METHOD STATEMENT
Method Statement
for
SERVICING OF AMMONIA TOWER T-1220 (AMINAT)
JUBAIL
SUBMITTED BY:
RIMAL AL JAZEERA
SAHARA BUILDING, P.O BOX 2681 – AL JUBAIL 31951
KINGDOM OF SAUDI ARABIA
METHOD STATEMENT
TABLE OF CONTENTS
1. INTRODUCTION.............................................5
2. PROJECT SCOPE............................................5
3. PURPOSE..........................................................6
4. REFERENCE.....................................................7
5. EQUIPMENT AND TOOLS.............................7
6. MANDATORY PPE..........................................7
7.1 PRIOR TO EXECUTION................................8
7.2 PREPARATION FOR REPAIR WORK.........8
7.3 LIFTING EQUIPMENTS................................9
7.4 SAFETY PRECAUTIONS..............................9
7.5 HOUSE KEEPING..........................................9
1. INTRODUCTION
Acronym Description
NH3 Ammonia
°C Unit Of temperature
M2 Square meter
M3 Cubic meter
M Meter
EA Each
µ Microns
LM Linear Meter
2. PROJECT SCOPE
ITEM DESCRIPTION
1 Site visit to Identify the work location & Inspection of proposed site.
13 D-blinding.
14 Removal of scaffolding.
15 Housekeeping.
3. PURPOSE
Contents
1. RESPONSIBILITES:
HSSE Manager- Shall make sure that all the safety requirements are
fulfilled by daily basis in order to avoid any loss of time.
HSSE Supervisor- Shall carry out risk assessments and consider how
risk could be reduced and also carry out regular site inspections to
check policies & procedures are being properly implemented.
4. REFERENCES:
This method statement takes reference from Aminat Email: 14-2237 Servicing of Tower
T-1220 and Drawing No: specification Doc No: VD-41416-MS024-T1220-001 & VD-
41416-MS023-T1220-002.
Crane(100 TON)
Fork Lift ( 5 Ton )
Ventury fan
Air Compressor
Jumbo Bag
Dump truck
Hydraulic trolley
Torque Wrench
General tool box trolley
Lifting tools for crane
Chain blocks D-shekel and belts
24-volt light
Cartridge filter
Fire extinguisher
Rope ladder
Utility hoses
6. MANDATORY PPE
1. Hard Hat
2. Boots with steel mid sole and toe caps
3. Gloves – suitable for task
4. Goggles – suitable for task
5. Respiratory mask
6. Safety Harness.
All the blinds including one gasket must be placed on each and every
blind location.
Shift the complete tools trolley one day before start the shutdown.
Confine space training as per HSE policy of all the work man to be done
prior to start the internal activity inside the tower.
Trained and certified whole watchman and fire watch to be arrange
before opening the manhole.
Certified crane and operator must be available one day before start the
activity.
Proper placement of crane near the work location followed by its
degree, angle, radius, boom length and capacity to be check one day
before start the activity.
Certified rigger level 3 must be arranged in both the shift.
7. 3 LIFTING EQUIPMENT
All rigging equipment used for the lifting will have a valid test
certificate
All rigging equipment shall be visually inspected by the rigging
supervisor and Subcontractor safety personnel during assembly to
assure that no damage has occurred and having required color
code.
7. 4 SAFETY PRECAUTIONS
5. 5 HOUSE KEEPING