DAILY DIARY FOR THE MONTH: - JANUARY 2022

NAME OF THE EMPLOYEE: DHRUBAJYOTI DATTA DESIGNATION: SITE ENGINEER HQ: DABRA
DATE DESCRIPTION OF WORK
A2 stem 2nd tie beam staging and bottom shuttering. P10 pier cap staging work is in progress. A2
01-01-2022 approach earthwork is in progress.

02-01-2022 Sunday.

03-01-2022 P6 shaft 4th lift bar bending. Erection work at P3-P4 span. A2 approach earthwork is in progress.

P6 Pier Shaft 4th lift vertical bar bending. A2 stem 2nd tie beam bar bending and placing is in
04-01-2022 progress. Erection work at P3-P4 span.

P6 Pier Shaft 4th lift vertical bar bending. A2 stem 2nd tie beam bar bending and placing is in
05-01-2022 progress. Erection work at P3-P4 span.

06-01-2022 No work due to railfall.

P6 Pier shaft 4th lift vertical bar fixing. A2 tie beam reinforcement fixing in progress. Erection work at
07-01-2022 P3-P4 span.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam reinforcement fixing
08-01-2022 in progress. A2 approach earthwork is in progress.

09-01-2022 Sunday.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
10-01-2022 progress. A2 tie beam shuttering board fixing in progress.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam shuttering board
11-01-2022 fixing in progress. A2 approach earthwork is in progress.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam shuttering board
12-01-2022 fixing in progress. A2 approach earthwork is in progress.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam shuttering board
13-01-2022 fixing in progress. A2 approach earthwork is in progress.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
14-01-2022 progress.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
15-01-2022 progress.

16-01-2022 Sunday.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
17-01-2022 progress. A2 stem tie beam casting complete.

P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
18-01-2022 progress.

P6 pier shaft 4th lift reinforcement fixing. P10 pier cap reinforcement making is in progress. P7 3rd
19-01-2022 lift staging work. A2 approach eathwork is in progress.

20-01-2022 Went to Agra Office.(Official Purpose)


P6 pier shaft 4th lift reinforcement fixing. P10 pier cap staging is in progress. P7 3rd lift links bar
21-01-2022 bending in progresss. A2 approach eathwork is in progress. Erection work at P3-P4 span.

P6 pier shaft 4th lift reinforcement fixing. P10 pier cap staging is in progress. P7 3rd lift staging work
22-01-2022 and links bar bending in progresss. A2 approach eathwork is in progress.

23-01-2022 Sunday.

P6 pier shaft 4th lift shuttering in progress. P7 shaft 3rd lift reinforcement making. P4-P5 span
24-01-2022 errection.

25-01-2022 P6 pier shaft 4th lift shuttering in progress. P4-P5 span erection in progress.

26-01-2022 Holiday (Republic Day)

27-01-2022 P6 pier shaft 4th lift shuttering is going on. P4-P5 erection in progress.

28-01-2022 Load Deflection Test on 18.3 m Plate Girder and 30.5 OWG at banganaga bridge.

29-01-2022 P7 Pier shaft reinforcement work. P4-P5 erection in progress.

30-01-2022 Sunday.

31-01-2022 P6 shaft deshuttering. P6 shaft reinforcement making. Erection work P4-P5 span.