NAME OF THE EMPLOYEE: DHRUBAJYOTI DATTA DESIGNATION: SITE ENGINEER HQ: DABRA
DATE DESCRIPTION OF WORK
A2 stem 2nd tie beam staging and bottom shuttering. P10 pier cap staging work is in progress. A2
01-01-2022 approach earthwork is in progress.
02-01-2022 Sunday.
03-01-2022 P6 shaft 4th lift bar bending. Erection work at P3-P4 span. A2 approach earthwork is in progress.
P6 Pier Shaft 4th lift vertical bar bending. A2 stem 2nd tie beam bar bending and placing is in
04-01-2022 progress. Erection work at P3-P4 span.
P6 Pier Shaft 4th lift vertical bar bending. A2 stem 2nd tie beam bar bending and placing is in
05-01-2022 progress. Erection work at P3-P4 span.
P6 Pier shaft 4th lift vertical bar fixing. A2 tie beam reinforcement fixing in progress. Erection work at
07-01-2022 P3-P4 span.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam reinforcement fixing
08-01-2022 in progress. A2 approach earthwork is in progress.
09-01-2022 Sunday.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
10-01-2022 progress. A2 tie beam shuttering board fixing in progress.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam shuttering board
11-01-2022 fixing in progress. A2 approach earthwork is in progress.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam shuttering board
12-01-2022 fixing in progress. A2 approach earthwork is in progress.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 tie beam shuttering board
13-01-2022 fixing in progress. A2 approach earthwork is in progress.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
14-01-2022 progress.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
15-01-2022 progress.
16-01-2022 Sunday.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
17-01-2022 progress. A2 stem tie beam casting complete.
P6 shaft 4th lift reinforcement fixing. Erection work at P3-P4 span. A2 approach earthwork is in
18-01-2022 progress.
P6 pier shaft 4th lift reinforcement fixing. P10 pier cap reinforcement making is in progress. P7 3rd
19-01-2022 lift staging work. A2 approach eathwork is in progress.
P6 pier shaft 4th lift reinforcement fixing. P10 pier cap staging is in progress. P7 3rd lift staging work
22-01-2022 and links bar bending in progresss. A2 approach eathwork is in progress.
23-01-2022 Sunday.
P6 pier shaft 4th lift shuttering in progress. P7 shaft 3rd lift reinforcement making. P4-P5 span
24-01-2022 errection.
25-01-2022 P6 pier shaft 4th lift shuttering in progress. P4-P5 span erection in progress.
27-01-2022 P6 pier shaft 4th lift shuttering is going on. P4-P5 erection in progress.
28-01-2022 Load Deflection Test on 18.3 m Plate Girder and 30.5 OWG at banganaga bridge.
30-01-2022 Sunday.
31-01-2022 P6 shaft deshuttering. P6 shaft reinforcement making. Erection work P4-P5 span.