You are on page 1of 2

DAILY DIARY FOR THE MONTH: - JUNE 2021

NAME OF THE EMPLOYEE: DHRUBAJYOTI DATTA DESIGNATION: SITE ENGINEER HQ: DABRA
DATE DESCRIPTION OF WORK

P6 & P7 pile cap, P10 1st lift reinforcement binding. A2 stem 3rd lift and tie beam casting
01-06-2021
complete. A1 approach earthwork in progress.

02-06-2021 P6 & P7 pile cap, P10 1st lift reinforcement binding. A1 approach earthwork in progress.

P6 pile cap & P10 1st lift reinforcement binding. P7 pile cap shuttering complete. A1 approach
03-06-2021
earthwork in progress.

P6 pile cap reinforcement binding. P7 pile cap casting complete. A1 approach earthwork in
04-06-2021
progress.
P6 pile cap reinforcement binding. P10 pier 1st lift shuttering in progress. A1 approach
05-06-2021
earthwork in progress.

06-06-2021 SUNDAY

P6 pile cap casting complete. P10 pier 1st lift shuttering in progress. A1 approach earthwork in
07-06-2021
progress.

P7 shaft 1st lift reinforcement binding. P10 pier 1st lift shuttering in progress. A1 approach
08-06-2021
earthwork in progress.

P6 & P7 shaft 1st lift reinforcement binding. P10 pier 1st lift shuttering in progress. A1
09-06-2021
approach earthwork in progress.
P6 & P7 shaft 1st lift reinforcement binding. P10 pier 1st lift shuttering in progress. A1
10-06-2021
approach earthwork in progress.
P6 & P7 shaft 1st lift reinforcement binding. P10 pier 1st lift shuttering is completed. A1
11-06-2021
approach earthwork in progress.
P6 shaft 1st lift reinforcement binding. P10 pier 1st lift casting complete. A1 approach
12-06-2021
earthwork in progress.

13-06-2021 SUNDAY

14-06-2021 P6 shaft 1st lift reinforcement binding. P7 1st lift shaft shuttering. P4 pier cap casting complete.

P6 shaft 1st lift reinforcement binding. P7 1st lift shaft shuttering. A1 approach earthwork in
15-06-2021
progress.
P6 shaft 1st lift reinforcement binding. P7 1st lift shaft casting. A1 approach earthwork in
16-06-2021
progress.

P4 OHE Mast reinforcement placing and shuttering. P6 shaft 1st lift shuttering. P7 1st lift
17-06-2021
shaft deshuttering. A1 approach earthwork in progress.
18-06-2021 P4 OHE Mast casting. P6 shaft 1st lift shuttering. A1 approach earthwork in progress.

19-06-2021 P7 2nd lift shaft reinforcement placing. A1 approach earthwork in progress.

20-06-2021 SUNDAY

21-06-2021 P7 2nd lift reinforcement placing. P6 shaft 1st lift casting. A1 & A2 approaches earthwork.

22-06-2021 P7 2nd lift reinforcement placing. P4 pedestal casting. A1 & A2 approaches earthwork.

23-06-2021 P7 2nd lift shuttering. A1 approaches earthwork.

24-06-2021 P7 2nd lift shuttering. A1 approaches earthwork.

25-06-2021 P7 2nd lift shuttering. P6 2nd lift reinforcement. A1 approaches earthwork.

26-06-2021 P7 2nd lift casting. P6 2nd lift reinforcement. A1 & A2 approaches earthwork.

27-06-2021 SUNDAY

28-06-2021 P6 2nd lift shuttering in progress. A1 approaches earthwork.

29-06-2021 P6 2nd lift shuttering complete. A1 & A2 approaches earthwork.

P6 2nd lift casting complete. P8 shaft 2nd lift reinforcement making complete. A1 & A2
30-06-2021
approaches earthwork.

Counter Signed By In charge Signature of Employee with Designation