DAILY DIARY FOR THE MONTH: - SEPTEMBER 2020

NAME OF THE EMPLOYEE: DHRUBAJYOTI DATTA DESIGNATION: SITE ENGINEER HQ: DABRA
DATE DESCRIPTION OF WORK

Reinforcement placing at A1 bed block and P1 pier cap. P2 pier cap deshuttering. P3 pier 5th
1.10.2020
lift reinforcement placing in progress. P10/9 , P10/7 & A2/10 boring in progress.

2.10.2020 Holiday(Gandhi Jayanti)

Reinforcement placing at A1 bed block and P1 pier cap. P2 OHE mast reinforcement placing.
3.10.2020
P3 pier 5th lift reinforcement placing in progress. P10/9 , P10/7 & A2/10 boring in progress.

4.10.2020 SUNDAY

P2 OHE mast shuttering in progress. P3 pier 5th lift reinforcement placing in progress. A2/10
5.10.2020
& P10/7 boring.
P2 OHE mast shuttering complete. P3 pier 5th lift reinforcement placing in progress. A2/10
6.10.2020
boring. P10/9 casting complete.
P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring. P10/7 pile
7.10.2020
casting complete.
P2 OHE mast casting completed. P3 pier 5th lift reinforcement placing in progress. A2/17,
8.10.2020
A2/14, A2/10 boring.

9.10.2020 P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring.

10.10.2020 P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring.

11.10.2020 SUNDAY

12.10.2020 P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring.

13.10.2020 P3 pier 5th lift shuttering in progress. A2/17, A2/14 boring. A2/10 casting complete.

P2 pedestal shuttering complete. P3 pier 5th lift shuttering in progress. A2/17 boring. A2/14
14.10.2020
casting complete.
P2 pedestal casting completed. P3 pier 5th lift shuttering in progress. A2/5, A2/17, A2/20
15.10.2020
boring.

16.10.2020 P3 pier 5th lift shuttering in progress. A2/5, A2/13, A2/20 boring.

17.10.2020 P3 pier 5th lift shuttering in progress. A2/5, A2/13, A2/20 boring.

18.10.2020 SUNDAY
19.10.2020 P3 pier 5th lift casting completed. A2/5, A2/13, A2/20 boring.

20.10.2020 P3 pier 5th lift deshuttering in progress. A2/5, A2/13, A2/20 boring.

21.10.2020 P3 pier 5th lift deshuttering completed. A2/5, A2/13, A2/20 boring.

P2 pier cap destaging work in progress. P3 pier 6th lift reinforcement placing. A2/5, A2/13,
22.10.2020
A2/20 boring.
P2 pier cap destaging work in progress. P3 pier 6th lift reinforcement placing. A2/5 boring
23.10.2020
complete. A2/13, A2/20 boring.

24.10.2020 P3 pier 6th lift reinforcement placing. A2/13, A2/20 boring.

25.10.2020 SUNDAY

26.10.2020 P3 pier 6th lift reinforcement placing. A2/17 reinforcement cage making complete.

P3 pier 6th lift reinforcement placing. A2/5 reinforcement cage making complete. A2/17
27.10.2020
casting done.
P3 pier 6th lift reinforcement placing. A2/20 reinforcement cage making complete. A2/5
28.10.2020
casting done.
P3 pier 6th lift reinforcement placing. A2/16 boring. A2/20 casting done. A2/13
29.10.2020
reinforcement cage making complete.

30.10.2020 P3 pier 6th lift reinforcement placing. A2/16 boring. A2/13 casting done.

31.10.2020 P3 pier 6th lift reinforcement placing. A2/16 & A2/9 boring.

Counter Signed By In charge Signature of Employee with Designation