You are on page 1of 18

KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 1 of 18

Method Statement Title:

INSTALLATION OF SCAFFOLDING

Reviewed by Kinetics Approved by


Submitted by Kinetics Project
Contractor Construction Safety Health & Manager
QA/QC
Manager Officer Manager

Signature: Amira
Name: Nursyafiqah Amira

Date: 12/04/2022

Time: 2:00PM

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 2 of 18

1.0 Introduction
This Method Statement outlines methodology and acceptable parameters for installation of scaffold at
KM1 walkable ceiling.

The detail of this proposal includes type of Plants and machinery, sequence/area of works, inspection
(Quality Control) and Safety

2.0 Resources

2.1 Materials

All materials used on site must be approved type and they are as follows: -

No Type / Brand Name Description of Materials


1 Platforms Aluminum 51mmx254mm
2 Guardrails Horizontal barrier >970mm <
1140mm
3 Toe Board Aluminum 2 x4 lumber
4 Mid rails Horizontal barrier >970mm <
1140mm
5 Ladder Stand Aluminum 4m Height

2.2 Machinery and Equipment

No Type / Model Quantity


1 Tabular Scaffold (Complete Set) 1
2 Chain block 1 tons 1
3 Handtools 1
4 Meter tape 1
5 Spirit level 1

2.3 Manpower involved/Plan


Designation / Name Key Person Quantity
Manager: Nik Shamrul 1
Engineer: Lee Keen Pauu 1
Supervisor: Muhammad Syarifuddin 1
EHS: Anbarasan 1
QA/QC: Nursyafiqah Amira 1

3.0 Primary Requirement

3.1 Coordination Requirement

iii.1.1 Identification of location before start the walkable ceiling works.

3.2 Other Operation Requirement

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 3 of 18

3.2.1 Non-works or unauthorized public are not allowed to access or enter the construction
site
3.2.2 Signage with clear instruction will be label at the entrance of the site. Storage area
will be in the site area
3.3 Receiving
3.3.1 All delivery to the site shall be informed to the site manager/ to have the plan for
unloading. Upon arrival of materials at the storage yard, the materials controller with
match delivery notes and shall verify the consignment.
3.3.2 Unloading can be done manually by team with using 7 tonnes or above mobile crane
/ 1 tones or above forklift/ or manual labour mobilize or machinery tools such as pallet
jack. Be sure to hook belts to component with the right number of point and position
so that the load of the component itself do not damaged or broken especially the
coating/ discolour.
3.3.3 All materials received at the site shall be visually inspected by site supervisor/
engineer for any damage after unloading. Any damage shall be taken immediately,
if possible to avoid any delay of erection.
3.3.4 Inspection for delivery on site shall be carry out the inspection together with KINETIC
QAQC & Client Representative for proper checking before used it.
3.3.5 Mock-up inspection shall be carry out together with Kinetics QAQC before proceed
the work of installation and approved by Client.
3.4 Handling

3.4.1 All materials shall be carried out inspection before start install to avoid excessive
stress, damage and crack to components during handling in site

3.4.2 Supervisor shall closely monitor the workers involved in the road works activity and
it’s shall be done in proper manner and comply with all safety requirement

3.4.3 Proper equipment and accessories shall be used during this activity shall be
inspected to ensure it is in good condition

3.4.4 Quality inspection shall be done to all type of materials which involved in this activity
before sent it to storage area. This inspection shall be done according to ITP
requirement

4.0 Work Activity Methodology/ Arrangements

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 4 of 18

4.1 Site Preparation

No Activity Sequence
1 a) To inform related Project Manager, System Owner and KINETICS EHS
management before start work for the day.

b) To obtain the entire relevant valid EHS document before start work.

To assign all the workers, stuff to attend safety induction before start work.

Get the valid permit for the workers and machinery to enter the site.

2 iii) Inform the Project Manager or person in charge before start work

iii) Detail of the activity to be performed shall be informed/briefed and explained


before starting work

iii) Precautions must be taken before and during activity in accordance to DOSH
standard

iii) During the progress of activity, the work shall be under the continuous
supervision of an experienced foreman.

e) Provide safeguards, including related signages, barricades, temporary fences, warning


lights and other similar items that are required for protection of all personnel during all
activity involved.

3 Mobilization of tools and workers

iii) To inform related Project Manager, System Owner and EHS Management
before start work for the day.

iii) Obtained the entire relevant valid EHS document before start work.

iii) All Vehicles to comply the wheel stopper when loading material.

iii) Get advised from KINETICS project management team for the location for
material storage.

e) Shall be used forklift to mobilize the materials into the work area if necessary.

f) Pallet Jack shall be used during work where necessary for mobilize the material to work
location needed.

4 To brief the workers on the job sequence and streamline their job for hazard avoidance
prior work starts.

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 5 of 18

5 Hard barricade all working area by using tubular scaffolding.

6 To prepare the power supply to the working area by using extension wire.

7 Barricade of working area with properly.

8 WORK SEQUENCE

A. INSTALLATION OF SCAFFOLDING FOR ACCESS TOWER (FROM KM1


GROUND TO LEVEL 1)

i. Scaffold detail is 3mx2mx9m


ii. Safe working load (SWL)=600kg/m2
iii. Access Platform after external scaffold to opening
area(Plywood)=8mx2mx12mm(thickness)

PICTURE: LOCATION OF SCAFFOLDING FOR ACCESS TOWER (FROM KM1


GROUND TO LEVEL 1 )

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 6 of 18

iv. Procedure of installation:

- Obtain relevant approved shop drawing of scaffolding from consultant


- Setting out the position and location for installation with references to exact
location
- Make sure that area where scaffolding erection is taking place shall be fully
isolated and barricaded to prevent entry of unauthorized personnel
- Installed ledgers to the length 3m sized so that joint are staggered. Ledgers to
be fixed to the standard using right-angle coupler
- Fix 1st lift transoms will be fixed to the ledgers with putlog clips adjacent to the
standard
- Installed the guardrails (refer drawing) with a mid-rails or as required by
National Standard.
- Once all guardrails are completed including stop-ends toe board will be fitted
to all elevations
- Installed the toe boards (metal deck) with the minimum of 102mm (3 ½
inches) in height to accommodate the use of 2x4 lumber as toe boards or as
required National Standard and must be secured to prevent movement.
- Ledgers bracing to fixed to the end pairs of standard and alternative pairs of
standard using swivel couplers within 300mm of the node point
- Netting must be placed between the toe board and mid rails to prevent
materials falling onto the ground exposing people below to fall hazards
- All poles, legs or upright of scaffolds shall be plumb and rigidly braced to
prevent swaying and displacement. Sufficient ties or raking shores shall be
provided to ensure that scaffold fall away from the object being scaffolder
- Scaffold shall be planked end to end on each side of the object. The planking
needs to be supported around the subject to ensure the decking or planking
will sufficiently hold the intended weight and tools and materials (Refer
calculation)
- For vertical ladder attached internally to the narrow side clear hand and foot
holds shall be provided by blocking pieces if necessary. Where vertical
ladders rise 4m an intermediate landing is 2.0m

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 7 of 18

- Once the scaffold has been erected essentially supervisor will offer to KSM for
inspection along with handover certificate and Scaff tag

B. INSTALLATION OF SCAFFOLDING FOR WORKING PLATFORM AND


MATERIAL RECEIVING INSIDE AHU6 WITH PLASTIC BOXUP

a) Scaffold detail is 6mx3mx5m

b) Safe working load (SWL)=900kg/m2

c) Chain Block capacity=1000kg/1 tons

PICTURE: LOCATION OF SCAFFOLDING FOR WORKING PLATFORM AND


MATERIAL RECEIVING INSIDE AHU6 WITH PLASTIC BOXUP

d) Procedure of installation:

- Obtain relevant approved shop drawing of scaffolding from consultant

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 8 of 18

- Setting out the position and location for installation with references to exact
location
- Make sure that area where scaffolding erection is taking place shall be fully
isolated and barricaded to prevent entry of unauthorized personnel
- Installed ledger with 6m length with joint staggered using right angle coupler
- Fix 1st lift transoms will be fixed to the ledgers with putlog clips adjacent to the
standard
- Installed the guardrails with have top rail and mid rail with National standard
design.
- Once all guardrails are completed including stop-ends toe board will be fitted
to all elevations required
- Installed two standard rails for used the chain block point (refer drawing) used
lifting the I beam moving
- Installed the toe boards (metal deck) as toe boards or as required National
Standard and must be secured to prevent movement and floor protection
- Ledgers bracing to fixed to the end pairs of standard and alternative pairs of
standard using swivel couplers within 300mm of the node point
- Scaffold shall be planked end to end on each side of the object. The planking
needs to be supported around the subject to ensure the decking or planking
will sufficiently hold the intended weight and tools and materials (Refer
calculation)
- For vertical ladder attached internally to the narrow side clear hand and foot
holds shall be provided by blocking pieces if necessary. Where vertical
ladders rise 4m an intermediate landing is 2.5m
- Once the scaffold has been erected essentially supervisor will offer to KSM for
inspection along with handover certificate and Scaff tag

C.INSTALLATION OF HANGING SCAFFOLDING FOR WORKING PLATFORM AND


ACCESS INSIDE WALKABLE CEILING

a) Scaffold detail is:


 Access platform=6mx1.5mx1.0m
 Working platform=20mx2mx1.5m
b) Safe working load (SWL)=905.66kg/m2

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 9 of 18

c) Chain Block capacity=1000kg/1 tonne

PICTURE: LOCATION OF HANGING SCAFFOLDING FOR WORKING


PLATFORM AND ACCESS INSIDE WALKABLE CEILING

d) Procedure of installation:

- Obtain relevant approved shop drawing of scaffolding from consultant

- Set out the position and location for installation with references to grid line

- Make sure that area where scaffolding erection is taking place shall be fully
isolated and barricaded to prevent entry of unauthorized personnel

- Ledgers to be sized so that joint are staggered. Ledgers to be fixed to the


standard using right-angle coupler and must be level in accordance to tolerance
along 20m Length

- Fix 1st lift transoms will be fixed to the ledgers with putlog clips adjacent to the
standard and to support the boards every 1.2m. The minimum and maximum
board overhangs will be observed

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 10 of 18

- The transoms must be tied to the permanent beam structure at the 1.2m
intervals. The scaffold will be carried out the necessary clamp at every ledgers
fixing to the existing beam.

- This lift will be fully boarded.

- Installed the guardrails no less than 970mm (32 inch) or not more than 1140mm
(45 inch) high with a mid-rails or as required by National Standard. There must
not be a gap between guardrails or between toe boards and guardrails, greater
than 470mm (18 inch)

- Once all guardrails are completed including stop-ends toe board will be fitted to
all elevations and the window reveals. All to be boards will be secured at a
minimum two position using putlog clips to the standard. Stop ends will be fixed
using ‘dead man’ puncheon where necessary

- Installed the toe boards with the minimum of 102mm (3 ½ inches) in height to
accommodate the use of 2x4 lumber as toe boards or as required National
Standard and must be secured to prevent movement. Toe boards are to be of
aluminums or steel performed to match the scaffold

- Ledgers bracing to fixed to the end pairs of standard and alternative pairs of
standard using swivel couplers within 300mm of the node point

- Netting must be placed between the toe board and mid rails to prevent materials
falling onto the ground exposing people below to fall hazards

- All poles, legs or upright of scaffolds shall be plumb and rigidly braced to prevent
swaying and displacement. Sufficient ties or raking shores shall be provided to
ensure that scaffold fall away from the object being scaffolder

- Fully planked of the scaffold work platform with aluminums or steel scaffold
planks or 51mm x 254mm (2’’x10’’ inches nominal to accommodate the use of
nominal lumber which is more prevalent than thickness 2x10 that meets planking
requirement.

- Scaffold shall be planked end to end on each side of the object. The planking
needs to be supported around the subject to ensure the decking or planking will
sufficiently hold the intended weight and tools and materials (Refer calculation)

- For vertical ladder attached internally to the narrow side clear hand and foot
holds shall be provided by blocking pieces if necessary. Where vertical ladders
rise 4m an intermediate landing is 2.5m

- Identify the location and approved shop drawing.

- Setting out-Existing Beam Structure will be used as reference for setting out of
opening and subsequently setting out for position Beam Structure as support.

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 11 of 18

- Boards will be placed above the beam structure and clams to be used to lock
tubes onto ‘I’ beams along 10m to the existing walkaway.

- Tubes will be placed above or positioned inside the web parallel beams. In all
cases they will be locked in position using beam clamps

- Working away from the ladder position scaffolders will fix bottom guardrails
progressively to the standard using right angle couplers. The main guardrail will
be fixed at a minimum height 950mm above the working platform. An
intermediate guardrail will be fixed to ensure no vertical gap greater than 470mm
between guardrails

- Scaffolders will be used the advanced guardrails principle by installing guardrails


progressively from below using step system

- Once the scaffold has been erected essentially supervisor will offer to KSM for
inspection along with handover certificate and Scaff tag

D. Dismantle Scaffold

- After removal of materials and equipment from the working platform, dismantle
generally in the reverse order of the erection sequence

- Removal the ties to the permanent structure should progress at the same rate as
the dismantling process.

- Do not remove ties until the dismantling of the scaffold reached the level of the
ties

- Do not remove diagonal braces until it necessary to remove the standard which
it is a attached

- Ledgers should not be removed from any working level before the removal of
scaffold planks from the same level

- Localized overloading by stacking dismantled equipment on a partially


dismantled scaffold shall be avoided

- Stack materials neatly in the appropriate stillages and pallets.

- Prior to the dismantling of scaffolding that is taking place and also during
dismantling process the following safety precautions must be followed.

a) Upon completion, joint survey with KSM shall be carried out to check for compliance
with the specified requirement.

9 COVID 19 Safety Measures to be follow strictly throughout the setup.

10 To do final housekeeping at works area and proper material arrangement.

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 12 of 18

5.0 Inspection, Testing and Commissioning Proposal

Inspection and Test Plans (ITP) shall include inspection at the following stage.

a) Receiving of materials / machinery


i. Material on site inspection
ii. Material quality inspection

b) In-process inspection during installation


i. Setting out by inspection

c) Final stage prior to handover


i. Quality on work done inspection
ii. Final handover inspection

ITP shall also address the “Hold Point”, where approval on the work activity is required.

Refer to Attachment 1: Inspection and Test Plans

6.0 List of Attachments / Appendices / References

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 13 of 18

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 14 of 18

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 15 of 18

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 16 of 18

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 17 of 18

Rev. 0 Rev. date: 20211106


KM1 WALKABLE CEILING PROJECT

Work Method Statement for Installation of


scaffolding
Prepared by: Ref. no:
KM1-YUTONGDYNAMIC-PB-
(Signature) Amira WMS-0010
Revision: 00

Name: Nursyafiqah Amira Date: 22/03/2022


Contact no.: 017- 706 4685
Company: YU TONG DYNAMIC SDN BHD Page 18 of 18

Rev. 0 Rev. date: 20211106

You might also like