Professional Documents
Culture Documents
Comparative Compile Final-1
Comparative Compile Final-1
OF ASSAM
DISTRICT :- JORHAT
LAC :- JORHAT
taken up under any scheme / programmes like NlCPR /NEC/NABARD/State plan / FDR
FDR( CRF) / MLAADS / PMGSY / Economic importance etc nor shall be proposed for
This working estimate amounting to 149.97 L (Rupees One Forty Nine Lakhs and
Ninety seven Thousand ) only has been framed by the Executive Engineer, PWRD, Jorhat, Dergaon & Titabor
Territorial Road Division to show the probable cost for the above mentioned working estimate.
REPORT
The estimate for the above work is sanctioned for Rs 1,50,73,000.00 Lakh vide Govt order no
AA/PWR/2020-21-23720. Accordingly, the work is alloted to the contractor Sri Rupanjal Barbaruah as per
formal work order No. CE/DEVTB/267/2020-21/05 Dt. 31/12/2020 at their own quoted rate for an amounting
to Rs 1,35,65,700.00. Now the work is going on during execution is observed that some additional work like
feeder roads improvement to be done as per requirement of site which provide benefit in communication to
the people of the locality. The amount required for execution of works is within the sanctioned amount.
The following provisions are originally incorporated in this estimate.
1. Cleaning and Grubbing.
2. Earthwork in Embankment
3. Earthwork in Subgrade & shoulder
4. GSB
5. Earthwork in Excavation
6. WBM-III
6. I.C.B.P
7. Plain & Reinforced cement concrete
9. Traffic Sign
9. Unlined surface Drain
10. HPC laying 600mm dia NP3
The itemwise excess and savings have been shown in the comparative statement enclosed with the
proposed working estimate.This estimate has been prepared incorporating the rate as per quoted in tender by
the contractor and as per SOR of rural roads for 2017-18.
All works will be carried out as per APWD General Specifications current in the state.
Counter Signed By
Superintending Engineer
COST ESTIMATE
Name of work:- Working Estimate of Improvement/construction (i) Sankarpur Road (ii) Jana Path (iii) Meghan Paul Path (iv) L.k. Path
(remaining Portion) (v) Nepali Basti Road (vi) Khemnath Path (Package II) (Garmur Baghchung interconnected road under Signature
Project of SOPD-G (State Priority Scheme) for the year 2020-21, Jorhat LAC, Package No. SOPD-G-20-21-04)
(b) Jana Path Cum. as per Annexure 2.2.1 47.25 120.00 5670.00
(f) Khemnath Path Cum. as per Annexure 2.6.1 42.00 120.00 5040.00
Sub Total= 89.25 10710.00
9/6.7 Providing and laying Interlocking Concrete Block
Pavement (ICBP) conforming to IS:15658-2006
including all lead and lift complete as per technical
specification and as directed. (a)80mm thick interlocking
precast blocks having compressive strength of
40N/sq.mm.
(b) Jana Path Sqm. as per Annexure 2.2.1 1720.00 980.00 1685600.00
(f) Khemnath Path Sqm. as per Annexure 2.6.1 697.50 980.00 683550.00
Sub-Total= 2417.50 2369150.00
10/11.4
Plain/Reinforced cement concrete, in open foundation
complete as per drawing and technical specification
including steel shuttering formwork.(Cl 1500,1700 &
2100) (B) Grade M20
Case I-Using concrete mixer
(b) Jana Path cum as per Annexure 2.2.1 47.25 6100.00 288225.00
(f) Khemnath Path cum as per Annexure 2.6.1 42.00 6100.00 256200.00
Sub Total = 89.25 544425.00
11/10.2B Providing and erecting direction and place
identification retro-reflectorised sign as per IRC:67
made of encapsulated lens type reflective sheeting vide
Clause 1701.2.3, fixed over aluminium sheeting, 2 mm
thick with area not exceeding 0.9 sqm supported on a
mild steel single angle iron post 75 x 75 x 6 mm firmly
fixed to the ground by means of properly designed
foundation with M-15 grade cement concrete 450 x
450 x 600 mm, 600 mm below ground level as per
approved drawing and Technical Specification Clause
1701
(b) Jana Path Hec 0.11 42648.30 4478.07 0.11 36500.00 4015.00 0.11 36500.00 3942.00 0.00 73.00
(c)Megan Paul Path Hec 0.10 42648.30 4264.83 0.10 35500.00 3550.00 0.10 35500.00 3550.00 0.00 0.00
(d) L K Path Hec 0.128 42648.30 5458.98 0.13 35500.00 4615.00 0.22 35500.00 7973.30 3358.30 0.00
(d) Nepali Basti Road Hec 0.09 42648.30 3838.35 0.09 35500.00 3195.00 0.09 35500.00 3195.00 0.00 0.00
(e) Khemnath Path Hec 0.024 42648.30 1023.56 0.02 35500.00 710.00 0.036 35500.00 1278.00 568.00 0.00
Construction of cum
2 embankment (a) 780.55 230.60 179995.10 780.55 150.00 117082.50 798.27 150.00 119740.18 2657.68 0.00
Sankarpur Road
(c)Megan Paul Path cum 275.22 230.60 63465.73 275.22 150.00 41283.00 328.30 150.00 49244.48 7961.48 0.00
Construction of sub
grade and earthen
3 shoulders cum 316.05 286.30 90485.12 316.05 150.00 47407.50 324.76 150.00 48714.29 1306.79 0.00
(a)Sankarpur Road
(b) Jana Path cum 315.00 286.30 90814.50 315.00 150.00 47250.00 324.00 150.00 48600.00 1350.00 0.00
(c)Megan Paul Path cum 96.50 286.30 27627.95 96.50 150.00 14475.00 96.50 150.00 14475.00 0.00 0.00
(d) L K Path cum 284.99 286.30 81593.21 284.99 150.00 42748.50 356.69 150.00 53502.80 10754.30 0.00
(d) Nepali Basti Road cum 42.00 286.30 12024.60 42.00 150.00 6300.00 42.00 150.00 6300.00 0.00 0.00
Providing, laying,
spreading and
5 compacting stone cum 146.19 4650.72 679877.13 146.19 4650.00 679783.50 149.00 4650.00 692850.00 13066.50 0.00
aggregates (a)
Jana Path
(d) L K Path cum 144.00 4601.05 662551.49 144.00 4650.00 669600.00 179.80 4650.00 836067.09 166467.09 0.00
(e) Khemnath Path cum 49.50 4650.72 230211.00 49.50 4650.00 230175.00 57.00 4650.00 265050.00 34875.00 0.00
Providing, laying,
spreading and
6 compacting stone cum 119.93 4727.61 566985.22 119.93 4650.00 557674.50 123.41 4650.00 573841.97 16167.47 0.00
aggregates
(a)Sankarpur Road
(c ) Megan Paul Path cum 51.56 4684.40 241539.38 51.56 4650.00 239754.00 51.56 4650.00 239765.63 11.63 0.00
(e) Nepali Basti Road cum 39.37 4662.80 184485.90 39.57 4650.00 184000.50 39.57 4650.00 183979.66 0.00 20.84
(b) Khemnath Path sqm 682.50 805.50 549754.00 682.50 980.00 668850.00 697.50 980.00 683550.00 14700.00 0.00
Plain/Reinforced
cement concrete,in
10 cum 47.25 6893.00 325694.00 47.25 6100.00 288225.00 47.25 6100.00 288225.00 0.00 0.00
open foundation
(a) Jana Path
(f) Khemnath Path cum 42.00 6893.00 289506.00 42.00 6100.00 256200.00 42.00 6100.00 256200.00 0.00 0.00
HP Culvert NP-3
Earthwork in excavation
12 (a) Sankarpur Road
cum 13.610 102.00 1388.22 13.61 65.00 884.65 13.610 65.00 884.65 0.00 0.00
Bedding of pipe cum 3.780 1369.05 5175.01 3.78 1200.00 4536.00 3.780 1200.00 4536.00 0.00 0.00
Providing & laying
reinforced cement Rm 5.000 2886.80 14434.00 5.00 3000.00 15000.00 5.000 3000.00 15000.00 0.00 0.00
concrete pipe NP3
SAY 21000.00
HP Culvert NP-3
Earthwork in excavation
13 cum 27.220 102.00 2776.44 27.22 65.00 1769.30 54.44 65.00 3538.60 1769.30 0.00
(a) Megan Paul Path
Bedding of pipe cum 7.560 1369.05 10350.02 7.56 1200.00 9072.00 15.12 1200.00 18144.00 9072.00 0.00
COMPAIRETIVE STATEMENT
Name of work:- Working Estimate of Improvement/construction (i) Sankarpur Road (ii) Jana Path (iii) Meghan Paul Path (iv) L.k. Path (remaining Portion) (v) Nepali Basti Road (vi) Khemnath
Path (Package II) (Garmur Baghchung interconnected road under Signature Project of SOPD-G (State Priority Scheme) for the year 2020-21, Jorhat LAC, Package No. SOPD-G-20-21-04)
Bedding of pipe cum 7.560 1369.05 10350.02 7.56 1200.00 9072.00 7.56 1200.00 9072.00 0.00 0.00
Providing & laying
reinforced cement Rm 10.000 2886.80 28868.00 10.00 3000.00 30000.00 10.00 3000.00 30000.00 0.00 0.00
concrete pipe NP3
SAY 42000.00
Construction of unlined
15 surface drains Rm 400.000 58.20 23280.00 400.00 60.00 24000.00 460.00 60.00 27600.00 3600.00 0.00
(a) Megan Paul Path
HP Culvert NP-3
Earthwork in excavation
16 (a) Sankarpur Road
cum 0.000 0.00 0.00 0.00 0.00 0.00 13.610 65.00 884.65 884.65 0.00
Bedding of pipe cum 0.000 0.00 0.00 0.00 0.00 0.00 3.780 1200.00 4536.00 4536.00 0.00
Providing & laying
reinforced cement Rm 0.000 0.00 0.00 0.00 0.00 0.00 5.00 3000.00 15000.00 15000.00 0.00
concrete pipe NP3
Name of Work :- Construction of Shankarpur Road under SOPD(G) for 2019-20 under Jorhat, Dergaon & Titabor
Territorial Road Division in Jorhat L.A.C. for the year 2019-20.
Ch. 0.00
C/S AREAS
Cross Sectional Area of E/W in embankment
80mm thick ICBP 75mm WBM Gr-III = 1/2 x ( 5.90 + 7.85 ) x 0.65 -
125mm GSB 1/2 x ( 3.50 + 4.54 ) x 0.65 = 1.856 Sqm
5.00
3.00
Cross Sectional Area of E/W in shoulder
0.30
3.50 = 1/2 x ( 5.00 + 5.90 ) x 0.30
Existing Earthen Road 0.65 - 3.30 x 0.30 = 0.645 Sqm
4.54
7.85
4.18
7.55
4.63
7.64
4.76
7.70
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Ch. 120.00 C/S AREAS
Cross Sectional Area of E/W in embankment
80mm thick ICBP 75mm WBM Gr-III = 1/2 x ( 5.90 + 7.85 ) x 0.65 -
125mm GSB 1/2 x ( 3.50 + 4.54 ) x 0.65 = 1.856 Sqm
5.00
3.00
Cross Sectional Area of E/W in shoulder
0.30
3.50 = 1/2 x ( 5.00 + 5.90 ) x 0.30
Existing Earthen Road 0.65 - 3.3 x 0.30 = 0.645 Sqm
4.54
7.85
5.14
7.85
4.73
7.64
4.46
7.70
Ch. 240.00 C/S AREAS
80mm thick ICBP 75mm WBM Gr-III Cross Sectional Area of E/W in embankment
125mm GSB = 1/2 x ( 5.90 + 7.79 ) x 0.63 -
5.00 1/2 x ( 3.60 + 4.61 ) x 0.63 = 1.727 Sqm
3.00
Cross Sectional Area of E/W in shoulder
0.30
3.60 = 1/2 x ( 5.00 + 5.90 ) x 0.30
Existing Earthen Road 0.63 - 3.3 x 0.30 = 0.645 Sqm
4.61
7.79
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
4.43
7.64
4.66
7.72
4.38
7.57
4.12
7.27
4.18
7.57
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
4.33
7.66
4.69
7.78
4.38
7.57
4.76
7.70
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
EARTHWORK STATEMENT Annexure - IV
Name of Work :- Construction of Shankarpur Road under SOPD(G) for 2019-20 under Jorhat, Dergaon & Titabor
Territorial Road Division in Jorhat L.A.C. for the year 2019-20.
Name of Work :- Construction of Shankarpur Road under SOPD(G) for 2019-20 under Jorhat, Dergaon & Titabor
Territorial Road Division in Jorhat L.A.C. for the year 2019-20.
Ch. 0.00
C/S AREAS
Cross Sectional Area of E/W in embankment
80mm thick ICBP 75mm WBM Gr-III = 1/2 x ( 6.40 + 8.20 ) x 0.60 -
125 mm GSB 1/2 x ( 4.80 + 5.76 ) x 0.60 = 1.212 Sqm
5.50
4.00
Cross Sectional Area of E/W in shoulder
0.30
4.80 = 1/2 x ( 5.50 + 6.40 ) x 0.300
Existing Earthen Road 0.60 - 4.30 x 0.300 = 0.495 Sqm
5.76
8.20
4.54
6.85
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
Rate analysis of HPC 600 mm dia NP-3
2/9.2/B/ii Type B (First class bedding) Granular materials 7.5x1.65x0.30 = 3.71 cm 3.78 1369.05 5175.01
3/9.3/iii Providing and laying H.P.C 600 mm dia NP-3 RM 5.00 2886.80 14434.00
Total 20997.229
SAY Rs 21000.00
Total = 1 x Rs 21000.00 = Rs 21000.00
Proposed H/C
Chainage (m)
Distance (m)
Width (m)
( Mtr.)
Width (m)
Width (m)
Width (m)
Area (m2)
Thickness
Thickness
Quantity
Quantity
(m3)
(m3)
(m)
(m)
(11)=(10)x (14)=(2)x (16)
(1) (2) (3) (4) (9) = (4) (10) (12) = (4) (13) (15) = (9)
(9)x(2) (13)x(12) =(2)x(15)
0.00 0.00 10.00 3.00 10.00 10.00 0.125 0.000 10.00 0.075 0.00 10.00 0.000
20.00 20.00 5.10 3.00 3.00 3.00 0.125 16.250 3.00 0.075 9.750 3.00 130.000
50.00 30.00 5.20 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
80.00 30.00 5.00 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
110.00 30.00 4.90 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
140.00 30.00 5.30 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
170.00 30.00 5.25 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
200.00 30.00 5.30 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
230.00 30.00 5.40 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
260.00 30.00 5.60 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
290.00 30.00 5.20 3.00 3.00 3.00 0.125 11.250 3.00 0.075 6.750 3.00 90.000
320.00 30.00 5.00 3.00 3.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
350.00 30.00 5.30 3.00 3.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
380.00 30.00 5.30 3.00 3.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
410.00 30.00 5.30 3.00 3.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
440.00 30.00 5.30 3.00 3.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
470.00 30.00 5.30 3.00 3.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
500.00 30.00 5.30 3.00 3.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
525.00 25.00 8.00 3.00 6.00 6.00 0.150 16.875 6.00 0.075 8.438 6.00 112.500
309.875 Cum 146.188 Cum 1682.500 Sqm
Levelling Coarse 18 % 55.778
0.50 m 0.50 m
PCC Restraint wall
250 M X 300 M
0.305 m
NOT TO SCALE
Name of Work :- Construction of Meghan Pal Road (Lichubari Colony) under SOPD(G) for 2019-20 under Jorhat,
Dergaon & Titabor Territorial Road Division in Jorhat L.A.C.
Ch. 0.00
C/S AREAS
Cross Sectional Area of E/W in embankment
80mm thick ICBP 75mm WBM Gr-III = 1/2 x ( 4.90 + 6.25 ) x 0.45 -
125mm GSB 1/2 x ( 3.00 + 3.72 ) x 0.45 = 0.997 Sqm
4.00
2.50
Cross Sectional Area of E/W in shoulder
0.30
3.00 = 1/2 x ( 4.00 + 4.90 ) x 0.30
Existing Earthen Road 0.45 - 2.80 x 0.30 = 0.495 Sqm
3.72
6.25
3.90
6.40
3.68
6.55
4.13
6.64
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Ch. 120.00 C/S AREAS
Cross Sectional Area of E/W in embankment
80mm thick ICBP 75mm WBM Gr-III = 1/2 x ( 4.90 + 6.34 ) x 0.48 -
125mm GSB 1/2 x ( 2.90 + 3.67 ) x 0.48 = 1.121 Sqm
4.00
2.50
Cross Sectional Area of E/W in shoulder
0.30
2.90 = 1/2 x ( 4.00 + 4.90 ) x 0.30
Existing Earthen Road 0.48 - 2.8 x 0.30 = 0.495 Sqm
3.67
6.34
3.52
6.25
3.72
7.00
4.04
6.85
Ch. 240.00 C/S AREAS
80mm thick ICBP 75mm WBM Gr-III Cross Sectional Area of E/W in embankment
125mm GSB = 1/2 x ( 4.90 + 6.55 ) x 0.55 -
4.00 1/2 x ( 3.00 + 3.88 ) x 0.55 = 1.257 Sqm
2.50
Cross Sectional Area of E/W in shoulder
0.30
3.00 = 1/2 x ( 4.00 + 4.90 ) x 0.30
Existing Earthen Road 0.55 - 2.8 x 0.30 = 0.495 Sqm
3.88
6.55
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
3.76
6.70
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
CROSS SECTIONAL AREAS OF EARTHWORK IN EMBANKMENT AND SHOULDER Annexure - III
Junior Engineer, PWRD, Jorhat, Asstt. Executive Engineer, PWRD Executive Engineer,PWRD, Jorhat,
Dergaon Titabor Territorial Road Division Jorhat Territorial Road Sub-Division-I Dergaon Titabor Territorial Road Division
Name of Work :- Construction of Meghan Pal Road (Lichubari Colony) under SOPD(G) for 2019-20 under Jorhat, Dergaon & Titabor
Territorial Road Division in Jorhat L.A.C.
2/9.2/B/ii Type B (First class bedding) Granular materials 7.5x1.65x0.30 = 3.71 cm 3.78 1369.05 5175.01
3/9.3/iii Providing and laying H.P.C 600 mm dia NP-3 RM 5.00 2886.80 14434.00
Total 20997.229
SAY Rs 21000.00
Total = 4 x Rs 21000.00 = Rs 84000.00
NAME OF WORK :- Construction of LK PATH (Balance Length)(From CH. 800.00 M to CH. 1440.00 M)
under SOPD(G) for the year 2019-20 under PWD, Jorhat Dergaon Titabor Territorial Road Division, Jorhat.
Proposed H/C
Chainage (m)
Distance (m)
Width (m)
Thickness(m)
( Mtr.)
Width (m)
Width (m)
Area (m2)
Thickness
Width(m)
Quantity
Quantity
(m3)
(m )
(m)
3
(7)=(6)*(5 (10)=(2)x
(1) (2) (3) (4) (5) (6) 8) = (5) (9) (11) = (5) (12) =(2)x(11)
)*(2) (9)x(8)
0.00 0.00 4.60 3.00 3.00 0.125 0.00 3.00 0.075 0.00 3.00 0.00
30.00 30.00 4.50 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
60.00 30.00 4.50 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
90.00 30.00 4.40 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
120.00 30.00 4.30 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
150.00 30.00 4.30 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
180.00 30.00 4.30 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
210.00 30.00 4.40 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
240.00 30.00 4.30 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
270.00 30.00 4.50 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
300.00 30.00 4.30 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
330.00 30.00 4.40 3.00 3.00 0.150 13.50 3.00 0.075 6.750 3.00 90.00
360.00 30.00 4.20 3.00 3.00 0.150 13.50 3.00 0.075 6.750 3.00 90.00
390.00 30.00 4.40 3.00 3.00 0.150 13.50 3.00 0.075 6.750 3.00 90.00
420.00 30.00 4.30 3.00 3.00 0.150 13.50 3.00 0.075 6.750 3.00 90.00
450.00 30.00 4.30 3.00 3.00 0.150 13.50 3.00 0.075 6.750 3.00 90.00
460.00 10.00 4.30 4.00 4.00 0.150 6.00 4.00 0.075 2.625 4.00 35.00
470.00 10.00 4.30 3.00 3.00 0.125 0.00 3.00 0.075 2.250 3.00 30.00
510.00 40.00 4.40 3.00 3.00 0.125 0.00 3.00 0.075 9.000 3.00 120.00
540.00 30.00 4.30 3.00 3.00 0.000 0.00 3.00 0.075 6.750 3.00 90.00
570.00 30.00 4.50 3.00 3.00 0.000 0.00 3.00 0.075 6.750 3.00 90.00
600.00 30.00 4.30 3.00 3.00 0.000 0.00 3.00 0.075 6.750 3.00 90.00
630.00 30.00 4.40 3.00 3.00 0.125 11.25 3.00 0.075 6.750 3.00 90.00
640.00 10.00 4.20 3.00 3.00 0.125 3.75 3.00 0.075 2.250 3.00 30.00
201.00 144.38 1655.00
Formation Width
Proposed H/C
Chainage (m)
Distance (m)
Width (m)
Thickness(m)
( Mtr.)
Width (m)
Width (m)
Area (m2)
Thickness
Width(m)
Quantity
Quantity
(m3)
(m )
(m)
3
Bell Mouth @ 3% of WBM Gr-II = 0.236 Cum
Feeder Road 3 = 58.00 x 2.50 x 0.075 = 10.875 Cum
Bell Mouth @ 3% of WBM Gr-II = 0.326 Cum
Total WBM Gr-II = 179.80 cum
(0.150m X 0.150m X
Junior Engineer,PWRD
Asstt. Executive Engineer, PWD Executive Engineer, PWD
Jorhat Territorial Road Sub-Division Jorhat Territorial Road Sub-Division Jorhat Dergaon & Titabor Te
Jorhat Jorhat Road Division Jorhat
erritorial
NAME OF WORK :- Construction of LK PATH (Balance Length)(From CH. 800.00 M to CH. 1440.00 M) under SOPD(G) for the year 2019-
20 under PWD, Jorhat Dergaon Titabor Territorial Road Division, Jorhat.
Rate analysis of HPC 600 mm dia NP-3
2/9.2/B/ii Type B (First class bedding) Granular materials 7.5x1.65x0.30 = 3.71 cm 3.78 1369.05 5175.01
3/9.3/iii Providing and laying H.P.C 600 mm dia NP-3 RM 5.00 2886.80 14434.00
Total 20997.229
SAY Rs 21000.00
Total = 1 x Rs 21000.00 = Rs 21000.00
2/9.2/B/ii Type B (First class bedding) Granular materials 7.5x1.65x0.30 = 3.71 cm 3.78 1369.05 5175.01
3/9.3/iii Providing and laying H.P.C 600 mm dia NP-3 RM 5.00 2886.80 14434.00
Total 20997.229
SAY Rs 21000.00
Total = 2 x Rs 21000.00 = Rs 42000.00
0.25 m 0.25 m
Earthen shoulder subgrade
0.15
2.5m 0.15
m m
NOT TO SCALE
STATEMENT I
Name of work: Construction of Khemnath Path (Ch. 0.00 km to
Ch. 0.210 km by providing ICBP under SOPD(G) for the year 2019-
20 under Jorhat,Dergaon & Titabor Territorial Road Division in
Jorhat LAC.
Clearing and grubbing road land = 1 150 1.6 = 0.024 Hect
1 40 3 = 0.012 Hect
Total = 0.036 Hect
Proposed H/C
Chainage (m)
Distance (m)
Width (m)
width
Width (m)
Width (m)
Thickness
Thickness
Quantity
Quantity
Quantity
(m3)
(m3)
(m2)
(m)
(m)
(7)=(2)* (10)=(2)* (12)=(2)*
(1) (2) (3) (4) (6) (8) = (4) (9) (11) = (4)
(5)*(6) (8)*(9) (11)
0.00 0.00 6.00 6.00 0.150 0.000 6.00 0.075 0.000 6.00 0.00
15.00 15.00 4.00 5.00 0.150 11.250 5.00 0.075 5.625 5.00 82.500
30.00 15.00 4.00 3.00 0.150 6.750 3.00 0.075 3.375 3.00 60.000
60.00 30.00 4.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
90.00 30.00 4.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
120.00 30.00 4.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
150.00 30.00 4.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
180.00 30.00 4.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
210.00 30.00 4.00 3.00 0.150 13.500 3.00 0.075 6.750 3.00 90.000
99.000 Cum 49.500 Cum 682.500 Sqm
Asstt. Executive Engineer, PWDJorhat State Road Sub-Division Executive Engineer, PWDJorhat State Road Division