SAMBERIGI WATER PROJECT

PROJECT PROPOSALI.

DescriptionA.

Project Title
Rehabilitation of Water System
B.

Project Location
Bote, Bato, Catanduanes
C.

Brief Summary of the Project


The project primarily intends to decrease the poverty incidence in the barangay, in linewith the
thrust of the National Government which is directed towards poverty reduction. It willprovide 221
HHs in the barangay an access to clean and safe water. It also seeks to eliminate theincidence of
water-borne diseases in the barangay which was recorded at 55 cases of skindiseases during the
preceding year.As the more serious sickness which may be brought about by unsafe water will drain
thebudget of the family, availability of safe drinking water is a must to every household. Easy
accessto safe water will also result to savings in time of family members which will pave way for
theaccomplishment of other profitable undertakings.Although 90.5% percent of the households
have water connections provided by thebarangay, it failed to provide them with sufficient supply of
clean and potable water. As such,there is a necessity to tap the appropriate water source in the
barangay through the SALINTUBIGprogram of the DILG.The project will augment LGU

s undertaking in improving the water system of thebarangay through its Economic Development
Fund. Barangay Bote has also spent part of itsdevelopment fund for the said water system,
accomplishing the construction of the existingwater tank that has a capacity of 21.6 cu. m and laying
of the existing pipelines of the barangaywater system.
D.

Project Goals and Objectives


In general, the project is aimed at reducing the poverty threshold of the barangay from80% to 65%.
Specifically, it will provide the 1,105 individuals in 221 households in the barangayan access to safe
drinking water. It will also promote good health and cause the eradication ofwater-borne diseases;
and will reduce the time allotted by family members in fetching water,thus savings in time would
provide for the accomplishment of other lucrative activities.
E.

Total Project Cost


Scribd
Trusted by over 1 million members
Try Scribd FREE for 30 days to access over 125 million titles without ads or interruptions!

Start Free Trial


Cancel Anytime.

Table 1. Total Project Cost and percentage of contributionSource of Fund Amount %


ShareDepartment of the Interior and LocalGovernment900,000.00 85.5%Municipal Government of
Bato, Catanduanes 90,000.00(direct counterpart)41,500.00(fund provision to other
activities)12.5%Beneficiaries 21,000.00(in-kind)2%
F.

Target Beneficiaries
The beneficiaries of the project are the whole residence of Barangay Bote. With propermanagement,
it will give them abundant supply of safe and clean water which will also preventthem from being
afflicted by diseases caused by contaminated water. The easy access to apotable water supply will
also result to savings in time in fetching drinking water, therefore,would give time to residents to
accomplish other profitable tasks.
G.

Project Partners
In the barangay level, the direct partner during the construction phase is the Barangay Council.Other
organizations in the barangay such as the
purok, youth and women’s organization will
contribute to labor component of project construction. Once operational, the Barangay BoteWater
and Sanitation Association with the assistance of the Barangay Council and the
MunicipalGovernment will take charge in the operation and maintenance of the project.
H.

Technical Evaluation
The proposed water tank will be constructed within the mountainous terrain having an elevationof
73.24 meters and distance of 3.069 kilometers from the service area. With slopes rangingfrom 8-15
percent and soil components primarily made of Luciana clay, the site is notsusceptible to landslide
and erosion. Also, the proposed site is not susceptible to excessivesurface run-off or flooding, not
located near an active fault line, and will not disturb anyhistorical and monumental markers.
II.

Project Components and Implementation Schedule


Table 2. Time table of ActivitiesActivities Date Responsible Agency / Office1.

Creation of Municipal Waterand Sanitation (WATSAN)Council and Water andSanitation (WATSAN)


Teamor Project Management UnitApril 10, 2014 Office of the Mayor2.

Authorization of the Mayorto enter into a MOA throughApril 14, 2014 Office of the
SangguniangBayan

SB Resolution3.

Conduct of communityconsultationApril 21, 2014 WATSAN, Barangay Council4.

Water sources inventory


April-May, 2014 WATSAN, Barangay Council,Municipal Engineering Office5.

Organization/Reactivation ofBarangay Bote Water andSanitation AssociationApril, 2014 WATSAN,


Barangay Council6.

Preparation, submission andapproval of the requireddocuments and othernecessary materialsApril



September, 2014 WATSAN, DILG ProvincialOffice, DILG Regional OfficeNo. 57.

MOA signing and transfer offundOctober, 2014 Office of the Mayor, DILGProvincial Office,
DILGRegional Office No. 5,WATSAN8.

Project Implementationa.

Procurement andDelivery of Supplies andMaterialsOctober, 2014 BAC, GSOb.

Construction of WaterTank and Pipe LayingOctober-December, 2014 Municipal Engineering Office,


Barangay Council, People’s
Organization (Purok, Youthand Women), WATSAN (Boteand MLGU)c.

Liquidation of Expensesthrough preparation andsubmission of Statementof Expenditures (SOE)and


Receipt ofDisbursementDecember, 2014 WATSAN, MunicipalTreasurer, MunicipalAccountant,
Auditor, DILGProvincial Office, DILGRegional Office No. 5d.

Inauguration andTransfer of ProjectManagement to BoteWater and SanitationAssociationDecember,


2014 Office of the Mayor, BarangayCouncil, Bote Water andSanitation Association, LGU-WATSANe.

Project Monitoring October 2014 onwards Project Management Unit /LGU-WATSAN


III.

Work and Financial Plan


Table 3. Work and Financial Plan
Project Component / ParticularPhysicalTargetCost perItemFinancial
RequirementsBeneficiaryEquityLGU-Bato DILG Total
A.

Pre-Implementation Phase
1.

Creation of Municipal Water andSanitation (WATSAN) Council andWater and Sanitation (WATSAN)
Teamor Project Management Unit (PMU)
1,000.00 1,000.00 1,000.00
2.

Authorization of the Mayor to enter