T-1220 AMMONIA TOWER SERVICING

JUBAIL
METHOD STATEMENT

RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE


(RIMAL)

Method Statement
for
SERVICING OF AMMONIA TOWER T-1220 (AMINAT)
JUBAIL

SUBMITTED BY:
RIMAL AL JAZEERA
SAHARA BUILDING, P.O BOX 2681 – AL JUBAIL 31951
KINGDOM OF SAUDI ARABIA

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 1 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

METHOD STATEMENT

Date: 08 December 2020

Nijam s Mohammed SITE ENGINEER


Prepared by
Name Designation Signature

Rashid A Khan SITE MANAGER


Reviewed by
Name Designation Signature

Reda H. Mesbah PROJECTS MANAGER


Approved by
Name Designation Signature

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 2 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

TABLE OF CONTENTS

1. INTRODUCTION.............................................5
2. PROJECT SCOPE............................................5
3. PURPOSE..........................................................6
4. REFERENCE.....................................................7
5. EQUIPMENT AND TOOLS.............................7
6. MANDATORY PPE..........................................7
7.1 PRIOR TO EXECUTION................................8
7.2 PREPARATION FOR REPAIR WORK.........8
7.3 LIFTING EQUIPMENTS................................9
7.4 SAFETY PRECAUTIONS..............................9
7.5 HOUSE KEEPING..........................................9

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 3 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

1. INTRODUCTION

 This document is a statement of the procedure that proposes to adopt the


servicing of AMINAT AMONIA TOWER T-1220, This document covers the
procedure for the servicing and final box-up after obtain the closer
certificate from AMINAT operation, maintenance and asset integrity team

Definition and Abbreviations

Acronym Description

NH3 Ammonia

PPM Parts Per Million

°C Unit Of temperature

M2 Square meter

M3 Cubic meter

M Meter

EA Each

µ Microns

LM Linear Meter

2. PROJECT SCOPE

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 4 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

ITEM DESCRIPTION

1 Site visit to Identify the work location & Inspection of proposed site.

2 Scaffolding erection prior to start the job activity.

3 Blinding and D-blinding activity.

4 Opening of 24” # 300 manholes (3nos).

5 Removal of random packing and stricter packing.

6 Removal of bed # 1&2 including pipe distributer.

7 Cleaning inside the tower.

8 Installation of random packing and stricter.

9 Installation of bed# 1&2.

10 Installation of pipe distributor.

11 Inspection of entire component installed inside the tower.

12 Manhole box up by using torque value.

13 D-blinding.

14 Removal of scaffolding.

15 Housekeeping.

3. PURPOSE

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 5 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

 This method statement explains the planned and safe execution


procedures for the servicing and final closer for AMINAT AMONIA
TOWER T-1220.

Contents

1. RESPONSIBILITES:

 Project Manager: Shall be responsible for overall implementation of the


company safety & quality plan and ensure efficient execution of works
in accordance with project manager.

 QC Manager- : Shall oversee all the activities, whether all are


executed as per the quality planned project specifications.

 HSSE Manager- Shall make sure that all the safety requirements are
fulfilled by daily basis in order to avoid any loss of time.

 HSSE Supervisor- Shall carry out risk assessments and consider how
risk could be reduced and also carry out regular site inspections to
check policies & procedures are being properly implemented.

 Qc Supervisor: Shall ensure that all records pertaining to the


particular works are maintained and accepted by CONTRACTOR/
COMPANY
 QC Inspector- Shall ensure that all works are carried out as per IFC
drawings, project specifications and standards and he have to
coordinate inspection as per ITP with CLIENTQC inspectors for
inspection.

4. REFERENCES:

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 6 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

 This method statement takes reference from Aminat Email: 14-2237 Servicing of Tower
T-1220 and Drawing No: specification Doc No: VD-41416-MS024-T1220-001 & VD-
41416-MS023-T1220-002.

5. EQUIPMENT AND TOOLS

 Crane(100 TON)
 Fork Lift ( 5 Ton )
 Ventury fan
 Air Compressor
 Jumbo Bag
 Dump truck
 Hydraulic trolley
 Torque Wrench
 General tool box trolley
 Lifting tools for crane
 Chain blocks D-shekel and belts
 24-volt light
 Cartridge filter
 Fire extinguisher
 Rope ladder
 Utility hoses

6. MANDATORY PPE

1. Hard Hat
2. Boots with steel mid sole and toe caps
3. Gloves – suitable for task
4. Goggles – suitable for task
5. Respiratory mask
6. Safety Harness.

7.1 PRIOR TO EXECUTION

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 7 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

- Materials Storage and Handling.

 The tower packing ring and stricter materials shall be shifted to


AMINAT lay down yard for the cleaning.
 Ensure that all materials are secured followed by AMINAT HSE
policy.

7.2 PREPARATION FOR REPAIR WORK

 Scaffolding must be installed for blinding activity prior to shut down.


 Security gate pass is require to enter the vehicle , materials and
manpower.
 Dump truck and Fork lift must be available one day before prior to start
the activity.
 Proper lighting must be arranged to work round the clock.

 All the blinds including one gasket must be placed on each and every
blind location.
 Shift the complete tools trolley one day before start the shutdown.
 Confine space training as per HSE policy of all the work man to be done
prior to start the internal activity inside the tower.
 Trained and certified whole watchman and fire watch to be arrange
before opening the manhole.
 Certified crane and operator must be available one day before start the
activity.
 Proper placement of crane near the work location followed by its
degree, angle, radius, boom length and capacity to be check one day
before start the activity.
 Certified rigger level 3 must be arranged in both the shift.

7. 3 LIFTING EQUIPMENT

Ref: Aminat - 14-2237, Servicing of Tower T-1220 Page : 8 of 9


Contractor: RIMAL ALJAZEERA FOR OPERATIONS AND MAINTENANCE Size : A4
Printing Date: 08 December 2020 Rev : 0
T-1220 AMMONIA TOWER SERVICING
JUBAIL
METHOD STATEMENT

 All rigging equipment used for the lifting will have a valid test
certificate
 All rigging equipment shall be visually inspected by the rigging
supervisor and Subcontractor safety personnel during assembly to
assure that no damage has occurred and having required color
code.

7. 4 SAFETY PRECAUTIONS

 Follow work permit instructions


 Transport safety as per RC standard.
 No hot work to be carried out.
 Use appropriate respiratory and hand gloves.

5. 5 HOUSE KEEPING

 Maintain good housekeeping all the time.


 Proper material stacking / arrangement.
 Remove unnecessary material from site.
 Assign helpers for regular housekeeping.
 Housekeeping shall be done before, during and after the job
completion.

END of this Document