Professional Documents
Culture Documents
Nisoc: Quality Contorol Plan (QCP)
Nisoc: Quality Contorol Plan (QCP)
PAGE D00 D01 D02 D03 D04 PAGE D00 D01 D02 D03 D04
1 X 66
2 X 67
3 X 68
4 X 69
5 X 70
6 X 71
7 X 72
8 X 73
9 X 74
10 X 75
11 X 76
12 X 77
13 X 78
14 X 79
15 X 80
16 X 81
17 X 82
18 X 83
19 X 84
20 X 85
21 X 86
22 X 87
23 X 88
24 X 89
25 X 90
26 91
27 92
28 93
29 94
30 95
31 96
32 97
33 98
34 99
35 100
36 101
37 102
38 103
39 104
40 105
41 106
42 107
43 108
44 109
45 110
46 111
47 112
48 113
49 114
50 115
51 116
52 117
53 118
54 119
55 120
56 121
57 122
58 123
59 124
60 125
61 126
62 127
63 128
64 129
65 130
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
CONTENTS
1. INTRODUCTION ............................................................................................................................................. 4
2. GENERAL DEFINATION …………………………………….……….……………………………………………..5
3. PURPOSE ....................................................................................................................................................... 5
4. SCOPE ............................................................................................................................................................ 6
5. DEFINITIONS & ABBREVIATION .................................................................................................................. 7
6. QUALITY OBJECTIVES ................................................................................................................................. 8
7. ROLES, RESPONSIBILITY, AUTHORITY AND COMMUNICATION ............................................................ 9
ROLES, RESPONSIBILITIES .............................................................................................................................................. 9
7.1 PROJECT ROLES AND JOB PROFILE ................................................................................................................ 9
7.2 RESPONSIBILITY AND AUTHORITY .................................................................................................................... 9
8. CONTROL OF DOCUMENTED INFORMATIONS ....................................................................................... 11
8.1 CONTROL OF DOCUMENTS ............................................................................................................................ 11
8.2 CONTROL OF RECORDS ................................................................................................................................ 11
8.3 DOCUMENTATIONS FOR QUALITY CONTROL ................................................................................................... 12
9. PREPARATION AND QUALIFICATION OF WELDING PROCEDURES………...………………………….12
9.1 QUALIFICATION OF WELDERS………………………………………………………………………………….12
9.2 FILED QUALITY CONTOROL ……………………………………………………………………………………13
9.3 RADIOGRAPHY AND OTHER NON-DESTRUCTIVE METHODS ………………………………..…………14
10. INSPECTION AND TEST PLANS................................................................................................................. 15
11. QUALITY CONTROL PROCEDURES AND STANDARD PRACTICES………………………………...…….16
12 QC SUPPLEMENTARY DOCUMENTS…………………………………………………………………..………18
12.1 TEST AND INSPECTION DOCUMENTATION……………………………………………………………………..…..…18
12.2 RECORD FILE OF QC DOCUMENTATION…………………………………………………………………………..…18
12.3 HAND OVER OF AS-BUILT DOCUMENTS………………………………………………………………………19
13. CONTROL OF MONITORING AND MEASURING DEVICES ................................................................................... 19
14. EXTERNALLY PROVIDED PROCESSES, PRODUCTS AND SERVICES ................................................. 20
15. PRODUCTION AND SERVICE PROVISION ................................................................................................ 20
16. PURCHASING ............................................................................................................................................... 20
17. PURCHASING PROCESS ................................................................................................................................ 22
17.1 PURCHASING INFORMATION .......................................................................................................................... 22
17.2 VERIFICATION OF PURCHASED PRODUCT ....................................................................................................... 22
17.3 CONTROL OF PRODUCTION, FABRICATION, CONSTRUCTION, COMMISSIONING AND SERVICE PROVISION .......... 23
18. IDENTIFICATION AND TRACEABILITY………………………………………………………………...………23
19. OPERATION.................................................................................................................................................. 24
19.1 PLANNING AND CONTROL .............................................................................................................................. 24
19.2 MONITORING AND MEASUREMENT OF PROCESSES ........................................................................................ 24
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
1. INTRODUCTION
Binak oilfield in Bushehr province is a part of the southern oilfields of Iran, is located 20 km
northwest of Genaveh city.
With the aim of increasing production of oil from Binak oilfield, an EPC/EPD Project has
been defined by NIOC/NISOC and awarded to Petro Iran Development Company
(PEDCO). Also PEDCO (as General Contractor) has assigned the EPC-packages of
the Project to "Hirgan Energy - Design and Inspection" JV.
2. GENERAL DEFINITION
3. PURPOSE
“Hirgan Energy - Design and Inspection “has implemented a Quality Management System to
satisfy the needs of Client and to improve management of the project as per project contractual
requirements. This Project Quality Plan shows the structure of the Quality Management System
and describes how it works and introduces the policy and procedures or references used by
Contractor to ensure conformance to the necessary requirements of international standards: ISO
9001 and additional contractual requirements of Integrated Management Systems (IMS). It also
delineates authorities, interrelationships and responsibilities of the personnel responsible for
performing within the system. This Project Quality Plan is used internally to guide the
Contractor's employees through the various requirements of the ISO 9001 standard which will be
met and maintained in order to ensure customer satisfaction obligation and policy, continuous
improvement of the processes and provide the necessary instructions that create an empowered
workforce.
This Project Quality Plan is used externally to introduce our Quality Management System to our
relevant interested parties and other external organizations. The Project Quality Plan is used to
familiarize them within the implemented controls at the project, to assure them that the integrity
of the Quality Management System is maintained, focused on customer satisfaction and
continuous improvement.
One of the main priorities of “Hirgan Energy - Design and Inspection “is to maintain high quality
of the works and to improve continuously the Quality System. The present manual covers all
construction quality assurance and quality control procedures, practices and documentation, as
follows:
QUALIFICATION OF WELDERS.
- Ultrasonic inspection,
- Magnetic particle inspection,
- Liquid penetrant inspection,
- Preparation of welding books and welding inspection reports,
- Supervision of pipeline/flow line pigging and gauging,
- Supervision of hydrostatic testing,
- Completion of the documentation,
4. SCOPE
The quality plan is applicable to all of quality management actions in the process of project
management, design, procurement, construction, pre-commissioning, commissioning, handover
and startup.
PROJECT DETAILS
In the surface part of this project and according to the policies made, the National
Iranian South Oilfields Company intends a set of gas pressure density, including the
construction of two rows with a row of reciprocating electric compressor tow with a
total capacity of 15 MFMR Build the firm using new technologies and advanced
control system. According to the technical, economic and environmental studies and
also the review of available options, it has been decided to build a Binak gas pressure
compression complex near the existing gas facilities.
Also, in the surface part of this project and due to the increase in the oil flow of Binak
field, the construction of 8-inch underground gas transmission pipelines and 4-inch
aboveground gas transmission pipelines is on the agenda of the National Iranian
South Oil Fields Company.
In the underground part of this project, construction of location and access road to
wells of 6 newly constructed wells (2 of which need power supply and other related
facilities for in-well pump use) and modifications to 4 existing wells (Along with
electricity supply for pump use in wells and other required facilities) is on the agenda
of the National Iranian South Oil Fields Company. In addition, the construction of 6
new flow pipelines from the aforementioned development wells to the Booster-Cluster
Binak complex and the development of the existing multi-way Booster-Cluster Binak
are among the job descriptions of this project.
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
For the purposes of this document, the following terms and definitions apply:
6. QUALITY OBJECTIVES
Contractor's Project Manager ensures that Project Quality Objectives are established at relevant
functions and levels. The objectives are measurable and consistent with the quality policy. Our
Project Quality Objectives are:
from Project schedule will be analyzed to find deviation causes. Then the
suitable compensation plan will be provided and followed up by responsible
specialists which will be defined by Project Manager.
ROLES, RESPONSIBILITIES
This is the responsibility of QA/QC manager to performance this document (PQP) as the template
and guideline for Project Quality Plan requirement of contractor.
Project Manager:
Project manager is responsible to manage the PROJECT scope, time, cost according
to the contract and also ensure all rules, regulations and standards are met to satisfy
the relevant interested parties of the PROJECT with acceptable level of risk and use of
all possible opportunities.
The Project Manager is responsible for overall Project's Quality requirements and
ensures its implementation. He shall provide all necessary resources (budget,
manpower and technical affairs, etc.) to fulfil the Project quality and schedule. He will
fully support the team of quality, auditors and inspectors.
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
Project Manager is also owner and responsible against the Project Quality Plan and
ensure all its requirements are met during the execution of the project.
The Project QA/QC Manager is responsible to manage for Quality of project work
performance and accomplishments. All technical documents required to be reviewed
shall be according to quality requirements. The Project QA/QC Manager works directly
and closely with Project Manager.
The Project Engineering Manager is responsible for Project technical issues
including, design review, verification and validation issues in activities such as
preparation, review, approval, distribution and maintaining up to date project technical
documents and technical communications.
The Project HSE Manager is responsible for ensuring the health, safety and welfare of
all personnel involved in the performance and/or inspection of the work, and also
responsible for the risk management issues from the beginning of the PROJECT. This
person will act according to the requirements of the “Risk Management Procedure” and
will follow-up the risks and opportunities of the project.
The Project Planning and Control Manager is responsible for planning, scheduling,
progress measurement, and reporting, invoicing, and cost control to all phase of the
work. It is possible to exclude cost controlling to independent discipline according to the
scale and scope of the PROJECT and the project structure to cover the strategy and
objectives of the COMPANY.
The Project Procurement Representative is responsible for all Procurement activities
of project. The inspection and quality measures shall be fully communicated among
both procurement and quality teams to assure the quality policy.
The Site Manager is responsible for Quality of Site work performance and
accomplishments. All technical documents required to be reviewed shall be according
to quality requirements. The Site Manager works directly and closely with QA/QC
manager to ensure the effective quality level and minimize the project quality risk of work
to the acceptable risk level with the appropriate risk strategy defined in risk assessment
table.
Project Employees - All employees are responsible for the quality of their work and
implementation of the Quality Policy, IMS requirements and procedures applicable to
processes they perform. Employees are motivated and empowered to identify and
report any known or potential problems and issues then recommend related
solutions through internal audits and/or the continual improvement, risk/opportunity and
corrective action processes.
Responsibility Assignment Matrix: Responsibilities of project team against different
tasks have been defined in the Responsibility Assignment Matrix. (Attachment)
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
To satisfy the COMPANY requirement, Project DCC or documentation responsible persons are
to review the addition requirements and also numbering, filing, coding and document control
procedures and apply them with reference to “Project Coordination Procedure (BK-GNRAL-HD-
000-PM-PR-0001)”.
All Documents will be identified by a unique code which is describes in “Project Coordination
Procedure”. DCC provides a list of latest version of Project documents and status of every
document. This list is available for all employees through computer network sharing facilities.
The documents are hyperlinked to this list.
Distribution of documents will be done through transmittal forms according to the above
mentioned procedures. Also our computer base systems will able us to define access, control
and distribute documents appropriately.
All QC procedures and ITPs shall be reviewed by QA/QC Manager and engineering
department and approved by Project Manager. According to Contract, relevant procedure shall
be submitted to TPI and COMPANY for approval, comment or information.
Other Project procedure according the scope of procedure will be reviewed by related
Managers and approved by Project Manager and will be controlled by QA/QC Manager.
COMPANY has right to review and comment the PROJECT related procedures according to
contract and its scope.
“Project final documents” will be provided according to the Contractual requirements.
- Instrumentation.
The forms were prepared on the grounds of the recommendations given by related codes and
standards, and in compliance with the good field practice.
The preparation and qualification of the welding procedures is carried out by Welding /NDE
(Non-Destructive Evaluation) Group (see fig.1) in accordance with the requirements of ASME
IX, API Standard 1104, ANSI/ASME B31.3, B31.4, B31.8, AWS D1.1, etc.
There are many welding procedures covering most of the pipeline and in-plant piping
construction activities. These procedures are prepared by EPC Contractor engineers and
qualified under the supervision of EPD/EPC Contractor , They are included in MDL .
Any further qualification of a procedure that may appear necessary for a job will be prepared by
experienced welding engineers and submitted to the Client for approval. After being approved
by the Client, the procedure will be carried out in the fabrication yard by experienced welders
under the supervision of welding inspectors from EPC Contractor QA/QC Department, Certified
materials and consumables shall be used. The mechanical testing will take place in authorized
laboratory, approved by the EPD/EPC Contractor.
The welder’s testing and qualification is carried out by the Welding/ NDE Group (see fig.1).
The qualification of welders under the qualified welding procedures is carried out according to
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
the requirements of ASME IX API Standard 1104, ANSI/ASME B31.3, B31.4, B31.8, AWS
D1.1, etc The testing takes place in the fabrication yard under the supervision of welding
inspectors from EPC Contractor QA/QC Department . Certified materials and consumables are
used. Welder’s Performance Test Record is prepared and signed for the successful welders.
The welders are provided with ID cards for the duration of the works.
The field quality control is carried out by the Field Inspection Group (see fig.1). The following
activities take place:
Gamma-ray sources,
The evaluation of the results is performed by Welding/NDE Group .The staff is properly qualified.
The minimum qualification required is Level II.
The welding book for the pipelines, and the welding inspection report for the in plant piping, are final
documents summarizing all welding and NDT carried out. They contain welding history and reference to
all reports related to the welding of a pipeline or in-plant piping element. The preparation of these
documents is a continuous processes during the execution the words. The completion of such document
takes place after the line or spool obtains status of “NDT clear”. The welding book/welding inspection
report, together with all related inspection reports, form the Test Package, which is to be completed
before the hydrostatic testing.
Examples are :
Inspection and Test Plans shall define the efforts of EPC Contractor and EPD/EPC
Contractor and Vendors and Subcontractors with regard to Quality Assurance and Quality
Control associated with execution of specific Work. EPC Contractor shall ensure that
Inspection and Test Plans provided by Vendors and Subcontractors comply with the
Contract documents.
Some of key Quality Control documents and requirements based on the project scope and
needs are listed as below:
Procurement Procedures:
EPC Contractor shall issue a Procurement Procedure to be issued to COMPANY as
per contract requirements
Construction Procedures
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
Welding Procedures
Welding Procedures Specifications (WPS), Procedure Qualification Records (PQR) and
Welder's qualification Certificates are normally required and shall be submitted to the
EPC Contractor for review / approval prior to the start of any welding works at plant.
NDT Procedures
Non Destructive Testing Procedures are required and it May be submitted to the EPC
Contractor / TPI for review or approval. The contractual requirements will be defined in
relevant Inspection and Test Plan.
In order to provide the assurance of the quality, the following procedures and standard practices
are applied:
All these documents are based on the applicable codes and standards, such as ASME Section V,
ASME Section VIII, ASME Section IX, ANSI/ASME B31.3, B31.4, B31.8, API Standard 1104, etc.,
as well as on the schedules and specifications of Client.
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
The procedures and standard practices are included in MDL of the Project .
The following quality control procedures have to be developed for control of activities in Project's
different stages. The decision of preparing these documents is by the QC department according to
the contract and the scope of the PROJECT. All QC Procedures shall be prepared and submitted
to Contractor by subcontractors/ vendors/ suppliers or manufactures according to contract spilt of
work.
a) Mechanical QC Procedures
Protection, Preservation. & Maintenance of Equipment
Fabrication, Installation & Pressure Testing of Piping & Vessels
Installation of Mechanical Equipment
Preparation of Rotating Equipment for Operation
NDT Procedure / Welding Procedure
Heat Treatment Procedure
b) Civil and Steel Structure QC Procedures
Steel Structure Fabrication & Installation
Earth Work Procedure
Concrete Work Procedure (Form Work, Concrete Pouring, Curing, Grouting and
Repair)
Building Construction (Masonry Wall, Precast, Roof Construction, etc.)
c) Electrical QC Procedures
General Electrical Works Procedure (Including cabling, Conduit Installation, Cathodic
Protection System- C.P. Data sheet, Grounding System Installation, UPS, Junction Box
installation, Switchgears, lighting system, Control Panel, Termination & Splicing, HV
Cables, etc.)
Electric Motor Installation
Generator Installation
d) Instrumentation QC Procedures
Instrument Installation (Calibration, Hook up, loop check, etc.)
Pressure Testing of Instrument Piping
e) Painting and Insulation Procedures
Painting and Insulation Procedure (including Surface Preparation)
Concrete Fire Proofing (if any)
Coating Procedure
f) Storage Tanks Procedures
Storage Tanks Fabrication Procedures
Storage Tanks Installation Procedures
Storage Tanks Pressure Test Procedures
NDT/Welding Procedures
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
Personnel performing quality control activities will be informed by DCC department of the
latest approved documents and procedure which are necessary for the execution of the
work. The submitting of Project documents to COMPANY is in according to Agreement.
The following technical documents to be used for the construction of the PROJECT will be
made available to the Quality Control Staff at the work Site:
Construction drawings
P&ID diagrams
COMPANY specifications
Technical specifications (detail engineering)
Codes and standards
Project working procedures and / or instructions
Vendors inspection and testing certificates
Vendors requirements and instructions
Other applicable documents
QA/QC Documentation
QA/QC Documentation Retention
EPC Contractor will submit to the EPD/EPC Contractor the Copies of Project Quality
Control and Quality Assurance documentations for archival. CONTRACTOR will retain
his own copy for a minimum period of two years or project duration, any period is
longer. Project manager is responsible to control and permit files deletion and
document retention and disposition as per project documentation control procedure.
Warranty Claims
In such cases where there is a failure of the product, the QA/QC Handover Dossiers
will be able to identify whether there is a product manufacturing, installation,
construction defect or if it was an operational failure.
13. CONTROL OF MONITORING AND MEASURING DEVICES
Any electrical/ electronic instrument and measuring devices used to determine the acceptability
of an item will be calibrated and monitored for its state of accuracy.
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
Rule to follow is: if the measuring device determines the conformity of the item it calibrated or
validated before use, then it will be calibrated.
Transit levels
Electrical measuring devices
Frequency meters
Precision levels
Mechanical measuring instruments
Pumps to measure flow capability
Pete tubes
Pressure gauges
Relief valves
Revolutions per minute (RPM) measuring instruments
Other devices which use to determine conformity of an item
Project manager shall ensure that externally provided processes, products and services conform
to requirements and control measures are provided and fully executed. Any required inspection
or measurement and monitoring shall be provided to meet the determined results with no
unacceptable risk.
Production and service provision activities which are describe as following, will be done by
Subcontractors. Site Manager supervises construction activities. Also QA/QC department will
monitor these activities during audits, KPIs and Project control reports to ensure all ISO 9001
and contractual requirements will be fulfilled.
16. PURCHASING
Following procedures define the procurement phase quality activities to ensure that QC/QA
Manager properly monitor procurement activities and supplier performance:
Definition of critical characteristics for purchased products that affect the quality of the
PROJECT outcome and the method of communication these characteristics to supplier to
enable adequate control of purchased product throughout the PROJECT will be done as
describe in " supplire Quality Control Requirements".
Purchase of materials and equipment and associated quality documentation will be done in
according to Project schedule which will be monitored by QA/QC Manager to ensure of quality.
Based on the criticality and complexity of the equipment, inspection level will be defined.
There are 4 inspection levels for equipment and materials is according to “Procurement
procedure ICE-EID-MI-SP01-Rev.01
Level I:
Inspection Level I is defined as a full stage inspection carried out progressively from
commencement of manufacturing to final acceptance. This does not normally mean full-time
witnessed in-line inspection during product manufacturing; however, this may be required on
occasions where work program demands regular attendance.
Level II:
Inspection Level II is defined as specific stage inspection of equipment and final
inspection of equipment prior to shipment. Stages of inspection shall be agreed upon during a
pre-inspection meeting to be held with the VENDORS after purchase award.
Level III:
Inspection Level III is defined as final condition or as built examination(s) and test(s). Inspection
may be on one or more pieces of equipment or on a random batch selection.
Level IV:
Inspection Level IV is defined as the review and acceptance/endorsement of
manufacturer's attestation, including any data book requirements to approved ITP.
Sub Contractor shall arrange a kick-off meeting and pre-inspection meeting between EPC
Contractor and EPD/EPC Contractor representatives at supplier shop, for all key equipment
packages, prior to start of manufacturing activities by Supplier.
EPC Contractor will carry out inspection of all procured equipment or other items during design,
fabrication, manufacturing and testing according to requirements defined in the contract
technical specifications, codes, and standards which will be reviewed in design process.
Hold, witness, review, monitoring, reviewed and approved and surveillance points will be
identified in the ITP for Contractor, Supplier, Third-Party Inspector or authorized Inspector, and
EPD/EPC Contractor and COMPANY.
Supplier appraisals, Quality assurance audits of Suppliers, Quality surveillance and inspection
of Supplier's activities are describe in purchase procedure (BK-GNRAL-PEDCO-000-PM-PR-
0005) and ICE-EID-MI-SP01-Rev.01
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
a) Evaluates and selects its suppliers based on their ability to supply product or service in
accordance with requirements;
b) Defines the type and extent of control to be exercised depending upon the type of product or
service, the impact of purchased product or service on the quality of final service/product,
and previously demonstrated capability and performance of Vendors.
The method and purchase process is in accordance with the purchase procedure (BK-GNRAL-
PEDCO-000-PM-PR-0005).
Purchase Orders and other documents contain information describing the product to be
purchased, including where appropriate:
EPC Contractor does not use any product until it has been verified as conforming to
requirements.
Purchased product shall be inspected for acceptance at the Suppliers shop or the construction
نگهداشت و افزایش تولید میدان نفتی بینک
سطح االرض و ابنیه تحت االرض
When verification performs at supplier premises, EPC Contractor states the intended verification
arrangements and the method of product release on the Purchase Order.
19. OPERATION