COMPREHENSIVE PROJECT PROFILE

Agency: MINDORO STATE COLLEGE OF AGRICULTURE AND TECHNOLOGY


Sector: Infrastructure Development

I. BASIC INFORMATION

1. Project Title REPAIR & MAINTENANCE: PROVISION OF 2 UNITS


FIRE ESCAPE STAIRS IN OLD SCIENCE LABORATORY
BUILDING & EDUCATION BUILDING

2. Project Description Fire escape stairs is an important component in building


structure which serves as additional safety feature in case of fire
and other emergency situations.

3. Project Type Capital Assistance / Technical Assistance

4. Project Components Project components are as follows:


I. Design & Layout
II. Program of Works
III. Procurement/Bidding & Awards

5. Project Objectives The projects aims to:


1. Improve college facilities with the provision of two units
fire emergency escape stairs in two academic buildings;
2. To provide students and faculty with safe and accessible
secondary exits of the buildings;
3. To upgrade student-support services.
4. Serves as one of the compliance for the Fire Code of the
Philippines.
5. To secure & pass Fire Safety Inspection Clearance

6. Project Outcomes
 Newly built 3-level fire emergency escape stairs with
0.9m wide.
 Improved safety features in two academic buildings
7. Project Location
Provinces
Municipalities Oriental Mindoro
Victoria
Barangay Alcate

II. PROJECT STATUS


1. On-going
2. Pipeline
3. Proposed /

Status of Project Preparation:


Project Idea /
Pre-Feasibility Study
Feasibility Study
Detailed Engineering
Fund Negotiation
Review Level:
RDC
ICC-TB
NEDA Board

III. PROJECT JUSTIFICATION


1. Project Background

The Mindoro State College of Agriculture and Technology


(MinSCAT) has on-going building constructions which requires
safety features in compliance with the existing laws and regulations.
Currently, the Old Science Laboratory Building and Education
Building has no secondary exits in the form of stairs in which the
Bureau of Fire Protection is requiring for an educational facility
with three of more level to provide secondary stairs as Fire
Emergency Escape.

2. Goal
The project aims to:
1. Provide a safe and reliable academic facilities equipped with
necessary safety features complied with the existing codes, laws
and regulations.

3. Purpose 1. To provide students and faculty with safe and accessible


emergency exits;
2. Enhance security features of the two academic facilities

4. Project Outputs  Newly built 3-level fire emergency escape stairs with 0.9m
wide.
 Improved safety features in two academic buildings

5. Project Activities
I. Coordinate with the municipal Fire Bureau/Council
II. Construction of Fire Emergency Escape Stairs.

6. Project Linkages
N/A
IV. PROJECT FINANCING
1. Funding Requirement (in Million Pesos)
2. Project Financing
3. Funding Source MDS
4. Counterpart Funding
5. Financial Viability

V. PROJECT BENEFITS AND COSTS

1. Beneficiaries Personnel, faculty, staff and students, MinSCAT community

2. Social Benefits
The construction of this project will provide safer and comfortable
educational facilities for the stakeholders.

3. Economic Benefits A safe and more reliable facilities will protect its users against
emergency situations such as fire and earthquakes. Protecting the
people will benefits the economy in general and long term.
4. Social Costs No additional social cost is needed.

5. Economic Costs An amount of P1,000,000.00 is needed to finish the provision of


two emergency stairs in two academic facilities.

VI. PROJECT IMPLEMENTATION


1. Agencies Involved
Mindoro State College of Agriculture and Technology
2. Implementation Schedule
Year Physical Indicator Amount (in Million
Pesos)
 Fire Escape Stairs 2 units Php 1,000,000.00
Clearing & Grubbing 2 lots 3399.36
Concreting Works (inc. 30 cu.m. 23711.925
Reinforcing Steel)
Formwork & Falsework 2 Lot 54956.32
019
Structural Steel 2 lots 560008.116
Roof & Roof Framing System 2 lots 110479.2
Railings 2 lots 247445.08
*refer to POW for
details
GRAND TOTAL Php 1,000,000.00

The project will operate under the supervision of the designated


3. Administrative Feasibility project manager in coordination with the following
department/unit of MinSCAT:
 Administration and Finance & Auxiliary Services

4. Environmental Clearance No environmental clearance is needed since the project is also


located in the existing road (rough road)

5. Social Acceptability The project is socially acceptable


VII. PROJECT PHOTO or LOCATION MAP (to be submitted)

Proposed Design

Prepared by:

JOHN EMMANUEL M. MERHAN


Administrative Aide VI
Date: November 10, 2019