ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
REVISION RECORD
Issued for
A 26-Aug-21 Review &
Comments
MA FR IKR
Page 2
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
TABLE OF CONTENTS
DEFINITIONS ........................................................................................................................... 4
ABBREVIATIONS..................................................................................................................... 6
1 EXECUTIVE SUMMARY .................................................................................................. 7
1.1 PROJECT NAME AND CONTACT PERSON ........................................................................ 8
1.2 REPORTING REQUIREMENTS ............................................................................................ 8
1.3 SUMMARY OF FINDINGS ..................................................................................................... 8
2 INTRODUCTION .............................................................................................................. 9
2.1 PROJECT SCOPE ................................................................................................................. 9
3 MONITORING COMMITMENTS AND STANDARDS ..................................................... 11
3.1 MONITORING STANDARDS ............................................................................................... 11
3.2 METHOD .............................................................................................................................. 12
3.3 MONITORING LOCATIONS ................................................................................................ 12
3.4 MONITORING RESULTS..................................................................................................... 13
3.5 WASTEWATER CHEMICAL ANALYSIS ............................................................................. 14
3.6 QUALITY ASSURANCE AND QUALITY CONTROL ........................................................... 15
4 NON-COMPLIANCE ...................................................................................................... 16
5 CONCLUSIONS ............................................................................................................. 16
APPENDIX-A: MONITORING PHOTOGRAPHS .................................................................... 17
LIST OF TABLES
Table 1-1: Project Proponent ....................................................................................................................... 8
Table 3-1 Air Pollutant Limits in Ambient Air ............................................................................................. 11
Table 3-2: Details of monitoring locations ................................................................................................. 12
LIST OF FIGURES
Figure 2-1 : Location Map ............................................................................................................................ 9
Page 3
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
DEFINITIONS
Page 4
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
Page 5
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
ABBREVIATIONS
Page 6
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
1 EXECUTIVE SUMMARY
Abu Dhabi Distribution Company (ADDC) awarded a contract to Larsen & Toubro Limited for the
Supply of Recycled Water along Abu Dhabi Al Ain Road - Construction of Pipelines from Main
Pump Station to Intermediate Pump Station - Package B” which can be briefly classified into
pipeline and tank construction. for pipeline construction the scope involves supply and installation
of recycled water transmission pipelines Installation (including internal & external protection) of 85
km of various diameters (DN 1600 mm, DN 1000 mm, DN 900 mm, DN 700 mm, DN 500 mm, DN
300 mm, DN 250 mm) between Main pump station and the chlorination Station. For Tanks, the
scope involves Structural Design and construction of new steel recycled water tanks at Bu Touq,
Al Wathbah Palace and Bal Dheba areas with capacities of 9000 m3, 8500 m3 and 7500 m3
respectively and access roads. Tank construction includes all site works, civil, mechanical,
electrical, instrumentation, & control works and all associated works.
Larsen & Toubro Limited, commonly known as L&T, is an Indian technology, engineering,
construction, manufacturing and financial services conglomerate headquartered in Mumbai,
Maharashtra, India. It was founded by two Danish engineers taking refuge in India. The company
has business interests in basic and heavy engineering, construction, realty, manufacturing of
capital goods, information technology, and financial services. As of 2020, L&T Group comprises
118 subsidiaries, 6 associates, 25 joint-venture and 35 joint operations companies.
Three key products/services which L&T is engaged in are: Construction and project-related
activity; manufacturing and trading activity; and engineering services. For administrative
purposes, L&T has been structured into five broad categories:
Construction – this covers Buildings & Factories, Heavy Civil Infrastructure, Transportation
Infrastructure, Power Transmission & Distribution, Water & Effluent Treatment, Metallurgical
& Material Handling and Smart World & Communication;
EPC Projects – this includes Hydrocarbon Engineering, Power and Power Development;
Manufacturing – this includes Defense Equipment & Systems, Heavy Engineering,
Construction, Mining & Industrial Machinery, Industrial Valves and Electrical & Automation
Systems;
Services – this includes Realty, Information Technology, Technology Services and Financial
Services.
Others – this includes Hyderabad Metro, Infrastructure Development Projects and corporate
functions.
Velosi has been appointed by COMPANY to conduct the Environmental monitoring study of
pipeline near Al Wathba Site Area of Larsen and Toubro Site office. The following Environmental
Monitoring activities were carried on 18th August, 2021. The sample collected for wastewater
testing were sent to ISO: 17025 certified laboratory for further laboratory analysis.
Ambient Air Quality Monitoring (01 Location/Point)
Waste Water Analysis (01 Sample)
Page 7
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
Project Proponent
Zone 4
Page 8
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
2 INTRODUCTION
Abu Dhabi Distribution Company (ADDC) awarded a contract to Larsen & Toubro Limited for the
Supply of Recycled Water along Abu Dhabi Al Ain Road - Construction of Pipelines from Main
Pump Station to Intermediate Pump Station - Package B” which can be briefly classified into
pipeline and tank construction. for pipeline construction the scope involves supply and installation
of recycled water transmission pipelines Installation (including internal & external protection) of 85
km of various diameters (DN 1600 mm, DN 1000 mm, DN 900 mm, DN 700 mm, DN 500 mm, DN
300 mm, DN 250 mm) between Main pump station and the chlorination Station. For Tanks, the
scope involves Structural Design and construction of new steel recycled water tanks at Bu Touq,
Al Wathbah Palace and Bal Dheba areas with capacities of 9000 m3, 8500 m3 and 7500 m3
respectively and access roads. Tank construction includes all site works, civil, mechanical,
electrical, instrumentation, & control works and all associated works.
Page 9
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
Page 10
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
Maximum Allowable
Substance Symbol Average Time
Limits (g/m3)
350 1 hour
60 1 year
30 (mg) 1 hour
Carbon Monoxide CO
10 (mg) 8 hour
400 1 hour
Nitrogen Dioxide NO2
150 24 hour
200 1 hour
Ozone O3
120 8 hour
230 24 hour
Total Suspended Particles TSP
90 1 year
Lead Pb 1 1 year
Source: Federal Law. 2006. “Regulation for the Protection of Air from Pollution. “Council of
Ministers Decree No. 12, UAE.
Page 11
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
3.2 METHOD
Air Quality Monitoring:
Air Quality Analyser (Combined Sampler) was utilized to carry out Indoor Air Quality Analysis at
one (01) selected location as suggested by the COMPANY’s HSE Advisor. Air Quality Monitoring
was carried out for Temperature, Relative Humidity, Carbon Monoxide (CO), Carbon Dioxide
(CO2), Nitrogen Dioxide (NO2), Sulphur Dioxide (SO2), Ozone (O3), Particulate Matter (PM10) &
Total Organic Compounds (TVOC). Analyser was installed for Eight (08) hours at selected
locations to record the readings.
Monitoring Location
Page 12
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
TITLE DETAILS
SAMPLE ID AAQM-01
TEMPERATURE0C 40
Page 13
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
Sample: Zone 4
Page 14
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
Page 15
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
4 NON-COMPLIANCE
The environmental monitoring was conducted for ambient air quality and waste water sampling
analysis for Al Wathba Site Area. The samples collected of wastewater was sent to ISO: 17025
certified laboratory for further laboratory analysis. All the parameters monitored at site were in
compliance with applicable standards.
5 CONCLUSIONS
The Ambient Air Quality carried out at one (01) Location/point all the parameters were found
to be within the compliance as per Cabinet Decree (12) of 2006, Federal Environmental agency
of UAE, Regarding Regulation Concerning Protection of Air from Pollution, and Annexure (8)
Ambient Air Quality Standards.
The wastewater sampling and testing has been carried out of one (01) sample and all the
parameters were found within allowable limits.
Page 16
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
Page 17
ENVIRONMENTAL MONITORING REPORT
ADDC PROJECT D107604 PACKAGE-B ABU DHABI
PHOTOGRAPHS