COMPLETION DRAWING OF CAUSEWAY

TOP & BOTTOM


MAIN STEEL SHORT LENGTH TOR10 @ 150MM C/C,
MAIN STEEL LONG LENGTH TOR12 @150MM C/C
A' 22.660M 22.660M
M30 SLAB

BOTH SIDE
MAIN STEEL TOR16 @ 150MM C/C, M7.5 MIDDLE M30 WALL M7.5 MIDDLE
DIST STEEL TOR12 @ 150MM C/C FILLING FILLING
PORTION PORTION

TOP & BOTTOM


MAIN STEEL LONG LENGTH M7.5 MIDDLE FILLING PORTION M30 RAFT 100mm thk
TOR16 @ 200MM C/C,
MAIN STEEL SHORT LENGTH M7.5 PCC
TOR10 @ 200MM C/C
A
L-SECTION SECTION A-A'

M30 SLAB

DOWNSTREAM SIDE UPSTREAM SIDE

M30 WALL
M30 WALL
NOTES
M7.5 MIDDLE 1. ALL DIMENSIONS & LEVELS ARE IN METERS, UNLESS SPECIFIED
FILLING OTHERWISE.
PORTION

K. S. POWAR
Project Name :- Construction of rain water harvesting reservoir at JNPP site,
village madban, rajapur taluka, district ratnagiri.

Drawing Name :- Completion Drawing of Causeway

Drawing prepared by :- Akshay Powar NPCIL CE Sign :-


Date :- Date :-
HALF TOP & HALF SECTIONAL PLAN Contract Sign :- NPCIL ENC Sign :-
Date :- Date :-