friction
roller bearings housed in “L” shaped bearing brackets for ease of removal during routine
maintenance. Flangeless wheels with guide rollers would also be acceptable. Solid
wheels shall be of forged/rolled steel or cast steel. In general, the track wheels shall
conform to Clause 11 of IS 3177.
Rails
The rails shall be specified as being suitable for the crane duty used no square bars will
be acceptable. The rails shall be complete with end stops, holding down bolts and taper
washers and shall be suitable for connection to the station earth. Access to the crane for
maintenance purposes from the walking plate form by means of a steel ladder with cage
shall be provided. The crane shall be provided with full length walkway on drive side
girder and small walkway on other girder. Walkway shall be at least 500 mm clear
inside.
Couplings
All couplings shall be of steel or cast iron of grade 260 conforming to IS 210 and shall
be designed to suit the maximum torque that may be developed. The manual drive shaft
and hoist drum shall be connected to the gear box input shaft through a flexible shock
absorbing coupling as per Clause 8 of IS 3177.
Shafts
All shafts shall be made of steel as per Clause 9 of IS 3177.
Electrical details
The general technical details for the electrical systems specified elsewhere in the
document will apply to the electrical equipment for the gantry crane also. The following
points deal with the special requirements for the crane. In case of any contradiction with
the electrical specifications described elsewhere in this document, the special
requirements detailed hereafter shall have precedence.
415 V, 3 Phase, 4 wire electric power supply will be available at one point for the crane
bus. The Bidder shall provide a metal enclosed switch box housing a 63 A TPN switch,
CT operated ammeter and voltmeter, with selector switch. This switch box shall be
located approx. 1.2 meters above the floor level. The incoming cable must be of suitable
size aluminum conductor, PVC insulated, PVC sheathed, strip armoured. From this
switch onwards, the Bidder shall arrange and terminate the supply at the crane bus.
Crane Power Supply
415 Volts +/- 10%, 3 Phase, 4 Wire, 50 Hz +/- 5%, AC through trolley lines.
Current Collector
Two No. per trolley line shall be provided; each rated for 100% of total crane rating.
Double collectors on each earth trolley shall be provided and these shall be different
from those on the power trolley line. Collector rollers and shoes shall be designed to
reduce sparking to the minimum level possible Power Distribution on Crane. An off/load
manual isolator, with a locking facility shall be provided immediately after the current
collectors on the incoming line on the crane.
Power from the isolator shall be taken to the circuit breaker located in protective panel of
the crane. The breaker shall be provided with under voltage, overload and short circuit
release or relays. The breaker can only be closed when:
All controllers are in neutral position;
None of the stator or directional contactors are in closed position;
Door/gate switches are not actuated;
Rotary and gravity limit switches for hoist motion not operated.
Panels
All panels shall be of free-standing floor mounted construction, suitable to withstand any
vibrations emanating from the crane. The panel and its components shall conform to
standards of Electrical Technical Specifications for LT Switchgear/Panel, described
elsewhere in this document.
Motors
Heavy duty motors suitable for crane operation, shall be reversible, suitable for frequent
acceleration and mechanical breaking, totally enclosed, fan cooled, wound rotor type.
The duty of the motor shall be S5, as per IS 325. Class of insulation shall be “B”. The
pull-out torque is to be not less than 225% of full load torque, corresponding to 40%
CDF (Cycle Duration Factor of the motor).The main motor shall have the speed ranges
suitable for gearbox and operating speed for a Class 2 crane.
Brakes
Brakes shall be provided for hoisting motions. Brakes shall be thruster type. Brakes shall
be designed to be fail-safe whenever there is a current interruption, either intentionally or
by main power supply failure. The capacity of brakes, brake drums, shoes and brake
adjustment shall be as per Clause 14.4 of IS 3177.
Limit Switches
Only drum limit switches are acceptable. Roller operated, resetting limit switches shall
be provided for all motors. For each hoist motion, a rotary type over-winding self-
resetting limit switch shall be provided. An indication shall be provided to the operator
whenever this limit switch has been operated. Limit switches shall be fitted to prevent
over travelling and over traversing and any other special requirements.
Resistance
Resistance’s shall be air-cooled, robust, heavy duty, corrosion resistant, punched
stainless steel grid type/cast iron grid resistor. Suitable tapping points shall be provided.
Resistance boxes shall be mounted in racks that permit independent travel of any
selected box.
Pendent Controller
1. Pendent push button station shall comprise of the following and be
suitable for 110 V AC:
2. Key operated ON push button-standard green button.
3. on signal lamp-green lens.
4. Emergency OFF push button-standard red button.
5. Hoisting push button- standard black button.
6. Lowering push button-standard yellow button.
7. Micro Hoisting push button- standard black button.
8. Micro Lowering push button- standard black button.
9. Cross traverse forward push button- standard black button.
10. Cross traverse reverse push button- standard black button.
11. Micro Cross traverse forward push button- standard black button.
12. Micro Cross traverse reverse push button- standard black button.
13. Long traverse forward push button- standard black button.
14. Long traverse reverse push button- standard black button.
15. Micro Long traverse forward push button- standard black button.
16. Micro Long traverse reverse push button- standard black button.
17. Crane light ON/OFF push button.
18. Bell ON/OFF push button
CIRCUIT BREAKER
SYSTEM RATING
SL.NO UNIT
PARAMETERS 400 220 132
I II III IV V VI
Nominal operating
1 kV 400 132
Voltage 220
Highest system
2 kV 420 145
Voltage 245
3 Frequency Hz 50 50 50
Nominal operating
4 A 4000 2000
current(at 40°C) 3150
a) Lightning
6 kVp 1425 650
impulse 1050
b) Power kV
650 275
frequency rms 460
Rated withstand voltage between terminals with circuit breaker open
a) Lightning
7 kVp Lightning Impulse: As per IEC 62271-203
impulse
b) Power kV
frequency rms Power frequency: As per IEC 62271-203
Radio interference
8 voltage at frequency µV 1000 1000 500
range 0.5 to 2 MHz
Rated short-circuit
9 breaking current kA 63 50 40
(r.m.s.), 3s:
Rated making
10 kAp 157.5 100
current (peak): 125
Rated break time as
11 ms 40 60
per IEC 60
12 Total break time ms 45 65 65
Operating
22 Spring-Spring/ Spring-Spring/ Spring-Spring/
mechanism :
Hydromechanical Hydromechanical Hydromechanical
– spring – spring – spring
Rated operating
23
sequence O-0.3s-CO-3 min-CO
Time for recharging
24
CO cycle CO-15sec-CO
25 Number of trip coils 2 in each pole
Number of closing
26
coils 1 in each pole
Rated control
27 V
voltage (DC) 220V DC
Number of CO
operations
28 permissible No. 10000
without
maintenance
DISCONNECTORS
SYSTEM RATING
SL.NO UNIT
PARAMETERS 400 220 132
I II III IV V VI
1 Rated Voltage kV 420 245kV 145
Lightning impulse
2 withstand voltage kVp 1425 1050 650
against ground
Lightning impulse
withstand voltage
3 kVp Lightning Impulse: As per IEC 62271-203
across isolating
distance
Power frequency
kV
4 withstand voltage 650 460 275
rms
against ground
Power frequency
withstand voltage Kv
5 Power frequency: As per IEC 62271-203
across isolating rms
distance
Nominal operating
6 A 4000 3150 2000
current
7 Number of poles 3
8 Dynamic current kAp 157.5 125 100
Rated short-circuit
9 withstand current kA 63 50 40
(r.m.s.), 3s
Type of operating
10 Motor operation Motor operation Motor operation
mechanism
Mechanical endurance
11 M2
clause as per IEC
Number of drives per
12 1
3 phase
13 System Earthing Effectively earthed
14 Control voltage (DC) V 220 DC
Number of CO
15 operations permissible No. 10000
without maintenance
GROUNDING SWITCHES
SYSTEM RATING
SL.NO UNIT
PARAMETERS 400 220 132
I II III IV V VI
1 Rated Voltage kV 420 245kV 145
Lightning impulse
withstand voltage 650
2 against ground kV 1425 1050
Lightning impulse
withstand voltage
across isolating
3 distance kV Lightning Impulse: As per IEC 62271-203
Power frequency
withstand voltage 275
4 against ground kV 650 460
Power frequency
withstand voltage
across isolating
5 distance Kv Power frequency: As per IEC 62271-203
Nominal operating
2000
6 current A 4000 3150
8 Number of poles 3
9 Dynamic current kA 157.5 125 100
Rated short-circuit
withstand current 40
12 (r.m.s.), 3s kA 63 50
Type of operating
13 mechanism Motor operation
Number of drives per
14 3 phase 1
15 Control voltage (DC) V 220 DC
Number of CO
operations permissible
16 without maintenance No. As per latest IEC standard or equivalent.
SYSTEM RATING
SL.NO UNIT
PARAMETERS 400 220 132
I II III IV V VI
1 Rated Voltage kV 420 245 145
Lightning impulse
withstand voltage 650
2 against ground kV 1425 1050
Lightning impulse
withstand voltage
across isolating
3 distance kV Lightning Impulse: As per IEC 62271-203
Power frequency
withstand voltage 275
4 against ground kV 650 460
Power frequency
withstand voltage
across isolating
5 distance Kv Power frequency: As per IEC 62271-203
Nominal operating
2000
6 current A 4000 3150
Inductive current
8 switching capability A , kV As per IE C standard
Capacitive current
9 switching capability A , kV As per IEC standard
10 Number of poles 3
11 Dynamic current kA 157.5 125 100
Rated short-circuit
withstand current 40
14 (r.m.s.), 3s kA 63 50
Type of operating
15 mechanism Motor operation
Number of drives per
16 3 phase 1
17 Control voltage (DC) V 220 DC
18 Short-circuit making: Class E1
Number of CO
permissible without
19 maintenance No. As per latest IEC standard or equivalent.
CURRENT TRANSFORMERS
SYSTEM RATING
SL.NO UNIT
PARAMETERS 400 220 132
I II III IV V VI
1 Rated Voltage kV 400 220 132
Highest system
2 kV 420 245 145
voltage
3 Accuracy Metering 0.2s & protection PS
Core number per
Nos. 7 6 5
phase
4
- Metering 0.2S
- Protection PX
Radio interference
voltage at 1.1 Un/ 3
5 µV 1000 1000 500
and frequency range
0.5 to 2 MHz
6 Rating Primary A As per SLD
Rated secondary
A 1
current
Accuracy Class for all
10 As per SLD
cores
Burden in VA for all
11 As per SLD
cores
Instrument security
12 factor (ISF) for <5
metering core
13 Partial discharge level pC Below 5
14 Max exc current at Vk A As per SLD
Max CT sec resistance
15 Ohms As per SLD
in Ohms at 75 °C
Knee point voltage at
16 different ratios for all V As per SLD
cores
Rated short-circuit
17 kA 63 50 40
withstand current 3s,
Dynamic current
18 kAp 157.5 125 100
withstand
Maximum temperature
19 rise over an ambient As per relevant IEC
temperature of 40°C
Lightning impulse
20 kVp 1425 1050 650
withstand voltage
Power frequency kV
21 650 460 275
withstand voltage rms
Power frequency
withstand voltage kV
22 3
between secondary rms
terminal and earth
System Neutral
23 Effectively earthed
Earthing
POTENTIAL TRANSFORMERS
SYSTEM RATING
SL.NO. UNIT
PARAMETERS 400 220 132
I II III IV V VI
1 Rated voltage KV 400 220 132
Highest System
KV 420 245 145
2 voltage
3 Frequency Hz 50
4 Primary winding kV 400/√3 220/√3 132/√3
5 Secondary winding V 110/√3
No of secondary
6 Nos. As per SLD
windings
15 Rated voltage factor 1.2 times continuously & 1.5 times for 30 sec
System Neutral
16 Effectively earthed
Earthing
TECHNICAL RATING
Sr. No. UNIT
PARTICULARS 400 220 132
I II III IV V VI
1 Rated Voltage, kVrms kV 400 220 132
Highest System
kV 420 245 145
voltage
2 Rated Frequency, Hz Hz 50
3 Grounding Effectively Earthed
One - Minute Power Frequency Dry and Wet Withstand Voltage, (kV rms)
1.2 / 50 microseconds Full Wave Impulse Withstand Voltage for all Equipment, (kV p)
10 Max. switching surge kVp 670(at 2kA) 500 (at 1kA) 280 (at 1kA)
residual voltage 650 (at
500A)
11
a)
i) Arrester Housing kVpeak ±1425 ±1050 ±650
b)
i) Arrester Housing kV ± 1050 -NA- -NA-
peak
c)
i) Arrester Housing kV rms 630 460 275
17.1.2 It is not the intent to specify completely herein all details of the design and construction of
equipments. However, the equipment shall conform in all respects to standards of engineering, design and
workmanship listed in clause no.2 and shall be capable of performing in continuous commercial operation
up to the supplier's guarantee in a manner acceptable to the purchaser, who will interpret the meanings of
drawings and specification and shall have the power to reject any work or material which, in his judgment,
is not in accordance therewith .The equipments offered shall be complete with all components necessary for
their effective and trouble free operation. Such components shall be deemed to be within the scope of
supplier's supply, irrespective of whether those are specifically brought out in this specification and/or the
commercial order or not.
17.1.3 As per the site condition and availability of suitable mode of transportation, the bidder may suggest
the 400Kv class 500 MVA Auto-transformer of Single Phase (1-ϕ) or Three Phase (3-ϕ). For the
aforementioned purpose, necessary approval shall be obtained from AEGCL.
17.2.0 STANDARDS:
17.2.1.0 The Transformer and associated accessories shall conform to the latest issues of the standards as
given below, except to the extent explicitly modified in this specification.
17.2.1.1 In case equipment conforms to other international standard which ensure equivalent or better
performance than that specified under Clause 17.3.0, then relevant extracts of the same shall be forwarded
with the bid and the salient features of comparison shall be brought out separately in additional information
schedule.
17.3.1.0 The transformers shall conform in all respects to high standards of engineering, design,
workmanship and latest revisions of relevant standards at the time of offer and the purchaser shall have the
power to reject any work or material which, in his judgment, is not in full accordance therewith.
17.3.1.1 The equipment to be supplied against this specification shall be suitable for satisfactory continuous
operation under the tropical conditions mentioned in chapter 2 of this bidding document.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
17.3.1.2 The transformers shall in general have constant ohmic impedance between HV and IV on all taps.
However, in case of transformer to be connected for parallel operation:
i) The percentage impedance, vector group, OLTC connection and range etc. of the transformers shall be
matched.
ii) Necessary provision is to be kept in the transformer control scheme for parallel operation with the
OLTC control scheme having provision of Master/Follower/Independent /Off operation etc.
iii) External or internal reactors shall not be used to achieve the specified HV/LV and IV/LV impedances
17.3.1.3 The Transformer shall be multi-winding, oil immersed complying as per Specific technical
parameters and suitable for outdoor installation.
17.3.1.4 The transformer of manufacturer having 50 or higher MVA rating and 132 or higher voltage rating
must be in successful operation in any STATE or CENTRAL utility for not less than five (5) years as on
date of NIT.
17.3.1.5 Rated Capacity and Voltage of the Transformers as per present requirement of AEGCL:
a) 500 MVA - 400/220/33 KV and 160 MVA - 220/132/33 KV Auto Transformer with loaded 33
KV tertiary winding.
The transformers should be Type Tested as per IS 2026 or IEC 60076 in conjunction with their relevant
Part. Necessary test documents of previously tested similar or higher rated (both in MVA and voltage class)
transformer shall have to be submitted with the bid.
Materials, which have never been tested for critical performance, shall not be accepted.
Type test certificates shall be acceptable only if:-
(a) Tests are conducted in an independent and well known (NABL/BIS Accredited) testing
laboratory, or
(b) Tests are conducted in manufacturer’s own laboratory. In this case,
(i) The laboratory must have ISO 9000 (or its equivalent) series certification; and
(ii)Tests have been witnessed by technically qualified representatives of earlier clients or
purchaser.
Test reports to be acceptable must be related directly to the materials offered. Test reports for higher class of
equipment are acceptable with commitment to perform the type tests free of any charge on the particular
equipment(s) after the award of contract.
Type Test Reports older than five (5) years on the date of Technical bid opening shall not be accepted.
Full Type Test Reports of at least the following equipment must be submitted: -
1. 500, 160, 100 and 50 MVA class Power Transformer
2. Tap Changer
3. Transformer Oil
4. Bushings
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
5. Buchholz Relay
6. Pressure Relief Device
7. Bushing Current Transformer
8. Oil Surge Relay
9. Cooling Gears
10. AVR Relay
11. On line drying system
AEGCL shall accept type test report of higher MVA rating transformer of same voltage levels as that of the
BID for evaluation purpose only. But atleast one out of the offered transformers covered under this package
should be subjected to short circuit test and test report should be submitted to AEGCL in case of successful
bidder.
(iii) Sweep Frequency Response Analysis (SFRA/FRA) shall have to be carried out as special test for
each transformer at manufacturer’s premises in presence of representative of AEGCL free of cost. Test
result shall have to be handed over to AEGCL. Before commissioning of the Transformer at site, the same
SFRA/FRA test will have to be carried by the test engineers of the manufacturer in presence of customer’s
representative for comparing the results to take the decisions of the commissioning. The Testing Engineers
& FRA kit for such pre-commissioning site testing shall have to be arranged by the manufacturer free of
cost.
(iv) Tests at Manufacturer’s works: The Transformers shall be subjected to type & routine test, special
tests and no load & load loss measurement as per relevant IS.
(v) Guaranteed Technical Particulars: The Bidder shall furnish all guaranteed technical particulars as
called for in this specification along with each copy of Bid submission. Bids lacking information in this
respect may not be considered.
(vi) Core Materials: Core materials should be directly procured from either the manufacturer or their
accredited reputed marketing organization and not through any agent.
17.6.1.0 The no-load loss, load loss and auxiliary losses (cooler loss) as well as total losses shall be
guaranteed under penalty for each transformer subject to Clause 17.6.1.2 and 17.6.1.3. For the purpose of
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
penalty computation, the test figures of the no-load and the total losses of each transformer will be
compared with the corresponding guaranteed figures.
17.6.1.1 The no-load losses, load losses and auxiliary losses shall not exceed the values specified in the
Maximum losses Clause (i.e., Clause 17.6.1.3). No positive tolerance on no-load loss, load loss and
auxiliary losses as well as total losses will be allowed. Any change in the figures assigned for transformer
losses will not be permitted after opening of bids and evaluation will be carried out on the basis of
information made available at the time of bid opening. Bid with higher losses as that of provided in the
Technical Data Sheet, bid will be treated as non-responsive.
17.6.1.2 The capitalization of power/auto transformer losses shall be as per formula given in SECTION AA
of CBIP Manual on Transformers, 2013 (Publication No. 317). The calculation results should be
submitted to AEGCL for final approval.
The loss figures (both guaranteed & test) for the purpose of this clause shall be at rated frequency and
voltage and at principal tap and 75º C.
Sr. Rating Voltage Rating (kV) Phase No Load I2R Stray Aux.
No (MVA) Load Loss (kW) + Loss
Loss (kW) Eddy
(kW) (kW)
1. 500 400/220/33 3- Phase AT 90 500 375 125 15
2. 160 220/132/33 3- Phase AT 30 200 145 55 6
3. 100 220/33 3- Phase AT 43 245 200 45 5
4. 50 132/33 3- Phase AT 25 125 105 20 3
5. 167 (400/√3)/(200/√3)/33 1-Phase AT 45 200 140 60 6
17.7. Transportation
17.7.1.1 The Contractor shall be responsible to select and verify the route, mode of transportation and make
all necessary arrangement with the appropriate authorities for the transportation of the equipment. The
dimension of the equipment shall be such that when packed for transportation, it will comply with the
requirements of loading and clearance restrictions for the selected route. It shall be the responsibility of the
contractor to coordinate the arrangement for transportation of the transformer for all the stages from the
manufacturer’s work to site.
17.7.1.2 The contractor shall carry out the route survey along with the transporter and finalise the detail
methodology for transportation of transformer and based on route survey; any modification/ extension/
improvement to existing road, bridges, culverts etc. if required, shall be in the scope of the contractor.
17.7.1.3 The inland transportation of the Transformer shall be on trailers equipped with GPS system for
tracking the location of transformer at all times during transportation from manufacturer works to
designated site. The contractor shall intimate to Employer about the details of transporter engaged for
transportation of the Transformer for tracking the transformer during transit. Requirement of Hydraulic
trailer is envisaged for 400kV class Transformers.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
17.7.1.4 All metal blanking plates and covers which are specifically required to transport and storage of the
transformer shall be considered part of the transformer and handed over to the Purchaser after completion of
the erection. Bill of quantity of these items shall be included in the relevant drawing/document.
17.7.1.5 The necessary arrangement shall be ensured by the contractor to take care of pressure drop of dry
air during transit and storage till completion of oil filling during erection. A dry air pressure testing valve
with necessary pressure gauge and adaptor valve shall be provided. Generally, the duration of the storage of
transformer at site with dry air, shall preferably be limited to three months, after which the Transformer
shall be processed as per the recommendation of manufacturer if not filled with oil. The dry air cylinder(s)
provided to maintain positive pressure can be taken back by the contractor after oil filling.
17.7.1.6 In case turret, having insulation assembly, is transported separately then positive dry air pressure
shall be ensured.
17.7.1.7 Transformer shall also be fitted with Electronic impact recorders (on returnable basis) at least 2
numbers for 400kV Class Transformer and 1 number for below 400kV class Transformers during
transportation to measure the magnitude and duration of the impact in all three directions. The mounting
location of impact recorder shall be finalised during detailed engineering. The acceptance criteria and limits
of impact, which can be withstood by the equipment during transportation and handling in all three
directions, shall not exceed “3g” for 50mSec (20Hz) or as per contractor standard, whichever is lower.
17.8.0 Performance
17.8.1.0 The transformers shall be used for bi-directional flow of rated power. The major technical
parameters of three phase transformer units are defined at Annexure – A.
17.8.1.1 Transformers shall be capable of operating under natural cooled condition up to the specified load.
The forced cooling equipment shall come into operation by pre-set contacts of winding temperature
indicator and the transformer shall operate as a forced cooling unit initially as ONAF up to specified load
and then as OFAF. Cooling shall be so designed that during total failure of power supply to cooling fans and
oil pumps, the transformer shall be able to operate at full load for at least ten (10) minutes without the
calculated winding hot spot temperature exceeding 140 deg C. Transformers fitted with two coolers, each
capable of dissipating 50 per cent of the loss at continuous maximum rating, shall be capable of operating
for 20 minutes in the event of failure of the oil circulating pump or blowers associated with one cooler
without the calculated winding hot spot temperature exceeding 140deg C at continuous max rating. The
contractor shall submit supporting calculations for the above and the same shall be reviewed during design
review.
17.8.1.2 The transformer shall be free from any electrostatic charging tendency (ECT) under all operating
conditions when all oil circulation systems are in operation. In general, oil flow speed shall not exceed 1.0
m/sec within winding in the oil flow system of the transformers. The manufacturer shall ensure that there is
no electrostatic charging tendency in the design.
17.8.1.3 The transformers shall be capable of being continuously operated at the rated MVA without danger,
at any tapping with voltage variation of +/-10% corresponding to the voltage of that tapping.
17.8.1.4 The transformers shall be capable of being over loaded in accordance with IEC-60076-7. There
shall be no limitation imposed by bushings, tap changers etc. or any other associated equipment.
17.8.1.5 Tank hotspot shall not exceed 130 Deg. Celsius. Maximum ambient temperature shall be
considered as 50 Deg. C.
17.8.1.6 The transformer and all its accessories including bushing/ built in CTs etc. shall be designed to
withstand without damage, the thermal and mechanical effects of any external short circuit to earth and of
short circuits at the terminals of any winding for a period of 2 secs. The short circuit level of the HV & IV
System to which the transformers will be connected is as follows:
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
17.8.1.7 Transformer shall be capable of withstanding thermal and mechanical stresses caused by
symmetrical or asymmetrical faults on any terminals. Mechanical strength of the transformer shall be such
that it can withstand 3-phase and 1- phase through fault for transformer rated voltage applied to HV and / or
IV terminals of transformer. The short circuit shall alternatively be considered to be applied to each of the
HV, IV and tertiary (LV) transformer terminals as applicable. The tertiary terminals shall be considered not
connected to system source. For short circuit on the tertiary terminals, the in-feed from both HV & IV
system shall be limited by the transformer self-impedance only and the rated voltage of HV and IV
terminals shall be considered. The maximum short circuit output current at the tertiary terminals shall be
limited to a safe value to make the transformer short circuit proof. The transformer shall be designed to
withstand for short circuit duration of 2 seconds for Thermal stress and the same shall be verified during
design review.
17.8.1.8 The maximum flux density in any part of the core and yoke at the rated MVA, voltage and
frequency shall be such that under 10 % continuous over-voltage condition it does not exceed 1.9 Tesla at
all tap positions.
17.8.1.9 Transformers shall withstand without damage, heating due to the combined voltage and
frequency fluctuations which produce the following over fluxing conditions:
17.10.1.0 The transformers shall be designed with particular attention to the suppression of harmonic voltage,
especially the third and fifth so as to minimise interference with communication circuit.
17.10.1.1 The noise level of transformer, when energised at normal voltage and frequency with fans and
pumps running shall not exceed the values specified at Annexure - A, when measured under standard
conditions.
17.11.1.0 The following shall constitute as Measureable Defects for the purpose of Defect Liabilities as per
relevant clauses of GCC / SCC of the bidding document:
a) Repair, inside the Transformer and OLTC (including oil migration) either at site or at factory is
carried out after commissioning.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
b) The concentration of any fault gas is more than values of condition-1 indicated in clause no 6.5 of
IEEE-C57.104-2008, which are as detailed below:
c) The winding tan delta goes beyond 0.005 or increase more than 0.001 within a year w.r.t. pre-
commissioning values. No temperature correction factor shall be applicable for tan delta.
d) The moisture content goes above 12 ppm at any temperature during operation including full load.
17.12.1.1 Design reviews shall be conducted by Purchaser or an appointed consultant during the
procurement process for transformers; however, the entire responsibility of design shall be with the
manufacturer. Purchaser may also visit the manufacturer’s works to inspect design, manufacturing and test
facilities at any time.
17.12.1.2 The design review will commence after placement of award and shall be finalised before
commencement of manufacturing activity. These design reviews shall be carried out in detail to the specific
design with reference of the transformer under the scope. It shall be conducted generally following the
CIGRE “Guidelines for conducting design reviews for transformers - Guidelines for conducting
design reviews for power transformers working group A2.36 Task Force 2 (Replaces TB 204)”.
17.12.1.3 The manufacturer shall provide all necessary information and calculations to demonstrate that the
transformer meets the requirements for short circuit strength and durability. The latest recommendations of
IEC or Cigre SC 12 shall be applied for short circuit withstand evaluation.
17.12.1.4 The validity of Type tests (except dynamic short circuit test) of Transformer shall be not
older than 5 years as on the date of NOA, provided that offered transformer is of same design as that of
type tested transformer and active materials like – CRGO, copper conductor and insulation material are of
same or better grade with respect to type tested unit. Failing which, type testing of transformer shall be
carried out by the contractor at his own cost. Further, type test report of Transformer from the same
manufacturing plant shall only be acceptable. With regard to Validity of Dynamic short circuit test, refer
clause 17.4.0 above.
17.13.1.1.2 All seams and joints which are not required to be opened at site, shall be factory welded, and
wherever possible they shall be double welded. Welding shall conform to BS-5135/IS 9595. After
fabrication of tank and before painting, dye penetration test shall be carried out on welded parts of jacking
bosses, lifting lugs and all load bearing members. The requirement of post weld heat treatment of tank/stress
relieving shall be based on recommendation of BS-5500 table 4.4.3.1/IS 10801.
17.13.1.1.3 Tank stiffeners shall be provided for general rigidity and these shall be designed to prevent
retention of water.
17.13.1.1.3 The tank shall be of proven design either bell type with bolted /welded joint or conventional
type with welded / bolted top cover. Bell type tank shall be provided with joint at about 500 mm above the
bottom of the tank. The welded joint shall be provided with flanges suitable for repeated welding. The joint
shall be provided with a suitable gasket to prevent weld splatter inside the tank. Proper tank shielding shall
be done to prevent excessive temperature rise at the joint.
b. A minimum of four jacking pads in accessible position to enable the transformer complete with oil to be
raised or lowered using hydraulic jacks. Each jacking pad shall be designed to support with an adequate
factor of safety at least half of the total mass of the transformer filled with oil allowing in addition to
maximum possible misalignment of the jacking force to the centre of the working surface.
d. 04 nos. of Gate valves for UHF sensors for PD Measurements (applicable for 400kV
Transformer only) at various locations. Location of valves shall be finalized during design review.
e. Suitable provisions of pockets for OTI, WTI & RTDs including two spare pockets.
17.13.1.1.5 The tank shall be designed in such a way that it can be mounted either on the plinth directly or
on rollers, as per manufacturer's standard practice.
17.13.1.1.6 The base of each tank shall be so designed that it shall be possible to move the complete
transformer unit by skidding in any direction without damage when using plates or rails.
17.13.1.2.2 At least two adequately sized inspection openings one at each end of the tank, shall be
provided for easy access to bushings and earth connections. The inspection covers shall not weigh more
than 25 kg. Handles shall be provided on the inspection cover to facilitate lifting.
17.13.1.2.3 The tank cover shall be provided with pockets for oil and winding temperature indicators. The
location of pockets (for OTI, WTI & RTDs including two spare pockets) shall be in the position where oil
reaches maximum temperature. Further, it shall be possible to remove bulbs of OTI/WTI/RTD without
lowering the oil in the tank. The thermometer shall be fitted with a captive screw to prevent the ingress of
water.
17.13.1.2.4 Bushing turrets, covers of inspection openings, thermometer pockets etc. shall be designed to
prevent ingress of water into or leakage of oil from the tank.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
17.13.1.2.5 To allow for the effect of possible induced and capacitive surge current flow, the tank cover
and bushing turret shall be fixed to the transformer in such a way that good electrical contact is maintained
around the perimeter of the tank and turrets.
17.13.1.2.6 The transformer shall be provided with a suitable diameter pipe flange, butterfly valve, bolted
blanking plate and gasket shall be fitted at the highest point of the transformer for maintaining vacuum in
the tank.
The transformer cover and generally the internal spaces of the transformer and all pipe connections shall
be designed so as to provide efficient venting of any gas in any part of the transformer to the Buchholz
relay. The space created under inspection /manhole covers shall be filled with suitable material to avoid
inadvertent gas pockets. The Covers shall be vented at least at both longitudinal ends. The design for gas
venting shall take into accounts the slopes of the plinth (if any) on which the transformer is being
mounted.
All bolted connections shall be fitted with weather proof, hot oil resistant, resilient gasket in between for
complete oil tightness. If gasket is compressible, metallic stops/other suitable means shall be provided to
prevent over-compression.
The properties of all the above gaskets / O-Rings shall comply with the requirements of IS-11149. Gaskets
and O-rings shall be replaced every time whenever the joints are opened.
To prevent transformer movement during earthquake, suitable clamping devices shall be provided for
fixing the transformer to the foundation.
17.13.1.7 Conservator
17.10.1.7.1 Main tank conservator shall have air cell type constant oil pressure system to prevent oxidation
and contamination of oil due to contact with moisture. Conservator shall be fitted with magnetic oil level
gauge with potential free high and low oil level alarm contacts and prismatic oil level gauge.
17.13.1.7.2 Conservator tank shall have adequate capacity with highest and lowest visible-levels to meet
the requirements of expansion of total cold oil volume in the transformer and cooling equipment from
minimum ambient temperature to top oil temperature of 110 deg C. The capacity of the conservator tank
shall be such that the transformer shall be able to carry the specified overload without overflowing of oil.
17.13.1.7.3 The conservator shall be fitted with lifting lugs in such a position so that it can be removed for
cleaning purposes. Suitable provision shall be kept to replace air cell and cleaning of the conservator as
applicable.
17.13.1.7.4 Conservator shall be positioned so as not to obstruct any electrical connection to transformer.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
17.13.1.7.5 The connection of air cell to the top of the conservator is by air proof seal preventing entrance
of air into the conservator. The main conservator tank shall be stencilled on its underside with the words
“Caution: Air cell fitted”. Lettering of at least 150 mm size shall be used in such a way to ensure clear
legibility from ground level when the transformer is fully installed. To prevent oil filling into the air cell,
the oil filling aperture shall be clearly marked. The transformer rating and diagram plate shall bear a
warning statement that the “Main conservator is fitted with an air cell”.
17.13.1.7.6 Contact of the oil with atmosphere is prohibited by using a flexible air cell of nitrile rubber
reinforced with nylon cloth. The temperature of oil in the conservator is likely to raise up to 110 deg.C
during operation. As such air cell used shall be suitable for operating continuously at this temperature.
17.13.1.7.7 The transformer manual shall give full and clear instructions on the operation, maintenance,
testing and replacement of the air cell. It shall also indicate shelf life, life expectancy in operation, and the
recommended replacement intervals.
17.13.1.7.8 The conservator tank and piping shall be designed for complete vacuum / filling of the main
tank and conservator tank. Provision must be made for equalising the pressure in the conservator tank and
the air cell during vacuum / filling operations to prevent rupturing of the air cell.
17.13.1.7.9 The contractor shall furnish the leakage rates of the rubber bag/ air cell for oxygen and
moisture. It is preferred that the leakage rate for oxygen from the air cell into the oil will be low enough so
that the oil will not generally become saturated with oxygen. Air cells with well proven long-life
characteristics shall be preferred. OLTC shall have conventional type conservator (without aircell) with
magnetic oil level gauge with potential free oil level alarm contact and prismatic oil level gauge.
17.13.2.2 The feed pipe to the transformer tank shall enter the transformer cover plate at its
highest point and shall be straight for a distance not less than five times its internal diameter on the
transformer side of the Buchholz relay, and straight for not less than three times that diameter on the
conservator side of the relay. This pipe shall rise towards the oil conservator, through the Buchholz relay,
at an angle of not less than 5 degrees. The feed pipe diameter for the main conservator shall be not less
than 80 mm.
17.13.2.3 The Gas-venting pipes shall be connected to the final rising pipe between the transformer and
Buchholz relay as near as possible in an axial direction and preferably not less than five times pipe
diameters from the Buchholz relay.
17.13.2.4 A double flange valve of preferably 50 mm and 25 mm size shall be provided to fully drain the
oil from the main tank conservator and OLTC conservator tank respectively.
17.13.2.5 Pipe work shall neither obstruct the removal of tap changers for maintenance or the opening of
inspection or manhole covers.
To extract the harmful constituents like water, acids etc. from oil, Thermosyphon filter of
cylindrical shape with perforated steel trays filled with absorbents such as active alumina should be
provided.
The filter assembly shall be mounted on the transformer as well as ground supported and connected with
pipes and shut off valves. Suitable instructions required to be followed for commissioning, dismantlement
and maintenance of filter arrangement, re-generation and storage of the absorbent etc. must be included in
the instrumentation manual. A detailed drawing showing internal arrangement shall be submitted.
The oil & absorbent capacity required in the thermo-syphon filter is as under.
i) Quantity of oil - 1.0% of total oil by weight
ii) Quantity of absorbent - 0.2% to 0.25% of total oil by weight
17.13.4.2 It shall be capable of withstanding full internal vacuum at mean sea level. It shall be mounted
directly on the tank. Suitable canopy shall be provided to prevent ingress of rain water. One set of potential
free contacts (with plug & socket type arrangement) per device shall be provided for tripping. Following
routine tests shall be conducted on PRD:
a) Air pressure test
b) Liquid pressure test
c) Leakage test
d) Contact operation test
e) Dielectric test on contact terminals
17.13.5.0 Sudden Pressure Relay
17.13.5.1 One number of Sudden Pressure relay with alarm/trip contacts (Terminal connection plug &
socket type arrangement) shall be provided on tank of transformer. Operating features and size shall be
reviewed during design review. Suitable canopy shall be provided to prevent ingress of rain water.
Pressurised water ingress test for Terminal Box (routine tests) shall be conducted on Sudden Pressure
Relay
The relay shall be provided with a test cock suitable for a flexible pipe connection for checking its
operation and taking gas sample. A copper tube shall be connected from the gas collector to a valve
located about 1200 mm above ground level to facilitate sampling while the Transformer in service.
Suitable canopy shall be provided to prevent ingress of rain water. Each device shall be provided with two
potential free contacts (Plug & socket type arrangement), one for alarm / trip on gas accumulation and
the other for tripping on sudden rise of pressure.
17.13.6.2 The Buchholz relay shall not operate during starting/ stopping of the transformer oil
circulation under any oil temperature conditions. The pipe or relay aperture baffles shall not be used to
decrease the sensitivity of the relay. The relay shall not mal-operate for through fault conditions or be
influenced by the magnetic fields around the transformer during the external fault conditions. Pressurised
water ingress test for Terminal Box (routine tests) shall be conducted on Buchholz relay.
17.13.8.1 In addition to the above, the following accessories shall be provided for remote indication of oil
temperature:
17.13.9.2 In addition to the above, the following accessories shall be provided for remote indication of oil
temperature:
Temperature transducer with Pt100 sensor for each winding (As per ANNEXURE- J)
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
RTD shall be provided with Pt100 temperature sensor having nominal resistance of 100 ohms at zero
degree centigrade. The Pt100 temperature sensor shall have three wire ungrounded system. The calibration
shall be as per IEC 60751-2 or equivalent. The Pt100 sensor may be placed in the pocket containing
temperature sensing element. RTD shall include image coil, Auxiliary CTs, if required to match the image
coil, for WTI system and shall provide dual output 4-20mA for remote WTI and SCADA system
individually. The transducer, Auxiliary CT shall be installed in the Individual Marshalling Box. Any
special cable required for shielding purpose, for connection between Pt100 temperature sensor and
transducer, shall be in the scope of Contractor. 4-20mA signal shall be wired to Digital RTCC / BCU panel
for further transfer data to SCADA through IEC 61850 compliant communications. The temperature
indicators (OTI & WTI) shall be so mounted that the dials are about 1200 mm from ground level. Glazed
door of suitable size shall be provided for convenience of reading.
17.13.10.3 Optical sensors & temperature measuring unit (for 400/220/132 kV Class Transformer)
17.10.10.3.1 Optical temperature sensors shall be fitted on each Transformer unit. 16 number probes for 3-
ph unit and 8 number probes for 1-ph unit shall be provided. The optical sensors measuring system shall
be of direct measurement non-calibrating type. All the sensors shall be brought out to separate optical
sensor box or in Individual Marshalling Box mounted on transformer tank to facilitate measurement of
temperature during service life on each unit.
17.13.10.3.2 In order to facilitate measurement of temperature from the optical sensors, temperature
measuring unit/system having at least 16 channels shall be mounted inside the separate optical sensor box
or Transformer Marshalling Box for each transformer unit. The measuring unit shall be capable to retain
temperature data for at least 30 days with facility to download these data.
17.13.10.3.3 Temperature measuring unit/system shall be suitable for satisfactory operation with ambient
conditions and IEC 61850 compliant to interface with Employer’s SCADA system through FO port.
17.13.10.3.4 Location of optical temperature sensors inside the transformer shall be decided during design
review.
17.13.10.3.5 The installation and commissioning at site shall be done under the supervision of OEM
representative or OEM certified representative.
17.13.10.4.2 Two earthing terminals suitable for connection to 75 x 12 mm galvanised steel flat shall also
be provided on each cooler, individual/common marshalling box and any other equipment mounted
separately. For the tank-mounted equipment like online drying/ Online DGA/ Optical Sensor Box etc.
double earthing shall be provided through the tank for which provision shall be made through tank and
connected through two flexible insulated copper links.
17.13.10.4.3 Equipotential flexible copper link of suitable size at least 4 Nos. for Tank mounted
turret with tank and tank with cover and or Bell shall be provided. For other components like - pipes,
conservator support etc. connected to tank shall also be provided with equipotential flexible copper link.
Each transformer unit should have provision for earthing and connected to grounding mat when not in
service. For this purpose, neutral shall have provision for connection to ground by a brass/tinned copper
grounding bar supported from the tank by using porcelain insulator. The end of the tinned/brass copper bar
shall be brought to the bottom of the tank at a convenient point for making bolted connection to 75 X 12
mm GS flat connected to station grounding mat. The other end of the tinned/brass copper bar shall be
connected to the neutral bushing through flexible conductor/jumper. HV & IV Terminals shall also be
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
earthed through neutral by flexible copper connection. Contractor shall provide suitable arrangement for
the above.
17.13.9.0 Core
17.13.9.1 The magnetic circuit shall be core type. Each limb shall be joined with top and bottom yokes.
The laminations shall be made from high grade non-ageing cold rolled grain oriented (CRGO) silicon
alloy of HI -B or its equivalent grade steel preferably of ZDKH class of material or of equivalent grade
(as per BIS / IEC). Indian transformer manufacturers shall use core material as per above specification
with BIS certification. Only those bidders who directly imported CRGO either from the manufacturer
or through their accredited marketing organization of repute (and not through any agent) shall be
considered. In support of this requirement the bidder shall submit an undertaking in specified
format (Annexure C) in the form of affidavit on Rs.100/- stamp paper, duly notarized.
17.13.10.2 The CRGO shall be cut at Mill’s authorized Processing unit only.
17.13.9.3 The temperature of any part of the core or its support structure in contact with oil shall not
exceed 120 deg C under normal operating condition and 130 deg C under 10% over voltage and maximum
ambient air temperature conditions of 50 deg C. Adequate temperature margin shall be provided to
maintain the long-life expectancy for this material.
17.13.9.4 Core and winding shall be capable of withstanding the shock during transport, installation
and service and adequate provision shall be made to prevent movement of core and winding with
respect to tank during these conditions.
17.13.9.5 All steel sections used for supporting the core shall be thoroughly sand / shot blasted after
cutting, drilling and welding.
17.13.9.6 Each core lamination shall be insulated with a material that will not deteriorate due to pressure
and hot oil.
17.13.9.7 The supporting frame work of the core shall be so designed as to avoid presence of pockets
which would prevent complete emptying of tank through drain valve or cause trapping of air during oil
filling.
17.13.9.8 Adequate lifting lugs will be provided to enable the core and windings to be lifted.
17.13.9.9 The core shall be earthed to the core clamping structure at one point only, through a removable
external link of minimum size of 80 sq. mm copper suitably located and protected to facilitate testing after
installation of the transformer. The removable links shall have adequate section to carry ground fault
current. Separate identification name plate/labels shall be provided for the ‘Core’ and ‘Core clamp’ on the
outside of tank cover.
17.13.9.10 In case core laminations are divided into sections by insulating barriers or cooling ducts parallel
to the plane of the lamination, tinned copper bridging strips shall be inserted to maintain electrical
continuity between sections.
17.13.9.11 The insulation for the core to bolts and core to clamps shall be such as to withstand a test
voltage of 2 (two) KV rms at 50 Hz for one minute.
17.13.9.12 The maximum flux density in any part of the core and yoke at the rated MVA, voltage &
frequency shall be such that less than 10% continuous over voltage condition does not exceed 1.9 Tesla.
17.13.9.13 For consideration of over fluxing, the transformer shall be suitable for continuous operation for
values of over fluxing at (i) 110% (ii) one minute for 125% and (iii) 5 seconds for 140% of rated voltage.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
17.13.9.14 The Transformer shall be of BOLTLESS core design. The Bidders will furnish documentary
evidence with proof of their experience and performance in such type of design.
17.13.9.15 When bell type construction is offered, suitable projecting guides shall be provided on core
assembly to facilitate removal of tank. The supporting framework of core shall be so designed so as to
avoid presence of pockets, which would prevent complete emptying of the tank through drain valve or
cause trapping of air during oil filling.
17.13.9.16 Successful Bidder shall furnish calculation towards maximum peak value of magnetizing in-
rush current and shall justify that the transformer will not trip due to this during initial charging and
subsequent charging.
17.13.9.17 Oil ducts shall be provided where necessary to ensure adequate cooling. The welding structure
and major insulation shall not obstruct the free flow of oil through such ducts.
17.13.9.18 The prime core materials are only to be used. Bidder’s should furnish following document as
applicable as a proof towards use of prime Core material to be submitted before the stage inspection:
All parts of the cores shall be of robust design capable of withstanding any shocks to which they may be
subjected during lifting, transport, installation and service.
17.14.0 Windings
17.14.1.0 General
The Contractor shall ensure that windings of all transformers are made in dust proof and conditioned
atmosphere. The conductors shall be of electrolytic grade copper free from scales and burrs.
The insulation of transformer windings and connections shall be free from insulating compounds
which are liable to soften, ooze out, shrink or collapse and shall be non-catalytic and chemically
inactive in transformer oil during service.
Coil assembly and insulating spacers shall be so arranged as to ensure free circulation of oil and to
reduce the hot spot of the winding.
The coils would be made up, shaped and braced to provide for expansion and contraction due to
temperature changes.
The conductor shall be transposed at sufficient intervals in order to minimize eddy currents and to
equalise the distribution of currents and temperature along the winding.
The windings shall be designed to withstand the dielectric tests specified. The type of winding used
shall be of time tested. An analysis shall be made of the transient voltage distribution in the
windings, and the clearances used to withstand the various voltages. Margins shall be used in
recognition of manufacturing tolerances and considering the fact that the system will not always be
in the new factory condition.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
The barrier insulation including spacers shall be made from high- density precompressed pressboard
(1.1 gm/cc minimum for load bearing and 1 gm/cc minimum for non-load bearing) to minimize
dimensional changes.
The conductor insulation shall be made from high-density (at least 0.75 gm/cc) paper having high
mechanical strength. The characteristics for the paper will be reviewed at the time of design review.
Wherever required, electrostatic shield, made from material that will withstand the mechanical
forces, will be used to shield the high voltage windings from the magnetic circuit.
All winding insulation shall be processed to ensure that there will be no detrimental shrinkage after
assembly. All windings shall be pre-sized before being clamped.
Windings shall be provided with clamping arrangements which will distribute the clamping forces
evenly over the ends of the winding. The bracing of the windings and connections shall be such that
these parts shall safely withstand the cumulative effects of stresses which may occur during
handling, transportation, installation and service including line-to–line and line-to–ground faults.
In the case of ICTs with tertiary, the insulation of LV (Tertiary) winding shall be adequate to
withstand surge voltages appearing across them as a result of transfer due to impulse striking
on HV or IV terminals. The transformer shall be suitably designed so that the surges
transferred to tertiary winding do not exceed the permissible limits without the use of any
external means such as surge capacitors etc. under any condition. The tenderer shall also state
whether the transferred surges could be restricted to 170 KVP without the use of any external
means. The current density of the conductor used for tertiary winding shall not exceed the
current density specified for the main winding/conductor.
The stacks of windings shall receive adequate shrinkage treatment before and after final
assembly. Adjustable devices if necessary, shall be provided for taking up possible shrinkage
of coils if any, in service. The provision made in this respect shall be clearly brought out in the
Bid.
The transformer manufacturer should have in house availability of vapour phase Drying (VPD)
plant for proper drying of the insulation. In case VPD facility is not available, the bidder will prove
that the method of drying adopted by them is equivalent or better than VPD in terms of level of
dryness and other benefits of VPD.
The windings and connections of all transformers shall be braced to withstand socks, which may
occur during transport or due to switching and other transient conditions during service.
The winding shall be clamped securely in place, so that they will not be displaced or deformed
during short circuit. The assembled core and winding shall vacuum dried and suitably impregnated
before removing from the treating tank.
If the transpose winding is built up of section of disc coils, separated by spacers, the clamping
arrangements shall be such that equal pressures are applied to all columns of spacers. All such
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
spacers shall be securely located, shall be of suitable material and shall receive adequate shrinkage
treatment before assembly.
Winding shall be subjected to a shrinking and seasoning process, so that no further shrinkage occurs
during service. Adjustable devices shall be provided for taking up possible shrinkage in service.
Winding shall not contain sharp bends which might damage the insulation or produce high dielectric
stresses. No strip conductor wound on edge shall have width exceeding six times the thickness.
Varnish application on coil windings may be given only for mechanical protection and not for
improvement in dielectric properties. In no case varnish or other adhesive, be used which will seal
the coil and prevent evacuation of air and moisture and impregnation by oil.
Winding and connections shall be braced to withstand shocks during transport or short circuit.
Permanent current carrying joints in the windings and leads shall be welded or brazed. Clamping
bolts for current carrying parts inside oil shall be made of oil resistant material which shall not be
affected by acidity in the oil steel bolts, if used, shall be suitably treated.
Terminals of all windings shall be brought out of the tank through bushings for external
connections.
The winding shall be so designed that all coil assemblies of identical voltage ratings shall be
interchangeable and field repairs to the winding can be made readily without special equipment. The
coils shall have high dielectric strength.
Coils shall be made of continuous smooth high-grade electrolytic copper conductor, shaped and
braced to provide for expansion and contraction due to temperature changes.
Adequate barriers shall be provided between coils and core and between high and low voltage coil.
End turns shall have additional protection against abnormal line disturbances. The TM is to submit
the process at the time of the bid.
Tappings shall not be brought out from inside the coil or from intermediate turns and shall be so
arranged as to preserve as far as possible magnetic balance of the transformer at all voltage ratios.
The mating faces of bolted connections shall be appropriately finished and prepared for achieving good long
lasting, electrically stable and effective contacts. All lugs for crimping shall be of the correct size for the
conductors. Connections shall be carefully designed to limit hot spots due to circulating eddy currents.
Winding termination interfaces with bushings shall be designed to allow for repeatable and safe
connection under site conditions to ensure the integrity of the transformer in service.
The winding end termination, insulation system and transport fixings shall be so designed that the
integrity of the insulation system generally remains intact during repeated work in this area.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Allowances shall be made on the winding ends for accommodating tolerances on the axial
dimensions of the set of bushings and also for the fact that bushings may have to be rotated to get
oil level inspection gauges to face in a direction for ease of inspection from ground level.
In particular, rotation or straining of insulated connections shall be avoided during the fastening of
conductor pads (or other methods) on the winding ends onto the termination surfaces of the bushing.
Suitable inspection and access facilities into the tank in the bushing oil-end area shall be provided to
minimize the possibility of creating faults during the installation of bushings.
The transformer shall be capable of remaining in operation at full load without the measured
winding hot spot temperature exceeding 150°C for:
The permissible temperature of the top oil shall refer to the specific loading combination for which
the total losses are the highest. Individual permissible winding temperature rise shall be considered
relative to the specified loading combination which is the most severe for the particular winding
under consideration.
Specific requirement of bushings and their ratings etc. are as per general technical parameters.
17.17.0 Bushings
The electrical and mechanical characteristics of bushings shall be in accordance with IS: 2099 and
IS: 3347 (Part-III/Section-I). Dimensions and requirements of condenser bushings shall be in
accordance with IS 12676, 1989.
Bushings shall be robust and designed for adequate cantilever strength to meet the requirement of
seismic condition, substation layout and movement along with the spare
Transformer with bushing erected and provided with proper support from one foundation to another
foundation within the substation area. The electrical and mechanical characteristics of bushings
shall be in accordance with IEC: 60137/DIN 42530. All details of the bushing shall be submitted for
approval and design review.
420kV, 245 kV and 145 kV bushings shall be RIP bushing & 36 KV bushings shall be of porcelain
or oil communicating type. No arcing horns shall be provided on any bushing. Bushing shall be as
per technical particulars furnished. Bushings of identical rating shall be interchangeable.
Where turret type current transformers are specified, the bushings shall be removable without
disturbing the current transformers.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Bushing for voltage of 52 kV and above shall be RIP bushing with composite polymer insulator. 36
kV and below voltage class bushing shall be solid porcelain or oil communicating type.
RIP type bushing shall be provided with tap for capacitance and tan delta test. Test taps relying on
pressure contacts against the outer earth layer of the bushing is not acceptable.
RIP Bushing shall be specially packed to avoid any damage during transit and suitable for long
storage, with non-returnable packing wooden boxes with hinged type cover. Without any gap
between wooden planks. Packing Box opening cover with nails/screws type packing arrangement
shall not be acceptable. Bushing oil end portion shall be fitted with metal housing with positive dry
air pressure and a suitable pressure monitoring device shall be fitted on the metal housing during
storage to avoid direct contact with moisture with epoxy. Alternatively, oil filled metal housing with
suitable arrangement for taking care oil expansion due to temperature variations shall also be
acceptable. Manufacturer shall submit drawing/ documents of packing for approval during detail
engineering. Detail method for storage of bushing including accessories shall be brought out in the
instruction manual.
The terminal marking and their physical position shall be as per IEC: 60076.
Tan delta measurement at variable frequency (in the range of 20 Hz to 350 Hz) shall be carried out
on each condenser type bushing (OIP & RIP) at Transformer manufacturing works as routine test
before despatch and the result shall be compared at site during commissioning to verify the
healthiness of the bushing.
If the bushing Tan delta goes beyond 0.005 or increase is more than 0.001 within the warrantee
period w.r.t. pre-commissioning values, the contractor shall arrange to replace the defective bushing
by new one. No temperature correction factor shall be applicable for tan delta.
Special precaution shall be taken to eliminate moisture from paper insulation during manufacture,
assembly, transport and erection.
Bushing turrets shall be provided with vent pipes which shall be connected to route any gas
collection through the Buchholz relay.
To accommodate the bushing current transformers, space provided on the various voltage class
bushings shall be as under:
420kV : 400 mm *
245kV : 300 mm *
: 600 mm **
145kV : 100 mm *
: 300 mm **
: 600 mm ***
Note:
* = for one BCT
** = For two BCTs
*** = For three BCTs
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Bushing terminals shall be provided with terminal connectors of approved type and size for
connection to external parts. Terminal connectors should have been successfully type tested
strictly as per IS: 5561.
Connectors shall be of electrolytic grade copper forged and silver plated/tinned. No part of
a clamp shall be less than 10 mm thick.
Non-magnetic stainless-steel nuts, bolts and plain washers shall be used. Nuts and bolts shall
have hexagonal head with threads as per IS and shall be fully threaded type. Instead of spring
washers, check/lock nuts shall be provided.
The connectors shall be designed for minimum 120% of the maximum current carrying
capacity of the ACSR conductor and the temperature rise under these conditions shall not be
more than 50% of that of the main conductor.
It shall be possible to remove turret mounted CTs from the transformer tank without removing
the tank cover. Necessary precaution shall be taken to minimize the eddy currents and local
heat generated in the turret.
All secondary leads shall be brought to a terminal box near each bushing. These terminals shall
be wired up to the Cooler Control Cabinet using separate cables for each core/phase.
Bushing CT parameters indicated in the specification are tentative and liable to change within
reasonable limits. The Bidder shall obtain the Purchaser's approval before proceeding with
design of Bushing CTs.
The terminal marking and their physical position shall be in accordance with IS: 2026 unless otherwise
specified.
The neutral of the transformer shall be brought out through bushing. The neutral terminal of 3-phase
transformer shall be brought to the ground level by a brass/tinned copper grounding bar, supported from the
tank by using porcelain insulators. The end of the brass/tinned copper bar shall be brought to the bottom of
the tank, at a convenient point, for making bolted connection to two (2) 75 x 12 mm galvanised steel flats
connected to Employer's grounding mat.
neutral CT and earthing of neutral shall be provided by contractor. The neutral formation shall be such
that neutral winding of single-phase spare transformer can be disconnected or connected to either of the
three phase banks.
Delta Formation (applicable for 1-Phase Transformer) :( if specified in BPS)
The tertiary/LV winding terminals of the transformer shall be brought out through bushing. The contractor
shall connect Tertiary/LV of 1-phase transformers in DELTA configuration by overhead connection to
operate in 3-Phase Bank. The Delta shall be formed by approximate size of 3" IPS Al tube, which shall be
insulated with heat shrinkage insulating sleeve or cable of suitable voltage class and adequate thickness and
shall be supported by structure mounted bus post insulators at suitable intervals. Jumpers (twin) wherever
provided shall also be insulated at site using suitable insulation tape or sleeve atleast 52kV class for 33kV
Bus and atleast 36kV class for below 33kV voltage class Bus. The minimum phase to phase horizontal
spacing for delta formation shall be 1.5 meter. Suitable cable shall be used for delta formation for below
33kV winding All associated materials like bus post insulators, Aluminium tube, clamps & connectors,
support structures; hardware etc. required for tertiary delta formation shall be provided by the
contractor.
17.18.0 Cooling Equipment and its Control
The cooler shall be designed using radiator banks or tank mounted radiators. Design of Cooling
system shall satisfy the performance requirements.
In case of separately mounted radiator bank arrangement, the main tank shall have provision such
that cooler banks can be placed on either side of the main tank without the need of any extra
member/pipe maintaining the electrical clearances.
The radiator shall be of sheet steel in accordance with IS 513 and minimum thickness 1 mm. Each
radiator bank shall be provided with the following accessories:
If radiators are directly mounted on tank, sufficient number of thermometer pockets fitted with
captive screw cap on the inlet and outlet of tank side pipe of radiators shall be provided to record
temperature during temperature rise test.
One number standby fan shall be provided with each radiator bank.
Cooling fans shall not be directly mounted on radiator. It may cause undue vibration. These shall be
located so as to prevent ingress of rain water. Each fan shall be suitably protected by galvanised
wire guard. The exhaust air flow from cooling fan shall not be directed towards the main tank in any
case.
Two (2), 100% centrifugal or axial in line oil pumps, if applicable, (out of which one pump shall be
standby) shall be provided with each radiator bank. Measures shall be taken to prevent mal-
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
operation of Buchholz relay when all oil pumps are simultaneously put into service. The pump shall
be so designed that upon failure of power supply to the pump motor, the pump impeller will not
limit the natural circulation of oil.
An oil flow indicator shall be provided for the confirmation of the oil pump operating in a normal
state. An indication in the flow indicator and potential free contacts for remote alarm shall be
provided.
Valves shall be provided across the pump and oil flow indicator to avoid oil drain and long outage
during maintenance / replacement of pump and oil flow indicator.
Cooling fans and oil pump motors shall be suitable for operation from 415 volts, three phase 50 Hz
power supply and shall conform to IS: 325 / IEC 60034. Each cooling fan and oil pump motors shall
be provided with starter thermal overload and short circuit protection. The motor winding insulation
shall be conventional class 'B' type. Motors shall have hose proof enclosure equivalent to IP: 55 as
per IS: 4691/ IEC 60034-5.
The cooler pipes, support structure including radiators and its accessories shall be hot dip galvanised
or corrosion resistant paint should be applied to external surface of it.
Air release device and oil plug shall be provided on oil pipe connections. Drain valves shall be
provided in order that each section of pipe work can be drained independently.
Automatic operation control of fans/pumps shall be provided (with temperature change) from
contacts of winding temperature indicator. The Contractor shall recommend the setting of WTI for
automatic changeover of cooler control over entire cooling option. The setting shall be such that
hunting i.e. frequent start-up operations for small temperature differential do not occur.
Suitable manual control facility for cooler fans and oil pumps shall be provided. Selector switches
and push buttons shall also be provided in the cooler control cabinet to disconnect the automatic
control and start/stop the fans and pump manually. The changeover to standby oil pump in case of
failure of service oil pump shall be automatic.
In addition to the traditional starting of fan and pump by winding & oil temperature, the starting of
forced cooling shall be done if the load exceeds a current setting of 0.6 p.u. for 5 seconds.
Furthermore, a one-week timer is required to check the healthiness of the cooling system on a
routine basis for one hour at a time.
One potential free initiating contact for all the above conditions shall be wired independently to the
terminal blocks of cooler control cabinet and for single ph. Unit connection shall be extended
further to CMB.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
The cooler control cabinet / Individual Marshalling box shall have all necessary devices meant for
cooler control and local temperature indicators. All the contacts of various protective devices
mounted on the transformer and all the secondary terminals of the bushing CTs shall also be wired
upto the terminal board in the cooler control cabinet/Individual Marshalling box. All the CT
secondary terminals in the cooler control cabinet shall have provision for shorting to avoid CT open
circuit while it is not in use.
All the necessary terminations for remote connection to Purchaser's panel shall be wired upto the
Marshalling Box.
The Contractor shall derive AC power for Cooler Control Circuitry from the AC feeder. In case
auxiliary power supply requirement for Cooler Control Mechanism is different than station auxiliary
AC supply, then all necessary converters shall be provided by the Contractor. Details of station
auxiliary power supply are mentioned in CLAUSE 7.1.2 OF CHAPTER 7.
17.18.1.2.1 Cooling Equipment Control (OFAF or ODAF) for Unit Coolers (if applicable)
i) Suitable manual control facility for unit cooler shall be provided.
ii) The changeover to standby unit cooler bank oil pump in case of failure of any service unit
cooler shall be automatic.
iii) Selector switches and push buttons shall also be provided in the cooler control cabinet to
disconnect the automatic control and start/stop the unit cooler manually.
iv) Cooler fans & oil pumps of all unit coolers (except standby cooler) shall operate continuously.
The starting of unit cooler shall be done as soon the Circuit Breaker of HV/IV/LV (as
applicable) side is switched on.
v) Once started the cooling shall remain in operation as long as the transformer is in service.
When the transformer is switched off the cooling shall continue to run for a further duration of
30 minutes. This timer shall be at least adjustable from 15 to 60 minutes. Further, a one-week
timer is required to check the healthiness of the complete cooling system on a routine basis for
one hour at a time. Spurious operation should however be avoided by appropriate settings. All
settings shall be adjustable
vi) Adequate warning/ safety labels are required to indicate that the fans may start at any time.
vii) If any one group(s) is out of service and isolated, this shall not affect the automatic starting of
the other unit cooler.
viii) Following lamp indications shall be provided in cooler control cabinet:
· Cooler Supply failure (main)
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
One potential free initiating contact for all the above conditions shall be wired independently to the terminal
blocks of cooler control cabinet and for single ph. unit connection shall be extended further to CMB.
17.19.0 Paint system and procedures
The typical painting details for transformer main tank, pipes, conservator tank, radiator, control cabinet/
marshalling box / oil storage tank etc. shall be as given in Annexure – D. The proposed paint system shall
generally be similar or better than this. The quality of paint should be such that its colour does not fade
during drying process and shall be able to withstand temperature up to 120 deg C. The detailed painting
procedure shall be finalized during award of the contract.
g) Sufficient quantity of oil necessary for first filling of all tanks, coolers and radiators at the proper level
along with 10% extra oil by weight for topping up shall be supplied in non-returnable containers suitable
for outdoor storage.
h) The Bidder shall warranty that characteristic of oil furnished shall comply with the requirements
specified in IEC: 60296 with the latest amendment /revision and shall be suitable for EHV grade
transformers.
(Note: The color of the barrels in which Naphthenic based transformer oil is to be supplied shall be
Red)
up to the specified parameter by circulation within the transformer. The Unused inhibited Insulating Oil
parameters including parameters of oil used at manufacturer’s works, processed oil, oil after filtration and
settling are attached at Annexure – E. The oil test results shall form part of equipment test report.
Sufficient quantity of oil necessary for maintaining required oil level in case of leakage in tank, radiators,
conservator etc. till the completion of warranty period shall be supplied.
Inhibited oil used for first filling, testing and impregnation of active parts at manufacturer's works shall be
of same type of oil (in line with IEC 60076-3) which shall be supplied at site and shall meet parameters as
per specification.
The particle analysis shall be carried out in an oil sample taken after completion of the oil filtration at site.
The procedure and interpretation shall be in accordance with the recommendation of CIGRE report WG-
12.17 - “Effect of particles on transformer dielectric strength”.
Dummy insulation test block (2 Nos.) shall be inserted in the active part of Transformer at factory and same
shall be used to detect the volume of moisture content. Manufacturer to ensure that moisture content in the
dummy insulation test block is less than 0.5% after drying process of solid insulation. Out of two dummy
blocks, one block shall be used during manufacturing stage and another one shall be sent with Transformer
at site. Before application of vacuum and oil filling, the 2nd dummy block shall be used for DP Test (Degree
of polymerisation). To review the moisture content in the active part insulation at site during erection, Dew
Point method shall be applied.
Procedures for site drying, oil purification, oil filling etc. shall be done as per EMPLOYER Field
Quality Plan (FQP).
The duration of the vacuum treatment shall be demonstrated as adequate by means of water / dew
point measurement with a cold trap or other suitable method. The vacuum shall be measured on the
top of the transformer tank and should be less than 1mbar.
Oil filling under vacuum at site shall be done with transformer oil at a temperature not exceeding
65°C. Vacuum shall not be broken until the Transformer is oil filled up to the Buchholz relays.
The minimum safe level of oil filling (if different from the Buchholz level) to which
the Transformer shall be oil filled under vacuum, shall be indicated in the manual.
The Ultra High Vacuum type oil treatment plant (on returnable basis) of adequate capacity
(generally 6000 litres per hour and above) suitable for treatment of oil in EHV class Transformer
shall be used. The plant shall be capable of treatment of new oil (as per IEC 60296) and
reconditioning of used oil (as per IS: 1866/IEC: 60422 for oil in service) at rated capacity on single
pass basis as follow:
filtered oil.
vi) Processing temperature shall be automatically controlled and have an adjustable range from
40 deg C to 80 deg C.
The above oil treatment plant (Filtration unit) shall be arranged by the bidder at his own cost.
The insulating oil for the Transformer shall be delivered at site generally not before 90 days from the date of
commissioning, with prior information to the Employer, in view of risk involved in balk storage, pilferage
and fire hazard. In case this oil is not filled in Transformer due to delay in commissioning, same oil shall be
used only after testing and ensuring that oil parameters are well within the specified limits.
Insulating oil shall be delivered to the site in returnable oil drums / flexi bag / tanker. The oil drums / flexi
bag / tanker shall be taken back without any extra cost to Employer within generally 45 days after utilisation
of oil but in any case, before contract closing. However, the spare oil shall be delivered in non-returnable
drums.
17.21.2 Cabling
17.21.2.1 All interconnecting control and power cables between various parts of Transformers like turret
CT, MBs, Fans, pumps, Buchholz, PRD etc. shall be routed through covered cable tray or GI conduit and
shall be properly dressed. All cables shall be armoured type. Un-armoured cables (if provided) in any
circuitry, shall be through GI conduit and no part shall be exposed. Cable terminations shall be through stud
type TB and ring type lugs. Typical Technical specification for cables is attached at Annexure-I. Contractor
shall provide type tested cables from approved sources. No type testing for cables is envisaged. Both ends of
all the wires (control & power) shall be provided with proper ferrule numbers for tracing and maintenance.
Further, any special cables (if required) shall also be considered included in the scope. All cable accessories
such as glands, lugs, cable tags/ numbers etc. as required shall be considered included in the scope of
supply.
Cabling of spare unit with isolator switching arrangement shall be in such a way that spare unit of
transformer can be connected in place of faulty unit without physically shifting and all the control,
protection, indication signals of spare unit shall be brought in common marshalling box of all the banks.
From CMB all the control, protection and indication signals of R, Y, B and Spare units shall be transferred
to Purchaser’s Control panels / SCADA. Change-over of spare unit signals with faulty unit shall be done
through Purchaser’s C & R panels / SCADA level. Changeover of RTCC signals shall be carried out in
CMB.
17.22.0 Tap Changing Equipment
Each transformer shall be provided with On Load Tap changing equipment as specified elsewhere.
OLTC shall be motor operated suitable for local as well as remote operation. The diverter switch or arcing
switch shall be designed so as to ensure that its operation once commenced shall be completed
independently of the control relays or switches, failure of auxiliary supplies etc. To meet any contingency
which may result in incomplete operation of the diverter switch, adequate means shall be provided to
safeguard the transformer and its ancillary equipment. The current diverting contacts shall be housed in a
separate oil chamber not communicating with the oil in main tank of the transformer. The contacts shall be
accessible for inspection without lowering oil level in the main tank and the contacts shall be replaceable.
Necessary safeguards shall be provided to avoid harmful arcing at the current diverting contacts in the event
of operation of the OLTC gear under overload conditions of the transformer.
The OLTC oil chamber shall have oil filling and drain valve, oil sampling valve, relief vent and level glass.
Oil sampling valve of minimum size, accessible from ground, shall be provided to take sample of oil from
the OLTC chamber. It shall also be fitted with an oil surge relay which shall be connected between OLTC
oil chamber and OLTC conservator tank.
Tap changer shall be so mounted that bell cover of transformer can be lifted without removing connections
between windings and tap changer.
OLTC shall be suitable for manually handle operated and electrically motor operated. For local
manual operation from Local OLTC Control cabinet (Drive Mechanism Box), an external handle
shall be provided.
OLTC’s Local control cabinet shall be mounted on the tank in accessible position. The cranking
device/handle for manual operation for OLTC gear shall be removable and suitable for operation by
a man standing at ground level. The mechanism shall be complete with the following:
a. Mechanical tap position indicator which shall be clearly visible from near the transformer.
b. A mechanical operation counter of at least five digits shall be fitted to indicate the number of
operations completed and shall have no provision for resetting.
c. Mechanical stops to prevent over-cranking of the mechanism beyond the extreme tap positions.
d. The manual control considered as back up to the motor operated on load tap changer control
shall be interlocked with the motor to block motor start-up during manual operation.
e. The manual operating mechanism shall be labelled to show the direction of operation for raising
the voltage and vice-versa.
f. An electrical interlock to cut-off a counter impulse for reverse step change being initiated during
a progressing tap change and until the mechanism comes to rest and resets circuits for a fresh
position.
For electrical operation from local as well as remote, motor operated mechanism shall be provided.
It shall not be possible to operate the electric drive when the manual operating gear is in use. It shall
not be possible for any two controls to be in operation at the same time. Transfer of source in the
event of failure of one AC supply shall not affect the tap changer. Thermal device or other means
shall be provided to protect the motor and control circuit. The Local OLTC Drive Mechanism Box
shall house all necessary devices meant for OLTC control and indication. It shall be complete with
the followings:
i. A circuit breaker/contactor with thermal overload devices for controlling the AC auxiliary supply
to the OLTC motor
ii. Emergency Push Button to stop OLTC operation
iii. Cubicle light with door switch provided with anti-condensation metal clad heaters to prevent
condensation of moisture
iv. Padlocking arrangement for hinged door of cabinet
v. All contactors relay coils and other parts shall be protected against corrosion, deterioration due to
condensation, fungi etc.
vi. The cabinet shall be tested at least IP 55 protection class.
All relays and operating devices shall operate correctly at any voltage within the limits specified
below. In case auxiliary power supply requirement for OLTC DM Box is different than station
auxiliary AC supply, then all necessary converters shall be provided by the Contractor.
In case auxiliary power supply requirement for OLTC DM Box is different than station auxiliary
AC supply, then all necessary converters shall be provided by the Contractor.
Operating mechanism for on load tap changer shall be designed to go through one step of tap
change per command only, until the control switch is returned to the off position between
successive operations / repeat commands.
Limit switches shall be provided to prevent overrunning of the mechanism and shall be directly
connected in the control circuit of the operating motor provided that a mechanical de-clutching
mechanism is incorporated. In addition, a mechanical stop shall be provided to prevent over-running
of the mechanism under any condition. An interlock to cut-out electrical control when it tends to
operate the gear beyond either of the extreme tap positions.
OLTC local control cabinet shall be provided with tap position indication for the transformer. Drive
Mechanism shall be equipped with a fixed resistor network capable of providing discrete voltage
steps or provide 4-20mA transducer outputs for tap position indication in CMB (for single phase
unit) and input to Digital RTCC/SCADA system.
'Local-remote' selector switch shall be provided in the local OLTC control cabinet. In Local mode,
all electrical commands from remote (i.e. from CMB, Digital RTCC, SCADA etc.) shall be cut-
off/blocked. Electrical operations to change tap positions shall be possible by using raise/lower push
buttons under local mode from DM Box. In remote mode electrical commands from CMB/ Digital
RTCC/SCADA etc. shall be executed. The remote-local selector switch shall be having at-least two
spare contacts per position.
Following minimum contacts shall be available in DM Box, which shall be wired to CMB for single
phase unit. Further these contacts shall be wired to Digital RTCC panel:
a. INCOMPLETE STEP which shall not operate for momentary loss of auxiliary power.
b. OLTC motor overload protection
c. Supply to DM Motor fail
d. OLTC IN PROGRESS
e. Local / Remote Selector switch position
f. OLTC upper/lower limits reached
All relays, switches, fuses etc. shall be mounted in the OLTC local control cabinet and shall be
clearly marked / labelled for the purpose of identification.
A permanently legible lubrication chart if required shall be fitted within the OLTC local control
cabinet.
Following contacts shall be wired to TBs in CMB for further wiring to C & R Panels.
d) 415V Main AC supply Fail
e) 415V Standby AC supply Fail
Following contacts shall be wired to TBs in CMB for further wiring to digital RTCC Panel:
(c) INCOMPLETE STEP
(d) OLTC motor overload protection
(e) Supply to DM Motor fail
(f) OLTC IN PROGRESS
(g) Local / Remote Selector switch positions of DM
(h) OLTC upper/lower limits reached
(i) 'Independent-combined-remote’ selector switch positions of CMB
Further, OLTC Tap position Digital indications for all three 1-Ph Transformer units either separately or
through selector switch shall be provided in CMB. The same shall also be wired to Digital RTCC Panel to
display tap positions for all three 1-ph unit separately.
17.23.0 Digital RTCC Panel
The digital RTCC relay shall have Automatic Tap Changer control and monitoring relay with Automatic
Voltage Regulating features (referred as Digital RTCC relay) to remotely control and monitor OLTC.
The contractor shall also provide Digital RTCC panel consisting of 4 Nos. Digital RTCC relays. Further,
one spare Digital RTCC relay shall also be provided in the same panel. Each digital RTCC relay shall be
used to control 1 bank of transformers (i.e. 1 No. 3-Phase unit)
Digital RTCC relay shall be microprocessor based adopting the latest state of the art design & technology
with in-built large display for ease of programming and viewing. The unit supplied shall be field
programmable so that in the event of change in transformer / location, it could be customized to site
conditions without sending back to works. The programming shall be menu driven and easily configurable.
If it is designed with draw out type modules, it should take care of shorting all CT inputs automatically
while drawing out. The CT / VT ratio shall be field programmable and Relay shall display the actual HV
Voltage and current considering suitable multiplying factors. The system shall be self-sufficient and shall
not require any additional devices like parallel balancing module etc.
All Digital RTCC Relays shall be of same make for smooth integration of these relays for parallel
operations of all transformers in the substation.
The RTCC Panel shall be provided with digital RTCC relay having Raise/Lower push buttons, Manual/
Automatic mode selection features, Master / Follower/ Independent/Off mode selection features for control
of OLTC. Touch screen option in the relay, instead of electrical push button/switch is also acceptable.
In Manual Mode: In this mode, power system voltage based automatic control from digital RTCC relay
shall be blocked and commands shall be executed manually by raise/lower push buttons.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
In Auto Mode: In Auto mode, digital RTCC relay shall automatically control OLTC taps based on power
system voltage and voltage set points. An interlock shall be provided to cut off electrical control
automatically upon recourse being taken to the manual control in emergency.
Master Position: If the digital RTCC relay is in master position, it shall be possible to control the OLTC
units of other parallel operating transformers in the follower mode by operation from the master unit.
Follower Position: If the digital RTCC relay is in Follower position, control of OLTC shall be possible only
from panel where master mode is selected.
Independent Position: In independent position of selector switch, control of OLTC shall be possible only
from the panel where independent mode is selected. Suitable interlock arrangement shall be provided to
avoid unwanted/inconsistent operation of OLTC of the transformer
Raise/Lower control: The remote OLTC scheme offered shall have provision to raise or lower taps for the
complete bank of three 1-phase transformers / 3-Phase Transformers. Individual 1-phase OLTC operation
shall not be possible from the remote-control panel.
Digital RTCC relays shall communicate with SCADA using IEC 61850 through FO port to monitor,
parameterise & control the OLTC. Any software required for this purpose shall be supplied. The supplied
software shall not have restriction in loading on multiple computers for downloading and analyzing the data.
Software shall indicate the current overview of all measured parameters of the connected transformer in real
time.
The digital RTCC Relay shall have multiple selectable set point voltages and it shall be possible to select
these set points from SCADA, with a facility to have the possibility of additional set points command from
SCADA.
Communication between the Digital RTCC relays to execute the commands for parallel operation shall be
implemented using required communication protocol. IEC- 61850 GOOSE messaging between Digital
RTCC relays for OLTC parallel operation is not permitted. Suitable communication hardware shall be
provided to communicate up to distance of 1km between digital RTCC relays. Scope shall also include
communication cables between digital RTCC relays. Cables as required for parallel operation of OLTCs of
all transformers (including existing transformers wherever required) from Digital RTCC relays shall be
considered included in the scope of bidder.
The Digital RTCC relay shall have additional programmable Binary Inputs (minimum 7 Nos.) and Binary
outputs (minimum 7 Nos.) for Employer’s future use. It shall be possible to have additional module for
Binary Input / output as well as Analogue input module depending upon requirement.
The relays shall ensure positive completion of lowering/raising of the OLTC tap, once the command is
issued from the relay. "Step-by-Step" operation shall be ensured so that only one tap change from each tap
changing pulse shall be affected. If the command remains in the "operate" position, lock-out of the
mechanism is to be ensured.
Following minimum indications/alarms shall be provided in Digital RTCC relay either through relay display
panel or through relay LEDs:
However, fiber optic cable, power cable, control cables, as applicable, between IMB (for 3-Ph unit) to
switchyard panel room/control room and power supply (AC & DC) to MB and integration of above said
IEC-61850 compliant equipment with Substation Automation System shall be under the scope of sub-station
contractor.
17.25.0 Constructional features of Cooler Control Cabinet/ Individual Marshalling Box/ Common
Marshalling Box/ Junction Box / Outdoor cubicle and Digital RTCC Panel:
Each transformer unit shall be provided with local OLTC Drive Mechanism Box, cooler control cabinet
/individual marshalling box, Digital RTCC panel (as applicable) and common marshalling (for a bank of
three 1-phase units) shall be provided.
Common marshalling box (for single phase unit) shall be floor mounted and of size, not less than 1600mm
(front) X 650mm (depth) X 1800mm (height). Individual Marshalling Box and Cooler control Box shall be
tank mounted or ground mounted.
The cooler control cabinet / individual marshalling box, common marshalling box, Junction box and all
other outdoor cubicles (except OLTC Drive Mechanism box) shall be made of stainless-steel sheet of
minimum thickness of 1.6 mm. Digital RTCC panel shall be made of CRCA sheet of minimum thickness of
2.5mm and shall be painted suitably as per Annexure –D.
The degree of protection shall be IP: 55 for outdoor and IP: 43 for indoor in accordance with IS: 13947/IEC:
60947.
All doors, removable covers and plates shall be gasketed all around with suitably profiled. All gasketed
surfaces shall be smooth straight and reinforced if necessary, to minimize distortion to make a tight seal. For
Control cubicle / Marshalling Boxes etc. which are outdoor type, all the sealing gaskets shall be of EPDM
rubber or any better approved quality, whereas for all indoor control cabinets / Digital RTCC panel, the
sealing gaskets shall be of neoprene rubber or any better approved quality. The gaskets shall be tested in
accordance with approved quality plan, IS: 1149 and IS: 3400.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Ventilating Louvers, if provided, shall have screen and filters. The screen shall be fine wire mesh of brass.
All the control cabinets shall be provided with suitable lifting arrangement. Thermostat controlled space
heater and cubicle lighting with ON-OFF switch shall be provided in each panel.
The size of Common marshalling box shall not be less than 1600mm (front) X 650mm (depth) X 1800mm
(height). All the separately mounted cabinets and panels shall be free standing floor mounted type and have
domed or sloping roof for outdoor application.
Secondary resistance and magnetising current characteristics of PX class (protection) (as per IEC) CT of
same rating shall be similar. This is applicable for Neutral CT (outdoor) also and shall be reviewed during
detail engineering.
One set of hand tools of reputed make packed in a carry bag/box broadly comprising of double ended
spanners (open jaws, cranked ring, tubular with Tommy bar each of sizes 9mm to 24mm, one set each),
adjustable wrenches (8 &12 inch one set), gasket punches (of different sizes used - one set), pliers (flat nose,
round nose & side cutting one of each type), hammer with handle (one ), files with handle (two), knife with
handle (one), adjustable hacksaw (one), and cold chisel (one), bushing handling and lifting tools with nylon
rope/belt, chain block (2 Nos.) and D-Shackle shall be supplied.
The following fittings & accessories shall be provided with each transformer covered in this specification.
The fittings listed below are not exhaustive and other fittings which are required for satisfactory operation of
the transformer are deemed to be included:
Conservator for main tank with aircell, oil filling hole and cap, isolating valves, drain valve,
magnetic oil level gauge, prismatic oil level gauge and dehydrating silicagel filter breather with
flexible connection pipes to be used during replacement of any silicagel breather.
Conservator for OLTC with drain valve, oil surge Relay, filling hole with cap, prismatic oil level
gauge and dehydrating breather.
Oil preservation equipment, Thermosyphon filter with valves.
Pressure relief devices
Sudden pressure relief relay (for 400kV Transformer only)
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Buchholz relay double float, reed type with isolating valves on both sides, bleeding pipe with pet
cock at the end to collect gases and alarm / trip contacts.
Air release plug
Inspection openings and covers
Bushing of each type with metal parts and gaskets to suit the termination arrangement
Winding & Oil temperature indicators
Cover lifting eyes, transformer lifting lugs, jacking pads, towing holes and core and winding lifting
lugs
Protected type mercury or alcohol in glass thermometer or magnetic or micro-switch type dial type
temperature indicator as applicable
Rating and diagram plates on transformers and auxiliary apparatus
Roller Assembly (as per clause 17.10.1.6)
On load tap changing gear, OLTC DM Box, Off Circuit Tap Changer (OCTC) individual
marshalling box / Cooler control cabinet, Common Marshalling Box, Fibre optic sensor box and
Digital RTCC Panel as applicable
Cooling equipment
Bushing current transformers, Neutral CT
Oil flow indicators (if applicable)
Terminal marking plates
Valves schedule plate
Bottom oil sampling valve, Drain valves, Filter valves at top and bottom with threaded male
adaptors, Shut off valves on the pipe connection between radiator bank and Transformer tank, Shut
off valves on both sides of Buchholz relay, Sampling gas collectors for Buchholz relay at accessible
height, Valves for Radiators, Valve for vacuum application, Valve for on line DGA, valves for
Drying out system, Flow sensitive conservator Isolation valve, Valve for UHF sensors, valves for
NIFPS system etc.
Ladder to climb up to the Transformer tank cover with suitable locking arrangement to prevent
climbing during charged condition
Suitable Platform for safe access of Flow sensitive non-return valve and buchholz relay shall be
provided, in case these are not accessible from transformer top.
Haulage lugs
Neutral bus connection arrangement.
Brass/tinned copper grounding bar supported from the tank by using porcelain insulator and flexible
conductor for earthing of neutral, HV & IV terminals.
On line insulating oil drying system.
Online Dissolved Gas (Multi-gas) and Moisture Measuring Equipment
On line dissolved Hydrogen and Moisture Measuring Equipment
Fibre optic sensor-based temperature measuring system.
Nitrogen Injection Type Fire Prevention & Extinguishing System.
Automatic Mulsifire System (or High Velocity Water Spray System)
Managed Ethernet switch, LIU patch cords etc. shall be provided in CMB/MB. All IEC 61850
compliant signals from various monitoring equipment/accessories shall be wired upto the Ethernet
switch.
The Contractor shall carry out a comprehensive inspection and testing programme during manufacture of
the equipment. The inspection envisaged by the Purchaser is given below. This is however not intended to
form a comprehensive programme as it is Contractor's responsibility to draw up and carry out such a
programme in the form of detailed quality plan duly approved by Purchaser for necessary implementation.
All accessories and components of transformer shall be purchased from approved soured of purchaser. All
process tests, critical raw material tests and witness / inspection of these testing shall be carried out as per
approved manufacturing quality plan (MQP) by purchaser.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
The manufacturer shall be fully equipped to perform all the required tests as specified. Bidder shall confirm
the capabilities of the proposed manufacturing plant in this regard when submitting the bid. Any limitations
shall be clearly stated in.
The contractor shall bear all additional costs related to tests which are not possible to carry out at his own
works.
The contractor shall carry out type & routine tests as per “Annexure-H & Annexure-I”. All tests shall be
done in line with IEC: 60076 and the test procedures as mentioned in “Annexure-H”. Complete test report
shall be submitted to purchaser after proper scrutiny and signing on each page by the test engineer of the
contractor.
1) Bushing (Type Test as per IEC:60137 including Snap back & Seismic test for 400 kV and
above voltage class bushing)
2) OLTC (Test as per IEC:60214 and IP-55 test on driving mechanism box)
3) Buchholz relay
4) OTI & WTI
5) Pressure Relief device Test (including IP 55 test in terminal box)
6) Sudden Pressure Relay Test (including IP 55 test in terminal box)
7) Magnetic Oil Level gauge & Terminal Box for IP-55 degree of protection.
8) Air Cell (Flexible air separator) - Oil side coating, Air side under Coating, Air side outer
coating and coated fabric as per IS: 3400/ BS: 903/ IS: 7016
9) Marshalling & common marshalling box and other outdoor cubicle (IP-55 test)
10)RTCC (IP-43)
Further, drop-out setting shall be 1g and threshold setting shall be in the range of 5g to 10g.
Check for proper provision for bracing to arrest the movement of core and winding assembly inside the
tank.
Gas tightness test to confirm tightness and record of dew point of gas inside the tank. Derivation of leakage
rate and ensure the adequate reserve gas capacity.
Check and record condition of each package, visible parts of the transformer etc. for any damage. Check and
record the gas pressure in the transformer tank as well as in the gas cylinder. Visual check for wedging of
core and coils before filling up with oil and also check conditions of core and winding in general.
Check and record reading of impact recorder at receipt and verify the allowable limits as per manufacturer's
recommendations.
Check for the adequate protection on the electric circuit supplying the accessories.
Check resistance of all windings on all steps of the tap changer. Insulation resistance measurement for the
following:
i) Control wiring
ii) Cooling system motor and control
iii) Main windings
iv) Tap changer motor and control
DGA of oil just before commissioning and after 24 hours energisation at site.
Gradually put the transformer on load, check and measure increase in temperature in relation to the load and
check the operation with respect to temperature rise and noise level etc.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Nitrogen Injection Type Fire Protection System (NIFPS) shall be designed to prevent explosion of
transformer tank and the fire during internal faults resulting from arc and also to extinguish the external oil
fires on transformer/ reactor due to tank explosion and/or external failures like bushing fires, OLTC fires
and fire from surrounding equipments, etc.
The system shall work on the principle of Drain & stir. On activation, it shall drain a predetermined quantity
of oil from the tank top through drain valve to reduce the tank pressure, isolate conservator tank oil and
inject nitrogen gas at high pressure from the bottom side of the tank through inlet valves to create stirring
action and reduce the temperature of oil below flash point to extinguish the fire. On operation, the quantity
of oil removed from the tank shall be such that adequate amount of oil shall remain to cover active part (i.e.
core coil assembly).
Electrical isolation of transformer shall be an essential pre-condition for activating the system.
i) Open the quick opening drain valve to drain the top layer oil
ii) Shut off the conservator isolation valve to prevent flow of oil from the Conservator tank to the main tank
iii) Open the Nitrogen regulator valve to inject Nitrogen into the transformer tank to create stirring of oil.
There shall be interlock to prevent activation of the system if the transformer is not electrically isolated.
There shall also be provision for isolating the system during maintenance and/or testing of the transformer.
The Nitrogen regulator valve shall be designed in such a way that the Nitrogen shall not enter the
transformer tank even in case of passing/ leakage of valve.
Owner shall provide two distinct station auxiliary DC feeders for control purposes. The system shall work
on station DC supply with voltage variation defined in Data Sheet .The control box of fire protection system
shall have facility to receive these feeders for auto changeover of supply. It shall be the contractor’s
responsibility to further distribute power to the required locations. In case auxiliary DC power supply
requirement is different than station auxiliary DC supply, then all necessary DC-DC converters shall be
provided by the Contractor.
Following minimum indications and alarms shall be provided in the local cubicle as well as in the control
box:-
Nitrogen cylinder pressure indication - manometer with sufficient number of
adjustable NO contacts
Nitrogen cylinder pressure low
Fire in Transformer/ Reactor
Oil drain started
Conservator oil isolation valve closed
Nitrogen injection started
DC supply fail
Oil drain valve closed
Gas inlet valve closed
The scope of supply shall include the following items and any other items required for safe and trouble free
operation of the system.
i) Fire extinguishing cubicle with base frame and containing at least the following:
Nitrogen gas cylinder of sufficient capacity with pressure regulator and
manometer with sufficient number of adjustable NO contacts.
Oil Drain Assembly including oil drain pipe extension of suitable size for
connecting pipes to oil pit
Mechanical release device for oil drain and nitrogen release
Limit switches for monitoring of the systems
Panel lighting
Flanges on top of the panel for connecting oil drain and nitrogen injection pipes
for transformer
Back up pressure switch to operate nitrogen gas valve
Pressure indicators for Nitrogen pressure of the cylinder and actual injection
through Nitrogen regulator
ii) Control box to be installed in the control room of the station for monitoring
system operation, automatic control and remote operation, with alarms,
indications, switches, push buttons, audio signal, suitable for tripping and
signalling.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
This storage tank shall be placed in the pit made of brick walls with PCC (1:2:4) flooring with suitable cover
plates to avoid ingress of rain water. The design of tank and pit shall be finalized during detailed
engineering. All underground oil and gas storage tanks design shall be certified by petroleum and
explosive safety organisation, Nagpur, India.
(i). Designed for very slow removal of moisture that may enter the oil system or generated
during cellulose decomposition. Oil flow to the equipment shall be controlled through
pump of suitable capacity.
(ii). The equipment shall display the moisture content in oil (PPM) of the inlet and outlet oil
from the drying system. The moisture in inlet & outlet oil (PPM) shall have to be
displayed in Local SCADA besides local HMI.
(iii). Minimum capacity of moisture extraction shall be 10 Litres before replacement of
cartridge.
Calculation to prove the adequacy of sizing of the on line insulating oil drying system
along with make and model shall be submitted for approval of purchaser during detail
engineering.
The equipment shall be supplied with Operation Manual (2 set for every unit), Software (if any), and Compact
disc giving operation procedures of Maintenance Manual & Trouble shooting instructions.
The Monitor shall be a microprocessor based Intelligent Electronic Device (IED), designed to continuously
detect and measure dissolved Hydrogen and Water content, even at very low concentrations, in Transformer
Oil. It should be easy to install and it should be possible to retrofit it on an energized transformer, without
shutting down the transformer.
The monitor shall be designed for permanent outdoor use in high voltage sub-station environments, for
ambient temperatures of 0 deg C to 55 deg C and oil temperatures of 5 deg C to 105 deg C.
The monitor shall be suitable to detect and measure dissolved Hydrogen in ppm, without significant
interference from other fault and atmospheric gases. The monitor shall also be suitable to detect Water
Content measured in ppm.
The Hydrogen sensors shall have long lifetime in oil. The sensors shall be able to withstand pressure from
vacuum to 10 psi.
Following LEDs for local display on control unit, and suitable contacts & analog signal shall be provided
for wiring to remote location:
The Breather shall be equipped with test button which should allow to carry out a self-test and to check the
functions like relay circuits, heating or the signal transmission in the control room, etc. at any time.
Control unit shall be equipped with a USB / RS 485 port for downloading the operational data logged by the
unit. All necessary software required for downloading and analysing the logger data shall also be provided
by the supplier. Supply of Laptop/PC for above software is not envisaged.
The moisture and temperature measurement system (sensor) installed should be modular making it easy to
replace the same if at all the same is necessary during the service of breather.
The equipment shall operate at input supply of 230V AC, 50 Hz. Any converter if required shall be supplied
with the equipment.
Degree of Protection shall be at least IP55 for which type Test report shall be submitted. Necessary
protective devices shall be provided in order to protect the equipment against over voltages & high
frequency interference.
The control unit shall be equipped with suitable heater to prevent moisture condensation.
The size of Condition controlled maintenance free dehydrating breather shall be decided based on the
volume of transformer oil during detailed engineering.
For OLTC conservator, conventional breather shall be supplied as per technical specification.
Condition Controlled Maintenance Free Type Breather of alternate proven technology shall also be
acceptable.
17.43.0 Automatic Mulsifire System (or High Velocity Water Spray System)
17.43.1.0 Description:
This system is widely used for fire fighting of outdoor transformers. Spray type fire protection essentially
consists of a network of projectors and an array of heat detectors used to sense high temperature near the
transformer / reactor to be protected. If the temperature exceeds the set value, the automatic mulsifire
system sprays water at high pressure through a Deluge valve from the pipe network laid for this system.
Fire detectors located at various strategic points are on the surface of the transformer to control fire on any
burning oil spilled over.
a) Main Hydrant
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
This is used to carry the water to various parts of the switchyard or transformer substation and forms the
backbone of the system. Sturdy corrosion-free pipes and valves are used for this purpose. The materials
should be able to withstand fire for a reasonable duration.
b) Fire Detector
Fire detectors can either be thermocouples or specially designed bulbs which burst when they experience a
high temperature and release any valves or checking device to start the water supply.
d) Pumps
Pumps are provided to fill the hydrants initially and to maintain its pressure. Pumps driven by electrical
motors are a standard provision; however, the standby pumps should preferably be diesel engine driven. It
is recommended that the main and standby pumps in a pump house be segregated.
As per IEEMA specification, from safety considerations, the following electrical clearances are
recommended between the mulsifier system pipe work and live parts of the transformer to be protected.
420 kV bushing 3500 mm
245 kV bushing 2150 mm
145 kV bushing 1300 mm
52 kV bushing 630 mm
36 kV bushing 320 mm
Each Deluge valve shall be provided with a local panel from which will enable manual
electrical operation of the valve.
In addition to this, each valve shall be provided with local operation latch.
Test valves shall simulate the operation of Deluge valves and shall be of quick opening
type.
Annexure – A 1.0
Technical Particulars / Parameters of Transformers
(500MVA (3 phase) and 167 MVA (1 phase) 400/220/33 kV, Auto Transformer)
Clause Description Unit Technical Parameters
No.
1.1 Rated Capacity
HV MVA 500 167
IV MVA 500 167
LV (Tertiary) : MVA 1/3 RD of rated capacity of HV
Active + Reactive loading winding
1.2 Voltage ratio (Line to Line) 400/220/33
1.3 Single / Three Phase Design 3 (THREE) 1 (SINGLE)
1.4 Applicable Standard IEC 60076
1.5 Frequency Hz 50 50
1.6 Cooling & Percentage Rating at different ONAN/ONAF/(OFAF or
cooling ODAF) : 60% / 80%/100%
OR
ONAN/ONAF1/ONAF2: 60% /
80%/100%
OR
OFAF (with 5 x 25% unit cooler
if specified in Section Project)
1.7 Type of Transformer Constant Ohmic impedance type
(Refer note 1)
1.8 Impedance at 75 Deg C
HV-IV
Max. Voltage tap % 10.3
Principal tap % 12.5
Min. Voltage tap % 15.4
HV-LV
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
HV kVp 1300
IV kVp 950
LV kVp 250
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Neutral kVp 95
iii) Switching Impulse withstand Voltage
HV kVp 1050
iv) One Minute Power Frequency withstand
Voltage
HV kVrms 570
IV kVrms 395
LV kVrms 95
Neutral kVrms 38
v) Neutral Grounding Solidly grounded
vi) Insulation
HV Graded
IV Graded
LV Uniform
vii) Tertiary Connection Ungrounded Delta
viii) Tan delta of winding % < 0.5
1.15 Vector Group (3 –ph) YNaOd11
(unless specified differently elsewhere)
1.16 Tap Changer OLTC
i) Rated voltage
HV kV 420
IV kV 245
LV kV 52
Neutral kV 36
ii) Rated current (Min.)
HV A 1250
IV A 2000
LV A 3150
Neutral A 2000
iii) Lightning Impulse withstand Voltage
HV kVp 1425
IV kVp 1050
LV kVp 275
HV kVp 1050
IV kVp 850
v) One Minute Power Frequency withstand
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Voltage
HV kVrms 695
IV kVrms 505
LV kVrms 105
Neutral kVrms 77
vi) Minimum total creepage distances
HV mm 13020
IV mm 7595
LV mm 1300
Neutral mm 1116
vii) Tan delta of bushings
HV % < 0.4
IV % < 0.4
LV % < 0.4
Neutral
viii) Max Partial discharge level at Um
HV pC 10
IV pC 10
LV pC 10
Neutral -
1.18 Max Partial discharge level at 1.58 * Ur / pC 100
√3
1.19 Max Noise level at rated voltage and at dB 80
principal tap at no load and all cooling
active
1.20 Maximum Permissible Losses of 500 MVA 167MVA
Transformers
i) Max. No Load Loss at rated voltage and kW 90 45
frequency
75O C
Notes:
1. For parallel operation with existing transformer, the impedance, OLTC connection & range
and the winding configuration (if necessary) is to be matched.
2. No external or internal Transformers / Reactors are to be used to achieve the specified
HV/IV, HV/LV and IV/LV impedances.
3. Tan delta of Winding & Bushing shall be measured at ambient temperature. No temperature
correction factor shall be applied.
4. The criteria for Transformer losses shall be “Copper Loss (Load Loss) > Iron Loss (No
Load Loss) > Cooler Loss (Auxiliary Loss)”.
ANNEXURE – A 2.0
HV kVrms 395
IV kVrms 275
LV kVrms 95
Neutral kVrms 38
v) Neutral Grounding Solidly grounded
vi) Insulation
HV GRADED
IV GRADED
LV UNIFORM
vii) Tertiary Connection DELTA
viii) Tan delta of winding % <0.5%
1.14 Vector Group (3 –ph) YNa0d11
(unless specified differently
elsewhere)
1.15 Tap Changer OLTC
i) Tap Range & No. of steps –5% to +10% of HV variation in
the step of 1.25%, 12 Steps
ii) Location of Tap changer HV SIDE
iii) Design Constant flux voltage variation
type as per cl. 6.2 of IEC 60076
part-I
iv) Tap control Full capacity - on load tap changer
suitable for group / independent,
remote /local electrical and local
manual operation and bidirectional
power flow
1.16 Bushings
i) Rated voltage
HV kV 245
IV kV 145
LV kV 52
Neutral kV 36
ii) Rated current (Min.)
HV A 800
IV A 1250
LV A 800
Neutral A 1000
iii) Lightning Impulse withstand Voltage
HV kVp 1050
IV kVp 650
LV kVp 275
Neutral kVp 170
iv) Switching Impulse withstand
Voltage
HV kVp 850
V) One Minute Power Frequency
withstand
Voltage
HV kVrms 505
IV kVrms 305
LV kVrms 105
Neutral kVrms 77
Notes:
1. For parallel operation with existing transformer, the impedance, OLTC connection & range
and the winding configuration (if necessary) is to be matched.
2. No external or internal Transformers / Reactors are to be used to achieve the specified
HV/IV, HV/LV and IV/LV impedances.
3. Tan delta of Winding & Bushing shall be measured at ambient temperature. No temperature
correction factor shall be applied.
4. The criteria for Transformer losses shall be “Copper Loss (Load Loss) > Iron Loss (No
Load Loss) > Cooler Loss (Auxiliary Loss)”.
ANNEXURE – A 3.0
Technical Particulars/Parameters
(132/33 KV, 50 MVA 3-Phase Transformer)
Technical
Sl. No. Description Unit
Parameters
Rated Capacity
1.1 HV MVA 50
LV MVA 50
Rated Voltage ratio (HV/LV) (Line to
1.2 kV 132/33
Line)
1.3 Single / Three Phase Design Three
1.4 Applicable Standard IEC 60076
1.5 Frequency Hz 50
1.6 Cooling ONAN/ONAF
1.7 Rating at different cooling % 60/100
Constant Ohmic
1.8 Type of Transformer impedance type
(Refer Note1)
1.9 HV-LV Impedance at 75 Deg C at
i) Max. Voltage tap % 10.3
ii) Principal tap % 12.5
iii) Min. Voltage tap % 15.4
1.10 Service OUTDOOR
1.11 Duty CONTINUOUS
1.12 Overload Capacity IEC 60076-7
Temperature rise over 50 deg C
1.13
Ambient Temp
i) Top oil measured by thermometer Deg C 50
Average winding measured by resistance
ii) Deg C 55
method
1.14 Windings
System Fault level
i) HV kA 31.5
LV kA 25
Lightning Impulse withstand Voltage
HV kVp 650
ii) LV kVp 170
HV Neutral kVp 95
LV Neutral kVp 170
Switching Impulse withstand Voltage
iii)
HV kVp 460
iv) One Minute Power Frequency withstand
Voltage
HV kVrms 275
LV kVrms 70
HV Neutral kVrms 38
LV Neutral kVrms 70
v) Neutral Solidly grounded
Insulation
vi) HV GRADED
LV UNIFORM
Tan delta of winding at ambient
vii) % <0.5%
Temperature
Vector Group (3Ph-Bank)
1.15 YNyn0
(unless specified differently elsewhere)
1.16 Tap Changer OLTC
–15% to +5% in the
i Tap range& No. of steps step of 1.25% for HV
variation, 16 steps
Constant flux voltage
ii Design variation type as per cl.
6.2 of IEC 60076 part-I
Full capacity on load
tap changer suitable for
group/independent,
iii) Tap control remote /local electrical
and local manual
operation and bi-
directional power flow.
1.17 Bushings
Rated voltage
HV kV 145
i)
LV kV 36
Neutral(HV & LV) kV 36
Rated current (Min.)
HV A 800
ii)
LV A 1000
Neutral(HV & LV) A 1000
Lightning Impulse withstand Voltage
HV kVp 650
iii)
LV kVp 170
Neutral kVp 170
One Minute Power Frequency withstand
Voltage
iv) HV kVrms 305
LV kVrms 77
Neutral HV & LV) kVrms 77
Minimum total creepage distances
HV mm 4495
v)
LV mm 1116
Neutral(HV & LV) mm 1116
Notes:
1. For parallel operation with existing transformer, percentage impedance, OLTC connection &
range, vector group and the winding configuration (if necessary) is to be matched.
2. No external or internal Transformers / Reactors are to be used to achieve the specified HV/IV,
HV/LV and IV/LV impedances.
3. Tan delta of Winding & Bushing shall be measured at ambient temperature. No temperature
correction factor shall be applied.
4. The criteria for Transformer losses shall be “Copper Loss (Load Loss) > Iron Loss (No Load
Loss) > Cooler Loss (Auxiliary Loss)”.
ANNEXURE – A 4.0
Technical Particulars/Parameters
(220/33 KV, 100 MVA 3-Phase Transformer)
Technical
Sl. No. Description Unit
Parameters
Rated Capacity
1.1 HV MVA 100
LV MVA 100
Rated Voltage ratio (HV/LV) (Line to
1.2 kV 220/33
Line)
1.3 Single / Three Phase Design Three
1.4 Applicable Standard IEC 60076
1.5 Frequency Hz 50
1.6 Cooling ONAN/ONAF/OFAF
1.7 Rating at different cooling % 60/80/100
Constant Ohmic
1.8 Type of Transformer impedance type
(Refer Note1)
1.9 HV-LV Impedance at 75 Deg C at
i) Max. Voltage tap % 10.3
ii) Principal tap % 12.5
iii) Min. Voltage tap % 15.4
1.10 Service OUTDOOR
1.11 Duty CONTINUOUS
1.12 Overload Capacity IEC 60076-7
Temperature rise over 50 deg C
1.13
Ambient Temp
i) Top oil measured by thermometer Deg C 50
Average winding measured by resistance
ii) Deg C 55
method
1.14 Windings
System Fault level
i) HV kA 50
LV kA 31.5
Lightning Impulse withstand Voltage
HV kVp 950
ii) LV kVp 170
HV Neutral kVp 95
LV Neutral kVp 170
Switching Impulse withstand Voltage
iii)
HV kVp 750
iv) One Minute Power Frequency withstand
Voltage
HV kVrms 395
LV kVrms 70
HV Neutral kVrms 38
LV Neutral kVrms 70
v) Neutral Solidly grounded
Insulation
vi) HV GRADED
LV UNIFORM
Tan delta of winding at ambient
vii) % <0.5%
Temperature
Vector Group (3Ph-Bank)
1.15 YNyn0
(unless specified differently elsewhere)
1.16 Tap Changer OLTC
–15% to +5% in the
i Tap range& No. of steps step of 1.25% for HV
variation, 16 steps
Constant flux voltage
ii Design variation type as per cl.
6.2 of IEC 60076 part-I
Full capacity on load
tap changer suitable for
group/independent,
iii) Tap control remote /local electrical
and local manual
operation and bi-
directional power flow.
1.17 Bushings
Rated voltage
HV kV 245
i)
LV kV 36
Neutral(HV & LV) kV 36
Rated current (Min.)
HV A 800
ii)
LV A 1000
Neutral(HV & LV) A 1000
Lightning Impulse withstand Voltage
HV kVp 1050
iii)
LV kVp 170
Neutral kVp 170
One Minute Power Frequency withstand
Voltage
iv) HV kVrms 650
LV kVrms 77
Neutral (HV & LV) kVrms 77
v) Minimum total creepage distances
HV mm 7595
LV mm 1116
Neutral(HV & LV) mm 1116
Tan delta of bushing at ambient
vi) Temperature
HV % <0.4%
Max Partial discharge level at Um
vii)
HV pC 10
1.18 Max Partial discharge level at 1.5Um/√3 pC 100
Max Noise level at rated voltage and at
1.19 principal tap on full load and all cooling dB 75
active
Clearance of air, mm
1.20 a) phase to phase, HV / LV mm 1430 / 350
b) phase to earth, HV / LV mm 1270 / 320
Maximum current density Amp/
1.21 250
sq. cm
Maximum flux density in any part of the
1.22 core and yoke at rated MVA, System Tesla 1.9
voltage and rated frequency
No-Load Loss in KW shall not exceed the
1.23 value given in this Data Sheet. & No KW 43
positive tolerance is allowed
Load Loss in KW at 750C shall not exceed
1.24 the value given in this Data Sheet. & No KW 245
positive tolerance is allowed
1.25 Auxiliary Loss in KW KW 5
Notes:
1. For parallel operation with existing transformer, percentage impedance, OLTC connection &
range, vector group and the winding configuration (if necessary) is to be matched.
2. No external or internal Transformers / Reactors are to be used to achieve the specified HV/IV,
HV/LV and IV/LV impedances.
3. Tan delta of Winding & Bushing shall be measured at ambient temperature. No temperature
correction factor shall be applied.
4. The criteria for Transformer losses shall be “Copper Loss (Load Loss) > Iron Loss (No Load
Loss) > Cooler Loss (Auxiliary Loss)”.
Annexure–B
Design Review Document
Annexure-C
UNDERTAKING
supply of:
to AEGCL.
In accordance with the terms of the said tender, we hereby undertake that we shall use imported prime CRGO steel
lamination and not the second grade CRGO steel lamination for the manufacturing of the transformers against this
Tender. Further, we shall produce the following documents at the time of inspection of transformers:
a) Invoice of supplier
b) Mill’s Test Certificate issued by Customs
c) Packing list
d) Bill of lading
e) Bill of entry Certificate issued by Customs.
Annexure – D
Painting Procedure
non-
corrosive
Paint
(two
& IS:6005
coated minimum white for
coats)
100µm interior
Control cabinet / Marshalling Box - No painting is required.
Note: (*) Indicates Sa 2 ½ as per Swedish Standard SIS 055900 of ISO 8501 Part-1.
Annexure – E
A Function
B Refining/Stability
C Performance
E Oil used (inhibited) for first filling, testing and impregnation of active parts at
manufacturer's works shall meet parameters as mentioned below:
F Each lot of the oil shall be tested prior to filling in main tank at site for the
following:
G After filtration & settling and prior to energisation at site oil shall be tested for
following:
(BDV)
* Separate oil sample shall be taken and test results shall be submitted within 45 days
after commissioning for approval of AEGCL.
Annexure–F
1.1. Transformer with Isolator switching arrangement: Employer intends to replace any of
the Transformer unit by the spare Transformer unit using isolator switching arrangement
so as to avoid physical shifting the Transformer.
Connection of spare unit of Transformer with other units shall be made by isolator
switching arrangement. Neutral formation for spare unit of Transformer shall be done by
manual connection. The spare Transformer unit shall be completely erected and
commissioned similar to the other Transformer units. The contractor shall carry out all
pre-commissioning tests on the spare Transformer similar to the unit kept in service.
For this purpose if specified in BPS, HV and Neutral Connections of spare unit shall be
extended upto the other unit(s) by forming auxiliary buses connection through
flexible/rigid conductor. All associated materials like Bus post insulators, Aluminium
tube, conductors, clamps & connectors, insulator strings, hardware, cables, support
structures, required for the above-mentioned arrangement shall be provided by the
contractor. However, the detail configuration and hardware shall be finalised during
detailed engineering and shall be subject to Employer’s approval.
Any special maintenance procedure required shall be clearly brought out in the instruction
manual.
1.2. Transformer without isolator switching arrangement: Employer intends to keep the
spare Transformer unit without isolator switching arrangement due to space limitation. In
case of failure of any of the running unit, this spare Transformer shall be physically
The spare Transformer shall be placed on the elevated foundation block to facilitate
quick movement. The Transformer unit may be required to be stored for long duration.
The spare Transformer unit shall be completely erected and commissioned similar to
the other Transformer units. However, erection of separate cooler bank is not envisaged.
In case conservator is cooler bank mounted, suitable arrangement for mounting of
conservator on tank top cover shall be provided. The contractor shall carry out all pre-
commissioning tests on the spare Transformer similar to the unit kept in service.
All other items shall be suitably packed in reusable boxes. Arrangement shall be made to
minimize moisture ingress inside the boxes. All pipes and radiators shall be provided with
blanking plates during long duration storage to prevent entry of foreign material/ water.
Annexure- G
1.0 Bushing Current Transformer and Neutral Current Transformer Parameters (On each phase) for
3-ph, 500MVA 400/220/33 kV and 1-ph, 167 MVA (400/√3)/ (200/√3)/33 Transformers:
CORE 1 25 mA 25 mA
25 mA
CORE 2 - -
25 mA
CORE 3
Refer to note 1
Page 487 of 954
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
2.0 Technical Parameters of Bushing Current Transformers and Neutral Current Transformers for 160MVA
220/132/33 kV 3-Ph Transformers:
Description Bushing Current Transformer Parameters (Transformer)
HV IV Neutral
Side Side Side
(a) Ratio
CORE 2 - - 100 mA
NOTE:
3 Technical Parameters of Bushing Current Transformer and Neutral Current Transformer for 50 MVA
132/33 kV 3-Ph Transformers:
HV HV Neutral LV LV Neutral
Side Side Side Side
(a) Ratio
(d) Application
NOTE:
4.0 Technical Parameters of Bushing Current Transformer and Neutral Current Transformer for 100
MVA 220/33 kV 3-Ph Transformers:
HV HV Neutral LV LV Neutral
(a) Ratio
(d) Application
NOTE:
(i) Parameters of WTI CT for each winding shall be provided by the contractor.
(ii) For estimation of spares, one set of CTs shall mean one CT of each type used in transformer.
(iii) The CT used for REF protection must have the identical parameters in order to limit the
circulating current under normal condition for stability of protection.
Annexure- H
Test Procedures
General
Tests shall be carried out as per following procedure. However, IEC 60076 shall be followed in general for
other tests. Manufacturer shall offer the transformer unit for type testing with all major fittings including
radiator bank, Marshalling Box, Common Marshalling Box RTCC (as applicable) assembled.
After assembly each core shall be tested for 1 minute at 2000 Volts between all yoke clamps, side plates and
structural steel work (core to frame, frame to tank & core to tank).
The insulation of core to tank, core to yoke clamp (frame) and yoke clamp (frame) to tank shall be able to
withstand a voltage of 2 kV (DC) for 1 minute. Insulation resistance shall be minimum 1 GΩ for all cases
mentioned above.
After the transformer has been under liquid without excitation for at least 3 hr, the average liquid
temperature shall be determined and the temperature of the winding shall be deemed to be the same as the
average liquid temperature. The average liquid temperature is taken as the mean of the top and bottom
liquid temperatures. Measurement of all the windings including compensating (in case terminal is
available at outside) at normal and extreme taps.
In measuring the cold resistance for the purpose of temperature-rise determination, special efforts shall be
made to determine the average winding temperature accurately. Thus, the difference in temperature between
the top and bottom liquid shall not exceed 5 K. To obtain this result more rapidly, the liquid may be
circulated by a pump.
The short-circuit impedance and load loss for a pair of windings shall be measured at rated current &
frequency with voltage applied to the terminals of one winding, with the terminals of the other winding
short-circuited, and with possible other windings open- circuited. The difference in temperature between the
top and bottom liquid shall not exceed 5 K. To obtain this result more rapidly, the liquid may be circulated
by a pump. Loss measurement for all combinations (HV-IV, HV-LV, IV-LV and at Normal and extreme
taps).
5. Short term heat run test (Not Applicable for unit on which temperature rise test is performed)
In addition to the type test for temperature rise conducted on one unit, each cooling combination shall
routinely be subjected to a short term heat run test to confirm the
performance of the cooling system and the absence of manufacturing defect such as major oil flow leaks that
may bypass the windings or core.
For ODAF or OFAF cooling, the short term heat run test shall be done with the minimum number of pumps
for full load operation in order to shorten the temperature build up. Each short term heat run test is
nevertheless expected to take about 3 hours.
For ODAF or OFAF cooled transformers an appropriate cross check shall be performed to prove the
effective oil flow through the windings. For this purpose the effect on the temperature decay by switching
the pumps off/ on at the end of the heat run should demonstrate the effectiveness of the additional oil flow.
Refer to SC 12, 1984 CIGRE 1984 SC12-13 paper by Dam, Felber, Preiniger et al.
Short term heat run test may be carried out with the following sequence:
Heat run test with pumps running but oil not through coolers.
Raise temperature to 5 deg less than the value measured during temperature rise test.
Stop power input and pumps for 6 minutes and observe cooling down trend
Restart pumps and observe increased cooling trend due to forced oil flow
This test is applicable for the Transformer without Pump also (ONAN or ONAF rating). For such type of
transformer test may be carried out with the following sequence:
Arrangement shall be required with pump of suitable capacity (considering the oil velocity) without cooler
bank. Raise the oil temperature 20-25 deg C above ambient. Stop power input and pumps for 6 minutes and
observe cooling down trend. Restart pumps and observe increased cooling trend due to forced oil flow.
Gas chromatographic analysis on oil shall also be conducted before, during and after this test and the values
shall be recorded in the test report. The sampling shall be in accordance with IEC 60567.
The temperature rise test shall be conducted at a tap for the worst combination of loading (3-Winding Loss)
for the Top oil of the transformer.
Oil sample shall be drawn before and after heat run test and shall be tested for dissolved gas analysis. Oil
sampling to be done 2 hours prior to commencement of temperature rise test. Keep the pumps running for 2
hours before and after the heat run test. Take oil samples during this period. For ONAN/ONAF cooled
transformers, sample shall not be taken earlier than 2 hours after shut down. The acceptance norms with
reference to various gas generation rates shall be as per IEC 61181.
This test shall be generally carried out in accordance with IEC 60076-2
For each cooling combination with cooler bank, tests shall be done on the maximum current tap for
a minimum of 12 hours for ONAN/ONAF and 24 hours for ODAF or OFAF or ONAF2 with
saturated temperature for at least 4 hours while the appropriate power and current for core and load
losses are supplied.
The total testing time, including ONAN heating up period, steady period and winding resistance
measurements is expected to be about 48 hours.
DGA tests shall be performed before and after heat run test and DGA results shall generally
conform to IEC/IEEE/CIGRE guidelines.
Full details of the test arrangements, procedures and conditions shall be furnished with the test certificates
and shall include at least the following.
iii. General:
• time
• Voltage between phases
Notes: The probes may be left in position provided the reliability and integrity of unit will
not be jeopardized during its long-life expectancy.
Record the ‘cold’ resistance of each winding and the simultaneous top oil and
ambient air temperatures, together with the time required for the effect to
disappear.
Record the thermal time constant of the winding.
Log the half-hourly readings of the quantities as for the top oil temperature rise
test.
Provide a table of readings, after shut-down of power, giving the following
information ;
a) Time after shut- down:
b) Time increment:
c) Winding resistance: At least 20 minutes reading
d) Resistance increment:
Provide a record of all calculations, corrections and curves leading to the determination
of the winding temperatures at the instant of shut-down of power.
Record any action taken to remedy instability of the oil surge device during initiation
of the oil circulating pumps.
Temperature measurements as per special probes or sensors (fibre optic) placed at various
locations shall also be recorded.
7. Dielectric Tests
Following Test shall be performed in the sequence given below as per IEC 60076-3:2013
clause 7.2.3 shall be followed:
a) Lightning impulse tests (LIC, LIN)
b) Switching impulse (SI)
c) Applied voltage test (AV)
d) Line terminal AC withstand test (LTAC)
e) Induced voltage test with partial discharge measurement (IVPD)
Following tests shall be carried out with applying 20% to 80% of rated Impulse & Switching impulse
(upto 60% for IV, Sr. No. 7 & 8 of below table) voltage. Finally, measured value shall be
extrapolated for 100% rated voltage.
Table for Transfer surge (Impulse) at Max, Nor. and Min. Voltage Tap
Similar tests to be conducted for switching surge transformer at Max, Nor. and Min. Voltage
Tap.
Where 1.1 : HV Terminal
2.1 : IV Terminal
3.1 & 3.2 : LV or Tertiary Terminal
Acceptance criteria
Transfer surge at Tertiary should not exceed 250kVp at any conditions for 400kV Voltage class
Transformer. For other transformer it shall be below the impulse level of LV winding.
9. Chopped wave & full wave lightning impulse test for the line terminals (LIC & LI)
and Switching impulse test
Chopped wave lightning impulse and switching impulse test shall be performed at normal and
extreme taps on Unit-1, Unit-2 and Unit-3 respectively for 1-Ph unit, otherwise R ph, Y Ph and B Ph
respectively for 3-Ph unit. All the parameters as per IEC shall be mentioned in the report.
10. Measurement of power taken by fans and oil pumps (100 % cooler bank)
Losses of each fan and pumps including spare shall be measured at rated voltage and frequency. Fans
and Pumps shall be mounted with cooler bank as per approved drawing during measurement. Serial
No, applied voltage, measured current, frequency and make shall be furnished in the test report.
All tanks and oil filled compartments shall be completely filled with air or oil of a viscosity not
greater than that of insulating oil conforming to IEC 60296 at the ambient temperature and subjected
to a pressure equal to normal head of oil plus 35 kN/sq.m (5 psi) measured at the base of the tank.
This pressure shall be maintained for a period of not less than 12 hours for oil and 1 hour for air
during which no leakage shall occur.
All transformer tanks shall be subjected to the specified vacuum. The tank designed for full vacuum
shall be tested at an internal pressure of 3.33 KN/Sq. absolute (25 torr) for one hour. The permanent
deflection of flat plate after the vacuum has been released shall not exceed the values specified
below:
-------------------------------------------------------------------------------------
Horizontal Length Permanent deflection of flat plate (in mm)
(in mm)
-------------------------------------------------------------------------------------
Up to and including 750 5.0
All transformer tanks, its radiator, conservator and other fittings together or separately shall be
subjected to a pressure corresponding to twice the normal head of oil or normal oil head pressure
plus 35 KN/sq.m whichever is lower, measured at the base of the tank and maintained for one hour.
The permanent deflection of flat plates after the excess pressure has been released shall not exceed the
figure specified above for vacuum test.
12. Dynamic short circuit withstand test shall be carried out as per IEC 60076-5. Dynamic short
circuit test shall be carried out in HV-IV combination at nominal & extreme tap positions. For LV
winding, dynamic short circuit shall be carried out either on HV-LV or IV-LV combination,
whichever draws higher short circuit current as per calculation. Type tests shall be carried out before
short circuit test. Following shall also be conducted before and after Short Circuit test:
Detail test procedure shall be submitted by contractor & shall be approved before short
circuit test.
Annexure - I
Test Plan
No. Test Um Um
≤ 170kV > 170kV
5. Magnetic balance test (for three phase Transformer only) Routine Routine
9. Full wave lightning impulse test for the line terminals (LI) Routine -
13. On-load tap changer test(Ten complete cycle before LV test) Routine Routine
15. Core assembly dielectric and earthing continuity test Routine Routine
18. Short duration heat run test (Not Applicable for unit on which Routine Routine
temperature rise test is performed)
19. Measurement of no load current & Short circuit Impedance with Routine Routine
415 V, 50 Hz AC.
21. High voltage with stand test on auxiliary equipment and wiring after Routine Routine
assembly
24. Chopped wave lightning impulse test for the line terminals (LIC) Type Routine
25. Switching impulse test for the line terminal (SI) Type Routine
28. Lightning impulse test for the neutral terminals (LIN) Type Type
33. Measurement of power taken by fans and oil pumps Type Type
(Not applicable for ONAN)
34. Dynamic Short circuit withstand test (If specified in BPS) Type Type
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
ANNEXURE J
PT 100 Resistance (Temerature Vs Resistance)
(BS 1904: 1984 & IEC 751: 1985)
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
ANNEXURE - K
1.1. Online Dissolved Gas (Multi-gas) and Moisture Analyser along with all required
accessories including inbuilt display shall be provided with each Transformer for measurement
& analysis of dissolved gases and moisture in the oil. Interpretations shall be as per IEC 60599-
1999.
1.2. The equipment shall detect, measure and analyse the following gases:
1.3. The analyser should measure (not calculate) all above gases and should have 100%
sensitivity. The equipment shall be capable of transferring data to sub-station automation
system confirming to IEC 61850. Necessary interface arrangement shall be provided by the
contractor for integration with automation system. The necessary type test report for such
confirmation shall be submitted during detailed engineering.
1.4. Equipment shall have facility to give SMS alert to at least three users whenever any fault
gas violates the predefined limit.
1.5. Equipment should work on station auxiliary supply. In case other supply is required for the
equipment then suitable converter shall be included. All the necessary power and control cables,
communication cables, cable accessories as required shall be provided by the supplier.
1.6. Online DGA shall be installed out door on Transformer in harsh ambient and noisy
condition (Electromagnetic induction, Corona, and capacitive coupling). Equipment shall be
mounted separately on ground. Suitable arrangement shall be provided to support and protect
the inlet and outlet piping arrangement. The connecting oil lines must be of Stainless-Steel rigid
pipes or flexible hoses. The equipment shall be suitable for proper operation in EHV substation
(800kV) environment where switching takes place in the EHV/HV System. The suitable
indications for power On, Alarm, Caution, normal operation etc. shall be provided on the front
panel of the equipment. The equipment shall have IP55 Stainless Steel enclosure, suitable for 55
0
C ambient temperature and EMI and EMC compatibility. The Equipment must carry a
minimum of five (5) years manufacturer’s Warranty.
1.7. The equipment shall display all the individual gas and moisture concentration on its
display unit and shall have facility to download all the stored the data from the unit for further
analysis. The sampling rate shall be selectable as 2 or 4 or 6 or 12 hours etc. The equipment
shall have inbuilt memory to store these results for complete one year even if sampling is done
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
at the lowest interval. The carrier and calibration gas (if applicable) shall have minimum
capacity to work for at least three years without replacement. All the consumable (if any) upto
warrantee period shall be included in the scope of supply
1.8. The Equipment must have an automatic Calibration facility at fixed intervals. For
calibration if anything required including cylinder must be mounted with the Equipment.
1.12. The equipment shall be supplied with all necessary accessories required for carrying out
DGA of oil sample complete in all respect as per the technical specification. The following
shall be also form a part of supply.
i) Software
ii) Operation Manual (2 set for every unit),
iii) Software Manual and
iv) Compact disc giving operation procedures of Maintenance Manual & Trouble shooting
instructions.
1.13. The installation and commissioning at site shall be done under the supervision of OEM
representative or OEM certified representative.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Annexure - L
LIST OF TESTING EQUIPMENT
3 Stainless Steel Oil sampling bottle (One Litre Capacity) SCIENO TECH 1 ltr
ANNEXURE - M
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
1.1 All Power & Control cables shall be supplied from Employer’s approved vendors.
1.2 Separate cables shall be used for AC & DC.
1.2 Separate cables shall be used for DC1 & DC2.
1.3 At least one (1) core shall be kept as spare in each copper control cable of 4C, 5C or 7C size
whereas minimum no. of spare cores shall be two (2) for control cables of 10 core or higher
size.
1.4 The Aluminium/Copper wires used for manufacturing the cables shall be true circular in
shape before stranding and shall be uniformly good quality, free from defects. All aluminium
used in the cables shall be of H2 grade.
1.5 The fillers and inner sheath shall be of non-hygroscopic, fire retardant material, shall be
softer than insulation and outer sheath shall be suitable for the operating temperature of the
cable.
1.6 Progressive sequential marking of the length of cable in metres at every one metre shall be
provided on the outer sheath of all cables.
1.7 Strip wire armouring method (a) mentioned in Table 5, Page-6 of IS: 1554 (Part 1) – 1988
shall not be accepted for any of the cables. For control cables only round wire armouring
shall be used.
1.8 The cables shall have outer sheath of a material with an oxygen index of not less than 29 and
a temperature index of not less than 250°C.
1.9 All the cables shall conform to fire resistance test as per IS: 1554 (Part - I).
1.10 The normal current rating of all PVC insulated cables shall be as per IS: 3961.
1.11 Repaired cables shall not be accepted.
1.12 Allowable tolerance on the overall diameter of the cables shall be plus or minus 2 mm.
1.13 PVC Power Cables
1.13.1 The PVC (70°C) insulated 1100V grade power cables s hall be of FR type, C1 category,
conforming to IS: 1554 (Part-I) and its amendments read along with this specification and
shall be suitable for a steady conductor temperature of 70°C. The conductor shall be stranded
aluminium. The Insulation shall be extruded PVC to type-A of IS: 5831. A distinct inner
sheath shall be provided in all multi core cables. For multi core armoured cables, the inner
sheath shall be of extruded PVC. The outer sheath shall be extruded PVC to Type ST-1 of IS:
5831 for all cables. The contractor can used copper cable of required size.
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Schedule-2
List of drawings to be submitted by successful bidder for approval of the
1 General Arrangement (with provision of pockets for PT-100 sensors for remote /SCADA oil
& winding Temperature Indications) Overall dimensions to be restricted as per Clause 5.3
3 Rating and diagram plate (additional information such as Guaranteed /Measured losses;
Guaranteed /Measured impedances at extreme and normal taps; Guaranteed /Measured
Temperature rises for oil & winding; Core weight; Copper weight and Core & winding
weight
shall be invariably mentioned )
6 Foundation Plan
7 Transport Outline
8 H.V. Bushing
10 L.V. Bushing
11 Neutral Bushing
I) HV
iii) LV.
15 Conservator Tank.
22 OLTC Schematic with group simultaneous mode of control. Connectivity for tap raise -lower
operations and Tap Position Indication.through SCADA & TMCTS
23 OLTC legend
25 RTCC legend
26 Radiators.
ii) Main and standby supply circuit alongwith heater and lighting circuit
iii) Power circuit for Fans Gr.I, Gr.II & Standby
v) Power circuit for pumps Gr.I, Gr.II and Standby (as per requirement)
vi) Control circuit for Pumps Gr.I, Gr.II, (as per requirement)
winding temperature.
x) Alarm & Trip Circuit (for MOG, PRV, Main Buchholz & OLTC Buchholz
xi)) Wiring diagram of PT - 100 (for remote / SCADA WDG Temp. and Oil Temp.
Indication)
xii) Cable Termination Plan (Co-ordination) between
a) FCC to RTCC
b) FCC to OLTC
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
35 Roller Assembly
36 N2 Injection fire protection system drawing with Bill of material.(as per requirement)
37 HVWS fire protection system drawing with Bill of material.(as per requirement)
38 GTP for approval
39 Complete Bill of Materials.
40 QAP
41 Type Test Report conducted on identical transformer within last 5 years (if any)
42 I2R calculations
43 Impedance calculations
44 Short circuit calculations
45 Cooling calculations
46 Core cutting schedule (Core shall be cut at Mill’s authorised processing unit ony)
Schedule-3
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
1. Flux density at
(i) (145/36, 245/145, 245/145/36, 420/245) kV & 48.5
Hz, Tesla
(ii) (132/33, 220/132/33, 220/132, 132/33) kV & 50
Hz, Tesla.
2. Core Data
(i) Core weight in Kg.
(ii) Gross core area [mm²]
(iii) Stacking factor.
(iv) Net core iron area [mm²] [ii x iii]
3. Specific losses [W/Kg.]
(i) At maximum flux density corresponding to
(145/36, 245/145, 245/145/36, 420/245) KV and
48.5 HZ.
(ii) At maximum flux density corresponding to
(132/33, 220/132/33, 220/132, 132/33) KV and
50Hz.
4. Volt ampere/Kg
(i) At maximum flux density corresponding to
(145/36, 245/145, 245/145/36, 420/245) KV and
48.5 HZ.
(ii) At maximum flux density corresponding to
(132/33, 220/132/33, 220/132, 132/33) KV and
50Hz.
5. Calculated/guaranteed iron loss in KW at:
(i) Rated voltage and rated frequency
(ii) Rated voltage and rated frequency
6. Current density [A/Sq. mm] for
(i) HV
(ii) LV
7. Conductor size [in mm²]
(i) HV winding
a) Bare
b) Insulated
c) No of conductors in parallel
(ii) LV winding
a) Bare
b) Insulated
c) No of conductors in parallel
8. Copper weight
(i) H.V. windings
(ii) LV windings
(iii) For Tap connections,
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
NB: - 1. Approximate values in weight and losses etc. are not allowed.
2. Tolerance of + 5% in weights may be quoted without any approximation
Place:
Date:
Bidder’s name:
Signature, designation, seal
Schedule-4
Maximum Flux Density and Core Weight Calculation
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Bmax = E/ (4.44 x f x Ai x N)
NB: -
1 Specific loss vs. flux density graph for the type of core lamination to be used has to be furnished.
2. VA/Kg. Vs flux density graph for the core lamination to be used has to be furnished.
3. Any other factor assumed for above calculation to be explained with reasons.
N.B:- The bidder may use its own method of calculation towards determination of maximum
flux Density and weight of the core. But the same shall be supported with proper explanation
and Justification.
Place:
Date: Signature of Bidder
With seal of Company.
Schedule-5
Sl No. Component Characteristics Type Quantum Ref Doc & Form of Inspection Remarks
of Acceptable Record Agency
of Inspection Norm
Inspection
1.0 MATERIAL
1.1 Copper Conductor
1.1.1 Sample check Testing Sampling/lot TM Spec Insp.rec Vendor/TM CHP at
on winding ord QC Vendor
conductor for end
electrical
conductivity
1.1.2 Dimensions Width Measurem -Do- TM Spec -Do- -Do- CHP at
& ent Vendor
Thickness ( Bare) & end
Visual for
scratches, dentarks
Sl No. Component Characteristics Type of Quantum Ref Doc & Form of Inspection Remarks
Inspection of Acceptable Record Agency
Inspection Norm
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
Welds(DP test)
2.2.3 dimensions between Testing Each Unit TM Spec Insp Vendor/TM CHP at
wheels, demonstrate Record QC Vendor
turning of wheels end
through 90 deg. &
further dimensional
check
2.2.4 Leakage Test of Testing Each Unit TM Spec Insp Vendor/TM CHP at
conservator Record QC Vendor
end
2.2.5 Measurement of Testing Each Unit TM Spec Insp Vendor/TM CHP at
film thickness of Record QC TM for
total DFT
measure
ment
during
final
inspectio
n
(i) Zinc chromate Meas -Do- -Do- -Do- -Do-
paint
Sl No. Component Characteristics Type of Quantum Ref Doc & Form of Inspection Remarks
Inspection of Acceptable Record Agency
Inspection Norm
internal fillings Spec Record ’s QC
(Tightness test)
2.7.2 Dry power TC Verif Each Unit IS 2099/TM Insp Vendor/TM
frequency test on Spec Record ’s QC
terminal & tapping
2.7.3 Measurement of TC Verif Each Unit IS 2099/TM Insp Vendor/TM
dielectric dissipation Spec Record ’s QC
factor &
capacitance
2.7.4 Partial discharge Testing Each Unit IS 2099/TM Insp Vendor/TM CHP at
test followed by Spec Record ’s QC Vendor
dielectric dissipation end
factor & capacitance
measurement for
condenser bushings
&
creepage distance
measurement.
Sl No. Component Characteristics Type of Quantum Ref Doc & Form of Inspection Remarks
Inspection of Acceptable Record Agency
Inspection Norm
Record ’s QC
2.14 Tap changer
2.14.1 Type & Rating Visual Each Unit TMs Spec Insp Vendor/TM
Record ’s QC
2.14.2 Physical condition Visual Each Unit TMs Spec Insp Vendor/TM
Record ’s QC
2.14.3 Mechanical Operation Testing Each Unit TMs Spec Insp Vendor/TM
Check Record ’s QC
2.14.4 Insulation Testing Each Unit TMs Spec Insp Vendor/TM
Resistance Test Record ’s QC
2.15 Cooling fan
2.15.1 HV test Testing Each Unit IS 2312 Insp Vendor/TM
Record ’s QC
2.15.2 Insulation Resistance -Do- -Do- -Do- -Do- -Do-
Test
2.15.3 Performance Test -Do- -Do- -Do- -Do- -Do-
2.15.4 DFT of -Do- -Do- TM’s Spec -Do- -Do-
Galvanization on
Fan guard
3.0 MANUFACTURING
3.1 Assembled Core
3.1.1 Visual & Visual/ Each TM’s Spec Insp Vendor/TM CHP at
dimensional check Meas Assembly Record ’s QC TM’s
during assembly Works
stage
3.1.2 Check on Meas/T Each Customer Insp Vendor/TM CHP at
completed core for esting Assembly Spec Record ’s QC TM’s
measurement of Works
iron loss
3.1.3 2KV H.V.test (Core Testing Each Customer Insp Vendor/TM CHP at
insulation test) Assembly Spec Record ’s QC TM’s
between Core & Works
clamps for one
minute And
Insulation
resistance test of
core & clamps
(clamps)
3.1.4 Visual & Visual -Do- -Do- -Do- -Do- CHP at
dimensional checks TM’s
for straightness & Works
roundness of core,
thickness of limbs
and suitability of
clamps
3.2 Wound Coils
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
3.2.1 Visual check for Visual Sampling/L TM’s Spec Insp Vendor/TM CHP at
brazed joints ot Record ’s QC TM’s
wherever Works
applicable
3.2.2 Visual check of Visual Sampling/L TM’s Spec Insp Vendor/TM CHP at
insulation on the ot Record ’s QC TM’s
conductors & Works
between the
windings
3.2.3 Check for the Testing -Do- -Do- -Do- -Do- CHP at
Sl No. Component Characteristics Type of Quantum Ref Doc & Form of Inspection Remarks
Inspection of Acceptable Record Agency
Inspection Norm
absence of short TM’s
circuit between Works
parallel strands of
PICC
3.3 Coil & Core assembled
3.3.1 Active part before
drying
(i) Visual check Visual Each Unit TM’s Spec Insp Vendor/TM CHP at
Record ’s QC TM’s
Works
(ii) Check insulation Meas -Do- -Do- -Do- -Do- CHP at
distance between TM’s
high voltage Works
connections,
between high
voltage connection
cables & earth and
other live parts
(iii) Check Meas -Do- -Do- -Do- -Do- CHP at
insulating distance TM’s
between low Works
voltage connections
and earth and other
parts
(iv) 2KV core Testing -Do- -Do- -Do- -Do- CHP at
insulation test TM’s
Works
3.3.2 Active part
after drying
(i) Measurement & VPD Each Unit TM’s Spec Insp TM’s In
recording of Data Record testing/TM’ s process
temperature & QC check
drying time during card
vacuum treatment review
by
Custome
r
(ii) Check for VPD Each Unit TM’s Spec Insp TM’s In
completeness of Data Record testing/TM’ s process
drying QC check
card
review
by
Custome
r
CHAPTER 17: TECHNICAL SPECIFICATION FOR TRANSFORMERS (UPTO 400KV)
3.5.1.15 Measurement of
the harmonics of
the no-load current
3.5.1.16 Measurement of
capacitance and
ten δ to determine
capacitance
between winding
and earth. Value of
tanδ should not be
more than 0.5% at
20°C
3.5.1.17 Oil leakage test on
Sl No. Component Characteristics Type Quantum Ref Doc & Form of Inspection Remarks
of Inspection Acceptable Record Agency
of Norm
Inspection
transformer tank as
per CBIP
3.5.1.18 Test on OLTC
3.5.1.19 Magnetic
balance
test
3.5.2 Type Test
3.5.2.1 Temperature-rise Testing One Unit IS 2026/IEC Insp Customer/ CHP at
test with 2 x 50% on each 60076 Record TM TM’s
radiator banks rating Works
including DGA test
after & before temp
rise test
3.5.2.2 Measurement of CHP at
the power taken by TM’s
the fans Works
3.5.2.3 Pressure
Note:
1.TM – Transformer Manufacturer
2.CHP – Customer Hold Point
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
Bidder shall furnish calculation in support of selection of capacity as well as number of Cells, Float &
Boost charger current / Voltages.
(ii) The scope also covers the design, manufacture, assembly, testing at the manufacturer’s works
of 48 V D.C. Maintenance free Valve regulated Lead Acid Battery, having minimum capacity of 300
AH and associated battery charger with provisions of both float and boost charging of battery along
with necessary accessories, fittings etc.
Each battery shall have sufficient capacity for continuous DC supply to PLCC Terminals, Protection
Coupler Units, Fiber Optic Terminals, EPAXes, Remote Terminal Unit (RTU) etc. as and when
required as well as float charging current of the battery.
The battery shall consist of 24 number of cells, float & boost voltage to achieve a system
voltage 48V. Battery shall have 20% spare capacity. Supplier shall furnish characteristic curve for
satisfactory operation and maintenance of battery under service condition.
Bidder shall furnish calculation in support of selection of Float & Boost charger current/Voltages.
18.2. RATING OF BATTERY AND FUNCTION OF CHARGER:
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
D.C. Power Supply shall comprise a set of Battery (220V) of desired capacity, a Float charger and a
Float cum Boost Battery Charger (minimum 60A) in parallel operation. In this mode the charger shall
be required not only to continuously feed a variable load but also deliver trickle/boost charging
current for the battery. Charger shall have 20% spare capacity. Battery will be capable of feeding the
DC load requirement of the Sub-station in case of failure of the charger. Ampere-hour capacity of the
battery shall be designed considering the current load and expected future load due to extension of the
Sub-Station (if not specified, then minimum 3 nos of future bays are to be considered for each voltage
class). A detailed design calculation for both battery & charger are to be submitted for approval.
18.3. TRICKLE / BOOST CHARGE VOLTAGE:
The trickle and Boost charge voltage per cell shall be as follows:
a) 220V Battery Bank
i) TRICKLE CHARGE: Per Cell Voltage 2.2 V to 2.25±0.02 V
ii) Boost charge voltage should vary between 2.23 to 2.3V/cell.
18.4. VOLTAGE / CURRENT REGULATION OF CHARGER:
Output voltage for float charging from battery charger shall be auto controlled by adjusting the firing
angle of thyristor for float charger to keep the voltage variation within ± 1% from no load to full load
and AC supply voltage variation of ±10% and frequency variation of ± 3% of 50 Hz. Manual control
of output voltage shall also be possible through Auto/Manual selector switch.
The Boost / Quick charger shall be similar type as Float / Trickle charging equipment, but shall be
provided with control arrangement for ‘auto/manual’ current regulation features, necessary for quick
charging. An automatic VOLTAGE controller for boost charging shall control the output VOLTAGE
WITH CURRENT LIMIT AS LIMITED FOR RESPECTIVE BATTERY CAPACITY by adjusting
the firing angle of the thyristor.
18.5. CLIMATIC CONDITIONS:
The equipment to be supplied against the specification shall be suitable for satisfactory continuous
operation under the climatic condition mentioned in chapter 2 of this bidding document.
18.6. DESCRIPTION OF BATTERY:
Type:
The DC batteries shall be VRLA (Valve regulated Lead Acid) type & shall be Normal Discharge type
and shall conform to IS 15549:2004/ IEC 60896-21 & 22:2004/ BS 6290- PART IV/ IEEE-1188
standard. These batteries are to be factory-filled, charged & shall be suitable for a long life under
continuous float operations & occasional discharges. The 220V DC system is unearthed system. The
offered battery shall be compact and shall require no maintenance. All safety equipment required for
installation shall be provided by the manufacturer.
Constructional requirements:
The design of battery shall be as per field proven practices. Partial plating of cells is not permitted.
Paralleling of cells externally for enhancement of capacity is not permitted. Protective transparent
front covers with each module shall be provided to prevent accidental contact with live module/
electrical connections.
Plates:
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
Positive plates shall be made pasted type using high purity corrosion resistant alloy for deep
discharge, durability, maintenance free, long life both in cyclic as well as in float applications. The
Grids are of Semi Radial Squarish grid to reduce internal resistance and travel current in shorter time.
Negative plates shall be heavy duty, durable flat pasted plate using lead alloy pasted Semi Negative
Squarish Grid. Negative plates shall be designed to match the life of Positive plates & combination of
positive & negative plates shall ensure long life, durability & trouble-free operation of battery.
Computer controlled/ PLC operated in-house equipment should be deployed for preparation of lead
oxide and paste to ensure consistency in paste quality & properties.
Containers:
The container material shall have chemical & electro-chemical compatibility & shall be acid resistant
and shall conform to UL-94/ ASTM-D-2863 standard. The material shall meet all the requirements of
VRLA batteries and be consistent with the life of battery. The container shall be fire retardant. The
porosity of the container shall be such as not to allow any gases to escape except from the regulation
valve. The tensile strength of the material of the container shall be such as to handle the internal cell
pressure of the cells in the worst working condition. Cell shall not show any deformity of bulge on the
sides under all working conditions. The container shall be capable of withstanding the rigorous of
transport, storage and handling. The containers shall be enclosed in a steel tray.
For identification, each cell/module shall be marked in a permanent manner to indicate the following
information:
(i) Cell Serial Number
(ii) Positive & Negative, embossed on the cover
(iii) Month & Year of Manufacturing
Cell Covers:
The cell covers shall be made of suitable material compatible with the container material and
permanently fixed with the container by Hermetic Heat-Sealing technique. It shall be capable to
withstand internal pressure without bulging or cracking. It shall also be fire retardant. Fixing of
Pressure Regulation Valve & terminal posts in the cover shall be such that the seepage of electrolyte,
gas escapes and entry of electro-static spark are prevented.
Separators:
The separators used in manufacturing of battery cells, shall be of glass mat or synthetic material
having high acid absorption capability, resistant to sulphuric acid & shall have good insulating
properties. Sufficient separator overlap & PVC shield protection in bottom edges of the plates is to be
provided to prevent short circuit formation between the edges of adjacent plates. The design of
separators shall ensure that there is no misalignment during normal operation & handling.
Pressure Regulation Valve:
Each cell shall be provided with a pressure regulation valve. The valve shall be self-re- sealable. The
vent plug shall be made with suitable grade of fire-retardant plastic material. Each valve opening shall
be covered with flame barrier capable of preventing the ingress of flame into the cell interior, when
the valve opens & hydrogen/ oxygen gas mixture is released. The valve unit shall be such that it
cannot be opened without a proper tool. The valve shall be capable to withstand the internal cell
pressure specified by the manufacturer.
Terminal Posts:
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
Both the +ve & -ve terminals of the cells shall be capable of proper termination & shall ensure its
consistency with the life of the battery. The terminals shall have lead plated adequate solid copper/
brass core cross-section to avoid overheating at maximum current load. The surface of the terminal
post extending above the cell cover including bolt hole shall be coated with an acid resistant &
corrosion retarding material. Terminal posts or any other metal part which is in contact with the
electrolyte shall be made of the same alloy as that of the plates or of a proven material that does not
have any harmful effect on cell performance. Both +ve & -ve posts shall be clearly and
unambiguously identifiable.
Connectors, Nuts & Bolts, Heat Shrinkable Sleeves:
Where it is not possible to bolt the cell terminals directly to assemble a battery, separate non-
corroding lead coated copper connectors of suitable size shall be provided to enable connection of the
cells. Copper connections shall be suitably lead coated to withstand corrosion due to sulphuric
acid/fumes at a very high rate of charge or discharge.
Nuts & bolts for connecting the cells shall be made of copper, brass or stainless steel. Copper or brass
nuts & bolts shall be effectively lead coated to prevent corrosion. Stainless steel bolts & nuts can be
used without lead coating.
All inter cell connectors shall be protected with heat shrinkable sleeves for reducing the
environmental impact including a corrosive environment.
More than one cable may be required to be connected to the battery terminals. Suitable arrangement
for termination of multiple cables shall be provided so as to avoid extra load on the battery terminals.
Necessary insulating supports for termination of these cables on batteries shall also be
supplied by the bidder.
All connectors shall be capable of continuously carrying the 30 min. discharge current of the
respective batteries and shall be capable to carry 4KA for 1 sec.
Flame Arrestors:
Each cell shall be equipped with a Flame Arrestor to defuse the Hydrogen gas escaped during charge
& discharge. Material of the flame arrestor shall not affect the performance of the cell.
Battery Bank Stand:
All batteries shall be mounted in a suitable metallic stand/ frame. The frame shall be properly painted
with the acid resistive paint & should have protection against harmful effects due to tropical
environment. The suitable insulation shall be provided between stand/ frame and floor to avoid the
grounding of the frame/ stand. The jointing of the frames should not leave crevices and ensure proper
and tight fit.
Numbering tags for each cell shall be attached to the racks. Provision for clamping outgoing cables
shall be kept.
18.7. CAPACITY REQUIREMENTS:
When the battery is discharged at 10-hour rate, it shall deliver 80% of Rated Capacity (corrected at
27°C) before any of the cells in the battery bank reaches 1.85 V/cell.
The battery shall be capable of being recharged from the fully exhausted condition (1.75 V/cell)
within 10hrs up to 90% state of charge. All the cells in a battery shall be designed for continuous float
operation at the specified float voltage throughout the life.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
The capacity (corrected at 27°C) shall also not be less that Rated capacity & not more that 120% of
Rated capacity before any cell in the battery bank reaches 1.75 V/cell. The battery voltage shall not be
less than the following values, when a fully charged battery is put to discharge at a rate of 1/10th of
the Rated Capacity:
(a) After SIX minutes of discharge: 1.98V/cell
(b) After SIX hours of discharge: 1.92V/cell
(c) After EIGHT hours of discharge:1.85V/cell
(d) After TEN hours of discharge: 1.75V/cell
Loss in capacity during storage at an average ambient temperature of 35°C for a period of 6 months
shall not be more than 60% and the cell/battery shall achieve 85% of its rated capacity within 3
charge/discharge cycles and full rated capacity within 5 cycles, after the storage period of 6 months.
Voltage of each cell in the battery set shall be within 0.05V of the average voltage throughout the
storage period. Ampere hour efficiency shall be better than 90% and watt-hour efficiency shall be
better than 80%. However, the battery to be manufactured and to be delivered at site in such a way
that load can be connected with the battery within 15 days from date of installation, date of initial
charging is to be mentioned on the battery.
18.8. EXPECTED BATTERY LIFE
The battery shall be capable of giving 1200 or more charge/discharge cycles at 80% Depth of
Discharge at an average temperature of 27°C. Depth of Discharge is defined as the ratio of the
quantity of electricity (in Ampere Hour) removed from a cell or battery on discharge to its rated
capacity. The battery sets shall have a minimum expected life of 20 years at Float operation.
18.9. ASSOCIATED EQUIPMENTS & ACCESSORIES (For each set of battery):
7 Material Identification
8 Valve Operation
11 Discharge Capacity
14 Recharge behavior
Impact of Stress Temperature of 60°C for brief duration exposure time with 3hrs
16
discharge test
B. BATTERY CHARGERS
18.13. SCOPE:
(i) Battery Charger for 220V/110V DC Battery Bank:
The DC system for 220V DC is unearthed. The Battery Chargers as well as their automatic regulators
shall be of static type and shall be compatible with VRLA batteries. All battery chargers shall be
capable of continuous operation at the respective rated load in float charging mode while supplying
the DC load. The chargers shall also be capable of Boost charging the associated DC battery at the
desired rate.
Under normal operating conditions the charger should give a D.C. output equal to the steady demand
load for signal lamps, auxiliary relays etc. plus an output to trip coils and closing coils of the circuit
breakers and relays as and when required as well as float charging current of the battery. Charger shall
have 20% spare capability.
(ii) Battery Charger for 48V DC Battery Bank:
The charger shall be suitable for charging the battery and supplying the load simultaneously. The
entire charger scheme shall be divided in two sections, "float charger section" and "float-cum-boost
charger section". The float-cum-booster charger shall be suitably operated either in float mode or in
boost-cum-standby float charger mode. The float charger and the float-cum-Boost Charger shall have
adjustable output current 60 Amps D.C. for 300 AH for float charging and 60 Amps DC for boost
charging. Charger shall have 20% spare capability.
Under normal operating condition, with the input AC supply present, the float charger section' shall
supply the DC load and also float the battery by trickle charging and the "float cum boost charger
section" shall be kept off. The maximum demand load on the charger shall be 60A for 300AH
Battery.
18.14. GENERAL DESCRIPTION FOR CHARGERS:
a) The battery chargers shall be provided with facility for both automatic and manual control of
output voltage and current. A selector switch shall be provided for selecting the mode of output
voltage/current control, whether automatic or manual. When on automatic control mode during float
charging, the chargers output voltage shall remain within + 1% of the set value, for AC input voltage
variation of + 10%, frequency variation of + 5% a combined voltage and frequency variation of +
10% and a DC load variation from zero to full load.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
b) The battery chargers shall have constant voltage characteristics throughout the range (from
zero to full load) at the floating value of the voltage so as to keep the battery fully charged but without
harmful overcharge.
c) The chargers shall have load limiters having drooping characteristics, which shall cause,
when the voltage control is in automatic mode, a gradual lowering of the output voltage when the DC
load current exceeds the Load limiter setting of the Charger. The Load- limiter characteristics shall be
such that any sustained overload or short circuit in DC system shall not damage the Charger nor shall
it cause blowing of any of the Charger fuses. The Charger shall not trip on overload or external short
circuit.
d) Uniform and step less adjustments of voltage setting (in both manual and automatic modes)
shall be provided on the front of the Charger panel covering the entire float charging output range
specified. Step less adjustments of the Load-limiter setting shall also be possible from 80% to 100%
of the rated output current for charging mode.
e) During Boost Charging, the Battery Charger shall operate on constant voltage with current
limit mode (when automatic regulator is in service) to restrict battery charging current as specified.
After completion of boost charging this float cum boost converter section either goes standby mode or
float mode as desired by the system.
f) The Charger manufacturer may offer an arrangement in which the voltage setting device for
Float charging mode is also used as output voltage limit setting device for Boost charging mode and
the Load-limiter of Float charging mode is used as current setting device in boost charging mode for
Float cum Boost Converter section. For Float charger section shall provide separate arrangement.
g) Suitable filter circuits shall be provided in all the chargers to limit the ripple content (Peak to
Peak) in the output voltage to 1% irrespective of the DC load level, when they are not connected
to a battery.
h) MCCB
All Battery Chargers shall have sufficient MCCBs on the input side to receive cables from two
sources.
Mechanical interlock should be provided such that only one source shall be closed at a time. It shall
be of P2 duty and suitable for continuous duty with breaking capacity minimum 25KA at 415V AC.
MCCB’s should have auxiliary contacts for annunciation.
i) Rectifier Transformer
The rectifier transformer shall be continuously rated, dry air cooled (A.N) an of class F insulation
type. The rating of the rectifier transformer shall have 10% overload capacity. The transformer shall
be of suitable rating to comply with maximum output with minimum input voltage.
j) Rectifier Assembly
The rectifier assembly shall be fully/half controlled bridge type and shall be designed to meet the duty
as required by the respective charger. The rectifier shall be provided with heat sink having their own
heat dissipation arrangements with natural air cooling. Necessary surge protection devices and
rectifier type test acting HRC fuses shall be provided in each arm of the rectifier connections.
k) Instruments
One AC voltmeter and one AC ammeter along with selector switches shall be provided for all
chargers. One DC voltmeter and DC ammeter (with shunt) shall be provided for all chargers. The
instruments shall be of 96 mm X 96 mm square dial & shall be flush type, dust proof and moisture
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
resistant. The instruments shall have easily accessible means for zero adjustment. The instruments
shall be of 1.5 accuracy class. In addition to the above a centre zero voltmeter with selector switch
shall also be provided for 220 V Chargers for testing purpose.
l) Air Break Switches
One DC output switch shall be provided in all chargers. They shall be air break type suitable for 500
Volts AC/ 250 V DC. The contacts of the switches shall open and close with a snap action. The
operating handle of the switch shall be fully insulated from circuit. ‘ON’ and ‘OFF’ position on the
switch shall be clearly indicated. Rating of switches shall be suitable for their continuous load.
Alternatively, MCCB’s of suitable ratings shall also be acceptable in place of Air Break Switch.
m) Fuses
All fuses shall be HRC Link type. Fuses shall be mounted on fuse carriers which are in turn mounted
on fuse bases. Wherever it is not possible to mount fuses on carriers, fuses shall be directly mounted
on plug-in type base. In such case one insulated fuse pulling handle shall be supplied for each charger.
Fuse rating shall be chosen by the Bidder depending on the circuit requirement. All fuses in the
chargers shall be monitored. Fuse failure annunciation shall be provided on the failure of any fuse.
n) Blocking Diode
Blocking diode shall be provided in the positive pole of the output circuit of each charger to prevent
current flow from the DC battery into the charger. All the semiconductor devices shall be protected
with power transient suppressor circuit.
o) Annunciation System
Audio-visual indications through bright LEDs shall be provided in all Chargers for the following
abnormalities: -
(i) AC Power failure.
(ii) Rectifier/chargers fuse blown (separate for Float & Float cum boost).
(iii) Over voltage across the battery when boost charging.
(iv) Abnormal DC Bus voltage (High/Low)
(v) Any other annunciation if required
Potential free NO contacts of above abnormal conditions shall also be provided for common remote
indication “CHARGER TROUBLE” in Owner’s Control Board. Indication for charger in float mode
and boost mode through indication lamps shall be provided for chargers. A Potential free contact for
float/boost mode shall be provided for external interlocks.
p) Name Plates and Marking
The name plates shall be white with black engraved letters. On top of each Charger, on front as well
as rear ides, larger and bold name plates shall be provided to identify the Charger. Name plates with
full and clear inscriptions shall also be provided on and inside of the panels for identification of the
various equipment and ease of operation and maintenance.
18.15. Charger Construction
The Chargers shall be indoor, floor-mounted, self-supporting sheet metal enclosed cubicle type. The
Contractor shall supply all necessary base frames, anchor bolts and hardware. The Chargers shall be
fabricated from 2.0mm cold rolled sheet steel and shall have folded type of construction. Removable
gland plates for all cables and lugs for power cables shall be supplied by the Contractor. The lugs for
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
power cables shall be made of electrolytic copper with tin coat. Power cable sizes shall be advised to
the Contractor at a later date for provision of suitable lugs and drilling of gland plates. The Charger
shall be tropicalized and vermin proof. Ventilation louvers, if provided shall be backed with screens.
All doors and covers shall be fitted with synthetic rubber gaskets. The chargers shall have hinged
double leaf doors provided on front and on backside for adequate access to the Charger’s internals.
All the charger cubicle doors shall be properly earthed. The degree of protection of enclosure shall be
at least IP-42 as per IS: 13947 Part-1.
All indicating instruments, control switches and indicating lamps shall be mounted on the front side of
the Charger.
Each Charger shall be furnished completely wired up to power cable lugs and terminal blocks and
ready for external connections. The control wiring shall be carried out with PVC insulated, 1.5
sq.mm. Stranded copper wires. Control terminals shall be suitable for connecting two wires, with 2.5
sq.mm stranded copper conductors. Each wire shall be continuous from end to end and shall not have
any joint within itself. The insulation grade of the wiring shall be 1100 V grade. The colour of 3
Phase, 4 Wire AC. supply shall be red, yellow, blue and black for phases and neutral. The D.C. wiring
shall be of the colour other than the above (preferably grey) with the +ve and -ve marking in the
ferrule. All terminals shall be numbered for ease of connections and identification. Each wire shall
bare a ferrule or tag on each end for identification. At least 20% spare terminals shall be provided for
control circuits.
The insulation of all circuits, except the low voltage electronic circuits shall withstand test voltage of
2 KV AC for one minute. An air clearance of at least ten(10) mm shall be maintained throughout for
such circuits, right up to the terminal lugs. Whenever this clearance is not available, the live parts
shall be insulated or shrouded.
18.16. Painting of Charger
The Panels shall be pre-treated using 7-Tank process and then Epoxy Powder Coated with Paint shade
of RAL 7032.
The inside of the chargers shall be glossy white. Each coat of finishing synthetic enamel paint shall be
properly staved. The paint thickness shall not be less than fifty (50) microns.
18.17. TESTS ON CHARGER
Battery Chargers shall conform to all type tests as per relevant Indian Standard. Performance test on
the Chargers shall also be carried out on each charger as per specification. Rectifier transformer shall
conform to all type tests in IS: 4540 and short circuit test as per IS: 2026. Following type tests shall be
carried out for compliance of specification requirements: -
a. Voltage regulation test.
b. Load limiter characteristics test
c. Efficiency tests
d. High voltage tests
e. Temperature rise test
f. Short circuit test at no load and full load at rated voltage for sustained short-circuit.
g. Degree of protection test
h. Measurement of ripple by oscilloscope.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
9 When a fully charged battery is put to discharge at a rate of 1/10 th of the RatedCapacity, the
battery voltage shall not be less than:
1.98 V/cell
After SIX minutes of discharge
1.98V/cell
After SIX hours of discharge 1.92 V/cell
After EIGHT hours of discharge 1.85 V/cell
1.85V/cell
After TEN hours of discharge 1.75 V/cell
Sl
Standard No. Title
No
VOLTAGE LEVEL
Sl No Technical Parameters
400KV 132 kV 220 kV
I II III IV V
Suspension Suspension/
2 Type of mounting Pedestal
/Pedestal Pedestal
Rated Continuous
6 3150A 800 A 1250 A
Current
Minimum Guaranteed
resistive component of
12 500 Ohm 570 ohm 570 ohm
impedance in Blocking
Frequency range
10KA. However,
Coordination shall be
Nominal discharge
done by taking 20KA
14 current of protective 10 KA 10 KA
8/20 micro-sec
device
discharge in to
consideration.
Rated voltage of
15 > 15.72 KV rms 4.5 KV 9 KV
protective device
protective device
Radio Influence Voltage < 500 micro Volt @ < 500 micro < 500
18
(RIV) 280KV. volt microvolt
Attenuation in tuned
19 > 7.5 dB >7.5 dB >7.5 dB
frequency band
The device connected across the main coil and tuning device which prevents the
line trap from being damaged by transient over voltages which may occur across
it. The protective device shall be so designed and arranged that neither a
significant alteration in its protective function nor physical damage shall result
either from the temperature rise or magnetic field of the main coil at continuous
rated current, rated short-time current or from emergency overload current. It
shall neither enter into operation as a result of the power frequency voltage
developed across the line trap by rated short time current nor shall it remain in
operation after a response to a transient over voltage which is immediately
followed by the power frequency voltage developed across the line trap by rated
short-time current.
19.2.3.1.4 The protective device shall be shunt connected to the main coil and
the tuning device.
19.2.3.1.5 For proper coordination with the lightning arrester installed in the
substations and generating stations, the wave traps shall be provided with
protective device with nominal discharge current of 10 KA.
19.2.3.2DESIGN REQUIREMETS:
19.2.3.2.1 Ability to withstand rated short-time current: The line trap so
designed shall be capable to withstand the mechanical forces produce by
asymmetrical peak value of the short-time current.
19.2.3.2.2 Insulation level:
The insulation level for the insulation between the terminals of a line trap is
governed by the rated voltage of the protective device. The insulation of the
main coil and the tuning device shall be adequately rated for:-
a) the voltage developed across the line trap at the rated power
frequency by the rated short-time current. The rated voltage of the protective
device shall be higher than this voltage developed across the line trap.
b) the front of wave impulse spark over voltage or the residual voltage
caused by the nominal discharge current of the protective device, which ever is
higher.
19.2.3.2.3 System Voltage insulation:
The system voltage insulation of a line trap is provided by insulator strings or
post insulators. The line trap system voltage insulation shall be consistent with
the other equipment in the associated high voltage transmission network.
19.2.3.2.4 Tensile strength of suspension system:
The suspension system of a line trap shall be designed for a tensile stress of at
least twice the mass of the line trap in kilograms, multiplied by 9.81 to convert
to newtons, plus 5000 N.
19.2.3.3 ACCESSORIES:
a. Bird barriers: The bird barrier design shall be such that no entrance to the line
trap shall admit a sphere having a diameter of 16 mm.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
parts shall be hot dip galvanized. The arrangement of minimum three nos. of tie
rod assembly shall be required to avoid shearing from thread of tie rod
assembly.
19.2.3.6 DRAWINGS:
The following drawings indicating all the dimensions etc. with complete
technical details shall be enclosed together with technical bid :
(i) General arrangement for Line Trap indicating
dimensions, technical parameters, weight etc
(ii) Suspension / mounting arrangement indicating
dimensions
(iv) Tuning pot ckt arrangement
(v) Details of terminal clamp/connectors suitable for
AAAC/ACSR conductor and quac/twin ACSR Moose
conductor
(viii) Suspension fittings (hardware) for line trap
(ix) Disc Insulator with general technical specification
(x) Lightning Arrestor as protective device for Tuning Pot
(xi) Bird barriers
(xii) Other accessories of Line Trap
(xiii) Any other components/drawings not covered
19.3.0 TECHNICAL SPECIFICATIONS OF LINE MATCHING
UNIT/LINE MATCHING DISTRIBUTION UNIT (LMU/LMDU):
19.3.1 GENERAL REQUIREMENT:
The indoor PLCC equipments are connected to line through co-axial cable –
outdoor coupling device – Coupling Capacitors for transmission & reception of
carrier frequency signals. Coupling devices are connected in between HF
terminal of Coupling Capacitor and indoor PLCC terminals through co-axial
cable.
The coupling device proposed to be procured shall perform following functions
as a composite unit:
1. Compensate the reactive component of coupling capacitor(s) impedance
in order to efficiently transmit the carrier signals with the help of tuning
device.
2. It shall match the impedance between power line and coaxial cable end.
3. Two numbers 'phase to earth' type coupling filters shall be used to
achieve 'phase to phase'/ ' Inter-circuit coupling'. Connection
between secondaries of the two phase to earth type coupling device
shall be through a balancing transformer/hybrid such that reliable
communication shall be ensured even when one of the coupled phase is
earthed or open circuited on the line side.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
4. The coupling device shall be suitable for use with coupling capacitor of
2200 to 8800 pf and shall be programmable.
5. Insulation withstand voltage shall be 10 kV RMS for one minute.
6. Impulse withstand voltage for high voltage input side to ground shall be
10 kV and co-axial cable input to ground shall be 3 kV.
7. The nominal peak power of the coupling device shall not be less than
1000W.
8. The coupling device shall have inbuilt three element protective device
consisting of drainage coil, Lighting Arrestor and Earthing Switch
confirming to relevant standards. The same shall be generally meet the
following requirements:
(a) Drainage Coil: The drainage coil shall effectively ground the 50Hz
power frequency current received from coupling capacitor(s) but shall
not permit HF signal to ground. The power frequency impedance shall
be less than 1.5 ohm and continuous current capacity at power
frequency shall be 1.5Amp.
(b) Lightning Arrestor: The lighting arrestor shall effectively ground the
high voltage surges coming from power line side at the terminal of
coupling device. The lighting arrestor shall stand spark over voltage of
3.3 kV.
(a) The Earth Switch: The earthing switch shall ground the primary
terminal of coupling device when required. The rated current for
earthing switch shall not be less than 150 Amp.
9. The interconnections in the coupling device shall be made with special
high frequency Liz wires.
10. The impedance matching shall be prefect so that the return loss is minimum.
19. 3.1.5 TYPE TESTS:
Valid Type Test reports not more than 5-Year-old performed for following tests
along with all test result sheets & reference documents shall be submitted with
the offer here under.
• Composite Loss
• Return Loss
• Distortion & Intermodulation
• Lightning Impulse Voltage Withstand
• Power frequency Voltage Withstand
• Drain Coil
• Environmental test
• Degree of protection : IP 55
• Earth switch
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
Maximum
CHAPTER 18: TECHNICAL temperatureFORlimit
SPECIFICATION forBATTERY AND CHARGER
220V DC
2 satisfactory operation of
0
coupling 65 C
device mounted outdoor
3 Composite loss ≤ 1 dB
4 Return loss ≥ 12 dB
12 Drainage Coil :
14 Lighting Arrestor :
Earthing Switch
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
19.4.9.17 The data rate required for one compressed speech channel shall be less
than 7 kbit/s.
19.4.9.18 In a substation, selected compressed voice channels shall be through
connectable on a digital basis to other PLC terminals/links.
19.4.10.0. Narrowband Data Transmission
19.4.10.1 The PLC shall provide - as software options – up to four integrated
modems for narrowband data transmission.
19.4.10.2 Transmission speed, channel center-frequencies and the spectral
bandwidth shall be programmable in steps for commonly used data rates,
ranging from 100 bit/s to 9’600 bit/s in bandwidth of 240 Hz to 3’400 Hz
respectively.
19.4.10.3 The narrowband modems shall be designed for low delay and short
recovery times following a link disturbance.
19.4.10.4 Adaptive equalizers, individually configurable for each narrowband
modem, shall ensure optimum performance over time, by compensating
changing channel characteristics. In a 4 kHz channel, it shall be possible to
transmit up to 4 x 2’400 bit/s, or 2 x 4’800 bit/s, or 1 x 9’600 bit/s.
19.4.10.5 Data transmission above 2 kHz band-limited speech shall be possible
at 2 x 2’400 bit/s or 1 x 4’800 bit/s.
19.4.11.0 Broadband Data Transmission
19.4.11.1 The PLC shall provide – as software option – an integrated modem for
broadband / high speed data transmission. Transmission speed and spectral
bandwidth shall be programmable via PC/Notebook.
19.4.11.2 The speed and transmission bandwidth shall be programmable for up
to 32 kbit/s in 4 kHz spectral bandwidth, up to 128 kbit/s in 16 kHz bandwidth
and up to 256 kbit/s in 32 kHz bandwidth.
19.4.11.3 The data rates shall be selectable in steps, compliant with commonly
used standardized data rates.
19.4.11.4 The system shall support automatic transmission speed adaptation in
five user-defined steps, self-adapting to the prevailing line condition (noise and
interference).
19.4.11.5 The broadband modem shall provide a facility for automatic detection
and suppression of narrowband interferers.
19.4.11.6 Special operating modes shall allow transferring analog speech (with
an upper cut-off frequency of 2 kHz) and a broadband modem (operated in the
frequency band above 2 kHz) in channels with nominal bandwidth BN of 4 kHz
and 8 kHz. The data rate of the broadband modem using the remaining 2 kHz
bandwidth shall be at least 9.6 kbit/s, the data rate of the broadband modem
using the remaining 6 kHz bandwidth shall be up to 48 kbit/s.
19.4.12.0 Data Multiplexing
19.4.12.1 The PLC equipment shall provide an internal multiplexer for the time-
division multiplexing of up to 6 serial data channels and/or Ethernet/IP traffic.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
Bidder shall quote for protection signalling equipment suitable for 4 commands
with separate trip counters for transmit and receive. With regard to trip counters
alternate arrangement .i.e. Laptop along with software & all accessories to
download events including carrier receipt and transmit shall be acceptable.
Laptop for the above shall be supplied at each substation under this contract..
High security and dependability shall be ensured by the manufacturer.
Probability of false tripping and failure to trip shall be minimum. Statistical
curves/figures indicating above mentioned measures shall be submitted along
with the bid.
The DPC shall be housed in offered PLCC panel.
Reports of the following tests shall be submitted for approval for protection
signalling equipment and relays associated with the protection signalling
equipment and interface unit with protective relay units, if any.
i) General equipment interface tests :
a. Insulated voltage withstand tests
b. Damped oscillatory waves disturbance test
c. Fast transient bursts disturbance test
d. Electrostatic discharge disturbance test
e. Radiated electromagnetic field test
f. RF disturbance emission test
ii) Specific power supply tests
a) Power supply variations
b) Interruptions
c) LF disturbance emission
d) Reverse polarity
iii) Tele-protection system performance tests
a) Security
b) Dependability
c) Jitter
d) Recovery time
e) Transmission time
f) Alarm functions
g) Temperature and Humidity tests (As per IEC 68-2)
a. Dry heat test (50°C for 8 hours)
b. Low temperature test (-5°C for 8 hours)
c. Damp heat test (40°C/95%RH for 8 hours)
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
All the above tests at i, ii & iii (except temperature & humidity tests) shall be as
per IEC 60834-1 and the standards mentioned therein.
iv) Relays
a) Impulse voltage withstand test as per IEC 60255.
b) High frequency disturbance test as per IEC 60255.
19.5.2 The bidder shall offer voice frequency transmission equipment, which
shall work on frequency shift or coded signal principle for transmission/
reception of protection signals.
19.5.3 The teleprotection shall conform to IEC 60834-1, 1999.
19.5.4 Up to two integrated, independent teleprotection systems shall be
configurable, each operating in its respective channel for single- or dual-channel
PLC configurations.
19.5.5 Each teleprotection system shall support the transmission of up to four
independent and simultaneous commands, programmable individually for
blocking, permissive tripping or direct tripping (intertripping).
19.5.6 The transmission of the command signals shall be accomplished within
the speech bandwidth or within the spectral bandwidth of the broadband
modem, i.e. the teleprotection shall not require the allocation of extra / separate
bandwidth.
19.5.7 During transmission of protection commands, other services like speech
and data shall be temporarily interrupted in order to transmit the protection
signal at increased power (command signal boosting).
19.5.8 The nominal transmission time shall be < 11 ms, < 12 ms and < 13 ms
for blocking, permissive tripping and direct tripping respectively.
19.5.9 The equipment for protection shall have high degree of reliability and
speed. It shall be guaranteed to function reliably in the presence of noise
impulse caused by isolator or breaker operation.
19.5.10 The required SNR shall be less or equal than 6 dB for a dependability of
< 1E-03 for blocking and permissive tripping, and for a dependability of < 1E-
04 for direct tripping, i.e. the probability of missing a command in a maximum
actual transmission time Ttr = 15 ms, 17 ms and 22 ms respectively.
19.5.11 The probability of an unwanted command (security) shall for any SNR
condition (worst case) be not higher than 1E-03, 1E-06 and 1E-09 for blocking,
permissive tripping and direct tripping respectively.
19.5.12 Electrically isolated opto-coupler inputs, solid-state outputs and
mechanical relay outputs shall be available as I/O interfaces to the protection
devices. Voltage range shall be selectable from 24 VDC to 250 VDC nominal.
19.5.13 Commands shall be freely allocatable to the inputs and the outputs,
alarms shall be freely allocatable to the outputs (programmable via HMI).
19.5.14 It shall be possible to individually delay and prolongate the input
command signals or to prolongate the output command signals and to monitor
their duration (all parameters configurable via HMI).
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
19.5.15 All transmitted and received commands shall be logged with time
stamps of 1 ms resolution by the internal event-recorder.
19.5.16 The teleprotection shall provide an integrated cyclic loop test.
19.5.17 The teleprotection shall be software-programmable via PC HMI with
GUI.
19.5.18 For single-purpose teleprotection applications, the nominal transmission
bandwidth of the PLC terminal shall be configurable for 2 kHz or 2.5 kHz in
each direction. A service phone channel shall optionally be available in this
operating mode.
19.5.19 PRINCIPAL TECHNICAL REQUIREMENTS OF TELE
PROTECTION COUPLER
TABLE-III
Number and type of 4 solid state relays and 2 mechanical relay contacts per
outputs teleprotection interface.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
Security (Probability of
unwanted command <1E-03 <1E06 <1E-09
under worst-case SNR
condition)
19.6.2 PLATES
Positive plates shall be made of flat pasted type using lead-cadmium antimony
alloy for durability, high corrosion resistant, maintenance free, long life both in
cyclic as well as in ,float applications. Negative plates shall be heavy duty,
durable flat plate using lead calcium alloy pasted box grid. Negative plates shall
be designed to match the life of positive plates and combination of negative and
positive plates shall ensure long life, durability and trouble-free operation of
battery. PLC operated equipment should be deployed for preparation of paste to
ensure consistency in paste quality. Conventional / manual type of paste
preparation is not allowed.
19.6.3. CONTAINER AND LID
The containers and lids shall be made of a special grade polypropylene
copolymer plastic material. They shall be sufficiently robust and not liable lo
deformation under internal operating pressures and within the temperature range
naturally encountered, leak proof, non-absorbent and resistant to the acid with
low water vapour permeability.
19.6.4 VENT PLUGS
Each cell shall be equipped with one-way safety valve with opening pressure of
5±1 psi and closing pressure 4±1 psi. The vent plug shall be made with suitable
grade of fire retardant plastic material. Each valve opening shall be covered with
flame barrier capable in preventing the ingress of flame into the cell interior
when the valve opens and hydrogen / oxygen gas mixture is released.
19.6.5. SEPARATORS
Separator shall be made of spun glass, micro porous matrix and shall be
resistant to Sulphuric Acid. It shall be capable of keeping the entire electrolyte
and shall be electrically insulated. Sufficient separator overlap and PVC shield
protection to top and bottom edges of the plates is to be provided to prevent
short circuit formation between the edges of adjacent plates.
19.6.6 CONNECTORS
The connectors shall be lead coated copper of suitable size to join the cells. The
connectors shall be suitably designed and coated to withstand corrosion due to
sulphuric acid. The coating should be adequate and tenacious. All the copper
inter cell connectors shall be provided with heal shrinkable sleeves except at the
connecting points.
19.6.7. ELECTROLYTE
The electrolyte shall be prepared from the battery grade Sulphuric Acid
confirming to ISS: 266. The batteries shall be supplied in factory filled and
charged condition.
19.6.8 WATER
Water required for preparation of electrolyte shall conform to IS: I069.
19.6.9. PLATE CONNECTION
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
Sl No DESCRIPTION
1 Gas Emission
7 Material Identification
8 Valve Operation
11 Discharge Capacity
14 Recharge behavior
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
19.7.17 The SMPS battery charger shall have constant voltage characteristics
throughout the range ( from zero to full load) at floating value of the voltage so
as to keep the VRLA batteries fully charged but without harmful overcharge.
19.7.18. The float cum boost charger works on 415 V AC, 50 Hz supply (or 230
V AC, 50 Hz supply). The battery charger should be capable of delivering the
full rated load at the specified voltage at the output terminals. The set output
voltage is maintained for AC input variation of + 10% and load variation from
0-100% of rated full load.
19.7.19 The charger voltage in float mode of operation is normally be set at 54
V DC and the same shall be adjustable between 48 and 54 V DC through
variable potentiometer. When the charger is selected to boost mode, it should
supply charging at the rated current maximum. This shall be adjusted from 20%
to 100% of rated current through potentiometer.
19.7.20 All these circuits are housed in freestanding cabinet of folded sheet
steel (thickness of sheet steel should not be less than 2.5mm) construction
finished in stove enamel light gray colour conforming to shade of 631 of IS: 5.
The cabinet is provided with front and back doors for easy accessibility. All
meters, meter selector switches, control switches and LCD display
(Microprocessor unit) etc are to be provided on the front panel. The AC input
and DC output MCCB'S and control switches are provided on middle inside of
the breaker panel. The cable terminations are provided on front side of the
cubicles.
19.7.21 PARTICULARS FOR 48 VDC
Type FLOAT CUM BOOST CHARGER
Hot swappable rectifier modules 25A/48V, N+1 configuration.
TABLE-IV (a)
SL NO DESCRIPTION PARAMETERS
SYSTEM OUTPUT
12 VOLTAGE 55.2V DC+1%(at load terminal)
PROTECTION
INDICATION
AC input ON : Required
DC output ON : Required
Float ON : Required
Boost ON : Required
TABLE-IV (c)
CONTROLS AND SWITCHES
Auto /manual voltage regulator selector Single tern potentiometer for float voltage
switch adjust
Float and boost voltage variable Single tern potentiometer for boost voltage
potentiometer adjust
Manual voltage adjust variable Single tern potentiometer for charger total
potentiometer current adjust
ADDTIONAL FEATURES
the CO trunk. The software of the EPAX should support both the E & M and
CO trunks and should have the facility to be interconnected to P & T trunks for
CO Access.
19.8.3 The EPAX should support single, two- or three-digit numbering
scheme. The exchange should support a minimum of 16 out pulsing digits and a
maximum of 20 out pulsing digits at time from a normal telephone. The
exchange should be fully Non-blocking.
19.8.4 The duplication of both CPU and PSU is to be provided as in-built
features in the offered exchange.
19.8.5 The EPAX should support a maximum configuration of 250 Ports. The
EPAX shall have universal ports wherein any type of line card or trunk card of
the EPAX can be inserted into any slots. Also, the number of trunks can be
either E & M or CO or a combination of both. The offered exchange shall work
purely as a PLCC switch or a combination of PLCC & CO or a network switch
or a combination of PLCC, CO, Fibre and digital microwave.
19.8.6 The offered switch shall have compatibility with E1 type card wherein a
direct 2 MB stream can be connected to the switch.
19.8.7 The switch shall have ISDN compatibility for interfacing with PSTN
and other public ISDN exchanges. A valid TEC certification for ISDN
compatibility to be enclosed without the same the bid is liable for rejection.
19.8.8 The switch shall be equipped with voice guidance feature to navigate
the subscriber in using the major features of the exchange. Data transmission
through MODEM pooling shall be available in the exchange. The EPAX shall
support exclusive Load Despatch Express type communication network with all
to one and one to All type of trunk access. This feature shall be in addition to
the normal All to All type. The exchange offered needs to be type tested for
EMC specifications in line with IEC recommendations 495 for PLCC
equipment. A valid certification for EMC compliance from any government
laboratory within three years as on date of bid opening needs to be enclosed
with the bid. The EPAX must have been EMI / EMC tested for the following as
per IEC 495 to suit the stringent conditions in the Sub-station environment.
a. Impulse Voltage withstand test (IEC 255-4).
b. High Frequency disturbance susceptibility test (IEC 255-22-1).
c. Electrical Fast Transient Susceptibility Test (IEC 801-4).
d. Electrostatic discharge susceptibility test (IEC 801-2). Radiated
susceptibility (IEC 801-3).
19.8.9. The Bidders shall offer suitable telephone equipment for automatic
dialling which must work in full cordination with the already provided
telephone equipment in the existing PLC system.
19.8.10 The bidder shall offer the latest state-of-art digital based
Microprocessor EPAX suitable for direct connection to the PLCC terminals
without the need of any four wire-interconnecting device (EFGS/EMFGS). The
EPAX shall employ stored programme technique and utilize Time Division
Multiplexing.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
19.8.11. The EPAX shall be suitable for internal communication between the
local subscribers as well as for selective communication over tie lines.
The special features of the offered EPAX shall be as follows:
i) EPAX is of latest microprocessor-based design, which employs Pulse Code
Modulation/Time Division Multiplexing principle.
The following are the advantages over space division/reed relay switching:
a) Fully solid-state circuitry and hence high reliability in operation.
b) Fast response
c) Low operation and maintenance cost
d) High traffic handling capacity - Fully Non-blocking type
e) Compact size
f) Noise free operation
ii) Self checking diagnostics facility as a built-in feature of the EPAX. In
view of this, the maintenance of the EPAX is extremely simple.
iii) The design of the software structure should be very flexible. Using any
standard telephone instrument, the following programming shall be done at
site:
- Modification of local subscriber number
- Modification of subscriber priority
- Modification of subscriber facilities like Access to Tie lines and Follow Me
- Modification of Tie line number
- Modification of Tie line groups
- Modification of Exchange number
- Allocation of Alternate route
- Transit call barring
The above programming facility at site should not require any additional test
equipment.
iv) Built-in main distribution frame with Protective Devices such as surge
arresters and fuses for all limbs of subscriber lines and tie lines to protect the
sophisticated electronic circuitry of the exchange from damage due to external
surges/spikes.
v) The EPAX is suitable for easy expansion if required at a later date.
As per your requirement, supply of EPAXs equipped with 16,32,64 subscriber
lines and 8,16,32 tie lines (PLCC directions). The ultimate capacity of the
EPAX shall be 250 ports for flexible usage of either the subscriber lines or trunk
lines.
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
19.8.13. The line interface circuit module shall serve as an interface between the
subscriber line and the exchange whereas the trunk interface circuit module
shall serve as an interface between the tie line and the exchange. However, the
EPAX shall be possible to expand either the number of subscriber lines or tie
lines if required, at a later date, in view of the modular construction adopted.
The EPAX shall have a 32-bit microprocessor and programmable at site. The
software shall support both E&M signalling and CO trunks. The EPAX shall be
provided with universal ports wherein the Subscriber line card and CO trunk
card can be inserted into any slots. . If the ultimate capacity of the trunks has
been used and on a later date the board intends to increase the trunk capacity the
same can be done by decreasing the subscriber lines and thereby increasing the
trunks. Vice versa for subscriber lines if the ultimate capacity is reached by
reducing the trunks the subscriber lines can be increased.
19.8.14 The duplication of both the CPU and PSU is to be provided as an in-
built feature in the offered EPAX. The EPAX shall support the digital telephone
with display on a single pair of cable. The offered EPAX shall be provided with
a voice guidance card, which helps the subscriber in using, the all the features of
the exchange viz. call back etc. The EPAX shall be fully automatic and should
function without the help of an operator. The details of site programming
facility shall be provided in detail.
19.8.15. The EPAX shall have the following facilities:
a) Follow me
b) Priority interrupt/Conference
c) Automatic alternate route selection
d) Ring when free
e) Line Lock out
f) Either party release
g) Real time clock
h) Audible and visual alarm on all fault conditions.
19.8.16. The EPAX shall be self-contained and provide its own ringing current
and tones.
19.8.17. Visual display with LED’s shall be available on each line and trunk
card to display call status. Visual and audible alarms shall be provided on all
fault conditions based on the self-diagnostic routines.
19.8.18. The EPAX is to be housed in dust proof steel cabinet.
19.8.19. The EPAX works on 48V DC +15% -10% supply. The loop resistance
for subscriber lines is 1000 maximum and for Tie lines 1500 maximum.
19.8.20. The offered EPAX shall support the system software to work as an
exclusive PLCC exchange or a combination of PLCC and CO trunks or as a
network exchange on E&M. It is very important to note that these three
combinations shall be available on the system software so that the purchaser can
CHAPTER 18: TECHNICAL SPECIFICATION FOR 220V DC BATTERY AND CHARGER
switch to the exact application at the time of commissioning. The offered EPAX
shall work in conjunction with the existing EPAXs of other makes in the grid.
19.8.21. The offered EPAX shall have ISDN compatibility for the CO trunks.
The system software shall be posted on flash memory as per the latest
International standards for fast and reliable operations. The EPAX shall also
support a minimum dialling of 16 digits at a time and a maximum of 20 digits.
The EPAX shall have compatibility with E1 trunks for expansion in later stage.
It should have the software in-built for through connectivity from E1 trunk to
PLCC trunks.
19.8.22. The EPAX should be provided with universal ports for peripheral cards
so that any combination of subscribers and trunks can be selected by the user by
inserting suitable interface cards.
19.8.23. The EPAX must have been EMI/ EMC tested for the following as per
IEC 495 to suit the stringent conditions in the Sub-station environment.
1.Impulse Voltage withstand test. (IEC 255-4)
2. High Frequency disturbance susceptibility test (IEC 255-22-1)
3.Electrical Fast Transient Susceptibility Test (IEC 801-4)
4.Electrostatic discharge susceptibility test (IEC 801-2)
5.Radiated susceptibility. (IEC 801-3).
19.9.0 TECHNICAL SPECIFICATION OF HIGH FREQUENCY
COAXIAL CABLE
19.9.1 The high frequency coaxial cable shall be required to connect the line
matching unit / line matching distribution unit installed in the switchyard of the
substation to the carrier equipment installed in the carrier rooms.
19.9.2. The high frequency cable to be offered by the bidders shall be suitable
for being laid directly to the ground or in trench or ducts.
19.9.3. The cable shall be PVC sheathed and steel armoured. The capacitance
of the cable shall be low so as to minimise attenuation of the signal within
carrier frequency range. The impedance of the cable shall be so as to match the
output impedance of the PLC terminals and secondary impedance of the
coupling units. The cable shall be installed to withstand a test voltage of 4 KV.
19.9.4 Bidders shall specify attenuation per Km. of high frequency coaxial
cable at various frequencies in the range of 80 to 450 KHz.
19.9.5. High frequency cable shall be supplied on drums containing lengths of
minimum 500 metres.
TABLE-V
Sl No Description Particulars
Cable Core and Air Centre Conductor wrapped with Spaced Centre
Conductor wrapped with Spaced Radial
3
thickness:1.00 mm. Diameter over Pe tube: 5.20
mm.
6 Inner Jacket Special cable grade PVC Radial thickness 0.70 mm.
10 Electrical data:
16 Min.Bending radius 15 Cm
CHAPTER 20: TECHNICAL SPECIFICATION FOR XLPE CABLE WITH TERMINATION
20.1 SCOPE
(i) The specification covers Design, Engineering, Construction, Supply & Delivery, Erection, Laying,
Testing & Commissioning including Transportation & Insurance, Storage of XLPE Cable of different
ratings and their associated works.
Other internationally accepted standards which ensure equivalent or better performance than that specified in
the standards referred shall also be accepted. Copies of such standards shall be submitted by the bidder along
with the bid.
As a mark of technical conformance, all sheets of the specification shall be furnished by each
bidder with the signature and company seal affixed thereon. In case of any deviations, the same
shall be carried out in the deviation schedule only. Deviations not mentioned in Deviation schedule
will not be considered.
The bidder shall also submit the GTP as per Annexure-1 duly signed with date & company seal for
acceptance of the Technical Bid unless which the bid may be considered as non-responsive.
20.4 CONSTRUCTION
1. For 132KV and above: The cable shall be of applicable EHV grade as per requirement according to
price schedule, single core, unarmored, stranded compacted circular Copper conductor in case of
cross section less than or equals to 800 sq.mm or segmental compacted circular (Miliken) Copper
conductor in case of cross section over 800 sq.mm, core screening by a layer of semiconducting tape
followed by a layer of semiconducting compound, crosslinked polyethylene (XLPE) dry cured
insulation, insulation screening with semiconducting compound extruded directly over the insulation,
longitudinal sealing by a layer of non woven tape with water swellable absorbent over insulation
screen, followed by radial sealing of corrugated & seamless or seam welded aluminum with
asphalt coating & overall PE sheathed & graphite coated and conforming to the technical
particulars of specification.
For 33KV : Untinned annealed copper of class 2 as per IS 8130/1984 and any latest amendments
to it. The shape of conductor shall be compacted, stranded, and circular, shielded with conductor
screen of black extruded semi-conducting XLPE compound , XLPE insulation, shielded with
insulation screen of black extruded semi-conducting compound, black semi-conducting tape and
metallic screen of copper tape, Inner sheath extruded PVC type ST2, single layer of strip/ round
steel or round hard drawn aluminium wire armoured as per IS :7098 part II and black extruded FR
PVC (TypeST-2) overall sheathed, conforming generally to IS:7098 (PartII).
Cables used earlier or repaired after damaged shall not be accepted. IS 7098 part 3 shall be followed
for manufacturing of cable along with technical specification.
2. The construction of cable shall generally conform to the description mentioned above. Bidder
may offer necessary layers such as separation tape, binder tapes etc additionally as per their
manufacturing practices for meeting required performance of the offered cable. The bidder shall
enclose with the bid, drawing showing cross section of the cable.
3. The cable shall be suitable for laying underground with uncontrolled back fill and chances of
flooding by water and suitably designed by the addition of chemicals in the outer sheath to be
protected against rodent and termite attack.
4. The cables shall be designed to withstand all mechanical, electrical and thermal stresses under
steady state and transient operating conditions.
5. Progressive sequential marking of the length of cable in meters at every one meter shall be
provided on the outer sheath of the cable.
6. The cables shall have outer sheath of a material with an Oxygen Index of not less than 29 and a
Temperature index of not less than 250°C.
7. Allowable tolerance on the overall diameter of the cables shall be plus or minus 2mm.
8. IS 7098 part III shall be followed for cable construction.
METALLIC SCREEN:
The metallic screen shall be of Lead Alloy ‘E” as per IS 7098 Part III sheet with asphalt coating.
The metallic screen shall be designed to meet the requirement of the system short circuit rating
of 31.5KA for 3 sec (for 33KV), 40KA for 3Sec (for 132KV) and 50KA for 3 sec (for 220KV).
ARMOURING (FOR 33KV CABLE)
a) The armoring shall be of non-magnetic material.
b) Armoring shall be applied over the insulation or protective barrier or non-metallic part
of insulation screening, in case of single core cables or inner sheath in case of screened
and armoured single core cables.
c) The armour wires/strips shall be applied as closely as practicable the direction of lay of
the armour shall be left hand. For double wires/strips armoured cables, this requirement
shall apply to the inner layer of wires/strips. The outer layer shall, except in special
cases, be applied in the reverse direction to the inner layer, and there shall be a
separator of suitable non-hygroscopic material; such as plastic tape, bituminized cotton
tape, bituminized hessian tape, rubber tape, proofed tape between the inner and outer
layers of armour wires strips.
d) A binder tape may be applied on the armour.
e) The joints in armour wires of strips shall be made by brazing or welding and the surface
irregularities shall be removed. A joint in any wire/strip shall be at least 300 mm from
the nearest joint in any other armour wire/strip in the completed cable, Number of joint
in a single wire to be limited.
OUTER SHEATH
The outer sheath shall consist of extruded black colored PE of ST2 grade as per IS: 5831 (1984).
The outer sheath shall be designed for protection against termite and rodent attack and shall be
coated with graphite.
20.6 RATING
The bidder shall declare current rating of cable for maximum conductor temperature of 90 degree C
under continuous operation. A complete set of calculation made in arriving at the current rating shall
be furnished for laying condition under present.
Packing shall be sturdy and adequate to protect the cables, from any injury due to mishandling or other
conditions encountered during transportation, handling and storage. Both cable ends shall be sealed
with hermetically sealed by means of water blocking compound followed by heat shrinkable caps
totally coated inside with mastic so as to prevent to cable for moisture penetration during transit,
The bidder shall consider supply of cable on returnable drums basis. Contractor shall take back all the
cable drums from site after successful laying, testing and commissioning of cables. If any length of
cable remains unused, the same shall be adjusted by the employer.
Embossing of outer sheet: the following details on the other sheet of cable at a regular interval of 1(one)
meter.
(a) Name of Customer i.e. AEGCL
(b) Conductor size, type of insulation and voltage grade.
(c) Manufacturer’s name.
(d) Year of manufacturing
20.8 TESTS
All routine and acceptance tests shall be conducted as per IEC60840/IEC62067. All type tests
conducted during last five years from the date of NIT as per IEC 60840:1999/ IEC 62067:2001
including its amendments on the XLPE insulated HT cable should be submitted. The diameter of test
cylinder during bending test shall be as per IS:7098 (Part3) or the diameter of drum barrel to be used
for dispatch of cables which ever is lower. For accessories type test reports should be submitted as per
Clause 11.3.2 IEC 60840:1999/ Clause12.4.2 IEC62067:2001 & including amendments.
Following additional type tests shall be carried out on outer sheath of XLPE insulated HT cable.
a. Oxygen index and temperature index test as per ASTMD-2863.
b. Chemical composition test for verifying lead sheath composition.
All tests as prescribed in IEC-60840 shall be performed after installation of
cable.
TESTS AFTER INSTALLATION
All tests as prescribed in IEC-60840:1999/IEC 62067:2001 shall be performed after installation of
cable.
20.9 TRENCHING
The cable trench work involves earth excavation for cable trench, back filling and removal of
excess earth from site. The work site shall be left as clean as possible.
The trench shall be excavated using manual/ mechanical modes as per field conditions.
Where paved foot paths are encountered, the pavements labs shall be properly stored and
reinstated. Identification markers of other services shall be properly stored and restored.
The sides of the excavated trenches shall wherever required be well shored up.
Suitable barriers should be erected between the cable trench and pedestrian/motor way to prevent
accidents. The barriers shall be painted with yellow and black or red and white coloured cross
stripes. Warning and caution boards should be consciously displayed. Red lights as warning signal
should be placed along the trench during the nights.
The excavated material shall be properly stored to avoid obstruction to public and traffic
movement.
The bottom of the excavated trench should be levelled flat and from any object which would
damage the cable. Any gradient encountered shall be gradual.
20.10 PAYING OUT
The excavated cable trench shall be drained of all water and the bed surface shall be smooth,
uniform and fairly hard before paying out the cable. The cable shall be rolled in the trench on cable
rollers, spaced out of uniform intervals. The paying out process must be smooth and steady without
subjecting the cable to abnormal tension. The cable on being paid out shall be smoothly and evenly
transferred to the ground after providing the cushion. The cables shall never be dropped. All snake
bends shall be straightened. Suitable size cable stocking pulling eye shall be used for pulling the
cable. While pulling the cable by winches or machines, the tension loading shall be by tension
indicator and shall not exceed the permissible value for the cable. The cable laying shall be performed
continuously at a speed not exceeding 600 to1000 meters per hour.
The cable end seal shall be checked after laying and if found damaged shall immediately be resealed.
Sufficient number of heat shrinkable cable end sealing caps shall be stocked at site stores for testing
and jointing work. The integrity of the outer sheath shall be checked after the cable is laid in
position.
20.11 LAYING OF CABLES
The installation, testing and commissioning work for laying of cable in the entire route within the
substation, through the outside cable laying corridor as per designated approved route shall mainly
consist of:
a) Route survey for the entire route length under the scope of work. This is also to finalize
drum wise cable length with their tolerances.
b) Clearances from relevant authorities for lying of cables.
c) Formation of buried cable trenches for cables as per specification including supply and
installation of warning tape, protective tiles / brick layer of minimum class designation 50
(50kg./sq.cm.) cable protection covers for entire route, construction of jointing bays,
back filling of trenches and restoration as per specification.
d) Road, rail and canal crossings through HDPE pipe for each cable and restoration as per
specification.
e) Cable markers as per statutory requirements shall be provided all along the route at a
maximum distance of 500 meters and other important locations. Also the location of
underground cable shall be clearly indicated on the marker.
f) Supply and installation of straight through joints for complete route.
g) Design, supply and installation of suitable hangers and other necessary structures for
running the cable at over head road bridge.
h) Supply and installation of all critical installation materials like trefoil clamps, neoprene
cushions, support brackets etc. as required for complete route to avoid damages of the
cable. Neoprene cushion shall be provided at road and rail bridge crossings to avoid
damage of cable due to vibrations during movement of trains and vehicles.
i) Termination of cables, bonding of screen/sheath to the earth station through
disconnecting type link boxes and SVL (sheath voltage limiter) at cable conductor
junction-point etc. Bidder shall adopt ends bonding for route under scope as per STP or
as per detailed Engineering. Earthing stations/ Earthing pits, earthing materials and
20.13 CLAMPS
Clamps shall be pressure die cast aluminium (LM-6) or Nylon-6 or fiber glass and shall include
neoprene rubber lining wherever the cable touches the clamps and below the clamp base and
necessary fixing non magnetic nuts, bolts, washer etc. The thickness of neoprene rubber shall not be
less than 10 mm inside around the inner surface of the trefoil clamp and minimum 20 mm thick
below the base of trefoil clamp. The neoprene shall be tested as per ISIII49-1984. Clamps shall be
provided at every one meter of cable runs. The contractor shall submit drawings of trefoil clamps and
arrangements for Employer approval.
20.14 CABLE HANDLING
The inspection of cable on receipt, handling of cables, paying out, flaking, cushioning with sand or
sieved compacted soil, back-filling, reinstatement of road surface, providing and fixing joint
markers, route indicators, precautions of joint holes, sump holes and all necessary precautions that are
required shall be carefully planned and in general conform to IS1255- 1983 or its equivalent.
DAMAGE TO PROPERTY
The contractor shall take all precautions while excavation of trench, trial pits etc., to protect the
public and private properties and to avoid accidental damage. Any damages caused shall be
immediately repaired and brought to the notice of the concerned and to the Employer.
- The contractor shall bear all responsibilities and liabilities and shall bear all costs of the
damages so caused by him or by his workman or agents.
- At places where the cables cross private roads, gates of residential houses or buildings, the cables
shall be laid in HDPE pipes of adequate strength using HDD technology.
The cables shall never be bent, beyond the specified bending radius.
20.23 ROAD, RAIL & CANAL CROSSINGS
The road cutting, whether cement concrete asphalt or macadam road surface, rail crossing and canal
crossing shall be taken after obtaining approval from the concerned authorities i.e. Railway authorities,
irrigation deptt., civic authorities traffic police, telephone authorities etc. and work should be planned to
be completed in the shortest possible time. Where necessary, the work shall be planned during night or
light traffic periods. HDPE pipes shall be used for cable. HDPE pipes diameter should not be less
than1.5 times the cable diameter.
20.24 TRENCHLESS DIGGING
It is envisaged that trenchless digging shall be used for crossing National highways, Rail line and canal
and this shall be in the scope of bidder. Trenchless digging shall also be used where the concerned
authorities do not permit open cut method and it is essentially required to carry out for installation of
underground cables. The trenchless digging methods shall generally conform to ITU-T 1.38. The
various methods of trenchless digging such as hand/ manual auguring (upto15m.) impact moulding
(from 16m to about 40-50m.).HDD (above40-50m) shall be adopted based on the soil/ site
conditions and the requirement and exact method for trenchless digging shall be finalized during detail
engineering as per actual site/ soil condition. The equipment used for HDD shall be capable of
drilling at least 100m at one go. The contractor shall propose the exact methods and procedures for
implementation of trenchless digging at various crossings taking into consideration the following
guidelines, for approval by the Employer.
1. Guided boring/drilling technology is to be used.
2. Radio or any detection system should be used for avoiding damage to
existing underground utilities.
3. The depth of boring should be such as to clear any underground
utilities/obstacles. However in no case the depth of boring shall be less
than 1.65m from the road surface.
4. In horizontal and vertical boring, the system should be capable of going
up to 10 meter below ground.
5. The span of HDD will be decided in charge as per site requirements.
6. Excavation and back filling of trial pits and verification of soil condition.
7. Excavation of entry and Exit pits.
8. Erection of drill machined. Drilling of pilot hole.
9. Placement and driving hand augur.
10. Placement and carrying out impact moling.
11. Reaming and widening of bore holes in steps (if required).
12. Pulling of product pipe.
The temporary reinstatement of roadways should be inspected at regular intervals, more frequently in
rainy season and immediately after overnight rain for checking settlement and if required the temporary
reinstatement should be done.
After the subsidence has ceased the trench may be permanently reinstated and the surface restored to the
best possible condition.
20.27 MANHOLES
Manholes shall be provided at every proposed joint location for jointing bays. The bidder shall
identify the location of the joint bays after carrying out detailed survey of the cable route and
excavation of the trial pits. The delivery lengths of the cables shall match the location.
The Contractor shall get inspected by a representative of the Employer, all manholes before carrying
out the backfilling. Pipe and cable sealing, installation of joint bus and cable service loops as per
approved drawings shall be visually inspected and checked for tightness.
The contractor shall submit design and drawing of Jointing bay including manholes in the buried
cable trench portion for withstanding a live load of 20 tons vehicle plus 30% for impact from
moving vehicle. The Contractor shall propose a suitable procedure for testing the manhole for
approval by the Employer. Manholes type approved by the Employer only shall be acceptable. The
manhole shall include sufficient number of suitable entries.
All works shall be carried out under supervision of the engineer in charge of his representative.
20.28 TOOLS AND PLANTS
The successful bidder shall have all necessary tools, plant and equipment to carry out the survey and
cable installation work.
The bidders are instructed to give all the details of equipment at their disposal to carryout the work
successfully and speedily.
20.29 BENDING RADIUS:
The cable jointing accessories shall include the end terminating kits, straight through joints and
also any special tools and tackles required for making these joints.
The straight through joints shall be either Pre-molded Heat Shink type complete with all
accessories. The joint shall preferably be built up as per the construction of the main cable and
shall have electrical and mechanical withstand capabilities same as or better than the main cable.
The joints shall be suitable for tropical climatic conditions.
The outdoor end termination up to 245 KV XLPE Cable shall be Anti-fog, Pre-molded type
Silicon Rubber stress cone. Torque controlled mechanical shear head bolted connector with
polymeric composite housing (resin cast body with silicon shed housing), dry type self-supporting
with Plug-in / Plug-out facilities. The termination base plate and the cable's metallic sheath shall
be electrically insulated from the self supporting structure by means of stand-off epoxy insulators
designed to withstand both mechanical and electrical stresses in services. The Polymeric insulator
in grey colour shall be used. In addition upon, arcing horn and shield ring shall have to be supplied
as required for 245 & 420 KV XLPE cables.
The outdoor end termination for 400kV shall be based on the Silicon / EPR-based stress relief cone
with the epoxy housing and the oil-impregnated cylindrical capacitor cone (so called condenser
cone type) to secure the uniform longitudinal voltage distribution all along the termination. Pre-
molded type Silicon Rubber sleeve outdoor end termination for 400kV may be offered by the
manufacturer if the same is available.
The outdoor terminals should be suitable for heavily polluted atmospheric conditions with total
creepage distance of 31 mm/ kV and protected creepage distance of not more than 50% of the total
creepage distance. The cable end terminals for terminating the cables shall be fully compatible
with the cables to be supplied.
The Indoor Termination at GIS SF6 Housing shall be based on the Silicon Rubber based stress
relief cone and the epoxy resin housing. There shall be mechanical devices to maintain the
interface pressure. Stress relief cone and mechanical devices shall be designed to fit with
controlled interference over the cable insulation and shall follow the cable's diameter variations
still guaranteeing under any service condition a sufficient positive pressure to control the electric
field concentration. There shall be epoxy insulating plate to isolate between cable sheath and GIS
chamber. The SVLs (Sheath Voltage Limiter) shall be installed to protect epoxy insulating plate
from switching impulse. Plug-in type leading conductors shall be supplied though at the time of
detailed engineering confirmation shall be given for selection of plug-in type. Design and scope of
delivery shall be fully complying with IEC-60859, IEC-62271-209 and possibly adjusted to
various needs of project. The main insulation components shall be fully examined and tested in the
factory.
The detailed description on jointing procedure shall be furnished during detailed engineering.
The details of the performance of end terminations / straight through joints as offered with the
period in service in reputed Indian Utility should be furnished for 145 KV & 245 KV and reputed
International/ Indian utility for 420 KV Cable accessories for evaluation of the techno-commercial
offer.
The accessories shall be Type Tested as per relevant IEC 60840 & Type test report shall have to be
furnished for technical evaluation.
(i) At cable terminating end sufficient length of spare cable shall be left in the ground
and at cable tray also at GIS, for future needs.
(ii) The rise of the cable immediately from the ground shall be enclosed in PVC/ PE pipe of
suitable diameter to protect against direct exposure to the sun.
(iii) The cable shall be properly fastened using non-metallic clamps.
(iv) Appropriate labels shall be fixed identifying the phase circuit, voltage and date of
commissioning etc., on the cable supporting structure.
(v) The sealing end shall be mounted on pedestal insulators to isolate them from their
supporting steel work.
(vi) Protection from contact with the exposed metal work at the termination shall be
provided by resin bonded glass fiber shroud.
(vii) Providing earth stations with all required materials, like leads, connectors etc. Earth
The screens at both ends, shall be brought out and bonded to the earth station through
disconnecting type link boxes or through SVL wherever applicable.
On the basis of the length of the cable and rise of sheath Voltage the bonding maybe required as
follows:
1. Single End Bonding
2. Double End Bonding
3. Cross Bonding
4. Mid point bonding
All accessories and consumables used in the termination should be of good quality and compatible
with the cable. At the time of single end bonding parallel copper conductor along the length of the
cable shall have to be provided between the two ends of the cable. Bonding cable of 6.6KV copper
shall be provided for bonding of metallic sheath/ Screen.
20.32 CONNECTION OF RADIAL WATER BARRIER AND CABLE SCREEN
If the metallic radial water barrier is insulated from the metallic wire screen a connection suitable
to carry the currents occurring during operation must be installed between metallic radial water
barrier of the cable and metallic wire screen in joints and sealing ends.
20.33 STATUATORY APPROVAL OF WORKS
Contractor shall make an application on behalf of the owner for submission to the Electrical
Inspectorate along with copies of required certificates complete in all respects and submit to the
engineer-in-charge for onward transmission well ahead of time so that the actual commissioning of
system/ equipment is not delayed for want of inspection by the Inspector. Contractor shall arrange
the actual inspection of work by the Electrical Inspector. Necessary coordination and liaison work
in this respect shall be the responsibility of the contractor.
The Inspection and acceptance of work as above shall not absolve the Contractor from any of his
responsibilities under this contract.
Any other statutory approval of works required for the electrical installation (such as Factory
Inspector, CCOE, etc.) is also included in contractor’s scope.
Supply & execution of job is subjected to regulations time to time framed by the AERC; approval
Govt. Of Assam, and NOC from Assam Pollution Control Board. Contractor shall complete the
entire job in compliance with the same.
20.34 INSPECTION, TESTING AND COMMISSIONING
Inspection of Supplied materials and Site works time to time during execution: Inspection of
AEGCL and clearance from AEGCL will be in Contractor responsibility. Expenditure related to
this inspection will be in contractor account. Site inspection, testing and commissioning of
electrical installation shall be carried out as per enclosed Specification and Inspection and Test
Plans included or referred in this BID. All the equipment installed by the contractor shall be tested
and commissioned, as required and no separate payments shall be made unless otherwise specified
in the Schedule of Rates. Contractor shall carefully inspect all equipment and submit the
manufacturer’s Certificate before installation. Any damage or defect noticed shall be brought to
the notice of the engineer-in-charge at that time and same shall be rectified or replaced by
CONTRACTOR on his OWN RISK AND COST within TIME FRAME. Complete testing of
power transmission system would be carried out under the supervision of the Employer.
Any work not conforming to the execution drawings, specifications or codes shall be rejected
forthwith and the contractor shall carry out the rectification at his own cost.
The contractor shall carry out all the tests as enumerated in the tender and technical
specifications and technical documents which may be furnished to him during performance of
the work.
Before the electrical system is made live, the electrical contractor shall carry out suitable tests
to establish to the satisfaction of the Employer that the installation of equipment, cabling/
wiring and connections have been correctly done and are in good working condition and that
the system/ equipment will operate as intended.
All tests shall be conducted in the presence of Employer/ Engineer-in-Charge or his authorized
representative unless he waives this requirement in writing. Contractor shall arrange testing
equipment, as required to carry out the tests. Test results shall be recorded on approved
Performa and certified records of the tests shall be submitted to the Employer/ Engineer-in-
Charge.
Prior intimation to be given to the Employer before finalizing of date of scheduled inspection at
least 15 days in advance.
Clearance in favour of contractor for dispatch of equipment/material from respective works of
manufacturer will be covered by the Employer after physical inspection and witnessing
satisfactory routine and acceptance tests. Contractor will have to arrange physical inspection
and witnessing of Routine and Acceptance Test of materials/equipments at respective
manufacturer’s works by two engineer of the Employer and cost of such inspection shall have
to be borne by contractor. Clearance for dispatch of equipments & materials from respective
works of manufacturers will be conveyed by the Employer after verification and acceptance
thereafter.
After the completion of all tests and rectification of all defects pointed out during final
inspection, plant start-up trials shall commence. During the start-up trials, contractor shall
provide skilled/ unskilled personnel and supervision round the clock at his own cost. The
engineer-in-charge/Employer will decide the number and the category of workmen and their
duration. Any defects noticed during the start-up trials relating to the equipment supplied and
work carried out by the contractor, shall be rectified by the contractor at his own cost.
The Employer shall have the right to get the defects rectified at the risk and cost of the
contractor if he fails to attend to the defects immediately as desired.
Contractor shall also inform the Employer/ Engineer-in-charge, well in advance in case services
of any OEM (Equipment manufacturer) are required and same shall be arranged by Contractor
at the time of commissioning on his own cost.
Contractor shall furnish site acceptance test (SAT) procedures from the equipment supplier and
get it approved from the Employer/ Engineer-in-charge before carrying out the same at site.
Contractor shall prepare detailed testing, pre-commissioning and commissioning procedures for
the entire installation. These shall include Performa for defining activities and recording of test
results.
It is the responsibility of the contractor to coordinate and provide all necessary assistance to
other contractors / agencies/ vendors involved in the complex for proper and timely execution
of the works. Further contractor shall do all the liaisoning, documentation or other related
formalities with respective authorities/agencies for successfully charging/commissioning of
system.
The following equipment/ items as included in Contractor’s scope of supply shall be tested and
inspected by the Employer or his authorized representative before dispatch at the
manufacturer’s works. Test certificates duly signed by the Employer or his authorized
representative shall be submitted by the contractor as part of the final document:
a) EHV cable & optical fiber cables.
b) Jointing & termination kits for above items
20.35 ENGINEERING DATA AND DRAWINGS
The Bidder shall necessarily submit all the drawings/ documents unless anything is waived. The
Bidder shall submit 4(four) sets of drawings/ design documents/ data/ test reports as may be
required for the approval of the Employer.
All drawings submitted by the Bidder including those submitted at the time of bid shall be in
sufficient detail to indicate the type, size, arrangement, material description, Bill of Materials,
weight of each component, break-up for packing and shipment, dimensions, internal and the
external connections, fixing arrangement required and any other information specifically
requested in the specifications.
All engineering data submitted by the Bidder after final process including review and
approvalbytheEmployershallformpartoftheContractDocumentandtheentireworks performed
under these specifications shall be performed in strict conformity, unless otherwise expressly
requested by the Employer in Writing.
a. To ensure that the equipment and services under the scope of this Contract whether
manufactured or performed within the Bidder’s Works or at his sub-bidder’s premises or at
the Employer’s site or at any other place of work are in accordance with the specifications,
the Bidder shall adopt suitable quality assurance programme to control such activities at all
points necessary. Such programme shall be outlined by the Bidder and shall befinally
accepted by the Employer after discussions before the award of Contract.
b. Quality Assurance Documents
The Bidder shall be required to submit the following Quality Assurance Documents within three
weeks before laying/ erection of the equipment.
(i) All Non-Destructive Examination procedures, stress relief and weld repair procedure
actually used during fabrication and reports including radiography interpretation
reports.
(ii) Welder and welding operator qualification certificates.
(iii) Welder’s identification list, listing welder’s and welding operator’s qualification
procedure and welding identification symbols.
(iv) Raw material test reports on components as specified by the specification and/or agreed
to in the quality plan.
(v) Stress relief time temperature charts/ oil impregnation time temperature charts.
(vi) Factory test results for testing required as per applicable codes/ mutually agreed quality
plan/ standards referred in the technical specification.
(vii) The quality plan with verification of various customer inspection points (CIP) as mutually
agreed and methods used to verify the inspection and testing points in the quality plan were
performed satisfactorily.
5. Equipment furnished shall be complete in every respect with all mountings, fittings,
fixtures and standard accessories normally provided with such equipment and/or needed
for erection, completion and safe operation of the equipment as required by applicable
codes though they may not have been specifically detailed in the Technical
Specifications unless included in the list of exclusions. Materials and components not
specifically stated in the specification but which are necessary for commissioning and
satisfactory operation of the work unless specifically excluded shall be deemed to be
included in the scope of the specification and shall be supplied without any extra cost.
All similar standard components/ parts of similar standard equipment provided shall be
inter-changeable with one another.
A) The contractor shall assume full responsibility for supply, fabrication and detailing, if
required of the steel structures and for their satisfactory performance. All detail
drawings for the structures shall be supplied to the successful bidder by the
Employer/Engineer. However, the contractor shall have to submit the construction
drawings to the Engineer/Employer solely prepared on the basis of these supplied
drawings. Equipment Structure drawings, supplied by the employer, shall have to be
modified to suit to the approved GA drawings of the equipment and electrical layout
drg. And to be submitted to Engineer for approval. Employer/ Engineer shall have the
right to instruct the contractor to make any changes in details necessary to make the
construction conform to the requirement of the Contract Document.
B) The contractor shall supply all materials, deliver the same to site, and provide all labour,
erection plant and equipment, fixtures, fitting and all temporary and permanent works
necessary for satisfactory completion of the job in all respects.
All Structural Steel Materials to be used in construction within the purview of the
specification shall comply with :IS:2062 –Structural Steel (Grade-A) (fusion welding quality)
and manufactured by Prime Rollers e.g. SAIL/ TISCO/ IISCO/ RINL. In case of MS sections
not manufactured by prime rollers or such sections are not available with prime rollers the
same is to be procured from approved conversion agents of prime manufacturer(s).In such
case, prior approval of the Engineeris to be obtained by the contractor.
Successful bidder on receipt of structural drawing from department shall submit within 15
days, a detailed raw material procurement plan indicating MS sectionwise producers name to the
Engineer for approval. On according approval in this aspect, work for fabrication protos shall
be taken up in hands.
Entire fabrication job of MS structural shall not be entrusted to more than two sub- vendors.
Further, a list of bonafide fabricators, not exceeding 6 (six) shall be furnished to the
Engineer for according approval within 15(fifteen) days from the date of handing over of
drawings.
All electrodes to be used under the contract shall comply with any of the following Indian
Standard Specifications as may be applicable.
i) IS:814: Covered electrodes for metal arc welding of Structural Steel.
ii) IS:815: Classification and coding of covered electrodes for metal arc welding of mild steel
and low alloy high tensile steel.
iii) IS:144: Covered electrodes for the metal arc welding of high tensile structural steel.
All bolts and nuts shall be of grade 5.6HRH and shall conform to the requirements of IS:6639
and IS:1367 and galvanizing quality shall be as per IS:1367. All bolts and nuts shall be of
minimum diameter of 16mm unless otherwise stated. All mildsteel for bolts and nuts when
tested in accordance with the following Indian Standard specification shall have a tensile
strength of not less than 44Kg/Sq.mm. and a minimum elongation of 23 percent on a gauge
length of 5.6A, where `A' is the cross sectional area of the test specimen-
Washers shall be made of steel conforming to IS:226, IS:961 as may be applicable under the
provisions of the contract and shall be electrogalvanized.
7 FASTNERS & CONNECTIONS:
a) BOLTS: All connections shall be bolted with 16mm bolts.
b) SPLICES: Splicing shall be avoided unless the length of a member exceeds 6.0 m or so. The
member of splices shall be limited to a practical minimum. No credit shall be allowed for
bearing on a butting areas. Lap joints in leg members shall be preferred to butt joints.
c) STEP BOLTS: Step bolts shall be of 16mm diameter and shall have round or hexagonal head.
Each step bolt shall be provided with two hexagonal nuts. The minimum bolt length and
length of unthreaded portion shall be 180 and 125mm respectively. Step bolts shall not
be used as connection bolts. The step bolts shall be spaced alternately on the inner
gaugelineoneachfaceoftheangleabout40cmcenters.Theyshallbefurnished for one leg of each
steel structure column from its base elevation.
e) BILL OF MATERIAL: Bill of material shall give the size, length and weight of each
member and the total weights of steel structures. It shall also include the number of bolts,
nuts and washers per structure.
Where the specification does not contain references to workmanship, equipment, materials
and components of the covered equipment, it is essential that the same must be new of highest
grade of the best quality of their kind conforming to best engineering practice and suitable for
the purpose for which they are intended.
In case where the equipment, materials or components are indicated in the specification as
“similar” to any special standard, the Employer shall decide upon the question of similarity.
When required by the specification or when required by the Employer the Bidder shall
submit, for approval, all the information concerning the materials or components to be used in
manufacture, Machinery, equipment, materials and components supplied, installed or used
without such approval shall run the risk of subsequent rejection, it being understood that the
cost as well as the time delay associated with the rejection shall be borne by the Bidder.
The design of the Works shall be such that installation, future expansions, replacements and
general maintenance may be undertaken with a minimum of time and expenses. Each
component shall be designed to be consistent with its duty and suitable factors of safety, subject to
mutual agreements. All joints and fastenings shall be devised, constructed and documented so
that the component parts shall be accurately positioned and restrained to fulfill their required
function. In general, screw threads shall be standard metric threads. The use of other thread
forms will only be permitted when prior approval has been obtained from the Employer.
Whenever possible, all similar part of the Works shall be made to gauge and shall also be
made interchangeable with similar parts. All spare parts shall also be interchangeable and
shall be made of the same materials and workmanship as the corresponding parts of the
Equipment supplied under the Specification. Where feasible, common component units shall be
employed in different pieces of equipment in order to minimize spare parts stocking
requirements. All equipment of the same type and rating shall be physically and electrically
interchangeable.
All materials and equipment shall be installed in strict accordance with the manufacturer’s
recommendation(s). Only first-class work in accordance with the best modern practices will be
accepted. Installation shall be considered as being the erection of equipment at its permanent
location. This, unless otherwise specified, shall include unpacking, cleaning and lifting into
position, grouting, leveling, aligning, coupling of or bolting down to previously installed
equipment bases/ foundations, performing the alignment check and final adjustment prior to
initial operation, testing and commissioning in accordance with the manufacturer’s tolerances,
instructions and the Specification.
Provision for Exposure to Hot and Humid climate: Outdoor equipment supplied under the
specification shall be suitable for service and storage under tropical conditions of high
temperature, high humidity, heavy rainfall and environment favourable to the growth of fungi
and mildew.
20.40PACKAGING & PROTECTION
a. All the equipment shall be suitably protected, coated, covered or boxed and crated to
prevent damage or deterioration during transit, handling and storage at Site till the time
of erection. On request of the Employer, the Bidder shall also submit packing details/
associated drawing for any equipment/ material at a later date, in case the need arises.
While packing all the materials, the limitation from the point of view of availability of
Railway wagon sizes in India should be taken into account. The Bidder shall be
responsible for any loss or damage during transportation, handling and storage due to
improper packing. Any demurrage, wharf age and other such charges claimed by the
transporters, railway etc. shall be to the account of the Bidder. Employer takes no
responsibility of the availability of the wagons.
b. All coated surfaces shall be protected against abrasion, impact, discoloration and any other
damages. All exposed threaded portions shall be suitably protected with either a metallic or
a non-metallic protecting device. All ends of all valves and piping and conduit
equipment connections shall be properly sealed with suitable devices to protect them
from damaged. The parts which are likely to get rusted, due to exposure to weather
should also be properly treated and protected in a suitable manner.
a.All metal surfaces shall be subjected to treatment for anti-corrosion protection. All
ferrous surfaces for external use unless otherwise stated elsewhere in the specification or
specifically agreed shall be hot-dip galvanized after fabrication. High tensile steel nuts and
bolts and spring washers shall be electro galvanized to service condition. All steel
conductors including those used for earthing/grounding (above ground level) shall also be
galvanized accordingtoIS:2629.
The minimum weight of the zinc coating shall be 610gm/sq.m and minimum thickness of
coating shall be 85 microns for all items thicker than 6mm. For items lower than 6mm
thickness requirement of coating thickness shall be as per relevant ASTM. For surface, which
shall be embedded in concrete the zinc coating shall be 610gm/sqm minimum.
The galvanized surfaces shall consist of a continuous and uniform thick coating of zinc firmly
adhering to the surface of steel. The finished surface shall be clean and smooth and shall be free
from defects like discoloured patches bare spots, unevenness of coating, spelter which is loosely
attached to the steel globules, spiky deposits, blistered surface, flaking or peeling off etc. The
presence of any of these defects noticed on visual or microscopic inspection shall render the
material liable to rejection.
After galvanizing no drilling or welding shall be performed on the galvanized parts of the
equipment excepting that nuts may be threaded after galvanizing. Sodium dichromate treatment
shall be provided to avoid formation of white rust after hot dip galvanization.
The galvanized steel shall be subjected to six one minute dips in copper sulphate solution as per IS-
2633.
Sharp edges with radii less than 2.5mm shall be able to withstand four immersions of the
Standard Preece test. All other coatings shall withstand six immersions. The following
galvanizing tests should essentially be performed as per relevant Indian Standards
- Coating thickness
- Uniformity of zinc
- Adhesion test
- Mass of zinc coating
Galvanized material must be transported properly to ensure that galvanized surfaces are not
damaged during transit. Application of zinc rich paint at site shall not be allowed.
c. PAINTING
All sheet steel work shall be degreased, pickled, phosphate in accordance with the IS-6005 “Code of
practice for phosphating iron and sheet”. All surfaces which will not be easily accessible after
shop assembly shall be forehand be treated and protected for the life of the equipment.
The surfaces, which are to be finished painted after installation or require corrosion protection
until installation shall be shop painted with at least two coats of primer. Oil, grease, dirt and
swaf shall be thoroughly removed by emulsion cleaning. Rust and scale shall be removed by
pickling with dilute acid followed by washing with running water, rinsing with slightly alkaline
hot water and drying.
After phosphating, thorough rinsing shall be carried out with clean water followed by final
rinsing with dilute dichromate solution and oven drying. The phosphate coating shall be sealed
with application of two coats of ready mixed, stoving type zinc chromate primer. The first coat
may be “flash dried” while the second coat shall be stoved.
After application of the primer, two coats of finishing synthetic enamel paint shall be applied
each coat followed by stoving. The second finishing coat shall be applied after inspection of first
coat of painting.
The exterior color of the paint shall be as per shade no: 697 of IS-5 and inside shall be glossy
white for all equipment, marshalling boxes, junction boxes, control cabinets, panels etc. unless
specifically mentioned under respective sections of the equipments. Each coat of primer and
finishing paint shall be slightly different shade to enable inspection of the painting. A small
quantity of finishing paint shall be supplied for minor touching up required at site after
installation of the equipments.
In case the Bidder proposes of follow his own standard surface finish and protection procedures
or any other established painting procedures like electrostatic painting etc. the procedure shall be
submitted along with the Bids of Employer’s review and approval.
20.42 HANDLING, STORING AND INSTALLATION
g.The design and workmanship shall be in accordance with the best engineering practices to
ensure satisfactory performance throughout the service life. If at any stage during the
execution of the Contract, it is observed that the erected equipment(s) do not meet the above
minimum clearances as given in clause 4.7.1 the Bidder shall immediately proceed to correct the
discrepancy at his risks.
132KV Suspension and Tension Insulator Hardware Fittings with Insulators: will be as per standard
technical specification of Sub-Station Projects of AEGCL.
The contractor shall establish and maintain quality control procedures for different items of
work and materials to ensure that all work is performed in accordance with the specifications
and best modern practice.
In addition to the Contractor's quality control procedures, materials and workmanship at all
times shall be subjected to inspection by the Engineer. As far as possible all inspection by the
Engineer or Engineer's representative shall be made at the Contractor's fabrication shop whether
located at site or elsewhere. The contractor shall cooperate with the Engineer in permitting
access for inspection to all places where work is being done and in providing free of cost of all
necessary help in respect of tools and plants, instrument, labour and material required to carry
out the inspection. Materials or workmanship not in reasonable conformance with the
provisions of this specification may be rejected at any time during the progress of the work.
The quality control procedure shall cover but not be limited to the following items of work :
i)Steel: Quality, manufacturer's test certificates, test reports including procurement in-voice of
representative samples of materials from unidentified stocks if permitted to be used.
ii) Bolts, nuts & Washers: Manufacturer's certificate, dimension check, material testing
iv) Welds: Inspection, X-ray, ultrasonic test, magnetic particle tests as required
vi) Galvanizing: Tests in accordance with IS:2633 – Method of testing uniformity of coating on
zinc coated articles and IS:2629 Recommended practice for hot - dip galvanizing of iron and
steel. Raw zinc & samples collected from bath shall be tested at third party laboratory as
per direction of the Engineer.
The contractor shall submit a detailed material inspection plan on the basis of various IS codes
& standard practices in respect of structural fabrication, galvanization, bolts, nuts, anchor bolts
etc. much prior to commencement of the job.
20.44 FABRICATION WORKMANSHIP:
All workmanship shall be equal to the best practice in modern structural shop and shall conform
to the provisions of IS:800/ IS:802.
Rolled materials before being laid off or worked, must be clean free from sharp kinks, bends, or
twists and straight within the tolerances allowed by IS:1852. If straightening is necessary it may be
done by mechanical means or by the application of a limited amount of localised heat not
exceeding 600oC.
Cutting shall be effected by shearing, cropping or sawing. Use of mechanically controlled Gas
Cutting Torch may be permitted for mild steel provided special care is taken to leave sufficient
metal to be removed by machining, so that all metal that has been hardened by flame is
removed. To determine the effective size of members cut by gas, 3mm shall be deducted from
each cut edge.
The erection clearance for cleated ends of members connecting steel to steel shall preferably be
not greater than 2mm at each end. The erection clearance at ends of beams without cleats shall
not be more than 3mm at each end, but where for practical reasons greater clearance is
necessary, suitably designed clearance shall be provided.
All members shall consist of rolled steel sections.
Holes for bolts shall not be more than 1.5mm larger than the diameter of the bolt passing
through them unless otherwise stated.
All members shall be cut to jig and all hole shall be punched and drilled to jig. All parts shall be
carefully cut and holes accurately located after the members are assembled and tightly clamped
or bolted together.
Drifting or rimming of holes shall not be allowed. Holes for bolts shall not be formed by gas
cutting process.
Punching of holes will not be permitted for M.S. members upto 8mm thick and in no case shall
a hole be punched where the thickness of the material exceed the diameter of the punched hole.
Minimum bolt spacing and distances from edges of members shall in accordance withthe
provisions in the relevant Indian Standard Specification.
Built members shall, when finished, be true and free from all kinds of twists and open joints
and the material shall not be defective or strained in any way.
All bolts shall be galvanized including the threaded portion except the foundation bolts for
which galvanizing work shall be done for a length of 100mm (min) to 175mm (max) measured
from the tip of the treaded portion. The threads of all bolts shall be cleared of smelter by
spinning or brushing. A die shall not be used for cleaning the threads unless specially approved
by the Engineer. All nuts shall be galvanized with the exception of the threads which shall be
oiled. In case of foundation bolts the same shall be galvanized excepting the length of
embedment.
When in position all bolts shall project through the corresponding nuts but not exceeding 10
mm. The nuts of all bolts attaching insulator sets and earth conductor clamps to the structure
shall be carefully positioned as directed by the Engineer.
Bolts and nuts shall be placed in such a way so that they are accessible by means of an ordinary
spanner.
Foundation bolts shall be fitted with washer plates or anchor angles and flats, nuts etc. and shall
be manufactured from mild or special steel.
Washers shall be tapered or otherwise suitably shaped, where necessary to give the heads and nuts
of bolts a satisfactory bearing. The threaded portion of each bolt shall project out through the
nut at least by 3mm. In all cases the bolt shall be provided with a washer of sufficient thickness
under the nut. In addition to the normal washer, one spring washer or lock nut shall be provided
for each bolt for connections subjected to vibrating forces or otherwise as may be specified in
the drawings.
The thickness of spring washer shall be 3.5 mm for bolt diameter 16 mm and 4 mm for bolt
diameter 20 mm.
20.45 CLEANING & GALVANIZING:
CLEANING:
After fabrication has been completed and accepted, all materials shall be cleared off rust, loose
scale, dirt, oil grease and other foreign substances.
GALVANIZING:
All materials shall be hot-dip galvanized after fabrication and cleaning. Re tapping of nuts after
galvanizing is not permitted.
Galvanizing for structural mild steel products shall meet the requirements of IS:4759. All holes
in materials shall be free of excess spelter after galvanizing.
Galvanizing for fasteners shall meet the requirements of IS:1367. The spring washers shall be
electrogalvanized as per IS:1573.
Finished materials shall be dipped in to the solution of dichromate after galvanizing for white rust
protection during transportation.
All galvanizing shall be uniform and of standard quality. Quantity of zinc shall meet the
requirement of IS:209.
Mass of Zinc Coating:
The mass of zinc coating for different class of materials, as given in Table below, shall be
followed:
MASS OF ZINC COATING
Sl. No. Product Electro meter Minimum value of
reading (micron) average mass of
coating
i) Casting - gray iron, malleable iron 610 (gm/m2)
ii) Fabricated steel articles :
a) 5 mm thick and over 86 610
b) Under 5 mm, but not less than 2 mm 65 460
c) Under 2 mm, but not less than 48 340
1.2mm
Threaded work other than tubes and
iii)
tube fittings :
a) 10 mm dia and over 43 300
b) Under 10 mm dia 39 270
Materials on which galvanizing has been damaged shall be acid stripped and re-galvanized, unless,
in the opinion of Engineer, the damage is local and can be repaired by zinc spraying or by
applying a coating of galvanizing repair compound. Where re-galvanizing is required, any
member which become damaged after having been dipped twice shall be rejected.
SHOP ASSEMBLY:
One of each type of steel structures shall be assembled in the shop to such an extent as to ensure
proper field erection in order to facilitate inspection by the Engineer.
SHOP TEST:
The following shop tests shall be performed with relevant provisions of I.S. Codes :
a) General Inspection
b) Material test.
c) Assembly test.
d) Galvanizing test.
The contractor shall furnish four certified copies of reports of all tests to the Engineer.
20.46 FOUNDATION
WORKS:
GENERAL REQUIREMENT:
The design of RCC foundation for gantry and other equipment structures to be constructed shall
be the responsibility of the contractor. All design of RCC foundation works shall conform to IS:
456 (2000) unless otherwise mentioned herein. All designs and details shall be subject to approval
of the Engineer. Effect of additional surcharge due to earth filling shall duly be taken into
account during design.
However, detailed foundation design shall be based on the actual soil parameters which shall be
ascertained by the intending bidder. Any variation in design of foundations due to change in
soil parameters during execution of work shall not affect the terms of the Contract. No extra
payment on account of any change what so ever in soil parameters will be entertained.
20.47 DESIGN OF FOUNDATIONS:
The foundations shall be designed such that the upper structure shall be securely supported. Any
unequal displacement that may cause harmful effect to the upper structures shall not be
allowed. The safety factors for strength and stability of the foundations shall be as per relevant
code.
The overload factor shall be taken as 1.1 for designing foundations of all gantry and equipment.
The loads, shear and moment values shall be multiplied with this overload factor, so as to
obtain the design values.
20.49 ELECTRO-MECHANICAL EQUIPMENT FOUNDATIONS:
The foundation shall be so designed that the upper equipment shall be securely supported. The
effect of vibration of the equipment, impact load when in operation and over turning force due
to abnormal condition of equipment shall be considered in foundation design. The safety factor for
stability of the foundations shall be as per relevant code with an overload factor of 1.1.
Following minimum values shall be used while designing foundations :
Detail design calculations for each type of foundation shall be submitted for approval of
Engineer. Such details shall show the following requirements.
The contractor shall set all lines and grades or elevation of the ground at all footings and
set the necessary stakes that are required for the work and will be responsible for their
accuracy. Employer/ Engineer may check lines and levels set by the Contractor from time to
time, and inadequacies if any, shall be rectified by the contractor as per the direction of the
Engineer, but the responsibility for their accuracy shall rest entirely with the Contractor.
C) DETAIL DRAWINGS:
Details of each type of foundation submitted for Employer's/ Engineer's approval shall be as
shown on the approved design drawings and shall conform to the requirements described
hereafter. No change shall be made without the written approval of Employer/ Engineer. The detail
drawings shall include but not limited to the following:
i) Detail dimensions of foundation.
ii) Details of setting dimensions of foundation.
iii) Details of placing of all reinforcing steel which shall conform to the
Building Code Requirements for Reinforced Concrete (IS:456) and the
Manual of Standard Practice for Detailing Reinforced Concrete Structure
unless otherwise specified herein.
iv) Details of type size and length of each reinforcing steel including
schedule of bar bending to be submitted to the Engineer at site
This section describes the functional requirements, major technical parameters and Type
testing, Factory Acceptance Testing & Site Acceptance Testing requirements for underground
fibre optic cables and HDPE pipes. Marking, packaging, transportation & installation
requirements have also been described. The payment will be made for the executed route length
only. However, specified service loops and lengths for wastage, installation/working for FO
cable & HDPE ducts shall be considered as required by the bidder for which no additional
payment will be made.
20.52.1 General
The underground fibre optic cable shall be armoured and shall be suitable for direct burial as
well as for underground installation in pipes. The cable should be of low weight, small volume
and high flexibility. The mechanical design and construction of each unit shall be inherently
robust and rigid under all condition of operation, adjustment, replacement, storage and
transport. The fibre optic cable shall be a UV resistant, rodent proof. The underground fibre
optic cable (UGFO) shall be offered from a manufacturer who has been manufacturing UGFO
for the last five (5) years and UGFO manufactured & supplied by such manufacturer shall have
been in satisfactory operation.
20.52.2 Applicable Standards
The cable shall conform to the standards named below and the technical specifications
described in the following sections.
i). ITU-T Recommendations G.652
ii). Electronic Industries Association, EIA/TIA 455-78A, 455-3A/33/41/25A /
81A / 82B, 455-62A, 455-164A/167A/174, 455-168A/169A/170/175A, 455-
176, 455-59, EIA/TIA 598, EIA 455- 104.
iii) International Electro technical Commission standards, IEC60304, IEC60794-
1-2, IEC60811-5-
iv) Bellcore GR-20
v) Indian Railways standard specification no IRS:TC55(Oct 96) (including all
amendments)
vi) ASTM:A167-92,ASTM:751-92b,ASTM:A751-92,ASTM:A370-
82,ASTM:D2581-
91,ASTM:D2287-81, ASTM:D 638 for FRP, ASTM :D 217,556, 93-IP-34
for Jelly, ASTM:D
570,211 for PBTP, ASTM:D1505for Poly Carbonate, ASTM:D1633,150 for
HDPE.
20.52.3 Fibre Type(s) and Counts
The Cable shall consist of 24 fibres Dual-Window Single mode (DWSM), G.652 optical
fibres and shall meet the requirements stipulated in Table 1
DWSM Optical Fibre Characteristics(Table-1)
Cladding non-circulatory ≤ 1%
1300 to 1324 nm
Zero Dispersion Wavelength:
0.092 ps/(nm2xkm) maximum
Zero Dispersion Slope:
service life span of 25 years. The cable construction and mechanical parameters for the
Armoured OFC shall be as specified in the Table 2 below.
Table 2
Armoured Cable Construction and Mechanical Parameters
Strength Members
The armoured optical fibre cable shall have solid non-metallic strength member(s)/ Solid
metallic member(s) or the combination of both. The metallic strength member shall be of high
grade steel wire, music spring quality as per ASTM-A228/A228M-93 and shall have suitable
chemical coating for proper adhesion with sheath material. The central fibre optic unit should
include a central strength member of non-metallic Fibre Reinforced Plastic (FRP) only.
Peripheral strength members and aramid yarns are also acceptable. The central FRP strength
member may be of slotted type with SZ lay (reverse oscillation lay) of fibre units or it may be
cylindrical type with helical or SZ lay of fibre units. The construction of the central strength
member shall be such as to meet the mechanical strength requirements specified in this
specification.
Filling Compound
The interstices of the central fibre optic unit and cable shall be filled with a suitable
compound to prohibit any moisture ingress or any longitudinal water migration within the
fibre optic unit or along the fibre optic cable. The water tightness of the cable shall meet or
exceed the test performance criteria as per IEC60794-1-2-F5. The filling compound used
shall be a non-toxic homogenous waterproofing compound that is free of dirt and foreign
matter, anti-hygroscopic, electrically nonconductive and non-nutritive to fungus. The
compound shall also be fully compatible with all cable components it may come in contact
with and shall inhibit the generation of hydrogen within the cable. The filling compound shall
remain stable for ambient temperature up to +70°C and shall not drip, flow or leak with age or
at change of temperature. Reference method to measure drip point shall be as per IEC 60811-
5-1 and drip point shall not be less than 70°C.
The Sheath / Inner jacket
The Sheath shall be made of High Density Polyethylene-HDPE (Red /Black) and shall be
smooth, concentric, and free from holes, splits, blisters and other surface flaws. The sheath
shall be extruded directly over the central fibre optic unit and shall also be non-hygroscopic.
The cable sheath design shall permit easy removal without damage to the optical fibres or
fibre units. The sheath shall be made from good quality of weather resistant polyethylene
compound HDPE and thickness shall be > 1.5mm including the strength member if used in
the sheath.
Armouring of cable
Over the inner PE sheath armouring and outer sheath shall be provided to make the cable
termite and rodent proof. The thickness of the stainless steel alloy armour shall be >
0.125mm. The steel armour shall be both side coated with a copolymer of thickness >
0.05mm so as to bond the armouring to the outer jacket and make a unitary construction.
Stainless steel shall be armouring corrugated transversely for lateral strength and bending
flexibility to be applied longitudinally with an overlap of 10% (minimum) over the inner PE
sheath. The corrugation over the entire length of the tape used in the cable shall be uniform,
electrically continuous (applicable to all metallic elements used in the cable) and bonded to
the outer sheath. The force of adhesion of the armour to the outer sheath shall be minimum 14
Newton and shall be tested as per ASTM:4565 test method. Suitable glue adhesive should be
provided in between overlap portion of cable armouring for bonding to avoid ingress of
moisture (below the armour). The height of the corrugation shall be 0.6mm (min.) and the
pitch shall be 2.5mm(max.). Height and pitch of corrugation shall be measured between crest
and tough base line. The corrugated armouring of stainless steel shall offer excellent corrosive
resistance and shall be AISI Alloy no. 304 and the chemical composition and mechanical
properties of steel shall be as specified in table 1 & 2 of ASTM : A167-92b for AISI 304
respectively.
The Outer Jacket
A non-metallic moisture barrier sheath (Red or Black in colour) shall be applied over the
armour, which shall consist of tough weather resistance made of HDPE. The thickness shall
be uniform and shall not be less than 2.0mm (Red in colour) for the cable having inner and
outer HDPE sheath. The outer jacket shall have smooth finish and shall be termite resistant.
The raw material and additive used to make the outer sheath termite proof shall be clearly
mentioned by the manufacturer of the cable.
In case of HDPE material black in colour is used, the material from finished product shall be
subjected to the following tests mentioned in Table 3 below;
Table 3
7.Tensile strength and Elongation at >2 Kg.mm2 and > 500% respectively
break
Rip Cord: Suitable rip cord(s) shall be provided to open the outer sheath of the cable. The rip
cord(s) shall be properly waxed to prevent wicking action and shall not work as a water
carrier.
20.52.5 Mechanical Parameters & Tests: The offered cable shall meet requirement of
mechanical characteristic & tests specified in this specification.
20.52.6 Cable drums, Marking, Packaging and Transport
All optical fibre cable shall be supplied on strong wooden drums provided with lagging with
adequate strength, constructed to protect the cabling against all damage and displacement
during transit, storage and subsequent handling during installation. The cable drum shall be
suitable to carry underground fibre optic cable of required length. However, the exact lengths
for drums to be supplied for each link shall be determined by the Contractor during detailed
engineering/survey. Drum schedule shall be approved by the Employer before manufacturing
the FO cable. Both cable ends in the drum shall be sealed and shall be readily accessible. The
drum shall be marked with arrows to indicate the direction of rotation. Both the ends of the
cable shall be provided with pulling eye. The pulling eye and its coupling system should
withstand the same tensile load as applicable to the cable. The following marking shall be
done on each side of the cable drums.
i) Drum number
ii) Consignee’s name and address
ii) Contractor’s name and address
iv) Type of cable
v) Number of fibres
vi) Type of fibres
vii) Year of manufacturing, month & batch no
viii) Name of manufacturer
ix) Total cable length
x) Inner end marking and Outer end marking
Packing list supplied with each drum shall have all the information provided on marking on
the respective cable drum and following additional information: OTDR length measurement
of each fibre and Ratio of fibre and cable length.
20.52.7 Optical fibre cable marking
A suitable marking shall be applied in order to identify this cable from other cables. Marking
on the cable shall be indelible, of durable quality, shall last long and shall be applied at
regular interval of one-meter length. Marking shall be imprinted and must clearly contrast
with the surface and colours used must withstand the environmental influences experienced in
the field. The accuracy of the sequential marking must be within + 0.5% of the actual
measured length. The sequential length marking must not rub off during normal installation.
In case laser printing is used the marking shall not exceed 0.15 mm depth. The optical fibre
cable shall have the following markings in every meter.
i) Type of Cable
ii) Running meter length
iii) Number of fibres
iv) Type of fibre
v) Laser symbol & caution notice
vi) Year of manufacture and batch no.
vii) Manufacturer’s name
viii) Owner’s Name
TABLE-5
The PLB HDPE pipe shall have two concentric layers viz. outer layer and inner layer. The outer layer
shall be made of HDPE material and the inner layer of solid permanent lubricant. These concentric
layers shall be co-extruded and distinctively visible in cross section under normal lighting conditions
and generally conform to IS-9938. The colour of the PLB HDPE pipe shall be finalized during detail
engineering. In the finished PLB HDPE pipe, the co-extruded inner layer of solid permanent lubricant
shall be continuous and integral part with HDPE outer layer and preferably be white in colour. The
inner layer of solid permanent lubricant shall not come out during storage, usage and throughout the
life of the pipe. The pipe shall be supplied in a continuous length of 1000 (one thousand) meter in coil
form, suitable for transportation, installation and handling purposes. The finished pipe shall be of
good workmanship such that the pipe is free from blisters, shrink holes, flaking, chips, scratches,
roughness, break and other defects. The pipe shall be smooth, clean and in round shape, without
eccentricity. The ends shall be cleanly cut and shall be square with axis of the pipe.
General
The HDPE pipe shall conform to the following standard and the technical specifications described in
the following sections.
a) IS: 4984 / IS: 2530/IS:14151/(part1)/ IS:9938/IS:7328/IS12235(Part-9)/IS:5175
b) ASTM D 1693/ ASTM D 638/ ASTM D 648/ ASTM D 790 / ASTM D 1712/
ASTM D 2240/ ASTM D 4565 / ASTM F 2160/ ASTM G 154
c) TEC-spec no. GR/CDS-08/02/NOV-04(including all amendments)-HDPE pipe for
use as duct for optical fibre cable.
Material
The raw material used for the PLB HDPE pipe shall meet the following requirements:
(i) The anti-oxidant establishers, colour master batch and other additive used shall be
physiologically harmless and shall be used only to minimum extent necessary to meet
the specification.
(ii) Usage of any additives used separately or together, should not impair the long-term
physical and chemical properties of the PLB HDPE pipe. Under Ground Fibre Optics-
Technical Specification Page 13 of 32.
(iii) Suitable Ultra Violet stabilizers may be used for manufacture of the PLB HDPE pipe to
protect against UV degradation when stored in open for a minimum period of 8 months.
(iv) The ash content of the colour master batch shall not be more than 12% when tested as
per method detailed below:
Test Method for ash content: About one gram of the sample under test shall be taken
and dried at 105°C for two hours in a platinum or glazed porcelain or silica or quartz
crucible. The weight of the sample shall be noted. Subsequently, the sample with the
crucible shall be transferred to a muffle furnace maintained at 600±50°C and allowed to
remain there for three hours. The ash content may be calculated as a percentage of the
weight of the original sample.
(V) The base HDPE resin used for manufacturing outer layer of pipe shall conform to any
grade of IS-7328 or to any equivalent standard meeting the following requirement
when tested as per standards referred in this Section below.
a) Density (outer and inner layer): 940 to 958kg/m3 at 27°C. The density of completed
PLB HDPE shall not be differ by more than 0.003gms/cc by this value when tested
as per IS:2530 or IS:7328.
b) Melt Flow Rate (MFR): 0.2 to 1.1 g/10 minutes at 190°C & 5 kg load: when tested
as per IS:2530. The MFR of the outer layer of the completed PLB HDPE pipe shall
not differ by more than 30% of this value.
c) Tensile Strength at Yield: 20 N/mm2 minimum, when tested As per ASTM D 638,
Type-IV specimens
d) Elongation at break: >600%, when tested as per ASTM D638, Type-IV specimens
e) Flexural Modulus at 1% strain: 690 N/mm2 minimum, when tested as per ASTM D
790.
f) Hardness, Shore-D: Between 60 and 65 units, when tested as per ASTM D 2240
g) Heat Deflection Temperature at 45 g/mm2: 65ºC minimum, when tested as per
ASTM D 648.
h) Environmental Stress Crack resistance, When tested with 10% Igepal, CO 0630
Solution 50ºC: 96 hrs., when tested as per ASTM D 1693, No cracks.
i) Weathering in artificial (UV) light (Specimens shall be as per ASTM D 638 Type-
IV) and cut from compression moulded sheet. After exposure for 720 hrs., Tensile
strength shall be tested. The variation shall not be greater than 20% compared to
tensile strength obtained at above.
j) OIT (in Aluminium Pan): 30 minutes minimum, when tested as per standard
k) UV Stabiliser Content: Hindered Amine Light Stabliser minimum 0.15%, when
analysed as per FT-IR method.
(VI) In the inner layer of PLB HDPE pipe, the friction reducing, polymeric material to be
used as the inner layer lubrication material shall be integral with HDPE layer. The
lubricant materials shall have no toxic or dermatic hazards for safe handling.
Dimension of pipe
The nominal size of the pipe shall be minimum 40mm for OFC Cable and minimum 160mm for 132KV
Cable and Thickness ,Pressure of the HDPE pipe will be depending as per the requirement of site
Condition.
Accessories of PLB HDPE pipe
The following accessories are required for jointing the pipe and shall be supplied along with the pipe.
The manufacturers shall provide complete design details, procedure for method of installation and type
of the material used for the accessories. No part of the accessories shall contain metal part and
minimum pulling force of the coupler shall be 330kgf. The accessories shall pass the ageing test at
70+2ºC and there shall be no leakage when tested for 168 hours.
i) Plastic coupler: The coupler shall be used to join two PLB HDPE pipes. The coupling
shall be able to provide a durable airtight and watertight joint between two pipes
without deteriorating the strength of the pipes. The strength of coupler shall match the
primary strength of the PLB HDPE pipe and threaded coupler is not acceptable. The
jointing shall meet the air pressure test of 15 kg/cm2 for a minimum period of 2 hours
without any leakage.
ii) End plug: This shall be used for sealing the ends of empty pipe, prior to installation of
FO cable and shall be fitted immediately after laying of the PLB HDPE pipe, to
prevent entry of any unwanted elements such as dirt, water, moisture, insects/rodents
etc.
iii) Cable sealing plug: This is used to hold the cable and prevent entry of any unwanted
elements, as specified above.
iv) End cap: This cap is made of hard rubber, shall be fitted with both ends of PLB
HDPE pipe to prevent the entry of any unwanted elements such as dirt, water,
moisture, insects/rodents during transportation and storage.
v) Set of installation/maintenance accessories comprising of C-Spanners for tightening
plastic coupler (4 nos.), Rotary duct cutter (2 nos.), spare cutting wheel (4 nos. Per
Rotary Duct cutter), Chamferring tool for giving slight chamfer to the ends of
PLB HDPE pipe shall be used during maintenance of the PLB HDPE pipes and
these items (1set) shall be supplied along with the pipe.
Workmanship
The pipe shall be free of blisters, shrink holes, break and other defects. The PLB HDPE pipe ends
shall be cut as square as possible to longitudinal aspects. The internal and external PLB HDPE pipe
surfaces shall be smooth. The colour should be uniform throughout.
Marking
All the pipe, shall be clearly marked at intervals of 1 meters with the following data which is not
less than 5 mm high. The details of marking on pipe shall be approved by Employer before
commencement of manufacturing.
i) Owner’s Name with logo
ii) Manufacture’s name or trade mark
iii)Year of manufacturing
iv) Type of PLB HDPE pipe and size
v) Running length marking
Tests & Inspection: The general condition of testing & inspection is given in section-03 of
technical specification.
Type Test
The PLB HDPE pipes & accessories offered to be supplied should have been type tested as per
requirement specified in relevant TEC specification or equivalent standard. The Bidder shall enclose
the previous type test report and/or type approval certificate from Telecom Engineering Centre
(TEC), Department of Telecommunication, according to relevant TEC for the proposed PLB HDPE
duct meeting the specified requirement.
Factory Acceptance Testing:
The following tests shall be carried out during Factory Acceptance Testing (FAT) in Table 2- 4.
20.52.11 Installation of Underground Fibre Optic Cable System
The Underground Fibre Optic Cable shall be installed along the power cable to be supplied &
installed under this Project. This part of the section describes the installation procedures, installation
of PLB HDPE pipes, installation of RCC hume pipes and GI Pipes, marking, backfilling, installation
of underground FO cable, construction of manholes, splicing, termination and site acceptance testing
requirements of the underground fibre optic cabling system.
20.52.12 Installation of PLB HDPE Pipe
One PLB HDPE pipe shall be laid at bottom of the trench after making the surface smooth and
providing minimum 80 mm sieved, stone free sand bedding. After laying the pipe additional sieved
sand shall be added to increase the height of the sand layer to a total of 200 mm hence positioning
the PLB HDPE pipe in the middle of the layer. Other important steps are described as under:
a. PLB HDPE Pipe shall be laid in a flat bottom trench free from stones, sharp edged
debris.
b. The Pipe shall be placed in trenches as straight as possible. Minimum bending radius of
pipe and fibre optic cable shall always to be taken into account.
c. The ends of pipes shall always be closed with end plugs to avoid ingress of mud, water
or dust i.e. all pipe opening shall be sealed to avoid entry of foreign material.
d. The pipes shall be joined tightly & properly through plastic couplers and the joint shall
be smooth and free from steps. The joints shall be made properly so that it passes the
duct integrity test specified in this section. All joints shall be assembled with proper
tools only.
e. Coupler shall not be placed along the bend portion of the pipe
f. Cable sealing plugs shall be provided at all manhole locations and at locations cable is
coming out of the pipe and empty pipe ends i.e. all pipe openings shall be sealed to
avoid entry of foreign objects.
g. PLB HDPE pipes shall be installed in a manner that fibre optic cable can be pulled,
blown, de-blown without damaging the fibre optic cable due to stresses. The Contractor
shall all joints inspected before carrying out the backfilling, by a representative of
Owner/Employer. Joints shall be visually inspected and checked for tightness.
20.52.13 Reinstatement
The contractor shall be required to carry out reinstatement of the excavated area. Reinstatement shall
include all works necessary (such as reconstruction of metalled/asphalt road, footpath etc) to restore
the excavated area to original quality and shape. Temporary reinstatement of footpath stipulated in
this section shall be carried out as a part of backfilling. The Contractor shall be responsible for
carrying out complete reinstatement work irrespective of area or type of reinstatement without any
additional cost implication to Employer.
20.52.14 Installation of GI Pipe
The GI pipe of nominal bore of minimum 100 mm shall be laid wherever road crossings, bridge
crossings, railway crossings are encountered on the route as well as on wall/floor crossings in a
building. PLB HDPE pipe shall be inserted into GI pipe. Whenever it is not possible to install the
FO cable underground due to non availability of the right of way or any other unavoidable reasons,
the HDPE ducts along with FO cable shall be installed in GI pipe on the wall inside the sewerage
pipe and or on the existing rock/concrete/brick wall/surface with suitable fixing arrangement and
concreting, if necessary, with specific approval of the Employer in case to case basis. The GI pipe
shall conform to at least medium class and conform to IS: 1239 (Part – I). In regard to bridge and
culvert crossing, GI pipe may be installed by concreting the GI pipe along the bridge or by using
supporting brackets or by laying underneath the existing footpath etc. The PLB HDPE pipes shall be
installed through this GI pipe. Wherever underground fibre optic cable is required to be spliced to
overhead fibre optic cable using the outdoor Joint Boxes installed on towers, GI pipes shall be used
to protect the portion of the cable/duct upto a height of about 6 to 10 meters and shall be extended in
the ground up to suitable depth of the trench so that minimum bending radius of the cable is
maintained. The GI pipe shall be properly clamped/ fixed on the tower leg. The Contractor shall
supply and install all necessary accessories as part of the installation work. The Contractor shall
propose the exact methods and procedures for implementation of crossings taking into consideration
the following guidelines, for approval by the Employer:
a. The GI pipe shall be extended at least 5 meters on each side of crossing
subject to availability of space and approval of the Employer.
b. Two GI pipes shall be joined using proper tools, sockets and accessories etc.
c. Proper arrangements shall be made to seal the ends of GI pipe after
installation of PLB HDPE pipes.
d. Minimum bending radius of optical fibre cable shall always be taken into
consideration.
e. 1:2:4 concrete shall be used for encasing of the GI pipe, wherever required.
f. The floor of the trench shall be levelled by laying at least 50 mm of soft soil
or sieved sand before installing the GI pipe.
g. The GI pipes shall be supplied in standard lengths of 6m or as approved by
Employer.
h. The GI pipe shall be sealed at both ends.
i.The GI pipe of suitable length shall be provided at road crossings, bridge
crossings, railway crossings encountered on the route as well as on wall/floor
crossings in a building and also for protection of fibre optic cable at
tower/pole mounted joint boxes.
20.52.15 Underground Fibre Optic Cable Installation
The cable shall be installed inside the 40mm diameter PLB HDPE pipe installed under this package
along the route(s). Generally the cable shall be installed by compressed air blowing technique.
However, for spans upto 150 meter, the Contractor can use pulling method for installation of OFC in
HDPE pipe. If any temporary manhole or hand hole is required for installation of OFC, the same will be
done by the Contractor without any additional cost implication. Adopting pulling method for
installation of OFC for spans more than 150 meter, shall be subjected to approval of the Employer and
shall be substantiated by proper justification. Contractor shall take into consideration the following
guidelines, for installation of OFC approval by the Employer.
a. The Optical Fibre Cable Drums shall be handled with utmost care.
The drum shall not be subjected to shocks by dropping etc. They shall not be
normally rolled along the ground for long distance and when rolled, shall in
the direction indicated by the arrow. The battens shall be removed only at the
time of actual laying.
b. A blowing machine in association with an appropriate compressor shall be
used for blowing.
c. Temporary blowing chambers (if required) shall be constructed and then
backfilled after blowing operation is completed.
d. Locations along the route, which provide easy access points for blowing
machine and compressor, shall be determined.
e. Before starting the cable blowing, PLB HDPE pipe shall be checked
for obstacles or damage. Checking shall be done by using a proper sized
mandrel.
f. Always blow downhill wherever possible.
g. Multiple blowing machines may be used in tandem if so required.
h. Care must be taken not to violate the minimum bending radius applicable for
the fibre optic cable. Tension in the cable during laying shall not exceed
tension limit of the OFC. Installation by pulling may be permitted by the
Employer only in specific cases where installation by blowing is not feasible
on specific approval from the Employer. In case pulling is used, the pulling
speed shall be determined considering the site condition. While installing the
cable, excess length of about 10 meters shall be stored at each joint location
for each side. Excess length of 10 m shall be kept at one ends of a road
crossing culvert crossing and 20 meters at one end of bridges. However, exact
excess lengths and manhole locations shall be finalised during detailed
engineering depending upon the site requirement.
20.52.16 Trenchless Digging
It is envisaged that trenchless digging shall be used in short section for crossing National highways,
important road or rail crossings etc. Trenchless digging shall be used where the concerned
authorities do not permit open cut method and it is essentially required to carry out for installation of
HDPE pipe.
Contractor’s Scope of Work for Trenchless Digging
The Contractor’s scope of work under this contract shall include, but shall not be limited to, the
following:
(a) Identify, provide and transport all equipment to the locations along the route
as per the requirement to install PLB HDPE pipe by trenchless digging
method.
(b) Excavation and backfilling of entry and exit pits.
(c) Detection and protection of existing underground facilities of other utilities
along the route.
(a) Installation of 40 mm PLB HDPE pipe along the specified route by trenchless
digging method and joining of PLB HDPE pipe by plastic coupler and sealing
of PLB HDPE pipe at both ends by end plugs.
(b) Installation of manholes, termination of PLB HDPE pipes into the manholes
and sealing of PLB HDPE pipes at the manhole entry as per approved
drawings.
(c) Providing all plants, tools and tackles, consumables, marking and fencing
required for the execution of the work as per the best engineering and safety
practices.
(d) Maintain all lights, guards, plates, safety measures, sign boards etc. When and
where necessary and/or required by the Owner/Employer or by any other
statutory authority for the protection of works and/or for the safety and
convenience of the public or the workers at the installation sites.
(e) Arrange electricity by arrangement of generators or other means at the site
wherever required.
(f) Arrange construction water at the sites.
c. SAT Reports
d. As built drawings
requirements are indicated in table 2-9 and in no case losses attributed due to other factors viz. Extra
splice, kinks, will be acceptable to the limit determine by the following formula:
Max attenuation @ 1550 nm: 0.21dB/km + 0.05dB x total no of splices + 0.5dB x connector
Max attenuation @ 1310nm: 0.35dB/km + 0.05dB x total no of Splices + 0.5dB x connector
Any increase in attenuation or step discontinuity in attenuation shall not be acceptable and shall
constitute a cable failure during installation. The Contractor shall have to either replace the concerned
cable span at its own cost or provide additional splicing, joint box and manholes required to rectify the
fault at its own cost. The fibre attenuation shall be tested again after replacement or rectification of
fault. In case it is found that the splices are bad (loss is unacceptable as per approved test procedures),
the Contractor shall have to do re-splicing and provide new Joint Box wherever required at no
additional cost to the Owner/Employer. After re-splicing the end to end testing shall be repeated. The
splice testing requirements are indicated in table below.
Item Description
Item Description
Item Description
Fibre continuity and link attenuation (bi-directional) for each fibre at 1310
1
&1550 nm by OTDR
Fibre continuity and link attenuation (bi-directional) for each fibre at 1310
2
&1550 nm by Power Meter & Laser Source
Average splice loss (bi-directional) for each splices and average splice loss
3
for the link by OTDR at 1550 nm.
In order to route the OFC (Optical Fibre Cable) from the underground trench to the control room
building it is necessary to install the cable on walls inside PLB HDPE pipe over the existing cable
tray/raceways inside the building.
Installation of PLB HDPE pipe on wall
The PLB HDPE pipe may be required to be installed on the wall using steel or G.I clamps. The
contractor will provide the required clamps and other consumables sufficient for such installation.
The contractor will take care of aesthetics while installation. The OFC will be pulled through the
PLB HDPE pipe with due care as described in relevant Para of this specification.
20.52.19 INSPECTION & TESTING
Type Testing
Bidder shall offer the type tested product meeting the requirement of technical specifications.
Factory Acceptance Tests
Factory acceptance tests shall be conducted on randomly selected final assemblies of all equipment
to be supplied. Visual inspection shall be carried out on 100% basis for all the equipment/items
offered. Factory acceptance testing shall be carried out on Underground fibre optic cable, Joint
box, PLB HDPE pipe etc.
20.52.20 System Maintenance
The one year period commencing immediately after the operational acceptance is called the Defect
liability Period/warranty period. Operational Acceptance shall be given on successful completion
of SAT. During this period, the Contractor shall replace or repair all defective parts. The one year
period commencing immediately after the operational acceptance is called the Warrantee
Period/Defect Liability Period. During the Warranty Period/Defect Liability Period, the Contractor
shall guarantee that there shall be minimum outage of the supplied system. During this period, the
Contractor shall replace or repair all defective parts and shall have prime responsibility for
maintaining an operational system.
20.52.21 Documentation
The documentation provided shall include the following:
(a) Detailed list of the deliverables
(b) Description of the products
(c) Technical particulars
(d) Installation manuals
(e) Maintenance manuals
(f) Quality assurance manuals, Manufacturing Quality Plan (MQP) & Field Quality
5 Frequency 50 Hz
No. of Core 1C
15 CABLE DETAILS :
CONDUCTORS
16 INSULATION
VOLUME II Page 617 of 954
i Insulation material XLPE
ii Insulation thickness 8.8 mm (Nominal thickness)
CHAPTER 20: TECHNICAL SPECIFICATION FOR XLPE CABLE WITH TERMINATION
20.54 SPECIFIC TECHNICAL PARTICULARS FOR 132 KV & 220KV XLPE CABLE
5 Frequency 50 Hz
a)material XLPE
16.6 Insulation Screen: Type & Material Extruded semi conducting compound.
19.4 Whether test will be witnessed by Yes. Acceptance test will be witnessed.
purchaser or his representative
20 INSTALLATION, TERMINATION
AND JOINTS
1500C cm/Km
22 Laying Configuration Trefoil formation.
24 Termination
26 Joints Required No
27 Earth Link Boxes Required Yes. In both end and at joints as per cable
bonding system
28 Surge Suppressor Required Yes
CHAPTER 21: TECHNICAL SPECIFICATION FOR 420 kV (50, 63, 80 & 125) MVAr,
SHUNT REACTOR, NGR & SURGE ARRESTER
21.1.1.0 SCOPE:
This section covers the specific technical particulars, climatic and Isoceraunic conditions, system
particulars etc., suiting to which the shunt reactor, NGR & SA as per the requirement given in the
schedule of requirement, shall be offered.
The design of 3 phase 50, 63, 80, 125 MVAr reactor bank shall be suitable for bay width of the
substation/s.
If the reactor is intended to be used as Line reactor then NGR and SA shall be supplied as per
technical specification. However, if it is intended to be used as Bay reactor, then NGR and SA
shall not be supplied.
Each reactor shall be supplied with (i) One number or Oil Storage tank, (ii) 3 nos. of oil
sampling bottles, (iii) On line DGA, (iv) Fiber optic sensors, (v) Nitrogen Injection System for
Protection against the Fire & Explosion.
21.1.2.2All electrical devices shall be given tropical and fungicidal treatment and shall be capable
of satisfactory operation under the severe climatic conditions that would prevail at site as described
above.
22.1.2.3The equipment offered shall be suitable for continuous operation under above conditions at
the full rated capacity.
21.1.2.3 The equipment offered shall be suitable for hot line maintenance techniques.
i) Power devices (like drive motors 415 Volts, 3 phase, 4 wire, 50 Hz.
etc.) Neutral grounded AC supply.
iii) D.C. alarm control and Two separate 220 Volts, two wires
protective device ungrounded D.C. supply
from battery.
PS
Class
(c) Maximum CT Secondary Resistance
CORE 1 1 Ohm 1 Ohm 1 Ohm
CORE 2 1 Ohm - -
CORE 3 1 Ohm 15-10-2.5 Ohm -
CORE 4 - 15-10-2.5 Ohm -
(d)Exciting current Max at Vk/4
CORE 1 250mA 250mA -
CORE 2 250mA - -
CORE 3 250mA 20mA at 3000/1 -
30mA at 2000/1
120mA at 500/1
CORE 4 - 20mA at 3000/1 -
30mA at 2000/1
120mA at 500/1
(e) Application
Temperature Indicator
CORE 2 Restricted earth fault -
(on one phase only)
NOTE:
1. CT shall be as per IS: 2705 (latest amended)
2. It shall be possible to remove the CTs from the reactor tank without removing the reactor cover.
Necessary precautions shall be taken to minimize eddy currents and local heat generated in the
turret.
3. CT Secondary leads shall be brought out to a weather proof terminal box near the bushings.
These terminals shall be wired out to cooler control cabinet/ marshalling box using separate
cables for each core.
4. CT characteristics shall be subject to the purchaser's approval.
5. Magnetization current of CTs shall be < or = 30 mA at highest tap.
6. The secondary excitation current of class PS shall not be more than 4% of rated secondary
current at 25 % of knee point voltage.
7. Class (for relevant protection and duties) as per IEC: 60185.
21.1.6.1 GAPLESS SURGE ARRESTER:
21.1.7.1 Shunt Reactor shall be connected to the 400 kV systems for reactive load compensation
and it shall be capable of controlling the dynamic over voltage occurring in the system due to load
rejection.
21.1.7.2Shunt Reactor shall be capable of operating continuously at a voltage 5% higher than rated
voltage of shunt reactor without injurious heating.
21.1.7.3Temperature rise shall be guaranteed when reactor is operating at 420 kV (Highest voltage
of system).
22.1.7.4The Reactor shall be subjected to switching surge over voltage up to 2.5 p.u. and
temporary over voltage for few cycles, of the order of 2.3 p.u., followed by power frequency over
voltage up to 1.5 p.u. The reactor must withstand the stresses due to above transient dynamic
conditions which may cause additional current flow as a result of changed saturation
characteristics / slope beyond 1.5 p.u.
21.1.7.5The bidder shall clearly guarantee in his bid that the equipment offered shall perform
satisfactorily under both the power frequency and switching such over voltages shall not cause any
damage to the winding or withstanding Thermal and mechanical effects of short circuit at the
21.1.7.6 The neutral grounding reactors are required for grounding of the neutral point of shunt
reactors to limit the secondary arc current and the recovery voltage to a minimum value.
SECTION - II
21.2.1.2The scope of work shall also include EITHER complete erection, testing and
commissioning of all the equipments/accessories furnished under this specification OR only
supervision of erection, testing and commissioning of all the equipment furnished under this
Specification.
21.2.1.3 It is not the intent to specify completely herein all the details of design and construction of
the equipment. However, the equipment shall confirm, in all respect to high standards of
engineering, design and workmanship and be capable of performing in continuous commercial
operation up to guarantee in a manner acceptable to the purchaser, who will interpret the meaning
of drawings and specifications and shall have the power to reject any work or material which in his
opinion are not in full accordance therewith. Such components shall be deemed to be within the
scope of Bidders supply irrespective of whether those are specifically brought out in this
specification or not. The Reactors should be free from Polychlorinated Biphenyls
(PVB/PCB)
21.2.1.4 All deviations from this specification shall be separately listed in specified Schedule, in the
absence of which, it will be presumed that the provision of the specification are complied with by
the bidder.
21.2.2 STANDARDS:
21.2.3All equipments provided under this specification, shall, in General conform to the latest
issued including amendments of the following standards.
21.2.4 In case equipment conforms to other internationally acceptable standards which ensure
equivalent or better performance than that specified under clause 2.2.0 then English version of such
standards or relevant extracts of the same shall be forwarded with the bid and the salient features of
comparison shall be brought out separately in the bid.
21.2.5Accessories, components, parts and raw materials shall conform to relevant Indian standards.
21.3.0 Duty Requirements: The Reactors and all its accessories like CTs etc., shall be
designed to withstand without injury, the thermal and mechanical effects of any external short
circuit to earth and of short circuits at the terminals considering infinite bus arrangement of
values specified as under:
420kv – 63kA for 3 sec
145kv – 40kA for 3 sec
21.4.0 Radio Interference & Noise Level
The reactors shall be designed with particular attention for suppression of maximum harmonic
voltage especially the third and fifth so as to eliminate wave form distortion and minimize
interference with communication circuits.
The noise level, when energized at normal voltage and frequency shall not exceed, when
measured under standard conditions, the values specified in NEMA, TR-I.
The reactor shall be capable of operating under the natural cooled condition.
21.5.0 The maximum current density for design of reactors within specified limits of reactor
losses shall not exceed the limits of 300 amps per sq.cm. All requirement of magnetic circuit
shall be as per CBIP Manual no 295.
21.7INSULATION
Impulse & Power Frequency Voltage Withstand Values: For rated nominal system voltage
of 132 KV & 400 KV following minimum power frequency and impulse withstand voltage
should be offered for the windings.
Power Frequency
System Voltage Highest Switching Surge Impulse
Withstand Voltages
System Withstand Voltage Withstand
Voltage Voltage
400KV 420KV 364 KV with PD * 1050KVp 1300KVp
* The Partial Discharge level should be ≤ 100 pico coulomb at 1.5Um/√3 (Method 2) as per IS
2026 part 3 or IEC 60076-3.
21.8 VIBRATION AND STRESS LEVEL: Vibration and stress level shall not be more than
200 microns peak to peak at rated voltage and frequency. The average vibration shall not
exceed 60 microns peak to peak.
21.10 FREQUENCY: All the reactors shall be suitable for continuous operation with a
frequency variation of + 4% to -4% from normal 50 Hz without exceeding the specified
temperature rise.
21.11 IMPEDANCE: The range of constant impedance shall be upto 1.5 pu voltage and the
Bidder shall furnish complete saturation characteristics of the offered Reactors upto 2.5 pu
voltage.
The total losses in kilowatts (including BIS tolerance) at rated output, rated voltage and rated
frequency at 75oC shall be guaranteed by the bidder. It may be noted that the losses of the
reactor shall not exceed during final testing of the reactor, if the same exceeds from the
maximum ceiling limit of reactor losses as detailed above then the reactor shall not be
accepted.
One 400 KV, 50/63/80/125 MVAR three phase shunt reactor of each manufacturer (if there
are more than one manufacturer) shall be subject to heat run test (Temperature rise test).
21.13 CONSTRUCTION DETAILS : The features and construction details of Reactor shall
be in accordance with the requirements stated hereunder:
21.14 Tank
21.14.1 The tank shall be of Conventional or Bell type construction for 400 KV Reactor
covered under this specification. In case of Conventional type, top cover shall be bolted to tank
body and in case of Bell type, top cover shall be welded to the tank body.
21.14.2 Tank shall be of welded construction and fabricated from tested quality low carbon
steel suitable for welding & of following minimum sheet thickness. Tank cover - 20 mm, sides
including inspection cover- 8 mm, Base - 20 mm.
21.14.3 All seams and those joints not required to be opened at site shall be factory welded and
wherever possible they shall be double welded. After completion of tank construction and
before painting, 'Dye Penetration Test' shall be carried out on welded parts of jacking bosses,
lifting lugs and all load bearing members.
21.14.4 Tank stiffeners preferably shall be provided for general rigidity and these shall be
designed to prevent retention of water.
21.14.5 The tanks shall be designed to withstand the following without permanent distortion.
21.14.5.1 Mechanical shocks during transportation.
21.14.5.2 Vacuum filling of oil at 10 milli torr in Reactor with all fittings.
21.14.5.3 Continuous internal pressure of 35 kN/m 2 over normal hydrostatic pressure of
oil.
21.14.5.4 Short circuit forces &
21.14.5.5 Under seismic condition /events both horizontal/vertical.
21.14.6 Where ever possible the Reactor tank and its accessories shall be designed without
pockets wherein gas may collect. Where pockets cannot be avoided, pipes shall be provided to
vent the gas into the main expansion pipes if any.
21.14.7 The shields shall be such that no magnetic fields shall exist outside the tank. They shall
be of magnetically permeable material. If required impermeable shields shall be provided at the
coil ends. Tank shield shall not resonate when excited at the natural frequency of the
equipment.
21.14.8 The base of each tank shall be so designed that it shall be possible to move the
complete reactor unit by skidding in any direction without injury when using plates or rails.
21.14.9 The tank shall be provided with :
21.14.9.1 Lifting lugs suitable for lifting the equipment complete with oil.
21.14.9.2 A minimum of four jacking pads in accessible position at 500mm height to enable the
Reactor complete with oil to be raised or lowered using hydraulic or screw jacks. Each
jacking pad shall be designed to support with an adequate factor of safety for atleast half of the
total mass of the reactor filled with oil allowing in addition for maximum possible
misalignment of the jacking force to the centre of the working surface. The location of jacking
pads shall be such that there should not be any interference with the civil foundation of rails in
either direction i.e. longitudinal or transverse.
21.14.9.3 Suitable haulage holes shall be provided.
21.14.10
(i) Inspection cover/access windows & Manholes:
Suitable man-hole with a welded flange and a properly gasketted bolted cover having of
minimum thickness of 10 mm shall be provided on the tank cover. The man- hole shall be of
sufficient size to offer easy access to the lower ends of the bushings, terminal etc.
(ii) Space for free movement in Reactor Tank for inspection:
Details of passage & free space provided inside the main tank should be indicated in concerned
drawing to allow free movement of at-least two persons for inspection of active parts etc. To
be more specific it may please be noted that minimum clearance from outer most
winding/connection leads/supports to tank shall not be less than 200 mm.
21.14.11 All bolted connections to the tank shall be fitted with suitable oil tight
Neoprene/nitrile gaskets which shall give satisfactory service under all operating conditions.
Special attention shall be given to the methods of making the hot oil tight joints between the
tank and the cover as also between the cover and the bushings and all other outlets to ensure
that the joints can be remade satisfactorily and easily with the help of semi-skilled labour.
Where compressible gaskets are used, stoppers/ runners shall be provided to prevent over
compression.
21.14.12 Suitable guides shall be provided for positioning the various parts during assembly or
dismantling. Adequate space shall be provided between the core and windings assembly and
the bottom of the tank for collection of any sediment.
21.14.13 The design of the tank, lifting lugs shall be such that the complete Reactor assembly
filled with oil can be lifted with the use of these lugs without any damage or distortions.
21.14.14 For the complete Reactor we have clearly brought out our requirement of various
types of valves in Annexure-V enclosed brings out details of type, size and quantity of valves
which are to be provided at various locations. This requirement has to be confirmed by the
Bidders without any deviation. However, at the time of drawing approval, any change in
no./size of valves desired by the supplier can be considered subject to acceptable submission
by the supplier and with due approval of purchaser.
21.14.15 Gasketing Arrangement : It may be noted that all gasketted joints shall be grooved
one using ‘O’ rings of nitrile rubber or better, such as the joints between bushing turret and
bushing flange, inspection covers of inspection windows and all other openings provided for
the purpose of inspection of internal parts of the Reactor etc. The main conventional / bell tank
gasket between top cover & tank/ upper tank and bottom tank shall be single piece ‘O’ ring
cord/gasket of nitrile rubber or material of better quality. The gasketting arrangement shall be
grooved one with proper stopper to avoid over compression. It is to be noted that one
additional set of gaskets shall be delivered by the Bidder along with transformer to replace the
used gaskets at the time of erection of the unit.
21.14.16 Ladder: One detachable bolted type mild steel (MS) ladder with anti-climbing
arrangement shall be provided. Ladder for climbing up to & over top cover of Shunt Reactors
shall be mechanically sturdy enough to bear the load of healthy maintenance staff without any
shake/jerks. The arrangement shall not be detached after erection and commissioning of the
unit, hence shall be provided with padlock locking arrangement for anti-climbing device. On
the upper top of the ladder, provision for support shall be made. However, the arrangement of
the ladder shall be to purchaser’s approval. Collapsible ladder shall not be acceptable to us.
21.14.17 In case of bell tank, suitable earthing bridge between upper and lower tank shall be
provided at least on two places each on HV & Neutral side and at one place on other both
sides.
21.15 Tank Cover
(a) The tank cover shall be sloped to prevent retention of rain water and shall not distort when
lifted.
(b) Inspection cover/man holes shall be provided
(c) The tank covers shall be fitted with pockets at the position of maximum oil temperature of
MCR (Maximum Continuous Rating) for inserting bulbs of oil and winding temperature
indicators. It shall be possible to remove these bulbs without lowering the oil in the tank. The
thermometer shall be fitted with a captive screw to prevent the ingress of water.
(d) Bushings, turrets, covers of inspection openings, thermometer, pockets etc., shall be
designed to prevent ingress of water into or leakages of oil from the tank.
(e) All bolted connections shall be fitted with weather-proof, hot oil resistant gasket in
between, for complete oil tightness. If gasket is compressible, metallic stoppers shall be
provided to prevent over-compression.
21.16 Axles and Wheels
(a) The Reactors are to be provided with flanged bi- directional wheels and axles. These shall
be so designed as not to deflect excessively to interfere with the movement of the Reactor.
Wheels shall be provided with suitable bearings which shall be rust and corrosion resistant.
Fittings for lubrication shall also be provided.
(b) The wheels are required to swivel and they shall be arranged so that they can be turned
through an angle of 90 degrees when the tank is jacked up to clear of rails.
(c) Flanged wheels provided shall be suitable for use on rail track guage of 1676 mm in
longitudinal and transverse direction.
The reactor shall be suitable for mounting on concrete plinth foundation directly. The wheels
and the axles shall be suitable for fixing to the undercarriage of shunt reactor to facilitate
movements of shunt reactor on rail track.
21.17 Anti-Earthquake/Transport Clamping Device
(a) To prevent Reactor movement during earthquake, clamping device shall be provided
for fixing Reactor to the foundation. The Bidder shall supply necessary bolts for embedding in
the concrete foundation. The arrangements shall be such that the Reactor can be fixed to or
unfastened from these bolts as desired. The fixing of the Reactors to the foundations shall be
designed to withstand seismic events to the extent that a static co-efficient of 0.3g. applied in
the direction of least resistance to that loading will not cause the Reactor or clamping devices
as well as bolts to be over stressed.
(b) Locking arrangement to eliminate relative movement between top yoke/active parts
with the Reactor tank shall be sturdy enough to bear transport hazards taking in to account the
poor road conditions and also considering that road transportation of Reactor will not be on
hydraulic trailers.
21.19 Tank Earthing Arrangement: Two earthing pads complete with two number tapped
holes M10 bolts plain and spring washer suitable for connection to 75x10mm GI flat (to
connect with 40 mm dia MS rod used as the main earth mat conductor for 400Kv earth mesh)
shall be provided each at position close to two diagonally opposite bottom corners of tank.
Earthing strips up to the ground level and its connection with station earth pit shall be
provided by the Bidder.
21.20 Pressure Relief Device: A minimum of 2 (two) number of pressure relief devices of
reputed make and reliable quality shall be provided on each Reactor and these shall be
mounted preferably on the tank cover. Bidders must submit calculations to prove that the
no. and capacity of pressure relief device with location of each PRV provided on the Reactor
will adequately meet our requirement. The quantity of two numbers is on the basis that one no
will be required as per design calculation and one number additional PRD shall be provided
from the point of view of additional safety.
Constructional and design details of pressure relief device must be furnished and it should be
proved by calculation that the size and operating pressure setting of pressure relief device is
adequate, considering the rating of the Reactor and quantity of oil in the Reactor. Furnishing of
this information is a must. These PRD's shall be of sufficient size for rapid release of any
pressure that may be generated in the tank and which may result in damage to the equipment.
The device shall operate at a static pressure of less than the hydraulic test pressure of Reactor
tank. It shall be mounted directly on the tank. One set of electrically insulated contacts shall be
provided for alarm & tripping along-with the recommendations.
21.21 Buchholz Relay: A double float type Buchholz relay along with suitable moulded type
cover to avoid ingress of moisture/ rain water shall be provided. All the gases evolved in the
Reactor shall collect in this relay. The relay shall be provided with a test cock suitable for a
flexible pipe connection for checking its operation and for taking gas sample. A copper or
stainless-steel tube shall be connected from the gas collector to a valve located about 1200mm
above ground level to facilitate sampling of gas while the Reactor is in service. The device
shall be provided with two electrically independent ungrounded contacts, one for alarm on gas
accumulation and the other for tripping on sudden rise of pressure. The contacts of relay shall
be properly housed, sealed and gasketted to make the arrangement water proof. Entry of
moisture/water in the contact chamber needs to be eliminated. Cable entry to terminal box of
buchholz relay should be made through bottom of relay.
Note: The Bidders shall ensure that the compartments housing relay contacts of Pressure
Relief Valve, Buchholz Relay are made absolutely water and vermin proof. The
compartment housing contacts of PRV and Buchholz Relay shall be tested for water
proof at the time of inspection and effectiveness of water proofing shall be demonstrated
at the time of inspection. This should be noted carefully by the Bidder and specifically
confirmed in their Bid.
21.22 Rapid Pressure Rise Relay (RPRR): The provision for the same be made on main tank
to operate on rate of rise of pressure. An electrically insulated trip contact shall be provided in
RPRR relay as per requirement of NIFPS.
21.23.1 Oil Temperature Indicator (OTI): The Shunt Reactors shall be provided with
thermometer pockets for 150 mm dial type thermometer for top oil temperature indication. The
thermometer shall have adjustable electrically independent, potential free contacts for:
21.23.2 Winding Temperature Indicator (WTI): A device for measuring the hot spot
temperature of winding shall be provided on Shunt Reactors. It shall comprise of the
following:
Temperature sensing element.
Image coil.
Current Transformers.
150mm dia local indicating instrument with maximum reading pointer
mounted in marshalling box and with adjustable electrically independent
ungrounding contacts, besides that required one for high winding
temperature alarm and one for trip.
Calibration device.
Automatic ambient temperature compensation.
In addition to the above, the following remote indication equipment shall
be provided:
21.24.2.5 Each core lamination shall be insulated with a material that will not deteriorate due
to pressure and hot oil.
21.24.2.6 The insulation of core to bolts and core to clamps plates shall be able to
withstand a voltage of 2kV RMS or 3.5 KV DC for one minute.
21.24.2.7 Bidder will offer the core for inspection & approval by the purchaser during
the manufacturing stage. Bidder's call notice for this purpose should be accompanied
with the following documents, as applicable, as a proof towards use of prime core
material.
21.25 Windings
21.25.1 The Bidder shall ensure that windings of all Reactors are made in dust proof,
conditioned atmosphere. The Bidder shall furnish the facilities available at their works along
with the Bid.
21.25.2 The conductors shall be of electrolytic grade copper as per relevant IS. The maximum
current density for design of Reactors within specified limits of Reactor losses shall not exceed
the limits of 300 amps per sq.cm.
21.25.3 The insulation of Reactor windings and connections shall be free from insulating
compounds which are liable to soften, ooze out, shrink or collapse or be catalytic and
chemically active in Reactor oil during service.
21.25.4 Coil assembly and insulating spacers shall be so arranged as to ensure free circulation
of oil and to reduce the hot spot of the winding.
21.25.5 The conductor shall be transposed at sufficient intervals in order to minimize eddy
currents and equalize the distribution of currents and temperature along the windings.
21.25.6 All threaded connections shall be provided with locking facilities. All leads from the
winding to the terminal connectors and bushings shall be rigidly supported to prevent injury
from vibration. Guide tubes shall be used where practicable.
21.25.7 The windings shall be clamped securely in place so that they will not be displaced or
deformed during short circuits. The assembled core and windings shall be vacuum-dried and
suitably impregnated before removal from the treating tank. The copper conductors used in the
coil structure shall be best suited to the requirements and all permanent current carrying joints
in the windings and the leads shall be crimped or brazed preferably by high frequency brazing
system.
21.25.8 Bidder will offer the Copper and insulating material for windings for inspection &
approval by the purchaser during the manufacturing stage. Bidder’s call notice for this purpose
should be accompanied with the following documents, as applicable, as a proof towards use of
prime Copper and insulating material for windings.
The Bidders are required to confirm clearances and no change/reduction in clearances shall be
acceptable. The clearances shall be clear distances in air after accounting for clamps/connectors
dimensions to be mounted on the stud of bushings.
(a) For Bushings of all voltage class, the arrangement for connection of winding/neutral
terminal shall be indicated.
(b) The bushings shall be capable of withstanding without injury the electrical, thermal and
mechanical effects of external short circuits. Bushings shall be rated for short time thermal
current rating of 63/ 40 KA for 3 seconds, for 400/ 132 KV respectively.
(c) All the Reactors covered under this specification shall be utilized in heavily polluted
atmosphere. In view of this the Bidders while offering prices for the Reactors against this
contract may please note that the offer should be made out based on the creepage for the
bushings of 31mm per KV based on the voltage of 145KV/ 420KV. Thus, in the quoted prices
of Reactor cost of bushings should be included based on a creepage distance of 31mm per KV.
(d) All O.I.P. Condenser bushings shall be provided with :
(i) Oil level gauge.
(ii) Oil filling plug and drain valve, if not hermetically sealed.
21.28 Terminal Marking: The terminal marking and their physical position shall be in
accordance with IS: 2026.
joint less connection between Reactor neutral and earth pit and details in this regard shall be
intimated to the successful Bidder based on Reactor/substation layout design.
21.30 CORE EARTHING ARRANGEMENT: The Bidder should note our requirement in
this regard very clearly. It is required to bring out leads from core, end frame and tank to the
top of the Reactor through only three insulated bushings. The arrangement shall be housed in a
box at the top cover of Reactor tank with provision for interconnection between the studs of
bushings. The bushing housing shall have a suitable cover with gasket to make the
arrangement waterproof. A clear marking (engraved/punched) shall be made to indicate that
the housing contains core/end frame/ tank earthing arrangement. Please note that
stickers/flags/tags/painted marking for identification shall not be accepted. Arrangement shall
be such that even after removal of connections, oil shall not leak. Removable shorting strips
between the three bushing shall be provided. It may be noted that internal earthing of any
nature between core and End frame should not be provided. Earthing at site shall be done by
interconnecting the three bushings through shorting strips. This arrangement is to facilitate
checking of multiple core earthing in the Reactor.
The insulated cable to be used for core to Bushing connection & end frame to Bushing
connection should be of good quality with proper grounding arrangement. The size & no.
of strands of cable shall be subject to Purchaser’s approval.
21.31 COOLING EQUIPMENT FOR OIL NATURAL AND AIR NATURAL
COOLING (ONAN):
a) The radiator bank of the Shunt Reactor shall be separately mounted. All coolers/radiators
shall be attached on the reactor tank through header having suitable expansion joints (flexible
coupling) to ensure adequate mechanical strength against vibration etc. subject to specific
approval from the purchaser. Radiators directly mounted on reactor tank are not acceptable.
d) Each radiator bank shall be detachable and shall be provided with flanged inlet and
outlet branches.
e) Each radiator shall be suitable for full pressure & vacuum application as applicable for main
tank.
(f) Each radiator shall be provided with suitable lifting lugs and shut off/air release/sampling
valves.
(g) Expansion joints, one each on top and bottom cooler pipe connections as per ‘a’ above.
(h) Air release device/plug and oil d r a i n plug on oil pipe connections.
a) A sheet steel, vermin proof, weather proof marshalling box of a suitable construction shall
be provided for the Reactor ancillary apparatus. The Marshalling box shall be ground mounted.
The interior and exterior painting shall be in accordance with clause 17 The degree of
protection shall be IP 55 in accordance with IS:2147. It shall have double hinged door with pad
lock and pad locking arrangement. The thickness of front panel, door frame etc shall be 3 mm
while door & side panels may be of 2 mm.
a) All doors, removable covers and plates shall be gasketted all round with neoprene gaskets.
Louvers shall have screens and filters. The screens shall be of fine wire mesh made of brass
and GI wire.
The marshalling box shall accommodate the following:
• Temperature indicator for winding and oil
• Terminal boards and gland plates for incoming and outgoing cables.
• The temperature indicator shall be so mounted that the dials are not more than 1600 mm
from ground level and doors of the compartments shall be provided with glass windows of
adequate size.
• To prevent internal condensation a space heater shall be provided. It shall be so designed
that with the space heater on continuously, the temperature inside the marshalling box does not
exceed the safe operating limits at the service conditions.
• All incoming cables shall enter from bottom and the gland plate shall not be less than 450
mm from the base of the box. Gland plate shall be of minimum thickness 4 mm thick. The
gland plate and associated compartment shall be sealed in a suitable manner to prevent ingress
of moisture from the cable trench or conduit.
• The terminals shall be so staggered that the connection of external cable to any terminal
block should be possible without disturbing the rest of the connections. The terminal block
arrangements shall be such as to provide maximum accessibility to all conductor terminations
and any arrangement preventing ready access to other terminal screws shall not be accepted.
• All box wiring shall be in accordance with latest edition of IS: 375 or BS: 158.
• Marshalling box shall be type tested for IP 55 in accordance with IS: 2147.
• Bidder shall recommend sizes and nos. of external cables to be connected to the
marshalling box. All external cabling will be done by the Purchaser.
• A space heater and cubicle lighting with ON-OFF switch shall be provided.
• The gaskets shall be of neoprene rubber.
insulated barriers, non-disconnecting stud type terminals, washers, nuts and lock nuts.
Terminal block design shall include a white fiber marking strip with clear plastic, slip- on/clip-
on terminal cover. Markings on the terminal strips shall correspond to wire number and
terminal numbers on the wiring diagrams.
iii) Terminal blocks for current transformer secondary leads shall be provided with test links
and isolating facilities. Also, current transformer secondary leads shall be provided with short
circuiting and earthing facilities.
iv) Unless otherwise specified, terminal blocks shall be suitable for connecting the following
conductors on each side.
For all circuits except current transformer circuits minimum of two nos. 2.5 mm 2 copper.
For all CT circuits minimum of four nos. 4.0 mm 2 copper.
v) There shall be a minimum edge to edge clearance of 250 mm between the first row of
terminal blocks and the associated cable gland plate. Also the clearance between two rows of
terminal blocks shall be a minimum of 150 mm.
vi) Arrangement of the terminal block assemblies and the wiring channel within the
enclosure shall be such that a row of terminal blocks is run parallel and in close proximity
along each side of the wiring duct to provide for convenient attachment of internal panel
wiring. The side of the terminal block opposite the wiring duct shall be reserved for the
owner's external cable connection. All adjacent terminal blocks shall also share this field
wiring corridor. A steel strip shall be connected between adjacent terminal block rows at
450mm intervals for support of incoming cables.
vii) The number and sizes of the owner's multi core incoming cable will be furnished to the
successful Bidder.
21.34PAINTING
21.34.1 It has been observed that certain units received in the past by us are not having
good quality painting on inside & outside and with passage of time peeling of flakes of
paint takes place. In view of this the Bidders are requested to furnish in a separate sheet
painting procedure adopted by them for internal & external surfaces of the tank. This is
an essential requirement and details should be confirmed by the Bidders in their offer.
The internal and external surfaces including oil filled chambers and structural steel work to be
painted shall be shot or sand blasted to remove all rust and scale of foreign adhering matter or
grease. All steel surfaces in contact with insulating oil shall be painted with two coats of heat
resistant, oil insulating varnish.
21.34.2 All steel surfaes exposed to weather shall be given a primary coat of zinc chromate,
second coat of oil and weather resistant varnish of a colour distinct from primary and final two
coats of glossy oil and Epoxy light gray paint in accordance with shade no. 631 of IS-5.For
each Reactor oil paints should be obtained from same source to ensure compatibility & proper
finish.
21.34.3 All paints shal be carefully selected to withstand extremes of weather. The paint shall
not scale off or crinkle or be removed by abrasion due to normal handling. The process of
painting should be clearly described.
21.34.4 The minimumthickness of each coat of outside painting of tank shall be 20 microns and
the total thickness shall be minimum 80 microns.
21.3.5 Bolts & Nuts All bolts and nuts exposed to weather shall be hot dipped
galvanised/cadmium plated.
21.36.1 Terminal connectors for HV bushings shall be suitable for double (twin) Moose ACSR
(31.77 mm) conductor and suitable for horizontal and/or vertical takeoff arrangement i.e.
universal type. All terminal clamping arrangement shall be subject to Purchaser’s approval.
Regarding neutral earthing, details have been indicated in clause no. 12.0 of this specification.
21.36.2 Bushing terminals shall be provided with terminal connectors of approved type and
size for connection to external parts. Terminal connectors offered must have been successfully
type tested as per IS-5561.
21.36.3 All terminal connectors shall be manufactured out of gravity dye casting process only
and shall be free from blow holes, surface blisters, cracks and cavities. All sharp edges and
corners shall be blurred and rounded off. The aluminum alloy castings, if used, shall conform
to relevant IS.
21.36.5 All bolts, nuts and washers shall be of Hot Dip galvanised.
21.36.6 For bimetallic clamps, bimetallic strip of not less than 2 mm thickness shall be
provided.
21.36.7 Flexible connectors, if provided shall be made from tinned copper sheets.
21.36.8 Size of terminal (bushing stud)/conductor (ACSR Moose) for which the clamp is
designed and also rated current under site conditions shall be embossed/ punched on each part
of the clamp, except hardware.
21.36.9 All current carrying parts shall be designed and manufactured to have minimum
contact resistance. Clamps shall be designed corona controlled.
The nominal current rating and short time current rating of terminal connectors shall match the
corresponding rating of respective bushings i.e., 63KA for 3 seconds for 400kV, 40KA for 3
seconds for 145 kV. Test Reports to substantiate this requirement should be furnished along
with the offer.
21.37.1 Reactor oil shall be supplied by the bidder. The offered Price of Reactor therefore,
should include first filling of oil (including wastage) & 10% extra of that quantity. The
quantity of oil for first filling including wastage and 10% extra of that quantity should be
indicated by the Bidder in kilo-liters and in kg. The design of the Reactor shall be based on the
characteristic of EHV Reactor oil as per relevant IS, IEC, ASTM standards. Transformer oil
for each transformer covered under this Bid specification shall be supplied separately.
21.37.2 Although, oil for the Reactor is included in the scope of supply, but it may be noted
that the Reactor shall be supplied duly N 2 gas filled with suitable arrangement to ensure that
the pressure of gas is regularly maintained during transit and upto the date of filling of oil. For
this purpose, necessary gas cylinders with regulator shall be supplied on non-returnable basis.
Additional gas cylinders required for recouping and maintaining of positive Nitrogen
pressure upto filling of oil should be supplied by the manufacturer of Reactors and the
offered price should take into account this requirement.
21.37.3 The quality of the oil use for testing of Reactor shall conform to the oil parameters
specified in this clause. No inhibitors shall be used in the oil. The oil samples of Reactor will
be drawn for the oil used at factory & site as follows.
i. Prior to filling
ii. Before and after heat run test
iii. Before energizing
All tests as per IS: 335 (latest revision), IEC, ASTM standards shall be conducted on oil
samples.
a. Sufficient quantity of oil necessary for first filling of main tank, coolers, radiators and
conservators etc. upto the proper level + anticipated quantity of wastage of oil during first
filling shall be supplied in tankers. Please note, wastage means quantity of oil absorbed during
initial filling at works for testing. In addition to the oil needed for first filling , 10% extra
quantity of oil for topping up in future, shall be supplied in non-returnable container suitable
for outdoor storage. Therefore, total quantity of oil required for first filling shall be measured
at works at the time of testing on unit subjected to heat run test.
b. The supplier shall dispatch the Reactor in an atmosphere of pressurised Nitrogen. In this
case, necessary arrangement shall be ensured by the supplier to take care of pressure drop of
nitrogen during transit and storage till completion of oil filling during erection. A gas pressure
testing valve with necessary pressure gauge and adapter valve shall be provided.
c. The supplier shall warrant and confirm that oil to be used for the transformer testing at
Works & oil to be supplied for the transformer is free from Polychlorinated Biphenyls
(PVB/PCB). The transformer oil to be used and supplied by the Bidder for first filling at site
shall be new oil of EHV Grade-I having technical specification mentioned hereunder. Oil to be
used by the manufacturers at factory for the purpose of testing at their works shall be of
good quality having parameters matching with the parameters specified in the
specification. Specific approval of oil test results of oil proposed to be used for testing of
transformer in factory shall be obtained by the manufacturer from the purchaser before
filling in the unit.
13. Presence of oxidation inhibitor The oil shall not contain IS:335
antioxidant inhibitors.
Appendix `D’
18 N-dm analysis
CA% 4 –6%
CN% 40-43%
CP% 51-54%
d. Air cell type oil preservation system included with each Reactor shall ensure as under:
(a) The air inlet of COPS (Conservator Oil preservation System) shall be properly fitted on
the conservator for leak proof arrangement to ensure that the air does not come in contact with
oil under any circumstances.
(b) The size and capacity of the COPS (Conservator Oil preservation System) shall be
selected to suit the design of Conservator and to ensure proper operation for the quantity of
oil in the unit with the proper allowances. The COPS shall be of reputed make, proven design
and of established performance. Details in this regard are to be submitted with the offer by the
Bidder for verification. The Bidder is required to submit calculation with Bid to prove
adequacy of air cell & its size.
(c) The Bidder shall clearly indicate in the manual the procedure for installation of COPS
and precautions to be taken at the time of first oil filling under vacuum in the Reactor.
21.38.2 OPERATIONAL CONTROLS: The system operation shall be fully automatic and
activate from the required fire and other trip signals. In addition to automatic operation, remote
operation from control room/ remote centre and local manual control in the fire extinguishing
cubicle shall also be provided. System shall operate on following situations.
protection relays and tripping of circuit breaker of Reactor and operation of either Buchholtz
relay, or pressure relief valve (PRV) along with Rapid Pressure Rise Relay (RPRR) shall be
used to activate the system and logic for RPRR for system activation should include for
operation of Electrical protection relays and tripping of circuit breaker of Reactor. The exact
logic for system activation shall be finalized during detailed engineering.
21.38.4 FIRE PROTECTION: In case of fire, sensed by fire detectors, the system shall be
activated only after electrical isolation of the Reactor, confirmed by breaker trip. If the fire
detection is not associated with any other fault, the system activation shall be only manual.
Manual operation switch shall be provided in the control room/ remote control centre with a
cover to avoid accidental operation of it.
There shall be interlock to prevent activation of the system if the Reactor is not electrically
isolated. There shall also be provision for isolating the system during maintenance and/or
testing of the Reactor.
21.38.6 TECHNICAL PARTICULARS: The supplier shall be responsible for the design of
the complete system and shall submit the drawings and design calculations for the number of
fire detectors, pipe sizing of drain pipe and Nitrogen injection pipe, Nitrogen cylinder capacity,
number of injection points, etc. and get approval from Purchaser. Facility shall be provided to
test the system when the Reactor is in service, without actually draining the oil and injecting
Nitrogen. The Nitrogen regulator valve shall be designed in such a way that the Nitrogen shall
not enter the Reactor tank even in case of passing/ leakage of valve. The system shall work on
station DC supply. The DC system will be consisting of 2 separate DC source. The control box
of fire protection system shall have facility to receive these feeders for auto changeover of
supply. It shall be the contractor’s responsibility to further distribute power to the required
locations.
Following indications and alarms shall be provided in the cubicle as well as the control box:-
22.38.6.1 Nitrogen cylinder pressure indication.
22.38.6.2 Nitrogen cylinder pressure low.
22.38.6.3 Fire in Transformer/ Reactor.
22.38.6.4 Oil drain started.
22.38.6.5 Conservator oil isolation valve closed.
22.38.6.6 Nitrogen injection started.
21.39 DETAILS OF SUPPLY & WORK FOR SYSTEM EQUIPMENTS AND OTHER
RELATED ACTIVITIES: The scope of supply shall include the following items, any other
items required for safe & trouble free operation of the system and the scope of works include
complete earthwork (i.e. excavation, backfilling etc.), scope of supply also includes services to
be availed by the purchaser for erection and commissioning of NIFPS at EHV sub-stations of
AEGCL in ASSAM. , civil work with civil material for the entire open/ buried piping and
requisite foundations for the fire protection system, construction of safety wall, construction of
oil pits with provision of oil storage tank of MS and pipe supports for open/ buried, entrenched
and over ground piping and valves. The system design shall also conform to TAC/NFPA
norms.
(i) Fire extinguishing cubicle with base frame and containing at least the following:
• Nitrogen gas cylinder of sufficient capacity with pressure regulator and manometer
with sufficient number of adjustable NO contacts.
• Oil Drain Assembly including oil drain pipe extension of suitable size for
connecting pipes to oil pit.
• Mechanical release device for oil drain and nitrogen release.
• Limit switches for monitoring of the systems.
• Panel lighting.
• Flanges on top of the panel for connecting oil drain and nitrogen injection pipes
for Reactor.
• Limit switch for pressure switch/sensor.
• Pressure indicators for Nitrogen pressure in the cylinder and after Nitrogen
regulator.
(ii) Control box to be installed in the control room of the station for monitoring system
operation, automatic control and remote operation, with alarms, indication light, switches, push
buttons, audio signal, suitable for tripping and signaling.
(iii) Conservator isolation valve which shall be flow sensitive and shut off when the flow in the
pipe is more than the flow expected in the permissible normal operating conditions. It shall be
provided with position indicator remote alarm indication.
(iv) Required number of fire detectors to be located in strategic locations to be finalized during
detailed engineering. One set (required number) of fire detectors for each NIFPS shall be
supplied as spare for future replacement.
(v) Flow Sensitive Conservator Isolation Valve.
(vi) All controls, alarms, panels, cables, cable trays (if required), junction boxes, valves etc.
21.39.2 In order to restrict the supply of oil in case of a fire in Reactor, provision shall be made
to isolate the conservator oil from the main tank.
21.39.3 A valve which shall be flow sensitive and shut off when the flow in the pipe is more
than the flow expected in the permissible normal operating conditions. This valve shall be
located in the piping between the conservator and the buchholz relay and shall not affect the
flow of oil from and to the conservator in normal conditions.
21.39.4 When the flow from conservator to main tank is more than the normal operating
conditions, the valve shall shut off by itself and will have to be reset manually. It shall be
provided with valve open/close position indicator along with alarm indication in control room
during closing operation of valve.
21.39.6 Instruction plate incorporating operating procedure / cautions shall be provided with
each NIFPS system.
Bidders shall offer Reactor completely fitted with Nitrogen Injection Fire Protection
Systems.
21.40.1 The Bidder should offer for a suitable on line monitoring device for regular
monitoring of 3 key gases and moisture for condition assessment and fault detection of the
400 KV Reactor . The device should measure 3 key dissolved gases viz. Hydrogen, Acetylene,
Carbon mono oxide with accuracy of ±10%. The minimum range of measurement of dissolved
gases shall be Hydrogen: 5 to 500, Acetylene: 3 to 5000, Carbon mono oxide: 10 to 5000. The
moisture content shall be measured from 0 to 100 % RS (in ppm). The device shall have
nonvolatile memory storage to prevent loss of data. The device shall be provided with user
configurable at least six alarm contacts & two front panel LED arrays. The alarm setting screen
shall be available for setting alarms based on level of 3 Key gases or moisture and rates of
change for Key gases. For configuring the six alarm settings, suitable PC software shall be
provided with the device. The device shall be supplied with two separate channels for remote
communication plus local USB and Ethernet connections. The device should support
communication Protocol viz. MODBUS, DNP 3.0 and IEC-61850. It shall be possible to
configure sampling rates to hourly/ daily. The alarm & Caution thresholds shall be user
configurable. The device should support Load monitoring by analyzing results with loading of
Reactor and device shall be provided with suitable software for graphical trending &
diagnostic analysis of results. The device shall have minimum maintenance requirements.
On line monitoring unit shall not be mounted on the body of the Reactor. A separate mounting
arrangement near the Reactor body with proper protective sheds & covers for protection
against sun and rains be provided. The mounting cubical shall have provision for
ventilation/cooling and also provision for reading of parameters by operators without opening
the box. On line monitoring unit shall be complete with provision for remote monitoring alarm
and indication in RTCC panel in control room. Complete details of offered device shall be
submitted by the Bidder and explained by suitable manual/pamphlets.
External temperature range : 0 to 55 o C
Operating Humidity : 10 to 95% RH non condensing
Enclosure : IP55
Input Power requirement : Voltage 120 to 260 V AC, Frequency 47 to 60 Hz;
The power supply should be able to withstand electrical surges & disturbances prevalent in
EHV substation.
21.40.2 Bidders shall offer Reactors completely fitted with On Line Monitoring Device of
reputed make suitable for monitoring of 3 Key gases.
Thermosyphon filter to tank shall be provided with flexible couplings. It may be noted that
rigid supports shall be provided for thermosyphon filter i.e., slotted type of fixing arrangement
is not acceptable.
21.40.4 Silicagel breather: Minimum 2 nos. dehydrating filter Silica Gel Breathers each of
100% breathing capacity are required and the same shall be provided. Size of breather and its
pipe connection is required to be indicated. However, each breather of minimum capacity of 8
kg having its pipe connection of minimum size of one-inch dia shall be preferable. Suitable
arrangement for parallel mounting of breathers shall be made for connecting both the Silica
Gel Breather to the main conservator. The passage of air should be through dual filter & Silica
Gel. Silica Gel shall be isolated from atmosphere by an oil seal. Adequate supports are
required to be provided for pipe connection to avoid any swing in air.
The capacity of dehydrating silicagel breather shall be adequate to ensure supply of dry air
only for the volumetric expansion/contraction of oil keeping in view the total quantity of oil in
the unit. The container of the breather shall be made of metal with glass enclosure along its
periphery to ensure that the transparency (to verify the colour of dehydrating agent) is
maintained during operation directly under sunlight (ultra violet rays) for long life. The
quantity of the dehydrating agent shall be sufficient keeping in view the climatic condition
specified and that the breather will be maintained generally two times in a year. This applies to
all the breathers provided with the Reactor.
21.41.2 The equipments and accessories furnished with the Reactor shall be suitably mounted
on the Reactor for ease of operation, inspection and maintenance and the mounting details shall
be subject to the approval of the purchaser. All valves shall be provided either with blind
companion flanges or with pipe plugs for protection.
21.41.3 Indication, alarm and relay equipment shall have contacts suitable for operation with
220V DC supply. Any other accessories or appliances recommended by the manufacturer for
the satisfactory operation of the Reactor shall also have 220V DC as input.
21.41.4 Marshalling Box shall be conforming to stipulation under relevant clause
21.41.5 Three nos 420KV and 1 no 145KV bush ings shall be of OIP condenser type
22.41.6 Equalizing pipes for maintaining equal pressure between main tank and at various
other locations as per design shall be provided. These equalizing pipes shall be routed such as
not to create any obstruction.
21.41.7 Accessories which are necessary for satisfactory operation of Reactor shall be deemed
to have been included in the accepted price without any extra cost to the Purchaser.
21.41.8 It may be noted that all the name plates/rating plates/diagram plates on Reactor shall be
engraved type/anodized type and shall be fixed using rivets/spot welding method. The method
of printing of letters on the R&D plate shall be such that inscriptions shall not fade by ultra
violet rays and other adverse weather conditions under which the same is subject to during
service life of Reactors.
21.41.9 Rating & Diagram Plate: In the R&D plate following additional information over &
21.42 CENTRE OF GRAVITY: The centre of gravity of the assembled Reactor shall be
low and as near to the vertical centre line as possible. The Reactor shall be stable with or without
oil. If the centre of gravity is eccentric relative to track gauge either with or without oil, its loca-
tion shall be shown on the outline drawing.
21.43 PACKING
The packing may be in accordance with the Bidder's standard practice but Bidder should give
full particulars of packing for the approval of the purchaser. Special arrangements should be
made to facilitate handling and to protect the projecting connections for damage in transit.
The Reactor shall be transported filled with inert gas preferably Nitrogen gas. The Bidder shall
ensure that adequate pressure of gas is maintained inside the tank throughout during
transportation by sending escorts and required apparatus and equipment with the Reactors.
All parts shall be adequately marked to facilitate field erection. Boxes and crates shall be marked
with the contract number and shall have a packing list enclosed showing the parts contained
therein. However, the verification of accessories shall be done in presence of supplier’s
representative.
21.44 TESTS
The manufacturer shall carryout routine test, additional routine tests and type tests on the
Reactor as per the relevant Indian Standard IS 5553 & IS-2026 with latest amendments, IEC
60076 & IEC 60289, CBIP Publication No 295, IEEE or any equivalent International Standard
.The details of tests are specified hereunder. It should be specifically noted by the bidder that
testing of each & every Reactor included in this Bid specification shall be carried out at the
manufacturer’s works in fully assembled condition complete with all fittings & accessories.
It is to note that on receipt of call from your end for final inspection of each unit, testing of the
unit shall be carried out in presence of our inspecting officer in line with approved QAP.
All routine and additional routine tests listed in the IEC 60289, IS 5553, IS: 2026 part-I will be
carried out on each shunt reactor on “free of cost” basis.
a.Switching Impulse test at 1050 KVp on line terminals as per IS 2026 part III.
b.Induced over voltage with partial discharge measurement at 364 KVAC (1.5PU/√3) for
60 minutes during which Partial Discharge level shall not exceed 100 pC.
c.Separate source voltage withstand test at 230 KV AC for one minute.
Oil Leakage Test on Tank : All tanks and oil filled compartments shall be completely filled
with air or oil of a viscosity not greater than that of insulating oil conforming to IS
335 at the ambient temperature and subjected to a pressure equal to normal tank pressure plus 35
kN/m.sq.(5psi), measured at the base of the tank. The pressure shall be maintained for a period
not less than 12 hours for oil and 1 hour for air during which time no leakage shall occur.
21.45.2 Capacitance & Tan delta Test: The measurement of capacitance and tan delta to
determine capacitance between winding & earth shall be carried out before and after series of
dielectric tests.
The measured Tan delta values of winding shall not exceed 0.45% at 20oC (degree
centigrade) temperature. In case Tan delta of Reactors during testing at works of
manufacturer is measured above maximum ceiling of 0.45%, then AEGCL reserves right
not to accept such of the Reactor. This requirement is to be confirmed specifically by the
Bidders in their offer.
21.45.3 Test On Bushings: Measurement of Tan-Delta, Capacitance & IR values of 400 KV &
132 KV bushings before & after tests on reactor.
IR values
a.Between Core and end frame
b.Between core and tank
c.Between End frame and main tank.
The measured IR value should be more than 1000 M. Ohms.
Measurement & recording of currents with application of 400v 3 phase a.c supply on HV
side
a.Between Core and end frame
b.Between core and tank
c.Between End frame and main tank.
21.45.6 Pressure Relief Device Test: All pressure relief devices provided in each reactor shall
be subject to test for its successful operation. It shall operate before reaching the test pressure
specified in clause 24.3 (C) of this specification. The device shall seal off after the excess
pressure has been relieved.
21.45.7 Measurement of Dew point prior to dispatch of the unit, filled with N2 gas: Dew
point is the temperature at which water vapours present in the gas filled in the Reactor begins
to condense. The transportation of Reactor from the factory of manufacturer’s works upto the
purchaser’s site is done with dry Nitrogen gas filled condition, due to weight limitation.
Positive gas pressure say 0.25 kg/cm2 is normally maintained during transportation as well as
during storage. In case positive pressure is not maintained then due to hygroscopic properties
of insulation used in Reactor possibility of absorption of moisture in insulation cannot be
overruled. Therefore, to check the dryness of insulation, measurement of dew point at factory
prior to dispatch and at site prior to oil filling is necessary and to be carried out. It may be
noted that dew point shall be measured at factory prior to dispatch. Temperature, pressure and
dew point at the time of gas filling (reading taken after stabilization) shall be taken and painted
on the Reactor tank. The minimum permissible value of dew point shall be (–) 25oC at normal
temperature and pressure.
21.45.8 DGA test of oil of main tank of Reactor before (initial) & after completion of all testing
shall be done and test results shall be submitted to the purchaser.
The temp. rise test shall be carried out at rated voltage of 420 KV, which is 5% more than the
system voltage. Thus, temperature rise test for shunt reactor shall be carried out at 420kV with
current at 420kV.
Gas chromatographic analysis of oil shall be conducted before and after heat run test and the
values shall be recorded in the test report. The sampling shall be in accordance with IEC-
60567. For the evaluation of the gas analysis in temperature rise test, a method will be
proposed which is based on the rate of increase of particular gases and the permissible limits of
minimum detectable value of gases and the maximum limit will be mutually discussed and
agreed upon between the Purchaser and Supplier. This shall be treated as reference during
maintenance of reactor in future.
The calibration of OTI and WTI shall be done by Reactor Manufacturer and these calibrated
OTI, WTI shall be used during testing of reactor. The Sr. No. of WTI, OTI shall be recorded
during testing of reactor and these indicators only shall be supplied with the reactor.
(B) Lightening Impulse Test at 550 KVp on Neutral as per IEC60076/ IS 2026
(C) Tank tests: Following Vacuum and Pressure tests shall be carried out.
(a) Vacuum Test (Fabrication Stage): One Reactor tank of each design shall be subjected to
the vacuum of 760 mm of Hg. The tanks designed for full vacuum (760 mm of mercury at sea
level or the barometric reading at the location of test) shall be tested at a maximum internal
pressure of 3.33kN/m.sq. (25 mm of Hg or 25 torr) for one hour i.e. 760-25=735 mm of Hg at
sea level and (Barometric reading -25mm Hg) at other location. The permanent deflection of
flat plates after vacuum has been released shall not exceed the values specified below :
Note: During vacuum testing, provisions of any kind of internal supports are not acceptable.
This fact is to be kept in view while finalizing design of tank.
(b) Pressure Test (Fabrication Stage): One Reactor tank of each design, its radiator,
conservator vessel, and other fittings together or separately shall be subjected to a pressure
corresponding to twice the normal head of oil or to normal pressure plus 35 kN/Sq.m,
whichever is lower, measured at the base of the tank and will be maintained for 1 hour. The
permanent deflection of the flat plate after the excess pressure has been released shall not
exceed the figures specified above for vacuum test as per clause 24.3(C) (a).
Note: -Permissible deflection indicated in table above are applicable for vacuum as well as
pressure test, separately.
21.47 SPECIAL TESTS ON SHUNT REACTORS : Following special tests other than
type and routine tests shall also be carried out on one rector of each manufacturer (if there are
more than one manufacturer)
21.47.1 Measurement of zero seq. impedance as per CL.16.10 of IS: 2026 Part-I.
21.47.2 Measurement of acoustic noise level before and after energizing the Reactor. as per
CL.16.12 of IS:2026 Part-I, NEMA TR1 & IEC 60076-10. Detailed calculations & conditions
outlined in the IEEE standard C 57.12.12.90 shall be followed.
21.47.3 Measurement of harmonic level i.e. fundamental, 3 rd,5th,7th,9th,11th.Measurement of
harmonic level of no load current i.e. fundamental, 3 rd, 5th,7th,9th,11th and total harmonic
distortion of voltage & current as per CL.16.13 of IS:2026 Part-I. Details of rms voltage
applied & print out of Harmonic Analyser shall be enclosed with report.
21.47.4 Magnetisation curve measurement & Knee point voltage measurement.
21.47.5 Marshalling Box of reactor shall be tested for IP: 55 protection in accordance with IS:
13947 (category-I) at CPRI / ERDA.
21.48 To summarize the requirement of tests for 400KV Shunt Reactor covered in this
Bid specification, are as under :
Number of
Clause
Nature of tests Reactors to be Test charges
No.
tested
1 2 3 4
24.2. Routine tests & On each unit While offering for the Bid, cost of all
additional routine these tests for specified no. of units as
tests per column ‘3’ should be included in
24.3 Type test: the total Bid price. Thus no
(A) Temperature rise On One unit additional charges shall be payable
test for any of the tests and therefore,
(B)Impulse test On One Unit offered Bid price
(C)Vacuum and On One unit
pressure test
24.4 Special tests On One unit
24.7 Tests at site On each unit
21.49 Specific approval of oil test results of oil proposed to be used for testing of
transformer in factory shall be obtained by the manufacturer from the purchaser before
filling in the unit. AEGCL shall not accept any other oil for testing purposes having lower
parameters than those specified in the Bid.
21.50 TESTS AT SITE: On delivery /receipt, after erection at site, the Reactor shall be subject
to the following tests, in presence of supplier's engineer.
21.50.1 Immediately upon receipt of Reactor at site and before unloading of Reactor from
trailer, core earthing, end frame earthing & tank earthing shall be checked. Only after
satisfactory verification that there is no multiple core earthing in Reactor, unloading of Reactor
shall be undertaken.
i) Insulation resistance test and polarisation index.
ii) DGA of oil and Dielectric, Tan-Delta, resistivity & moisture content
test of oil .
iii) Measurement of mutual reactance & magnetizing current at low
voltage.
iv) Measurement of winding resistance.
v) Tangent Delta, capacitance and insulations resistance tests of bushings.
vi) Dew point measurement & recording of pressure of Nitrogen gas.
vii) SFRA test
viii) After receipt of Reactor at site physical inspection shall be done for
checking any physical damage to Reactor tank & accessories. Further data of
Impact recorder shall be analysed for any changes before unloading of Reactor.
21.51 CHECKS & TESTS: Following checks & tests shall be carried out by Manufacturer at
different stages of manufacture & supply of Reactor and these reports shall be sent to the
purchaser for records :
a) Check completed Reactor against approved out line drawing, provision for all fittings,
finish level etc.
b) Jacking test on the assembled Reactor.
c) Measurement and recording of temperature and drying time during vacuum treatment.
d) Check for completeness of drying by measuring IR values & Tan Delta.
e) Certification of all test results.
21.52 TEST REPORTS: After all tests have been completed seven certified copies of each
test report shall be furnished. Each report shall supply the following information :-
i) Complete identification data including serial number of the Reactor.
ii) Method of application, where applied, duration and interpretation of results for each test.
Complete diagram of test circuits and details of test equipments including auxiliary
transformer, Instrument transformer shall be furnished.
iii) Where ever applicable parameters to be corrected to 75º C temperature.
iv) Test certificates of all the accessories and stage inspections.
21.53 TOOLS: The Reactor shall be supplied with a full outfit of tools, spanners, special tools
for assembling and dismantling Reactors with a rack for holding them as per Annexure IX. All
spanners shall be double ended & case hardened. The quantity of each item of tools shall be
indicated by the Bidder in Bid.
The bidder may furnish any other drawings which he considers necessary for giving complete
information about his equipment.
After receipt of an order, the successful bidder shall have to furnish, the following drawings in hard
as well as AutoCAD format, for approval of the purchaser.
General outline drawing showing front, side elevations and plan of the reactor and accessories
with detailed dimensions.
Detailed foundation drawing.
Drawings of each type of bushings, lifting dimensions, clearances between terminals and
ground, quantity of insulating oil, name plate details etc.
Large scale drawing of the winding indicating arrangement of terminal connections.
• Control and wiring diagrams and drawings showing temperature indicator, alarm circuits etc.
• Drawings showing Construction and mounting details of marshalling box / boxes.
• Detailed drawing showing wheel loading and its centre of gravity.
v) After receipt of the order, the successful bidder shall prepare a program for submission of
various drawings for the approval of the purchaser within commencement period.
vi) Drawings, diagrams, instructions and reports shall be identified by descriptive title indicating
their application to the equipment offered. All drawings and data shall be annotated in English
Language; Dimensions shall be in Metric system.
vii) The bidder may submit any other drawings found necessary in addition to the drawings
mentioned above or as asked during detailed engineering.
21.55 QUALITY ASSURANCE PROGRAMME: The Bidders must establish that a proper
quality assurance program is being followed by them for manufacture of Shunt Reactor. In
order to ensure this, suitable QAP should form a part of the technical Bid, which will be
submitted against this Bid specification. The quality Assurance Program must have a structure
as detailed in the following paragraphs.
i.Customers Specifications and Contract Review: The quality assurance and failure
prevention starts with careful study and scrutiny of our technical specifications and
requirements. The supplier shall carefully study all the technical parameters and other
particulars & the supplier shall categorically give his confirmation that these requirements shall
be met in a satisfactory manner.
ii.Design Control: The supplier shall furnish the checks exercised in design calculations
particularly in respect of short circuit forces and method of clamping end coil to show the
healthiness of the design. The salient features of design together with the certificates of design
engineers will have to be made available to the Purchaser.
iii.Engineering Documents :The supplier shall give complete information regarding copper
conductor, insulating paper, core materials, gaskets etc. bringing out the detailed description
and specification of these items with explanation as to how our requirements are being met in
this respect.
It will however be obligatory on the part of Bidder to allow third party inspection of all-
important material e.g. copper, core material, Insulating cylinder etc. Bidder shall furnish
certificate that the Reactor shall be manufactured with the input material approved by the
Purchaser and in case during independent third party inspection any of the above material is
found different than from approved list of vendors, in that case Purchaser reserves the right to
summarily reject complete Reactor and the manufacturer has to replace complete unit made out
from all input material from the vendors approved by the Purchaser.
v.Programme Chart: Based on above QAP and offered delivery schedule a tentative program
chart indicating period for various manufacturing/testing activities shall be submitted along
with QAP. The program chart should specify periods for various activities i.e. design, ordering
of new materials, assembly, testing etc.
It should be noted by the Bidders that submission of QAP with the Bid is an essential
requirement.
21.56.2 The successful Bidder shall keep the Purchaser informed in advance of the time of
starting and of the progress of manufacture of equipment at its various stages of
manufacturing, so that arrangements could be made for inspection.
21.56.3 No material shall be dispatched from its point of manufacture unless the material has
been satisfactorily inspected and tested.
21.56.4 The acceptance of any quantity of Reactor & its accessories shall in no way relieve
the successful Bidder of his responsibility for meeting all the requirement of this specification
and shall not prevent subsequent rejection if such equipments are later found to be defective.
Acceptance of condition regarding stage inspection at various stages which will be intimated to
successful Bidders shall be the essence of the contract to be placed against this Bid.
21.57 Inspection Programme: The Bidder shall chalk out a detailed inspection and testing
program for manufacturing activities for the various components. The Purchaser reserves the
right to get carried out any tests by a third party. All Cost of inspection/tests shall be borne by
the Bidder.
21.58.1 The supplier shall indicate the inspections and checks carried out at various stages of
the manufacture of the Reactors. A complete record of stage inspection would be kept by the
supplier and this record should be made available for inspection by the representative of the
Purchaser. The supplier should indicate the manufacturing program and the Purchaser will
have a right to depute its inspecting officers during the manufacture. Some of the
inspecting stages are tank during fabrication, coil winding, core building, assembly of coil on
core, the condition of the coil and core after the treatment in vacuum chamber, assembly within
the Reactor tank.
21.58.2 It may be noted that stage inspection for first unit or all the units, at our discretion,
shall be done by us at the following stages.
(a) Fabrication stage of tank: After fabrication, tank shall be inspected for measurement of its
dimensions, thickness of sheets used and leakage test by applying requisite pressure/vaccum.
(b) Building up of Core : After the core is built but before its clamping, our representative
will inspect the core to take complete weight of the core and also to measure approximate
core loss.
(c) Preparation of Winding : Once the coils are prepared but before the same are fitted on to
the core, stage inspection shall be done to take various measurements and also for weighment
of total weight of coil . Measurement of resistance shall be taken and for this purpose, a small
piece of conductor for winding shall be made available by the manufacture.
(d) Core Coil Assembly After VPD :
The Bidder has to submit with the Bid complete details of Drying out process of Reactor
adopted in its works. The details should include cycle, description, termination rate,
process diagram , size of oven , measurement method of moisture extracted etc.
Apart from the above, the Purchaser also reserves the right to carry out stage inspections at
other stages also, for which advance intimation shall be given and all necessary cooperation
shall be rendered by the manufacturer.
21.59.2 The WTI & OTI shall be calibrated during testing of Reactor and Serial Nos. of these
instruments shall be recorded in test reports. The WTI & OTI used during testing shall be
dispatched with the Reactor so that installation of same OTI & WTI on Reactor is done which
are utilized during testing of Reactor at suppliers works. The Bushings and Radiators on
Reactor (if heat run test is conducted) during testing of Reactor at manufacturers works are
required to be supplied with the same Reactor to avoid any mismatch / misalignment etc.
during assembly of Reactor. This should be noted for strict compliance and confirmed
specifically.
21.59.3 Whenever inspection call for a Reactor is given, the letter of inspection call will
accompany the following:
22.59.3.1 List of various fittings and accessories which are ready at the works and will be
offered for inspection. The Inspecting Officer will carry the list and check the items declared to
have been offered for inspection
22.59.3.2 It is expected that before a Reactor is finally offered for inspection, internal
testing of the Reactor for various important parameters like winding resistance, Reactor losses,
IR values etc. are already done. Routine test report for such tests shall also accompany the
letter of inspection call so that the Inspecting Officer at the time of inspection may verify the
parameters brought out in the preliminary report. Details of all tests should be clearly brought
out.
22.59.3.3 In case, for any reason’s inspection is not completed or equipment is not found
to be complete with all accessories as per confirmation given with the letter of inspection call,
the Purchaser will reserve the right to recover the complete cost of deputation of inspecting
team to the works of the manufacturer.
21.60 STORAGE, HANDLING & SHIPPING: When the Reactor is declared ready, the
manufacturer has to identify each and every item associated with this unit and a `Complete
Packing List shall be prepared in advance. The equipments shall be stored and handled
properly in shipping depot, while the same is under process of dispatch. The manufacturer
should ensure dispatch of all the related items and accessories with a particular unit of Reactor
along with tank. Bushing, radiators and other accessories of the Reactor should not be withheld
for use subsequently on units for testing purposes. If there are
Any items procured from sub-contractors which are to be directly installed like
instrumentation, panels, control gear etc. test and inspection report for the same shall be kept
separately and made available to purchaser’s inspecting officers.
It may be noted that NO CHANGE in any accessory or associated equipments after passing all
the test successfully shall be allowed and if this is subsequently detected it shall be binding on
the Bidder to replace with the same item with which the initial test were conducted at his part
failing which the entire test shall become null and void. The Purchaser at his discretion may
consider for rejection of the units thus supplied. The entire cost, for replacement of such
rejected units thus supplied and for repeating acceptance test, shall be borne by the Bidder.
In case for attending to defect in any accessory or inspection/ replacement of the accessory,
which may be bought out item for the Bidder; services of engineer of original manufacturer is
required, the same will be organized on immediate basis by the Bidder at his cost.
The Bidders are required to furnish, the following details of packages for supply of complete
quantity of materials/one complete equipment:
a.Total number of packages
b.Dimensional details of each package.
c.Weight of each package.
d.Nature of content (i.e. fragile or non-fragile)
In addition, the Bidder from outside India offering CIP prices shall also indicate the port of
entry in India.
21.61 For all Reactor included in the Bid specification, provisions and stipulations as per
CBIP Manual on Transformers/Reactor in regard to the following except as modified in
this document should be strictly adopted
equipment.
Further the supplier shall mount Vehicle tracking system (GPRS/ GPS/ GSM based) to track
the exact position of the vehicle on which the Autotransformer is being loaded for
transportation and during detailed engineering take approval for the equipment installed.
Note:- No charges shall be payable for installation of electronic impact recorder &
vehicle taking system during transportation while quoting transportation charges, this
aspect is to be kept in view.
ANNEXURE – I
LIST OF FITTINGS AND ACCESSORIES TO BE PROVIDED WITH EACH SHUNT
REACTORS
Each 400 KV 125 MVAR Reactor shall be provided with the following accessories.
One no. Dial type Thermometers for oil: A dial type indicating thermometer with
repeater of robust pattern mounted on one side of FCC at a convenient height to
read the temperature in the hottest part of the oil and fitted with alarm and trip
contacts. ROTI shall also be mounted on RTCC panel.
WTI for winding: These shall be indicating type, with repeater responsible to the
combination of top oil temperature and winding current, calibrated to follow the
hottest spot temperature of the Reactor winding. The winding temperature indicator
shall operate a remote alarm before the hottest spot temperature approaches a
dangerous value.
One magnetic type oil level gauge and prismatic oil level guage having 3
overlapped windows with low level alarm contacts and dial showing minimum,
maximum and normal oil levels.
One plane oil level gauge with three overlapped windows on other side of the
conservator shall also be provided.
Valves: 4 nos valves are required to be provided in each thermosyphon filter. Out
of 4 nos, 2 nos shall be provided for the purpose of disconnecting the oil flow between
the main tank and thermosyphon filter and 2 nos are to be provided for the purpose of
filtration of charge of the thermosyphon without disconnecting the thermosyphon from
body. Necessary valves required for NIFPS shall be provided.
A set of air release valves/ plugs on the top of the radiators and also at appropriate
places.
One double float gas detector relay (Buchholz relay) with alarm and tripping
contacts to detect accumulation of gas and sudden changes of oil pressure,
complete with shutoff valves and flanges couplings to permit easy removal without
lowering oil level in the main tank, a blend valve for gas venting, and test valve.
Make of buchholz relay shall be as per our discretion.
Heat exchangers or radiators complete with shut off valves and with facility for
oil draining arrangement.
Oil conservator, with required accessories for main tank.
Air cell type breathing arrangement with oil preserving equipment complete in all
respects of reputed make.
Eye bolts and lugs on all parts for easy handling.
Two grounding earthing terminals at diagonally opposite corner of tank.
One rating and diagram plate and one valve schedule plate.
A set of minimum 4/8/12 nos. (as per requirement) flanged bi- directional wheels
for rail mounting (for 1676 mm rail gauge.)
Number of Radiator Banks for ONAN cooling of the Reactor.
Suitable jacking pads, haulage lugs and haulage holes.
Inspection window & man holes with bolted cover as per Annexure-IV
Thermosyphon filter assembly (minimum 2 nos.) with complete details.
Lifting arrangement for the complete Reactor, core coil assembly and also tank.
One detachable bolted type MS ladder each on main tank and conservator tank
For the purpose of taking earthing connection from the neutral bushing, adequate
number of brackets with small support insulators shall be provided on the body of
the tank so that earthing could be arranged by purchaser near the earthing pit of
Reactor itself.
A separate weather proof Marshalling Box containing dial type thermometer,
winding temperature indicator and terminals of dial type thermometer, buchholz
relay, MOG etc.
Three separate connection i.e. connection from core, connection from end frame
and connection from tank shall be brought out on to a terminal box with cover.
Arrangement for inter connecting these terminals in the terminal box shall also be
provided. This arrangement shall facilitate verification of core, end frame and tank
insulation.
Minimum 2 nos Silica gel breathers.
All Reactors shall be supplied with a full outfit of tools, spanners, special tool. For
assembly and all spanners shall be double ended and of very good quality of
"Gedore" or "Taparia" or equivalent make.
The equipments and accessories furnished with the Reactor shall be suitably
mounted on the Reactor for ease of operation, inspection and maintenance and the
mounting details shall be subject to the approval of the purchaser. All valves shall
be provided either with blind companion flanges or with pipe plugs for protection.
Indication, alarm and relay equipment shall have contacts suitable for operation
with 220V DC supply. Any other accessories or appliances recommended by the
manufacturer for the satisfactory operation of the Reactor shall also have 220V DC
as input.
2. NIFPS: Nitrogen injection type fire prevention & extinguishing system with flow
sensitive conservator isolation valve shall be provided for all the Reactors as per relevant
clause.
3. OLMD: On Line Monitoring Device shall be provided for all the Reactors.
4. Bushing current transformers as per Section-I of Bid specification.
5. COMPATABILITY FOR SCADA OPERATIONS:
The Reactor should be compatible for SCADA connectivity. Further, ROTI and RWTIs shall
suit the following operation through SCADA.
a. Winding Temperature Indications on SCADA.
b. Oil Temperature Indication on SCADA.
The necessary fittings required for above SCADA operation are to be provided in addition to
the conventional fittings.
6. Accessories, which are not included in the above Annexure but details of which are
given in Bid specification and which are necessary for satisfactory operation of Reactor
shall be deemed to have been included in the accepted price without any extra cost to
the Purchaser.
ANNEXURE -II
LIST OF REACTOR ACCESSORIES AND THEIR TEST-CERTIFICATES TO BE
SUBMITTED BY MANUFACTURERS/APPROVED VENDORS
ANNEXURE – III
The following drawings and data for each item are to be submitted after placement of
order:-
(a) Outline dimensional drawings of Reactor and its accessories including conservator
complete with Bill of material and details of all parts, their quantity, rating & name of
Vendors indicating clearances of Reactor body from live terminals i.e. 400 KV & 132 KV.
(b) Drawing of Reactor tank with location of inspection windows, thickness of
side/bottom/top of tank, details of stiffener.
(c) Drawing indicating core construction with complete details of core dimensions, core
packet dimensions, no. of gap/gap length; thickness of core laminations; Gross and net core;
wt. of complete core.
(d) Drawing indicating core belting arrangement with details of belting, belting material etc.
(e) Large scale dimensioned drawings for 400 KV windings of the Reactor ; size and no. of
parallel of windings and of, cooling ducts, coil clamping arrangement, no./size & location of
pressure screws, clamping ring; top yoke arrangement etc.
(f) Detailed drawing of Reactor tank with complete core and winding indicating clearances
inside Reactor tank as also passage and space for free movement of at least two persons for
inspection of active parts etc.
(g) Schematic diagram showing the flow of oil in the cooling system as well as each limb and
winding. Longitudinal and cross-sectional views showing the duct sizes, cooling pipes etc. for
the Reactors/radiators drawn to scale.
(h) Drawings giving the weights for foundations.
(i) Combined Rating and diagram plate, which should also include details of guaranteed and
measured total losses as also winding resistances, impedance and reactance, weight of
copper/core/steel/oil & total weight.
(j) Schematic control and wiring diagram for all auxiliary equipment and control cubicle.
(k) Drawing showing constructional details, dimensions, mechanical & technical
particulars of bushings. Arrangement of terminals and details of connection of bushing shall
(o) Oil filling instruction plate for conservator fitted with Air cell breather arrangement
including equalizing arrangement if any required at the time of taking full Vacuum at site.
(q) Drawing of conservator indicating internal details of air cell MOG, oil level gauge and
silica gel breather pipe fitting arrangement.
(r) Drawings of all 400 KV & 132 KV bushings with complete details meeting Bid
specification requirement.
(s) Drawings of terminal connectors indicating plate thickness, no. of nut bolts with size and
other details.
(t) Drawing of detachable bolted type MS ladder with its complete details and fitting
arrangement on Reactor/ conservator tank.
(u) Drawing for neutral earthing arrangement indicating voltage rating of insulators and its
fitting arrangements, size of copper strips, terminal connectors etc.
(v) Detailed drawing indicating two views of all valves provided in the Reactor tank.
(w) Drawing of Thermosyph on filter with fixing arrangement with Reactor tank.
(y) Drawing showing weights of Reactors, Marshalling box with distance from central line of
Reactor for casting of civil foundation for Reactor and associated equipments.
(z) Drawing of Earthing terminal box showing earthing arrangement for core, end frame, tank
giving details of voltage class and current rating of terminal bushings.
(aa) Drawing indicating insulation thickness details and other arrangement provided between
core assembly and bottom yoke and base of bottom of tank.
(ab) Drawing indicating details of ‘O’ ring gasketting arrangement provided in Reactor tank
covers.
(ac) Drawing of stiffeners provided on top, each faces/sides of tank with their number and size.
(ad) Drawing indicating number, location, size of shields/ magnetic shunts and its material
provided inside the tank .
(ae) Drawing indicating internal details of Reactor giving complete details of clearances from
live parts.
(af) Drawing of internal winding termination arrangement indicating minimum clearance
between core and take off lead.
(ag) Drawing for Lead termination to bottom of 400 KV & 132 KV bushings.
(ah) Drawing of On Line Monitoring Device with details of mounting arrangement.
(ai) Internal drawing & design of Core & Winding indicating all attachment with identification
numbers, description including take-off arrangement of lead connection for Core & End frame
and related Bill of Material
(aj) Locking arrangement drawing for tank top cover, core & winding with complete
dimension & details.
(ak) Plan view of the bottom of Bell/Conventional Tank for complete details of core coil
resting arrangement, indicating clearly dimensional details, material of insulation, clamping
arrangement with details of nuts/ bolts, clearance from all sides provided at bottom.
(al) Drawing indicating complete details, dimensions & fixing arrangement of static end rings
if used.
(am) Other relevant drawings.
As soon as possible after the award of the contract the manufacturer shall supply four (4)
copies of the drawings as listed out above, which will describe the equipment in details for
approval and shall subsequently provide ten complete sets of final drawings, one of which shall
be auto- positive suitable for taking blue prints. Ten sets of instruction books, operation and
maintenance manuals and spare part bulletin, shall be supplied. In addition to above two sets of
manuals and drawings with test certificates for each unit to be dispatched as per dispatch
instructions.
APPENDIX I
Calculation for Hot Spot winding temperature for EHV Reactors
Overloading capability of the reactors and also the loading capability of reactors with out exceeding
temperature rise of winding beyond specified limits have been indicated in the technical specification.
In this regard following calculation based on maximum ambient air temperature as 50 degree
centigrade and maximum yearly average weighted air temperature as 32 degree centigrade using the
under mentioned formulae or any other authentic formulae shall be furnished.
-t/ τ 2y
θc = θa + ∆ θ b0 + (∆ θ b- ∆ θbo) ( 1- e) + (∆ θ c τ - ∆ θb τ) k
2 x
{(1+dk}
∆ θb = ∆ θ br --------------
{(1+d)} x
Where,
SIGNATURE
WITH SEAL OF BIDDER
APPENDIX -2
Tests on NGR (as applicable)
10. High voltage with stand test on auxiliary equipment and Routine wiring after assembly
11. Tank vacuum test Routine
terminating all control, alarm and auxiliary circuits. It shall be provided with hinged
doors with provision for locking and removable gland plates to be drilled at site.
Inspection window shall be provided for observation of the instruments without
opening the cabinet. It shall be mounted so as to provide convenient access from
ground level.
22.3.5. The cabinet shall be fitted with a thermostatically controlled anti-condensation
heater, a 15A, 1 phase, 5 pin socket outlets with switch and a cubicle illuminating
lamp suitable for operation on 240 V AC 50Hz supply.
22.3.6. Circuit breakers shall feature high repeatability of absolute closing time over a wide
range of parameters (ambient temperature, pneumatic pressure, control voltages,
etc).
22.3.7. Main poles shall operate simultaneously. There shall be no objectionable rebound
and the mechanism shall not require any critical adjustment. It shall be strong, rigid,
positive and fast in operation.
22.3.8. Disagreement circuit shall be provided which shall detect pole position discrepancy.
22.3.9. The design of the circuit breaker shall be such that contacts will not close
automatically upon loss of gas/ air pressure.
22.3.10. Closing release shall be capable of operating within the range of the rated voltage as
specified in the data sheet. Shunt trip shall operate satisfactorily under all operating
conditions of the circuit breaker up to the rated breaking capacity of the circuit
breaker with in the range of the rated voltages specified in the Data sheet.
22.3.11. Working parts of the mechanism shall be of corrosion resisting material. Bearings
which require grease shall be equipped with pressure type grease fittings. Bearing
pin, bolts, nuts and other parts shall be adequately pinned or locked to prevent
loosening or changing adjustment with repeated operation of the breaker.
22.3.12. All controls, gauges, relays, valves, hard drawn copper piping and all other
accessories as necessary shall be provided including the following:
22.3.13. Low pressure alarm and lock out relay with adjustable pressure setting suitable for
operation on DC system
22.3.14. A no-volt relay for remote indication of power failure for compressor motor/ Spring
Charge motor.
22.3.15. As long as power is available to the motor, continuous sequence of closing and
opening operations shall be possible.
22.3.16. After failure of power supply to the motor, at least one open-close-open operation
of the circuit breaker shall be possible.
22.3.17. Motor rating shall be such that it requires only about 30 seconds for full charging of
the closing spring.
22.3.18. Closing action of the circuit breaker shall compress the opening spring ready for
tripping.
22.3.19. During closing, springs are discharged and after closing of breaker, springs shall
automatically be charged for the next operation. Facility for manual charging of
closing springs shall be provided. Mechanical interlocks shall be provided in the
operating mechanism to prevent discharging of closing springs when the breaker is
already in the closed position.
22.5.5. Each pole shall form an enclosure filled with SF6 gas independent of two other
poles (for 245 & 145 kV CBs) and the SF6 density of each pole shall be monitored.
For CBs of voltage class of 36 kV, a common SF6 scheme/density monitor shall be
acceptable.
22.5.6. The dial type SF6 density monitor shall be adequately temperature compensated to
model the pressure changes due to variations in ambient temperature within the
body of circuit breaker as a whole. The density monitor shall have graduated scale
and shall meet the following requirements:
It shall be possible to dismantle the density monitor for checking/replacement
without draining the SF6 gas by providing suitable interlocked non return
valve coupling.
22.8.0. INTERLOCKS
22.8.1. Key release mechanical interlocks shall be incorporated in the operating mechanism
for interlocking with the associated isolators, so that operation of the circuit breaker
is dependent on a "key-trapped" situation. In addition, electrical interlocks with
associated isolators shall be provided.
22.10.0.ACCESSORIES
22.10.1. Gas Pressure Detector
The circuit breaker shall be provided with gas pressure monitor with temperature
compensation for initiating alarm and locking the operating mechanism in the event
of abnormality. Gas pressure monitor shall be provided for each pole
individually for 220 kV and 132 kV Circuit Breakers.
22.10.2. Position Indicator
Each pole of the circuit breaker shall be provided with a position indicator.
22.10.3. Terminals
Each circuit breaker shall be provided with suitable terminal pads of high
conductivity aluminium alloy for connecting to the line.
22.10.4. Auxiliary Switches
Each circuit breaker shall be equipped with auxiliary switches with sufficient
number of contacts for control, indication and interlocking purposes. Ten normally
open and ten normally closed contacts shall be provided as spares. All contacts shall
be rated for the DC voltage specified in data sheet.
22.10.5. Terminal Blocks
All accessories and control devices shall be completely wired. All wirings which
are connected to external circuit shall be terminated on terminal blocks installed in
the control cabinet. The terminal blocks provided shall have twenty (20) percent
spares.
22.10.6. Operating mechanism housing shall be supplied with all required accessories
including the following:
22.11.0.SUPPORT STRUCTURES
22.11.1. The Circuit Breakers shall be suitable for mounting on steel structures.
22.11.2. The support structure shall be of steel hot dip galvanised type. The height of
support structure shall be designed to keep the bottom most live part and bottom of
insulators of circuit breakers at minimum clearance from the plinth as specified in
data sheet.
22.11.3. All necessary galvanised bolts, nuts and washers to complete the erection shall be
furnished including the embedded anchor bolts for securing the supporting structure
to the concrete foundations.
22.12.0.NAME PLATES
22.12.1. All equipment shall have non-corrosive name plates fix at a suitable position
indelibly mark with full particular there on in accordance with the standard adapted.
22.13.0.EARTHING
22.13.1. Two earthing pads shall be provided on each supporting structure. Each control
cabinet or terminal box mounted on the supporting structure shall also be connected
to an earthing pad. Separately mounted control cabinets shall be provided with two
earthing pads adjacent to the base of the cabinet. The earthing connection shall be
bolted type and suitable for receiving 65mm x 12mm MS strip.
22.14.0.TERMINAL CONNECTORS
22.14.1. The equipment shall be supplied with required number of terminal connectors of
approved type suitable for ACSR conductors. The type of terminal connector, size
of connector, material, and type of installation shall be approved by the Employer,
as per installation requirement while approving the equipment drawings.
22.15.0.TESTS
22.15.1. All routine tests shall be carried out in accordance with relevant IS. All
routine/acceptance tests shall be witnessed by the Employer/his authorised
22.16.0.PRE-COMMISSIONING TESTS
22.16.1. Contractor shall carry out following tests as pre-commissioning tests. Contractor
shall also perform any additional test based on specialties of the items as per the
field instructions of the equipment Supplier or Employer without any extra cost to
the Employer. The Contractor shall arrange all instruments required for conducting
these tests along with calibration certificates and shall furnish the list of instruments
to the Employer for approval.
(a) Insulation resistance of each pole.
(b) Check adjustments, if any suggested by manufacturer.
(c) Breaker closing and opening time.
(d) Slow and Power closing operation and opening.
(e) Trip free and anti pumping operation.
(f) Minimum pick-up voltage of coils.
(g) Dynamic Contact resistance measurement.
(h) Functional checking of control circuits interlocks, tripping through
protective relays and auto reclose operation.
I II III IV V
2 No of poles 3 3
(3 Phase Ganged (3 Phase Ganged
Unit) Unit)
9 Rated Frequency Hz 50 50
10 Rated Short Circuit breaking kA RMS 40 25
current ( I )
- 3secs - symmetrical
I II III IV V
11 Rated Short Circuit making kA 2.5*I 2.5*I
current PEAK
12 Duty cycle 0-0.3 Sec - CO -3 0-0.3 Sec - CO -3 Min
Min -CO -CO
13 First pole to clear factor 1.3 1.3
14 Operating time
i) Opening Time ms Not exceeding Not exceeding
50 ms 50 ms
15 Insulation level
i) Power Frequency with kV RMS 275 70
Stand Voltage
ii) Impulse withstand kV Peak 650 170
Voltage
16 Minimum clearance between mm 1300 320
phases
21 Operating mechanism
a) Type Spring Charged Spring Charged
V 415 415
I II III IV V
23.2.0. STANDARDS
23.2.1. The equipment covered by this specification shall, unless otherwise stated be designed, constructed
and tested in accordance with the latest revisions of relevant Indian Standards and shall conform to
the regulations of local statutory authorities.
23.2.2. In case of any conflict between the Standards and this specification, this specification shall govern.
23.2.3. The current transformer shall comply also with the latest issue of the following Indian standard.
23.3.5. A complete leak proof secondary terminal arrangement shall be provided with each instrument
transformers, secondary terminal shall be brought into weather, dust and vermin proof terminal box.
Secondary terminal boxes shall be provided with facilities for easy earthing, shorting, insulating and
testing of secondary circuits. The terminal boxes shall be suitable for connection of control cable
gland.
23.3.6. All instrument transformers shall be of single phase unit.
23.3.7. The instrument transformers shall be so designed to withstand the effects of temperature, wind load,
short circuit conditions and other adverse conditions.
23.3.8. All similar parts, particularly removable ones, shall be interchangeable with one another.
23.3.9. All cable ferrules, lugs, tags, etc. required for identification and cabling shall be supplied complete
for speedy erection and commissioning as per approved schematics.
23.3.10.The instrument transformers shall be designed to ensure that condensation of moisture is controlled
by proper selection of organic insulating materials having low moisture absorbing characteristics.
23.3.11.All steel work shall be degreased, pickled and phosphated and then applied with two coats of Zinc
Chromate primer and two coats of finishing synthetic enamel paint.
23.5.8. All terminal strips shall be of isolating type terminals and they will be of minimum 10 A continuous
current rating.
23.5.9. All cable entries shall be from bottom. Suitable removable gland plate shall be provided on the box
for this purpose. Necessary number of cable glands shall be supplied fitted on to this gland plate.
Cable glands shall be screw on type and made of brass.
23.5.10.Each common marshalling box shall be provided with two numbers of earthing terminals of
galvanised bolt and nut type.
23.5.11.All steel, inside and outside work shall be degreased, pickled and phosphated and then applied with
two coats of Zinc Chromate primer and two coats of finishing synthetic enamel paint. The colour of
finishing paint shall be as follows: -
i) Inside: Glossy White
SL
A. Item Ratings and Particulars
No.
I II III IV
A Nominal system voltage 132 kV 33 kV
B Highest system voltage, kV 145 36
C Rated frequency ,HZ 50 50
D System earthing Solidly earth Solidly earth
E Insulation level
a) Impulse withstand voltage: kVp 660 170
One-minute p.f. Withstand
b)
voltage, kV (r.m.s.) 275 70
Short time current for one
F 40 25
second, kA
Minimum creepage distance,
G 4495 900
mm
H Temperature rise As per ISS As per ISS
I FEEDER C.T.
(i) No. of Cores 5 2
(ii) Transformation ratio
(iii) Rated out put
(a) Core-1 30 VA 30 VA
(b) Core-2 15 VA 15 VA
(c) Core-3 - N.A.
(d) Core-4 - N.A.
(e) Core-5 - N.A.
(iv) Accuracy class
(a) Core-1 0.2 0.2
(b) Core-2 5P 5P
(c) Core-3 PS N.A.
(d) Core-4 PS N.A.
(e) Core-5 PS N.A.
(v) Accuracy limit factor
(a) Core-1 - -
(b) Core-2 10 10
(c) Core-3 - -
(d) Core-4 -. N.A.
(e) Core-5 - N.A.
(vi) Instrument security factor
(a) Core-1 <5 <5
(b) Core-2 - -
CHAPTER 23: TECHNICAL SPECIFICATION FOR 132KV & 33KV CURRENT TRANSFORMERS (AIS)
(c) Core-3 - -
(d) Core-4 - N.A.
(e) Core-5 - N.A.
(vii) Minimum Knee point
voltage, Volts
(a) Core-1 - -
(b) Core-2 - -
(c) Core-3 1200 N.A.
(d) Core-4 800 N.A.
(e) Core-5 800 N.A.
(viii) Maximum secondary
resistance, ohm
(a) Core-1 - -
(b) Core-2 - -
(c) Core-3 3 N.A.
(d) Core-4 3 N.A.
(e) Core-5 3 N.A.
(ix) Maximum exciting current,
at Vk/4 mA
(a) Core-1 - -
(b) Core-2 - -
(c) Core-3 - N.A.
(d) Core-4 - N.A.
(e) Core-5 - N.A.
J TRANFORMER C.T.
(i) No. of Cores 5 4
(ii) Transformation ratio
(iii) Rated out put
(a) Core-1 30 VA 30 VA
(b) Core-2 15 VA 15 VA
(c) Core-3 - -
(d) Core-4 - -
(e) Core-5 - N.A.
(iv) Accuracy class
(a) Core-1 0.2 0.2
(b) Core-2 5P 5P
(c) Core-3 PS P.S.
(d) Core-4 PS P.S.
(e) Core-5
PS N.A.
(v) Accuracy limit factor
(a) Core-1 - -
(b) Core-2 10 10
(c) Core-3 - -
(d) Core-4 - -
(e) Core-5 -. N.A.
CHAPTER 23: TECHNICAL SPECIFICATION FOR 132KV & 33KV CURRENT TRANSFORMERS (AIS)
Note:
(i) It is intended to use different ratios of the same CT at the same time for various protections and
metering cores. The CTS should therefore be suitable for the above purpose by secondary
CHAPTER 23: TECHNICAL SPECIFICATION FOR 132KV & 33KV CURRENT TRANSFORMERS (AIS)
tapings only. The ratio change by secondary taps is acceptable as long as the required CT
specifications are achieved at all ratios.
(ii) The knee point voltage specified above shall be at higher ratio/ taps.
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
Applicable Standards
The Diesel Standby Generator and its components shall conform to the latest applicable standards
specified below:
24.3.1.1. DG set net out put after considering deration for engine and alternator separately due
to temperature rise in side the enclosure and on account of power reduction due to auxiliaries shall
be 100 kVA, 1500RPM, 0.8Pf, 415V, 3 phases, 50Hz. The above ratings are the minimum
requirements.
24.3.1.2 DG sets shall also be rated for 110% of full load for 1 hour in every twelve hrs of
continuous running.
24.3.2. The output voltage, frequency and limits of variation from open circuit to full load shall be
as follows
a) Voltage variation +5% of the set value provision shall exist to adjust
the
set value between 90% to 110% of nominal
Generator voltage of 415V.
24.3.3. The Diesel Generator and other auxiliary motor shall be of H class with temperature rise
limited to Class-F for temperature rise consideration.
24.3.4. NOISE LEVE & EMISSION PARAMETERS: These shall be as per latest Notification of
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
MOEF
24.4.1.1. The engine shall comply with the IS 10002/BS 5514/ISO 3046; latest edition
24.4.1.1.1. Diesel engine shall be turbo charged multicylinder V-type in line type with mechanical
fuel injection system.
24.4.1.1.2. The engine with all accessories shall be enclosed in a enclosure to make it work Silently
(within permissible noise level) without any degradation in its performance.
24.4.1.1.3. The Diesel Engines shall be directly water cooled. Cooling of water through radiator and
fan as envisaged.
24.4.1.2. The fuel used shall be High Speed Diesel oil (HSD) or Light Diesel Oil (LDO) as per
IS:1460.
24.4.2. Air Suction & Filtration
24.4.2.1.1. Suction of air shall be from indoor for ventilation and exhaust flue gasses will be let out to
outside atmosphere, Condensate traps shall be provided on the exhaust pipe.
24.4.2.1.2 Filter shall be dry type air filter with replaceable elements.
24.4.5.1. The engine shall be fitted with electronic governor suitable for class A-1 as per IS
10000.
24.4.5.2. The engine shall be fitted with a heavy, dynamically balanced fly wheel suitable
for constant speed governor duty.
24.4.6. ALTERNATOR
24.4.6.1. The alternator shall comply with BS 2613/IS 4722/IEC 34; latest edition.
24.4.6.1.1. The alternator shall be of continuously rated duty, suitable for 415 V, 3 phase, 50
Hz. Power development having brush-less, synchronous, self-excited, self-regulating
system.
24.4.6.2. The alternator shall be drip-proof, screen protected as per IP-23 degree of
Protection.
24.4.6.3. The rotor shall be dynamically balanced to minimize vibration.
24.4.6.4. The alternator shall be fitted with shaft mounted centrifugal fan.
24.4.6.4.1. It shall have the winding of class H but limited to Class-F for temperature rise
consideration.
24.4.6.4.2. The Alternator regulator shall be directly coupled to the engine and shall be
complete with the excitation system, automatic voltage regulation of +/- 1%, voltage
adjusting potentiometer and under/over speed protection.
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
24.4.6.6.1. Six (6) output terminals shall be provided in alternator terminal box. Terminals shall
be Suitable for 1 No. of single core, 3½Core 300 mm2 XLPE cable for 100 kVA DG
set. The neutral shall be formed in AMF panel. The generator terminal box shall be
suitable to house necessary cables and should be made of non-magnetic material.
24.4.6.5.1. The alternator with all accessories shall be enclosed in a enclosure to make it work
Silently (within permissible noise level)
24.4.7. COUPLING
24.4.7.1.1. The engine and alternator shall be directly coupled by means of self- aligning
flexible flange coupling to avoid misalignment.
24.4.7.2. The coupling shall be provided with a protecting guard to avoid accidental contract.
24.4.8.1.1. The engine and alternator shall be mounted on a common heavy duty, rigid
fabricated steel base frame constructed from ISMC of suitable sections.
24.4.8.1.2. Adequate number of anti-vibrations mounting pads shall be fixed on the common
base frame on which the engine and the alternator shall be mounted to isolate the
vibration from passing on to the common base frame or the foundation of the D.G.
Set.
24.4.9. PERIPHERALS
24.4.9.1.1. The Fuel tank of suitable capacity shall be provided on a suitably fabricated steel
platform. The tank shall be complete with level indicator marked in litres, filling
inlet with removable screen, an outlet, a drain plug, an air vent, an air breather and
necessary piping. The tank shall be painted with oil resistant paint and shall be
erected in accordance with Indian explosive act of 1932. Fuel tank shall be kept
outside of enclosure. The fuel piping shall be carried out to connect the D.G set kept
inside.
24.4.9.1.2. For transferring fuel to Fuel tank transfer pump is envisaged. The capacity of
transfer pump shall be adequate to fill the day tank in about 30 minutes. Fuel pump
shall be electrically driven.
24.4.9.2.1. Two nos. 24V batteries complete with all leads, terminals and stand shall be
provided. Each battery shall have sufficient capacity to give 10 nos. successive
starting impulse to the diesel engine.
24.4.9.2.2. The battery charger shall be complete with transformer, suitable rating (415 V, 3 Ph.,
50 Hz./230V, 1Ph., 50 Hz) rectifier circuit, charge rate selector switch for
“trickle”/’boost’ charge,
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
D.C. ammeter & voltmeter, annunciation panel for battery charge indication /
loading / failures.
24.4.9.2.3. The charger shall float and Boost Charge the battery as per recommendation of
manufacturer of battery. The charger shall be able to charge a fully discharged
battery to a state of full charge in 8 Hrs. with 25% spare capacity.
24.4.9.2.4. Manual control for coarse and fine voltage variation shall be provided. Float charger
shall have built-in load limiting features.
24.4.9.2.5. Ripple shall not be more than 1%(r.m.s) to get smooth DC voltage shall be provided.
24.4.9.2.7. Changeover scheme for selecting battery and battery charger by changeover switch
should be provided.
24.5.1.1. Each D.G. Set shall be provided with suitable instruments, interlock and protection
arrangement, suitable annunciation and indications etc. for proper start up, control,
monitoring and safe operation of the unit. One local AMF control panel
alongwith each
D.G. set shall be provided by the Supplier to accommodate these instruments,
protective relays, indication lamps etc. The AMF Panel shall have IP-52 degree of
Protection as per IS:12063.
24.5.2. The D.G. sets shall be provided with automatic start facility to make it
possible to take full load within 30 seconds of Power Supply failure.
24.5.3. Testing facility for automatic operation of D.G.Set shall be provided in AMF panel.
24.5.4. A three-attempt starting facility using two impulse timers and summation
timer for engine shall be proved and if the voltage fails to develop within 40 sec.
from receiving the first impulse, the set shall block and alarm to this effect shall be
provided in the AMF panel.
24.5.5.1. DG set shall be capable of being started/ stopped manually from remote as well as
local. (Remote START/STOP push button shall be provided in 415V ACDB).
However, interlock shall be provided to prevent shutting down operation as long as
D.G. Circuit breaker is closed.
24.5.5.2. The diesel generator shall commence a shutdown sequence whenever any of the
following conditions appear in the system :
a) Overspeed
b) Overload
c) High temperature of engine and cooling water.
d) High temperature inside enclosure
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
24.5.6.3. Thermostatically controlled space heaters and cubicle illumination operated by Door
Switch shall be provided in AMF panel. Necessary isolating switches and fuses
shall also be provided.
24.5.6.4. AMF panel shall have facility for adjustment of speed and voltage including fine
adjustments in remote as well as in local mode.
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
24.6.3. Arrangement shall be made for housing the Battery set in a tray inside the
Enclosure.
24.7.1. DG set enclosed in enclosure shall be installed on Concrete Pedestal 300mm above
FGL
24.8. DOCUMENTS
24.8.1. Following drawings and data sheet shall be submitted for approval:
(i) Data sheet for Engine, Alternator, Battery, AMF panel and Enclosure
(ii) GA drawing of DG set
(iii) Layout of DGset in the enclosure along with sections
(iv) GA and schematic of AMF panel
(v) Arrangement of inclined roof and pedestal.
24.8.2. The D G Set shall be supplied with
(i) D G Set test certificate
(ii) Engine Operation & maintenance Manual.
(iii) Engine Parts Catalogue.
(iv) Alternator Operation, maintenance & Spare parts Manual.
(v) Alternator test certificate.
24.9. TESTS
a) The Diesel generator sets shall be tested for routine and acceptance tests as per the
relevant IS/IEC standards.
b) The type test report for diesel engine and alternator are not required to be
submitted for the makes indicated at approved list of subvendors. For the new
makes (Other than those indicated at approved list of subvendors) type test reports
as per relevant standard shall be submitted for purchaser’s approval.
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
In addition to the checks and test recommended by the manufacturer, the Contractor shall carryout
the following commissioning tests to be carried out at site.
1. Load Test
The engine shall be given test run for a period of atleast 6 hours. The set shall be subjected to the
maximum achievable load as decided by Purchaser without exceeding the specified DG Set rating :
During the load test, half hourly records of the following shall be taken :
a) Ambient temperature.
b) Exhaust temperature if exhaust thermometer is fitted.
c) Cooling water temperature at a convenient point adjacent to the water output from the engine
jacket.
d) Lubricating oil temperature where oil cooler fitted.
e) Lubricating oil pressure.
f) Colour of exhaust gas
g) Speed
h) Voltage, wattage and current output. i) Oil tank level
The necessary load to carryout the test shall be provided by the purchaser.
5. Functional Tests
a) Functional tests on control panel.
b) Functional test on starting provision on the engine.
c) Functional tests on all Field devices.
d) Functional tests on AVR and speed governor.
6. Measurement of Vibration
The vibration shall be measured at load as close to maximum achievable load and shall not exceed
250microns.
8. The tests shall be carried out with the DG set operating at rated speed and at maximum
achievable load. Necessary correction for Test environment condition & background noise will be
applied as per IS:12065.
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
25.2.0.3 The contractor shall undertake detailed survey on the basis of the
tentative alignment fixed by the employer. The said preliminary alignment may,
however, change in the interest of economy to avoid forest and hazards in work.
While surveying the alternative route the following points shall be taken care by the
contractor.
After completing the detailed survey, the contractor shall submit the final profile
and tower schedule for final approval of the employer. The final profile and tower
schedule shall incorporate position of all type of towers. To facilitate checking of the
alignment, suitable reference marks shall be provided. For this purpose, concrete pillars
of suitable sizes shall be planted at all angle locations and suitable wooden/iron pegs
shall be driven firmly at the intermediate points. The contractor shall quote his rate
covering these involved jobs.
Only approved sag template shall be used for tower spotting and the final profiles.
However preliminary survey has been done by AEGCL and any further survey
required shall be done by the contractor.
After peg marking of the angle tower or tension towers, the contractor shall obtain
approval from the employer and thereafter pegging of suspension type tower shall
be done by the contractor and pegging of all the four legs of each type of towers at
all the locations shall be done.
When the survey is approved, the contractor shall submit to the employer a
complete detail schedule of all materials to be used in the line. Size and length of
conductor etc. are also to be given in the list. This schedule is very essential for
finalizing the quantities of all line material. The contractor shall furnish the same.
(c) The route should have minimum crossings of Major river, Railway lines,
National/State highways, overhead EHV power line and communication lines.
(d) The number of angle points shall be kept to minimum.
(e) The distances between the terminal points specified shall be kept shortest possible,
consistent with the terrain that is encountered.
(f) Marshy and low lying areas, river beds and earth slip zones shall be avoided to
minimize risk to the foundations.
(g) It would be preferable to utilize level ground for the alignment.
(h) Crossing of power lines shall be minimum. Alignment will be kept at a minimum
distance of 300 m from power lines to avoid induction problems on the lower voltage
lines.
(i) Crossing of communication line shall be minimized and it shall be preferably at right
angle. Proximity and parallelism with telecom lines shall be eliminated to avoid danger
of induction to them
(j) Areas subjected to flooding such as nalah shall be avoided.
(k) Restricted areas such as civil and military airfield shall be avoided. Care shall also be
taken to avoid aircraft landing approaches.
(l) All alignment should be easily accessible both in dry and rainy seasons to enable
maintenance throughout the year.
(m) Certain areas such as quarry sites, tea, tobacco and saffron fields and rich
plantations, gardens and nurseries which will present the Employer problems in
acquisition of right of way and way leave clearance during construction and maintenance
should be avoided.
(n) Angle points should be selected such that shifting of the point within 100 m radius is
possible at the time of construction of the line.
(o) The line routing should avoid large habitations, densely populated areas, Forests,
Animal/Bird sanctuary, reserve coal belt areas, oil pipe
line/underground inflammable pipe lines etc to the extent possible.
(p) The areas requiring special foundations and those prone to flooding should be
avoided.
(q) From the field book entries, the route plan and level profile shall be plotted and
prepared to the scales of 1:2000 horizontal and 1:200 vertical on 1 mm/5 mm/1 cm
square paper.
(r) If the difference in levels be too high, the chart may be broken up according to
requirement. A 400 meter overlap shall be shown on each following sheet. The chart
shall progress from left to right. For convenience in handling, the sheet size may be
limited to 594x841 mm (Al) size.
(s) After completing the detail survey, profiles shall be submitted to the Employer duly
spotted with tower for approval. While submitting the profiles after conducting the detail
survey, the contractor will also submit a copy of route alignment on the route map
indicating the surveyed route.
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
B. Check Survey:
(a) The Contractor shall conduct the check survey after the profiles are handed over to
the Contractor. The check survey shall include checking of deviation angles, checking of
levels at critical points. After completing the check survey, the tower spotting shall be
carried out by the Contractor and profiles shall be submitted to the purchaser for final
approval. The Contractor shall be responsible for correct setting of stubs. Discrepancies,
if any, shall be brought to the notice of purchaser and final approval shall be taken
before execution of work.
(b) The requirement of tower site levelling and revetment work, if required, shall also be
marked by the Contractor on the profiles while carrying out the detail or check survey
work.
(c) If due to site conditions any change in the tower location/provision of extension is
considered necessary compared to approve profiles, the contractor shall bring the same
to the knowledge of the purchaser well in time and get revised approval of the profile
before setting the stubs. The revised approval shall be conveyed to the Contractor by the
Purchaser.
C. Soil Resistivity:-
While carrying out detailed/ check survey work, the Soil Resistivity values will have to
be measured at convenient points along the route, not exceeding 2.50 Km between
adjacent points. The Soil Resistivity will be measured using 4 electrode method with an
inter electrode spacing of 50 M.
The following formula shall be used:
P=2πaR
Where a = Interelectrode spacing = 50M
R = Earth resistance measured in Ohms
P = Soil Resistivity in Ohm- m
The soil resistivity values shall be submitted duly marked on the route map and also in
the form of statement. The quoted rates for detailed survey/ check survey work shall be
inclusive of cost of measuring soil resistivity values along the proposed route and the
contractor will not be paid separately for this work.
D. RIGHT OF WAY (ROW)
The contractor shall refer to chapter 2 of this bidding document for obtaining ROW.
To ascertain soil parameters in various stretch, inter, the contractor shall carry
out sub-soil investigation through reputed soil consultant as approved by the
employer.
The test boring through different layers of all kinds of soil shall have to be carried
out by the contractor through the approved soil consultant as briefed hereunder.
II. Depth of boring below ground level shall be 15 M. only unless continuous
bedrock is encountered earlier. In case rock is encountered at any depth within 15
M. adequate study of rock and assessment of strength characteristics shall be done
and recommendation shall be given.
III.Undisturbed soil samples shall be obtained for the initial 4M depths at every
1.5M interval and at change of strata. After these initial 4M depths, samples shall
be obtained preferably at every 3M or where there is a change of strata, or as ad-
vised by the employer.
V. Standard penetration test as per IS: 2131 with latest amendment shall have to be
conducted in different strata and recorded properly.
VI. The ground water table shall be recorded during boring operation and incorpo-
rated in the bore log. If possible, the position of the water table just after mon-
soon period be ascertained from local people and indicated in the report.
VII. Plate Load test shall have to be conducted at special tower location.
CHAPTER 24: TECHNICAL SPECIFICATION FOR DG SET
The method and procedure of testing of soil sample to be followed shall be as per
relevant IS codes. Adequate volume of test samples shall be collected from site.
Ample shall be properly sealed immediately after recovery as specified in relevant
IS code and transported carefully to laboratory for carrying out necessary laboratory
tests to find out the following parameters of every samples. Data and time of taking of
the sample shall be recorded in the test report.
1 Natural moisture content, Liquid limit, Plastic limit and Plasticity index.
2 Bulk, dry and buoyant density of soil.
3 Void ratio (e-long P curve shall be submitted)
4 Specific gravity.
5 Grain size distribution (Sieve analysis and hydrometer analysis)
6 Tri-axial and consolidation tests (consolidation undrained and consoli-
dated drained as and when application in table, graph and drawing.
7 Permeability tests
8 Chemical tests for both water and soil samples at different layers.
9 Evaluation of safe bearing capacity at different strata for square footings
shall be done for a maximum value of 25-mm. settlements.
10 At depts. From 3M to 10M be different strata.
11 Factor of safety shall be considered as 3 for evaluation of safe bearing ca-
pacity of soil.
12 Unconfined compression test for cohesive soil (=0) if encountered.
The contractor shall make analysis of soil samples and rock cores as collected by him
in the field and approved by the employer as collected by him in the field and
approved by him in the field and approved by the employer as well as field tests and
laboratory tests. A comprehensive report shall have to be prepared by him, finally
incorporating all the data collected in proper tabular forms or otherwise along with the
analysis.
The 3(three) copies of report in the draft form shall be submitted for employer’s
approval. 6(six) copies of final report incorporation employer’s comments, if any
shall be submitted within 3(three) weeks after completion of this work.
Recommendations shall include but not be limited to the following items (a) to (p)
-------------------------------------------------------------------------------------------------
--
SL. Indian Title International
&
No. Standards
Internationally
re
co
gn
ise
d
St
an
da
rd
s.
------------------------------------------------------------------------------------------------
1. 2. 3. 4.
Part-II-1974
Part-III-1976
ofASCE/IEEE 691trans-
foundation for design and construction
mission line towers and poles.
-1989 Designs)
36. IS 5613 Code of practice for
(Part-II/Sec-2) design, installation and
-1985 maintenance of overhead
(Part-III/Sec.2) power lines (Section 2:
-1989 Installation and maintenance)
37. IS 6610-1972 Specification for heavy
washers for steel structures.
38. IS 6639-1972 Hexagonal bolts for steel ISO/R 272-
structure. 1968 ASTM
A394 CSA
B33.4
39. IS 6745-1972 Methods for ASTM
determination of weight A90 ISO
of zinc coating of zinc 1460
coated iron and steel
articles.
40. IS 8263-1976 Method of radio interference IEC 437-1973
tests on high voltage insulator NEMA 107-1964
26.1.2.2Type of Towers
26.1.2.2.1 Normal Towers
The towers for transmission lines are classified as given below. The bidder shall
design and quote for the following four types of towers (Standard/Standard
Towers):
Tower type D shall also be used as a Dead-End tower.
Type of Deviation Typical Use
Tower Limit
Dead End. a) Angle tower with Single or / and Double tension insulator
string.
b) Also, to be used for locations where uplift exist.
c) Dead end with 0 deg. to 15 deg. deviation both
on line side and sub station side (slack span)
The angles of line deviation specified are for the design span. The span may
however be increased up to an optimum limit with reduced angle of line
deviation if adequate ground and phase clearances are available. For this
purpose, the Contractor shall prepare a tower rating chart (weight/wind span as
function of various angles of deviations).
26.1.2.2.2 Body Extensions Truncations & Unequal Leg Extensions
Truncations
a) All Normal towers mentioned in Clause above shall be designed for 3, 6, 9,
12, 15- and 18-meter body extensions for maintaining adequate ground
clearance as per the terrain, without reducing the safety margins available in
normal towers in any manner. Towers which require more than 18 m extension
shall be treated as Special Towers.
b) All above extensions to normal towers shall be treated as part of normal
towers only.
c) Prices shall be quoted as per weight (in MT) basis on the guaranteed black
weight of towers.
d) Designs and drawings of all type of towers with extensions as mentioned in
(a) above along with foundations (all type) shall be submitted for approval of
the employer irrespective of whether such requirements are there or not for a
particular transmission line.
26.1.2.2.3 Special Towers
The towers which will be specially designed for very long spans such as Major
River crossings etc. that cannot be crossed by normal tower with extensions
shall be special towers.
The Bidder must furnish design of each of these special towers for approval of
the Employer. The Contractor shall quote for these towers separately at unit
rates by weight per MT of super structure and fittings and will supply the same
if so required.
26.1.3.0 SPANS AND CLEARANCES
26.1.3.1Normal span, Wind Span & Weight Span
The normal ruling span, wind span and weight span to be adopted for lines
covered under this Specification are specified in Annexure-1 of this section
along with all other parameters.
26.1.3.2Electrical Clearances
26.1.3.2.1 Ground Clearance
a) The minimum ground clearance of conductors above ground shall not be less
than the limits specified in Line Data at Annexure I, at a conductor temperature
of 85°C and in still air. However, to achieve the above clearance the standard
tower heights include the following additional allowances:
b) 150 mm to account for errors in stringing;
c) Conductor creep as calculated by over tensioning the conductor at a
temperature of 30°C lower than the stringing temperature or as determined from
the sag-tension tables, which include the final sags including the effects of
creep.
27.1.3.2.2 Clearances of live parts form cross arm & towers
The minimum clearances shall be adopted from the following Table.
SL Item Swinging Minimum Minimum Minimum
No in electrical electrical electrical
degrees clearances for clearances for clearances
line voltage 132 line voltage for line
kV 220 kV voltage 400
kV
1 SUSPENSION STRINGS
(a) Single suspension string Nil 1530 2130 3050
15° 1530 1980 3050
(in mm) 30° 1370 1830 1860
45° 1220 1675 -
60° 1070 - -
(b) Double suspension Nil 1530 2130 3050
2 Tension string Nil 1530 2130 3050
Single/ Double
3 Jumper Nil 1530 2130 3050
10° 1530 2130 3050
20° 1070 1675 1860
30° 1070 1675 -
Min vertical distance
4 between conductor or X-arm 3900 4900 7800
(single/double circuit) (in
mm)
Where, TM = Load
TI =50% of tension of conductor and 100% of tension of
ground wire at everyday temperature and nil wind for suspension tower and
100% for angle and dead-end towers for both conductor and ground wire.]
Φ= Angle of deviation of tower.
26.1.8.5 Vertical Loads: Reliability Condition (normal condition)
i) Loads due to weight of each conductor and ground based on appropriate
weight span, weight of insulator strings and accessories.
ii) Self weight of structures up to tower panel under consideration.
26.1.8.6Vertical Loads: Security Condition
i) Loads due to weight of each conductor or ground wire based on appropriate
weight span, weight of insulator strings and accessories taking broken wire
condition where the load due to weight of broken conductor/ground wire shall
be considered as 60% of weight span. For intact wire the vertical load shall be
considered as given in Clause: 26.1.8.5.
ii) Self weight of structures up to tower panel under consideration.
26.1.8.7 Vertical Loads: Safety Condition
(i) Same as Clause 26.1.8.6 (i) multiplied by overload factor of 2.0
(ii) Same as Clause 26.1.8.6 (ii).
(iii) A load of 1500 N shall be considered acting at each cross-arm tip as a
provision for weight of line man with tools.
(iv) An additional load of 3500 N at cross arm tip.
(v) All bracings and redundant members of the towers which are horizontal or
inclined up to 150 from horizontal shall be designed to withstand as ultimate
vertical load of 1500 N considered as acting at centre, independent of all other
loads.
26.1.8.8 Longitudinal Loads: Reliability Condition
A) Suspension and Tension Towers
i) Longitudinal loads for Suspension and Tension towers shall be taken as nil.
ii) Longitudinal loads which might be caused on tension towers by adjacent
spans of unequal length shall be neglected.
B) Dead End Tower
i) Longitudinal loads for Dead End Towers shall be considered corresponding to
mechanical tension of conductors and ground wires at every day temperature &
design wind pressure or at minimum temperature with 36% of design wind
pressure, whichever is more stringent.
26.1.8.9 Longitudinal Loads: Security Condition
A) Suspension Towers
The longitudinal loads corresponding to 50% of the mechanical tension of
conductor and 100% of mechanical tension of ground wire shall be considered
under everyday temperature and no wind pressure for broken wire only.
B) Tension Towers
Horizontal loads in longitudinal direction due to mechanical tension of
conductors and ground wire shall be taken for loading criteria mentioned in
Clause: 26.1.8.8 (B) for broken wires. For intact wires these loads shall be
considered nil.
C) Dead End Towers
Horizontal loads in longitudinal direction due to mechanical tension of
conductors and ground wire shall be taken for loading criteria mentioned in
Clause: 26.1.8.8 (B) for intact wires; however, for broken wires these loads shall
be considered nil.
26.1.8.10 Longitudinal Loads: Safety Condition
A) Normal Condition
i) Suspension and Tension Towers
These shall be taken as nil.
ii) Dead End Towers
These loads for Dead End towers shall be considered as corresponding to
mechanical tension of conductors/ground wire at every day temperature and nil
wind. Longitudinal loads due to unequal spans may be neglected.
B) Broken wire Condition
i) Longitudinal loads during construction simulating broken wire condition will
be based on stringing of one earth wire or one complete phase conductor at one
time.
ii) Suspension Towers
Longitudinal loads during stringing on suspension towers should be normally
imposed only by the passing restriction imposed during pushing of the running
block through the sheave. It will apply only on one complete phase of sub-
conductor or one earth wire. It will be taken as 10000 N per sub-conductor or
5000 N per earth wire.
iii) Tension and Dead-End Tower
Angle Towers used as dead end during stringing simulating broken wire
condition shall be capable of resisting longitudinal loads resulting from load
equal to twice the sagging tension (sagging tension is 50% of the tension at
every day temperature and nil wind) for one earth wire or one complete phase
sub- conductors which is in process of stringing. At other earth wire or
conductor attachment points for which stringing has been completed, loads
equal to 1.5 times the sagging tension will be considered.
26.1.8.11 Anti Cascading Checks
i) All angle towers shall be checked for the following anti-cascading conditions
with all conductors and G.W. intact only on one side of the tower.
ii) Transverse Loads:- These loads shall be taken under no wind condition.
iii) Vertical Loads:- These loads shall; be the weight of conductor/ground wire
intact on one side of tower, weight of insulator strings and accessories.
iv) Longitudinal Loads:- These Loads shall be the pull of conductor/ground wire
at every day temperature and no wind applied simultaneously at all points on
one side with zero-degree line deviation.
26.1.8.12 BROKEN WIRE CONDITIONS
A) SINGLE CIRCUIT TOWERS
Any one-phase conductor or earth wire broken, whichever is more stringent for
a particular member.
B) DOUBLE CIRCUIT TOWERS
i) SUSPENSION TOWERS
Any one phase conductor or earth wire broken, whichever is more stringent for
a particular member.
ii) ANGLE TOWERS, TYPE-B & C
Any two phases broken on the same side and same span or any one phase and
one ground wire broken on the same side and same span whichever combination
is more stringent for a particular member.
iii) ANGLE TOWERS, TYPE-D (Dead End Tower)
Any three phases broken on the same side and same span or any two phases and
one ground wire broke on the same side and same span whichever combination
is more stringent for a particular member.
26.1.9.0DESIGN WIND PRESSURE
26.1.9.1Design Wind Pressure for the purpose of this Specification shall be
taken as 793 N/m2 which corresponds to wind velocity at 10 m height. For
Design Wind Pressure at other heights reference shall be made to IS: 802 or
‘Transmission Line Manual’ published by Central Board of Irrigation and
Power, New Delhi. The Design Wind Pressure mentioned above is corresponds
to Wind Zone-5, Reliability Level-1 and Terrain Category-2 as per IS: 802.
26.1.10.0 OTHER DESIGN PARAMETERS
26.1.10.1 For other design parameters to be adopted for the design of towers
reference shall be made to Annexure I of this Specification.
26.1.11.0 MATERIALS
26.1.11.1 Tower Steel Sections
1.11.1.1 IS Steel Sections of tested quality of conformity with IS:2062
(Designated Y.S. 250 MPa) or/and IS:8500 (Designated Y.S. 350 Mpa) are to be
used in towers, extensions and stub setting templates. The Contractor can use
other equivalent grade of structural steel angle sections and plates conforming to
latest International Standards. However, use of steel grade having designated
yield strength more than that of EN 10025/BS-4360-50B grade (355MPa) is not
permissible.
26.1.11.1.2 Steel plates below 6mm size exclusively used for packing
plates/packing washers produced as per IS: 1079 (Grade -0) are also acceptable.
However, if below 6mm size plate are used as load bearing plates viz gusset
plates, joint splices etc. the same shall conform to IS: 2062 / BS : 4360 or
equivalent standard meeting mechanical strength/metallurgical properties
corresponding to Fe-410 or above grade (designated yield strength not more
than 355MPa), depending upon the type of grade incorporated into design. The
chequered plates shall conform to IS: 3502.
26.1.11.1.3 For designing of towers, preferably rationalized steel sections have
been used. During execution of the project, if any particular section is not
available, the same shall be substituted by higher section at no extra cost to
Employer and the same shall be borne by the Contractor. However, design
approval for such substitution shall be obtained from the Employer before any
substitution.
26.1.11.2 Fasteners: Bolts, Nuts and Washers
26.1.11.2.1 All bolts and nuts shall conform to 18-12427. All bolts and nuts
shall be galvanized as per IS: 1367 (Part-13)/18:2629 and shall have hexagonal
head and nuts, the heads being forged out of the solid truly concentric, and
square with the shank, which must be perfectly straight.
26.1.11.2.2 The bolt shall be of 16/24 mm diameter and of property class 5.6 as
specified in IS: 1367 (Part-III) and matching nut of property class 5.0 as
specified in IS: 136: (Part-VI).
26.1.11.2.3 Bolts up to M 16 and having length up to 10 times the diameter if
the bolt should be manufactured by cold forging and thread rolling process to
obtain good and reliable mechanical properties and effective dimensional
control. The shear strength of bolts for 5.6 grade should be 31 0 MPa minimum
as per IS: 12427. Bolts should be provided with washer face in accordance with
18:1363 (Part-I) to ensure proper bearing.
26.1.11.2.4 Nuts should be double chamfered as per the requirement of IS: 1363
Part-II'. It should be ensured by the manufacturer that nuts should not be
overlapped beyond 0.4MM oversize on effective diameter for size up to M 16.
26.1.11.2.5 Fully threaded bolts shall not be used. The length of bolts shall be
such that the threaded portion will not extend into the place of contact of the
members.
26.1.11.2.6 All bolts shall be threaded to take the full depth of the nuts and
threaded for enough to permit firm gripping of the members, but not further. It
shall be ensured that the threaded portion of each bolt protrudes not less than 3
mm and not more than 8mm when fully tightened. All nuts shall fit tight to the
point where the shank of the bolt connects to the head.
26.1.11.2.7 Flat and tapered washers shall be provided wherever necessary.
Spring washers shall be provided for insertion under all nuts. These washers
shall be steel electrogalvanised, positive lock type and 3.5mm in thickness for
16mm dia bolt and 4.5mm for 24mm bolt.
26.1.11.2.8 To avoid bending stress in bolts or to reduce it to minimum, no bolt
shall connect aggregate thickness of members more than three (3) times its
diameter.
26.1.11.2.9 The bolt positions in assembled towers shall be as per structural
drawing.
26.1.11.2.10 Bolts at the joints shall be so staggered that nuts shall be tightened
with spanners without fouling.
26.1.11.2.11 To ensure effective in-process Quality control it is essential that
the manufacturer should have in house testing facility for all tests like weight of
zinc coating, shear strength and other tests etc. The manufacturer should also
have proper Quality Assurance System which should be in line with the
requirement of this 5pecification and IS: 14000 series Quality System Standard
26.1.12.0 TOWER ACCESSORIES
26.1.12.1 Arrangement shall be provided for fixing of all tower accessories to
the tower at a height between 2.5 meters and 3.5 meters above the ground level.
26.1.12.2 Step Bolts & Ladders
26.1.12.2.1 Each tower shall be provided with step bolts conforming to IS:
10238 of not less than 16mm diameter and 175mm long spaced not more than
450mm apart and extending from 2.5 meters above the ground level to the top
of the tower. The step bolt shall be fixed-on one leg up to waist level and on two
diagonally opposite legs above waist level up to top of the towers. Each step
bolt shall be provided with two nuts on one end to fasten the bolt securely to the
tower and button head at the other end to prevent the feet from slipping away.
The step bolts shall be capable of with standing a vertical load not less than 1.5
KN.
26.1.12.2.2 For special towers, where the height of the super structure exceeds
50 meters, ladders along with protection rings as per approved design shall be
provided in continuation of the step bolts on one face of the tower from 30
meters above ground level to the top of the special structure. From 2.5m to 30m
height of super structure step bolts shall be provided. Suitable platform using
6mmthick perforated chequered plates along with suitable railing for access
from step bolts to the ladder and from the ladder to each cross-arm tip and the
ground wire support shall also to be provided. The platform shall be fixed on
tower by using counter-sunk bolts.
26.1.12.3 Insulator Strings and Earth wire Clamps Attachments
26.1.12.3.1 Single / Double suspension insulator string assemblies shall be used
for ‘A’ type tower as required. For the attachment of Suspension Insulator
string, a suitable strain plate of sufficient thickness for transferring the load to
the tower body shall be provided. To achieve requisite clearances, if the design
calls for providing extra D-shackles, link plate etc. before connecting the
1nsulator string the insulator string the same shall be supplied by the Contractor.
26.1.12.3.2 At tension towers strain plates of suitable dimensions placed on the
underside of each cross-arm tip, shall be provided for taking the hooks or D-
shackles of the tension insulator strings. Full details of the attachments shall be
provided to the successful bidder. To achieve requisite clearances, if the design
calls for providing extra D-shackles, link plate etc. before connecting the
insulator string the same shall be supplied by the Contractor.
26.1.12.3.3 All important crossing like Railway Tracks, Important Roads,
Rivers or any other Crossings of similar nature shall be done with Double
Insulator String.
26.1.12.4 Earth wire Clamps Attachment
27.1.12.4.1 Suspension Clamp
The detailed drawing shall be submitted by the Contractor for Employer's
approval. The Contractor shall also supply U- bolts, D-shackles wherever
required.
26.1.12.4.2 Tension Clamps
Earth wire peaks of tension towers shall be provided with suitable plates to
accommodate the shackle of tension clamps. The contractor shall also supply
the U-bolts wherever required and take Employer's approval for details of the
attachments before the mass fabrication.
26.1.12.5 Anti-climbing Device
Barbed wire type anti climbing device, as per IS 5613 shall be provided and
installed by the Contractor for all towers. The barbed wire shall conform to IS-
278 (size designation A 1). The barbed wires shall be given chromatin dip as per
procedure laid down in IS: 1340.
26.1.12.6 Danger, Number and Phase plate
Danger Plates, Number plates and phase plates shall be provided and installed
by the Contractor.
a) Each tower shall be fitted with a danger plate, number plate and a set of phase
plates. The transposition tower should have the provision of fixing phase plates
on both the transverse phases.
b) The letters, figures and the conventional skull and bones of danger plates
shall conform to IS-2551 and shall be in a signal red on the front of the plate.
c) The corners of the danger, number and circuit plates shall be rounded off to
remove sharp edges.
d) The letters of number and circuit plates shall be red enameled with white
enameled background.
26.1.12.7 Aviation Requirements
Aviation requirements, if indicated separately in Schedule of Requirements shall
be in the scope of the Contractor and the same shall conform to IS: 5613.
26.1.13.0 TOWER FABRICATION
26.1.13.1 The fabrication of towers shall be in conformity with the following:
26.1.13.1.1 Except where hereinafter modified, details of fabrication shall
conform to IS: 802 (Part-II) or the relevant international standards.
26.1.13.1.2 The tower structures shall be accurately fabricated to connect
together easily at site without any undue strain on the bolts.
26.1.13.1.3 No angle member shall have the two leg flanges brought together by
closing the angle.
26.1.13.1.4 The diameter of the hole shall be equal to the diameter of bolt plus
1.5mm.
26.1.13.1.5 The structure shall be designed so that all parts shall be accessible
for inspection and cleaning. Drain holes shall be provided at all points where
pockets of depression are likely to hold water.
26.1.13.1.6 All identical parts shall be made strictly inter-changeable. All steel
sections before any work are done on them shall be carefully levelled,
straightened and made true to detailed drawings by methods which will not
injure the materials so that when assembled, the adjacent matching surfaces are
in close contact throughout. No rough edges shall be permitted in the entire
structure.
26.1.13.1.7 Minimum Thickness of Tower Members:
The minimum thickness of galvanised and painted tower members shall be as
follows: -
Galvanised Painted
Other members 5 5
Annexure I
1.1.1 Basic System Data for Transmission Lines
(wet) KV rms
6. Protective shielding angle NOT EXCEEDING NOT EXCEEDING NOT EXCEEDING
against direct lightning 300 300 200
7.
Creepage Distance 27 mm/ KV 27 mm/ KV 27 mm/ KV
8. Minimum Corona Not less than 154 Not less than 156 Not less than 320
extinction voltage at 50Hz kV kV kV
AC system Dry condition
(phase to earth)
(ii) Across and along all roads and paths 6100 mm Plus sag corrections &
allowances
(ii) Across and along all roads and 7000 mm Plus sag
paths corrections & allowances
(viii) Size 7 / 4 mm
(ii) Across and along all roads and 8840 mm Plus sag
paths corrections & allowances
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES &
PILE FOUNDATION
27.1.1.1 SCOPE
This section covers the specifications for design of foundations for various types of towers and special
structures under different soil condition described herein after.
27.1.1.2 STANDARDS
For design of foundations reference shall be made to IS 4091 and latest relevant IS codes. Reference
shall also be made to ‘Transmission Line Manual’ issued by Central Board of Irrigation and Power,
New Delhi.
27.1.1.3 Foundations
Foundation includes supply of all labour, tools & machineries, excavation of soil, disposal and
backfilling, formwork, shuttering & strutting, materials such as cement, sand, coarse aggregates and
reinforcement steel and all associated activities, concreting, dewatering etc.
27.1.2 Type of Foundations
The foundation shall be of open cast type or as per BOQ. Plain Cement Concrete/Reinforced Cement
Concrete footing shall be used for all type of normal towers. All the four footings of the tower and
their extensions shall be similar for a particular location, except where soil condition and or water
table are different at different legs. The total depth of foundation, below ground level shall be 3.0 to
3.5meters. For Hard Rock type and also where specific site conditions / properties demand foundation
of different depths (lower or higher), the same shall be adopted.
27.1.3 TYPE OF FOUNDATION
27.1.3.1 Most of the paddy fields of Assam remain under water for more than 3 months in a year.
During the remaining period of the year sub-soil water is normally found near the surface below the
ground level. The Contractor shall note this factor while designing the foundation of towers.
27.1.3.2 It is expected that the type of foundations defined in following Clause shall be suitable for
use at various locations of all the Transmission Lines covered in this Bid Document. The Contractor
shall examine the suitability of the type of the foundation assigned for each location depending on the
soil investigation reports and the same shall be approved by the Employer based on the suggested
design of the foundation prepared as per the relevant soil investigation report. Under no circumstances
the approved design shall be altered by the contractor nor the employer shall be under any obligation
to approve a change in the design and employer is not liable for additional payement arising under
that circumstances.
27.1.3.3 The Contractor shall design and quote for the following four types of foundations and all the
foundations shall be RCC type.
(i) Dry type foundation: Design of this type of foundation shall be normally for dry / rocky / hard
soil for which, (a) weight of earth shall be assumed to be 1600 kg/cum. (b) The Limit Bearing
Capacity of the soil shall be 22000 kg/square meter. (c) The angle of repose shall be 30 deg.
(ii) Wet type foundation (Suitable for paddy field location): Design of this type of foundation shall
be for locations where sub-soil water level is found below 1.5 meters from the ground level. This
design shall also be suitable for paddy fields in Assam. The weight, the limit bearing capacity, the
angle of repose and the ultimate bearing capacity of soil up to depth of 1.5 meter shall be taken as
mentioned in (i) above and same for earth beyond 1.5-meter depth shall be taken as per (iv) below.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
(iii) Semi sub-merged type foundation: Design of this type of foundations shall be for locations
where sub-soil water level is found below 0.75 meter from the ground level. The weight, the limit
bearing capacity, the angle of repose and the ultimate bearing capacity of soil up to depth of 0.75
meter shall be taken as mentioned in (i) above and same for earth beyond 0.75-meter depth shall be
taken as per (iv) below.
(iv) Sub-merged type foundation: Design of this type of foundations shall be for locations where
sub-soil water level is found at less than 0.75 meter from the ground level including completely sub-
merged locations. (a) The weight of earth shall be assumed to be 850 kg/cum. (b) The limit bearing
capacity of the soil shall be 11000 kg/sq. meter. (c) The angle of repose shall be 15.
27.2.1 Design of Foundations
27.2.1.1 Design of foundations as classified under Cl. 27.1.3.1 for all towers and towers with
extensions shall be developed by the Contractor based on their soil investigation report and approved
thereof by Employer.
27.2.1.2 Depending on the site conditions other types of foundations shall also be designed suggested
by the contractor suitable for Intermediate conditions under the above classifications to affect more
economy or to suit specific site conditions encountered.
27.2.1.3 The proposal for these types of foundations shall be submitted by the Contractor based on the
detailed soil investigation and duly approved by employer.
27.2.1.4 The pile foundations if required shall also be designed by the contractor based on detailed
soil investigation report. The working drawing of these foundations shall be provided by the
contractor to the employer prior to execution stage based on requirements.
27.2.2 Construction of Tower Foundation, Stub Setting and Earthing
27.2.2.1 Excavation
27.2.2.1.1 The excavation work for foundations shall be taken up by the contractor progressively
stretch wise / section wise after obtaining approval from employer for the proposed stretch wise /
section wise tower schedule, profile etc. as per detailed survey along the approved route alignment.
27.2.2.1.2 Except as specifically otherwise provided, all excavation for footings shall be made to the
lines and grades of the foundations. The excavation wall shall be carried out considering the slope
stability as well as ground water table. All excavation shall be protected so as to maintain a clean sub
grade and provide worker safety until the footing is placed, using timbering, shoring, shuttering,
dewatering etc. Contractor shall especially avoid disturbing the bearing surface of the pad. Any sand,
mud, silt or other undesirable materials which may accumulate in the excavated pit or borehole shall
be removed by Contractor before placing concrete.
27.2.2.1.3 The soil to be excavated for tower foundations shall be classified as follows depending
upon the physical state of the soil at the time of excavation irrespective of the type of foundation
installed.
a) Dry Soil
Soil removable either manually, by means of a spade and shovel or mechanically by proclaims,
excavators etc. Excavation done in dry soil for wet, partially submerged, fully submerged and wet
black cotton type of foundations shall also be covered under this.
b) Wet Soil
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
Where the subsoil water table is encountered within the range of foundation depth or land where
pumping or bailing out of water is required due to presence of surface water shall be treated as wet
soil. The excavation done in wet soil in case of wet, partially submerged, fully submerged and wet
black cotton type of foundation shall also be covered under this.
c) Dry Fissured Rock
Limestone, laterite, hard conglomerate or other soft or fissured rock in dry condition which can be
quarried or split with crowbars, wedges, pickaxes etc. However, if required, light blasting may be
resorted to for loosening the material but this will not in any way entitle the material to be classified
as hard rock.
d) Wet Fissured Rock
Above fissured rock, when encountered with subsoil water within the range of foundation depth or
land where pumping or bailing out of water is required, shall be treated as wet fissured rock.
e) Hard Rock
Any rock excavation, other than specified under fissured rock above, for which blasting, drilling,
chiseling is required. The unit rate quoted for hard rock excavation shall be inclusive of all costs for
such drilling (including drilling required for anchoring), chiseling and blasting, etc.
27.2.2.1.4 No extra payment shall be admitted for the removal of fallen earth into a pit or borehole
once excavated.
27.2.2.1.5 Where rock is encountered, the holes for tower footings shall preferably be drilled. Blasting
where resorted to as an economy measure, shall be done with utmost care to minimise fracturing rock
and using extra concrete for filling the blasted area. All necessary precautions for handling and use of
blasting materials shall be taken. In cases where unnecessarily large quantities are excavated/blasted,
resulting in placement of large volumes of concrete, payment of concrete shall be limited to design
volumes of excavation, concreting, reinforcement etc. In case where drilling is done, the stubs may be
shortened suitably with the approval of the Owner.
27.2.2.1.6 The Contractor shall arrange & supply requisite blasting material and permission from
statuary body and be responsible for its storage and use, without any extra cost to the Owner.
27.2.2.1.7 Indian Standard IS:3764 snd relevant codes shall be followed regarding safety of
excavation work.
27.2.3 UNIT RATES AND MEASUREMENT FOR FOUNDATION
27.2.3.1 The indicative shape of RCC foundations are enclosed in this Specification. The bidder is
required to quote the unit rates for different foundation activity as a whole for geo-technical
investigation, excavation for different types of soils, shuttering & shoring, concreting, backfilling,
supply and placement of reinforcement steel, dewatering and all other incindential items for
completion of the work.
27.2.3.2 The unit rates of RCC foundation for each type of soil shall include excavation along with all
associated activities like shoring, shuttering, dewatering till completion of foundation work stock
piling, dressing, back filling of foundations after concreting with excavated/borrowed earth
(irrespective of lead) and consolidation of earth, carriage of surplus earth to the suitable point of
disposal as required by the employer or any other activity required for to completion of foundation
work in all respect.
27.2.3.3 Form boxes shall be used for casting of foundations. The unit rate of concreting shall include
the cost of supply, fabrication and placement of form boxes, cement, water, coarse and fine aggregates
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
mixing and placing of concrete, curing of concrete and any other activities related / required for
completion of concreting works of foundation. The payment for this item shall be made as per the
actual volumes of concreting completed but limited to design volume based on unit rates indicated in
the letter of award.
27.2.3.4 The unit rate of RCC foundation shall include supply and placement of reinforcement steel,
stirrups, wire for binding the reinforcement, chairs, bolsters and spacers etc. as required to complete
the foundation work.
27.2.4 Setting of Stubs
27.2.4.1 The stubs shall be set correctly and precisely in accordance with approved method at the
exact location, alignment and levels with the help of stub setting templates and levelling instruments.
Stubs setting shall be done in the presence of Owner’s representative available at site where required
and for which adequate advance intimation shall be given to Owner by Contractor. Tolerances as per
provisions of IS:5613 shall be allowed for stub setting.
27.2.4.2 Setting of stub at each location shall be approved by Owner.
27.2.4.3 However, in hilly region for towers with unequal leg extensions and for river crossing
towers, props may be used with complete accuracy and high skilled supervision, subject to prior
approval from Owner.
27.2.4.4 For all towers the Contractor shall submit for approval the proposed method for setting of
stubs.
27.2.5 Stub Setting Templates / Props
27.2.5.1 Stub setting templates shall be arranged by the Contractor at his own cost for all heights of
towers. Stub templates shall be of adjustable type. The Contractor shall also arrange for props for
setting of stubs at specific locations where use of prop is approved by the Owner. Stub templates /
props should be painted.
27.2.5.2 The Contractor shall deploy sufficient number of templates / props for timely completion of
the line without any extra cost to Owner.
27.2.5.3 However following minimum number of stub setting templates may be deployed by the
Contractor for every 100km of line length subject to minimum of 5 templates for suspension tower.
Templates for tower type Nos. to be deployed
i) A/DA 10
ii) For each type of B/DB, C/DC
and D/DD type 3
iii) For A/DA +18/25 M 1
iv) for D/DD+18/25 M 1
However, if more templates are required for timely completion of the lines, the Contractor shall
deploy the same without any extra cost to Owner. The number of sets of prop (if permitted) to be
supplied, will depend as per actual site condition and completion schedule of line.
27.2.5.4 One set of each type of stub setting template / props (if used) shall be supplied to the Owner,
on completion of the project, at no extra cost to Owner.
27.2.6 Mixing, Placing and Compacting of Concrete
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.2.6.1 The concrete shall be mixed in the mechanical mixer. However, in case of difficult terrain,
hand mixing may be permitted at the discretion of the Owner. The water for mixing concrete shall be
fresh, clean and free from oil, acids and alkalis. Saltish or blackish water shall not be used.
27.2.6.2 Mixing shall be continued until there is uniform distribution of material and mix is uniform
in colour and consistency, but in no case the mixing be carried out for less than two minutes. Normal
mixing shall be done close to the foundation but exceptionally, in difficult terrain, the concrete may
be mixed at the nearest convenient place. The concrete shall be transported from the place of mixing
to the place of final deposit as rapidly as practicable by methods which shall prevent the segregation
or loss of any ingredient. The concrete shall be placed and compacted before setting commences.
27.2.6.3 To avoid the possibility of reinforcement rods being exposed due to unevenness of the
bottom of the excavated pit, a pad of lean concrete 50mm thick and corresponding to a 1:3:6 nominal
mix shall be provided at the bottom of the pad.
27.2.6.4 The concrete shall be laid down in 150mm layers and consolidated well, so that the cement
cream works, up to the top and no honey-combing occurs in the concrete. A mechanical vibrator shall
be employed for compacting the concrete. However, in case of difficult, terrain, manual compaction
may permit at the discretion of the Owner. Monolithic casting of foundations must be carried out.
However, in case of unavoidable circumstances, a key construction joint can be provided at the
chimney-pad interface subject to approval of the Owner.
However, nothing extra shall be paid to the Contractor for providing such construction joints. After
concreting the chimney portion to the required height, the top surface should be finished smooth with
a slight slope towards the outer edge for draining rain water.
27.2.6.5 Wet locations shall be kept completely dewatered, both during and 24 hours after placing the
concrete, without disturbance of the concrete.
27.2.6.6 If minor defects in concrete surface is found after the form work has been removed, the
damage shall be repaired with a rich cement sand mortar to the satisfaction of the Owner before the
foundation is back filled.
27.2.6.7 The concrete foundation for transmission line towers shall consists of two portions viz. (i)
pyramid & (ii) chimney. In chimney portion, the thickness of the concrete cover should be such that it
provides minimum cover of not less than 10 cm from any part of the stub angle to the nearest outer
surface of the concrete in respect of all dry locations, limiting the minimum section of chimney to
30.5 cm. Sq. In respect of all wet locations, the section of chimney should be 45.72 cm. Sq. uniformly
for all sizes of stub angle.
27.2.6.8The chimney top or muffing must be 23 cm above ground level in dry locations, 38 cm in
irrigated field and 15.24 cm above maximum water level in tank beds.
27.2.6.9 The size of the bottom portion of the foundation viz. Pyramid should be designed according
to the nature of the sub soil met with at the design depth for the stub angles.
The maximum base thickness in the pyramid portion in case of sub-merged foundation may be taken
as 200 mm.
27.2.7 Curing
The concrete shall be cured by maintaining the concrete wet for a period of at least 10 days after
placing. Once the concrete has set for 24 hours the pit may be backfilled with selected moistened soil
and well consolidated in layers not exceeding 200mm thickness and thereafter both the backfill earth
and exposed chimney shall be kept wet for the remainder of the prescribed 10 days. The exposed
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
concrete chimney shall also be kept wet by wrapping gunny bags around it and wetting the bags
continuously during the critical 10 days period.
27.2.8 Backfilling and Removal of Stub Templates
27.2.8.1 After opening of formwork and removal of shoring, timbering, etc., backfilling shall be
started after repairs, if any, to the foundation concrete. Backfilling shall normally be done with the
excavated soil, unless it is a clay type or it consists of large boulders/stones, in which case the
boulders shall be broken to a maximum size of 80-mm. At locations where borrowed earth is required
for backfilling, Contractor shall bear the cost irrespective of leads & lift.
27.2.8.2 The backfilling materials shall be clean and free from organic or other foreign
materials. A clay type soil with a grain size distribution of 50% or more passing the no. 200 sieve are
unacceptable for backfilling. The earth shall be deposited in maximum 200mm layers, levelled,
wetted if necessary and compacted properly before another layer is deposited. The moisture content
for compaction shall be based on the Proctor compaction test results given in the Geo-technical
Report, Clause 3.0 of section III. The density of the compacted backfill material may further be
verified to the satisfaction of the Owner based on the sand-cone method described in the ASTM
D1556-82 standard.
27.2.8.3 The backfilling and grading shall be carried to an elevation of about 75mm above the
finished ground level to drain out water. After backfilling 50mm high, earthen embankment (band)
will be made along the sides of excavation pits and sufficient water will be poured in the backfilling
earth for at least 24 hours. After the pits have been backfilled to full depth the stub template can be
removed.
27.2.9 Benching
When the line passes through hilly/undulated terrain, levelling the ground may be required for casting
of tower footings at no extra cost to the Employer. All such activities shall be termed benching and
shall include cutting of excess earth and removing the same to a suitable point of disposal as required
by Owner. Benching shall be resorted to only after approval from Owner. Volume of the earth to be
cut shall be measured before cutting and approved by Owner for payment purposes.
Further, to minimise benching, unequal leg extensions shall be considered and provided if found
economical. The proposal shall be submitted by the Contractor with detailed justification to the
Owner.
27.2.10 Protection of Tower and Tower Footing
27.2.10.1 Tower shall be spotted such that the quantity of revetment are optimum. For tower locations
in undulated terrain such as hill / mountain slopes, options like use of unequal leg extensions for
towers, unequal chimney extensions etc. Shall be explored by the contractor for optimizing the need
for revetment & benching.
27.2.10.2 The work shall include all necessary stone revetments, concreting and earth filling above
ground level, the clearing from site of all surplus excavated soil, special measures for protection of
foundation close to or in nalas, river bank / bed, undulated terrain, protection of uphill / downhill
slopes required for protection of tower etc., including suitable revetment or galvanised wire netting
and meshing packed with boulders. The top cover of stone revetment shall be sealed with M-15
concrete (1:2:4 mix). Contractor shall recommend protection at such locations wherever required.
Details of protection of tower/tower footing are to be prepared by contractor duly approved by
Employer.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.2.10.3 Tower footings shall generally be backfilled using soil excavated at site unless unsuitable
for backfilling. In the latter case, backfilling shall be done with borrowed earth of suitable quality
irrespective of leads and lift. The unit rate for backfilling quoted shall include the required lead and
consolidation and levelling of earth after backfilling.
27.2.10.4 The quantities for protection work of foundations are provisional only. The unit rates shall
also be applicable for any quantity variations during execution. The same unit rates shall hold good
for protection work carried out on down hills or up hills slopes applicable for the tower locations.
27.2.10.5 The unit rates for random rubble masonry revetment quoted in price schedule shall also
include excavation & (1:6) random masonry and unit rate for top sealing with M-15 concrete. For
payment purposes the volume of random rubble masonry revetment shall be measured from bottom to
top sealing coat and paid at the unit rates indicated in the Letter Of Award. No extra payment shall be
made for allied works such as excavation for revetment, packed stone at head of weep holes etc.
However, no deduction shall be made for the volume enclosed by weep holes.
27.2.10.6 For some of the locations in nalas, river bed or undulated terrain etc., boulders of minimum.
150mm size bounded and packed in galvanised wire net/mesh of 8 SWG wire and 152 square
(maxm.) mesh are to be provided. These stones shall be provided in crates size of 2.0mx2.0m or as
deemed suitable for a particular location. Measurement shall be taken in cubic meters and 15%
deduction will be made for void from cage/stack measurements.
27.2.11 SEISMIC CONDITION
Each foundation shall be provided with the tie beam for each type of tower to take care of seismic
conditions. Force due to earthquake shall be assumed to be vertical 0.1g and horizontal 0.2g.
27.2.12 OVER LOAD FACTOR
The magnitude of limit loads for foundation should be taken as 10% higher than those of the
corresponding towers.
27.2.13 LOADS ON FOUNDATIONS
27.2.13.1 The foundation shall be designed to withstand the loads of the superstructure for the full
footing reactions obtained from the structure as per analysis in conformity with the relevant factors of
safety. The reactions on the footings shall be composed of the following types of loads for which they
shall be required to be checked.
1. Maximum tension or uplift
2. Maximum compression of down thrust
3. Maximum horizontal shear or side thrust
27.2.13.2 The additional weight of concrete in the footing below ground level over the earth weight
and the full weight of concrete above the ground level in the footing and the embedded steel parts will
also be taken into account adding to the down thrust.
27.2.14 GUARANTEED VOLUME OF FOUNDATIONS
27.2.13.1 The Bidder shall furnish guaranteed volumes of concreting and re-enforcement rods for
each type of foundation for each type of towers along with their bids
27.2.13.2 For the purpose of evaluations and comparisons, these guaranteed volumes shall be taken
into consideration and the different types of foundations.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.2.13.3 After award of the contract, the bidder shall submit to the Employer for its approval,
detailed design calculations and drawings for each type of foundation. In case, the volume of the
foundation, finally approved and accepted by the Employer on the basis of the designs and drawings
so submitted is more than the guaranteed volume, no extra amount shall be paid to the contractor. If,
however, the volume of the finally approved and adopted foundation is less than the guaranteed
volume, the payment shall be made on the basis of the finally accepted volume only.
27.2.13.4 The contractor may be asked at any time during the execution of the works to submit
designs for special types of foundations for different towers in different locations if required.
27.3 CONSTRUCTION OF BORED CAST IN-SITU-PILE FOUNDATION
27.3.1 General Requirement
27.3.1.1 The specification covers the technical requirements for piling work, general description of
work, quality and workmanship. In every case, work shall be carried out to the satisfaction of the
Employer in accordance with the Technical Specifications and conform to location, lines, grades and
cross sections shown on the construction drawing or as directed by the Employer. The specifications
are not, however, intended to cover all the minute details and the work shall be executed according to
the specified Indian Codes. Work shall be executed according to the IS Codes, best prevailing local
Public Works Department practice or to the recommendations of the relevant International Standards
or to the instructions of the Employer. This specification shall have precedence in case anything
contrary to this is stated anywhere in this Bid Document. In case of conflict between the Specification
and Codes, the former shall prevail.
27.3.1.2 The work shall include mobilization of all necessary equipments, providing necessary
engineering supervision through qualified and technical personnel, skilled and unskilled labour, etc. as
required to carry out the complete piling work. The minimum capacity of some key equipments are
listed below. However, bidder has to furnish information regarding the equipments they intend to
deploy for the project.
Note: Bidder may have to provide higher capacity equipments than mentioned above, as per the actual
requirement for the execution of the job, without any additional financial implication to AEGCL.
27.3.2.1 Layout and levels of structures etc. shall be made by the Contractor, at his own cost, from the
general grid of the plot and the bench marks given by the Employer. The Contractor shall make his
own arrangements, at his own cost, for locating the co-ordinates and position of piles as per approved
drawings and for determining the Reduced Level (R.L.) of the locations with respect to the single
bench mark indicated by the Employer. The Contractor shall provide at site all the required survey
instruments, materials and men to Employer for verification of the detailed layout and correctness of
the layout and levels to the satisfaction of the Employer so that the work can be carried out accurately
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
according to specifications and drawings. The contractor shall be solely responsible for the
correctness of layout and levels.
This section of the specification covers site preparation of the areas as indicated in the drawings.
27.3.3.1.2 The area shall be stripped to remove roots of grass, rubbish and slush, shrubs or other
organic materials. Spoiled materials shall be burnt or removed to approved disposal areas on or near
the job site as directed by the Employer.
This clause specifies the properties of common building materials unless otherwise mentioned in the
drawings or schedule of items. All materials viz., cement, steel, aggregates, water etc. which are to be
used for pile construction are detailed below. However, aggregates more than 20mm shall not be used,
except for lean concrete.
27.3.4.1.1 All coarse aggregates shall be as per IS:383 consisting of hard, strong, compact grained and
durable pieces of crushed stone having uniform in texture and colour and free from decay, flaws,
veins, cracks and sand holes. Coarse aggregates should be of angular shape & rectangular surface and
shall be free from organic or clay coatings and other impurities like disintegrated stones, soft flaky
particles, adherent coatings, clinkers, slag, mica and any other materials liable to affect the strength,
durability or appearance of concrete. The surface of a freshly broken stone shall be bright, clean, and
free from any dull, chalky or earthy appearance. Coarse aggregates with round surface shall not be
used. A coarse aggregate shall not absorb more than 5% of its weight of water after 24 hours
immersion. Samples shall be submitted by the Contractor and approved samples shall be retained by
the Employer for comparison of bulk supply.
27.3.4.1.2 Sieving and washing of aggregates by approved method shall be carried out wherever
required.
27.3.4.1.3 Grading of coarse aggregate shall generally conform to IS:383 and shall be such as to
produce a dense concrete of the specified proportions and strength and of consistency that will work
readily into position without segregation.
27.3.4.1.4 The maximum size of aggregate shall be as follows unless specified otherwise:
27.3.4.2 Cement
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
Cement used shall generally be ordinary Portland Cement conforming to the latest Indian Standard
Code IS:8112 or IS:12269. Alternatively, other varieties of cement other than ordinary Portland
Cement such as Portland Pozzolana Cement conforming to IS;1489 or Portland Slag Cement
conforming to IS:455 can also be used. The Contractor shall submit the manufacturer’s Test
certificate, for each consignment of cement procured, to the Employer. However, Employer reserves
the right to direct the Contractor to conduct tests for each batch/lot of cement used by the Contractor
and Contractor will conduct those tests free of cost at the laboratory so directed by the Employer. The
Contractor shall also have no claim towards suspension of work due to time taken in conducting tests
in the laboratory. Changing of brand or type of cement within the same structure shall not be
permitted without the prior approval of the Employer. Sulphate Resistant Cement shall be used if
Sulphate content is more than the limits specified in IS:456, as per Geotechnical investigation report
and as mentioned in the construction drawing. No additional payment shall be made for using
Sulphate Resistant Cement.
27.3.4.3 Sand
Sand shall be hard, durable, clean and free from any adherent coatings or organic matter and shall not
contain clay balls or pellets. The sand shall be free from impurities such as iron pyrites, alkalis, salts,
coal, mica, shale or other laminated materials, in such forms or quantities as to affect adversely the
hardening, strength, durability or appearance of concrete or to cause corrosions to any metal in contact
with such concrete. In no case the cumulative percentage of impurities in sand shall be more than 5%
by weight. All sand shall be properly graded. Unless otherwise directed by the Employer all sand shall
pass through IS Sieve no. 2.36 mm. Sand for concrete shall conform to IS:383.
27.3.4.4 Water
Water shall be clean, fresh and free from organic matters, acids or soluble salts and other deleterious
substances which may cause corrosion, discoloration, efflorescence etc. Potable water is generally
considered fit for use. Water to be used shall comply with the requirements of IS:456 . Average 28
days compressive strength of at least three 15 cm. cubes of concrete prepared with proposed water
shall not be less than 90% of average strength of three similar cubes prepared with distilled water. PH
of water shall generally be not less than 6.
27.3.4.5 Reinforcement
Reinforcement steel shall be clean and free from loose mill scales, dust, loose rust, oil and grease or
other coatings which may impair proper bond. Reinforcement shall be of epoxy coated complying the
appropriate Indian Standards from Primary Producer e.g TATA Steel, SAIL, Jindal, RINL, or
equivalent as per IS 13620:1993 or latest version. All steel bars including and above 6mm diameter
shall be of tested for quality. Substitution of reinforcement, other than those mentioned above, shall
not be permitted without the prior approval of the Employer.
All materials shall be stored by the Contractor in a manner aiding convenient access for identification
and inspection at all times. The storage arrangements shall be subject to the approval of the Employer.
Storage of materials shall be as described in IS:4082 .All materials shall be so stored as to prevent
deterioration or intrusion of foreign matter and to ensure the preservation of their quality and fitness
for the work. Any material which has deteriorated or has been damaged or is otherwise considered
defective by the Employer shall not be used for concrete, and shall be removed from site immediately,
failing which, the Employer will get the materials removed and the cost thereof shall be recovered
from contract price. The Contractor shall maintain up to date accounts of receipt, issue and balance
(stock wise) of all materials.
27.3.5.1 Cement
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
The cement shall be stored in dry enclosed shed, well away from the walls and insulated from the
floor to avoid contact with moisture. The cement shall be stacked in easily countable stacks to
facilitate removal of first in first out basis. The cement bags shall be gently kept on the floor to avoid
leakage of cement from the bags. Sub-standard or partially set cement shall be immediately removed
from the site as soon as it is detected. Cement stored for period beyond 90 days shall be tested before
use.
All coarse aggregates & sand shall be stored on brick soling or an equivalent platform so that they do
not come in contact with dirt, clay, grass or any other injurious substance at any stage. Aggregate of
different sizes shall be kept in separate and easily measurable stacks. If so desired by the Employer,
aggregates from different sources shall be stacked separately with proper care to prevent intermixing.
27.3.5.3 Reinforcement
Reinforcement steel shall be stored consignment wise and size wise, off the ground and under cover.
It shall be protected from rusting, oil grease and distortions. If directed by the Employer, the
reinforcement steel may have to be coated with cement wash before stacking, to prevent scale and rust
at no extra cost to the Employer. The stacks shall be easily measurable. Only steel needed for
immediate use shall be removed from storage. Fabricated reinforcement shall be carefully stored to
prevent damage, distortion, corrosion & deterioration.
27.3.6.1 General
27.3.6.1.1 This section of the specification deals with cement concrete, plain or reinforced, and covers
the requirement for concrete mix design, strength and quality, pouring at all levels, forming,
protection, curing finishing, admixtures, inserts and other miscellaneous works.
27.3.6.1.2 The provisions of IS:456 shall be complied with, unless permitted otherwise. Any other
Indian Standard Code shall form the part of the specification to the extent it has been referred to or
applicable within this specification.
27.3.6.1.3 The Contractor shall furnish all labour, material and equipment to form, place and finish all
structural concrete, concrete works and miscellaneous items complete, as described herein.
27.3.6.2 Admixtures
27.3.6.2.1 The admixtures in concrete for promoting workability, improving strength or for any other
purpose, shall be used only after the written permission from the Employer. The Admixtures shall
conform to IS:9103.
27.3.6.2.2 Admixtures should not impair durability of concrete nor combined with the constituent to
form harmful compounds nor increase the risk of corrosion of reinforcement.
27.3.6.2.3 Addition of admixtures should not reduce the specified strength of concrete in any case.
The workability, compressive strength and the slump loss of concrete with and without the use of
admixtures shall be established during the trial mixes before use of admixtures.
27.3.6.2.4 The chloride content of admixtures shall be independently tested for each batch before
acceptance.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.6.2.5 If two or more admixtures are used simultaneously in the same concrete mix, data shall be
provided to assess their interaction and to ensure their compatibility.
27.3.6.2.6 In case admixtures are used in the concrete for any structure, fresh mix design be done
considering the admixture with the specific approval from Employer. No extra payment shall be made
to the Contractor on this account.
27.3.6.3.1 The minimum grade of concrete to be used for piling shall be M-25 with minimum cement
content 400 kg/m3 and maximum water cement ratio of 0.5. Concrete shall conform to the controlled
design mix as specified in IS:456 . In addition, nominal mixes of 1:3:6 and 1:4:8 (with aggregates of
nominal size 40mm maximum, by weight converted to equivalent volume shall also be used as per
field quality plan. The concrete in aggressive surroundings due to presence of sulphate, etc., shall
confirm to IS:456.
27.3.6.3.2 The Contractor shall carry out concrete mix design in accordance with IS:10262 and submit
mix design calculations and get them approved from the Employer well in advance of installation of
pile foundations. The Contractor shall carry out adequate number of tests in accordance with IS:456 to
ensure concrete of the minimum specified strength at requisite workability(i.e.slump).
27.3.6.4 Workmanship
All workmanship shall be according to the current Industry standard and best practices. Before
starting a pour, the Contractor shall obtain the approval of the Employer in a “Pour Card” maintained
for this purpose. He shall obtain complete instructions about the material and proportions to be used,
Slump / workability, Quantity of water per unit weight of cement, number of test cubes to be taken,
type of finishing to be done, any admixture to be added, any limitation on size of pour and stopping of
concrete in case of premature stopping of pours.
Mixing of Concrete
27.3.6.4.1 All design mix concrete shall be mixed in mechanically operated mixer of an approved size
and type capable of ensuring a uniform distribution on the materials through the mass. However,
contractor can also use central batching plant situated within the area allocated for the Contractor’s
particular use.
27.3.6.4.2 The proportions of sand, coarse aggregate, cement and water shall be as determined by the
mix design. However, in case of nominal mix concrete (for lean concrete only) the proportions of
sand, coarse aggregate, cement and water shall be fixed. The proportions, as determined for design
mix concrete and shall always be approved by the Employer. The quantities of the cement, sand and
coarse aggregates shall be determined by weight.
However, for a faster progress at site, quantities of the cement, sand and coarse aggregates can be
converted to equivalent volume. The water shall be measured accurately after giving proper allowance
for surface water present in the aggregate for which regular check shall be made by the Contractor.
27.3.6.4.3 The water shall not be added to the mix until all the cement and aggregates consisting the
batch are already in the drum and dry mixed for at least one minute. Mixing of each batch shall be
continued until there is a uniformity in colour and consistency but in no case shall mixing be done for
less than two (2) minutes and at least forty (40) revolutions after all the materials and water are in the
drum. When absorbent aggregates are used or when the mix is very dry, the mixing time shall be
extended as may be directed by the Employer. Mixers shall not be loaded above their rated capacity as
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
it prevents thorough mixing. If there is segregation after unloading from the mixer the concrete should
be remixed.
27.3.6.4.3 The entire contents of the drum shall be discharged before the ingredients for the next batch
are fed into the drum. No partly set or remixed or excessively wet concrete shall be used and it shall
be immediately removed from site. Each time the work stops, the mixer shall be thoroughly cleaned
and when the next mixing commences, the first batch shall have 10% additional cement at no extra
cost to the Employer to allow for loss in the drum.
Concrete shall be handled and conveyed from the place of mixing to the place of final laying as
rapidly as practicable, by approved means, before the initial setting of the cement starts. Concrete
should be conveyed in such a way as will prevent segregation of Concrete which may occur during
transportation of concrete. In case of any such segregation during transport, the concrete shall be re-
mixed. During very hot or cold weather, if directed by the Employer, concrete shall be transported in
deep containers, having mortar leak proof, which will reduce the rate of water loss by evaporation and
loss of heat. Conveying equipments for concrete shall be well maintained and thoroughly cleaned
before commencement of concrete mixing. Such equipment shall be kept free from set concrete.
a) Formwork and placement of reinforcement shall be approved in writing by the Employer before
concrete is placed. The forms shall be well wetted and oil shavings, dirt and water that may have
collected at the bottom shall be removed before concrete is placed. Concrete shall be deposited in its
final position without segregation, rehandling or flowing. The interval between adding the water to
the dry materials in the mixer and the completion of the final placing inclusive of compaction of the
concrete shall be well within the
initial setting time for the particular cement in use or as directed by the Employer. As far as possible,
concrete shall be placed in the formwork by means approved by the Employer and shall not be
dropped from a height or handled in a manner which may cause segregation. Any drop over 1800 mm
shall have to be approved by the Employer. Once the concrete is deposited in its final position, it shall
not be disturbed. Care should be taken to avoid displacement of reinforcement or movement of
formwork.
c) After the concrete has been placed it shall be spread and thoroughly compacted by approved
mechanical vibration to a maximum subsidence without segregation and thoroughly worked around
reinforcement or other embedded fixtures into the correct form and shape. Vibrators shall not be used
for pushing and shovelling concrete into adjoining areas. Vibrators must be operated by experienced
men and over-vibration shall not be permitted. Head tamping in some case may be allowed subject to
the approval of the Employer. Care must be taken to ensure that the inserts, fixtures, reinforcement
and form work are not displaced or disturbed during placing of concrete. No concrete shall be placed
in open while it rains. If there has been any sign of washing of cement and sand, the concrete shall be
entirely removed immediately. Suitable precautions shall be taken in advance to guard against rains
before leaving the fresh concrete unattended. No accumulation of water shall be permitted on or
around freshly laid concrete. Tie beams, pile caps, footings shall be poured in one operation normally,
in special circumstances with the approval of the Employer these can be poured in horizontal layers
not exceeding 500 mm in depth. When poured in layers, it must be ensured that the under layer, is not
already hardened. Blending of under layer if any, shall be effectively removed.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
d) Wherever vibration has to be applied externally the design of formwork and the disposition of
vibrators shall receive special consideration to ensure efficient compaction and to avoid surface
blemishes.
27.3.6.7 Inserts
All anchors, anchor bolts, inserts, etc. and any other items those are required to be embedded in the
concrete shall be placed in correct position before pouring. Extra care shall be taken during pouring
operation to maintain their position as indicated in the drawings. These inserts shall be welded to the
nearest reinforcement to keep them in position and all such welding shall be deemed to be included in
the unit rate quoted and no extra payment shall be made on this account.
27.3.6.8 Blockouts
Blockouts in concrete as indicated in the drawing or as directed by the Employer shall be provided
wherever required. No extra payment shall be made to the Contractor on this account.
All concrete surfaces shall have even and clean finish, free from honeycombs, air bubbles, fins or
other blemishes. The formwork joints marks for concrete work exposed to view shall be rubbed with
carborundum stone and defects patched up with a paste of 1 part sand and 1 part cement and cured.
The finish shall be made to the satisfaction of the Employer. The unit rate of concrete work shall be
inclusive of the cost of cleaning and finishing exposed surface as mentioned above.
This section of the specification shall cover providing reinforcement steel and its cleaning, bending,
binding, placing with arrangements for chairs, supports and suitable covers for all reinforced concrete
works, below and above ground level as per drawings and specifications.
27.3.7.1.1 Reinforcement steel of same type & grade shall be used for structural reinforcement work
as detailed in the drawing released by the Employer. No work shall be commenced without proper
verification with the bar-bending schedule provided in the drawing .
27.3.7.1.2 Contractor shall supply, fabricate and place reinforcement to shapes and dimensions as
indicated on the drawings and as per specifications. The reinforcement shall be either plain or
deformed steel bars or welded wire fabric conforming to relevant IS specifications.
27.3.7.1.3 Any adjustment in reinforcement to suit field conditions and construction joints other than
shown on drawings shall be subjected to the approval of Employer.
27.3.7.2 Bending
27.3.7.2.1 Unless otherwise specified, reinforcement steel shall be bent in accordance with procedure
specified in IS:2502. Bends and shapes shall comply strictly with the dimensions in the approved Bar
Bending Schedule. Contractor shall be entirely responsible for its correctness. Bars correctly bend
shall only be used.
27.3.7.2.2 No reinforcement shall be bent when in position in the work without approval of the
Employer, whether or not it is partially embedded in concrete. Bars shall not be straightened in a
manner that will injure the material. Rebending can be done only if approved by the Employer.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
Reinforcement bars shall be bent by machine or other approved means producing a gradual and even
motion. All the bars shall be cold bent unless otherwise approved.
27.3.7.3.1 All reinforcement shall be accurately fixed and maintained in position as shown on the
drawings by approved means as mild steel chairs, and/or concrete spacer blocks. Bars intended to be
in contact, at crossing points, shall be securely bond together at all such points by two number
No.20G annealed soft-iron wire. Binders shall tightly embrace the bars with which they are intended
to be in contact and shall be securely held. The vertical distance between successive layers of bars
shall be maintained by provision of mild steel spacer bars. They should be so spaced that the main
bars do not sag preceptibly between adjacent spacers.
27.3.7.3.2 The placing of reinforcements shall be completed well in advance of concrete pouring.
Immediately before pouring, the reinforcement shall be checked by the Employer for accuracy of
placement and cleanliness and necessary correction as directed by him shall be carried out. The cover
for concrete over the reinforcements shall be as shown on the approved drawings unless otherwise
directed by the Employer. Care should be taken to ensure that projecting ends of ties and other
embedded metal do not encroach into the concrete cover. Where concrete blocks are used for ensuring
the cover and positioning reinforcement, they shall be made of mortar 1:2 (one part cement: two parts
sand) by volume and cured for at least (7) days. The sizes and locations of the concrete blocks shall be
approved by the Employer.
27.3.7.3.3 The longitudinal reinforcement shall project 52 times its diameter above cut-off level
unless otherwise indicated in the drawing.
27.3.7.3.4 The minimum diameter of the links or spirals bar shall be 10mm and the spacing of the
links or spiral shall not be less than 150mm and in no case more than 250mm. The laterals shall be
tied to the longitudinal reinforcement to maintain its shape and spacing.
27.3.7.3.5 Reinforcement cage shall be sufficiently rigid to withstand handling and installation
without any deformation and damage. As far as possible number of joints (laps) in longitudinal
reinforcement shall be minimum. In case the reinforcement cage is made up of more than one
segment, these shall preferably be assembled before lowering into casing tube/pile bore by providing
necessary laps as per IS:456.
27.3.7.3.6 The minimum clear distance between the two adjacent main reinforcement bars shall
normally be 100mm for the full depth of cage, unless otherwise specified.
27.3.7.3.7 The laps in the reinforcement shall be such that the full strength of the bar is effective
across the joint and the reinforcement cage is of sound construction. Laps and anchorage lengths of
reinforcing bars shall be in accordance with IS:456, unless otherwise specified. If the bars in a lap are
not of the same diameter, the smaller will guide the lap length.
27.3.7.3.8 Laps shall be staggered as far as practicable and as directed by the Employer. Not more
than 50% bars shall be lapped at a particular section. Lap joints shall be staggered by at least 1.3 times
the lapped length (Center to Center).
27.3.7.3.9 Proper cover and central placement of the reinforcement cage in the pile bore shall be
ensured by use of suitable concrete spacers or rollers, as required, without any additional cost to the
Employer.
27.3.7.3.10 Minimum clear cover to the reinforcement shall be 75mm unless otherwise mentioned.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.7.3.11 Unless otherwise specified by the Employer reinforcement shall be placed within the
following tolerance as specified in IS:456:2000.
The cover shall in no case be reduced by more than one-third of specified cover or 5mm whichever is
less.
27.3.7.3.12 Welding of reinforcement bars shall be avoided. However, welding may be done in
specific case subject to prior permission from the Employer.
The Contractor shall deploy all labour, equipment, tools & tackles and materials required for complete
execution of the work in accordance with the drawings and as described herein.
27.3.8.1 Excavation
27.3.8.1.1 The Contractor shall control the grading in the vicinity of all excavation so that the surface
of the ground will be properly slopped or diked to prevent surface water from running into the
excavated areas during construction.
27.3.8.1.2 Excavation shall include the removal of all materials required to execute the work properly
and shall be made with sufficient clearance to permit the placing, inspection and setting of forms and
completion of all works for which the excavation was done.
27.3.8.1.3 Side and bottoms of excavation shall be cut sharp and true, undercutting shall not be
permitted. Each side of excavation shall be used in lieu of formwork for placement of concrete unless
authorised, in special cases, by the Employer, where limitation of space for larger excavation
necessitate such decision.
27.3.8.1.4 When machines are used for excavation, the last 300mm before reaching the required level
shall be excavated by hand or by such equipment that will leave the soil at the required final level, in
its natural conditions.
27.3.8.1.5 Suitability for bearing of the bottoms of excavations shall be determined by the Employer.
27.3.8.1.6 The bottom of excavation shall be trimmed to the required level and when carried below
such levels, by error, shall be brought to level by filling with lean concrete 1:4:8 mix, with aggregate
of 40mm maximum nominal size at no additional cost to the Employer.
27.3.8.1.7 The Contractor shall be responsible for assumptions and conclusions regarding the nature
of materials to be excavated and the difficulty of making and maintaining the required excavations
and performing the work required as shown on the drawing and in accordance with these
specifications. The Contractor shall be responsible for any damage to any part of the work and
property caused by collapse of sides of excavations. Materials may be salvaged, if it can be done with
safety for the work and structure, as approved by the Employer. However, no extra claim shall be
entertained for materials not salvaged or any other damage to Contractor’s property as a result of the
collapse. He shall not be entitled to any claim for redoing the excavation as a result of the same.
27.3.8.1.8 Excavations for foundations specified shall be carried out at least 75mm or as specified in
relevant drawings below the bottom of structural concrete and then be brought to the required level by
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
placing lean concrete of 1:4:8 mix or as specified in drawings with aggregate of 40mm maximum
nominal size.
27.3.8.1.9 When excavation requires coffer dams, sheet piling, bracing, sheeting, shoring, draining,
dewatering etc. the Contractor shall have to provide the same as required and the cost there of shall be
included in the unit rate quoted for the item of excavation and contractor shall submit necessary
drawings showing arrangement and details of proposed installation and shall not proceed until he has
received approval from the Employer.
27.3.8.1.10 The Contractor shall have to constantly pump out the water collected in pits due to rain
water, springs, seepage etc. and maintain dry working conditions at no extra cost to the Employer.
27.3.8.1.11 For the purpose of excavation in earthwork, all types of soil including kankar, morum,
shingle and boulders are included and no separate payment shall be made for different type of soils
encountered.
27.3.8.4.1 General
27.3.8.4.1.1 If it is so desired by the Employer, the Contractor shall prepare, before commencement of
the actual work, design and drawings for form work and centering and get them approved by the
Employer. The form work shall conform to the shape, alignment and dimensions as shown in the
drawings. Form work shall be composed of steel and/or best quality shuttering wood of non-
absorbent type or plywood. Timber shall be free from significant knots and shall be of medium grain
as far as possible and hard woods shall be used as caps and wedges under or over posts. Plywood or
equivalent shall be used where specified to obtain smooth surfaces for exposed concrete work. Struts
shall generally be mild steel tubes, and strong sal ballis of 150mm in diameter or above. Bamboos,
small diameter ballis, etc. shall not be used unless approved by the Employer in specified cases.
Supports or props should not be supported on an unpropped lower suspended floor or beam unless
calculations are submitted to the Employer to confirm the strength of the lower floor or beam and no
propping shall be taken out until the Employer approval has been given.
27.3.8.4.1.2 The form work shall be true and rigid and thoroughly braced both horizontally and
diagonally. The forms shall be sufficiently strong to carry without undue deformation, the dead
weight of the concrete as well as working load. Where the concrete is vibrated, the formwork shall be
strong enough to withstand the effects of vibration, without appreciable deflection, bulging, distortion
or loosening off its components. The joints in the formwork shall be sufficiently tight to prevent any
leakage of mortar. The formwork shall be such as to ensure a smooth uniform surface free from
honeycombs, air bubbles, bulges, fins and other blemishes. Any blemish or defect found on the
surface of the concrete must be brought to the notice of Employer immediately and rectified free of
charge as directed by him. To achieve the desired rigidity, the bolts, space blocks, the wires and
clamps as approved by the Employer shall be used but they must in no way impair the strength of
concrete or leave stains or marks on the finished surface, where there are chances of these fixtures
being embedded, only mild steel or concrete of adequate strength shall be used. Bolts passing
completely through liquid retaining walls/slabs for the purpose of securing and aligning the formwork
should not be used.
27.3.8.4.1.3 Temporary openings for cleaning, inspection and for pouring concrete may be provided at
the base of vertical forms and as may be directed by the Employer. The temporary openings shall be
so formed that they can be conveniently closed when required and must not leave any mark on the
concrete.
27.3.8.4.2.1 All forms shall be thoroughly cleaned of old concrete wood shavings, saw dust, dirt and
dust sticking to them before they are fixed in position. All rubbish loose concrete, chippings,
shavings, saw dust etc. shall be scrupulously removed from the interior of the forms before the
concrete is poured. Along with wire brushes, brooms, etc. compressed air jet and/or water jet shall be
kept handy for cleaning, if directed by the Employer.
27.3.8.4.2.2 Before shuttering is placed in position the form surface in contact with concrete shall be
treated with approved non-standing oil or composition of other material approved by the Employer.
Care shall be taken that the oil or composition does not come in contact with reinforcing steel or
existing concrete surface. They shall not be allowed to accumulate at the bottom of the shuttering.
27.3.8.4.2.3 If formwork for pedestal/chimney is erected for the full height of the section, as placing
of concrete proceeds, wedges, spacer bolts, clamps or other suitable means shall be provided to allow
accurate adjustment of the formwork and to allow it to be removed gradually without jarring the
concrete.
27.3.8.4.3.1 The Contractor shall begin the removal of formwork only after approval of Employer. He
shall place on record the date on which the concrete is placed in different parts of the work and the
date of the removal of formwork there from. This record shall be checked and countersigned by the
Employer. The Contractor shall be responsible for the safe removal of formwork but the Employer
may delay the time of removal if he considers it necessary. Any work showing signs of damage
through premature removal of formwork or loading shall be entirely reconstructed without any extra
cost to Employer.
27.3.8.4.3.2 Forms for various types of structural components shall not be removed before the
minimum periods specified below which shall also be subject to the approval of the Employer.
27.3.8.4.3.3 No supporting forms shall be removed suddenly in such manner as to create shock
loading. Forms for sides shall not be removed before 2 days. Bottom forms shall not be removed
before 28 days unless this period is reduced with specified concurrence of the Employer. However, in
any case, formwork shall not be struck until the concrete has reached a strength at least twice the
stress to which the concrete may be subjected to, at the time of removal of forms.
Before re-use, all forms shall be thoroughly scrapped cleaned and joints, etc. shall be examined, when
necessary repaired and inside surface treated as specified. Formwork shall not be used/re-used, if
declared unfit or unserviceable by the Employer.
27.3.8.5.1.1 After completion of foundation footings, pile caps, pedestals, tie beams and other
constructions below the elevation of the grades, and prior to back filling, all forms of temporary
shoring, timber etc. shall be removed and the excavation cleaned of all trash, debris and perishable
materials, back filling shall begin only with the approval of the Employer.
27.3.8.5.1.2 The soil to be used for back filling purpose shall be inorganic material and shall be free
from any foreign substance which can harm or impair the strength of footing in any manner. In any
case the soil to be used for back filling purpose shall have the prior approval of the Employer.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.8.5.1.3 The soil to be used for back filling purpose shall be either from the excavated earth or
from the borrow pits, as directed by the Employer. The soil may have to be brought from a distance
up to 2 km. By the shortest haulage route as approved by the Employer. If directed by the Employer,
the excavated earth from the adjoining areas (which is to be disposed off up to a distance of 500
meters by manual labour) shall be used as for back filling purpose.
27.3.8.5.1.4 Back filling shall not be dropped directly upon or against any structure where there is
danger of displacement or damage.
27.3.8.5.1.5 Back filling shall be placed in horizontal layers not to exceed 200mm in thickness. Each
layer shall be compacted with proper moisture content and with such equipment as may be required to
obtain a density equal to or greater than 95% of maximum dry density as determined by the relevant
Indian Standard. The method of compaction shall be subject to the approval of the Employer. Pushing
of earth for back filling shall not be adopted under any circumstances.
27.3.8.5.1.6 On completion of structures, the earth surrounding them shall be accurately finished to
line and grade as shown on the drawings or as per the instruction of the Employer. Finished surface
shall be free of irregularities and depressions and shall be within 50mm of the specified level.
27.3.8.5.1.7 Any additional quantity of back filling, if required, beyond the excavation payment line
shall be done by the contractor at his own expense.
a) When the work is to be interrupted, the concrete shall be rebated at the joint to such shape and size
as may be required by the Employer or as shown on the drawings. All vertical construction joints shall
be made with stone boards, which are rigidly fixed and slotted to allow for the passage of the
reinforcing steel. If desired by the Employer, keys and/or dowel bars shall be provided at the
construction joints.
Construction joints shall be provided in positions as shown or described on the drawing. Where it is
not described, the joints shall be in accordance with the following :
i) In a column, the joint shall be formed about 75mm below the lowest soffit of the beams framing
into it.
ii) Concrete in tie beam shall be placed throughout without a joint, but if the provision or a joint is
unavoidable, the joint shall be vertical and at the middle of the span.
iii) In forming a joint, concrete shall not be allowed to slope away to thin edge. The locations of
construction joints shall be planned by the Contractor well in advance of pouring and have to be
approved by the Employer.
b) Before the fresh concrete is placed, the cement skin of the partially hardened concrete shall be
thoroughly removed and surface made rough by hacking, sand blasting, water jetting, air jetting or
any
other method as directed by the Employer. The rough surface shall be thoroughly wetted for about
two hours and shall be dried and coated with 1:1 freshly mixed cement sand slurry immediately
before placing the new concrete. The new concrete shall be worked against the prepared surface
before the slurry sets. Special care shall be taken to see that the first layer of concrete placed after a
construction joint is thoroughly rammed against the existing layer. Old joints during pour shall be
treated with 1:1 freshly made cement sand slurry only after removing all loose materials.
c) The unit rate of concrete work shall include the cost of construction joints.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
Newly placed concrete shall be protected by approved means from rain, sun & wind. Concrete placed
below ground level shall be protected from falling earth during and after placing. Concrete placed in
ground
containing deleterious substances shall be kept free from contact with such ground or with water
leaking from such ground during placing of concrete and for a period of three days or as otherwise
instructed by the Employer after placing of concrete. The ground water around newly poured concrete
shall be kept to an approved level by pumping or other approved means of drainage. Adequate steps
shall be taken to prevent floatation or flooding. Steps, as approved by the Employer, shall also be
taken to protect immature concrete from damage by debris, excessive loading, vibration etc. which
may impair the strength or durability of the concrete. All fresh concrete shall be covered with a layer
of Hessian or similar absorbent material and kept constantly wet for a period of seven days or more
from the date of placing of concrete as per directions of the Employer. Curing can also be made by
ponding. Concrete shall be cured by flooding with water of minimum 25mm depth for the period
mentioned above. Step shall also be taken to protect immature concrete from damage debris by
excessive loading, vibrations, abrasions, deleterious ground water, mixing
with earth or foreign materials, floatation etc. that may impair the strength and durability of the
concrete. Approved curing compound can be used with the permission of the Employer. Such
compound shall be applied to all exposed surfaces of the concrete as soon as possible after the
concrete has set.
Installation of piles shall be carried out as per pile layout drawings, installation criteria, technical
specifications and the directions of the Employer.
27.3.9.1.1 The equipment and accessories for installation of bored cast-in-situ piles shall be selected
giving due consideration to the sub soil conditions, ground water conditions and the method of
casting, etc. These shall be of standard type and shall have the approval of the Employer.
27.3.9.1.2 The capacity of the rig shall be adequate so as to reach the specified founding level.
27.3.9.1.3 Provision shall be kept for chiseling within the pile bore, as specified in this specification.
Chiseling shall be carried out only with the approval of Employer. The contractor must have the
provision of equipment/accessories which can bore in the hard rock strata if required, without any
additional
27.3.9.2.1 The Contractor while boring the pile bores, shall constantly collect the bore spoils and
these shall be compared with the layer wise soil classifications reported in the bore-log details of the
location, reported in
the soil investigation report. Should there be any variation between the two-soil classification, these
shall be immediately reported to the Employer.
27.3.9.2.2 Whenever the rock strata is encountered in the pile bore, the Contractor shall immediately
report the matter to the Employer and shall take up the work of rock chiseling or any other suitable
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
method only after the certification/approval of the Employer. Since the piles are required to be
terminated in the firm/hard strata and as stipulated in the construction drawing the Contractor shall
demonstrate such founding strata and seek approval of the Employer before terminating the piles.
27.3.9.2.3 The pile should be socketed and founded in good rock only. Whenever rock strata is
encountered at any pile bore and the level of good rock (i.e. rock strata is not highly fractured and
weathered and core recovery is not less than 80% with RQD 70%) is different than that is given in the
Geotechnical Investigation report, in that case to establish the level of good rock, core drilling is
necessary to be carried out at least upto 5m depth in rock strata encountered by the contractor without
any additional cost implication to AEGCL and no time extension will be permitted on this account.
27.3.9.2.4 In order to verify the terminating depth, where rock strata is met with, the rock samples
obtained from the bore spoils of pile shall also be tested for point load strength index and these shall
then be compared/correlated to the values of uniaxial compression strength test shown in the soil
investigation report. Accordingly, the termination of piles in the socketing zone shall be done with
prior approval of the Employer.
Piles shall be installed vertically as accurately as possible as per the construction drawing. The
permissible limits for deviation with respect to position and inclination/alignment shall conform to IS-
2911 (Part I/Sec.2), as reproduced below.
27.3.9.3.1 Maximum permissible deviation in alignment is 1.5% . Piles should not deviate more than
75mm or D/10 whichever is less from their positions at the working level. In case of piles deviating
beyond these limits, the piles should be replaced or supplemented by one or more additional piles
including the revised cap size( as the situation may be) at no additional cost to the Employer. Any
extra claim whatsoever from the contractor on this account shall not be entertained.
27.3.9.4 Boring
27.3.9.4.1 Boring operations shall be done by rotary or percussion type drilling rigs using Direct Mud
Circulation (DMC), Reverse Mud Circulation (RMC) methods or grab method. In soft clays and loose
sands bailer method, if used, shall be used with caution to avoid the effect of suction. In cohesive
soils, use of water for boring shall be restricted to a minimum, while boring in cohesion less deposits
water level in the bore hole shall be maintained at or slightly above the standing water table. Boring
operations by any of the above methods shall be done using drilling mud. The bidder shall be required
to furnish along with their bid, complete details regarding the installation of piles and the method by
which they wish to install the piles.
27.3.9.4.2 The Contractor shall satisfy himself about the suitability of the method to be adopted for
site. If DMC or RMC is used, bentonite slurry shall be pumped through drill rods by means of high-
pressure pumps. The cutting tools shall have suitable pores for the bentonite slurry to flow out at high
pressure. If the Contractor fails to make proper bore for any reason, the Contractor has to modify the
boring technique and switchover to other boring methods as approved by the Employer at no extra
cost to the Employer.
27.3.9.4.3 Working level shall be above the pile cut off level. After the initial boring of about 1.0 to
2.0m temporary guide casing shall be lowered in the pile bore. The diameter of guide casing shall be
of such diameter to give the necessary finished diameter of the concrete pile. The center line of guide
casing shall be checked before continuing further boring. Guide casing shall be minimum 2.0m
length. Additional length of guide casing shall be used depending on the conditions of the strata,
ground water level etc. as required by the Employer without any additional cost to the Employer.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.9.4.4 Use of drilling mud (bentonite slurry) for stabilising the sides of the pile bore is necessary
wherever subsoil is likely to collapse in the pile bore. Drilling mud to be used shall meet the
requirement as given in Annexure-C.
27.3.9.4.5 The bentonite slurry and the cuttings, which are carried to the surface by the rising flow of
the slurry shall pass through settling tanks of adequate size to remove the sand and spoils from the
slurry before the slurry is recirculated back to the boring. The bentonite slurry mixing and
recirculation plant shall be suitably designed and installed.
27.3.9.4.6 The bentonite slurry shall be maintained at 1.5m above the ground water level during
boring operations and till the pile is concreted. When DMC or RMC method is used the bentonite
slurry shall be under constant circulation till start of concreting.
27.3.9.4.7 The size of cutting tools shall not be less than the diameter of the pile as specified in the
drawing and not more than 75mm.
27.3.9.5 Chiseling
27.3.9.5.1 Chiseling, if required, may be resorted to with the permission of the Employer below the
socketing horizon. The chiseling tool or bit shall be of adequate size and weight so as to reach the
desired depth.
27.3.9.6.1 After completion the pile bore up to the required depth, the bottom of the pile bore shall be
thoroughly cleaned. Cleaning shall ensure that the pile bore is completely free from sludge/bored
material, debris of rock/boulder etc. Necessary checks shall be made as given in this Section to
confirm the thorough cleaning of the pile bore.
27.3.9.6.2 Pile bore shall be cleaned by fresh drilling mud through tremie pipe before start of
concreting and after placing reinforcement.
27.3.9.6.3 Pile bore spoil along with used drilling mud shall be disposed off from site up to 2 Km. or
as directed by the Employer.
27.3.9.7.1 When working near existing structures care shall be taken to avoid any damage to such
structures.
27.3.9.8 Concreting
27.3.9.8.1 Concreting shall not be done until the Employer is satisfied that the bearing strata
(soil/rock) met with the termination level of pile, satisfied the installation criteria/approved founding
depth.
27.3.9.8.2 The time between the completion of boring and placing of concrete shall not exceed 6 hrs.
In case the time interval exceeds 6 hrs the pile bore shall be abandoned. However, the Employer may
allow concreting, provided the Contractor extends the pile bore by 0.5 m beyond the proposed depth,
and clean the pile bore properly. The entire cost of all operation and materials for this extra length
shall be borne by the Contractor.
27.3.9.8.3 Pile bore bottom shall be thoroughly cleaned to make it free from sludge or any foreign
matter before and after placing the reinforcement cage.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.9.8.4 Proper placement of the reinforcement cage to its full length shall be ensured before
concerting.
27.3.9.8.5 Entire concreting in pile bores shall be done by tremie method. The operation of tremie
concreting shall be governed by IS:2911 Part I/Sec.2.Drilling mud shall be maintained sufficiently
above the ground water level.
27.3.9.8.6 Concreting operations shall not proceed if the contaminated drilling mud at the bottom of
the pile bore possess density more than 1.25 T/Cu.m. or sand content more than 7%. The drilling mud
sample shall be collected from the bottom of pile bore. This shall be checked at regular intervals, as
decided by the Employer thereafter.
27.3.9.8.7 Consistency of the drilling mud suspension shall be controlled throughout concreting
operations in order to keep the bore stabilised as well as to prevent concrete getting mixed up with the
thicker suspension of the mud.
27.3.9.8.8 It shall be ensured that volume of concrete poured is at least equal to the theoretically
computed volume of pile shaft being cast.
27.3.9.8.9 The temporary guide casing shall be entirely withdrawn cautiously, after concreting is done
up to the required level. While withdrawing the casing concrete shall not be disturbed.
27.3.9.8.10 Tests on concrete cubes shall be carried out as specified in this section of the
Specifications.
27.3.9.9.2 The top of concrete in pile shall be brought above the COL to remove all laitance and weak
concrete and to ensure good concrete at COL for proper embedment into pile cap.
27.3.9.9.3 When the pile cut off level is less than 1.0 meter below the working level, concrete shall be
cast up to the piling platform level to permit overflow of concrete for visual inspection. In case COL
of pile is more than 1.0 meter below working level then concrete shall be cast to minimum of one
meter above COL.
27.3.9.9.4 In the circumstances where COL is below ground water level, the need to maintain a
pressure on the unset concrete equal to or greater than water pressure shall be observed and
accordingly length of extra concrete above COL shall be determined by the Contractor with prior
approval of Employer.
27.3.9.10.1 Each pile shall be identified with a reference number and date wise proper record of
construction shall be maintained by the Contractor.
27.3.9.10.2 The convenience of installation may be taken into account while scheduling the sequence
of piling in a group. This scheduling shall avoid piles being bored close to other recently constructed
piles.
27.3.9.11.1 If any pile, already cast as per construction drawing, requires any extra casting due to any
change in cut off level or the cast pile top level is less than the specified level or for any other reason,
then the pile shall be built up by using M-20 grade of concrete with minimum cement content
400kg/m3, ensuring proper continuity with the existing concrete and to the satisfaction of the
Employer. Necessary reinforcement as per design requirement and suitable shuttering shall be
provided before casting the concrete. Surrounding soil shall also be built up to the required level by
proper compaction to ensure lateral capacity of the pile.
27.3.9.12.1 If any pile already cast requires breaking due to lowering in cut off level or for any other
reason, then the same shall be carried out, (not before seven days of casting of concrete in the piles)
without affecting the quality of existing pile such as loosening, cracking etc. to the satisfaction of the
Employer. No extra payment shall be made on this account.
27.3.9.13.1 The soil surrounding the piles shall be excavated up to the bottom of the lean concrete
below the pile cap with provision for working space sufficient enough to place shuttering,
reinforcement, concreting and any other related operations.
27.3.9.13.2 The exposed part of concrete above the COL, shall be removed/chipped off and made
square at COL not before seven days of casting of pile.
27.3.9.13.3 The projected reinforcement above COL shall be properly cleaned and bent to the
required shape and level to be anchored into the pile cap as shown in the drawing.
27.3.9.13.4 The pile top shall be embedded into the pile cap by minimum 50mm or clear cover to
reinforcement, whichever is higher.
27.3.9.13.5 All loose material on the top of pile head after chipping to the desired level shall be
removed and disposed off up to a lead of 2km or as directed by the Employer.
27.3.9.14.1 The Employer reserve the right to reject any pile which in his opinion is defective with
reference to technical specification & construction drawings on account of load capacity, structural
integrity, position, alignment, concrete quality etc. Piles that are judged defective shall be pulled out
or left in place as decided by the Employer without affecting the performance of adjacent piles. The
Contractor shall install additional piles to substitute the defective piles as per the directions of the
Employer at no extra cost to the Employer.
27.3.9.14.2 During execution of pile foundation work, if the bore holes need to be abandoned due to
any reason and pile position to be shifted or realigned, other than for any design requirement by the
Employer, fresh bore holes are to be executed at a suitable new position, which may vary from 2D to
3D (where, D is diameter of pile) as decided by the Employer, which may demand for resizing of pile
cap including possible increase in reinforcement quantity due to resizing of pile cap. In all such cases
the abandoned bore holes are to be filled up with plain cement concrete M15 so that no cavity remains
in the bore hole of the abandoned pile.
Any extra claim whatsoever from the contractor on account of abandoned bore hole, filling up of
abandoned bore hole with concrete and any extra cost due to resizing of pile cap including increase in
reinforcement quantity shall not be entertained by the Employer & the same have to be borne by the
contractor.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.9.15.1 The piles can be terminated at a depth based on design developed by the Employer, where
loads on the piles can be transmitted to the soil in a proper manner or the depth where specified `N'
value is achieved, whichever occurs later. However, in no case piles should be terminated at a higher
level than that indicated in the construction drawing.
27.3.9.15.2 Standard penetration test (SPT) shall be carried out starting from 1.0 M above the
specified pile termination depth and there after @ 1m. up to the pile termination depth.
27.3.9.15.3 The Standard Penetration Test (SPT) shall be carried out based on the following test
procedures:
The test shall be conducted by driving a standard split spoon sampler in the borehole by means of a
650 N hammer having a free fall of 0.75 M. The sampler shall be driven for 450 mm using the
hammer and the number of blows shall be recorded for every 150mm penetration. The number of
blows for the last 300 mm drive shall be reported as N value. The test shall be discontinued when the
blow count is equal to 100 or the penetration is less than 25mm for 50 blows, whichever is earlier. At
the location where the test discontinued, the penetration and the number of blows shall be reported.
Sufficient quantity of disturbed sample shall be collected from the split spoon sampler for
identification/classification of soil. The sample shall be visually classified and recorded at the site.
The specification for the equipments and other accessories, procedure for conducting the test and
collection of the disturbed soil sample shall conform to IS:2131.
27.3.9.16.1 The Contractor shall record all the information during installation of piles.
Typical data sheet for recording pile data as shown in Appendix D of IS:2911 Part I/Sec.2 shall be
maintained by the contractor. The pile data shall also include all the details as in Annexure-D. On
completion of each pile installation, pile record in triplicate shall be submitted to Employer within
two days of completion of concreting of the pile.
27.3.9.17.1 On completion of boring and cleaning the bottom of each pile bore shall be checked by
the methods as approved by the Employer, to ensure that it is free from pile bore spoil/debris and any
other loose material, before concreting. Concreting shall be done only after the approval of the
Employer.
27.3.9.17.2 For sampling of drilling mud from the pile bore the following method or any other
suitable method shall be adopted. A solid cone shall be lowered by a string to the bottom of pile bore.
A sampler tube closed at top with a central hole (hollow cylinder) is lowered over the cone, then a top
cover shall be lowered over the cylinder. Care shall be taken for proper fittings of assembly to
minimise the leakage while lifting the cone assembly to the ground surface. The slurry collected in the
sampler tube shall be tested for density and sand content.
27.3.9.18.1 Properties of drilling mud shall be checked as per requirements indicated in Annexure ‘C’
prior to the commencement of piling work and thereafter at least once in a week or as found necessary
by the Employer, one sample consisting of 3 specimens shall be tested.
27.3.9.18.2 Density and sand content of the drilling mud shall be checked in each pile.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.10.1 This covers the technical requirements for the supply and fabrication and/or erection of all
embedded steel parts by the Contractor. The extent and type of embedded steel parts to be erected
shall be as per detailed drawings.
27.3.10.2 The supply of embedded steel parts like ladders, steel pieces set in concrete inserts, dowel
bars required for construction joints etc. are in the scope of the Contractor. However, supply of anchor
bolts/stubs, as the case may be, will be supplied by tower contractor.
27.3.10.3 Embedded steel parts shall include items such as foundation anchor bolts, stubs, ladders,
steel pieces set in concrete inserts, dowel bars for concrete work etc. shown on the drawing or as
required by the Employer.
Material shall also include setting in forms for connecting in place and grouting as required. The
grouting operations, if required, shall be performed as per the direction of Employer.
27.3.10.4 The Contractor shall erect all embedded steel parts in accordance with the drawings and
these specifications including setting materials in concrete or grouting pieces in place, furnishing all
labour, materials, scaffolding, tools and services necessary for and incidental to the work to its
transporting, unloading, storing, handling and erection. Contractor shall furnish welding rods and
arrange for field welding as required in accordance with IS : 816.
27.3.10.5 Exposed surface of embedded material are to be painted with one coat of approved
anticorrosive and/or bituminous paint without any extra cost to the Employer. The threads of holding
down bolts shall be greased and protected with water proof tape.
27.3.11.0 Installation
27.3.11.1 During erection, the Contractor shall provide necessary temporary bracing or supports to
ensure proper installation of the materials. All materials shall be erected in the true locations as shown
in the drawings, plumb and level. Extreme care shall be taken to ensure that the threads of holding
down bolts and comparable items are protected from damage.
27.3.11.2 Groups of holding down bolts shall be set in such a manner that the tolerance of whole
group is not more than 3mm from its true position in plan at the top of the bolt and not more than
3mm from the required level. The top ends of all bolt shanks shall be in one plane to the tolerance
stated above. Holding down bolt assemblies shall be set vertically to a tolerance of not more than
1:500.
27.3.12.1 All steel work shall be efficiently and sufficiently protected against damage in transit to site
from any cause whatsoever. All protecting plates or bars and all ends of members at joints shall be
stiffened, all straight bars and plates shall be bundled, all screwed ends and machined surface shall be
suitably packed and all bolts, nuts, washers and small loose parts shall be packed separately in cases
so as to prevent damage or distortion during transit. Should there be any distortion of fabricated
members, the Contractor shall immediately report the matter to the Employer. Distorted reinforcement
bars or plates received from stores or distorted during transport from stores to the fabrication yard
shall not be used in fabrication unless the distortions are minor which in the opinion of the Employer
can be removed by acceptable methods. The cost of all such straightening shall be borne by the
Contractor within his unit rates. These distortions shall be rectified by the Contractor by cold bending.
If heating is necessary to rectify the defects, the details of the procedure shall be intimated to the
Employer whose approval shall be taken before such rectification. The temperature of heat treatment
shall not exceed the limits beyond which the original properties of steel are likely to be impaired.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.13.1 The foundation bolts / stubs, as required, for the tower structures shall be supplied by the
respective tower contractor. These shall be embedded in concrete while the foundation is cast. The
Contractor shall ensure the proper alignment of these bolts to match the holes in the base plate and
also co-ordinate with the respective tower contractor for its correctness. The final adjustment of these
bolts and their grouting are included in the scope of this contract. Grouting of block outs and the gap
between the base plate and top of concrete shall be done by the Contractor after finalisation of
alignments. The unit rate of concreting shall include the cost of above adjustments, grouting, and
skins etc. required for this purpose.
27.3.13.2 The Contractor shall be responsible for the correct alignment and levelling of all steel work
on site to ensure that the towers are in plumb.
27.3.13.3 Before erection of towers, by tower contractor, on the foundations the top surface of base
concrete shall be thoroughly cleaned with wire brushes and by chipping to remove all laitance and
loose materials and shall be chipped with a chisel to ensure proper bond between the grout and the
foundation concrete. The piling Contractor shall also be responsible for bringing down the top of
concrete to the desired level by chipping. In case the foundation as cast is lower than the desired level,
the Contractor shall make up the difference by providing additional pack plates without extra cost for
any such work or material. No steel structures shall be erected on their foundations unless such
foundations have been certified fit for erection by the Employer. Adequate number of air release holes
and inspection holes shall be provided in the base plate.
27.3.14.1 The Contractor shall be responsible for the stability of the structure at all stages of its
erection at site and shall take all necessary measures by the additions of temporary bracings and
guying to ensure adequate resistance to wind and also to loads due to erection equipment and their
operations.
Guying and bracing shall be done for erection equipment and their operations. Guying and bracing
shall be done in such a way that it does not interface with the movement or working of other agencies
working in
the area. For the purpose of guying, the Contractor shall not use other structures in the vicinity which
are likely to be damaged by the guy. Such temporary bracings shall neither be included in the
measurement nor extra rate shall be payable. Such temporary bracings used shall be the property of
the Contractor and may be removed by him at the end of the job from the site of work.
27.3.15.1.1 Furnishing of all labour materials and equipment and performance of all operations
necessary to complete the work of grouting of block outs and foundation bolt holes and under pinning
of base plates is in the scope of the Contractor. The cost of the above shall be included in the unit
concreting rate.
27.3.15.1.2 Grouting shall be adopted for filling the block outs, pockets below foundation bolt holes.
The block out and bolt holes which have to be grouted shall be cleaned thoroughly by use of
compressed air immediately before taking up the grouting operations.
27.3.15.1.3 Cement and alluminium powder or anti-shrinkage admixture of approved quality shall be
first blended thoroughly in the required proportions as per manufacturer’s specification. The mix of
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
grouting shall contain one part of cement and two parts of coarse sand. Admixture should be
according to IS:9103.
27.3.15.1.4 The quantity of aluminum powder shall usually be of the order of 0.005% by weight of
cement. Any grout which has been mixed for a period longer than half an hour shall not be used on
the work. Immediately after preparation the grout shall be poured into the block outs, pockets and
foundation bolt holes either from the sides or through the holes provided for this purpose in the base
plate, by using special equipment for pressure grouting. It shall be ensured by rodding and by tapping
of bolts that the block out is completely filled without leaving any voids. The pouring shall cease as
soon as each hole is filled and any excess grout found on the surface of the concrete foundation shall
be completely removed and the surface dried.
27.3.15.1.5 Under pinning It shall be resorted to for filling the space between the underside of base
plate and the top of foundation concrete. After grouting has been completed as specified above, space
between the top surface of the foundation concrete and the underside of the base plate shall be filled
with mortar or concrete depending upon thickness to be filled as follows :
Less than 40mm Dry packed cement mortar Over 40mm Dry packed fine concrete Mortar, fine
concrete shall be blended with aluminium powder about 0.005% by weight of cement or with anti-
shrinkage admixture in a suitable proportion to the cement mortar in accordance with the
recommendations of the manufacturer and subject to the approval of the Employer. Mortar shall
comprise cement, sand and water in proportion of approx. 1:3:0.4 by weight. Concrete shall comprise
cement, sand, 10mm max. Sized aggregate and water in proportion of 1:1.25:2:0.4 by weight. In all
cases minimum 28 days cube strength should not be less than 25N/mm2. Shims provided for the
alignment of bases shall be positioned at the edges of the base to permit subsequent removal which
shall take place not less than 7 days after the underpinning has been executed. The resulting cavities
shall be made good with the same grade of mortar or concrete as has been used for the underpinning
of the rest of the base plate.
27.3.15.1.6 Cement, sand and aluminium powder or approved anti-shrinkage admixture, shall first be
blended thoroughly in the required proportion. The mortar shall then be prepared by mixing with
quantity of water which will produce a sufficiently workable mix to enable complete and proper
compaction of the mortar.
27.3.15.1.7 The mortar shall then be placed below the base plate and rammed in a horizontal direction
for each edge until the mortar oozes out through the grout holes provided in the base plate.
27.3.15.1.8 When it is clear that the center of base has been properly filled, the mortar outside the
base plate shall be briefly rammed to ensure compaction below the edges. Any mortar which has been
mixed for a period longer than half an hour, shall not be used in the work.
27.3.15.2 Materials
27.3.15.2.1 Cement shall conform to the stipulations contained in IS:8112and shall have a fineness
(specific surface of cement) not less than 225 sq.m./kg when tested for fineness by Blaine’s air
permeability method as per IS:4031.
27.3.15.2.3 Water shall be clean and fresh and shall be of potable quality.
27.3.15.2.4 Aluminium powder or anti-shrinkage admixture like ‘Groutex’ CRS-NS grout (by Cement
Research Institute of India) or its equivalent shall be of standard brand from reputed manufacturer and
shall be approved by the Employer prior to its use for work.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
27.3.15.3 CURING
The work shall be cured for a period of 7 days commencing 24 hours after the completion of the
grouting and under pinning operations. The curing shall be done by covering the surfaces with wet
gunny bags.
27.3.16.1 This covers the technical requirement for furnishing and installation of bar grips complete
including all labour materials, equipments, staging, etc.
27.3.16.2 The Contractor shall furnish and install the bar grips for various dia. of deformed bars as
indicated in drawings and as required by these specifications. The bar grip splicing system shall be of
approved manufacturer and of the best quality available subject to approval of the Employer.
27.3.17.0 Splicing
27.3.17.1 a) The reinforcement bars are to be joined without any gap and the sleeve placed in position.
b) Pressure is applied by means of a hydraulic press which swages the sleeve down on the bar ends in
a series of bites which are applied at high pressure.
c) The job can also be done in two stages. The 1 st stage is to press the half sleeve on the loose bar at
the reinforcement yard. The 2nd stage work is to be done at the actual site after the loose bar is inserted
through the unpresented end of the sleeve and pressed in-situ.
27.3.17.2 The joints shall be staggered as far as possible. Necessary staging arrangements are to be
made by the Contractor.
27.3.17.3 It may be necessary to fix the sleeve to the reinforcement bars at one end in the open yard
for the facility of working. All these working details are to be furnished earlier subject to the approval
of the Employer.
27.3.17.4 The length of the sleeve should be adequate, that it is safe under the pull-out loading
conditions.
27.3.17.5 One percent representative samples of each dia. bars shall be sent for laboratory testing at
the cost of the Contractor to check the efficiency of the joints under ideal condition. These samples of
sleeves will be sent in the Laboratory for pull out tests.
27.3.17.6 All bar grips installation shall be subject to inspection and approval by the Employer before
concreting operation are performed. In case of any defect or joint being not up to mark, the same shall
be replaced by the Contractor at no extra cost.
27.3.18.0 MS Liner
MS liner (minimum 10 mm thick) shall be provided in line with Geo-Technical investigation report
relevant IS Codes wherever included in the construction drawings Approved by the Employer and/or
otherwise required by the Employer.
NOTE:
At the time of execution, the soil strata should match with the parameters considered in the design of
pile foundation. For that req. standard penetration tests will be carried out by contractor to ascertain
the design parameters. Any change req. in design will have to be carried out with the prior approval of
Engineer-in-charge.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
28.3.3 Wet
To be used for locations:
a) Where sub-soil water is met between 1.5 meters and the depth of foundation
below the ground level.
b) Which are in surface water for long period with water penetration not
exceeding one meter below the ground level e.g. paddy fields.
To be used at locations where sub-soil water table is met at less than 0.75 meter
below the ground level.
28.4.2 Depending on the site conditions other types of foundations shall also be
designed and provided by the Owner suitable for Intermediate conditions under
the above classifications to effect more economy or to suit specific site
conditions encountered.
28.4.3 The proposal for these types of foundations shall be submitted by the
Contractor based on the detailed soil investigation and duly recommended by
Engineer-incharge.
28.4.4 The special foundations like pile foundations if required shall also be
designed
by the Owner based on detailed soil investigation report .The working drawing
of these foundations shall be provided by the Employer to the Contractor during
execution stage based on requirements. For detailed specification for pile
foundations Section VIII of this specification shall apply.
28.7.1 Excavation
28.7.1.1 The excavation work for foundations shall be taken up by the
contractor progressively stretch wise / section wise after obtaining approval
from Owner for the proposed stretch wise / section wise tower schedule, profile
etc. as per detailed survey along the approved route alignment.
a) Dry Soil
Soil removable either manually, by means of a spade and shovel or
mechanically by proclaims, excavators etc. Excavation done in dry soil for wet,
partially submerged, fully submerged and wet black cotton type of foundations
shall also be covered under this.
b) Wet Soil
Where the subsoil water table is encountered within the range of foundation
depth or land where pumping or bailing out of water is required due to presence
of surface water shall be treated as wet soil. The excavation done in wet soil in
case of wet, partially submerged, fully submerged and wet black cotton type of
foundation shall also be covered under this .
e) Hard Rock
Any rock excavation, other than specified under fissured rock above, for which
blasting, drilling, chiseling are required. The unit rate quoted for hard rock
excavation shall be inclusive of all costs for such drilling (including drilling
required for anchoring), chiseling and blasting, etc.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
28.7.1.4 No extra payment shall be admitted for the removal of fallen earth into
a pit or borehole once excavated.
28.7.1.5 Where rock is encountered, the holes for tower footings shall
preferably be drilled. Blasting where resorted to as an economy measure, shall
be done with utmost care to minimise fracturing rock and using extra concrete
for filling the blasted area. All necessary precautions for handling and use of
blasting materials shall be taken. In cases where unnecessarily large quantities
are excavated/blasted, resulting in placement of large volumes of concrete,
payment of concrete shall be limited to design volumes of excavation,
concreting, reinforcement etc. In case where drilling is done, the stubs may be
shortened suitably with the approval of the Owner.
28.7.1.6 The Contractor shall arrange & supply requisite blasting material, and
be responsible for its storage and use, without any extra cost to the Owner.
28.8.2 The unit rates of excavation for each type of soil shall include excavation
along with all associated activities like shoring, shuttering, dewatering till
completion of foundation work stock piling, dressing, back filling of
foundations after concreting
with excavated/borrowed earth (irrespective of lead) and consolidation of earth,
carriage of surplus earth to the suitable point of disposal as required by the
Owner or any other activity required for to completion of foundation work in all
respect. The measurement for excavation shall be made on the basis of design
excavation Volume arrived at considering dimension of pit leaving 150mm gap
around (except for under cut foundations) the base pad or actually excavated
whichever is less and the unit rate of this item as indicated in Letter of Award.
The payment for excavation shall be made as per actual type of soil encountered
at the time of excavation, but the total payment for excavation portion shall not
exceed the amount as payable for excavation considering the soil type same as
that of foundation classification. The decision of the Owner shall be final and
binding with respect to classification of soil and foundations.
28.8.3 Form boxes shall be used for casting of foundations. The unit rate of
concreting
shall include the cost of supply, fabrication and placement of form boxes,
cement, water, coarse and fine aggregates mixing and placing of concrete,
curing of concrete and any other activities related / required for completion of
concreting works of foundation. The payment for this item shall be made as per
the actual volumes of concreting completed but limited to design volume based
on unit rates indicated in the letter of award.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
28.8.4 The unit rate of ‘Reinforcement Steel’ shall include supply and
placement of reinforcement steel, stirrups, wire for binding the reinforcement,
chairs, bolsters and spacers etc. as required to complete the foundation work.
The measurement of reinforcement steel for payments shall be made based on
the calculated weight of reinforcement steel in tones corrected to third place of
decimal as per relevant Indian Standard and as per working drawing or the
quantity of reinforcement steel actually used, whichever is less. No allowance
permitted towards wastage.
28.9.3 However, in hilly region for towers with unequal leg extensions and for
river crossing towers, props may be used with complete accuracy and high
skilled supervision, subject to prior approval from Owner.
28.9.4 For all towers the Contractor shall submit for approval the proposed
method for
setting of stubs.
28.10.5.2 The Contractor shall deploy sufficient number of templates / props for
timely
completion of the line without any extra cost to Owner.
However, if more templates are required for timely completion of the lines, the
Contractor shall deploy the same without any extra cost to Owner. The number
of sets of prop (if permitted) to be supplied, will depend as per actual site
condition and completion schedule of line.
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
28.10.5.4 One set of each type of stub setting template / props (if used) shall be
supplied to the Owner, on completion of the project, at no extra cost to Owner.
28.10.4 Form boxes shall be used for casting all types of foundations except at
an undercut interface for which the adjoining subsurface material shall provide
adequate support.
28.10.5 The concrete shall be laid down in 150mm layers and consolidated well,
so that the cement cream works, up to the top and no honey-combing occurs in
the concrete. A mechanical vibrator shall be employed for compacting the
concrete. However, in case of difficult, terrain, manual compaction may permit
at the discretion of the Owner. Monolithic casting of foundations must be
carried out. However, in case of unavoidable circumstances, a key construction
joint can be provided at the chimney-pad interface subject to approval of the
Owner.
However, nothing extra shall be paid to the Contractor for providing such
construction joints. After concreting the chimney portion to the required height,
the top surface should be finished smooth with a slight slope towards the outer
edge for draining rain water.
28.10.6 Wet locations shall be kept completely dewatered, both during and 24
hours after placing the concrete, without disturbance of the concrete.
28.10. 7 If minor defects in concrete surface is found after the form work has
been removed, the damage shall be repaired with a rich cement sand mortar to
the satisfaction of the Owner before the foundation is back filled.
28.11 Curing
The concrete shall be cured by maintaining the concrete wet for a period of at
least 10 days after placing. Once the concrete has set for 24 hours the pit may be
backfilled with selected moistened soil and well consolidated in layers not
exceeding 200mm thickness and thereafter both the backfill earth and exposed
chimney shall be kept wet for the remainder of the prescribed 10 days. The
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
exposed concrete chimney shall also be kept wet by wrapping gunny bags
around it and wetting the bags continuously during the critical 10 days period.
28.12.2 The backfilling materials shall be clean and free from organic or other
foreign
materials. A clay type soil with a grain size distribution of 50% or more passing
the no. 200 sieve are unacceptable for backfilling. The earth shall be deposited
in maximum 200mm layers, levelled, wetted if necessary and compacted
properly before another layer is deposited. The moisture content for compaction
shall be based on the Proctor compaction test results given in the Geo-technical
Report, Clause 3.0 of section III. The density of the compacted backfill material
may further be verified to the satisfaction of the Owner based on the sand-cone
method described in the ASTM D1556-82 standard.
28.13 Benching
When the line passes through hilly/undulated terrain, levelling the ground may
be required for casting of tower footings at no extra cost to the Employer. All
such activities shall be termed benching and shall include cutting of excess earth
and removing the same to a suitable point of disposal as required by Owner.
Benching shall be resorted to only after approval from Owner. Volume of the
earth to be cut shall be measured before cutting and approved by Owner for
payment purposes.
Further, to minimise benching, unequal leg extensions shall be considered and
provided if found economical. The proposal shall be submitted by the
Contractor with detailed justification to the Owner.
28.14.2 The work shall include all necessary stone revetments, concreting and
earth filling above ground level, the clearing from site of all surplus excavated
soil, special measures for protection of foundation close to or in nalas, river
bank / bed, undulated terrain, protection of up hill / down hill slopes required for
CHAPTER 27: TOWER FOUNDATION FOR 220KV & 132KV TRANSMISSION LINES & PILE
FOUNDATION
28.14.3 Tower footings shall generally be backfilled using soil excavated at site
unless unsuitable for backfilling. In the latter case, backfilling shall be done
with borrowed earth of suitable quality irrespective of leads and lift. The unit
rate for backfilling quoted shall include the required lead and consolidation and
levelling of earth after backfilling.
28.14.4 The quantities for protection work of foundations are provisional only.
The unit rates shall also be applicable for any quantity variations during
execution. The same unit rates shall hold good for protection work carried out
on down hills or up hills slopes applicable for the tower locations.
28.14.5 The unit rates for random rubble masonry revetment quoted in price
schedule shall also include excavation & (1:6) random masonry and unit rate for
top sealing with M-15 concrete. For payment purposes the volume of random
rubble masonry revetment shall be measured from bottom to top sealing coat
and paid at the unit rates indicated in the Letter Of Award. No extra payment
shall be made for allied works such as excavation for revetment, packed stone at
head of weep holes etc. However, no deduction shall be made for the volume
enclosed by weep holes.
28.14.6 For some of the locations in nalas, river bed or undulated terrain etc.,
boulders of minimum. 150mm size bounded and packed in galvanised wire
net/mesh of 8 SWG wire and 152 square (maxm.) mesh are to be provided.
These stones shall be provided in crates size of 2.0mx2.0m or as deemed
suitable for a particular location. Measurement shall be taken in cubic meters
and 15% deduction will be made for void from cage/stack measurements.
running out blocks will be of such a design that the seat is semi-circular and larger than the diameter
of the Conductor and it does not slip over or rub against the sides. The grooves shall be lined with
hard rubber or neoprene to avoid damage to Conductor and shall be mounted on properly lubricated
bearings.
29.05.2 The running blocks shall be suspended in a manner to suit the design of the cross arm. All
running out blocks especially those at the tensioning end, will be fitted on the cross arm with jute
cloth wrapped over the steel work and under the slings to avoid damage to the slings as well as to the
protective surface finish of the steel work. The Conductor shall be continuously observed for loose or
broken strands or any other kind of damage. When approaching towards end of a drum length, at least
three coils shall be left when the stringing operations are to be stopped. These coils are to be removed
carefully if another length is required to be run out, new length may be joined to the length already
run out by the compression joint in approved manner. The Conductor joints and clamps shall be
erected in such a manner that no bird caging, over tensioning of individual wires or layers or other
deformities or damage to the conductor shall occur. Clamps or bracing devices shall under erection
conditions allow no relative movement of strands or layers of the conductors.
29.05.3 Repairs of Conductors, in the event of damage being caused to isolated strands of a conductor
during the course of erection, if necessary, shall be carried out during the running out operations, with
repair sleeves. Repairing of Conductor surface with repair sleeve shall be done only in case of minor
damage, scuff marks etc., keeping in view both electrical and mechanical safety requirements.
Number of damaged strands shall not exceed 1/6 th of the total strands in the outer layer. The final
Conductor surface shall be clean, smooth and shall be without any projections, sharp points, cuts,
abrasions etc. Repair sleeves may be used when the damage is limited to the outermost layer of the
Conductor and is equivalent to the severance of not more than one third of the strands of the
outermost layer. No repair sleeve shall be fitted within 30 m of tension or suspension clamp or
fittings. Further, more than one repair sleeve per Conductor shall not be normally used in any single
span.
29.05.4 Conductor splices shall be so made that they do not crack or get damaged in the stringing
operation. The Contractor shall use only such equipment/ methods during Conductor stringing which
ensures complete compliance in this regard.
29.05.5 Derricks shall be used where roads, rivers, canals, telecommunication or overhead power
lines, railway lines, fences or walls have to be crossed during stringing operations. It shall be seen that
normal services are not interrupted, and no damage is caused to property. Shut down shall be obtained
when working at crossing of overhead power lines.
29.05.6 The sequence of running out shall be from top to downwards, i.e. the Ground-wire shall be
run out first followed by the Conductors in succession. Imbalances of loads on towers shall be
avoided as far as possible i.e. both Ground-wires, then both bundles of top Conductor and then both
bundles of middle Conductor followed by both bundle Conductors of bottom Cross-arm should be
strung.
29.05.7 The proposed transmission line may run parallel for certain distance with the existing
400/220/132KV lines which will remain energized during the stringing period. As a result, there is a
possibility of dangerous voltage build up due to electromagnetic and electrostatic coupling in the
pulling cables, Conductors and Ground-wires, which although comparatively small in magnitude
during normal operations, can be severe during switching and ground fault conditions on the
energised lines. It shall be the Contractor’s responsibility to take adequate safety precautions to
protect his employees and others from this potential danger.
29.06 STRINGING OF CONDUCTOR AND EARTHWIRE:
CHAPTER 29: ERECTION OF TRANSMISSION TOWER
29.06.1 The stringing of the Conductor shall be done by control in tension method by means of
tension stringing equipments. The equipments shall be capable of maintaining a continuous tension.
The maximum tension imposed on a conductor during stringing operations shall not exceed than that
necessary to clear obstructions on the ground. The contractor shall indicate in their offer, the sets of
tension stringing equipment he is having in his possession and the sets of stringing equipment he
would deploy exclusively for this work.
29.06.2 After being pulled, the Conductor/Ground-wire shall not be allowed to hang in the stringing
blocks for more than 96 hours before being pulled to the specified sag.
29.06.3 The Contractor shall give complete details of the stringing methods, which he proposes to
follow. At least one month in advance of the commencement of stringing, the Contractor will submit
the stringing charts for the Conductors and Ground-wire showing the initial and final sags and tension
for various temperatures and spans, alongwith equivalent spans in the lines, for the approval of the
purchaser. The stringing shall be carried out as per the stringing charts approved by the purchaser and
in accordance with relevant IS. All the tolerances for the line shall conform to IS :5613 (Part-2/Sec-2)
1995.
29.06.4 In hilly terrain and thick forest, where deployment of tension stringing machine is not
possible, manual stringing may be adopted after getting approval of Purchaser’s site Engineer. The
contractor shall deploy appropriate tools/equipments/machinery to ensure that the stringing operation
is carried out without causing damage to conductor/earth wire and conductor/earth wire is installed at
the prescribed sag-tension as per the approved stringing charts.
29.07 JOINTING:
29.07.1 The number of joints in Conductor/Ground-wire shall be kept to minimum possible by
properly selecting the drums from available lot of respective drums. All the joints on the Conductor
and Ground-wire shall be of compression type. Each part of the joint shall be cleaned by wire brush to
make it free of rust or dirt etc. and properly greased with anti-corrosive compound, as approved by
our Engineer before the final compression is done with the compressors. The cost of such grease etc.
used for joints shall not be paid extra and shall be deemed to be included in the stringing rates.
29.07.2 All joints shall be made at least 30 meters away from the structures. No joints shall be made
in the spans crossing over the main roads, railways, rivers etc. Not more than one joint per Conductor
shall be allowed in one span. Care shall be taken to mark the conductor for properly centering the
compression clamp before compressing. During compression operation, the conductor shall be
handled in such a manner as to prevent lateral or vertical bearing against the dies. After pressing the
joint the aluminium sleeve shall have all corners rounded, burrs and sharp edges removed and
smoothened.
29.07.3 Suitable protector shall be used during stringing of Conductor to avoid any damage to the
joint while it passes over the 785raveller.
29.08 SAGGING IN OPERATION:
29.08.1 The Conductors shall be pulled up to the desired sag and left in running block for at least one
hour after which the sag shall be rechecked and adjusted, if necessary, before transferring the
conductor from the running out blocks to the suspension clamps. The Conductors shall be clamped
within 36 hours of sagging in.
29.08.2 The sag will be checked in the first and the last span of the section in case of sections up to
eight spans and in one intermediate span also for sections with more than eight spans. The sag shall
also be rechecked when the Conductor have been drawn up and transferred from running blocks to the
insulator clamps.
CHAPTER 29: ERECTION OF TRANSMISSION TOWER
29.08.3 The running out blocks, when suspended from the transmission structure for sagging shall be
so adjusted that the Conductors on running out blocks will be at the same height as that of the
suspension clamps to which it is to be secured.
29.08.4 At sharp vertical angles, the sags and tensions shall be checked on both sides of the angle.
The Conductor and Ground-wire shall be checked on the running out blocks for equality of tension on
both sides. The suspension insulator assemblies will normally assume vertical positions when the
Conductor is clamped.
29.08.5 Tensioning and sagging operations shall be carried out in calm weather, when rapid changes
in temperature are not likely to occur.
29.09 TENSIONING & SAGGING OF CONDUCTOR AND EARTHWIRE:
The tensioning and sagging shall be done in accordance with the approved stringing charts before the
Conductor and Ground-wire is finally attached to the towers through the insulator strings for the
Conductor and Ground-wire clamps for the Ground-wire Dynamometers shall be used for measuring
tension in the Conductor and Ground-wire.
29.10 CLIPPING IN:
29.10.1 Clipping of the Conductors in position shall be done in accordance with the method approved
by our Engineer. At suspension location free center type suspension clamp with Armour rod set or
AGS type suspension clamp shall be used.
29.10.2 The jumpers at the section and angle towers shall be formed to parabolic shape to ensure
maximum clearance requirements. Pilot suspension insulator string shall be used, if necessary, to
restrict the jumper swings to the design values. Jumper connections of transposition towers shall be so
made that adequate clearances are available from tower body as well as phase conductors.
29.10.3 Fasteners in all fittings and accessories shall be secured in position. The security clip shall be
properly opened and sprung into position.
29.11 FIXING OF CONDUCTORS AND EARTHWIRE ACCESSORIES:
Spacers, spacer dampers, Vibration dampers (4-R type) and other Conductor and Ground-wire
Accessories supplied by the purchaser shall be installed by the Contractor as per the design/drawing
requirement and as per instructions of the Engineer. Spacers shall be fitted within 24 hours of the
Conductor clamping. While installing the Conductor and Ground-wire Accessories, proper care shall
be taken to ensure that the surfaces are clean and smooth and no damage shall occur to any part of the
Accessories.
29.12 REPLACEMENT:
If any replacements are to be affected after stringing and tensioning or during maintenance, members
and bracing shall not be removed without reducing the tension on the tower with proper guying or
releasing the Conductor. If the replacement of cross arms becomes necessary after stringing, the
Conductor shall be suitably tied to the tower at tension points or transferred to suitable roller pulleys
at suspension points.
29.13 FINAL CHECKING TESTING AND COMMISSIONING:
After completion of the works, final checking of the line shall be done by the Contractor to ensure that
all the foundation works, tower erection, and stringing have been done strictly in accordance with the
CHAPTER 29: ERECTION OF TRANSMISSION TOWER
specification and as approved by the purchaser. All the works shall be thoroughly inspected keeping
in view the following main points:
(a) Sufficient back-filled earth is lying over each foundation pit and it is adequately compacted.
(b) Concrete chimneys and their copings are in good finely shaped conditions.
I All the tower members are correctly used, strictly according to approved drawing and are free from
defects or damages, whatsoever.
(d) All bolts are properly tightened and punched/tack welded as per this specificatioI(e) The stringing
of the Conductors and Ground-wire has been done as per the approved sag and tension charts and
desired clearances are clearly available.
(f) All Conductor and Ground-wire Accessories are properly installed.
(g) All other requirements to complete the work like fixing of Danger Plate, Phase Plate, Number
Plate, Anti-climbing devices, Aviation Signal (wherever required) etc. are properly installed and the
painting has been done wherever required as per Aviation Rules.
(h) It should be ensured that revetment is provided, wherever required.
(i) The line insulation is tested by the Contractor by providing his own equipment labour etc. to the
satisfaction of the purchaser to ascertain the insulation condition of the line.
(j) Conductor continuity test is carried out to verify that each Conductor of the overhead line is
properly connected electrically also.
The line may be charged at a low value of Power Frequency Voltage for the purpose of testing.
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
AAAC Zebra
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
AAAC PANTHER
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
31.1.0 SCOPE
31.1.1 This Section of the Specification covers the technical parameters for
design, manufacture, testing at manufacturer’s works and supply of Conductor,
and accessories for Power Conductors.
31.2.0 POWER CONDUCTOR
31.2.1 TYPE OF CONDUCTOR
The ACSR Conductor shall generally conform to IEC: 61089/ IS: 398 (relevant
part)/ ASTM:B-232 except where otherwise specified herein.
Conductor conforming to a standard other than the Indian Standard specification
then an English version of the Standard in addition to the original standard if
written in a language other than English should be submitted indicating clearly
the advantage, if any, that would be obtained by the Employer for adopting this
standard instead of the said India Standard.
31.2.2 STANDARD TECHNICAL PARTICULARS
All ACSR Conductor shall satisfy all the parameters as furnished in Technical
Data Sheet.
All the aluminium and steel strands shall be smooth, uniform and free from all
imperfections, such as spills and splits, die marks, scratches, abrasions, etc.,
after drawing and also after stranding.
The steel strands shall be hot dip galvanised and shall have a minimum zinc
coating.
31.2.3 MATERIAL
The aluminium strands shall be hard drawn from electrolytic aluminium rods
having purity and copper content as per the values indicated in the STP. They
shall have the same properties and characteristics as prescribed in IEC: 60889.
The steel wire strands shall be drawn from high carbon steel wire rods produced
by either the acid or the basic open-hearth process, the electric furnace process,
or the basic oxygen process and shall conform to the chemical composition
indicated in the STP.
The Steel wire strands shall have the same properties and characteristics as
prescribed for regular strength steel wire in IEC : 60888.
The zinc used for galvanizing shall be electrolytic High Grade Zinc of purity. It
shall conform to and satisfy all the requirements of IS:209.
(4) per conductor length and shall not be closer than 15 meters from joint in the
same wire or in any other aluminium wire of the completed conductor.
Joints shall be made by cold pressure butt welding and shall withstand a stress
of not less than the breaking strength of individual strand as per STP.
In the Steel wires there shall be no joint of any kind in the finished wire entering
into the manufacture of the strand. There shall also be no strand joints or strand
splices in any length of the completed stranded steel core of the conductor.
31.2.5 STRANDING
The wires used in construction of a ACSR conductor shall, before and after
stranding, satisfy all requirements of IS 398 with latest amendments thereof.
The lay ratio of the different layers shall be within the limits as per the said
Standard. In all constructions, the successive layers shall have opposite
directions of lay, the outer most layer being right-handed. The wires in each
layer shall be evenly and closely stranded. In aluminium alloy stranded
conductors having multiple layers of wires, the lay ratio of any layer shall not be
greater than the lay ratio of the layer immediately beneath it.
31.2.6 TYPE/ROUTINE/ACCEPTANCE TESTS
Type Test:
The following tests shall be conducted on a sample/samples of the
conductor(s) required under the package from each stranding machine from
which the conductor is to be manufactured & supplied:
a) DC resistance test on stranded conductor
b) UTS test on stranded conductor
c) Corona extinction voltage test (dry)
d) Radio interference voltage test (dry)
Acceptance Test:
a) Visual and dimensional check on drum
b) Visual check for joints, scratches etc. and length measurement of
conductor by rewinding
c) Measurement of diameters of individual Steel and Aluminium
strands
d) Galvanizing test on steel strands
e) Check for lay Ratios of various layers
f) Torsion and Elongation tests on steel strands
g) Breaking load test on steel and Aluminium strands
h) Wrap test on Steel & Aluminium strands
i) DC resistance test on Aluminium strands
j) Procedure qualification test on welded joint of Aluminium
strands
k) Drum strength test (steel drum)
l) Barrel Batten strength test (wooden drum)
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
The above acceptance tests shall be repeated on one conductor sample taken
from site in presence of AEGCL’s representative for each 500km
progressive supply. The tests shall be carried out by the supplier at his cost at its
own premises or any other tests centre having required facilities. The sample
shall be selected by AEGCL’s site representative and the tests shall be
witnessed by AEGCL’s representative.
Routine Tests:
ACSR MOOSE
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
• Spacer shall restore normal spacing of the sub conductors after displacement
by wind, electromagnetic and the electrostatic forces under all operating
conditions including the specified short circuit level without permanent
deformation damage either to conductor or to the assembly itself. They shall
have uniform grip on the conductor
• For spacer requiring retaining rods, the retaining rods shall be designed for the
specified conductor size. The preformed rods shall be made of high strength,
special aluminium alloy of type 6061/65032 and shall have minimum tensile
strength of 35 kg/sq.mm. The ends of retaining rods should be ball ended. The
rods shall be heat- treated to achieve specified mechanical properties and give
proper resilience and retain the same during service.
• Four number of rods shall be applied on each clamp to hold the clamp in
position. The minimum diameter of the rods shall be 7.87 + 0.1 mm and the
length of the rods shall not be less than 1100 mm.
• Where elastomer surfaced clamp grooves are used, the elastomer shall be
firmly fixed to the clamp. The insert should be forged from aluminium alloy of
type 6061/65032. The insert shall be duly heat treated and aged to retain its
consistent characteristics during service.
• Any nut used shall be locked in an approved manner to prevent vibration
loosening. The ends of bolts and nuts shall be properly rounded for specified
corona performance or suitably shielded.
• Clamp with cap shall be designed to prevent its cap from slipping out of
position when being tightened.
• For the spacer involving bolted clamps, the manufacturer must indicate the
clamp bolt tightening torque to ensure that the slip strength of the clamp is
maintained between 2.5 kN and 5 kN. The clamp when installed on the
conductor shall not cause excessive stress concentration on the conductor
leading to permanent deformation of the conductor strands and premature
fatigue failure in operation.
• Universal type bolted clamps, covering a range of conductor sizes, will not be
permitted.
• The spacer shall be suitably designed to avoid distortion or damage to the
conductor or to themselves during service.
• Rigid spacers shall be acceptable only for jumpers.
• The spacer tube shall be made of aluminium alloy of type 6061/65032 or
6063/63400. If fasteners of ferrous material are used, they shall conform to
and be galvanised conforming to relevant Indian Standards. The spacer
involving ferrous fasteners shall not have magnetic power loss more than that
stipulated in the Standard Technical Particulars.
• Elastomer, if used, shall be resistant to the effects of temperature up to 95
deg.C, ultraviolet radiation and other atmospheric contaminants likely to be
encountered in service. It shall have good fatigue characteristics. The physical
properties of the elastomer shall be of approved standard.
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
• The spacer assembly shall have electrical continuity. The electrical resistance
between the sub-conductor across the assembly in case of spacer having
elastomer clamp grooves shall be suitably selected by the manufacturers to
ensure satisfactory electrical performance and to avoid deterioration of
elastomer under all service conditions.
• The spacer assembly shall have complete ease of installation and shall be
capable of removal/reinstallation without any damage.
• The spacer assembly shall be capable of being installed and removed from the
energised line by means of hot line technique.
31.5 FITTINGS AND ACCESSORIES FOR GROUND WIRES
Fittings and accessories for OPGW shall be used as per chapter 35.
interference noises. The suspension clamps shall be suitable to carry the bottom
part of the arcing horn and to receive the fittings of the insulator string.
The suspension clamps shall be such that the conductor should not slip at a load
of 25% of the breaking load of the conductor. The ultimate strength of the
clamp for vertical load shall not be less than the failing load of the Disc
Insulators.
32.2.1 STRAIN CLAMP
The bolted strain clamps shall also be made of malleable iron or aluminium
alloy; hot dip galvanised, lined with sheet aluminium liners and shall be suitable
to accommodate the conductor with necessary binding tapes etc. The lips shall
be rounded off carefully and conductor seating and the ball mouth shall be
smooth to avoid corona and radio interference noises. Suitable attachment for
receiving one side of arcing horns and for connecting to the insulator strings
shall be provided.
The strain clamps shall be such that the conductor should not slip at a load of
90% of the breaking load of the conductor. The ultimate strength of the clamp
for horizontal load shall not be less than the ultimate strength of the conductor
32.2.2 ARCING HORNS:
Arcing horns of approved size and dimensions shall be provided for every string
of insulators. The performance data for arcing horns to be supplied shall be
made available to the Employer.
32.2.3 OTHER INSULATOR STRING HARDWARE:
The strength of other string hardware namely anchor shackle, yoke plates,
socket-clevis etc. shall be co-ordinated with insulator disc strength.
32.3.0 Interchangeability
The hardware together with ball and socket fittings shall be of standard design,
so that this hardware is interchangeable with each other and suitable for use
with disc insulators of any make con1orming to relevant Indian/International
Standard.
32.4.0 Corona and RI Performance
Sharp edges and scratches on all the hardware fittings shall be avoided. All
surfaces must be clean, smooth, without cuts and abrasions or projections. The
Contractor/Manufacturer must give suitable assurance about the satisfactory
corona and radio interference performance of the materials offered by him.
32.5.0 Maintenance
The hardware fittings offered shall be suitable for employment of hot line
maintenance technique so that usual hot line operations can be carried out with
ease, speed and safety. The technique adopted for hot line maintenance shall be
generally bare hand method & hot stick method. The Bidder should clearly
establish in the bid, the suitability of his fittings for hot line maintenance.
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
The line side yoke plate shall have a notch & a working hole of suitable size.
The design of corona control rings/grading ring shall be such that it can be
easily replaced by employing hot line maintenance technique.
32.6.0 Designation
Ball and Socket Designation
The dimensions of the ball and socket shall be 16 mm (Alt-B) designation for 70
KN &90KN Insulators, 20 mm designation for hardware with 120kN & 160 kN
Insulators, in accordance with the standard dimensions stated in IS: 2486-(Part-
II) /IEC:120. The dimensions shall be checked by the appropriate gauge after
galvanising only.
32.7.0 Security Clips and Split Pins
32.7.1.1Security clips for use with ball and socket coupling shall be R-shaped,
hump type which provides positive locking 9f the coupling as per IS: 2486-
(Part-III)/IEC: 372. The legs of the security clips shall be spread after assembly
in the works to prevent complete withdrawal from the socket. The locking
device should be resilient, corrosion resistant and of suitable mechanical
strength. There shall be no risk of the locking device being displaced
accidentally or being rotated when in position. Under no circumstances shall the
locking devices allow separation of fittings.
32.7.1.2The hole for the security clip shall be countersunk and the clip should
be of such design that the eye of clip may be engaged by a hot line clip puller to
provide for disengagement under energised conditions. The force required to
pull the security clip into its unlocked position shall neither be less than 50 N (5
kg) nor more than 500 N (50 kg).
Split pins shall be used with bolts & nuts.
32.8.0 Arcing Horn for EHV Strings
32.8.1.1The arcing horn shall be provided on tower side of the hardware fittings.
The same shall be either ball ended rod type or tubular type.
32.8.1.2The spark gap shall be so adjusted to ensure effective operation under
actual field conditions.
32.12.0 Turnbuckle
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
32.12.1.1 The turn buckle is to be provided with single tension hardware fitting.
The threads shall be of sufficient strength to remain unaffected under the
specified tensile load.
32.12.1.2 The maximum length of the turn buckle from the connecting part of
the rest of the hardware fittings shall be 380 mm for 132KV and 220KV Line
and 520mm for 400KV Line. The details of the minimum and maximum
adjustment possible shall be clearly indicated in the drawing submitted with the
bid. An adjustment of 135 mm minimum for 132KV and 220KV Line and
150mm minimum for 400KV Line shall be possible with turnbuckle.
32.13.0 Suspension Assembly
32.13.1 The suspension assembly shall include free center type suspension
clamp along with standard preformed armour rods or armour grip suspension
clamp; except for Pilot insulator string for which only suitable Envelope type
suspension clamp shall be used.
32.13.2 The suspension clamp along with standard preformed armour rods set
shall be designed to have maximum mobility in any direction and minimum
moment of inertia so as to have minimum stress on the conductor in the case of
oscillation of the same.
32.13.2.1 The suspension assembly shall be designed, manufactured and
finished to give it a suitable shape, so as to avoid any possibility of hammering
between suspension assembly and conductor due to vibration. The suspension
assembly shall be smooth and without any cuts, grooves, abrasions, projections,
ridges or excrescence which might damage the conductor.
32.13.2.2 The suspension assembly/clamp shall be so designed so that it
minimises the static and dynamic stress developed in the conductor under
various loading conditions as well as during wind induced conductor vibrations.
It shall also withstand power arcs and have required level of Corona/AIV
performance.
32.14.0 Free Center Type Suspension Clamp
For the Free Center Suspension Clamp seat shall be smoothly rounded and
curved into a bell mouth at the ends. The lip edges shall have rounded bead.
There shall be at least two U-bolts for tightening of clamp body and keeper
pieces together.
32.15.0 Standard Preformed Armour Rod Set
32.15.1.1The Preformed Armour Rod Set suitable for Conductor shall be used
to minimise the stress developed in the sub-conductor due to different static and
dynamic loads because of vibration due to wind, slipping of conductor from the
suspension clamp as a result of unbalanced conductor tension in adjacent spans
and broken wire condition. It shall also withstand power arcs, chafing and
abrasion from suspension clamp and localised heating effect due to magnetic
power losses from suspension clamps as well as resistance losses of the
conductor.
32.15.1.2 The preformed armour rods set shall have right hand lay and the
inside diameter of the helices shall be less than the outside diameter of the
conductor in order to gently but permanently grip the conductor. The surface of
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
the armour rod when fitted on the conductor shall be smooth and free from
projections, cuts and abrasions, etc.
32.15.1.3 The pitch length of the rods shall be determined by the Bidder but
shall be less than that of the outer layer of conductor and the same shall be
accurately controlled to maintain uniformity and consistently reproducible
characteristic wholly independent of the skill of linemen.
32.15.1.4 The conductivity of each rod of the set shall not be less than
40% of the conductivity of the International Annealed Copper Standard (lACS).
32.16.0 Armour Grip Suspension Clamp
• The armour grip suspension clamp shall comprise of retaining strap, support
housing, elastomer inserts with aluminum reinforcements and AGS preformed
rod set.
• Elastomer insert shall be resistant to the effects of temperature up to 95oC,
Ozone, ultraviolet radiations and other atmospheric contaminants likely to be
encountered in service. The physical properties of the elastomer shall be of
approved standard. It shall be electrically shielded by a cage of AGS performed
rod set. The elastomer insert shall be so designed that the curvature of the AGS
rod shall follow the contour of the neoprene insert.
• The length of the AGS preformed rods shall be such that it shall ensure
sufficient slipping strength as specified in the Standard Technical Particulars
and shall not introduce unfavourable stress on the conductor under all operating
conditions.
32.17.0 Envelope Type Suspension Clamp
• The seat of the envelope type suspension clamp shall be smoothly rounded &
suitably curved at the ends. The lip edges shall have rounded bead. There shall
be at least two U-bolts for tightening of clamp body and keeper pieces together.
Hexagonal bolts and nuts with split-pins shall be used for attachment of the
clamp.
32.18.0 Dead End Assembly
32.18.1.1 The dead-end assembly shall be suitable for Conductor as detailed in
the document.
32.18.1.2 The dead-end assembly shall be compression type with provision for
comprising the jumper terminal at one end. The angle of the jumper terminal to
be mounted should be 30⁰ with respect to the vertical line. The area of bearing
surface on all the connections shall be sufficient to ensure positive electrical and
mechanical contact and avoid local heating due to I2R losses. The resistance of
the clamp when compressed on Conductor shall not be more than 75% of the
resistance of equivalent length of Conductor.
32.18.1.3 The assembly shall not permit slipping of, damage to, or failure of the
complete conductor or any part thereof at a load less than 95% of the ultimate
tensile strength of the conductor.
32.19.0 Fasteners: Bolts, Nuts and 'Washers
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
32.19.1.1 All bolts and nuts shall conform to IS: 6639. All bolts and nuts shall
be galvanised as per IS-1367 -(Part 13)/IS-2629. All bolts and nuts shall have
hexagonal heads, the heads being forged out of solid truly concentric, and
square with the shank, which must be perfectly straight.
32.19.1.2 Bolts up to M16 and having length up to 10 times the diameter of the
bolt should be manufactured by cold forging and thread rolling process to obtain
good and reliable mechanical properties arid effective dimensional control. The
shear strength of bolt for 5.6 grade should be 310 MPa minimum as per IS-
12427. Bolts should be provided with washer face in accordance with IS: 1363
Part-1 to ensure proper bearing.
32.19.1.3 Nuts should be double chamfered as per the requirement of IS: 1363
Part-III. It should be ensured by the manufacturer that nuts should not be over
tapped beyond 0.4 mm oversize on effective diameter for size up to M16
32.19.1.4 Fully threaded bolts shall not be used. The length of the bolt shall be
such that the threaded portion shall not extend into the place of contact of the
component parts.
32.19.1.5 All bolts shall be threaded to take the full depth of the nuts and
threaded enough to permit the firm gripping of the component parts but no
further .it shall be ensured that the threaded portion of the bolt protrudes not less
than 3 mm and not more than 8 mm when fully tightened. All nuts shall fit and
tight to the point where shank of the bolt connects to the head.
32.19.1.6 For parts/ components requiring grip strength viz. arcing horn, corona
rings & dead-end jumper assembly, fully threaded bolts can be used as an
alternative. Bolts & nuts for these parts/ components shall be of minimum 4.6
grade conforming to IS 6639 or equivalent International standards.
32.19.1.7 Flat washers and spring washers shall be provided wherever necessary
and shall be of positive lock type. Spring washers shall be electro-galvanised.
The thickness of washers shall conform to IS: 2016.
32.19.1.8 The Bidder shall furnish bolt schedules giving thickness of
components connected, the nut and the washer and the length of shank and the
threaded portion of bolts and size of holes and any other special details of this
nature.
32.19.1.9 To obviate bending stress in bolt, it shall not connect aggregate
thickness more than three time its diameter.
32.19.1.10 Bolts at the joints shall be so staggered that nuts may be tightened
with spanners without fouling.
32.19.1.11 Fasteners of grade higher than 8.8 are not to be used.
32.20.0 Materials
The materials of the various components shall be as specified hereunder. The
Bidders hall indicate the material proposed to be used for each and every
component of hardware fitting stating clearly the class, grade or alloy
designation of the material, manufacturing process & heat treatment details
and the reference standards.
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
Sl.
Name of item Material treatment Process of Standard Reference Remarks
No.
Stainless Steel/
1 - AISI 302 or
Security Clips Phospher Bronze
304-L/ IS-1385
Yoke Plate
4 Mild Steel Hot dip galvanized As per IS-226
or IS-2062
Sag Adjustment
5 plate Mild Steel Hot dip galvanized As per IS-226
or IS-2062
Mechanical
High Strength Al. strength of
Corona Control Alloy tube (6061/ Heat treated Hot dip ASTM-B429 or welded joint
6(a).
ring/ Grading ring 6063/1100 type or galvanized as per IS shall not be
65032/ 63400 Type) less than 20
KN
High Strength Al
Supporting ASTM-B429 or
Alloy 7061/ 6063/ Heat treated Hot dip
6(b). Brackets & as per IS:226 or
65032/63400 Type) galvanized
Mounting Bolts IS:2062
or Mild Steel
Envelope type
Clamp:
7(b). Mild Steel Hot dip galvanised As per IS-226
Cotter bolts/
or IS-2062
Hangers, Shackles,
Brackets
EC grade Al of
Dead End purity not less than
8(a)
Assembly: Outer 99.50%
. Sleeve
High strength
AGS clamp corrosion resistant
9. (a) IS:617 or
Al. alloy LM6, 4600 Cast/forged heat treated.
Supporting equivalent
or equivalent 6061
house
High strength Al
(b) Al insert and Forged and Heat treated ASTM:B42
alloy type 6061 or
retaining strap equivalent 9
32.21.0 Workmanship
32.21.1.1 All the equipment shall be of the latest design and conform to the best
modern practices adopted in the Extra High Voltage field. The Bidder shall
offer only such equipment as guaranteed by him to be satisfactory and suitable
for rated voltage of transmission lines and will give continued good
performance.
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
32.21.1.2 The design, manufacturing process and quality control of all the
materials shall be such as to give the specified mechanical rating, highest
mobility, elimination of sharp edges and comers to limit corona and radio-
interference, best resistance to corrosion and a good finish.
32.21.1.3 All ferrous parts including fasteners shall be hot dip galvanized, after
all machining has been completed. Nuts may, however, be tapped (threaded)
after galvanizing and the threads oiled. Spring washers shall be electro
galvanized. The bolt threads shall be undercut to take care of the increase in
diameter due to galvanizing. Galvanizing shall he done in accordance with IS:
2629 / IS-1367 (Part 13)or equivalent International Standards and shall satisfy
the tests mentioned in IS: 2633-1986or equivalent International Standards.
Fasteners shall withstand four dips while spring washers shall withstand three
dips of one-minute duration in the standard Preece test. Other galvanized
materials shall have a minimum average coating of zinc equivalent to 610 gm /
sq.m shall be guaranteed to withstand at least six successive dips each lasting
one (1) minute under the standard price test for galvanizing.
32.21.1.4 Before ball fittings are galvanized, all die flashing on the shank and
on the bearing surface of the ball shall be carefully removed without reducing
the dimensions below the design requirements.
32.21.1.5 The zinc coating shall be perfectly adherent of uniform thickness,
smooth, reasonably bright. Continuous and free from imperfections such as flux,
ash, rust, stains, bulky white deposits and blisters. The zinc used for galvanizing
shall be grade Zn 99.95 as per IS: 209or equivalent International Standards.
32.21.1.6 Pin balls shall be checked with the applicable “GO” gauges in at least
two directions. one of which shall be across the line of die flashing, and the
other 90o to this line. "NO GO" gauges shall not pass in any direction.
32.21.1.7 Socket ends, before galvanizing, shall be of uniform contour. The
bearing surface of socket ends shall be uniform about the entire circumference
without depressions, of high spots. The internal contours of socket ends shall be
concentric with the axis of the fittings as per IS: 2486or equivalent International
Standards.
The axis of the bearing surfaces of socket ends shall be coaxial with the axis of
the fittings. There shall be no noticeable tilting of the bearing surfaces with the
axis of the fittings.
32.21.1.8 In case of casting, the same shall be free from all internal defects like
shrinkage, inclusion, blow holes, etc. Pressure die casting shall not be used for
casting of components with thickness more than 5 mm
32.21.1.9 All current carrying parts shall be so designed and manufactured that
contact resistance is reduced to minimum.
32.21.1.10 No equipment shall have sharp ends or edges, abrasions or
projections and cause any damage to the inductor in any way during erection or
during continuous operation which would product high electrical and
mechanical stresses in normal working. The design of adjacent metal parts and
mating surfaces shall be such as to prevent corrosion of the contact surface and
to maintain good electrical contact under service conditions.
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
32.21.1.11 All the holes shall be cylindrical, clean cut and perpendicular to the
plane of the material. The periphery of the holes shall be free from burrs.
32.21.1.12 All fasteners shall have suitable corona free locking arrangement to
guard against Vibration loosening.
32.21.1.13 Welding of aluminium shall be by inert gas shielded tungsten arc or
inert gas shielded metal arc process. Welds shall be clean, sound, smooth,
uniform without overlaps, properly fused and completely sealed. There shall be
no cracks, voids incomplete penetration, incomplete fusion, under-cutting or
inclusions. Porosity shall be minimised so that mechanical properties of the
aluminium alloys are not affected. All welds shall be properly finished as per
good engineering practices.
32.22.0 Bid Drawings
32.22.1.1 The Bidder shall furnish full description and illustrations of materials
offered.
32.22.1.2 Fully dimensioned drawings of the complete insulator string hardware
and their component parts showing clearly the following arrangements shall be
furnished in five (5) copies along with the bid. Weight, material and fabrication
details of all the components should be included in the drawings.
(i) Attachment of the hanger or strain plate.
(ii) Yoke Plate
(iii) Suspension or dead-end assembly.
(iv) Arcing horn attachment to the string
(v) Hardware fittings of ball and socket type for inter connecting units.
(iv) Corona control rings/grading ring attachment to conductor and other
small accessories.
32.22.1.3 All drawings shall be identified by a drawing number and contract
number. All drawings shall be neatly arranged. All drafting & lettering shall be
legible. The minimum size of lettering shall be 3 mm. All dimensions &
dimensional tolerances shall be mentioned in mm.
The drawings shall include:
(i) Dimensions and dimensional tolerance.
(ii) Material, fabrication details including any weld details & any specified
finishes & coatings. Regarding material designation & reference of standards
are to be indicated.
(iii) Catalogue No.
(iv) Marking
(v) Weight of assembly
(vi) Installation instructions
(vii) Design installation torque for the bolt or cap screw.
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
(viii) Withstand torque that may be applied to the bolt or cap screw without
failure of component parts.
(ix) The compression die number with recommended compression pressure.
(x) All other relevant terminal details.
32.22.1.4 After placement of award, the Contractor shall submit fully
dimensioned drawings including all the components in four (4) copies to the
Employer for approval. After getting approval from the Employer and
successful completion of all the type tests, the Contractor shall submit thirty
(10) more copies of the same drawings to the Employer for further distribution
and field use at Employer’s end.
32.23.0 Completeness of works
Bidder shall assess the complete requirement of line hardware, hardware
accessories and assemblies in complete for the erection of the lines as per the
recommended erection practices.
The hardware assemblies shall be supplied complete with components, sub-
components, nuts, bolts, washer etc. fittings and accessories for conductor &
earth wire like Mid Span Joints, Repair Sleeves, and Stockbridge Vibration
Dampers.
The Contractor shall also supply all line and tower accessories.
32.24.0 Standards
32.24.1.1 The Hardware Fittings, conductor and earth wire accessories shall
conform to the following Indian Standards or equivalent International
Standards, which shall mean latest revisions, amendments/changes adopted and
published unless specifically stated otherwise in the specification.
1. IS: 209 Specification for Zinc.
2. IS: 398 Specification for Aluminum Conductors.
for Overhead Transmission Purposes,
3. IS: 1327 Method of Determination of Weight of
Zinc Coating on Tin Plate.
4. IS: 1573 Electroplated Coating of Zinc on Iron and Steel
5. IS: 2121 Specification for Conductors and Earthwire
Accessories for Overhead Power Lines
(Part-1 ) Armour Rods, Binding Wires and Tapes for
Conductors
(Part-2) Mid-span joints and Repair Sleeves for
Conductors
6. IS : 2486 Specification for Insulator Fittings for Overhead Power
Lines
CHAPTER 30: TECHNICAL SPECIFICATION FOR AAAC CONDUCTORS AND ACCESSORIES
insulators or add other stresses to the shells. The insulator caps shall be of the socket type provided
with nonferrous metal or stainless-steel cotter pins and shall provide positive locking of the coupling.
33.4.2.2 Security Clips:
The security clips shall be made of phosphor bronze or of stainless steel.
33.4.3 FILLER MATERIAL:
Cement to be used, as a filler material be quick setting, fast curing Portland cement. It shall not cause
fracture by expansion or loosening by contraction. Cement shall not react chemically with metal parts
in contact with it and its thickness shall be as small and as uniform as possible.
33.4.4 MATERIALS DESIGN AND WORKMANSHIP:
33.4.4.1 GENERAL:
(I) All raw materials to be used in the manufacture of these insulators shall be subject to strict raw
material quality control and to stage testing/ quality control during manufacturing stage to ensure the
quality of the final end product. Manufacturing shall conform to the best engineering practices
adopted in the field of extra high voltage transmission. Bidders shall therefore offer insulators as are
guaranteed by them for satisfactory performance on Transmission lines.
(II) The design, manufacturing process and material control at various stages be such as to give
maximum working load, highest mobility, best resistance to corrosion, good finish elimination of
sharp edges and corners to limit corona and radio interference voltages.
33.4.4.2 INSULATOR SHELL:
The design of the insulator shells shall be such that stresses due to expansion and contraction in any
part of the insulator shall not lead to deterioration. Shells with cracks shall be eliminated by
temperature cycle test followed by mallet test. Shells shall be dried under controlled conditions of
humidity and temperature.
33.4.4.3 METAL PARTS:
i) The pin and cap shall be designed to transmit the mechanical stress to the shell by compression and
develop uniform mechanical strength in the insulator. The cap shall be circular with the inner and
outer surfaces concentric and of such design that it will not yield or distort under loaded conditions.
The head portion of the pinball shall be suitably designed so that when the insulator is under tension
the stresses are uniformly distributed over the pinhole portion of the shell. The pinball shall move
freely in the cap socket either during assembly of a string or during erection of a string or when a
string is placed in position.
ii) Metal caps shall be free from cracks, seams, shrinks, air holes, blowholes and rough edges. All
metal surfaces shall be perfectly smooth with no projecting part or irregularities, which may cause
corona. All load bearing surfaces shall be smooth and uniform so as to distribute the loading stress
uniformly. Pins shall not show any microscopically visible cracks, inclusions and voids.
33.4.4.4 GALVANIZING:
All ferrous parts, shall be hot dip galvanized in accordance with IS: 2629. The zinc to be used for
galvanizing shall conform to grade Zn 99.95 as per IS: 209. The zinc coating shall be uniform,
smoothly adherent, reasonably light, continuous and free from impurities such as flux, ash, rust stains,
bulky white deposits and blisters. Before ball fittings are galvanized, all die flashing on the shank and
CHAPTER 33: TECHNICAL SPECIFICATION DISC INSULATOR
on the bearing surface of the ball shall be carefully removed without reducing the designed
dimensional requirements.
33.4.4.5 CEMENTING:
The insulator design shall. Be such that the insulating medium shall not directly engaged with hard
metal. The surface of porcelain and coated with resilient paint to offset the effect of difference in
thermal expansions of these materials. High quality Portland cement shall be used for cementing the
porcelain to the cap & pin.
33.4.4.6 SECURITY CLIPS (LOCKING DEVICES)
The security clips to be used as locking device for ball and socket coupling shall be „R‟ shaped hump
type to provide for positive locking of the coupling as per IS: 2486 (Part-IV). The legs of the security
clips shall allow for spreading after installation to prevent complete withdrawal from the socket. The
locking device shall resilient corrosion resistant and of sufficient mechanical strength. There shall be
no possibility of the locking device to be displaced or be capable of rotation, which placed in position,
and under no circumstances shall it allow separation of insulator units and fittings. „W‟ type security
clips are also acceptable. The hole for the security clip shall be counter sunk and the clip shall be of
such design that the eye of the clip may be engaged by a hot line clip puller to provide for
disengagement under energized conditions. The force required for pulling the clip into its unlocked
positions shall not be less than 50 N (5 kg.) or more than 500 N (50 kgs.).
33.4.4.7 MARKING:
Each insulator shall have the rated combined mechanical and electrical strength marked clearly on the
porcelain surface. Each insulator shall also bear symbols identifying the manufacturer, month, and
year of manufacture. Marking on porcelain shall be printed, not impressed, and shall be applied before
firing
33.4.5 BALL AND SOCKET DESIGNATION:
The dimensions of the ball and sockets for 70 and 90 KN insulator strings shall be of 16 mm and for
120 KN and 160 KN insulator strings shall be of 20 mm designation in accordance with the standard
dimensions stated in IS: 2486 (Part-II).
33.4.6-DIMENSIONAL TOLERANCE OF INSULATOR DISCS:
It shall be ensured that the dimensions of the disc insulators are within the limits specified below:
(b)
4 Dimensions
7 Electrical value
33.4.8 INTERCHANGEABILITY:
The insulators inclusive of the ball and socket fittings shall be of standard design suitable for use with
hardware fittings of any make conforming to relevant Indian Standards.
33.4.9 CORONA AND RIV PERFORMANCE:
All surfaces shall be even, smooth, without cuts, abrasions or projections. No part shall be subject to
excessive localized pressure. The metal parts and porcelain shall not produce any noise-generating
corona under all operating conditions
33.5.0 SUITABILITY FOR LIVE LINE MAINTENANCE:
The insulator shall be compatible for use with hot line or live line maintenance techniques so that
usual hot line operation can be carried out with easy speed and safety.
33.5.1 FREEDOM FROM DEFECTS:
Insulators shall have none of the following defects:
1) Ball pin shake.
2) Cementing defects near the pin like small blow holes, small hair cracks lumps etc.
3) Sand fall defects on the surface of the insulator.
33.5.2 INSULATOR STRINGS:
33.5.2.1 TYPE AND RATING:
The insulator strings shall be formed with standard discs described in this specification for use on 3
phases 132/220 KV 50 Hz effectively earthed systems in an atmosphere with pollution level as
indicated in project synopsis. Suspension insulator strings for use with suspension/tangent towers are
to be fitted with discs 70/90 KN EMS rating while tension insulator strings for use with Anchor/
Tension towers are to be fitted with discs of 120 KN / 160 KN EMS level rating.
33.5.2.2 STRING SIZE:
CHAPTER 33: TECHNICAL SPECIFICATION DISC INSULATOR
The sizes of the disc insulator, the number to be used in different types of strings, their electro-
mechanical strength and minimum nominal creep age distance shall be as given in clause 3.12.
33.5.3 STRING CHARACTERISTICS
33.5.3.1 The characteristics of the complete string shall be as follows:
Ii Lighting impulse withstand voltage (dry) KV Peak. 650 1050 650 1050
Iii Power frequency without voltage (wet) KV r.m.s. 275 460 275 460
Iv. Corona extinction voltage level KV rms - 176 - 176
v. Max. RIV for comp. Etc. strong including corona rings - 500 - 500
at 156 KV (rms). … hours clamps etc. at 1.1. times
maximum knee to ground voltage (micro volts).
vi. Mechanical failing load for each string (kgf) 6500 11500 11500 15500
Vii. No deformation load for each string (kgf) - 7705 - 10385
Viii. Max. voltage across any disc. 13% 13% 13% 13%
33.5.3.2 Insulator units after assembly shall be concentric and coaxial within limits as permitted by
Indian Standards.
33.5.3.3 The strings design shall be such that when units are coupled together there shall be contact
between the shell of one unit and metal of the adjacent unit.
CHAPTER 33: TECHNICAL SPECIFICATION DISC INSULATOR
Tension
14. 220 Double 2175 4380 2X2 2 X 120kN
Tension
15. 220 Single 2030 5180 1X2 1 X 90kN
Suspension
16. 220 Double 2030 5180 2X2 1 X 90kN
suspension
17. 220 Single 2175 5550 1X2 1 X 120kN
Tension
18. 220 Double 2175 5550 2X2 2 X 120kN
Tension
19. 220 Single 2550 5550 1X2 1 X 160kN
Tension
20. 220 Double 2550 5550 2X2 2 X 160kN
Tension
21. 400 Single 3335 9200 1X3 1 X 120kN
Suspension
22. 400 Double 3335 9200 2X3 2 X 120kN
suspension
23. 400 Single 3910 9200 1X3 1 X 160kN
Tension
24. 400 Double 3910 9200 2X3 2 X 160kN
Tension
7. Galvanizing
0
a) Minimum mass of zinc coating Gm/
sq.m. 600 600 600
70 KN 90 KN 120 KN 160 KN
Insulat Insulator Insulator Insulator
or
1.0 General
7. Galvanizing
0
Rod
a) Max. axial/radial run ----- ----- 1.2 % of 1.2 % of
out insulator insulator
length length
b) Max. angular deg ----- ----- 15 15
displacement
7.0 Galvanizing
a) Minimum mass of Gm/ ----- ----- 600 600
zinc coating
b) Minimum no. of one Nos. ----- ----- 6 dips 6 dips
minute dips in
c) Minimum purity of % ----- ----- 99.95 99.95
zinc used for
with minimum of 6 dips. The bidder shall specify the grade, composition and
mechanical properties of steel used for caps and pins.
34.3.3.2 SECURITY CLIPS:
The security clips shall be made of phosphor bronze or of stainless steel.
34.3.4 FILLER MATERIAL:
Cement to be used as a filler material shall be quick setting, for curing Portland
cement. It shall not cause fracture by expansion or loosening by contraction.
Cement shall not react chemically with metal parts in contract with it and its
thickness shall be as small and as uniform as possible.
34.4.0 MATERIAL DESIGN AND WORKMANSHIP:
34.4.1 GENERAL:
i) All raw materials to be used in the manufacture of these insulators shall be
subject to strict raw materials quality control and to stage testing quality control
during manufacturing stage to ensure the quality of the final end product.
Manufacturing shall conform to the best engineering practices adopted in the
field of extra high voltage transmission. Bidders shall therefore offer insulators
as are guaranteed by them for satisfactory performance on Transmission lines.
ii) The design, manufacturing process and material control at various stages be
such as to give maximum working load, highest mobility, best resistance to
corrosion good finish, elimination of sharp edges and corners to limit corona
and radio interference voltage.
34.4.2 INSULATOR SHELL:
The design of the insulator shell shall be such that stresses due to expansion and
contraction in any part of the insulator shall not lead to deterioration. Shells with
cracks shall be eliminated by temperature cycle test followed by temperature
cycle test followed by mallet test. Shells shall be dried under controlled
conditions of humidity.
34.4.3 METAL PARTS:
i) The twin ball pin and cap shall be designed to transmit the mechanical
stresses to the shell by compression and develop uniform mechanical strength in
the insulator. The cap shall be circular with the inner and outer surfaces
concentric and of such design that it will not yield or distort under loaded
conditions. The head portion of the insulator or is under tension the stresses are
uniformly distributed over the pinhole portion of the shell. The pinball shall
move freely in the cap socket either during assembly of a string or during
erection of a string or when a string is placed in position.
ii) Metal caps shall be free from cracks, seams, shrinks, air holes, blowholes and
rough edges. All metal surfaces shall be perfectly smooth with no projecting
parts or irregularities which may cause corona. All load bearing surfaces shall
be smooth and uniform so as to distribute the loading stresses uniformly. Pins
shall not show any macroscopically visible cracks, insulations and voids.
34.4.4 GALVANIZING:
CHAPTER 33: TECHNICAL SPECIFICATION DISC INSULATOR
All ferrous parts shall be hot dip galvanized six times in accordance with IS:
2629. The zinc to be used for galvanizing shall conform to grade Zn 99.5 as per
IS: 209. The zinc coating shall be uniform, smoothly adherent, reasonably light,
continuous and free from impurities such as flux ash, rust stains, bulky white
deposits and blisters. Before ball fittings are galvanized, all die flashing on the
shank and on the bearing surface of the ball shall be carefully removed without
reducing the designed dimensional requirements.
34.4.4.1 CEMENTING:
The insulator design shall be such that the insulating medium shall not directly
engage with hard metal. The surfaces of porcelain and coated with resilient paint
to offset the effect of difference in thermal expansions of these materials.
34.4.5 SECURITY CLIPS (LOCKING DEVICES)
The security clips to be used as locking device for ball and socket coupling shall
be „R‟ shaped hump type to provide for positive locking of the coupling as per
IS: 2486 (Part-IV). The legs of the security clips shall allow for sore adding
after installation to prevent complete withdrawal from the socket. The locking
device shall be resilient corrosion resistant and of sufficient mechanical
strength. There shall be no possibility of the locking device to be displaced or be
capable of rotation when placed in position and under no circumstances shall it
allow separation of insulator units and fitting „W‟ type security clips are also
acceptable. The hole for the security clip shall be countersunk and the clip shall
be of such design that the eye of the clip may be engaged by a hot line clip
puller to provide for disengagement under energized conditions. The force
required for pulling the clip into its unlocked position shall not be less than 50 N
(5 Kgs.) or more than 500N (50 Kgs.)
34.4.6 BALL AND SOCKET DESIGNATION:
The dimensions of the balls and sockets for 80 KN long rod insulators shall be
of 16mm and for 120 KN shall be of 20mm designation in accordance with the
standard dimensions stated in IS: 2486 (Part-III).
34.4.7-DIMENSIONAL TOLERANCE OF PORCELAIN LONG ROD
INSULATORS
It shall be ensured that the dimensions of the long rod insulators are within the
limits as per relevant IEC/ ISS.
34.5.0 TESTS (FOR DISC/ LONG ROD PORCELAIN INSULATORS):
34.5.1 The following tests shall be carried out on the insulator string and disc
insulators.
34.5.2 TYPE TEST:
This shall mean those tests, which are to be carried out to prove the design,
process of manufacture and general conformity of the material and product with
the intents of this specification. These tests shall be conducted on a
representative number of samples prior to commencement of commercial
production. The Bidder shall indicate his schedule for carrying out these tests.
34.5.3 ACCEPTANCE:
CHAPTER 33: TECHNICAL SPECIFICATION DISC INSULATOR
This shall mean these tests, which are to be carried out on samples taken from
each lot offered for pre-despatch inspection for the purpose of acceptance of the
lot.
34.5.4 ROUTINE TESTS:
This shall mean those tests, which are to be carried out on each insulator to
check the requirements, which are likely to vary during production.
34.5.5 TESTS DURING MANUFACTURE:
Stage tests during manufacture shall mean those tests, which are to be carried
out during the process of manufacture to ensure quality control such that the end
product is of the designed quality conforming to the intent of this specification.
34.5.6 TEST VALUE:
For all type and acceptance tests the acceptance values shall be the value
guaranteed by the bidder in the guaranteed technical particulars of the
acceptance value specified in this specification of the relevant standard
whichever is more stringent for that particular test.
34.5.7 TEST PROCEDURE AND SAMPLING NORMS:
The norms and procedure of sampling for the above tests shall be as per the
relevant Indian Standard or the internationally accepted standards. This will be
discussed and mutually agreed to between the supplier and purchaser before
placement of order. The standards and normal according to which these tests are
to be carried out are listed against each test.
34.5.8 TYPE TESTS:
The following type test shall be conducted on a suitable number of individual
unit components, materials or complete strings.
34.5.8.1 On the complete insulator string with hardware fittings.
a) Power frequency voltage withstand test with : IEC: 60383
corona control rings and under wet condition.
b) Switching surge voltage withstand test under : IEC: 60383
wet condition (For 400kV and above only)
c) Impulse voltage withstand test under dry condition. : IEC: 60383
d) Impulse voltage flashover test under dry : IEC: 60383
condition.
e) Voltage distribution test. : Applicable only for
Disc insulators only
f) Corona & RIV test under dry condition. : As per this
specification
g) Mechanical strength test. : As per this
specification
CHAPTER 33: TECHNICAL SPECIFICATION DISC INSULATOR
34.5.8.2 On Insulators:
a) Verification of dimensions. : IS: 731/ IEC: 60383
b) Thermal mechanical performance test: : IEC:60575
c) Power frequency voltage withstand and : IEC: 60383
flashover
(I) dry (ii) wet.
d) Impulse voltage withstand flashover test (dry) : IEC: 60383
e) Visible discharge test (dry) : IS:731
f) RIV test (dry) : IS:8263/ IEC: 60437
prices shall be taken into consideration for bid evaluation. For any change in the
design/type already type tested and the design/type offered against this
specification, purchaser reserves the right to demand repetition of tests without
any extra cost.
34.5.14.2 ACCEPTANCE AND ROUTINE TEST:
All acceptance and routine tests as stipulated herein shall be carried out by the
supplier in the presence of purchaser’s representative.
34.5.14.3 Immediately after finalisation of the programme of type/ acceptance/
routine testing, the supplier shall give sufficient advance intimation to the
purchaser to enable him to depute his representative for witnessing the tests.
For type tests involving tests on a complete insulator string with hardware
fittings, the purchaser will advice the supplier of the hardware fittings to provide
the necessary fittings to the place of the test.
34.5.14.4 In case of failure of the complete string in any type tests, the supplier
whose product has failed in the tests, shall get the tests repeated at his cost. In
case of any dispute, assessment of the purchaser as to the items that has caused
the failure in any of the type tests shall be final and binding.
34.6.1 INSPECTION:
i. Purchaser and its representative shall at all times be entitled to have access to
the works and to all places of manufacturer where insulators are manufactured
and the supplier shall afford all facilities to them for unrestricted inspection of
the works, inspection of materials, inspection of manufacturing process of
insulators and for conducting necessary tests as specified herein.
ii. The supplier shall keep the purchaser informed in advance of the time of
starting and of progress of manufacture of insulators in its various stages so that
arrangements could be made for inspection.
iii. No material shall be dispatched from its point of manufacture unless the
materials has been satisfactorily inspected and tested.
iv. The acceptance of any quantity of insulators shall in no way relieve the
supplier of his responsibility for meeting all the requirement of this specification
and shall not prevent subsequent rejection, if such insulators are later found to
be defective.
34.6.2 IDENTIFICATION / MARKING:
34.6.2.1 Each unit of insulator shall be legibly and indelibly marked with the
trade mark of the supplier, the year of manufacture, the guaranteed combined
mechanical and electrical strength in kilo-newtons abbreviated by „KN‟ to
facilitate easy identification and proper use.
34.6.2.2 The marking shall be on porcelain for porcelain insulators. The
marking shall be printed and not impressed and the same shall be applied before
firing.
34.7. QUALITY ASSURANCE PLAN:
CHAPTER 33: TECHNICAL SPECIFICATION DISC INSULATOR
spare fibres shall be tested by the cable manufacturer and any defective fibres shall be suitably
bundled, tagged and identified at the factory by the vendor.
35.1.3.10 Buffer Tube
Loose tube construction shall be implemented. The individually coated optical fibre(s) shall be
surrounded by a buffer for protection from physical damage during fabrication, installation and
operation of the cable. The fibre coating and buffer shall be strippable for splicing and termination.
Each fibre unit shall be individually identifiable utilizing colour coding. Buffer tubes shall be filled
with a water-blocking gel.
35.1.3.11 Optical Fibre Strain & Sag-Tension chart
The OPGW cable shall be designed and installed such that the optical fibres experience no strain
under all loading conditions defined in IS 802. Zero fibre strain condition shall apply even after a 25-
year cable creep.
For the purpose of this specification, the following definitions shall apply:
• Maximum Working Tension (MWT) is defined as the maximum cable tension at which there
is no fibre strain.
• The no fibre strain condition is defined as fibre strain of less than or equal to 0.05%, as
determied by direct measurements through IEC/ ETSI (FOTP) specified optical reflectometry
• The Cable strain margin is defined as the maximum cable strain at which there is no fibre
strain.
• The cable Maximum Allowable Tension (MAT) is defined as the maximum tension
experienced by the Cable under the worst case loading condition.
• The cable max strain is defined as the maximum strain experienced by the Cable under the
worst-case loading condition.
• The cable Every Day Tension (EDT) is defined as the maximum cable tension on any span
under normal conditions.
• The Ultimate /Rated Tensile Strength (UTS/ RTS/ breaking strength) is defined as the
maximum tensile load applied and held constant for one minute at which the specimen shall
not break. While preparing the Sag-tension charts for the OPGW cable the following
conditions shall be met:
• The Max Allowable Tension (MAT) / max strain shall be less than or equal to the MWT/
Strain margin of the cable.
• The sag shall not exceed the earth wire sag in all conditions.
• The Max Allowable Tension shall also be less than or equal to 0.4 times the UTS.
• The 25-year creep at 25% of UTS (creep test as per IEEE 1138) shall be such that the 25 year
creep plus the cable strain at Max Allowable Tension (MAT) is less than or equal to the cable
strain margin.
• The everyday tension (EDT) shall not exceed 20% of the UTS for the OPGW cable.
The Sag-tension chart of OPGW cable indicating the maximum tension, cable strain and sag shall be
calculated and submitted along with the bid under various conditions mentioned below:
1. 53° C , no wind and no ice
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
The spare cable shall be supplied on sturdy, corrosion resistant, steel drums suitable for long periods
of storage and re-transport & handling.
There shall be no factory splices allowed within a continuous length of cable. Only one continuous
cable length shall be provided on each drum. The lengths of cable to be supplied on each drum shall
be determined by a "schedule" prepared by the Contractor and approved by the owner.
35.1.3.16 Optical Ground Wire (OPGW)
OPGW cable construction shall comply with IEEE-1138, 2009. The cable provided shall meet both
the construction and performance requirements such that the ground wire function, the optical fibre
integrity and optical transmission characteristics are suitable for the intended purpose. The cable shall
consist of optical fibre units as defined in this specification. There shall be no factory splices within
the cable structure of a continuous cable length.
The composite fibre optic overhead ground wire shall be made up of multiple buffer tubes embedded
in a water tight aluminium/aluminium alloy/stainless steel with aluminium coating protective central
fibre optic unit surrounded by concentric-lay stranded metallic wires in single or multiple layers. Each
buffer tube shall have maximum 12 no. of fibres. All fibres in single buffer tube or directly in central
fibre optic unit is not acceptable. The dual purpose of the composite cable is to provide the electrical
and physical characteristics of conventional overhead ground wire while providing the optical
transmission properties of optical fibre.
35.1.3.17 Central Fibre Optic Unit
The central fibre optic unit shall be designed to house and protect multiple buffered optical fibre units
from damage due to forces such as crushing, bending, twisting, tensile stress and moisture. The
central fibre optic unit and the outer stranded metallic conductors shall serve together as an integral
unit to protect the optical fibres from degradation due to vibration and galloping, wind and ice
loadings, wide temperature variations, lightning and fault current, as well as environmental effects
which may produce hydrogen.
The OPGW design of dissimilar materials such as stainless-steel tube with aluminium or aluminium–
clad-steel wire strands are not allowed. Central fibre optic unit may be of aluminium or stainless-steel
tube with aluminium protective coating. In case of aluminium protective coating, the coating must
completely cover the tubes leaving no exposed areas of tubing that can make electrical contact either
directly or indirectly through moisture, contamination, protrusions, etc with the surrounding stranded
wires. The tube may be fabricated as a seamless tube, seam welded, or a tube without a welded seam.
35.1.3.18 Basic Construction
The OPGW cable construction shall conform to the applicable requirements of this specification,
applicable clauses of IEC 61089 related to stranded conductors and Table 1.2(a) OPGW Mechanical
and Electrical Characteristics. In addition, the basic construction shall include bare concentric-lay-
stranded metallic wires with the outer layer having left hand lay. The wires may be of multiple layers
with a combination of various metallic wires within each layer. The direction of lay for each
successive layer shall be reversed. The finished wires shall contain no joints or splices unless
otherwise agreed to by the Employer and shall conform to all applicable clauses of IEC 61089 as they
pertain to stranded conductors.
The wires shall be so stranded that when the complete OPGW is cut, the individual wires can be
readily regrouped and then held in place by one hand.
35.1.3.19 Breaking Strength
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
The rated breaking strength of the completed OPGW shall be taken as no more than 90 percent of the
sum of the rated breaking strengths of the individual wires, calculated from their nominal diameter
and the specified minimum tensile strength.
The rated breaking strength shall not include the strength of the optical unit. The fibre optic unit shall
not be considered a load bearing tension member when determining the total rated breaking strength
of the composite conductor.
35.1.3.20 Electrical and Mechanical Requirements
Table 1-2(a) provides OPGW Electrical and Mechanical Requirements for the minimum performance
characteristics. Additionally, the OPGW mechanical & electrical characteristics shall be similar to
that of the earthwire being replaced such that there is no or minimal consequential increase in stresses
on towers. For the purposes of determining the appropriate Max Working Tension limit for the
OPGW cable IS 802:1995 and IS 875: 1987 shall be applied. However, the OPGW installation sag &
tension charts shall be based on IS 802 version to which the line is originally designed. For the
OPGW cable design selection and preparation of sag tension charts, the limits specified in this section
shall also be satisfied. The Bidder shall submit sag-tension charts for the above cases with their bids.
Table 1.2(a)
OPGW Electrical and Mechanical Requirements
35.1.3.21Operating conditions
Since OPGW shall be located at the top of the transmission line support structure, it will be subjected
to Aeolian vibration, Galloping and Lightning strikes. It will also carry ground fault currents.
Therefore, its electrical and mechanical properties shall be same or similar as those required of
conventional ground conductors.
35.1.3.22 Installation
OPGW installed under live line condition, i.e. with all circuits charged to the rated line voltage as
specified in this section shall be generally in accordance with the IEEE Guide to the Installation of
Overhead Transmission Line Conductors (IEEE STD. 524 with latest revisions), with additional
instructions and precautions for live line working and fibre optic cable handling.
A tower structural analysis shall be carried out by the Contractor wherever required, based on the
relevant data to be provided by Employer, to ensure that with the replacement of existing earth wire
with the OPGW cable, the tower members remain within the statutory safety limits as per Indian
Electricity rules and if required the Contractor shall carry out the tower strengthening as necessary at
no additional cost to Employer. The OPGW cable sections shall normally be terminated & spliced
only on tension towers. In exceptional circumstances, and on Employer specific approval, cable may
be terminated on Suspension towers, but in this case tower strength shall be examined to ensure that
tower loads are within safe limits and if required, necessary tower strengthening shall be carried out
by the Contractor at no additional cost to Employer.
35.1.3.23Installation Hardware
The scope of supply includes all required fittings and hardware such as Tension assembly, Suspension
assembly, Vibration dampers, reinforcing rods, Earthing clamps, Downlead clamps, splice enclosure
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
etc. The Bidder shall provide documentation justifying the adequacy and suitability of the hardware
supplied. The quantity of hardware & fittings to meet any eventuality during site installation
minimum@ 1% shall also be provided as part of set/km for each transmission line without any
additional cost to Employer. The OPGW hardware fittings and accessories shall follow the general
requirements regarding design, materials, dimensions & tolerances, protection against corrosion and
markings as specified in clause 4.0 of EN 61284: 1997 (IEC 61284). The shear strength of all bolts
shall be at least 1.5 times the maximum installation torque. The OPGW hardware & accessories
drawing & Data Requirement Sheets (DRS) document shall consist of three parts:
(1) A technical particular sheet
(2) An assembly drawing i.e. level 1 drawing and
(3) Component level drawings i.e. level 2 & lower drawings. All component reference
numbers, dimensions and tolerances, bolt tightening torques & shear strength and
ratings such as UTS, slip strength etc shall be marked on the drawings.
The fittings and accessories described herein are indicative of installation hardware typically used for
OPGW installations and shall not necessarily be limited to the following:
(a) Suspension Assemblies: Preformed armour grip suspension clamps and aluminium alloy armour
rods/ reinforcing rods shall be used. The suspension clamps shall be designed to carry a vertical load
of not less than 25 KN. The suspension clamps slippage shall occur between 12kN and 17 kN as
measured. The Contractor shall supply all the components of the suspension assembly including
shackles, bolts, nuts, washers, split pins, etc. The total drop of the suspension assembly shall not
exceed 150 mm (measured from the centre point of attachment to the centre point of the OPGW). The
design of the assembly shall be such that the direction of run of the OPGW shall be the same as that of
the conductor.
(b) Dead End Clamp Assemblies: All dead-end clamp assemblies shall preferably be of performed
armoured grip type and shall include all necessary hardware for attaching the assembly to the tower
strain plates. Dead end clamps shall allow the OPGW to pass through continuously without cable
cutting. The slip strength shall be rated not less than 95% of the rated tensile strength of the OPGW.
(c) Clamp Assembly Earthing Wire: Earthing wire consisting of a 1500 mm length of aluminium or
aluminium alloy conductor equivalent in size to the OPGW shall be used to earth suspension and
dead-end clamp assemblies to the tower structure. The earthing wire shall be permanently fitted with
lugs at each end. The lugs shall be attached to the clamp assembly at one end and the tower structure
at the other.
(d) Structure Attachment Clamp Assemblies: Clamp assemblies used to attach the OPGW to the
structures, shall have two parallel grooves for the OPGW, one on either side of the connecting bolt.
The clamps shall be such that clamping characteristics do not alter adversely when only one OPGW is
installed. The tower attachment plates shall locate the OPGW on the inside of the tower and shall be
attached directly to the tower legs/cross-members without drilling or any other structural
modifications.
(e) Vibration Dampers: Vibration dampers type 4R Stockbridge or equivalent, having four (4)
different frequencies spread within the Aeolian frequency bandwidth corresponding to wind speed of
1m/s to 7 m/s, shall be used for suspension and tension points in each span. The Contractor shall
determine the exact numbers and placement(s) of vibration dampers through a detailed vibration
analysis as specified in technical specifications.
One damper minimum on each side per OPGW cable for suspension points and two dampers
minimum on each side per OPGW cable for tension points shall be used for nominal design span of
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
400 meters. For all other ruling spans, the number of vibration damper shall be based on vibration
analysis.
The clamp of the vibration damper shall be made of high strength aluminum alloy of type LM-6. It
shall be capable of supporting the damper and prevent damage or chaffing of the conductor during
erection or continued operation. The clamp shall have smooth and permanent grip to keep the damper
in position on the OPGW cable without damaging the strands or causing premature fatigue failure of
the OPGW cable under the clamp. The clamp groove shall be in uniform contact with the OPGW
cable over the entire clamping surface except for the rounded edges. The groove of the clamp body
and clamp cap shall be smooth, free from projections, grit or other materials which could cause
damage to the OPGW cable when the clamp is installed. Clamping bolts shall be provided with self
locking nuts and designed to prevent corrosion of threads or loosening in service.
The messenger cable shall be made of high strength galvanised steel/stain less steel. It shall be of
preformed and post formed quality in order to prevent subsequent droop of weight and to maintain
consistent flexural stiffness of the cable in service. The messenger cable other than stainless steel shall
be hot dip galvanised in accordance with the recommendations of IS:4826 for heavily coated wires.
The damper mass shall be made of hot dip galvanised mild steel/cast iron or a permanent mould cast
zinc alloy. All castings shall be free from defects such as cracks, shrinkage, inclusions and blow holes
etc. The surface of the damper masses shall be smooth.
The damper clamp shall be casted over the messenger cable and offer sufficient and permanent grip
on it. The messenger cable shall not slip out of the grip at a load less than the mass pull-off value of
the damper. The damper masses made of material other than zinc alloy shall be fixed to the messenger
cable in a suitable manner in order to avoid excessive stress concentration on the messenger cables
which shall cause premature fatigue failure of the same. The messenger cable ends shall be suitably
and effectively sealed to prevent corrosion. The damper mass made of zinc alloy shall be casted over
the messenger cable and have sufficient and permanent grip on the messenger cable under all service
conditions. The contractor must indicate the clamp bolt tightening torque to ensure that the slip
strength of the clamp is maintained between 2.5 kN and 5 kN. The clamp when installed on the
OPGW cable shall not cause excessive stress concentration on the OPGW cable leading to permanent
deformation of the OPGW strands and premature fatigue failure in operation. The vibration analysis
of the system, with and without damper and dynamic characteristics of the damper as detailed in
Technical Specification, shall have to be submitted. The technical particulars for vibration analysis
and damping design of the system are as follows
Sl
Description Technical Particulars
No
Span Length in meters
(i) Ruling design span: 400 meters
1
(ii) Maximum span: 1100 meters
(iii) Minimum Span: 100 meters
2 Configuration: As per Specifications
3 Tensile load in each: As per sag tension calculations
Standard preformed armour
4 Armour rods used:
rods/AGS
5 Maximum permissible dynamic strain: +/- 150 micro strains
The damper placement chart for spans ranging from 100m to 1100m shall be submitted by the
Contractor.
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
Placement charts should be duly supported with relevant technical documents and sample
calculations.
The damper placement charts shall include the following
(1) Location of the dampers for various combinations of spans and line tensions clearly indicating
the number of dampers to be installed per OPGW cable per span.
(2) Placement distances clearly identifying the extremities between which the distances are to be
measured.
(3) Placement recommendation depending upon type of suspension clamps (viz Free center
type/Armour grip type etc.)
(4) The influence of mid span compression joints, repair sleeves and armour rods (standard and
AGS) in the placement of dampers.
35.1.3.24 Fibre Optic Splice Enclosures (Joint Box)
All splices shall be encased in Fibre Optic Splice Enclosures. Suitable splice enclosures shall be
provided to encase the optical cable splices in protective, moisture and dust free environment. Splice
enclosures shall comply with ingress protection class IP 66 or better. The splice enclosures shall be
designed for the storage and protection of required number of optical fibre splices and equipped with
sufficient number of splice trays for splicing all fibres in the cable. No more than 12 fibres shall be
terminated in a single splice tray. They shall be filled with suitable encapsulate that is easily
removable should re-entry be required into the enclosures. Splice enclosures shall be suitable for
outdoor use with each of the cable types provided under this contract. Splice enclosures shall be
appropriate for mounting on transmission line towers above anticlimb guard levels at about 10 metres
from top of the tower and shall accommodate pass-through splicing. The actual mounting height and
location shall be finalised after Survey. Contractor shall be responsible for splicing of fibres and
installation of splice enclosures.
35.1.3.25 Optical Fibre Splices
Splicing of the optical fibre cabling shall be minimized through careful Contractor planning. There
shall be no mid-span splices allowed. All required splices shall be planned to occur on tower
structures. All optical fibre splicing shall comply with the following:
(a) All fibre splices shall be accomplished through fusion splicing.
(b) Each fibre splice shall be fitted with a splice protection sheath fitted over the final splice.
(c) All splices and bare fibre shall be neatly installed in covered splice trays.
(d) For each link, bi-directional attenuation of single mode fusion splices, shall not average more
than 0.05 dB and no single splice loss shall exceed 0.1 dB when measured at 1550 nm.
(e) For splicing, fibre optic cable service loops of adequate length shall be provided so that all
splices occurring at tower structures can be performed at ground level.
35.1.3.26 Fibre Optic Approach Cables
For purposes of this specification, a fibre optic approach cable is defined as the Armoured
underground fibre optic cable required to connect Overhead Fibre Optic Cable (OPGW) between the
final in line splice enclosure on the gantry / tower forming the termination of the fibre cable on the
power line and the Fibre Optic Distribution Panel (FODP) installed within the building. The estimated
fibre optic approach cabling length requirements are indicated in the appendices. However, the
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
Contractor shall supply & install the optical fibre approach cable as required based on detailed site
survey to be carried out by the Contractor during the project execution and the Contract price shall be
adjusted accordingly.
35.1.3.27 Basic Construction
The cable shall be suitable for direct burial, laying in trenches & PVC/Hume ducts, laying under false
flooring and on indoor or outdoor cable raceways.
35.1.3.28 Jacket Construction & Material
The Approach Cable shall be a UV resistant, rodent proof, armoured cable with metallic type of
armouring. The outer cable jacket for approach cable shall consist of carbon black polyethylene resin
to prevent damage from exposure to ultra-violet light, weathering and high levels of pollution. The
jacket shall conform to ASTM D1248 for density.
35.1.3.29 Optical, Electrical and Mechanical Requirements
Approach cable shall contain fibres with identical optical/ physical characteristics as those in the
OPGW cables. The cable core shall comprise of tensile strength member(s), fibre support/bedding
structure, core wrap/bedding, and an overall impervious jacket.
35.1.4.0 Fibre Optic Distribution Panel
Fibre Optic Distribution Panels is required for each location for termination of fibres in a manner
consistent with the following:
(a) FODPs shall be suitable for use with each of the cable types provided as part of this contract.
FODPs shall accommodate pass-through splicing and fibre terminations.
(b) FODPs for indoor use shall be supplied in suitable cabinets/racks with locking arrangement
(c) All FODPs shall be of corrosion resistant, robust construction and shall allow both top or
bottom entry for access to the splice trays. Ground lugs shall be provided on all FODPs and
the Contractor shall ensure that all FODPs are properly grounded. The FODP shall meet or
exceed ingress protection class IP55 specifications.
35.1.5.0 Optical Fibre Connectors
Optical fibres shall be connectorised with FC-PC type connectors preferably. Alternatively, connector
with matching patch cord shall also be acceptable. Fibre optic couplings supplied with FODPs shall
be appropriate for the fibre connectors to be supported. There shall be no adapters.
35.1.5.1 Service Loops
For purposes of this specification, cable and fibre service loops are defined as slack (extra) cable and
fibre provided for facilitating the installation, maintenance and repair of the optical fibre cable plant.
(a) Outdoor Cable Service Loops: In-line splice enclosures installed outdoors and mounted on the
utility towers shall be installed with sufficient fibre optic cable service loops such that the
recommended minimum bend radius is maintained while allowing for installation or maintenance of
the cable to be performed in a controlled environment at ground level.
(b) Indoor Cable Service Loops: FODPs shall provide at least three (3) metres of cable service loop.
Service loops shall be neatly secured and stored, coiled such that the minimum recommended bend
radius' are maintained.
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
(c) Fibre Units Service Loops: For all fibre optic cable splicing, the cable shall be stripped back a
sufficient length such that the fan-out of fibre units shall provide for at least one (1) metre of fibre unit
service loop between the stripped cable and the bare fibre fan-out.
(d) Pigtail Service Loops : Connectorised pigtails spliced to bare fibres shall provide at least 1 metre
of service loop installed in the FODP fibre organizer and at least one (1) metre of service loop to the
couplings neatly stored behind the FODP coupling panels.
(e) Fibre Service Loops : At least 0.5 metre of bare fibre service loop shall be provided on each side
of all fibre splices. The bare fibre service loops shall be neatly and safely installed inside covered
splice trays.
35.1.6.0 Test Equipment
Appendix-B provides mandatory test equipment requirements, to be provided. The parameters /
features of the mandatory equipments are enumerated in Table 1.3 below:
Table 1.3
Sl No Test Equipment Parameter
A. Test Equipment for OPGW cable
OTDR (Optical Time Domain
Equivalent to Anritsu MW9076B1 or
1 Reflectometer) for 1310/1550 nm with laser
better.
source.
2 Optical Attenuators (variable 1310/1550nm). Equivalent to JDSU OLA55 or better.
3 Optical Power meter (1310/1550nm) Equivalent to JDSU OLP55 or better
Equivalent to EXFO FLS300-23BL or
4 Laser Light Source (1310/1550nm)
better.
Optical Fibre Fusion Splicer incl. Fibre Equivalent to Sumitomo T-39-SE or
5
cleaver better.
6 Splice kit FIS – FI-0053-FF or equivalent
Optical test accessory kit including all
Necessary connectors, adaptors, cables,
7 FIS – FI-0053-TS-ST or equivalent
terminations and other items required for
testing
In case the offered make/model of test equipment has multiple options for the parameters, the option
of higher range shall be acceptable. The supplied test equipment shall be suitable for use in the high
EMI/EMC environment. The Contractor shall submit performance certificate for offered test
equipment from at least one customer. The Contractor shall offer only reputed make test equipment
such as Acterna (JDSU)/Anritsu/Sumitomo/Agilent/EXFO etc.
35.1.7.0Inspection & Testing Requirement
All materials furnished and all work performed under this Contract shall be inspected and tested.
Deliverables shall not be shipped until all required inspections and tests have been completed, and all
deficiencies have been corrected to comply with this Specification and approved for shipment by the
Employer.
Except where otherwise specified, the Contractor shall provide all manpower and materials for tests,
including testing facilities, logistics, power and instrumentation, and replacement of damaged parts.
The costs shall be borne by the Contractor and shall be deemed to be included in the contract price.
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
The entire cost of testing for factory, production tests and other test during manufacture specified
herein shall be treated as included in the quoted unit price of materials, except for the expenses of
Inspector/Employer’s representative.
Acceptance or waiver of tests shall not relieve the Contractor from the responsibility to furnish
material in accordance with the specifications.
All tests shall be witnessed by the Employer and/or its authorized representative (hereinafter referred
to as the Employer) unless the Employer authorizes testing to proceed without witness. The Employer
representative shall sign the test form indicating approval of successful tests.
Should any inspections or tests indicate that specific item does not meet Specification requirements,
the appropriate items shall be replaced, upgraded, or added by the Contractor as necessary to correct
the noted deficiencies at no cost to the Employer. After correction of a deficiency, all necessary
retests shall be performed to verify the effectiveness of the corrective action.
The Employer reserves the right to require the Contractor to perform, at the Employer's expense, any
other reasonable test(s) at the Contractor's premises, on site, or elsewhere in addition to the specified
Type, Acceptance, Routine, or Manufacturing tests to assure the Employer of specification
compliance.
35.1.8.0Testing Requirements
Following are the requirements of testing :
1. Type Testing
2. Factory Acceptance Testing
3. Site Acceptance Testing
35.1.9.0 Type Testing
"Type Tests" shall be defined as those tests which are to be carried out to prove the design, process of
manufacture and general conformity of the materials to this Specification. Type Testing shall comply
with the following:
(a) All cable & equipment being supplied shall conform to type tests as per technical specification.
(b)The test reports submitted shall be of the tests conducted within last seven (7) years for OPGW
cable prior to the date of proposal/offer submitted. In case the test reports are older than seven (7)
years for OPGW cable on the date of proposal/offer, the Contractor shall repeat these tests at no extra
cost to the Employer.
(c) The Contractor shall submit, within 30 days of Contract Award, copies of test reports for all of the
Type Tests that are specified in the specifications and that have previously ( before Contract award)
been performed. These reports may be accepted by the Employer only if they apply to materials and
equipment that are essentially identical to those due to be delivered under the Contract and only if test
procedures and parameter values are identical to those specified in this specifications carried out at
accredited labs and witnessed by third party / customer’s representatives. In the event of any
discrepancy in the test reports or any type tests not carried out, same shall be carried out by Contractor
without any additional cost implication to the Employer.
In case the Type Test is required to be carried out, then following shall be applicable:-
(d) Type Tests shall be certified or performed by reputed laboratories using material and equipment
data sheets and test procedures that have been approved by the Employer. The test procedures shall be
formatted as defined in the technical specifications and shall include a complete list of the applicable
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
reference standards and submitted for Employer approval at least four (4) weeks before
commencement of test(s). The Contractor shall provide the Employer at least 30 days written notice
of the planned commencement of each type test.
(e) The Contractor shall provide a detailed schedule for performing all specified type tests. These tests
shall be performed in the presence of a representative of the Employer.
(f) The Contractor shall ensure that all type tests can be completed within the time schedule offered in
his Technical Proposal.
In case of failure during any type test, the Supplier is either required to manufacture a fresh sample lot
and repeat all type tests successfully or repeat that particular type test(s) at least three times
successfully on the samples selected from the already manufactured lot at his own expenses. In case a
fresh lot is manufactured for testing then the lot already manufactured shall be rejected.
35.1.9.1Type Test Sample
The Contractor shall supply equipment/material for sample selection only after the Quality Assurance
Plan has been approved by the Employer. The sample material shall be manufactured strictly in
accordance with the approved Quality Assurance Plan. The Contractor shall submit for Employer
approval, the type test sample selection procedure. The selection process for conducting the type tests
shall ensure that samples are selected at random. For optical fibres/ Fibre Optic cables, at least three
reels/ drums of each type of fibre/cable proposed shall be offered for selection. For FO cable
installation hardware & fittings at least ten (10) samples shall be offered for selection. For Splice
enclosures at least three samples shall be offered for selection.
35.1.9.2List of Type Tests
The type testing shall be conducted on the following items
(a) Optical fibres
(b) OPGW Cable
(c) OPGW Cable fittings
(d) Vibration Damper
(e) Splice Enclosure (Joint Box)
(f) Approach Cable
35.1.9.3 Type Tests for Optical Fibres
The type tests listed below in table 2-1 shall be conducted on DWSM fibres to be supplied as part of
overhead cables. The tests specific to the cable type are listed in subsequent sections.
(Salt Spray)
Test
The test shall be conducted on a sample of sufficient
length in accordance with IEC 60794-1-2 E1. The
attenuation variation shall not exceed 0.05 dB/Km up
IEC 60794-1-
Tensile to 90% of RTS of fibre optic cable.
Performance 2 E1 /
17 The load shall be increased at a steady rate up to
EIA/TIA 455-
Test rated tensile strength and held for one (1) minute. The
33B
fibre optic cable sample shall not fail during the
period. The applied load shall then be increased until
the failing load is reached and the value recorded.
IEC 60794-4-
The OPGW cable construction shall be tested in
10 /
18 Lightning Test accordance with IEC 60794-1-2, Method
IEC 60794-1-
H2 for Class 1.
2 (2003)
On a fibre optic cable sample of minimum 1 metre length, two contact
clamps shall be fixed with a predetermined bolt torque. The resistance
DC Resistance shall be measured by a Kelvin double bridge by placing the clamps
19
Test (IEC 60228) initially zero metre and subsequently one metre apart. The tests shall
be repeated at least five times and the average value recorded after
correcting at 20°C.
The Tension Assembly is correctly fitted and is the same that will be carried out during installations.
Part 1:
The tension assembly (excluding tension clamp) shall be increased at a constant rate up to a load
equal to 50% of the specified minimum Failure Load increased at a constant rate and held for one
minute for the test rig to stabilise. The load shall then be increased at a steady rate to 67% of the
minimum Failure Load and held for five minutes. This load shall then remove in a controlled manner
and the Tension Assembly disassembled. Examination of the Tension Dead-End and associated
components shall be made and any evidence of visual deformation shall be documented.
Part 2:
The Tension Dead-End and associated components shall then be reassembled and bolts tightened as
before. The tensile load shall gradually be increased up shall gradually be increased up to 50% of the
specified Minimum Failure Load of the Tension Assembly and held for one minute for the Test Rig to
stabilise and the load shall be further increased at a steady rate until the specified minimum Failure
Load is reached and held for one minute. No fracture should occur during this period. The applied
load shall then be increased until the failing load is reached and the value shall be documented.
Acceptance Criteria for Tension/Suspension Assembly:
- No evidence of binding of the Nuts or Deformation of components at end of Part 1 of Test.
- No evidence of Fracture at the end of one minute at the minimum failure load during Part 2 of the
Test.
Any result outside these parameters shall constitute a failure.
(ii) Clamp Slip Strength Test for Suspension Assembly
The suspension assembly shall be vertically suspended by means of a flexible attachment. A suitable
length fibre optical cable shall be fixed in the clamps. Once the Suspension Clamp has been
assembled, the test rig is tensioned to 1 kN and the position scale on the recorder ‘zeroed’. The test rig
is then tensioned to 2.5 kN and the relative positions of the Reinforcing Rods, Armour Rods and
Suspension Clamp shall be marked by a suitable means to confirm any slippage after the test has been
completed. The relative positions of the helical Armour Rods and associated Reinforcing Rods at each
end shall be marked and also 2 mm relative position between clamp body and Armour Rods shall be
marked on one side. The load shall be increased to 12 kN at a loading rate of 3 kN/min and held for
one minute. At the end of this one-minute period, the relative displacement between clamp body and
the armour rods shall be observed. If the slippage is 2 mm or above, the test shall be terminated.
Otherwise, at the end of one minute the position of the clamp body and 2 mm. relative positions
between clamp body and armour rods shall be marked on the other side. After the one-minute pause,
the load shall be further increased at a loading rate of 3 kN/min, and recording of load and
displacement shall continue until either the relative Position displacement between clamp body and
armour rods reaches more than 2 mm or the load reaches the maximum slip load of 17 kN. On
reaching either of the above values the test is terminated. Visual examination of all paint marks shall
be recorded, and a measurement of any displacement recorded in the Table of Results.
Acceptance Criteria:
The Suspension Clamp has passed the Slip Test if the following conditions are met:
No slippage* shall occur at or below the specified minimum slip load.
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
*Definition of no slippage in accordance with IEC 61284, 1997:- Any relative movement less than 2
mm is accepted. The possible couplings or elongations produced by the cable as a result of the test
itself are not regarded as slippage.
Slippage shall occur between the specified maximum and minimum slip load of 12 -17 kN.
There shall be no slippage of the Reinforcing Rods over the cable, and no slippage of the
Armour Rods over the Reinforcing Rods.
The relative movement (i.e. more than 2 mm between Armour Rods & Clamp body) between
minimum 12 kN and maximum slip 17 kN, shall be considered as slip.
The Armour Rods shall not be displaced from their original lay or damaged**.
** Definition of no damage in accordance with convention expressed in IEC 61284:
1997 no damage, other than surface flattening of the strands shall occur.
Any result outside these parameters is a failure.
(iii) Slip Strength Test of Tension Clamp
Tension clamps shall be fitted on an 8 m length of fibre optic cable on both ends. The assembly shall
be mounted on a tensile testing machine and anchored in a manner similar to the arrangement to be
used in service. A tensile load shall gradually be applied up to 20 % of the RTS of OPGW.
Displacement transducers shall be installed to measure the relative movement between the OPGW
relative to the Reinforcing Rods and Tension Dead –End relative to Reinforcing Rods. In addition,
suitable marking shall be made on the OPGW and Dead-End to confirm grip. The load shall be
gradually increased at a constant rate up to 50 % of the UTS and the position scale of the recorder is
zeroed. The load shall then gradually increase up to 95 % of the UTS and maintained for one minute.
After one-minute pause, the load shall be slowly released to zero and the marking examined and
measured for any relative movement.
Acceptance Criteria:
- No movement* shall occur between the OPGW and the Reinforcing Rods, or between the
Reinforcing Rods and the Dead-End assembly.
- No failure or damage or disturbance to the lay of the Tension Dead-End, Reinforcing Rods or
OPGW.
* Definition of no movement as defined in IEC 61284: Any relative movement less than 2 mm is
accepted. The possible couplings or elongations produced by the conductor as a result of the test itself
are not regarded as slippage. Any result outside these parameters shall constitute a failure.
(iv) Grounding Clamp and Structure Mounting Clamp Fit Test
For structure mounting clamp, one series of tests shall be conducted with two fibre optic cables
installed, one series of tests with one fibre optic cable installed in one groove, and one series of tests
with one fibre optic cable in the other groove. Each clamp shall be installed including clamping
compound as required on the fibre optic cable. The nut shall be tightened on to the bolt by using
torque wrench with a torque of 5.5 kgm or supplier's recommended torque and the tightened clamp
shall be held for 10 minutes. After the test remove the fibre optic cable and examine all its
components for distortion, crushing or breaking. Also, the fibre optic cable shall be checked to ensure
free movement within the core using dial callipers to measure the diameter of the core tube. The
material shall be defined as failed if any visible distortion, crushing, cracking or breaking of the core
tube is observed or the fibre optic cable within the core tube is not free to move, or when the diameter
of the core tube as measured at any location in the clamped area is more than 0.5 mm larger or smaller
of the core diameter as measured outside the clamped area.
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
(ii) The self damping factor and flexural stiffness (EI) for fibre optic cable shall be calculated on the
basis of experimental results. The details to experimental analysis with these data shall be furnished.
(iii) The power dissipation curve obtained from Damper Characteristics Test shall be used for analysis
with damper.
(iv) Examine the Aeolian Vibration level of the fibre optic cable with and without vibration damper
installed at the recommended location or wind velocity ranging from 0 to 30 Km per hour, predicting
amplitude, frequency and vibration energy input.
(v) From vibration analysis of fibre optic cable without damper, antinode vibration amplitude and
dynamic strain levels at clamped span extremities as well as antinodes shall be examined and thus
lower and upper dangerous frequency limits between which the Aeolian vibration levels exceed the
specified limits shall be determined.
(vi) From vibration analysis of fibre optic cable with damper(s) installed at the recommended
location, the dynamic strain level at the clamped span extremities, damper attachment point and the
antinodes on the fibre optic cable shall be determined. In addition to above damper clamp vibration
amplitude and antinodes vibration amplitudes shall also be examined.
The dynamic strain levels at damper attachment point, clamped span extremities and antinodes shall
not exceed the specified limits. The damper clamp vibration amplitude shall not be more than that of
the specified fatigue limits.
(c) Fatigue Tests
(i) Test Set Up
The fatigue tests shall be conducted on a laboratory set up with a minimum effective span length of
30m. The fibre optic cable shall be tensioned at 25% of RTS of fibre optic cable and shall not be
equipped with protective armour rods at any point. Constant tension shall be maintained within the
span by means of lever arm arrangement.
After the fibre optic cable has been tensioned, clamps shall be installed to support the fibre optic cable
at both ends and thus influence of connecting hardware fittings are eliminated from the free span. The
clamps shall not be used for holding the tension on the fibre optic cable. There shall be no loose parts,
such as suspension clamps, U bolts, on the test span supported between clamps mentioned above. The
span shall be equipped with vibration inducing equipment suitable for producing steady standing
vibration. The inducing equipment shall have facilities for step less speed control as well as step less
amplitude arrangement. Equipment shall be available for measuring the frequency, cumulative
number of cycles and amplitude of vibration at any point along the span.
(ii) Fatigue Test
The vibration damper shall be installed on the test span with the manufacturer's specified tightening
torque. It shall be ensured that the damper shall be kept minimum three loops away from the shaker to
eliminate stray signals influencing damper movement.
The damper shall then be vibrated at the highest resonant frequency of each damper mass. For
dampers involving torsional resonant frequencies, tests shall be done at torsional modes also in
addition to the highest resonant frequencies at vertical modes. The resonance frequency shall be
identified as the frequency at which each damper mass vibrates with the maximum amplitude on
itself. The amplitude of vibration of the damper clamp shall be maintained not less than ±25/f mm
where f is the frequency in Hz.
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
The test shall be conducted for minimum ten million cycles at each resonant frequency mentioned
above. During the test, if resonance shift is observed, the test frequency shall be tuned to the new
resonant frequency.
The clamp slip test as mentioned herein shall be repeated after fatigue tests without retorquing or
adjusting the damper clamp, and the clamp shall withstand a minimum load equal to 80% of the slip
strength for a minimum duration of one minute.
After the above tests, the damper shall be removed from fibre optic cable and subjected to dynamic
characteristics test. There shall not be any major deterioration in the characteristics of the damper. The
damper then shall be cut open and inspected. There shall not be any broken, loose, or damaged part.
There shall not be significant deterioration or wear of the damper. The fibre optic cable under clamp
shall also be free from any damage.
For purposes of acceptance, the following criteria shall be applied:
(1) There shall not be any resonant frequency shift before and after the test by more than ± 20%
(2) The power dissipation of the damper before and after test at the individual resonant
frequencies do not differ by more than ± 20% Beside above tests, the type tests listed below
in the table shall also be conducted on Vibration Damper.
Sl
Test Name Test Procedure
No
Visual examination & Dimensional and material IEC 61897 Clause 7.1 &
1
verification 7.2
2 Clamp Slip test IEC 61897 Clause 7.5
3 Clamp bolt tightening test IEC 61897 Clause 7.7
4 Attachments of weights to messenger cable IEC 61897 Clause 7.8
Attachment of clamps to messenger
5 IEC 61897 Clause 7.8
cable
IEC 61897 Clause
6 Damper effectiveness evaluation
7.11.3.2
variation of the fibres during the duration of the test shall be less than ±0.05dB, and the internal
humidity rate measured, less than 2%.
(iii) Rain Withstand Test / Water Immersion test
The splice enclosure with optical fibres cable installed and fibres spliced fixed, shall be subjected to
24 hours of simulated rain in accordance with IEC 60060 testing requirements. No water seepage or
moisture shall be detected in the splice enclosure. The attenuation variation of the fibres after the test
shall be less than ±0.05dB.
(iv) Vibration Test
The splice enclosure, with fibres united inside, shall be subjected to vibrations on two axes with a
frequency scanning of 5 to 50 Hz. The amplitude of the vibrations shall be constant at 0.450mm, peak
to peak, for 2 hours, for each of the vibrations' axes. The variation in attenuation, of the fibres, shall
be less than ±0.05dB. The splice enclosure shall be examined for any defects or deformation. There
shall be no loosening or visible damage of the FO cable at the entry point.
(v) Bending and Torsion test
The splice enclosure, with fibres spliced inside, shall be firmly held in place and be subjected to the
following sequence of mechanical stresses on the cable:
a) 3 torsion cycles of ±180° shall be exercised on the cable. Each cycle shall be less than one
minute.
b) 3 flexure cycles of the cable, of ±180° with one cycle less than one minute.
The variation in the attenuation, of the fibres, shall be less than ±0.05dB. The cables
connection ring shall remain securely fixed to the box with the connection maintained firmly. No
defects/fissures shall be noted on the joint ring or on the splice enclosure
(vi) Tensile test
The splice enclosure with cable fixed to the boxes shall be subjected to a minimum tension of 448
N for a period of two minutes. No fissure shall be noted in the connections or on the box.
(vii) Drop Test
With 2 lengths of 11 metres of cable fixed to the box, it shall be dropped five times from a height of
10 metres. There shall be no fissure, at all, of the box, and the connections shall remain tight. The test
surface shall be carried out in accordance with IEC 60068-2-32.
35.1.9.8 Type Tests for Fibre Optic Approach Cable
The type tests to be conducted on the Fibre Optic Approach cable are listed in Table 2-3: Type Tests
for Fibre Optic Approach Cable. Unless specified otherwise in the technical specifications or the
referenced standards, the optical attenuation of the specimen, measured during or after the test as
applicable, shall not increase by more than 0.05 dB/Km.
The Sampling rate for the Factory acceptance tests shall be 10% of the batch size (minimum 2) for
FO cable drums, FODPs, Joint box and other similar items. Since FAT testing provides a measure of
assurance that the Quality Control objectives are being met during all phases of production, the
Employer reserves the right to require the Contractor to investigate and report on the cause of FAT
failures and to suspend further testing/ approvals until such a report is made and remedial actions
taken, as applicable.
35.1.9.13 Production Testing
Production testing shall mean those tests which are to be carried out during the process of production
by the Contractor to ensure the desired quality of end product to be supplied by him. The production
tests to be carried out at each stage of production shall be based on the Contractor’s standard quality
assurance procedures. The production tests to be carried out shall be listed in the Manufacturing
Quality Plan (MQP), alongwith information such as sampling frequency, applicable standards,
acceptance criteria etc.
The production tests would normally not be witnessed by the Employer. However, the Employer
reserves the right to do so or inspect the production testing records in accordance with Inspection
rights specified for this contract.
35.1.9.14 Factory Acceptance Tests on Optical Fibre to be supplied with OPGW
The factory acceptance tests listed in table below are applicable for the Optical fibres to be supplied.
The listed tests follow testing requirements set forth in IEEE standard 1138/IEC 60794. The
referenced sections specify the detailed test description. The acceptance norm shall be as specified in
the above-mentioned IEEE standards unless specified otherwise in the technical specifications.
Table 2-4
Factory Acceptance Tests for Optical Fibres: Optical Tests
The test report for the above tests for the fibers carried out by the Fiber Manufacturer and used in the
OPGW cables shall be shown to the inspector during OPGW cable FAT and shall be submitted along
with the OPGW cable FAT report.
35.1.9.15 Factory Acceptance Test on OPGW Cable
The factory acceptance tests for OPGW cable specified below in Table follow the requirements set
forth in IEEE standard 1138 / IEC 60794. The FAT shall be carried out on 10% of offered drums in
each lot as specified in technical specifications and the optical tests shall be carried out in all fibres of
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
the selected sample drums. The Rated Tensile Strength test shall be carried out on one sample in each
lot.
Table 2-5
Factory Acceptance Tests on OPGW
Applicable standard: IEEE 1138 / IEC 60794
Table 2-6
Factory Acceptance Tests On OPGW Fittings
S. No. Factory Acceptance Test
Suspension Assembly
1 UTS/Mechanical Strength of the assembly
2 Clamp Slip Test
3 Visual Material verification and dimensional checks as per approved
DRS/Drawings
4 Mechanical strength of each component
5 Galvanising test
Tension Assembly
6 Clamp Slip Strength test
Visual Material verification and dimensional checks as per approved
7
DRS/Drawings
8 Mechanical strength of each component
9 Galvanising Test
Vibration Damper
10 Galvanising test on damper, masses and messenger wires
11 Damper response (resonant frequencies)
12 Clamp Slip test
13 Strength of messenger wires
14 Attachments of weights to messenger cable
Factory Acceptance Test
15 Attachments of clamps to messenger cable
16 Clamp bolt tightening test
17 Clamp bolt torque test
18 Dynamic characteristic test.
19 Visual Material verification and dimensional checks as per approved
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
DRS/Drawings
Structure Mounting Clamp
20 Clamp fit test
21 Clamp Strength test
22 Visual Material verification and dimensional checks as per approved
DRS/Drawings
Table 2-7
Factory Acceptance Tests On Approach Cable
Sl No Factory Acceptance Test
1 Attenuation Co-efficient at 1310 nm and 1550 nm
2 Point discontinuities of attenuation
3 Visual Material verification and dimensional checks as per approved
DRS/Drawings
Table 2-8
Factory Acceptance Tests on Splice Enclosures (Joint Box)/FODP
completion of the work prior to commissioning, all equipment shall be tested to the satisfaction of the
Employer to demonstrate that it is entirely suitable for commercial operation.
35.1.9.21 Minimum Site Acceptance Testing Requirement for FO Cabling
Prior to installation, every spooled fibre optic cable segment shall be tested for compliance with the
Pre-shipment data previously received from the manufacturer. This requirement will preclude the
installation of out of specification cable segments that may have been damaged during shipment.
35.1.9.22 Phases of Site Acceptance Testing
SAT shall be carried out link by link from FODP to FODP. SAT may be performed in parts in case of
long links. The tests, checks, adjustments etc conducted by the Contractor prior to offering the
equipment for SAT shall be called Pre-SAT activities. The Pre-SAT activities shall be described in
the installation manuals and Field Quality Plan documents. Sag and tension of OPGW shall generally
be as per approved sag-tension chart and during installation, sag and tension of OPGW shall be
documented. Upon completion of a continuous cable path, all fibres within the cable path shall be
demonstrated for acceptance of the cable path. Fibre Optic cable site testing minimum requirements
are provided in Table 2- 9(a) through 2-9(c) below:
Table 2-9(a)
Fibre Optic Cable Pre-Installation Testing
Item: Description:
1 Physical Inspection of the cable assembly for damage
2 Optical fibre continuity and fibre attenuation with OTDR at 1550 nm
3 Fibre Optic Cable length measurement using OTDR
Table 2-9(b)
Fibre Optic Cable Splicing Testing
Item: Description:
1 Per splice bi-directional average attenuation with OTDR
2 Physical inspection of splice box/enclosure for proper fibre / cable routing
techniques
3 Physical inspection of sealing techniques, weatherproofing, etc.
Table 2-9(c)
Fibre Optic Cable Commissioning Testing
Item: Description:
1 End to End (FODP to FODP) bi-directional average attenuation of each fibre at
1310 nm and 1550 nm by OTDR.
2 End to End (FODP to FODP) bi-directional average attenuation of each fibre at
1310 nm and 1550 nm by Power meter.
3 Bi-directional average splice loss by OTDR of each splice as well as for all splices
in the link (including at FODP also).
4 Proper termination and labelling of fibres & fibre optic cables at FODP as per
approved labelling plan.
Supply of OPGW Cable & Hardware Fittings needed to tie the OPGW cable to the
towers/gantries.
Supervision of stringing of OPGW Cable at sites as per instruction by Employer. The
supervision shall include the inspection as per stringing procedure, proper location of drum
site, installation of stringing blocks/pulleys, proper sagging, proper installation of hardware,
proper tension as per Sag-Tension chart, provision of service loops of OPGW in jointing
locations
The Splicing work of OPGW Cable and after that testing of link.
35.1.10.3 Installation Hardware
All required hardware’s shall be installed along with OPGW Cable.
35.1.10.4 Installation of Approach Cable
The existing cable trenches/ cable raceways proposed to be used shall be identified in the survey
report. The Contractor shall make its best effort to route the cable through the existing available cable
trenches. Where suitable existing cable trenches are not available, suitable alternatives shall be
provided after Employer approval. However, the approach cable shall be laid in the HDPE pipe in all
condition. Suitable provisions shall be made by the Contractor to ensure adequate safety earthing and
insulated protection for the approach cable. All required fittings, supports, accessories, ducts, inner
ducts, conduits, risers and any item not specially mentioned but required for laying and installation of
approach cables shall be supplied and installed by the Contractor.
35.1.10.5 Optical Fibre Termination and Splicing
Optical fibre terminations shall be installed in Fibre Optic Distribution Panels (FODP) designed to
provide protection for fibre splicing of preconnectorized pigtails and to accommodate connectorized
termination and coupling of the fibre cables. The Contractor shall provide rack /wall mounted Fibre
Optic Distribution Panels (FODPs) sized as indicated in the appendices and shall terminate the fibre
optic cabling up to the FODPs. The location of FODP rack shall be fixed by the Contractor, with the
Employer’s approval.
35.1.10.6 Fibre Optic Distribution Panel
At each location requiring the termination of at least one fibre within a cable, all fibres within that
cable shall be connectorized and terminated in Fibre Optic Distribution Panels in a manner consistent
with the following:
(a) All fibre optic terminations shall be housed using FODPs provisioned with splice organizers and
splice trays. All fibres within a cable shall be fusion spliced to pre-connectorized pigtails and fitted to
the "Back-side" of the provided fibre optic couplings.
(b) Flexible protection shall be provided to the patch cord bunches going out from FODP to other
equipment.
35.1.10.7 Methodology for Installation and Termination
All optical fibre cable termination, installation, stringing and handling plans, guides and procedures,
and engineering analysis (e.g. tension, sag, vibration etc.) shall be submitted to the Employer for
review and approval in the engineering/design phase of the project, prior to establishing the final
cable lengths for manufacture. Installation procedures including details of personnel and time required
shall be documented in detail and submitted to Employer for approval. All installation practices shall
be field proven and ISO accredited.
All cable segments shall include service loops as specified in this specification .The maximum
allowable stringing tension, maximum allowable torsional shear stress, crush strength and other
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
physical parameters of the cable shall not be exceeded. The preventative measures to be taken shall be
documented in detail and submitted to Employer in advance of installation.
Optical fibre attenuation shall be measured after installation and before splicing. Any increase in
attenuation or step discontinuity in attenuation shall not be acceptable and shall constitute a cable
segment failure. In the event of cable damage or any fibre damage, the complete section (tension
location to tension location) shall be replaced as mid-span joints are not acceptable.
Any or all additional steel work or modifications required to attach the fibre cabling to the overhead
transmission/ distribution line towers shall also be carried out by the Contractor. It shall be the
Contractors responsibility to provide adequate communications among all crew members and support
staff to ensure safe and successful installations.
35.1.16.0 Cable Raceways
To the extent possible, existing cable raceways shall be utilised. The Contractor is required to provide
and install any additional indoor cable raceways which may be required for proper implementation of
the fibre optic cabling system. This requirement shall be finalised during survey. The cable raceways
shall conform to the following:
(a) All cable raceways shall be sized to support full loading requirements plus at least a 200% safety
loading factor.
(b) Indoor cable raceways shall be fabricated from construction grade aluminium, galvanized iron or
anodized sheet metal or any other suitable material approved by the Employer. Suitable anticorrosion
measures shall be provided. Steel fabricated raceways shall be finished inside and out, treated to resist
rust and to form a metal-to- paint bond.
(c)Mechanical construction drawings of the cable raceways shall be submitted for Employer’s
information & review
CHAPTER 35: TECHNICAL SPECIFICATION FOR OPGW
APPENDIX-A
Table A-1
Typical transmission line details(To be filled by the Bidder)
Design Minimum
Tension at Clearance in
Every Wind mtrs.
Max Sag – Weight –
Nominal Span (E/W Wind Zone Day Temp Pressure UTS –
Line S/C or Ground Earth
& Conductors in as per (32º C) and (kg/Sq-m) Earthwire
Voltage D/C Wire at 53ºC wire
mtrs.) IS 802 full wind considering (in Kg)
(in mtrs) (in Kg/km) A1 B1 C1
condition – gust factor
Earthwire) in
kg
S/C
400KV
D/C
S/C
220 KV
D/C
132 KV S/C
D/C
Design, manufacture, performance of the tubular conductor shall comply with all currently applicable
standards regulations and safety codes in the locality where the same is to be installed. Unless
otherwise, specified, bus bar should conform to the latest applicable Indian standards and in particular
to the following:
IS : 5082 : Specification for wrought – Aluminium & Aluminium alloy, bars, rods, tubes and sections
for electrical purpose.
IS – 2121-1982 : Specification for conductors and earth wire accessories for overhead power lines.
36.1.1 The equipment covered by the specification shall, unless otherwise stated be designed,
constructed and tested in accordance with the latest revisions of relevant Indian Standards and shall
conform to the regulations of local statutory authorities.
36.1.2 In case of any conflict between the standards and this specification, this specification shall
govern.
36.2.1 The plant and materials supplied shall be suitable for operation under the following climatic
and other conditions:
b) Minimum : 10 %
General
36.3.1 The Aluminium tubular bus bar shall be extruded from 63401 grade Aluminium alloy with
W.P. range 2 treatment. The rigid tubular conductors shall be of aluminium of standard type and
designed to operate within set temperature limits and to withstand thermal and electro mechanical
forces developed due to short circuits and vibration by wind. Material of Aluminium Tubular shall be
CHAPTER 36: TECHNICAL SPECIFICATION FOR 4” IPS ALUMINIUM TUBE
cold drawn aluminium tube with minimum 55% IACS conductivity at 20 o C temperature.
(International Annealed Copper standards)
Dimensional tolerances of the aluminium tube shall be as laid down in IS:2673 for the extruded tube.
36.3.2 Yield strength shall be based on tensile stress of 1335 kg/cm2 and the breaking strength shall
be based on the tensile stress of 1545 kg/cm2.
36.3.3 The temperature of tubular bas bar when carrying full load current shall not exceed 45 oC above
the site ambient temperature.
36.3.4 The material shall be clean smooth and free from any harmful effect. Standard Aluminium
pipes of diameter size 4”. Pipe to pipe joint is to be avoided as far as practicable during erection. In
case of Al tube jointing Argon welding process is to be adopted. Uses of very small pieces of Al tube
is to be avoided as far as practicable in order to minimize no of joints. The aluminium tubular bus bar
offered shall not have any sharp edges, cuts, abrasions, etc and shall be free from visible corona.
36.3.5 The radio interference voltage level of the tubular bus bar shall be below 500 micro volts, at a
voltage 20% above the highest line to earth value of the megahertz.
36.4.2 The maximum length of tube that can be supplied with and without stationing limitations on
transport stipulation shall be indicated in the Bid. Standard length of 7 meters for 4” IPS is preferred.
CHAPTER 37: SPECIFICATION FOR DESIGN AND FEBRICATION OF SUBSTATION STEEL STRUCTURES
Chapter – 37
SPECIFICATION FOR DESIGN AND FEBRICATION OF SUBSTATION STEEL
STRUCTURES
37.1.0 SCOPE
37.1.1 The scope of this section covers specifications for fabrication, proto-assembly, supply and
erection of galvanised steel structures for towers, girders, lightning masts and equipment
support structures. Towers, girders and lightning masts shall be lattice type structure
fabricated from structural steel conforming to IS 2062 (latest).
(latest). All equipment support
structures shall be fabricated from GI pipe conforming to YST 22 or of higher grade as per
IS 806.
37.1.2 Support structure for Circuit breaker and Isolators is not standardized and shall be designed
by the Contractor and approved by the Employer. Any other structures of 400kV, 220 kV,
132kV and 33kV class necessary to complete the substation to complete the work in all
respects shall be designed by the contractor.
37.1.3 The scope shall include supply and erection of all types of structures including bolts, nuts,
washers, hangers, shackles, clamps ant-climbing devices, bird guards, step bolts, inserts in
concrete, gusset plates, equipment mounting bolts, structure earthing bolts, foundation
bolts, spring washers, fixing plates, ground mounted marshaling boxes (AC/DC
Marshaling box & equipment control cabinets), structure mounted marshaling boxes and
any other items as required to complete the job.
37.1.4 The connection of all structures to their foundations shall be by base plates and embedded
anchor/foundation bolts. All steel structures and anchor/foundation bolts shall be fully
galvanized. The weight of the zinc coating shall be at least 0.610 kg/m2 for anchor bolts /
foundation bolts and for structural members. One additional nut shall be provided below
the base plate which may be used for the purpose of levelling.
37.1.5 In case of equipment support structure, Contractor may require to change the dimensions to
match the equipment bus bar height and to match the mounting arrangement of a particular
equipment. Further suitable modification shall be carried out in the drawings of equipment
support structures by the Contractor in order to suit fixation of accessories such as
marshalling boxes, MOM boxes, Control Cabinets, Junction box, surge counter, etc. in the
standard structure fabrication drawings. The Contractor will make these changes without
any price implication. The final drawings of mounting structures shall be submitted to
Medium and high strength structural steels with known properties conforming to any other
national or international standards may also be used.
37.2.2 Bolts
Bolts used shall conform to IS12427 or bolts of property class 4.6 conforming to IS 6639
may also be used.
High strength bolts, if used (only with steel conforming to IS 8500) shall conform to
property class 8.8 of IS 3757. Foundation Bolts shall conform to IS 5624.
Step bolts shall conform to IS 10238
CHAPTER 37: SPECIFICATION FOR DESIGN AND FEBRICATION OF SUBSTATION STEEL STRUCTURES
37.2.3 Nuts
Nuts shall conform to IS 1363 (Part 3). The mechanical properties shall conform to
property class 4 or 5 as the case may be as specified in IS 1367 (Part 6) except that the
proof stress for nuts of property class 5 shall be as given in IS 12427.
37.2.4 Washers
Washers shall conform to IS 2016. Heavy washers shall conform to IS 6610. Spring
washers shall conform to type B of IS 3663
Washers to be used with high strength bolts and nuts shall conform to IS 6649.
37.2.5 Galvanisation
Structural members, plain and heavy washers shall be galvanized in accordance with the
provisions of IS 4759.
Spring washers shall be hot dip galvanized as per service grade 4 of IS 4759 or IS 1537.
37.3.5 Maximum slenderness ratios for leg members, other stressed members and redundant
members for compression force shall be as per IS-802.
37.3.6 Minimum distance from hole center to edge shall be 1.5 x bolt diameter. Minimum distance
between center to center of holes shall be 2.5 x bolt diameter.
37.3.7 All bolts shall be M16 or higher as per design requirement.
37.3.8 Step Bolts: In order to facilitate inspection and maintenance, the structures shall be provided
with climbing devices. Each tower shall be provided with M16 step bolts 175mm long
spaced not more than 450mm apart, staggered on faces on one leg extending from about
0.5 meters above plinth level to the top of the tower. The step bolt shall conform to IS:
10238.
37.4.0 Design Parameters
All structures shall be designed for the worst combination of dead loads, live loads, wind
loads as per code IS:875, seismic forces as per code IS:1893, loads due to deviation of
CHAPTER 37: SPECIFICATION FOR DESIGN AND FEBRICATION OF SUBSTATION STEEL STRUCTURES
conductor, load due to unbalanced tension in conductor, torsional load due to unbalanced
vertical and horizontal forces, erection loads, short circuit forces including “snatch” in
the case of bundled conductors etc. Short circuit forces shall be calculated considering a
fault level of 40 kA, 50kA, 63kA or as applicable. IEC-60865 may be followed for
evaluation of short circuit forces.
All Pipe support structures used for supporting equipments shall be designed for the worst
combination of dead loads, erection load. Wind load/seismic forces, short circuit forces
and operating forces acting on the equipment and associated bus bars as per IS:806. The
material specification shall be as per IS: 1161 read in conjunction with IS: 806.
37.4.1.1 Switchyard structures such as columns, beams and equipment mounting structures shall be
designed as per IS 802 but for loading combinations specified hereunder. Computation of
wind loading on structural members, conductors, insulators, etc and other parameters shall
be as specified in IS 802 except otherwise specified in this Specification.
37.4.1.2 The switchyard structures shall be designed for following loads considered acting
simultaneously:
(i) Wire tension
(ii) Wind Load
(iii) Short Circuit Forces
(iv) Weight of supported wires, insulators, equipment etc and self-weight of structures.
An additional load of 3000 N shall be considered acting for weight of lineman and tools.
For beams this 3000 N load shall be considered acting at middle of the beam.
37.4.1.3 The design shall be checked for following two loading conditions:
37.4.1.4 The design shall be checked for following two loading conditions:
(A) Normal Conditions (all wires intact)
Under this condition, the loads shall be taken as under:
(i) Wire Tension:- Maximum Wire tension as specified in Clause 39.4.3
(ii) Wind Load:- Loads due to 100% Design Wind Pressure (after accounting for drag
coefficient and gust factor) on structures,
wires, insulators, equipment etc. Design wind pressure shall be as per Clause 39.4.2
(iii) Short Circuit Forces: Loading due to a 3 phase short circuit current of 63kA, 50kA, 40 kA
and 31.5 kA shall be considered
for 400kV, 220 KV,132 kV and 33 kV respectively subject to minimum of 10% of maximum
wire tension as considered in
(i) above.
(iv) Dead Weight:- All dead loads mentioned in Clause 39.4.1.2 (iv) shall be considered.
Conductor and shield wire weight shall
Note: Structures with earth peak shall assume to have two earth wires for design purpose in
broken wire condition.
37.4.4 Spans
Following Spans shall be considered in design of all structures as applicable:-
a). Line gantries (structures to terminate lines):
(i) For 400, 220, 132, Switchyard: 200 Meter, wind span
150 Meter, weight span
(ii) For 33 KV Switchyard: 75 Meter, wind & weight span.
b). All other Structures
(i) For 400 KV Switchyard: 75 Meter, wind & weight span
(ii) For 220 KV Switchyard: 75 Meter, wind & weight span
(iii) For 132 KV Switchyard: 50 Meter, wind & weight span
(iv)For 33 KV Switchyard: 20 Meter, wind & weight span.
37.4.5 Deviation Angle
The design of line gantries shall only be checked for a maximum deviation angle of 300 from
normal at center of gantries to Dead End Tower.
B) For protection against direct lightning G.I. wires of size 7/3.66 mm conforming to IS 2241
shall be considered for all switch yards.
Terminal/line take off gantries shall be designed for a minimum conductor tension of 4 metric tonnes
per phase for 400kV, 2 metric tonnes per phase for 220kV and 1 metric tonne per phase for 132 kV or
as per requirements whichever is higher . The distance between terminal gantry and dead end tower
shall be taken as 200 metres for 400/220kV and 100m for 132KV. The design of these terminal
gantries shall also be checked considering +/- 30 deg deviation of conductor in both vertical and
horizontal planes. For other gantries the structural layout requirements shall be adopted in design.
The beams shall be connected with towers/ columns by bolted joints. Wherever luminaries are
proposed to be fixed on gantries, the proper loading for the same shall be considered while designing.
Also holes for fixing the brackets for luminaries should be provided wherever required.
Foundation bolts shall be designed for the loads for which the structures are designed. Height of
Lightning masts shall be as per approved structure layout and designed for diagonal wind condition.
Lightning masts shall be provided with platforms for mounting lighting fixtures and a structural steel
ladder within its base up to the level of platform. The ladder shall be provided with protection rings.
The platforms shall also have protection railing. The details of lighting fixtures would be as per the
approved drawings.
37.5.1.1 The Contractor shall furnish design, drawing and Bill of Materials and shop manufacturing
drawings for every member to the Employer for approval after award of the Contract. The design
drawing should indicate not only profile, but section, numbers and sizes of bolts and details of typical
joints. In case Employer feels that any design drawing, BOM are to be modified even after its
approval, Contractor shall modify the designs & drawings and resubmit the design drawing, BOM as
required in the specification.
37.5.1.2 The fabrication drawings to be prepared and furnished by the Contractor shall be based on
the design approved by the Employer. These fabrication drawings shall indicate complete details of
fabrication and erection including all erection splicing details and typical fabrication splicing details,
lacing details, weld sizes and lengths. Bolt details and all customary details in accordance with
standard structural engineering practice whether or not given by the Employer. The fabrication
drawings shall be submitted to the Employer. Proto shall be made only after approval of fabrication
drawings.
37.5.1.3 Such approval shall, however, not relieve the Contractor of his responsibility for the safety of
the structure and good connections and any loss or damage occurring due to defective fabrication,
design or workmanship shall be borne by the Contractor.
37.5.1.4 The Mass fabrication work shall start only after the final approval to the proto corrected
Fabrication drawing is accorded by the Employer.
37.6.0 ACCESSORIES
39.6.1 Step Bolts
Each column/tower shall be provided with step bolts conforming to IS: 10238 of not less than 16mm
diameter and 175mm long spaced not more than 450mm apart and extending from 0.5 meters above
the plinth level to the top. Each step bolt shall be provided with two nuts on one end to fasten the bolt
CHAPTER 37: SPECIFICATION FOR DESIGN AND FEBRICATION OF SUBSTATION STEEL STRUCTURES
securely to the tower and button head at the other end to prevent the feet from slipping away. The step
bolts shall be capable of withstanding a vertical load not less than 1.5 KN.
The detailed drawing shall be submitted by the Contractor for Employer's approval. The Contractor
shall also supply U- bolts, Dshackles wherever required.
Earth-wire peaks of tension towers shall be provided with suitable plates to accommodate the shackle
of tension clamps. The contractor shall also supply the U-bolts wherever required and take Employer's
approval for details of the attachments before the mass fabrication.
37.7.0 FABRICATION
39.7.1 The fabrication of substation steel structures shall be in conformity with the following:
(i). Except where hereinafter modified, details of fabrication shall conform to IS: 802 (Part-II) or the
relevant international standards.
(ii). The tower structures shall be accurately fabricated to connect together easily at site without any
undue strain on the bolts.
(iii). No angle member shall have the two leg flanges brought together by closing the angle.
(iv). The diameter of the hole shall be equal to the diameter of bolt plus 1.5mm.
(v). The structure shall be designed so that all parts shall be accessible for inspection and cleaning.
Drain holes shall be provided at all points where pockets of depression are likely to hold water.
(vi). All identical parts shall be made strictly inter-changeable. All steel sections before any work are
done on them shall be carefully levelled, straightened and made true to detailed drawings by methods
which will not injure the materials so that when assembled, the adjacent matching surfaces are in
close contact throughout. No rough edges shall be permitted in the entire structure.
37.8.1 Foundation bolts for the towers and equipment supporting structures and elsewhere shall be
embedded in first stage concrete while the foundation is cast. The Contractor shall ensure the proper
alignment of these bolts to match the holes in the base plate.
37.8.2 The Contractor shall be responsible for the correct alignment and levelling of all steel work on
site to ensure that the towers/structures are plumb.
37.8.3 All foundation bolts for lattice structure, pipe structure is to be supplied by the Contractor.
37.8.4 All foundation bolts shall be fully galvanised so as to achieve 0.61 kg. per Sq.m. of Zinc
Coating as per specifications.
37.8.5 All foundation bolts shall conform to IS 5624 but the material, however shall be MS
conforming to IS: 2062.
37.9.0 GALVANIZING AND PAINTING
37.9.1 Galvanising of the various members of the structures shall be done only after all works of
sawing, shearing, drilling, filing, bending and matching are completed. Galvanising shall be done by
the hot dip process as recommended in IS: 2629 or other such authoritative international standards and
shall produce a smooth, clean and uniform coating of not less than 610 gm per square meter. The
preparation for galvanising and the galvanising process itself must not affect adversely the mechanical
properties of the treated materials.
37.9.2 All assembly bolts shall be thoroughly hot dip galvanized after threading. Threads shall be of a
depth sufficient to allow for the galvanized coating, which must not be excessive at the root of the
threads, so that the nut shall turn easily on the completed bolts without excessive looseness. The nut
threads shall not be galvanized, but oiled only.
37.9.3 The outside surface shall be galvanised. Sample of galvanised materials shall be supplied to the
galvanising test set out in IS 729 or other such authoritative international standards.
37.10 EARTHING
39.10.1 To keep provision in the structures for earthing, holes shall be drilled on two diagonally
opposite legs of the towers/columns/mounting structures. The holes shall be suitable for bolting GI
strips of size mentioned elsewhere in this specification (Vol II) and shall be such that the lower hole is
about 350 mm above the ground level, clear of the concrete muffing, for connecting the earthing strip.
assembled on a foundation as nearly similar as practicable to site and tested with suitable test loads as
per specified broken wire condition, multiplied by the corresponding factor of safety to ensure that the
design and fabrication complies with the requirements. Each structure shall be capable of
withstanding the above-mentioned tests without any injury or any permanent deflection at any part. If
any member is found to be weak or damaged the design should be suitably modified and the tower re-
tested.
37.11.2.2 After the first lot of the structures manufactured, the members forming one structure of each
type shall be selected at random from the lots of similar member and assembled in exactly the same
manner as to be done at site. The structure then shall be set on foundation as nearly similar as
practicable to site and tested with equivalent test load for which the structure has been designed.
37.11.2.3 No structure or any member thereof, which failed under the test shall be supplied.
Section 1
1.1 GENERAL INFORMATION
The material covered in this specification shall be used in route length of 6km in 220KV Alipurduar – Salakati
(PGCIL) D/C LILO at Agomoni, 1.5km of Bus Augmentation at Gossaigaon 132kV GSS (existing) and
0.252km of bus augmentation at Shankardevnagar 132kV GSS (existing).
1.2 SCOPE
The scope of work covered under package shall include complete Project Management, Design, Engineering,
Type Testing, Manufacture, Transportation to Site, Insurance, Storage, Erection, Testing & Commissioning
De-Stringing/Dismantling as detailed below on single source responsibility.
1.2.1
a) The supply of major equipments includes:
i. High Temperature Low Sag (HTLS) conductor with Composite Carbon Core.
ii. Hardware fittings suitable for offered HTLS conductor.
iii. Clamps & connectors for Hardware fittings suitable for offered HTLS conductor.
iv. Accessories for HTLS conductor.
h) The rates quoted shall include minor details which obviously and fairly intended and which may not have been
included in these documents but are essential for the satisfactory completion of the various works.
1.2.2 It is also responsibility of the Contractor to obtain any road permits and any other permits or licenses to execute
the works.
1.2.3 Dismantling of existing ACSR panther and ACSR Zebra conductor of all the circuits, re rolling on empty
drums, removing of hardware fittings, insulators and accessories, loading and unloading, transportation to
AEGCL store shall be carried out by the contractor.
1.2.4 Dismantling of existing clamps and connectors from Gantry to Bus bar of the respective bays at both end of the
substations and re-connection of clamps & connectors suitable for HTLS conductor shall be carried out for
the bays of the above transmission lines and substation buses. Design, Manufacture, testing at manufacturer’s
works, supply and erection of connectors, clamps and other accessories suitable for offered HTLS conductor
shall be carried out by the transmission line contractor under supervision of HTLS conductor supplier.
2
1.5 TYPE TEST REPORTS
1.5.1 HTLS conductors with composite carbon core and related Hardware fittings which have never been
tested for critical performance shall not be accepted. In such cases, a promise or agreement by a bidder to
have the equipment tested after award of a contract is not acceptable.
1.5.2 All Bids must be accompanied by the full Type Test Certificates of equipment offered. Such type test
certificates shall be acceptable only if: -
Tests are conducted in an independent and well-known testing laboratory, or
Tests are conducted in manufacturer’s own laboratory. In this case the laboratory must have ISO 9000 (or its
equivalent) series certification
1.5.3 Test reports to be acceptable must be related directly to the materials offered.
1.5.4 Type Test Reports older than five (5) years on the date of Technical bid opening shall not be accepted.
1.6 GUARANTEED TECHNICAL PARTICULARS
1.6.1 The Guaranteed Technical Particulars of the various items shall be furnished by the Bidders in the
prescribed Schedules of the Section with the Technical Bid. The Bidder shall also furnish any other
information's as in their opinion is needed to give full description and details to judge the item(s) offered by
them.
1.6.2 The data furnished in Guaranteed Technical Particulars should be the minimum or maximum value (as
per the requirement of the specification) required. A Bidder may guarantee a value more stringent than the
specification requirement. However, for testing purpose or from performance point of view, the material
shall be considered performed successfully if it achieves the minimum/maximum value required as per the
technical specification. No preference what so ever shall be given to the bidder offering better/more stringent
values than those required as per specification except where stated otherwise.
1.7 DRAWINGS
1.7.1 All drawings submitted by the Supplier including those submitted at the time of bid shall be in
sufficient detail to indicate the type, size, arrangement, dimensions, material description, Bill of Materials,
weight of each component, break-up for packing and shipment, fixing arrangement required, the dimensions
required for installation and any other information specifically requested in the Specifications.
1.7.2 Each drawing submitted by the Supplier shall be clearly marked with the name of the Owner, the unit
designation, the Specification title, the Specification number and the name of the Project. All titles, noting,
markings and in writings on the drawing shall be in English. All the dimensions should be to the scale and in
metric units.
1.7.3 The drawings submitted by the Supplier shall be reviewed by the Owner as far as practicable and
shall be modified by the Supplier if any modifications and/or corrections are required by the Owner in
compliance with Specifications. The Supplier shall incorporate such modifications and or corrections and
submit the final drawings for approval. Any delays arising out of failure by the Supplier to rectify the
drawings in good time shall not alter the Contract completion date.
1.7.4 The drawings shall be submitted for approval to the Owner.
1.7.5 Further, work by the Supplier shall be strictly in accordance with these drawings and no deviation shall
be permitted without the written approval of the Owner, if so required.
1.7.6 All manufacturing and fabrication work in connection with the equipment/material prior to the
approval of the drawings shall be at the Supplier’s risk.
1.11.3 The Owner or his duly authorised representatives reserves the right to carry out Quality Audit and
quality surveillance of the systems and procedures of the Supplier’s/his vendor’s Quality Management and
Control Activities.
TECHNICAL SPECIFICATION OF HTLS CONDUCTOR
WITH COMPOSITE CARBON CORE
2.1.1 The offered HTLS Conductor with composite carbon core which is wrapped with trapezoidal shaped
aluminium strands shall be capable of providing the specified maximum ampacity of 1700Amperes at a
continuous operating conductor temperature higher than that of not exceeding the maximum permissible
operating temperature for continuous operation of the offered HTLS Conductor and without exceeding the
level of maximum permissible sag as prescribe in clause no 2.1.6. and 2.2.
The physical and operating performance requirements of the transmission line with type HTLS conductor are
mentioned below. The bidder shall offer HTLS conductor complying with the specified requirements. The
Bidder shall indicate particulars of the proposed conductor in the relevant GTP schedule of BDS along with
calculations to establish compliance with the specified requirements.
2.1.2 Maximum Conductor sag for 325m (132kV) and 350m (220kV) span at steady state conductor
temperature and no wind corresponding to 50 Hz alternating current of 1700 Amperes per conductor under
ambient conditions specified at clause no. 2.1.1 will be such that the statutory ground clearance will be
maintained throughout the route keeping (erection) tension at 25% of UTS of conductor.
2.1.3 The calculations for Ampacity shall be based on IEEE Standard 738. The bidder in his bid shall
furnish calculations for the ampacity based on the above Standard for the proposed HTLS conductor.
2.1.4 The design of conductor shall be suitable for operation at a steady state conductor temperature
experienced for AC current flow of 1600 Amperes under the above ambient conditions based on ampacity
calculations mentioned above. The bidder shall also indicate the maximum permissible conductor
temperature for continuous operation without any deterioration of its electrical, mechanical & metallurgical
properties. The bidder shall also furnish the maximum permissible conductor temperature for short-term
operations including permissible duration of such short-term operation.
2.1.5 Each conductor / sub conductor in the bundle of HTLS conductor shall be suitable to carry minimum
specified 50 Hz alternating current 1700 Amperes of 50 Hz alternating current under the ambient conditions
& maximum conductor sag specified below while satisfying other specified technical requirements/
parameters as mentioned in the Service condition above.
2.1.6 Maximum permissible conductor sag for 325 m (132kV AAAC Panther) and 350 m (220kV AAAC
Zebra) span conductor at 85 ◦C operating temperature and nil wind corresponding to 50 Hz and at maximum
alternating current 518 (132kV) amp and 725 (220kV) amp per conductor under ambient conditions
specified above = 7.8m (132kV) and 8.4m (220kV). In case of HTLS conductor, the maximum sag for
permissible conductor temperature and nil wind for continuous operation shall not be considered more than
7.8m (132kV) and 8.4m (220kV). The bidder shall also furnish the maximum permissible conductor
temperature for short term operations including permissible duration of such short-term operation.
2.1.7 The bidder shall indicate the technical particulars and details of the construction of the conductor
in the relevant schedule of GTP. The bidder shall also guarantee the DC resistance of conductor at 20
deg C and AC resistance at the calculated temperature corresponding to 50Hz alternating current flow
of 1700 amperes at specified ambient conditions (maximum continuous operating temperature).
The bidder shall submit the supporting calculations for the AC resistance at 1600 Amperes and at 800
Amperes indicating details & justifications of values of temperature coefficient of resistance & DC to
AC resistance conversion factor(s) with due reference to construction / geometry of the conductor.
2.2.1 The HTLS conductor shall meet the following sag tension requirements for ruling span of 325m
(132kV) and 350 meters (220kV)
Sag-Tension calculation for HTLS conductor can be carried out by using PLSCAD. Following values shall
be considered for the purpose of sag-tension calculations:-
(i) Final values of modulus of elasticity of Aluminium/ Aluminium alloy/core, Coefficient of Linear
Expansion of Aluminium/ Aluminium alloy/ core, Stress-Strain coefficients & Creep coefficients of
aluminium/ Aluminium alloy/ core in the cable data (.wir file) used for calculation of sag in PLSCAD
shall be based on either of the following:
a) Existing ‘.wir’ files for offered conductor as available on PLS website.
b) A file derived from existing standard file for conductor of equivalent/ near equivalent stranding.
c) A file derived from type test conducted on conductor of same stranding.
In each of the above cases, proper justification in the form of test reports/ calculations/ print out of ‘.wir’
file as available on PLS website, etc. shall be required to be submitted during detailed engineering.
(ii) PLSCAD Sagging criteria/conditions shall be based on the sag tension limits specified above and shall be
carried out in a manner that the above mentioned sag tension limits are met in ‘After Creep’ as well as in
‘After Load’ condition.
2.2.2 Survey & profiling of existing line route using Total stations, verification of availability of
statutory electrical clearances using PLS-CADD software.
Sag-Tension calculations at various conditions mentioned above using parabolic equations shall be
submitted along with the bid. These calculations shall also include calculations for determination of
transition/knee point temperature. The bidder must use PLS-CADD software for sag tension
calculations.
2.2.3 The bidder shall also furnish sag & tensions under no wind for various temperatures starting from
0 deg C to maximum continuous operating temperature in steps of 5 deg C.
2.2.4 After award of the contract, the Supplier shall submit Sag-Tension calculations corresponding to
various conditions given above for all the spans as per detailed survey and spans ranging from 50 m to
1100 m in intervals of 50 m.
Besides above, the Supplier shall also furnish details of creep characteristics in respect of HTLS
conductor based on laboratory investigations/ experimentation (creep test as per IEE1138 or IEC
61395) conducted on similar type of conductor and shall indicate creep strain values corresponding to 1
month, 6 month, 1 year, 10 years & 20 years creep at everyday tension & at maximum continuous
operating temperature as well as room temperature.
Average ohmic losses (kW)= Loss load factor X 3 X Line length X no. of sub conductors per bundle X
(continuous operating current)2 X AC resistance per km guaranteed by the bidder at temperature
corresponding to continuous operating current under normal condition.
On testing, if it is found that actual losses are more than the values, quoted in the bid, undisputed
liquidated damages shall be recovered from the supplier at the following rates.
For fractional Kilowatt, penalties shall be applied on pro-rata basis. No bonus shall be payable for loss,
which are less than those, stated in the GTP.
2.4 Workmanship:
All the conductor strands shall be smooth, uniform and free from all imperfections, such as spills and
splits, cracks, die marks, scratches, abrasions, rust etc.
The finished conductor shall be smooth, compact, uniform and free from all imperfections
including kinks (protrusion of wires), wire cross over, over riding, looseness (wire being dislocated by
finger/hand pressure and/or unusual bangle noise on tapping), material inclusions, white rust, powder
formation or black spot (on account of reaction with trapped rain water etc.), dirt, grit etc.
2.5.2 No joints shall be permitted in the individual wires in the outer most layer of the finished
conductor. However, joints are permitted in the inner layer(s) of the conductor unavoidably broken
during stranding provided such breaks are not associated with either inherently defective wire or with
the use of short lengths of Aluminium Alloy wires. Such joints shall not be more than four (4) per
conductor length and shall not be closer than 15 meters from joint in the same wire or in any other
Aluminium Alloy wire of the completed conductor. A record of such joints for each individual length
of the conductor shall be maintained by The Contractor for Owners review.
2.5.3 Joints shall be made by cold pressure butt welding and shall withstand a stress of not less than the
breaking strength of individual strand guaranteed.
2.5.5 Tolerances
Manufacturing tolerances on the dimensions to the extent of one percent (±1%) shall be permitted for
individual strands and the complete conductor.
2.6 Materials
The materials used for construction of the conductor shall be such that the conductor meets the
specified technical and performance requirements.
After survey of the involved section of the line by tower contractor, the supplier shall determine the
most appropriate individual conductor lengths to be manufactured and supplied keeping in view tower
schedules, section lengths, special crossings etc. and the drum schedules shall be submitted to the
owner for review and approval.
The standard length of the conductor shall be indicated by the bidder in the guaranteed technical
particulars of offer. A tolerance of +/-5% on the standard length offered by the Bidder shall be
permitted. However, during execution cut lengths shall be acceptable matching with Tower Schedule
and allowable wastage of 1% added. Standard Length shall not more than 2500 meters. All lengths
outside this limit of tolerance shall be treated as random lengths.
Random lengths will be accepted provided no length is less than 70% of the standard length
and the total quantity of such random lengths shall not be more than 10% of the total quantity ordered.
When one number random length has been manufactured at any time, five (5) more individual lengths
each equivalent to the above random length with a tolerance of +/- 5% shall also be manufactured and
all the above six random lengths shall be dispatched in the same shipment. At no point, the cumulative
quantity supplied of such random lengths shall not be more than 12.5% of the total cumulative quantity
supplied including such random lengths. However, the last 20% of the quantity ordered shall be
supplied only in standard lengths as specified.
Bidder shall also indicate the maximum single length, above the standard length, he can
manufacture in the guaranteed technical particulars of offer. This is required for special stretches like
river crossing etc. The Employer reserves the right to place orders for the above lengths on the same
terms and conditions applicable for the standard lengths during the pendency of the Contract.
2.8.1 The installation & stringing of the offered HTLS conductor for the above transmission lines and
substation buses shall be carried out by the transmission line contractor under supervision of the HTLS
conductor supplier or Qualified Bidder itself. Bidder’s responsibility is to provide Sag-Tension chart
based on existing site conditions. It may be noted that AEGCL will not consider any modifications
(tower extensions etc) on existing tower/span.
2.8.2. The bidder’s engineers are to supervise whether appropriate safety measures along with
necessary safety tools and equipment’s to carry out stringing operations including mechanical/
structural safety of the towers, are maintained or not.
The following tests shall be conducted once on sample/samples of conductor from each manufacturing
facility:
Type tests specified under clause no. 2.9.1 shall not be required to be carried out if a valid test
certificate is available for the offered design, i.e., tests conducted earlier (not more than 5 years old at
the time of bid opening) and should have been conducted in accredited laboratory (accredited based on
ISO/IEC guide 25/17025 or EN 45001 by the National Accreditation body of the country where
laboratory is located) or witnessed by the representative (s) of CTU or State Transmission Utility.
In the case of composite core conductors, the tests specified under clause 2.9.1 shall be carried out before
stranding on as manufactured sample.
In the event of any discrepancy in the test report (i.e., any test report not applicable due to any design/
material/manufacturing process change including substitution of components or due to non-
compliance with the requirement stipulated in the Technical Specification) the tests shall be conducted
by the Contractor at no extra cost to the Employer/ Employer/ Employer.
As indicated in Clause no 2.9.1, no type test charges shall be payable to the supplier.
Bidder shall indicate the laboratories in which they propose to conduct the type tests. They shall ensure that
adequate facilities are available in the laboratories and the tests can be completed in these laboratories within
the time schedule guaranteed by them.
In case of failure in any type test the Supplier is either required to manufacture fresh sample lot and repeat
the entire test successfully once or repeat that particular type test three times successfully on the sample
selected from the already manufactured lot at his own expenses. In case a fresh lot is manufactured for
testing then the lot already manufactured shall be rejected.
The entire cost of testing for the acceptance and routine tests and Tests during manufacture as well as
type tests, if required, specified herein shall be treated as included in the quoted unit price of conductor,
except for the expenses of the inspector/Owner's representative.
In case of failure in any type test, if repeat type tests are required to be conducted, then all the expenses for
deputation of Inspector/Owner's representative shall be deducted from the contract price. Also, if on receipt
of the Supplier's notice of testing, the Owner's representative does not find material/ testing facilities to be
ready for testing the expenses incurred by the Owner for re-deputation shall be deducted from contract
price.
The Supplier shall intimate the Employer about carrying out of the type tests along with detailed
testing program at least 3 weeks in advance (in case of testing in India) and at kleast 6 weeks in
advance (in case of testing abroad) of the schedule date of testing during which the Owner will arrange
to depute his representative to be present at the time of carrying out the tests.
2.10.2. The Owner also reserves the right to conduct all the tests mentioned in this specification at his
own expense on the samples drawn from the site at Supplier’s premises or at any other test centre. In
case of evidence of non compliance, it shall be binding on the part of Supplier to prove the compliance
of the items to the technical specifications by repeat tests, or correction of deficiencies, or replacement
of defective items all without any extra cost to the Owner.
The Supplier shall offer material for selection of samples for type testing only after getting Quality
Assurance Plan approved from Owner’s Quality Assurance Deptt. The sample shall be manufactured strictly
in accordance with the Quality Assurance Plan approved by Owner.
The Supplier shall offer at least three drums for selection of sample required for conducting all the type test.
The Supplier is required to carry out all the acceptance tests successfully in presence of Owner’s
representative before sample selection.
2.11Test Reports
Copies of type test reports shall be furnished in at least three copies along with one original. One copy will
be returned duly certified by the Owner only after which the commercial production of the material shall
start.
Record of routine test reports shall be maintained by the Supplier at his works for periodic inspection
by the Employer’s representative.
Test Certificates of tests during manufacture shall be maintained by the Supplier. These shall be
produced for verification as and when desired by the Employer.
2.12 Inspection
The Employer’s representative shall at all times be entitled to have access to the works and all places of
manufacture, where conductor shall be manufactured and representative shall have full facilities for
unrestricted inspection of the Supplier’s works, raw materials and process of manufacture for
conducting necessary tests as detailed herein.
The Supplier shall keep the Employer informed in advance of the time of starting and of the progress of
manufacture of conductor in its various stages so that arrangements can be made for inspection.
No material shall be dispatched from its point of manufacture before it has been satisfactorily inspected
and tested, unless the inspection is waived off by the Employer in writing. In the latter case also, the
conductor shall be dispatched only after satisfactory testing for all tests specified herein have been
completed.
The acceptance of any quantity of material shall in no way relieve the Supplier of any of his
responsibilities for meeting all requirements of the Specification, and shall not prevent subsequent
rejection if such material is later found to be defective.
The following additional test facilities shall be available at the Supplier’s works:
a) Calibration of various testing and measuring equipment including tensile testing machine, resistance
measurement facilities, burette, thermometer, barometer etc.
b) Standard resistance for calibration of resistance bridges.
c) Finished conductor shall be checked for length verification and surface finish on separate rewinding
machine at reduced speed (variable from 8 to 16 meters per minute). The rewinding facilities shall have
appropriate clutch system and free of vibrations, jerks etc. with traverse laying facilities.
2.14 Packing
The conductor shall be supplied in non-returnable, strong, wooden/painted steel/hybrid (painted steel
cum wood) drums provided with lagging of adequate strength, constructed to protect the conductor against all
damage and displacement during transit, storage and subsequent handling and stringing operations in the field.
The Supplier shall select suitable drums for supply of conductor and shall be responsible for any loss or
damage to conductor and/or drum during transportation handling and storage due to improper selection of
drum or packing. The drums shall be suitable for wheel mounting and for letting off the conductor under a
minimum controlled tension of the order of 5 kN.
The Bidder should submit their proposed drum drawings along with the Bid.
a. One standard conductor length only shall be wound on each drum.
b. The conductor ends shall be properly sealed and secured on the side of one of the flanges to avoid
loosening of the conductor layers during transit and handling.
c. All wooden components shall be manufactured out of seasoned soft wood free from defects that may
materially weaken the component parts of the drums. Preservative treatment shall be applied to the entire
drum with preservatives of a quality which is not harmful to the conductor.
d.The flanges shall be of two ply construction with each ply at right angles to the adjacent ply and nailed
together. The nails shall be driven from the inside face flange, punched and then clenched on the outer face.
The thickness of each ply shall not vary by more than 3mm from that indicated in the figure. There shall be at
least 3 nails per plank of ply with maximum nail spacing of 75mm. Where a slot is cut in the flange to receive
the inner end of the conductor the entrance shall be in line with the periphery of the barrel.
e. The wooden battens used for making the barrel of the conductor shall be of segmental type. These shall be
nailed to the barrel supports with at least two nails. The battens shall be closely butted and shall provide a
round barrel with smooth external surface. The edges of the battens shall be rounded or chamfered to avoid
damage to the conductor.
f. Barrel studs shall be used for the construction of drums. The flanges shall be holed and the barrel supports
slotted to receive them. The barrel studs shall be threaded over a length on either end, sufficient to
accommodate washers, spindle plates and nuts for fixing flanges at the required spacing.
g. Normally, the nuts on the studs shall stand protruded of the flanges. All the nails used on the inner surface
of the flanges and the drum barrel shall be counter sunk. The ends of barrel shall generally be flushed with the
top of the nuts.
h. The inner cheek of the flanges and drum barrel surface shall be painted with a bitumen based paint.
i. Before reeling, card board or double corrugated or thick galvanized water-proof bamboo paper shall be
secured to the drum barrel and inside of flanges of the drum by means of a suitable commercial adhesive
material. After reeling the conductor, the exposed surface of the outer layer of conductor shall be wrapped
with water proof thick galvanized bamboo paper to preserve the conductor from dirt, grit and damage
during transport and handling.
j. A minimum space of 75 mm for conductor shall be provided between the inner surface of the external
protective tagging and outer layer of the conductor.
k. Each batten shall be securely nailed across grains as far as possible to the flange, edges with at least 2 nails
per end. The length of the nails shall not be less than twice the thickness of the battens. The nails shall not
protrude above the general surface and shall not have exposed sharp, edges or allow the battens to be released
due to corrosion.
l. The nuts on the barrel studs shall be tack welded on the one side in order to fully secure them. On the second
end, a spring washer shall be used.
m. A steel collar shall be used to secure all barrel studs. This collar shall be located between the washers and
the steel drum and secured to the central steel plate by welding.
n. Outside the protective lagging, there shall be a minimum of two binders consisting of hoop iron/ galvanized
steel wire. Each protective lagging shall have two recesses to accommodate the binders.
o. As an alternative to wooden drum, Bidder may also supply the conductors in returnable/ non-returnable
painted steel drums. After preparation of steel surface according to IS:9954, synthetic enamel paint shall be
applied after application of one coat of primer. Wooden/Steel drum will be treated at par for evaluation
purpose and accordingly the Bidder should quote in the package.
2.15 Marking
Each drum shall have the following information stenciled on it in indelible ink along with other
essential data:
a. Contract/Award letter number.
b. Name and address of consignee.
c. Manufacturer’s name and address.
d. Drum number
e. Size of conductor
f. Length of conductor in meters
g. Arrow marking for unwinding
h. Position of the conductor ends
i. Distance between outer-most Layer of conductor and the inner surface of lagging.
j. Barrel diameter at three locations & an arrow marking at the location of the measurement.
k. Number of turns in the outer most layer.
l. Gross weight of drum after putting lagging.
m. Tear weight of the drum without lagging.
n. Net weight of the conductor in the drum.
o. CIP/MICC No.
2.16 Service centre in India: If any manufacturer is from outside INDIA, they must have their service
centre and calibration facilities in India.
The Employer reserves the right to verify the length of conductor after unreeling at least ten (10) percent of
the drums in a lot offered for inspection.
2.18 Standards (Whichever applicable to Annealed Al. non-metallic solid core HTLS Conductor)
The conductor shall conform to the following Indian/International Standards, which shall mean latest
revisions, with amendments/changes adopted and published, unless specifically stated otherwise in the
Specification.
In the event of the supply of conductor conforming to standards other than specified, the Bidder shall
confirm in his bid that these standards are equivalent to those specified. In case of award, salient features of
comparison between the standards proposed by the Supplier and those specified in this document will be
provided by the Supplier to establish their equivalence.
Sl. International
No. Indian Title Standard
Standard
1. IS: 209-1992 Specification for zinc BS:3436-1986
2. IS: 398-1982 Specification for Aluminium Conductors IEC:1089-1991
for Overhead Transmission Purposes BS:215-1970
3. IS:398-1990 Aluminum Conductor Galvanised Steel BS;215-1970
Part-II Reinforced IEC:1089-1991
4. IS:398-1992 Aluminum Conductor Galvanised Steel-
Part-V Reinforced for Extra High Voltage (400 IEC:1089-1991
KV) and above BS:215-1970
5. IS : 1778-1980 Reels and Drums for Bare Conductors BS:1559-1949
6. IS : 1521-1991 Method of Tensile Testing of Steel Wire ISO 6892-1984
7. IS : 2629-1990 Recommended Practice for Hot Dip
Galvanising of Iron and Steel
8. Method of Testing Uniformity of
IS : 2633-1992 Coating on Zinc Coated Articles
9. IS : 4826-1992 Hot dip Galvanised Coating on Round IEC : 888-1987
Steel Wires BS:443-1969
10. IS : 6745-1990 Methods of Determination of Weight of BS:433-1969 ISO
Zinc Coating of Zinc Coated Iron and 1460 - 1973
Steel Articles
11. Method of Radio Interference Tests on IEC:437-1973
IS : 8263-1990 High Voltage Insulators NEMA:107-1964
CISPR
12. IS : 9997-1988 Aluminium Alloy Redraw Rods IEC 104 - 1987
13. Zinc Coated steel wires for stranded
Conductors IEC : 888-1987
14. Hard drawn Aluminium wire for
overhead line conductors IEC : 889-1987
IEC : 208-1966
15. IS:398 (Part-IV) Aluminium Alloy stranded conductor BS-3242-1970
16. Aluminium clad steel wires IEC:1232
Method of measurement of
17. resistivity of metallic materials IEC:468
18 Standard for calculating the current- IEEE738
temperature relationships of bare
overhead conductor
19. Design Validation Tests on Composite ASTM B987
Core
ANNEXURE –A
Tests on Conductors
1) Tests on Conductor (Whichever applicable to Annealed Al. non-metallic solid core HTLS Conductor)
Circles perpendicular to the axis of the conductor shall be marked at two places on a sample of
conductor of minimum 5 m length between fixing arrangement suitably fixed by appropriate fittings on
a tensile testing machine. The load shall be increased at a steady rate upto 50% of minimum specified
UTS and held for one minute. The circles drawn shall not be distorted due to relative movement of
strands. Thereafter the load shall be increased at steady rate to minimum UTS and held for one minute.
The Conductor sample shall not fail during this period. The applied load shall then be increased until the
failing load is reached and the value recorded.
The test is to be conducted at ambient temperature, between minimum and maximum ambient
temperature of 0 deg C and 50 deg C respectively.
b) at elevated temperature:
UTS Test on Stranded Conductor shall be conducted as per clause no. 1.1(a) specified above keeping
conductor temperature at the designed maximum temperature.
Two samples of conductor of minimum 5m length strung in horizontal twin bundle configuration with
required spacing between sub-conductors when subjected to 50Hz power frequency voltage shall have a
corona extinction voltage of not less than 154 kV rms line to ground under dry condition. There shall be no
evidence of corona on any part of the sample. The test should be conducted without corona control rings.
However, small corona control rings may be used to prevent corona in the end fittings. The atmospheric
condition during testing shall be recorded and the test results shall be accordingly corrected with suitable
correction factor as stipulated in IS:731- 1971
Stress-strain test as per IEC-1089 shall be conducted keeping conductor temperature at designed
maximum temperature. UTS for this test shall be 80% of the UTS guaranteed in the GTP.
Two conductor samples of length equal to at least 100 X d + 2 X a (where, d is the conductor diameter
and a is the distance between the end fitting and the gauge length) shall be strung at tension equal to 25
% of conductor UTS. The distance, a, shall be at least 25 % of the gauge length or 2 m whichever is the
smaller. The conductor samples shall be subjected to tests as indicated below:
I) On one of the conductor samples, the conductor temperature shall be maintained at 20 deg C for
1000 hours. The elongation/creep strain of the conductor during this period shall be measured
and recorded at end of 1 hour, 10-hour, 100 hour and subsequently every 100-hour upto 1000
hours’ time period.
II) (On other conductor sample, the conductor temperature shall be increased to design maximum
temperature in steps of 20 deg. C and thermal elongation of the conductor sample shall be mea-
sured & recorded at each step. The temperature shall be held at each step for sufficient duration
for stabilization of temperature. Further, the temperature of the conductor shall be maintained at
maximum continuous operating temperature (+10 Deg. C) for 1000 hours. The elongation/creep
strain of the conductor during this period shall be measured and recorded at end of 1 hour, 10-
hour, 100 hour and subsequently every 100-hour upto 1000 hours’ time period. After comple-
tion of the above, the core of the conductor sample shall be subjected to UTS test as mentioned
above at clause 1.1 of Annexure-A. The conductor core shall withstand a load equivalent to 95
% of UTS. In case of polymer composite core conductor, the flexural strength & glass transition
temperature of the core shall also be evaluated and the same shall not be degraded by more than
10 % over the initial value. The supplier shall plot the thermal elongation with temperature.
The supplier shall furnish details of creep characteristic in respect of the conducted based
on laboratory test and other laboratory investigations/ experimental conducted on similar type of
conductor and shall indicate creep strain values corresponding to 1 month, 6 month, 1 year, 10
year & 20 year creep at everyday tension & continuous designed temperature as well as room
temperature.
The conductor sample of minimum length of 35 meter shall be tensioned at 25 % of the UTS and shall
be passed through pulleys having diameter of 32 times that of the conductor with angle of 20 deg.
between the pulleys. The conductor shall be passed over the pulleys 36 times a speed of 2 m/sec. After
this test UTS test on the conductor shall be carried out. The core shall be inspected for any sign of
damage or cracking through dye penetration test as per ASTM D5117.
The conductor sample shall be suspended vertically and load applied by dropping a 650 Kg from an
elevation of 4 meters above the sample. The impact velocity shall be not be less than 8 m/sec. with an
initial pre-tension of 200 kg. The curve for load vs time shall be recorded and recorded load of failure
for core shall not be less than UTS of core.
The conductor sample of 10-15 m shall be loaded to 25% of UTS and then rotated in increasing steps of
+/-180 deg. In case of composite core conductors, after 4 rotations or after separation of aluminium
strands, the aluminium wires shall be cut and removed from the conductor and the exposed core shall be
twisted and shall withstand upto 16 rotations.
The conductor and supporting hardware shall be loaded to 25% of RTS. A dynamometer, load cell,
calibrated beam or other device shall be used to measure the conductor tension. Some means should be
provided to maintain constant tension to allow for temperature fluctuations during the testing. The
overall span between system terminations shall be a minimum of 30 m. The span shall be supported at a
height such that the static sag angle of the cable to horizontal is (1.5 + 0.5) deg in the active span. Means
shall be provided for measuring and monitoring the mid-loop (antinode) vibration amplitude at a free
loop, not a support loop. An electronically controlled shaker shall be used to excite the conductor in the
vertical plane. The shaker armature shall be securely fastened to the conductor so it is perpendicular to
the conductor in the vertical plane. The shaker should be located in the span to allow for a minimum of
six vibration loops between the suspension assembly and the shaker.
The test shall be carried out at one or more resonance frequencies (more than 10 Hz). The amplitude at
the antinode point shall be one third of conductor diameter. The assembly shall be vibrated for not less
than 10 million cycles without any failure. After the test, the conductor should not exhibit any damage
(broken strands). The conductor shall be tested to demonstrate that it retains at least 95% RTS.
The purpose of this test is verification of degradation characteristics of metallic and non-metallic
material when subjected to thermal cycling temperature cycling can create large internal stresses due to
thermal expansion mismatch between constituents.
Test Methods: -
Mechanical tension, 20 % UTS, marks on the conductor at the edge of the conductor.
100 cycles from room temperature up to maximum temperature. Hold at design maximum temperature +
2.5 deg. C for 5 minutes.
After the above mentioned 100 cycles, the mechanical tension shall be increased up to 70 % UTS at
room temperature and kept at this tension for 24 H. Thereafter release to 20 % UTS.
This cycling test shall be repeated 5 times.
During the test, temperature of connectors, conductor and resistance are recorded according to ANSI C
119.
A breaking load test is applied at the end of the test. Conductor strength has to be higher than 95% UTS.
In case of polymer composites, the flexural strength should not degrade by more than 10 % and the Glass
Transition temperature shall not degrade by more than 10 % after thermal cycling. Flexural strength shall be
obtained on the basis of test procedure indicated below.
A sample of aluminium clad invar strand measuring 30 cm in length shall be subject to bending with
help of a vise. The vised length of wire should be 5 cm and radius of bend 4.8 mm. The bending should
be first 90 degrees left and 90-degree right. After this operation the strand should cut at the bending
point. There should be no separation of core and aluminium at the bending point after this operation.
1.15 Compression test on aluminium clad wires (if applicable)
A sample of aluminium clad core strand 10 mm in length is to be compressed by a plate with a load of
3600 kgs. The aluminium and core strand should not break.
The temperature and elongation on a sample shall be continuously measured and recorded at interval of
approximately 15 degree C from 15 degree C to maximum continuous operating temperature
corresponding to rated current 1700Amps by changing the temperature by suitable means. Coefficient of
linear expansion shall be determined from the measured results.
1.17 Strand Brittle fracture test (for polymer composite core only)
The sample shall be tensioned to approx. 25 % of UTS with simultaneous application of 1NHNO3 acid
directly in contact with naked polymer composite core for 96 hrs. The contact length of acid shall not be less
than 40mm and thickness around the core not less than 10mm. The rod shall withstand 80% of SML for
96 hours. The rod shall withstand UTS test after 96 hours.
The drums shall be visually and dimensionally checked to ensure that they conform to the approved
drawings.
Conductor drums shall be rewound in the presence of the Employer. The Employer shall visually check
for scratches, joints etc. and that the conductor generally conform to the requirements of this
Specification. Ten percent (10%) drums from each lot shall be rewound in the presence of the
Employer's representative.
1.20 Dimensional Check on Core Wires and Aluminium/ Aluminium Alloy Wires
The individual strands shall be dimensionally checked to ensure that they conform to the requirement of
this Specification.
The test procedure shall be as specified in IEC: 888. The material shall conform to the requirements of
this Specification. The adherence of zinc shall be checked by wrapping around a mandrel four times the
diameter of steel wire.
The thickness of aluminium of the specimen shall be determined by using suitable electrical indicating
instruments operating on the direct measurement. Measurements shall be read to three decimal places,
and number rounded to two decimal places is considered as measured thickness. For reference purposes,
direct measurement shall be used to determine aluminium thickness on specimens taken from the end of
the coils.
In case of composite core HTLS conductor, the following procedure shall be applicable: -
Elongation Test: - The elongation of the composite core sample at shall be determined using extensometer.
The load along the core shall be gradually increased. The elongation achieved on reaching the tensile
strength of the core shall not be less than the value guaranteed in the GTP.
Torsion Test: The purpose of the test is to determine the resilience of the composite core to twisting and to
show that after the composite core has experienced the prescribed twisting, it will not crack or have a loss in
tensile strength due to the twisting. A sample length that is 170 times the diameter of the composite core
being tested is mounted in the gripping fixtures. One grip shall then be fixed so that it does not twist and the
other end shall be twisted a full 360 degrees and then fixed in this position for 2 minutes. Once the twist time
is completed, the core is untwisted an inspected for any crazing or other damage. If no damage is observed,
the composite core is then tensile tested to failure and the
final load recorded. For the test to be accepted, the composite core must withstand at least 100% of its rated
tensile strength. Two samples need to be completed in order to satisfy the testing requirement.
1.25 Breaking load test on Aluminium/ Aluminium Alloy & Composite core and D.C Resistance test on
Aluminium/ Aluminium Alloy wire
The above tests shall be carried out as per IEC: 888/889 and the results shall meet the requirements of
the specification.
1.26 Wrap test on Core wires (Applicable for steel/Al clad Steel/invar core only)
The wrap test on core strands shall be meet the requirements of IEC: 888. In case of aluminium clad
core wire, the same shall be wrapped around a mandrel of diameter of five times that of the strand to
form a helix of eight turns. The strand shall be unwrapped. No breakage of strand shall occurred.
Resistivity test as per IEC-468/IEC 889 shall be conducted to confirm minimum conductivity as per
specification requirement
Resistivity test as per IEC-468 shall be conducted to confirm minimum conductivity as per specification
requirement.
1.31 Glass Transition Temperature Test (for polymer composite core only)
Test method shall be as per ASTM D7028, A Standard Test Method for Glass Transition Temperature
of Polymer Matrix Composites by Dynamic Mechanical Analysis. The glass transition temperature shall
be greater than the maximum continuous operating temperature of the offered Composite Carbon Core
HTLS Conductor+ 35 deg C.
Bending test on polymer composite core (CFC) before stranding shall be performed as per ASTM
B987/B987M-17 on polymer composite core samples taken from composite core at conductor manufacturing
unit before stranding of conductor. Alternatively Bending test on polymer composite core (CFC) before
stranding may be performed at the core manufacturing unit on the samples taken from the same reel bein
supplied to conductor manufacturer subject to proper traceability of the same at the conductor manufacturers
works. Bending test on polymer composite core (CFC) shall also be performed as per ASTM B987/B987M-
17 on polymer composite core samples taken from stranded conductor. For test after stranding the diameter
of cylindrical mandrel shall be as following:
1) For high strength grade CFC – 60 times the diameter of
CFC
2) For Extra high strength grade CFC – 70 times the
diameter of CFC
A composite core sample shall be wrapped 180 degree around a cylindrical mandrel, and the specimen
brought to 15 % of the rated tensile strength of the composite core and held for 1 min. The mandrel
diameter shall be not more than 50 times the dia of composite core. After completion of the test, the core
shall withstand UTS test and dye penetration test.
1.34 Chemical Analysis of Aluminium/ Aluminium Alloy and Composite core/ INVAR Core Wires
Samples taken from the Aluminium /Aluminium Alloy and core coils/ strands shall be
chemically/spectrographically analyzed. The same shall be in conformity to the particulars guaranteed
by the bidder so as to meet the requirements stated in this Specification
Samples taken from the zinc ingots shall be chemically/ spectrographically analyzed. The same shall be
in conformity to the requirements stated in the Specification.
SECTION – 3 (A)
3.1 General
This section details technical particulars of hardware fittings and suspension clamps & compression
type dead end clamps for the HTLS Conductor to be proposed and supplied by the bidder. Each fitting shall
be suitable for HTLS conductor and to be supplied for satisfactory performance of complete conductor
system for continuous operation at the designed maximum temperature specified by them for the conductor.
The fittings shall be suitable for attachment to suspension and tension insulator strings along with hardware
fittings and shall include 2.5 % extra fasteners and Aluminum filler plugs.
The hardware fittings shall be suitable for use with long rod porcelain /string insulators having ball and
socket fittings. Each hardware fitting shall be supplied complete in all respects and shall include the
following hardware parts:
3.2.1 Suitable arcing horn as specified in clause 3.11 hereinafter.
3.2.2 Suitable yoke assemblies with the arrangement of fixing a set of arching horn and complying with the
specifications given hereinafter.
3.2.3 Bolts, Nuts, washers, split pin etc.
3.2.4 Suspension, tension clamps and dead-end assembly to suit conductor size as detailed in clause 3.3, 3.4
and 3.11, hereinafter.
3.2.5 Other necessary fittings viz D-shackles, eye links, extension links, ball clevis, socket clevis, clevis eye,
U clevis and chain link etc. to make the hardware fittings complete.
3.2.6 2.5% extra fasteners.
The suspension clamps shall be made of malleable iron or aluminium alloy, hot dip galvanised and shall be
suitable to accommodate the conductor together with one set of standard preformed armour rods. Suitable
sheet aluminium liners shall be provided. The suspension clamps shall be designed to avoid any possibility
of deforming or damaging the conductor. The lips shall be rounded off and the seating and the bell mouths
shall be smooth to avoid corona and radio interference noises. The suspension clamps shall be suitable to
carry the bottom part of the arcing horn and to receive the fittings of the long rod porcelain
insulator/insulator string.
The suspension clamps shall be such that the conductor should not slip at a load of 25% of the breaking load
of the conductor. The ultimate strength of the clamp for vertical load shall not be less than the failing load of
the Insulators.
The strain clamps shall also be made of malleable iron or aluminium alloy; hot dip galvanised, lined with
sheet aluminium liners and shall be suitable to accommodate the conductor with necessary binding tapes etc.
The lips shall be rounded off carefully and conductor seating and the ball mouth shall be smooth to avoid
corona and radio interference noises. Suitable attachment for receiving both side of arcing horns and for
connecting to the porcelain long rod insulator/insulator strings shall be provided.
The strain clamps shall be such that the conductor should not slip at a load of 90% of the breaking load of the
conductor. The ultimate strength of the clamp for horizontal load shall not be less than the ultimate strength
of the conductor.
3.5 Clamps fittings
The clamp fittings shall be suitable for attachment to suspension and tension porcelain long rod
insulator/insulator strings along with hardware fittings for normal stretches as well as river crossing stretches
and shall include 2.5 % extra fasteners. The supplier shall be responsible for satisfactory performance of
complete conductor system along with fittings offered by them for continuous operation at the designed
maximum temperature specified by them for the conductor.
3.6 Dimensions of long rod porcelain /Insulator String Along with Hardware Fitting
The various limiting dimensions of the long rod porcelain insulator/insulator strings shall generally be in
conformity with the dimensions of the hardware fittings. The Contractor shall be required to verify the
dimensions of the long rod porcelain insulator/insulator strings and shall ensure that the fittings are generally
conforming to the dimensions of the hardware fittings.
3.7 Interchangeability
The hardware for long rod porcelain insulator/insulator strings with disc insulators together with ball and
socket fittings shall be of standard design, so that this hardware are inter- changeable with each other and
suitable for use with insulators of any make conforming to relevant Indian/International Standard
3.8 Maintenance
The hardware fittings offered shall be suitable for employment of hot line maintenance technique so that
usual hot line operations can be carried out with ease, speed and safety. The technique adopted for hot line
maintenance shall be generally bare hand method & hot stick method.
3.9 Designation
The dimension of the ball and socket shall be 20mm for 120kN and 160KN Disc insulator. The designation
should be in accordance with the standard dimensions stated in IS: 2486-(Part-II)/IEC: 60120. The
dimensions shall be checked by the appropriate gauge after galvanising only.
3.10.1 Security clips for use with ball and socket coupling shall be R-shaped, hump type which provides
positive locking of the coupling as per IS: 2486-(Part-III)/ IEC: 60372. The legs of the security clips shall be
spread after assembly in the works to prevent complete withdrawal from the socket. The locking device
should be resilient, corrosion resistant and of suitable mechanical strength. There shall be no risk of the
locking device being displaced accidentally or being rotated when in position. Under no circumstances shall
the locking devices allow separation of fittings.
3.10.2 The hole for the security clip shall be countersunk and the clip should be of such design that the eye
of clip may be engaged by a hot line clip puller to provide for disengagement under energised conditions.
The force required to pull the security clip into its unlocked position shall not be less than 50 N (5 kg) or
more than 500 N (50 kg)
3.10.3 Split pins shall be used with bolts & nuts.
3.11.3 The air gap shall be so adjusted to ensure effective operation under actual field conditions.
The strength of yoke plate shall be adequate to withstand the minimum ultimate tensile strength as specified.
The plates shall be either triangular or rectangular in shape as may be necessary. The design of yoke plate shall take
into account the most unfavorable loading conditions likely to be experienced as a result of dimensional tolerances for
long rod porcelain insulator/disc insulators as well as components of hardware fittings within the specified range.
The plates shall have suitable holes for fixing arcing horn. All the corners and edges should be rounded off with a
radius of at least 3 mm. Design calculations i.e. for bearing & tensile strength, for deciding the dimensions of yoke
plate shall be furnished by the contractor. The holes provided for bolts in the yoke plate should satisfy shear edge
condition as per Clause No.10.2.4.2 of IS: 800-2007.
3.13.1 The turn buckle is to be provided with single/ double tension hardware fitting. The threads shall be of
sufficient strength to remain unaffected under the specified tensile load.
3.13.2 The maximum length of the turn buckle from the connecting part of the rest of the hardware fittings
shall be 520 mm. The details of the minimum and maximum adjustment possible shall be clearly indicated in
the drawing. An adjustment of 150 mm minimum shall be possible with turn buckle.
3.14.1 The suspension assembly shall be suitable for the HTLS Conductor, the bidder intends to supply. The
technical details of the conductor shall be as proposed by the bidder.
3.14.2 The suspension assembly shall be made of aluminium alloy and shall be suitable to accommodate the
conductor together with standard preformed armour rods or armour grip suspension clamp. The suspension
clamps shall be designed to avoid any possibility of deforming or damaging the conductor.
3.14.3 The suspension clamp along with standard preformed armour rods set shall be designed to have
maximum mobility in any direction and minimum moment of inertia so as to have minimum stress on the
conductor in the case of oscillation of the same.
3.14.4 The suspension clamp shall be designed for continuous operation at the temperature specified by the
bidder for conductor.
3.14.5 The suspension assembly shall be designed, manufactured and finished to give it a suitable shape, so
as to avoid any possibility of hammering between suspension assembly and conductor due to vibration. The
suspension assembly shall be smooth without any cuts, grooves, abrasions, projections, ridges or excrescence
which might damage the conductor.
3.14.6 The suspension assembly/clamp shall be designed so that it shall minimise the static & dynamic stress
developed in the conductor under various loading conditions as well as during wind induced conductor
vibrations. It shall also withstand power arcs & have required level of Corona/RIV performance.
For the Free Centre Suspension Clamp seat shall be smoothly rounded and curved into a bell mouth at the
ends. The lip edges shall have rounded bead. There shall be at least two U-bolts for tightening of clamp body
and keeper pieces together.
3.16.1 The dead-end assembly shall be suitable for the offered HTLS Conductor.
3.16.2 The dead-end assembly shall be of compression type with provision for compressing jumper terminal
at one end. The angle of jumper terminal to be mounted should be 30° with respect to the vertical line. The
area of bearing surface on all the connections shall be sufficient to ensure positive electrical and mechanical
contact and avoid local heating due to I2R losses. The resistance of the clamp when compressed on
Conductor shall not be more than 75% of the resistance of equivalent length of Conductor.
3.16.3 Die compression areas shall be clearly marked on each dead-end assembly designed for continuous
die compressions and shall bear the words ‘COMPRESS FIRST’ suitably inscribed near the point on each
assembly where the compression begins. If the dead-end assembly is designed for intermittent die
compressions it shall bear identification marks ‘COMPRESSION ZONE’ AND ‘NON- COMPRESSION
ZONE’ distinctly with arrow marks showing the direction of compressions and knurling marks showing the
end of the zones. The letters, number and other markings on the finished clamp shall be distinct and legible.
The dimensions of dead-end assembly before & after compression along with tolerances shall be guaranteed
in the relevant schedules of the bid and shall be decided by the manufacturer so as to suit the conductor size
& conform to electrical & mechanical requirement stipulated in the specification. These shall be guaranteed
in the relevant schedules of bid.
3.16.4 The assembly shall not permit slipping of, damage to, or failure of the complete conductor or any part
thereof at a load less than 95% of the ultimate tensile strength of the conductor.
3.16.5 Jumper bolting arrangement between jumper terminal/cone and terminal pad/plate of dead-end
assembly of tension hardware fittings shall be designed to suit the specification requirement of 1700A, as the
case may be, current and shall conform to the relevant Indian/International standards
3.16.6 For composite core HTLS conductor, dead end assembly shall inter-alia include collets, collet
housing, inner sleeve etc., suitable for the offered design of HTLS conductor.
3.17.1 All bolts and nuts shall conform to IS 6639. All bolts and nuts shall be galvanized as per IS 1367
(Part- 13)/IS 2629. All bolts and nuts shall have hexagonal heads, the heads being forged out of solid truly
concentric, and square with the shank, which must be perfectly straight.
3.17.2 Bolts up to M16 and having length up to 10 times the diameter of the bolt should be manufactured by
cold forging and thread rolling process to obtain good and reliable mechanical properties and effective
dimensional control. The shear strength of bolt for 5.6 grade should be 310 MPa minimum as per IS 12427.
Bolts should be provided with washer face in accordance with IS 1363 (Part-1) to ensure proper bearing.
3.17.3 Nuts should be double chamfered as per the requirement of IS 1363 Part- III 1984. It should be
ensured by the manufacturer that nuts should not be over tapped beyond 0.4 mm oversize on effective
diameter for size up-to M16.
3.17.4 Fully threaded bolts shall not be used. The length of the bolt shall be such that the threaded portion
shall not extend into the place of contact of the component parts.
3.17.5 All bolts shall be threaded to take the full depth of the nuts and threaded enough to permit the firm
gripping of the component parts but no further. It shall be ensured that the threaded portion of the bolt
protrudes not less than 3 mm and not more than 8 mm when fully tightened. All nuts shall fit and tight to the
point where shank of the bolt connects to the head.
3.17.6 Flat washers and spring washers shall be provided wherever necessary and shall be of positive lock
type. Spring washers shall be electro- galvanised. The thickness of washers shall conform to IS: 2016.
3.17.7 The Contractor shall furnish bolt schedules giving thickness of components connected, the nut and the
washer and the length of shank and the threaded portion of bolts and size of holes and any other special
details of this nature.
3.17.8 To obviate bending stress in bolt, it shall not connect aggregate thickness more than three time its
diameter.
3.17.9 Bolts at the joints shall be so staggered that nuts may be tightened with spanners without fouling.
3.17.10 To ensure effective in-process Quality control it is essential that the manufacturer should have all the
testing facilities for tests like weight of zinc coating, shear strength, other testing facilities etc, in- house. The
manufacturer should also have proper Quality Assurance system which should be in line with the
requirement of this specification and IS-.14000 services Quality System standard.
3.17.11 Fasteners of grade higher than 8.8 are not to be used and minimum grade for bolt shall be 5.6.
3.19.1 Mid Span Compression Joint shall be used for joining two lengths of conductor. The joint shall have a
resistively less than 75% of the resistivity of equivalent length of conductor. The joint shall not permit
slipping off, damage to or failure of the complete conductor or any part thereof at a load less than 95% of the
ultimate tensile strength of the conductor. It must be able to withstand the continuous design temperature of
conductor.
3.19.2 The dimensions of mid span compression joint before & after compression along with tolerances shall
be shall be guaranteed in the relevant schedules of the bid and shall be decided by the manufacturer so as to
suit the conductor size & conform to electrical & mechanical requirement stipulated in the specification. For
composite core conductor, suitable sleeve, collets, collet housing shall be used for core jointing.
Repair Sleeve of compression type shall be used to repair conductor with not more than two strands broken
in the outer layer. The sleeve shall be manufactured from 99.5% pure aluminium / aluminium alloy and shall
have a smooth surface. It shall be able to withstand the continuous maximum operating temperature of
conductor. The repair sleeve shall comprise of two pieces with a provision of seat for sliding of the keeper
piece. The edges of the seat as well as the keeper piece shall be so rounded that the conductor strands are not
damaged during installation. The dimensions of Repair sleeve along with tolerances shall be guaranteed in
the relevant schedules of the bid and shall be decided by the manufacturer so as to suit the conductor size &
conform to electrical & mechanical requirement stipulated in the specification.
3.21.1 Vibration dampers of 4R-stockbridge type with four (4) different resonances spread within the
specified aeolian frequency band width corresponding to wind speed of 1 m/s to 7 m/s are installed in the
existing line at suspension and tension points on each conductor in each span to damp out aeolian vibration
as well as sub- span oscillations. One damper minimum on each side per conductor for suspension points and
two dampers minimum on each side per conductor for tension points shall be used for a ruling design span of
325 meters (132kV) and 350 meters (220kV).
3.21.2 The bidder shall offer damping system including Stockbridge type dampers for proposed HTLS
Conductor for its protection from wind induced vibrations which could cause conductor fatigue /strand
breakage near a hardware attachment, such as suspension clamps. Alternate damping systems with proven
design offering equivalent or better performance also shall be accepted provided the manufacturer meets the
qualifying requirements stipulated in the Specifications. Relevant technical documents including type test
reports to establish the technical suitability of alternate systems shall be furnished by the Bidder along with
the bid. The damper shall be designed to have resonance frequencies to facilitate dissipation of vibration
energy through inter-strand friction of the messenger cable and shall be effective in reducing vibration over a
wide frequency range (depending upon conductor dia) or wind velocity range specified above. The vibration
damper shall meet the requirement of frequency or wind velocity range and also have mechanical impedance
closely matched with the offered HTLS conductor. The vibration dampers shall be installed at suitable
positions to ensure damping effectiveness across the frequency range. The power dissipation of the vibration
dampers shall exceed the wind power so that the vibration level on the conductor is reduced below its
endurance limit i.e 150 micro strain. The bidder shall clearly indicate the method for evaluating performance
of dampers including analytical and laboratory test methods. The bidder shall indicate the type tests to
evaluate the performance of offered damping system.
3.21.3 The clamp of the vibration damper shall be made of high strength aluminium alloy of type LM-6. It
shall be capable of supporting the damper and prevent damage or chafing of the conductor during erection or
continued operation. The clamp shall have smooth and permanent grip to keep the damper in position on the
conductor without damaging the strands or causing premature fatigue failure of the conductor under the
clamp. The clamp groove shall be in uniform contact with the conductor over the entire clamping surface
except for the rounded edges. The groove of the clamp body and clamp cap shall be smooth, free from
projections, grit or other materials which could cause damage to the conductor when the clamp is installed.
Clamping bolts shall be provided with self-locking nuts and designed to prevent corrosion of threads or
loosening in service.
3.21.4 The messenger cable shall be made of high strength galvanized steel/stain less steel with a minimum
strength of 135 kg/sqmm. It shall be of preformed and post formed quality in order to prevent subsequent
drop of weight and to maintain consistent flexural stiffness of the cable in service. The number of strands in
the messenger cable shall be 19. The messenger cable other than stainless steel shall be hot dip galvanised in
accordance with the recommendations of IS: 4826 for heavily coated wires.
3.21.5 The damper mass shall be made of hot dip galvanised mild steel/cast iron or a permanent mould cast
zinc alloy. All castings shall be free from defects such as cracks, shrinkage, inclusions and blowholes etc.
The surface of the damper masses shall be smooth.
3.21.6 The damper clamp shall be casted over the messenger cable and offer sufficient and permanent grip
on it. The messenger cable shall not slip out of the grip at a load less than the mass pull-off value of the
damper. The damper masses made of material other-than zinc alloy shall be fixed to the messenger cable in a
suitable manner in order to avoid excessive stress concentration on the messenger cables which shall cause
premature fatigue failure of the same. The messenger cable ends shall be suitably and effectively sealed to
prevent corrosion. The damper mass made of zinc alloy shall be casted over the messenger cable and have
sufficient and permanent grip on the messenger cable under all service conditions.
3.21.7 The damper assembly shall be so designed that it shall not introduce radio interference beyond
acceptable limits.
3.21.8 The vibration damper shall be capable of being installed and removed from energised line by means
of hot line technique. In addition, the clamp shall be capable of being removed and reinstalled on the
conductor at the designated torque without shearing or damaging of fasteners.
3.21.9 The contractor must indicate the clamp bolt tightening torque to ensure that the slip strength of the
clamp is maintained between 2.5 kN and 5 kN. The clamp when installed on the conductor shall not cause
excessive stress concentration on the conductor leading to permanent deformation of the conductor strands
and premature fatigue failure in operation.
3.21.10 The vibration analysis of the system, with and without damper and dynamic characteristics of the
damper as detailed under Annexure-A, shall have to be submitted. The technical particulars for vibration
analysis and damping design of the system are as follows:
Sl. No. Description Technical particulars
1. Span length in meters 325 meters (132kV) & 350
Ruling design span meters (220kV)
2. Configuration Double Circuit single / twin
bundle Conductor per phase
in vertical Configuration.
3. Tensile load in Conductor at temperature As per Sag – tension
of 0 deg. C and still air calculations
4. Armour rods used Standard preformed armour
rods/AGS
5. Maximum permissible dynamic strain +/- 150 micro strains
i.e. endurance limit.
3.21.11 The damper placement chart shall be submitted for spans ranging from 100m to 1100m. Placement
charts should be duly supported with relevant technical documents and sample calculations.
Location of the dampers for various combinations of spans and line tensions clearly indicating the number of
dampers to be installed per conductor per span.
Placement distances clearly identifying the extremities between which the distances are to be measured.
Placement recommendation depending upon type of suspension clamps (viz Free centre type/Armour grip
type etc.)
The influence of mid span compression joints, repair sleeves and armour rods (standard and AGS) in the
placement of dampers.
Bundle Spacer
2.5.1 Armour grip bundle spacers shall be used to maintain the spacing of 450 mm between the sub-
conductors [for 400kV] of each bundle under all normal working conditions.
2.5.2 Spacers offering equivalent or better performance shall also be accepted provided offer meets the
qualifying requirements stipulated in the Specification.
2.5.3 The offer shall include placement charts recommending the number of spacers per phase per span and
the sub span lengths to be maintained between the spacers while installing on the bundle conductors.
2.5.3.1 The placement of spacers shall be in such a way that adjacent sub spans are sufficiently detuned and
the critical wind velocity of each sub span shall be kept more than 30 km/hr. and to avoid clashing of sub
conductors. The placement shall ensure bundle stability under all operating conditions.
2.5.3.2 The placement chart shall be provided for spans ranging from 100m to 1100m. The number of
spacers recommended for a ruling design span of 400m [for 400kV] shall however be seven with no sub-
span greater than 70m and no end sub-span longer than 40m.
2.5.3.3 The Bidder may offer more number of spacers per ruling design span than the specified. However, I
such case, suitable price compensation shall be considered for evaluation. For the purpose of price
compensation, all the spans shall be assumed to be ruling design spans.
2.5.3.4 The Bidder shall also furnish all the relevant technical documents in support of their placement charts
along with the bid.
2.5.4 Jumpers at tension points shall also be fitted with spacers so as to limit the length of free conductor to
3.65 m and to maintain the sub conductor spacing of 450 mm [for 400kV] for bundle conductors. Bidder
shall quote for rigid spacer for jumper. It shall meet all the requirements of spacer used in line except for its
vibration performance. Spacers requiring retaining rods shall not be quoted for jumpers.
2.5.5 The spacer offered by the Bidder shall satisfy the following requirements.
2.5.5.1 Spacer shall restore normal spacing of the sub-conductors after displacement by wind,
electromagnetic and the electrostatic forces under all operating conditions including the specified short
circuit level without permanent deformation damage either to conductor or to the assembly itself. They shall
have uniform grip on the conductor
2.5.5.2 For spacer requiring retaining rods, the retaining rods shall be designed for the specified conductor
size. The preformed rods shall be made of high strength, special aluminium alloy of type 6061/65032 and
shall have minimum tensile strength of 35 kg/sq.mm. The ends of retaining rods should be ball ended. The
rods shall be heat-treated to achieve specified mechanical properties and give proper resilience and retain the
same during service.
2.5.5.3 Four number of rods shall be applied on each clamps to hold the clamp in position. The minimum
diameter of the rods shall be 7.87 + 0.1 mm and the length of the rods shall not be less than 1100 mm.
2.5.5.4 Where elastomer surfaced clamp grooves are used, the elastomer shall be firmly fixed to the clamp.
The insert should be forged from aluminium alloy of type 6061/65032. The insert shall be duly heat
treated and aged to retain its consistent characteristics during service.
2.5.5.5 Any nut used shall be locked in an approved manner to prevent vibration loosening. The ends of bolts
and nuts shall be properly rounded for specified corona performance or suitably shielded.
2.5.5.6 Clamp with cap shall be designed to prevent its cap from slipping out of position when being
tightened.
2.5.5.7 The clamp grooves shall be in uniform contact with the conductor over the entire surface, except for
rounded edges. The groove of the clamp body and clamp cap shall be smooth and free of projections,
grit or other material which cause damage to the conductor when the clamp is installed.
2.5.5.8 For the spacer involving bolted clamps, the manufacturer must indicate the clamp bolt tightening
torque to ensure that the slip strength of the clamp is maintained between 2.5 kN and 5 kN. The clamp when
installed on the conductor shall not cause excessive stress concentration on the conductor leading to
permanent deformation of the conductor strands and premature fatigue failure in operation.
2.5.5.9 Universal type bolted clamps, covering a range of conductor sizes, will not be permitted.
2.5.5.10 No rubbing, other than that of the conductor clamp hinges or clamp swing bolts, shall take place
between any parts of the spacer. Joint incorporating a flexible medium shall be such that there is no relative
slip between them.
2.5.5.11 The spacer shall be suitably designed to avoid distortion or damage to the conductor or to
themselves during service.
2.5.5.12 Rigid spacers shall be acceptable only for jumpers.
2.5.5.13 The spacer shall not damage or chafe the conductor in any way which might affect its mechanical
and fatigue strength or corona performance.
2.5.5.14 The clamping system shall be designed to compensate for any reduction in diameter of conductor
due to creep.
2.5.5.15 The spacer assembly shall not have any projections, cuts, abrasions etc. or chattering parts which
might cause corona or RIV.
2.5.5.16 The spacer tube shall be made of aluminium alloy of type 6061/65032. If fasteners of ferrous
material are used, they shall conform to and be galvanized conforming to relevant Indian
Standards.
2.5.5.17 Elastomer, if used, shall be resistant to the effects of temperature up to the designed maximum
temperature specified for the conductor, ultraviolet radiation and other atmospheric contaminants likely to be
encountered in service. It shall have good fatigue characteristics. The physical properties of the elastomer
shall be of approved standard. The supplier shall submit relevant type/ performance test certificate as per
applicable standard/ product specification for elastomer to confirm suitability of the offered elastomer for the
specified application.
2.5.5.18 The spacer assembly shall have electrical continuity. The electrical resistance between the sub-
conductor across the assembly in case of spacer having elastomer clamp grooves shall be suitably selected
by the manufacturers to ensure satisfactory electrical performance and to avoid deterioration of elastomer
under all service conditions.
2.5.5.19 The spacer assembly shall have complete ease of installation and shall be capable of
removal/reinstallation without any damage.
2.5.5.20 The spacer assembly shall be capable of being installed and removed from the energized line by
means of hot line technique.
3.22 PG Clamp, Come Along Clamp, T-Clamp, CVT Clamp, CB Clamp, CT&PT clamp, Pad clamp
for substation Bay stringing by HTLS conductor.
a. Standard Specification and tests shall be as per IS:5561.
b. Bolts, nuts and washers shall be made of mild steel and hot dip galvanized as per IS 2629. Small fittings
like spring washers, nuts etc. may be electrogalvanised.
c. The quality of HDG ferrous components shall be determined by the test given in IS:2633 and shall satisfy
the requirement of that standard.
d. The rated short time current shall be one of the standard values laid down in Indian Standards for the
associated circuit breakers, Switches etc.
e. Current carrying capacity same as conductor full current rating. For two different conductors, conductor
with smaller rating shall be considered.
f. No part of a clamp shall be less than 15 mm thick for fittings suitable for HTLS conductor, All sharp edges
and corners shall be blurred and rounded off.
g. For bimetallic connectors, copper alloy liner of minimum thickness of 2 mm shall be cast integral with
aluminium body.
h. From outermost hole edge to nearest edge of any clamps and connectors the distance shall not be less than
10 mm.
.23 Corona and RI Performance.
Sharp edges and scratches on all the hardware fittings shall be avoided. All surface must be clean, smooth,
without cuts and abrasions or projections. The Supplier shall be responsible for satisfactory corona and radio
interference performance of the materials offered by him.
3.24 Materials
The materials of the various components shall be as specified hereunder. The Bidder shall indicate the
material proposed to be used for each and every component of hardware fitting stating clearly the class,
grade or alloy designation of the material, manufacturing process & heat treatment details and the reference
standards.
3.24.1 The details of materials for different component are listed as in Table No-1 (a).
TABLE-1 (a)
(Details of Materials)
Sr. Name of item Material treatment Process of Reference Remarks
No Standard
.
1 Security Clips Stainless Steel/ - AISI 302 or 304-
Phospher Bronze L/ IS- 1385
2 For Free Centre /Envelope type clamps/PG Clamp/Come along clamp
a. Clamp Body, High Strength Al. Casted or forged
Keeper Piece Alloy 4600/ LM-6 & Heat treated IS:617or ASTM-
or 6061/65032 B429
b. Cotter bolts/ Mild Steel Hot dip As per IS-226 or
Hangers, galvanised IS-2062
Shackles,
Brackets
c. U Bolts Stainless Steel or Forged & & Heat AISI 302 or 304-
High Strength Al treated L ASTM B429
Alloy 6061/65032
d. P. A. Rod High Strength Al. Heat treatment ASTM-B429 Min. tensile
Alloy 4600/ LM-6 during strength of 35
or manufacturing kg/mm2
6061/65032
3 For AGS type clamp
High Strength
Corrosion resistant Casted or forged
(a) Supporting Al.Alloy 4600/ LM- & Heat treated S:617or ASTM-
House 6 or 6061/65032 B429
High Strength Al. High Strength Al.
Al insert & Alloy 4600/ LM-6 Casted or forged S:617or ASTM- Alloy 4600/ LM-6
(b) Retaining strap or 6061/65032 I & Heat treated B429 or 6061/65032
(c) Elastomer Molded on Al.
reinforcement
4. For Dead End Assembly
EC grade Al of
(a) Outer Sleeve purity not less
than99.50%
Hot Dip
(b) Steel Sleeve Mild Steel Galvanised IS:226/ IS-2062
5. Ball & Socket Class-IV Steel Drop forged &
Fittings, normalized Hot As per IS: 2004
dip galvanised
Hot dip As per IS-226 or
6. Yoke Plate Mild Steel galvanized IS-2062
High Strength Al. Mechanical
Corona Control Alloy tube strength of welded
7. ring/ t Grading (6061/6063/ 1100 Heat treated Hot ASTM-B429 or joint shall
ring ype or 65032/ 63400 dip galvanized as per IS not be lessthan 20
kN
Supporting than High strength Al Heat treated Hot ASTM-B429 or
8. 20 Brackets & Alloy 7061/ 6063/ dip galvanized as per IS:226 or
Mounting Bolts 65032/63400 S:2062
Type) or Mild Steel
Note: Alternate materials conforming to other national standards of other countries also may be offered
provided the properties and compositions of these are close to the properties and compositions of
material specified. Bidder should furnish the details of comparison of material offered viz a viz specified
in the bid or else the bids are liable to be rejected.
3.24 Workmanship
3.24.1 All the equipment shall be of the latest design and conform to the best modern practices adopted in the
Extra High Voltage field. The Bidder shall offer only such equipment as guaranteed by him to be satisfactory
and suitable for 220 kV transmission lines and will give continued good performance.
3.24.2 High current, heat rise test shall be conducted by the supplier to determine the maximum temperature
achieved in different components of fittings / accessories under simulated service condition corresponding to
operation of conductor at maximum (emergency) operating temperature. The material of the components
should be suitable for continued good performance corresponding to these maximum temperatures. The
supplier shall submit relevant type/performance test certificates as per applicable standards/product
specifications to confirm suitability of the offered material.
3.24.3 The design, manufacturing process and quality control of all the materials shall be such as to give the
specified mechanical rating, highest mobility, elimination of sharp edges and corners to limit corona and
radio-interference, best resistance to corrosion and a good finish.
3.24.4 All ferrous parts including fasteners shall be hot dip galvanised, after all machining has been
completed. Nuts may, however, be tapped (threaded) after galvanising and the threads oiled. Spring washers
shall be electro galvanized. The bolt threads shall be undercut to take care of the increase in diameter due to
galvanizing. Galvanizing shall be done in accordance with IS 2629 / IS 1367 (Part-13) and shall satisfy the
tests mentioned in IS 2633. Fasteners shall withstand four dips while spring washers shall withstand three
dips of one-minute duration in the standard Preece test. Other galvanized materials shall have a minimum
average coating of zinc equivalent to 600 gm/sqm., shall be guaranteed to withstand at least six successive
dips each lasting one (1) minute under the standard Preece test for galvanizing.
3.24.5 Before ball fittings are galvanized, all die flashing on the shank and on the bearing surface of the ball
shall be carefully removed without reducing the dimensions below the design requirements.
3.24.6 The zinc coating shall be perfectly adherent, of uniform thickness, smooth, reasonably bright,
continuous and free from imperfections such as flux, ash rust, stains, bulky white deposits and blisters. The
zinc used for galvanising shall be grade Zn 99.95 as per IS: 209.
3.24.7 Pin balls shall be checked with the applicable “GO” gauges in at least two directions. one of which
shall be across the line of die flashing, and the other 90o to this line. "NO GO" gauges shall not pass in any
direction.
3.24.8 Socket ends, before galvanising, shall be of uniform contour. The bearing surface of socket ends shall
be uniform about the entire circumference without depressions of high spots. The internal contours of socket
ends shall be concentric with the axis of the fittings as per IS: 2486/IEC: 120.
The axis of the bearing surfaces of socket ends shall be coaxial with the axis of the fittings. There shall be
no noticeable tilting of the bearing surfaces with the axis of the fittings.
3.24.9 In case of casting, the same shall be free from all internal defects like shrinkage, inclusion, blow
holes, cracks etc. Pressure die casting shall not be used for casting of components with thickness more than 5
mm.
3.24.10 All current carrying parts shall be so designed and manufactured that contact resistance is reduced to
minimum.
3.24.11 No equipment shall have sharp ends or edges, abrasions or projections and cause any damage to the
conductor in any way during erection or during continuous operation which would produce high electrical
and mechanical stresses in normal working. The design of adjacent metal parts and mating surfaces shall be
such as to prevent corrosion of the contact surface and to maintain good electrical contact under service
conditions.
3.24.12 All the holes shall be cylindrical, clean cut and perpendicular to the plane of the material. The
periphery of the holes shall be free from burrs.
3.24.13 All fasteners shall have suitable corona free locking arrangement to guard against vibration
loosening.
3.24.14 Welding of aluminium shall be by inert gas shielded tungsten arc or inert gas shielded metal arc
process Welds shall be clean, sound, smooth, uniform without overlaps, properly fused and completely
sealed.
There shall be no cracks, voids incomplete penetration, incomplete fusion, under-cutting or inclusions.
Porosity shall be minimised so that mechanical properties of the aluminium alloys are not affected. All welds
shall be properly finished as per good engineering practices.
3.25.3 All drawings shall be identified by a drawing number and contract number. All drawings shall be
neatly arranged. All drafting & lettering shall be legible. The minimum size of lettering shall be 3 mm. All
dimensions & dimensional tolerances shall be mentioned in mm.
The drawings shall include:
i) Dimensions and dimensional tolerance.
ii) Material, fabrication details including any weld details & any specified finishes & coatings. Regarding
material designation & reference of standards are to be indicated.
iii) Catalogue No.
iv) Marking
v) Weight of assembly
vi) Installation instructions
vii) Design installation torque for the bolt or cap screw.
viii) Withstand torque that may be applied to the bolt or cap screw without failure of component parts.
ix) The compression die number with recommended compression pressure.
x) Placement charts for damper.
xi) All other relevant terminal details.
3.25.4 After placement of award, the Contractor shall submit fully dimensioned drawing including all the
components in four (4) copies to the Owner for approval. After getting approval from the Owner and
successful completion of all the type tests, the Contractor shall submit ten (10) more copies of the same
drawings to the Owner for further distribution and field use at Employer’s end.
Die compression areas shall be clearly marked, on each equipment designed for continuous die compressions
and shall bear the words ‘COMPRESS FIRST’ ‘suitably inscribed on each equipment where the compression
begins. If the equipment is designed for intermittent die compressions, it shall bear the identification marks
‘COMPRESSION ZONE’ and ‘NON-COMPRESSION ZONE’ distinctly with arrow marks, showing the
direction of compression and knurling marks showing the end of the zones. The letters, number and other
markings on finished equipment shall be distinct and legible.
Note: 1) All the type test given in Clause No. 3.27.1.1 shall be conducted on complete single
suspension & Single Tension insulator unit.
2) All the type tests given under Clause No. 3.27.1.1 (a) to (e) shall also be
conducted on Single I Pilot, Double I Suspension & Double Tension insulator unit
3.27.8 Type tests specified under Clause 3.27.1 to 3.27.7 shall not be required to be carried out if a valid test
certificate is available for a similar design, i.e., tests conducted earlier should have been conducted in
accredited laboratory (accredited based on ISO/IEC guide 25/17025 or EN 45001 by the National
Accreditation body of the country where laboratory is located) or witnessed by the representative (s)
Central/State Power Utility.
In the event of any discrepancy in the test report (i.e., any test report not applicable due to any design /
material/manufacturing process change including substitution of components or due to non-compliance with
the requirement stipulated in the Technical Specification) the tests shall be conducted by the Contractor at no
extra cost to the Employer/ Employer/ Employer.
a. Clamp Slip strength Vs Torque test for suspension clamp: As per Annexure-B 1
b. Shore hardness test of elastomer cushion for
AG suspension clamp : As per Annexure-B 1
c. Bend test for armour rod set : As per IS:2121(Part-I),
Clause 7.5,7,10 & 7.11
d. Resilience test for armour rod set : As per IS:2121(Part-I),
Clause 7.5,7,10 & 7.11
e. Conductivity test for armour rods set : As per IS:2121(Part-I),
Clause 7.5,7,10 & 7.11
* Applicable for 4 R stockbridge dampers. For alternate type of vibration dampers (permitted as per
clause 3.27), as an alternative to dynamic characteristic test, damper efficiency test as per IEEE-664
may be proposed/ carried out by the supplier.
3.30.2 In case type testing is required due to non-availability of type test reports, or type test on the complete
insulator string, the Contractor has to arrange similar insulators at his own cost.
3.30.3 Bidder shall indicate the laboratories in which they propose to conduct the type tests. They shall
ensure that adequate facilities for conducting the tests are available in the laboratory and the tests can be
completed in these laboratories within the time schedule guaranteed by them in the appropriate schedule.
3.30.4 The entire cost of testing for type tests, acceptance and routine tests and tests during manufacture
specified herein shall be treated as included in the quoted Ex-works/CIF Price.
3.30.5 In case of failure in any type test, repeat type tests are required to be conducted, then, all the expenses
for deputation of Inspector/ Owner’s representative shall be deducted from the contract price. Also, if on
receipt of the Contractor's notice of testing, the Owner’s representative/Inspector does not find material &
facilities to be ready for testing the expenses incurred by the Owner’s for re- deputation shall be deducted
from contract price.
3.30.6 The Contractor shall intimate the Owner about carrying out of the type tests along with detailed
testing programme at least 3 weeks in advance of the scheduled date of testing during which the Owner will
arrange to depute his representative to be present at the time of carrying out the tests.
3.31.1 The Bidder has to indicate the schedule of following activities in their bids
i. Submission of drawing for approval.
ii. Submission of Quality Assurance programme for approval.
iii. Offering of material for sample selection for type tests.
iv. Type testing.
3.31.2 The Owner reserves the right of having at his own expense any other test(s) of reasonable nature
carried out at Contractor’s premises, at site, or in any other place in addition to the aforesaid type, acceptance
and routine tests to satisfy himself that the material complies with the specifications.
3.31.3 The Owner also reserves the right to conduct all the tests mentioned in this specification at his own
expense on the samples drawn from the site at Contractor’s premises or at any other test centre. In case of
evidence of noncompliance, it shall be binding on the part of Contractor to prove the compliance of the items
to the technical specifications by repeat tests, or correction of deficiencies, or replacement of defective items,
all without any extra cost to the Owner.
3.33.1 The Owner’s representative shall at all times be entitled to have access to the works and all places of
manufacture, where the material and/or its component parts shall be manufactured and the representatives
shall have full facilities for unrestricted inspection of the Contractor’s, sub- Contractor’s works raw
materials. Manufacturer’s of all the material and for conducting necessary tests as detailed herein.
3.33.2 The material for final inspection shall be offered by the Contractor only under packed condition. The
engineer shall select samples at random from the packed lot for carrying out acceptance tests.
3.33.3 The Contractor shall keep the Employer informed in advance of the time of starting and of the
progress of manufacture of material in its various stages so that arrangements could be made for inspection.
3.33.4 Material shall not be dispatched from its point of manufacture before it has been satisfactorily
inspected and tested unless the inspection is waived off by the Owner in writing. In the latter case also the
material shall be dispatched only after all tests specified herein have been satisfactorily completed.
3.33.5 The acceptance of any quantity of material shall in no way relieve the Contractor of his responsibility
for meeting all the requirements of the Specification, and shall not prevent subsequent rejection, if such
materials are later found to be defective.
3.34.1 All material shall be packed in strong and weather resistant wooden cases/crates. The gross weight of
the packing shall not normally exceed 200 Kg to avoid handling problems.
3.34.2 The packing shall be of sufficient strength to withstand rough handling during transit, storage at site
and subsequent handling in the field.
3.34.3 Suitable cushioning, protective padding, dunnage or spacers shall be provided to prevent damage or
deformation during transit and handling.
3.34.4 Bolts, nuts, washers, cotter pins, security clips and split pins etc. shall be packed duly installed and
assembled with the respective parts and suitable measures shall be used to prevent their loss.
3.34.5 Each component part shall be legibly and indelibly marked with trade mark of the manufacturer and
year of manufacture. However, in such type of component/item, which consists of many parts and are being
supplied in assembled condition (suspension clamp, vibration damper, etc.), the complete assembly shall be
legibly and indelibly marked on main body/on one of the parts.
3.34.6 All the packing cases shall be marked legibly and correctly so as to ensure safe arrival at their
destination and to avoid the possibility of goods being lost or wrongly dispatched on account of faulty
packing and faulty or illegible markings. Each wooden case/crate shall have all the markings stenciled on it
in indelible ink.
3.35 Standards
3.35.1 The Hardware fittings; conductor and earth wire accessories shall conform to the following
Indian/International Standards which shall mean latest revisions, with amendments/changes adopted and
published, unless specifically stated otherwise in the Specification.
3.35.2 In the event of the supply of hardware fittings; conductor accessories conforming to standards other
than specified, the Bidder shall confirm in his bid that these standards are equivalent to those specified. In
case of award, salient features of comparison between the Standards proposed by the Contractor and those
specified in this document will be provided by the Contractor to establish their equivalence.
SECTION – 3 (B)
3.1 General
This section details technical particulars of hardware fittings and suspension clamps & compression
type dead end clamps for the HTLS Conductor to be proposed and supplied for replacement of ACSR
panther conductor by the bidder. Each fitting shall be suitable for proposed HTLS conductor and to be
supplied for satisfactory performance of complete conductor system for continuous operation at the designed
maximum temperature specified by them for the conductor.
The hardware fittings shall be suitable for use with long rod porcelain /string insulators having ball and
socket fittings. Each hardware fitting shall be supplied complete in all respects and shall include the
following hardware parts:
3.2.1 Suitable arcing horn as specified in clause 3.11 hereinafter.
3.2.2 Suitable yoke assemblies with the arrangement of fixing a set of arching horn and complying with the
specifications given hereinafter.
3.2.3 Bolts, Nuts, washers, split pin etc.
3.2.4 Suspension, tension clamps and dead-end assembly to suit conductor size as detailed in clause 3.3, 3.4
and 3.16, hereinafter.
3.2.5 Other necessary fittings viz D-shackles, eye links, extension links, ball clevis, socket clevis, clevis eye,
U clevis and chain link etc. to make the hardware fittings complete.
3.2.6 2.5% extra fasteners.
The suspension clamps shall be made of malleable iron or aluminium alloy, hot dip galvanised and shall be
suitable to accommodate the conductor together with one set of standard preformed armour rods. Suitable
sheet aluminium liners shall be provided. The suspension clamps shall be designed to avoid any possibility
of deforming or damaging the conductor. The lips shall be rounded off and the seating and the bell mouths
shall be smooth to avoid corona and radio interference noises. The suspension clamps shall be suitable to
carry the bottom part of the arcing horn and to receive the fittings of the long rod porcelain
insulator/insulator string.
The suspension clamps shall be such that the conductor should not slip at a load of 25% of the breaking load
of the conductor. The ultimate strength of the clamp for vertical load shall not be less than the failing load of
the Insulators.
The strain clamps shall also be made of malleable iron or aluminium alloy; hot dip galvanised, lined with
sheet aluminium liners and shall be suitable to accommodate the conductor with necessary binding tapes etc.
The lips shall be rounded off carefully and conductor seating and the ball mouth shall be smooth to avoid
corona and radio interference noises. Suitable attachment for receiving both side of arcing horns and for
connecting to the porcelain long rod insulator/insulator strings shall be provided.
The strain clamps shall be such that the conductor should not slip at a load of 90% of the breaking load of the
conductor. The ultimate strength of the clamp for horizontal load shall not be less than the ultimate strength
of the conductor.
The clamp fittings shall be suitable for attachment to suspension and tension porcelain long rod
insulator/insulator strings along with hardware fittings for normal stretches as well as river crossing stretches
and shall include 2.5 % extra fasteners. The supplier shall be responsible for satisfactory performance of
complete conductor system along with fittings offered by them for continuous operation at the designed
maximum temperature specified by them for the conductor.
3.6 Dimensions of long rod porcelain /Insulator String Along with Hardware Fitting
The various limiting dimensions of the long rod porcelain insulator/insulator strings shall generally be in
conformity with the dimensions of the hardware fittings. The Contractor shall be required to verify the
dimensions of the long rod porcelain insulator/insulator strings and shall ensure that the fittings are generally
conforming to the dimensions of the hardware fittings.
3.7 Interchangeability
The hardware for long rod porcelain insulator/insulator strings with disc insulators together with ball and
socket fittings shall be of standard design, so that this hardware are inter- changeable with each other and
suitable for use with insulators of any make conforming to relevant Indian/International Standard
3.8 Maintenance
The hardware fittings offered shall be suitable for employment of hot line maintenance technique so that
usual hot line operations can be carried out with ease, speed and safety. The technique adopted for hot line
maintenance shall be generally bare hand method & hot stick method.
3.9 Designation
The dimension of the ball and socket shall be 16mm designation for 70 and 90KN and 20mm for 120kN Disc
insulator. The designation should be in accordance with the standard dimensions stated in IS:
2486-(Part-II)/IEC: 60120. The dimensions shall be checked by the appropriate gauge after galvanising
only.
3.10.1 Security clips for use with ball and socket coupling shall be R-shaped, hump type which provides
positive locking of the coupling as per IS: 2486-(Part-III)/ IEC: 60372. The legs of the security clips shall be
spread after assembly in the works to prevent complete withdrawal from the socket. The locking device
should be resilient, corrosion resistant and of suitable mechanical strength. There shall be no risk of the
locking device being displaced accidentally or being rotated when in position. Under no circumstances shall
the locking devices allow separation of fittings.
3.10.2 The hole for the security clip shall be countersunk and the clip should be of such design that the eye
of clip may be engaged by a hot line clip puller to provide for disengagement under energised conditions.
The force required to pull the security clip into its unlocked position shall not be less than 50 N (5 kg) or
more than 500 N (50 kg)
3.10.3 Split pins shall be used with bolts & nuts.
The strength of yoke plate shall be adequate to withstand the minimum ultimate tensile strength as specified.
The plates shall be either triangular or rectangular in shape as may be necessary. The design of yoke plate shall take
into account the most unfavorable loading conditions likely to be experienced as a result of dimensional tolerances for
long rod porcelain insulator/disc insulators as well as components of hardware fittings within the specified range.
The plates shall have suitable holes for fixing arcing horn. All the corners and edges should be rounded off with a
radius of atleast 3 mm. Design calculations i.e. for bearing & tensile strength, for deciding the dimensions of yoke
plate shall be furnished by the contractor. The holes provided for bolts in the yoke plate should satisfy shear edge
condition as per Clause No.10.2.4.2 of IS: 800-2007.
3.13 Turn Buckle
3.13.1 The turn buckle is to be provided with single/ double tension hardware fitting. The threads shall be of
sufficient strength to remain unaffected under the specified tensile load.
3.13.2 The maximum length of the turn buckle from the connecting part of the rest of the hardware fittings
shall be 520 mm. The details of the minimum and maximum adjustment possible shall be clearly indicated in
the drawing. An adjustment of 150 mm minimum shall be possible with turn buckle.
3.14.1 The suspension assembly shall be suitable for the HTLS Conductor, the bidder intends to supply. The
technical details of the conductor shall be as proposed by the bidder.
3.14.2 The suspension assembly shall be made of aluminium alloy and shall be suitable to accommodate the
conductor together with standard preformed armour rods or armour grip suspension clamp. The suspension
clamps shall be designed to avoid any possibility of deforming or damaging the conductor.
3.14.3 The suspension clamp along with standard preformed armour rods set shall be designed to have
maximum mobility in any direction and minimum moment of inertia so as to have minimum stress on the
conductor in the case of oscillation of the same.
3.14.4 The suspension clamp shall be designed for continuous operation at the temperature specified by the
bidder for conductor.
3.14.5 The suspension assembly shall be designed, manufactured and finished to give it a suitable shape, so
as to avoid any possibility of hammering between suspension assembly and conductor due to vibration. The
suspension assembly shall be smooth without any cuts, grooves, abrasions, projections, ridges or excrescence
which might damage the conductor.
3.14.6 The suspension assembly/clamp shall be designed so that it shall minimise the static & dynamic stress
developed in the conductor under various loading conditions as well as during wind induced conductor
vibrations. It shall also withstand power arcs & have required level of Corona/RIV performance.
The Preformed Armour Rods Set shall be used to minimise the stress developed in the conductor due to
different static and dynamic loads because of vibration due to wind, slipping of conductor from the
suspension clamp as a result of unbalanced conductor tension in adjacent spans and broken wire condition. It
shall also withstand power arcs, chafing and abrasion from suspension clamp and localized heating effect
due to magnetic power losses from suspension clamps as well as resistance losses of the conductor.
3.15.1 The preformed armour rods set shall have right hand lay and the inside diameter of the helices shall be
less than the outside diameter of the conductor to have gentle but permanent grip on the conductor. The
surface of the armour rod when fitted on the conductor shall be smooth and free from projections, cuts and
abrasions etc.
3.15.2 The pitch length of the rods shall be determined by the Bidder but shall be less than that of the outer
layer of conductor and the same shall be accurately controlled to maintain uniformity and consistently
reproducible characteristic wholly independent of the skill of linemen.
3.15.3 The length and diameter of each rod shall be furnished by the bidder in the GTP. The tolerance in
length of the rods between the longest and shortest rod in complete set should be within the limits specified
in relevant Indian/International Standards. The ends of armour rod shall be parrot billed.
3.15.4 The number of armour rods in each set shall be as per supplier’s design to suit HTLS Conductor
offered Standards. Each rod shall be marked in the middle with paint for easy application on the line.
3.15.5 The armour rod shall not lose their resilience even after five applications.
3.15.6 The conductivity of each rod of the set shall not be less than 40% of the conductivity of the
International Annealed Copper Standard (IACS).
3.16.1 The dead-end assembly shall be suitable for the offered HTLS Conductor.
3.16.2 The dead-end assembly shall be of compression type with provision for compressing jumper terminal
at one end. The angle of jumper terminal to be mounted should be 30° with respect to the vertical line. The
area of bearing surface on all the connections shall be sufficient to ensure positive electrical and mechanical
contact and avoid local heating due to I2R losses. The resistance of the clamp when compressed on
Conductor shall not be more than 75% of the resistance of equivalent length of Conductor.
3.16.3 Die compression areas shall be clearly marked on each dead-end assembly designed for continuous
die compressions and shall bear the words ‘COMPRESS FIRST’ suitably inscribed near the point on each
assembly where the compression begins. If the dead-end assembly is designed for intermittent die
compressions it shall bear identification marks ‘COMPRESSION ZONE’ AND ‘NON- COMPRESSION
ZONE’ distinctly with arrow marks showing the direction of compressions and knurling marks showing the
end of the zones. The letters, number and other markings on the finished clamp shall be distinct and legible.
The dimensions of dead-end assembly before & after compression alongwith tolerances shall be guaranteed
in the relevant schedules of the bid and shall be decided by the manufacturer so as to suit the conductor size
& conform to electrical & mechanical requirement stipulated in the specification. These shall be guaranteed
in the relevant schedules of bid.
3.16.4 The assembly shall not permit slipping of, damage to, or failure of the complete conductor or any part
thereof at a load less than 95% of the ultimate tensile strength of the conductor.
3.16.5 Jumper bolting arrangement between jumper terminal/cone and terminal pad/plate of dead end
assembly of tension hardware fittings shall be designed to suit the specification requirement of 1050A/800A,
as the case may be, current and shall conform to the relevant Indian/International standards
3.16.6 For composite core HTLS conductor, dead end assembly shall inter-alia include collets, collet
housing, inner sleeve etc., suitable for the offered design of HTLS conductor.
3.17.1 All bolts and nuts shall conform to IS 6639. All bolts and nuts shall be galvanized as per IS 1367
(Part- 13)/IS 2629. All bolts and nuts shall have hexagonal heads, the heads being forged out of solid truly
concentric, and square with the shank, which must be perfectly straight.
3.17.2 Bolts up to M16 and having length up to 10 times the diameter of the bolt should be manufactured by
cold forging and thread rolling process to obtain good and reliable mechanical properties and effective
dimensional control. The shear strength of bolt for 5.6 grade should be 310 MPa minimum as per IS 12427.
Bolts should be provided with washer face in accordance with IS 1363 (Part-1) to ensure proper bearing.
3.17.3 Nuts should be double chamfered as per the requirement of IS 1363 Part- III 1984. It should be
ensured by the manufacturer that nuts should not be over tapped beyond 0.4 mm oversize on effective
diameter for size upto M16.
3.17.4 Fully threaded bolts shall not be used. The length of the bolt shall be such that the threaded portion
shall not extend into the place of contact of the component parts.
3.17.5 All bolts shall be threaded to take the full depth of the nuts and threaded enough to permit the firm
gripping of the component parts but no further. It shall be ensured that the threaded portion of the bolt
protrudes not less than 3 mm and not more than 8 mm when fully tightened. All nuts shall fit and tight to the
point where shank of the bolt connects to the head.
3.17.6 Flat washers and spring washers shall be provided wherever necessary and shall be of positive lock
type. Spring washers shall be electro- galvanised. The thickness of washers shall conform to IS: 2016.
3.17.7 The Contractor shall furnish bolt schedules giving thickness of components connected, the nut and the
washer and the length of shank and the threaded portion of bolts and size of holes and any other special
details of this nature.
3.17.8 To obviate bending stress in bolt, it shall not connect aggregate thickness more than three time its
diameter.
3.17.9 Bolts at the joints shall be so staggered that nuts may be tightened with spanners without fouling.
3.17.10 To ensure effective in-process Quality control it is essential that the manufacturer should have all the
testing facilities for tests like weight of zinc coating, shear strength, other testing facilities etc, in- house. The
manufacturer should also have proper Quality Assurance system which should be in line with the
requirement of this specification and IS-.14000 services Quality System standard.
3.17.11 Fasteners of grade higher than 8.8 are not to be used and minimum grade for bolt shall be 5.6.
3.18 Accessories for the HTLS Conductor
3.22.1 This portion details the technical particulars of the accessories for Conductor.
3.22.2 2.5% extra fasteners, filler plugs and retaining rods shall be provided.
3.22.3 The supplier shall be responsible for satisfactory performance of complete conductor system along
with accessories offered by him for continuous operation at temperature specified for the HTLS Conductor.
3.19.1 Mid Span Compression Joint shall be used for joining two lengths of conductor. The joint shall have a
resistively less than 75% of the resistivity of equivalent length of conductor. The joint shall not permit
slipping off, damage to or failure of the complete conductor or any part thereof at a load less than 95% of the
ultimate tensile strength of the conductor. It must be able to withstand the continuous design temperature of
conductor.
3.19.2 The dimensions of mid span compression joint before & after compression along with tolerances shall
be shall be guaranteed in the relevant schedules of the bid and shall be decided by the manufacturer so as to
suit the conductor size & conform to electrical & mechanical requirement stipulated in the specification. For
composite core conductor, suitable sleeve, collets, collet housing shall be used for core jointing.
Repair Sleeve of compression type shall be used to repair conductor with not more than two strands broken
in the outer layer. The sleeve shall be manufactured from 99.5% pure aluminium / aluminium alloy and shall
have a smooth surface. It shall be able to withstand the continuous maximum operating temperature of
conductor. The repair sleeve shall comprise of two pieces with a provision of seat for sliding of the keeper
piece. The edges of the seat as well as the keeper piece shall be so rounded that the conductor strands are not
damaged during installation. The dimensions of Repair sleeve along with tolerances shall be guaranteed in
the relevant schedules of the bid and shall be decided by the manufacturer so as to suit the conductor size &
conform to electrical & mechanical requirement stipulated in the specification.
3.21.1 Vibration dampers of 4R-stockbridge type with four (4) different resonances spread within the
specified aeolian frequency band width corresponding to wind speed of 1 m/s to 7 m/s are installed in the
existing line at suspension and tension points on each conductor in each span to damp out aeolian vibration
as well as sub- span oscillations. One damper minimum on each side per conductor for suspension points and
two dampers minimum on each side per conductor for tension points shall be used for a ruling design span of
320 meters.
3.21.2 The bidder shall offer damping system including Stockbridge type dampers for proposed HTLS
Conductor for its protection from wind induced vibrations which could cause conductor fatigue /strand
breakage near a hardware attachment, such as suspension clamps. Alternate damping systems with proven
design offering equivalent or better performance also shall be accepted provided the manufacturer meets the
qualifying requirements stipulated in the Specifications. Relevant technical documents including type test
reports to establish the technical suitability of alternate systems shall be furnished by the Bidder along with
the bid. The damper shall be designed to have resonance frequencies to facilitate dissipation of vibration
energy through inter-strand friction of the messenger cable and shall be effective in reducing vibration over a
wide frequency range (depending upon conductor dia) or wind velocity range specified above. The vibration
damper shall meet the requirement of frequency or wind velocity range and also have mechanical impedance
closely matched with the offered HTLS conductor. The vibration dampers shall be installed at suitable
positions to ensure damping effectiveness across the frequency range. The power dissipation of the vibration
dampers shall exceed the wind power so that the vibration level on the conductor is reduced below its
endurance limit i.e 150 micro strain. The bidder shall clearly indicate the method for evaluating performance
of dampers including analytical and laboratory test methods. The bidder shall indicate the type tests to
evaluate the performance of offered damping system.
3.21.3 The clamp of the vibration damper shall be made of high strength aluminium alloy of type LM-6. It
shall be capable of supporting the damper and prevent damage or chafing of the conductor during erection or
continued operation. The clamp shall have smooth and permanent grip to keep the damper in position on the
conductor without damaging the strands or causing premature fatigue failure of the conductor under the
clamp. The clamp groove shall be in uniform contact with the conductor over the entire clamping surface
except for the rounded edges. The groove of the clamp body and clamp cap shall be smooth, free from
projections, grit or other materials which could cause damage to the conductor when the clamp is installed.
Clamping bolts shall be provided with self-locking nuts and designed to prevent corrosion of threads or
loosening in service.
3.21.4 The messenger cable shall be made of high strength galvanized steel/stain less steel with a minimum
strength of 135 kg/sqmm. It shall be of preformed and post formed quality in order to prevent subsequent
drop of weight and to maintain consistent flexural stiffness of the cable in service. The number of strands in
the messenger cable shall be 19. The messenger cable other than stainless steel shall be hot dip galvanised in
accordance with the recommendations of IS: 4826 for heavily coated wires.
3.21.5 The damper mass shall be made of hot dip galvanised mild steel/cast iron or a permanent mould cast
zinc alloy. All castings shall be free from defects such as cracks, shrinkage, inclusions and blowholes etc.
The surface of the damper masses shall be smooth.
3.21.6 The damper clamp shall be casted over the messenger cable and offer sufficient and permanent grip
on it. The messenger cable shall not slip out of the grip at a load less than the mass pull-off value of the
damper. The damper masses made of material other-than zinc alloy shall be fixed to the messenger cable in a
suitable manner in order to avoid excessive stress concentration on the messenger cables which shall cause
premature fatigue failure of the same. The messenger cable ends shall be suitably and effectively sealed to
prevent corrosion. The damper mass made of zinc alloy shall be casted over the messenger cable and have
sufficient and permanent grip on the messenger cable under all service conditions.
3.21.7 The damper assembly shall be so designed that it shall not introduce radio interference beyond
acceptable limits.
3.21.8 The vibration damper shall be capable of being installed and removed from energised line by means
of hot line technique. In addition, the clamp shall be capable of being removed and reinstalled on the
conductor at the designated torque without shearing or damaging of fasteners.
3.21.9 The contractor must indicate the clamp bolt tightening torque to ensure that the slip strength of the
clamp is maintained between 2.5 kN and 5 kN. The clamp when installed on the conductor shall not cause
excessive stress concentration on the conductor leading to permanent deformation of the conductor strands
and premature fatigue failure in operation.
3.21.10 The vibration analysis of the system, with and without damper and dynamic characteristics of the
damper as detailed under Annexure-A, shall have to be submitted. The technical particulars for vibration
analysis and damping design of the system are as follows:
3.21.11 The damper placement chart shall be submitted for spans ranging from 100m to 1100m. Placement
charts should be duly supported with relevant technical documents and sample calculations.
Location of the dampers for various combinations of spans and line tensions clearly indicating the number of
dampers to be installed per conductor per span.
Placement distances clearly identifying the extremities between which the distances are to be measured.
Placement recommendation depending upon type of suspension clamps (viz Free centre type/Armour grip
type etc.)
The influence of mid span compression joints, repair sleeves and armour rods (standard and AGS) in the
placement of dampers.
3.22 PG Clamp, Come Along Clamp, T-Clamp, CVT Clamp, CB Clamp, CT&PT clamp, Pad clamp
for substation Bay stringing by HTLS conductor.
a. Standard Specification and tests shall be as per IS:5561.
b. Bolts, nuts and washers shall be made of mild steel and hot dip galvanized as per IS 2629. Small fittings
like spring washers, nuts etc. may be electro-galvanised.
c. The quality of HDG ferrous components shall be determined by the test given in IS:2633 and shall satisfy
the requirement of that standard.
d. The rated short time current shall be one of the standard values laid down in Indian Standards for the
associated circuit breakers, Switches etc.
e. Current carrying capacity same as conductor full current rating. For two different conductors, conductor
with smaller rating shall be considered.
f. No part of a clamp shall be less than 15 mm thick for fittings suitable for offered HTLS conductor, All
sharp edges and corners shall be blurred and rounded off.
g. For bimetallic connectors, copper alloy liner of minimum thickness of 2 mm shall be cast integral with
aluminium body.
h. From outermost hole edge to nearest edge of any clamps and connectors the distance shall not be less than
10 mm.
3.23 Materials
The materials of the various components shall be as specified hereunder. The Bidder shall indicate the
material proposed to be used for each and every component of hardware fittings stating clearly the
class, grade or alloy designation of the material, manufacturing process & heat treatment details and the
reference standards.
3.23.1 The details of materials for different component are listed as in Table No-1 (b).
TABLE-1 (b)
(Details of Materials)
Sr. No. Name of item Material Process of Reference Remarks
treatment Standard
1 Security Clips Stainless Steel/ - AISI 302 or 304-
Phospher L/ IS- 1385
Bronze
2 For Free Centre /Envelope type clamps/PG Clamp/Come along clamp
a. Clamp Body, High Strength Casted or
Keeper Piece Al. Alloy 4600/ forged & Heat IS:617or ASTM-
LM-6 or treated B429
6061/65032
b. Cotter bolts/ Mild Steel Hot dip As per IS-226 or
Hangers, Shackles, galvanised IS-2062
Brackets
c. U Bolts Stainless Steel Forged & & AISI 302 or 304-L
or High Strength Heat treated ASTM B429
Al Alloy
6061/65032
d. P. A. Rod High Strength Heat treatment ASTM-B429 Min. tensile
Al. Alloy 4600/ during strength of
LM-6 or manufacturing 35 kg/mm2
6061/65032
3 For AGS type clamp
High Strength
Corrosion Casted or
(a) Supporting House resistant forged & Heat S:617or ASTM-
Al.Alloy 4600/ treated B429
LM-6 or
6061/65032
High Strength High
Al insert & Al. Alloy 4600/ Casted or S:617or ASTM- Strength Al.
(b) Retaining strap LM-6 forged I & Heat B429 Alloy 4600/
or 6061/65032 treated LM-6
or
6061/65032
(c) Elastomer Molded on Al.
reinforcement
4. For Dead End Assembly
EC grade Al of
(a) Outer Sleeve purity not less
than99.50%
Hot Dip
(b) Steel Sleeve Mild Steel Galvanised IS:226/ IS-2062
5. Ball & Socket Class-IV Steel Drop forged &
Fittings, normalized Hot As per IS: 2004
dip galvanised
Hot dip As per IS-226 or
6. Yoke Plate Mild Steel galvanized IS-2062
High Strength Mechanical
Al. Alloy tube strength of
7. Corona Control (6061/6063/ Heat treated ASTM-B429 or welded joint
ring/ t Grading ring 1100 Hot dip as per IS shall
ype or 65032/ galvanized not be less
63400 than 20 kN
Supporting than 20 High strength Al Heat treated ASTM-B429 or
8. Brackets & Alloy 7061/ Hot dip as per IS:226 or
Mounting Bolts 6063/ galvanized S:2062
65032/63400
Type) or Mild
Steel
Note: Alternate materials conforming to other national standards of other countries also may be offered
provided the properties and compositions of these are close to the properties and compositions of
material specified. Bidder should furnish the details of comparison of material offered viz a viz specified
in the bid or else the bids are liable to be rejected.
3.24 Workmanship
3.24.1 All the equipment shall be of the latest design and conform to the best modern practices adopted in the
Extra High Voltage field. The Bidder shall offer only such equipment as guaranteed by him to be satisfactory
and suitable for 132 kV transmission lines and will give continued good performance
3.24.2 High current, heat rise test shall be conducted by the supplier to determine the maximum temperature
achieved in different components of fittings / accessories under simulated service condition corresponding to
operation of conductor at maximum (emergency) operating temperature. The material of the components
should be suitable for continued good performance corresponding to these maximum temperatures. The
supplier shall submit relevant type/performance test certificates as per applicable standards/product
specifications to confirm suitability of the offered material.
3.24.3 The design, manufacturing process and quality control of all the materials shall be such as to give the
specified mechanical rating, highest mobility, elimination of sharp edges and corners to limit corona and
radio-interference, best resistance to corrosion and a good finish.
3.24.4 All ferrous parts including fasteners shall be hot dip galvanised, after all machining has been
completed. Nuts may, however, be tapped (threaded) after galvanising and the threads oiled. Spring washers
shall be electro galvanized. The bolt threads shall be undercut to take care of the increase in diameter due to
galvanizing. Galvanizing shall be done in accordance with IS 2629 / IS 1367 (Part-13) and shall satisfy the
tests mentioned in IS 2633. Fasteners shall withstand four dips while spring washers shall withstand three
dips of one minute duration in the standard Preece test. Other galvanized materials shall have a minimum
average coating of zinc equivalent to 600 gm/sqm., shall be guaranteed to withstand at least six successive
dips each lasting one (1) minute under the standard Preece test for galvanizing.
3.24.5 Before ball fittings are galvanized, all die flashing on the shank and on the bearing surface of the ball
shall be carefully removed without reducing the dimensions below the design requirements.
3.24.6 The zinc coating shall be perfectly adherent, of uniform thickness, smooth, reasonably bright,
continuous and free from imperfections such as flux, ash rust, stains, bulky white deposits and blisters. The
zinc used for galvanising shall be grade Zn 99.95 as per IS: 209.
3.24.7 Pin balls shall be checked with the applicable “GO” gauges in at least two directions. one of which
shall be across the line of die flashing, and the other 90o to this line. "NO GO" gauges shall not pass in any
direction.
3.24.8 Socket ends, before galvanising, shall be of uniform contour. The bearing surface of socket ends shall
be uniform about the entire circumference without depressions of high spots. The internal contours of socket
ends shall be concentric with the axis of the fittings as per IS: 2486/IEC: 120.
The axis of the bearing surfaces of socket ends shall be coaxial with the axis of the fittings. There shall be no
noticeable tilting of the bearing surfaces with the axis of the fittings.
3.24.9 In case of casting, the same shall be free from all internal defects like shrinkage, inclusion, blow
holes, cracks etc. Pressure die casting shall not be used for casting of components with thickness more than 5
mm.
3.24.10 All current carrying parts shall be so designed and manufactured that contact resistance is reduced to
minimum.
3.24.11 No equipment shall have sharp ends or edges, abrasions or projections and cause any damage to the
conductor in any way during erection or during continuous operation which would produce high electrical
and mechanical stresses in normal working. The design of adjacent metal parts and mating surfaces shall be
such as to prevent corrosion of the contact surface and to maintain good electrical contact under service
conditions.
3.24.12 All the holes shall be cylindrical, clean cut and perpendicular to the plane of the material. The
periphery of the holes shall be free from burrs.
3.24.13 All fasteners shall have suitable corona free locking arrangement to guard against vibration
loosening.
3.24.14 Welding of aluminium shall be by inert gas shielded tungsten arc or inert gas shielded metal arc
process Welds shall be clean, sound, smooth, uniform without overlaps, properly fused and completely
sealed.
There shall be no cracks, voids incomplete penetration, incomplete fusion, under-cutting or inclusions.
Porosity shall be minimised so that mechanical properties of the aluminium alloys are not affected. All welds
shall be properly finished as per good engineering practices.
3.25.3 All drawings shall be identified by a drawing number and contract number. All drawings shall be
neatly arranged. All drafting & lettering shall be legible. The minimum size of lettering shall be 3 mm. All
dimensions & dimensional tolerances shall be mentioned in mm.
The drawings shall include:
i) Dimensions and dimensional tolerance.
ii) Material, fabrication details including any weld details & any specified finishes & coatings. Regarding
material designation & reference of standards are to be indicated.
iii) Catalogue No.
iv) Marking
v) Weight of assembly
vi) Installation instructions
vii) Design installation torque for the bolt or cap screw.
viii) Withstand torque that may be applied to the bolt or cap screw without failure of component parts.
ix) The compression die number with recommended compression pressure.
x) Placement charts for damper.
xi) All other relevant terminal details.
3.25.4 After placement of award, the Contractor shall submit fully dimensioned drawing including all the
components in four (4) copies to the Owner for approval. After getting approval from the Owner and
successful completion of all the type tests, the Contractor shall submit ten (10) more copies of the same
drawings to the Owner for further distribution and field use at Employer’s end.
Die compression areas shall be clearly marked, on each equipment designed for continuous die compressions
and shall bear the words ‘COMPRESS FIRST’ ‘suitably inscribed on each equipment where the compression
begins. If the equipment is designed for intermittent die compressions, it shall bear the identification marks
‘COMPRESSION ZONE’ and ‘NON-COMPRESSION ZONE’ distinctly with arrow marks, showing the
direction of compression and knurling marks showing the end of the zones. The letters, number and other
markings on finished equipment shall be distinct and legible.
Note: 1) All the type test given in Clause No. 3.27.1.1 shall be conducted on complete single
suspension & Single Tension insulator unit.
2) All the type tests given under Clause No. 3.27.1.1 (a) to (e) shall also be conducted on
Single I Pilot, Double I Suspension & Double Tension insulator unit
3.27.8 Type tests specified under Clause 3.27.1 to 3.27.7 shall not be required to be carried out if a valid test
certificate is available for a similar design, i.e., tests conducted earlier should have been conducted in
accredited laboratory (accredited based on ISO/IEC guide 25/17025 or EN 45001 by the National
Accreditation body of the country where laboratory is located) or witnessed by the representative (s)
Central/State Power Utility.
In the event of any discrepancy in the test report (i.e., any test report not applicable due to any design /
material/manufacturing process change including substitution of components or due to non-compliance with
the requirement stipulated in the Technical Specification) the tests shall be conducted by the Contractor at no
extra cost to the Employer/ Employer/ Employer.
f. Clamp Slip strength Vs Torque test for suspension clamp: As per Annexure-B 2
g. Shore hardness test of elastomer cushion for
AG suspension clamp : As per Annexure-B 2
h. Bend test for armour rod set : As per IS:2121(Part-I),
Clause 7.5,7,10 & 7.11
i. Resilience test for armour rod set : As per IS:2121(Part-I),
Clause 7.5,7,10 & 7.11
j. Conductivity test for armour rods set : As per IS:2121(Part-I),
Clause 7.5,7,10 & 7.11
i. Slip strength test for dead end assembly : As per IS:2486 (Part-I) Clause 5.4
j. Ageing test on filler (if applicable) : As per Annexure-C 2
* Applicable for 4 R stockbridge dampers. For alternate type of vibration dampers (permitted as per
clause 3.27), as an alternative to dynamic characteristic test, damper efficiency test as per IEEE-664
may be proposed/ carried out by the supplier.
3.30.2 In case type testing is required due to non-availability of type test reports, or type test on the complete
insulator string, the Contractor has to arrange similar insulators at his own cost.
3.30.3 Bidder shall indicate the laboratories in which they propose to conduct the type tests. They shall
ensure that adequate facilities for conducting the tests are available in the laboratory and the tests can be
completed in these laboratories within the time schedule guaranteed by them in the appropriate schedule.
3.30.4 The entire cost of testing for type tests, acceptance and routine tests and tests during manufacture
specified herein shall be treated as included in the quoted Ex-works/CIF Price.
3.30.5 In case of failure in any type test, repeat type tests are required to be conducted, then, all the expenses
for deputation of Inspector/ Owner’s representative shall be deducted from the contract price. Also, if on
receipt of the Contractor's notice of testing, the Owner’s representative/Inspector does not find material &
facilities to be ready for testing the expenses incurred by the Owner’s for re- deputation shall be deducted
from contract price.
3.30.6 The Contractor shall intimate the Owner about carrying out of the type tests along with detailed
testing programme at least 3 weeks in advance of the scheduled date of testing during which the Owner will
arrange to depute his representative to be present at the time of carrying out the tests.
3.31.1 The Bidder has to indicate the schedule of following activities in their bids
i. Submission of drawing for approval.
ii. Submission of Quality Assurance programme for approval.
iii. Offering of material for sample selection for type tests.
iv. Type testing.
3.31.2 The Owner reserves the right of having at his own expense any other test(s) of reasonable nature
carried out at Contractor’s premises, at site, or in any other place in addition to the aforesaid type, acceptance
and routine tests to satisfy himself that the material comply with the specifications.
3.31.3 The Owner also reserves the right to conduct all the tests mentioned in this specification at his own
expense on the samples drawn from the site at Contractor’s premises or at any other test centre. In case of
evidence of noncompliance, it shall be binding on the part of Contractor to prove the compliance of the items
to the technical specifications by repeat tests, or correction of deficiencies, or replacement of defective items,
all without any extra cost to the Owner.
3.32 Test Reports
3.32.1 Copies of type test report shall be furnished in at least six copies along with one original. One copy
shall be returned, duly certified by the Owner, only after which the commercial production of the concerned
material shall start.
3.32.2 Copies of acceptance test report shall be furnished in at least six copies. One copy shall be returned,
duly certified by the Owner, only after which the materials will be despatched.
3.32.3 Record of routine test report shall be maintained by the Contractor at his works for periodic inspection
by the Owner’s representative.
3.32.4 Test certificates of tests during manufacture shall be maintained by the Contractor. These shall be
produced for verification as and when desired by the Owner.
3.33 Inspection
3.33.1 The Owner’s representative shall at all times be entitled to have access to the works and all places of
manufacture, where the material and/or its component parts shall be manufactured and the representatives
shall have full facilities for unrestricted inspection of the Contractor’s, sub- Contractor’s works raw
materials. manufacturers of all the material and for conducting necessary tests as detailed herein.
3.33.2 The material for final inspection shall be offered by the Contractor only under packed condition. The
engineer shall select samples at random from the packed lot for carrying out acceptance tests.
3.33.3 The Contractor shall keep the Employer informed in advance of the time of starting and of the
progress of manufacture of material in its various stages so that arrangements could be made for inspection.
3.33.4 Material shall not be dispatched from its point of manufacture before it has been satisfactorily
inspected and tested unless the inspection is waived off by the Owner in writing. In the latter case also, the
material shall be dispatched only after all tests specified herein have been satisfactorily completed.
3.33.5 The acceptance of any quantity of material shall in no way relieve the Contractor of his responsibility
for meeting all the requirements of the Specification, and shall not prevent subsequent rejection, if such
materials are later found to be defective.
3.34.1 All material shall be packed in strong and weather resistant wooden cases/crates. The gross weight of
the packing shall not normally exceed 200 Kg to avoid handling problems.
3.34.2 The packing shall be of sufficient strength to withstand rough handling during transit, storage at site
and subsequent handling in the field.
3.34.3 Suitable cushioning, protective padding, dunnage or spacers shall be provided to prevent damage or
deformation during transit and handling.
3.34.4 Bolts, nuts, washers, cotter pins, security clips and split pins etc. shall be packed duly installed and
assembled with the respective parts and suitable measures shall be used to prevent their loss.
3.34.5 Each component part shall be legibly and indelibly marked with trade mark of the manufacturer and
year of manufacture. However, in such type of component/item, which consists of many parts and are being
supplied in assembled condition (suspension clamp, vibration damper, etc.), the complete assembly shall be
legibly and indelibly marked on main body/on one of the parts.
3.34.6 All the packing cases shall be marked legibly and correctly so as to ensure safe arrival at their
destination and to avoid the possibility of goods being lost or wrongly despatched on account of faulty
packing and faulty or illegible markings. Each wooden case/crate shall have all the markings stencilled on it
in indelible ink.
3.35 Standards
3.35.1 The Hardware fittings; conductor and earthwire accessories shall conform to the following
Indian/International Standards which shall mean latest revisions, with amendments/changes adopted and
published, unless specifically stated otherwise in the Specification.
3.35.2 In the event of the supply of hardware fittings; conductor accessories conforming to standards other
than specified, the Bidder shall confirm in his bid that these standards are equivalent to those specified. In
case of award, salient features of comparison between the Standards proposed by the Contractor and those
specified in this document will be provided by the Contractor to establish their equivalence.
The voltage across each insulator unit shall be measured by sphere gap method. The result obtain shall
be converted into percentage. The voltage across any disc shall not exceed 9% for suspension insulator
strings and 10% for tension insulator strings.
The suspension string shall be tested in suspension mode, and tension string in tension mode itself in
laboratory span of minimum 30 metres. In the case of suspension string a load equal to 600kg shall be
applied along the axis of the suspension string by means of turn buckle. The insulator string along with
hardware fittings and four sub-conductors (each tensioned at 43kN shall be secured with clamps. The
system shall be suitable to maintain constant tension on each sub-conductors throughout the duration of
the test. Vibration dampers shall not be used on the test span. Both the sub-conductors shall be
vertically vibrated simultaneously at one of the resonance frequencies of the insulators string(more than
10 Hz) by means of vibration inducing equipment. The peak to peak displacement in mm of vibration
at the antinode point, nearest to the string, shall be measured and the same shall not be less than
1000/f1.8 where f is the frequency of vibration in cycle/sec. The insulator string shall be vibrated for
not less than 10million cycles without any failure. After the test the disc insulator shall be examined for
looseness of pins and cop or any crack in the cement. The hardware shall be
examined for looseness, fatigue failure and mechanical strength test. There shall be no deterioration of
properties of hardware components and composite long rod/disc insulators after the vibration test.
The composite long rod insulators shall be subjected to the Mechanical performance test followed by
mechanical strength test as per relevant standards.
The Disc insulators shall be subjected to the following tests as per relevant standards.
Two hollow aluminium tubes of 32 mm diameter for the conductor shall be placed 450 mm apart
respectively. An alternating current over the range of 1000 to 1500 amperes shall be passed through
each tube. The reading of the wattmeter with and without suspension assemblies along with line side
yoke plate, clevis eye shall be recorded. Not less than three suspension assemblies shall be tested. The
average power loss for suspension assembly shall be plotted for each value of current. The value of the
loss corresponding to 875 (132Kv) 1200 amperes shall be read off from the graph and the same shall be
limited to the value guaranteed by the supplier.
1.12 Shore Hardness Test for Elastomer Cushion for AG Suspension Assembly
The shore hardness at various points on the surface of the elastomer cushion shall be measured by a
shore hardness meter and the shore hardness number shall be between 65 to 80.
Heating cycle test shall be performed in accordance with IS 2121 (Part-II-1981) with following
modifications: -
i. Temperature of conductor during each cycle: 40 deg. C above designed maximum operating temperature
of the conductor.
ii. Number of cycles: 100
iii. Slip strength test shall also be carried out after heating cycle test.
i. The above dynamic characteristics test on five dampers shall be conducted. The above dynamic
characteristics test on five dampers shall be conducted.
ii. The mean reactance and phase angle Vs frequency curves shall be drawn with the criteria of best fit
method.
iii. The above mean reactance response curve should lie within 0.191 f to 0.762 f Kgf/mm limits where f is
frequency in Hz.
iv. The above mean phase angle response curve shall be between 25 o to 130o within the frequency range of
interest.
v. If the above curve lies within the envelope, the damper design shall be considered to have successfully
met the requirement.
vi. Visual resonance frequencies of each mass of damper are to be recorded and to be compared with the
guaranteed values.
(b) Vibration Analysis
The vibration analysis of the conductor shall be done with and without damper installed on the span. The
vibration analysis shall be done on a digital computer using energy balance approach. The following
parameters shall be taken into account for the purpose of analysis:
i) The analysis shall be done for single conductor without armour rods as per the parameters given of this
part of the Specification. The tension shall be taken from Sag & Tension calculation (o deg. C & no wind
condition and 350 m ruling span) for a span ranging from 50 m to 1100.
ii) The self damping factor and flexural stiffness (El) for conductor shall be calculated on the basis of
experimental results. The details for experimental analysis with these data should be furnished.
iii) The power dissipation curve obtained from Dynamic Characteristics Test shall be used for analysis with
damper.
iv) Examine the 941aeolian vibration level of the conductor with and without vibration damper installed at
the recommended location or wind velocity ranging from 0 to 30 Km per hour, predicting amplitude,
frequency and vibration energy input.
v) From vibration analysis of conductor without damper, anti-node vibration amplitude and dynamic strain
levels at clamped span extremities as well as antinodes shall be examined and thus lower and upper
dangerous frequency limits between which the Aeolian vibration levels exceed the specified limits shall be
determined.
vi) From vibration analysis of conductor with damper/dampers installed at the recommended location, the
dynamic strain level, at the clamped span extremities, damper attachment point and the antinodes on the
conductor shall be determined. In addition to above damper clamp vibration amplitude and anti-node
vibration amplitudes shall also be examined.
The dynamic strain levels at damper attachment points, clamped span extremities and antinodes shall not
exceed the specified limits. The damper clamp vibration amplitude shall not be more than that of the
specified fatigue limits.
(c) Clamp Slip and Fatigue Tests
i) Test Set Up
The clamp slip and fatigue tests shall be conducted on a laboratory set up with a minimum effective
span length of 30 m. The conductor shall be tensioned at tension corresponding to 0 deg & no wind
condition and ruling span 350 from sag –tension calculation and shall not be equipped with protective
armour rods at any point. Constant tension shall be maintained within the span by means of lever arm
arrangement. After the conductor has been tensioned, clamps shall be installed to support the conductor
at both ends and thus influence of connecting hardware fittings are eliminated from the free span. The
clamps shall not be used for holding the tension on the conductor. There shall be no loose parts, such as
suspension clamps, U bolts on the test span supported between clamps mentioned above. The span shall
be equipped with vibration inducing equipment suitable for producing steady standing vibration. The
inducing equipment shall have facilities for stepless speed control as well as stepless amplitude
arrangement. Equipment shall be available for measuring the frequency, cumulative number of cycles
and amplitude of vibration at any point along the span.
ii) Clamp Slip test
The vibration damper shall be installed on the test span. The damper clamp, after lightning with the
manufacturer’s specified tightening torque, when subjected to a longitudinal pull of 2.5 kN parallel to
the axis of conductor for a minimum duration of one minute shall not slip i.e. the permanent
displacement between conductor and clamp measured after removal of the load shall not exceed 1.0
mm. The load shall be further increased till the clamp starts slipping. The load at which the clamp slips
shall not be more than 5 kN.
iii) Fatigue Test
The vibration damper shall be installed on the test span with the manufacturer’s specified tightening
torque. It shall be ensured that the damper shall be kept minimum three loops away from the shaker to
eliminate stray signals influencing damper movement.
The damper shall then be vibrated at the highest resonant frequency of each damper mass. For dampers
involving resonant frequencies, tests shall be done at torsional modes also in addition to the highest
resonant frequencies at vertical modes. The resonance frequency shall be identified as the frequency at
which each damper mass vibrates with the maximum amplitude on itself. The amplitude of vibration of
the damper clamp shall be maintained not less than ± 25/f mm, where f is the frequency in Hz.
The test shall be conducted for minimum ten million cycles at each resonant frequency mentioned
above. During the, test if resonance shift is observed the test frequency shall be tuned to the new
resonant frequency.
The clamp slip test as mentioned hereinabove shall be repeated after fatigue test without re-torquing or
adjusting the damper clamp, and the clamp shall withstand a minimum load equal to 80% of the slip
strength for a minimum duration of one minute.
After the above tests, the damper shall be removed from conductor and subjected to dynamic
characteristics test. There shall not be any major deterioration in the characteristic of the damper. The
damper then shall be cut open and inspected. There shall not be any broken, loose, or damaged part.
There shall not be significant deterioration or wear of the damper. The conductor under clamp shall
also be free from any damage.
For the purpose of acceptance, the following criteria shall be applied.
a. There shall not be any frequency shift by more than +2 Hz for frequencies lower than 15 Hz and ± 3 Hz
for frequencies higher than 15 Hz.
b. The force response curve shall generally lie within guar anteed % variation in reactance after fatigue test
in comparison with that before fatigue test by the Contractor.
c. The power dissipation of the damper shall not be less than guaranteed % variation in power dissipation
before fatigue test by the Contractor. However, it shall not be less than minimum power dissipation which
shall be governed by lower limits of reactance and phase angle indicated in the envelope.
ANNEXURE – B 2
The voltage across each insulator unit shall be measured by sphere gap method. The result
obtain shall be converted into percentage. The voltage across any disc shall not exceed 9% for
suspension insulator strings and 10% for tension insulator strings.
The suspension string shall be tested in suspension mode, and tension string in tension mode
itself in laboratory span of minimum 30 metres. In the case of suspension string a load equal to
600kg shall be applied along the axis of the suspension string by means of turn buckle. The
insulator string along with hardware fittings and four sub-conductors (each tensioned at 43kN
shall be secured with clamps. The system shall be suitable to maintain constant tension on each
sub-conductor throughout the duration of the test. Vibration dampers shall not be used on the
test span. Both the sub-conductors shall be vertically vibrated simultaneously at one of the
resonance frequencies of the insulators string (more than 10 Hz) by means of vibration
inducing equipment. The peak to peak displacement in mm of vibration at the antinode point,
nearest to the string, shall be measured and the same shall not be less than 1000/f1.8 where f is
the frequency of vibration in cycle/sec. The insulator string shall be vibrated for not less than
10million cycles without any failure. After the test the disc insulator shall be examined for
looseness of pins and cop or any crack in the cement. The hardware shall be
examined for looseness, fatigue failure and mechanical strength test. There shall be no
deterioration of properties of hardware components and composite long rod/disc insulators
after the vibration test.
The composite long rod insulators shall be subjected to the Mechanical performance test
followed by mechanical strength test as per relevant standards.
The Disc insulators shall be subjected to the following tests as per relevant standards.
One hollow aluminium tubes of 29mm diameter for the conductor shall be used for 132KV.
An alternating current over the range of 300 amps to 700 shall be passed through the tube. The
reading of the wattmeter with and without suspension assemblies alongwith line side yoke
plate, clevis eye shall be recorded. Not less than three suspension assemblies shall be tested.
The average power loss for suspension assembly shall be plotted for each value of current. The
value of the loss corresponding to 300 Amperes shall be read off from the graph and the same
shall be limited to the value guaranteed by the supplier.
The test shall be done in accordance with Grease drop point test method. The specimen should
be drop as a droplet when kept at a temperature 40 deg. C above designed maximum operating
temperature of the conductor for 30 minutes. The temperature shall then be increase till one
droplet drops and the temperature recorded.
1.12 Shore Hardness Test for Elastomer Cushion for AG Suspension Assembly
The shore hardness at various points on the surface of the elastomer cushion shall be measured
by a shore hardness meter and the shore hardness number shall be between 65 to 80.
i. Temperature of conductor during each cycle: 40 deg. C above designed maximum operating
temperature of the conductor.
ii. Number of cycles: 100
iii. Slip strength test shall also be carried out after heating cycle test.
CHAPTER 39: TECHNICAL SPECIFICATION OF HTLS CONDUCTOR
i. The above dynamic characteristics test on five dampers shall be conducted. The above dynamic
characteristics test on five dampers shall be conducted.
ii. The mean reactance and phase angle Vs frequency curves shall be drawn with the criteria of best
fit method.
iii. The above mean reactance response curve should lie within 0.191 f to 0.762 f Kgf/mm limits
where f is frequency in Hz.
iv. The above mean phase angle response curve shall be between 25 o to 130o within the frequency
range of interest.
v. If the above curve lies within the envelope, the damper design shall be considered to have
successfully met the requirement.
vi. Visual resonance frequencies of each mass of damper are to be recorded and to be compared
with the guaranteed values.
(b) Vibration Analysis
The vibration analysis of the conductor shall be done with and without damper installed on the span.
The vibration analysis shall be done on a digital computer using energy balance approach. The
following parameters shall be taken into account for the purpose of analysis:
i) The analysis shall be done for single conductor without armour rods as per the parameters given
of this part of the Specification. The tension shall be taken from Sag & Tension calculation (o deg.
C & no wind condition and 320 m ruling span) for a span ranging from 50 m to 1100.
ii) The self-damping factor and flexural stiffness (El) for conductor shall be calculated on the basis
of experimental results. The details for experimental analysis with these data should be furnished.
iii) The power dissipation curve obtained from Dynamic Characteristics Test shall be used for
analysis with damper.
iv) Examine the vibration level of the conductor with and without vibration damper installed at the
recommended location or wind velocity ranging from 0 to 30 Km per hour, predicting amplitude,
frequency and vibration energy input.
v) From vibration analysis of conductor without damper, anti-node vibration amplitude and dynamic
strain levels at clamped span extremities as well as antinodes shall be examined and thus lower and
upper dangerous frequency limits between which the Aeolian vibration levels exceed the specified
limits shall be determined.
vi) From vibration analysis of conductor with damper/dampers installed at the recommended
location, the dynamic strain level, at the clamped span extremities, damper attachment point and the
CHAPTER 39: TECHNICAL SPECIFICATION OF HTLS CONDUCTOR
antinodes on the conductor shall be determined. In addition to above damper clamp vibration
amplitude and anti-node vibration amplitudes shall also be examined.
The dynamic strain levels at damper attachment points, clamped span extremities and antinodes
shall not exceed the specified limits. The damper clamp vibration amplitude shall not be more than
that of the specified fatigue limits.
(c) Clamp Slip and Fatigue Tests
i) Test Set Up
The clamp slip and fatigue tests shall be conducted on a laboratory set up with a minimum
effective span length of 30 m. The conductor shall be tensioned at tension corresponding to 0
deg & no wind condition and ruling span 320 from sag –tension calculation and shall not be
equipped with protective armour rods at any point. Constant tension shall be maintained within
the span by means of lever arm arrangement. After the conductor has been tensioned, clamps
shall be installed to support the conductor at both ends and thus influence of connecting
hardware fittings are eliminated from the free span. The clamps shall not be used for holding
the tension on the conductor. There shall be no loose parts, such as suspension clamps, U bolts
on the test span supported between clamps mentioned above. The span shall be equipped with
vibration inducing equipment suitable for producing steady standing vibration. The inducing
equipment shall have facilities for stepless speed control as well as stepless amplitude
arrangement. Equipment shall be available for measuring the frequency, cumulative number of
cycles and amplitude of vibration at any point along the span.
ii) Clamp Slip test
The vibration damper shall be installed on the test span. The damper clamp, after lightning
with the manufacturer’s specified tightening torque, when subjected to a longitudinal pull of
2.5 kN parallel to the axis of conductor for a minimum duration of one minute shall not slip i.e.
the permanent displacement between conductor and clamp measured after removal of the load
shall not exceed 1.0 mm. The load shall be further increased till the clamp starts slipping. The
load at which the clamp slips shall not be more than 5 kN.
iii) Fatigue Test
CHAPTER 39: TECHNICAL SPECIFICATION OF HTLS CONDUCTOR
The vibration damper shall be installed on the test span with the manufacturer’s specified tightening
torque. It shall be ensured that the damper shall be kept minimum three loops away from the shaker
to eliminate stray signals influencing damper movement.
The damper shall then be vibrated at the highest resonant frequency of each damper mass. For
dampers involving resonant frequencies, tests shall be done at torsional modes also in addition to the
highest resonant frequencies at vertical modes. The resonance frequency shall be identified as the
frequency at which each damper mass vibrates with the maximum amplitude on itself. The amplitude
of vibration of the damper clamp shall be maintained not less than ± 25/f mm, where f is the
frequency in Hz.
The test shall be conducted for minimum ten million cycles at each resonant frequency mentioned
above. During the, test if resonance shift is observed the test frequency shall be tuned to the new
resonant frequency.
The clamp slip test as mentioned hereinabove shall be repeated after fatigue test without re-torquing
or adjusting the damper clamp, and the clamp shall withstand a minimum load equal to 80% of the
slip strength for a minimum duration of one minute.
After the above tests, the damper shall be removed from conductor and subjected to dynamic
characteristics test. There shall not be any major deterioration in the characteristic of the damper.
The damper then shall be cut open and inspected. There shall not be any broken, loose, or damaged
part. There shall not be significant deterioration or wear of the damper. The conductor under clamp
shall also be free from any damage.
For the purpose of acceptance, the following criteria shall be applied.
a. There shall not be any frequency shift by more than +2 Hz for frequencies lower than 15 Hz and ±
3 Hz for frequencies higher than 15 Hz.
b. The force response curve shall generally lie within guar anteed % variation in reactance after
fatigue test in comparison with that before fatigue test by the Contractor.
c. The power dissipation of the damper shall not be less than guaranteed % variation in power
dissipation before fatigue test by the Contractor. However, it shall not be less than minimum power
dissipation which shall be governed by lower limits of reactance and phase angle indicated in the
envelope.
Samples taken from the zinc ingot shall be chemically analyzed as per IS-209-1979. The
purity of zinc shall not be less than 99.95%.
2.5.2 Tests for Forgings
The chemical analysis hardness tests and magnetic particle inspection for forgings, will be as
per the internationally recognized procedures for these tests. The, sampling will be based on
heat number and heat treatment batch. The details regarding test will be as discussed and
mutually agreed to by the Contractor and Employer in Quality Assurance Programme.
2.5.3 Tests on Castings
The chemical analysis, mechanical and metallographic tests and magnetic particle inspection
for castings will be as per the internationally 951ecognized procedures for these tests. The
samplings will be based on heat number and heat treatment batch. The details regarding test
will be as discussed and mutually agreed to by the Contractor and Employer in Quality
Assurance Programme.
ANNEXURE – C 1
Acceptance Tests
1. Mid Span Compression Joint for Conductor
a. Hardness Test
The Brinnel hardness at various points on the steel sleeve of conductor core and tension clamp
shall be measured.
2. Vibration Damper for Conductor
a. Verification of Resonance Frequencies
The damper shall be mounted on a shaker table and vibrate at damper clamp displacement of
+/-0.5 mm to determine the resonance frequencies. The resonance shall be visually identified
as the frequency at which damper mass vibrates with maximum displacement on itself. The
resonance frequency thus identified shall be compared with the guaranteed value. A tolerance
of ± 1 Hz at a frequency lower than 15 Hz and ± 2 Hz at a frequency higher than 15 Hz only
shall be allowed.
b. Clamp Slip Test
Same as Clause 2.2 I (ii) of Annexure-B.
c. Clamp Bolt Torque Test
The clamp shall be attached to a section of the conductor/earthwire. A torque of 150 percent of
the manufacturer’s specified torque shall be applied to the bolt. There shall be no failure of
component parts. The test set up is as described in Clause 2.2 I (i), Annexure-B.
d. Strength of the Messenger Cable
The messenger cable shall be fixed in a suitable tensile testing machine and the tensile load
shall be gradually applied until yield point is reached. Alternatively, each strand of messenger
cable may be fixed in a suitable tensile testing machine and the tensile load shall be gradually
applied until yield point is reached. In such a case, the 95% of yield strength of each wire shall
be added to get the total strength of the cable. The load shall be not less than the value
guaranteed by the Contractor.
e. Mass Pull off Test
CHAPTER 39: TECHNICAL SPECIFICATION OF HTLS CONDUCTOR
Each mass shall be pulled off in turn by fixing the mass in one jaw and the clamp in the other
of a suitable tensile testing machine. The longitudinal pull shall be applied gradually until the
mass begins to pull out of the messenger cable. The pull off loads shall not be less than the
value guaranteed by the Contractor.
f. Dynamic Characteristics Test
The test will be performed as acceptance test with the procedure mentioned for type test with
sampling mentioned below :
Vibration Damper of - 1 Sample for 1000 Nos. & below Conductor
- 2 Samples for lot above 1000 & up to 5000 nos
- Additional 1 sample for every additional 1500 technical specifications pieces above 5000.
iii. If individual results do not fall within the envelope, averaging of characteristics shall be done.
a. Force of each damper corresponding to particular frequency shall be taken & average force of
three dampers at the frequency calculated.
b. Similar averaging shall be done for phase angle.
c. Average force Vs frequency and average phase Vs frequency curves shall be plotted on graph
paper. Curves of best fit shall be drawn for the entire frequency range.
d. The above curves shall be within the envelope specified.
ANNEXURE – C 2
Acceptance Tests
1. Mid Span Compression Joint for Conductor
a. Hardness Test
The Brinnel hardness at various points on the steel sleeve of conductor core and tension
clamp shall be measured.
2. Vibration Damper for Conductor
a. Verification of Resonance Frequencies
The damper shall be mounted on a shaker table and vibrate at damper clamp displacement of
+/-0.5 mm to determine the resonance frequencies. The resonance shall be visually identified
as the frequency at which damper mass vibrates with maximum displacement on itself. The
resonance frequency thus identified shall be compared with the guaranteed value. A tolerance
of ± 1 Hz at a frequency lower than 15 Hz and ± 2 Hz at a frequency higher than 15 Hz only
shall be allowed.
b. Clamp Slip Test
CHAPTER 39: TECHNICAL SPECIFICATION OF HTLS CONDUCTOR
c. Average force Vs frequency and average phase Vs frequency curves shall be plotted on graph
paper. Curves of best fit shall be drawn for the entire frequency range.
d. The above curves shall be within the envelope specified.
CHAPTER 39: TECHNICAL SPECIFICATION OF HTLS CONDUCTOR