NAME OF THE EMPLOYEE: DHRUBAJYOTI DATTA DESIGNATION: SITE ENGINEER HQ: DABRA
DATE DESCRIPTION OF WORK
Reinforcement placing at A1 bed block and P1 pier cap. P2 pier cap deshuttering. P3 pier 5th
1.10.2020
lift reinforcement placing in progress. P10/9 , P10/7 & A2/10 boring in progress.
Reinforcement placing at A1 bed block and P1 pier cap. P2 OHE mast reinforcement placing.
3.10.2020
P3 pier 5th lift reinforcement placing in progress. P10/9 , P10/7 & A2/10 boring in progress.
4.10.2020 SUNDAY
P2 OHE mast shuttering in progress. P3 pier 5th lift reinforcement placing in progress. A2/10
5.10.2020
& P10/7 boring.
P2 OHE mast shuttering complete. P3 pier 5th lift reinforcement placing in progress. A2/10
6.10.2020
boring. P10/9 casting complete.
P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring. P10/7 pile
7.10.2020
casting complete.
P2 OHE mast casting completed. P3 pier 5th lift reinforcement placing in progress. A2/17,
8.10.2020
A2/14, A2/10 boring.
9.10.2020 P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring.
10.10.2020 P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring.
11.10.2020 SUNDAY
12.10.2020 P3 pier 5th lift reinforcement placing in progress. A2/17, A2/14, A2/10 boring.
13.10.2020 P3 pier 5th lift shuttering in progress. A2/17, A2/14 boring. A2/10 casting complete.
P2 pedestal shuttering complete. P3 pier 5th lift shuttering in progress. A2/17 boring. A2/14
14.10.2020
casting complete.
P2 pedestal casting completed. P3 pier 5th lift shuttering in progress. A2/5, A2/17, A2/20
15.10.2020
boring.
16.10.2020 P3 pier 5th lift shuttering in progress. A2/5, A2/13, A2/20 boring.
17.10.2020 P3 pier 5th lift shuttering in progress. A2/5, A2/13, A2/20 boring.
18.10.2020 SUNDAY
19.10.2020 P3 pier 5th lift casting completed. A2/5, A2/13, A2/20 boring.
20.10.2020 P3 pier 5th lift deshuttering in progress. A2/5, A2/13, A2/20 boring.
21.10.2020 P3 pier 5th lift deshuttering completed. A2/5, A2/13, A2/20 boring.
P2 pier cap destaging work in progress. P3 pier 6th lift reinforcement placing. A2/5, A2/13,
22.10.2020
A2/20 boring.
P2 pier cap destaging work in progress. P3 pier 6th lift reinforcement placing. A2/5 boring
23.10.2020
complete. A2/13, A2/20 boring.
25.10.2020 SUNDAY
26.10.2020 P3 pier 6th lift reinforcement placing. A2/17 reinforcement cage making complete.
P3 pier 6th lift reinforcement placing. A2/5 reinforcement cage making complete. A2/17
27.10.2020
casting done.
P3 pier 6th lift reinforcement placing. A2/20 reinforcement cage making complete. A2/5
28.10.2020
casting done.
P3 pier 6th lift reinforcement placing. A2/16 boring. A2/20 casting done. A2/13
29.10.2020
reinforcement cage making complete.
30.10.2020 P3 pier 6th lift reinforcement placing. A2/16 boring. A2/13 casting done.
31.10.2020 P3 pier 6th lift reinforcement placing. A2/16 & A2/9 boring.