A1 VALLEY PORTION E/W VOLUME FILLED

A1 VALLEY PORTION BOULDER PITCHING AND FILLER MATERIAL VOLUME


UPTO HFL
AREA AT FILL VOLUME OF SOIL AREA OF BOULDER VOLUME OF BOULDER AREA OF FILLER VOLUME OF BOULDER
CHAINAGE UPTO HFL B/W CH. CHAINAGE MATERIAL MATERIAL MATERIAL MATERIAL
1176372.132 64.23 1254.337 1176372.132 5.351 104.567 2.676 52.284
1176352.470 63.36 1290.200 1176352.470 5.285 106.875 2.643 53.438
1176332.470 65.66 1308.200 1176332.470 5.402 107.838 2.701 53.919
1176312.470 65.16 1289.000 1176312.470 5.381 107.934 2.691 53.967
1176292.470 63.74 1262.400 1176292.470 5.412 104.223 2.706 52.112
1176272.470 62.50 1267.707 1176272.470 5.010 98.357 2.505 49.179
1176252.000 61.36 1219.800 1176252.000 4.600 85.242 2.300 42.621
1176232.000 60.62 1046.425 1176232.000 3.925 73.213 1.962 36.606
1176212.070 44.39 230.225 1176212.070 3.422 15.953 1.711 7.977
1176207.070 47.70 0 1176207.070 2.959 0.000 1.479 0.000
TOTAL VOLUME 10168.294 BOULDER VOL. 804.203 FILLER VOL. 402.101