1. Purpose for which estimate is made : To estimate the cost of the construction of the
proposed construction
ii) Brick work in superstructure : 9" thick brick work in cement sand mortar 1:5” and 4.5"
thick brick work in cement sand mortar ratio 1:4
iii) Roofing : 6" thick RCC roofing as per structural design with
proper steel reinforcement.
iv) Wood & Steel Work : Wooden frame and wooden shutters & windows etc.
viii) Electrical installation : P.V.C. conduit wiring and switches etc. with ISI wires.
ix) Sanitary and water supply etc. : A suitable arrangement for sanitary & water supply will
be made.
Details of covered area as per drawing and its cost of construction. Including Pure white marble
stone flooring with granite polish, good quality of all sanitary, electrical work & POP work on walls
& false ceiling as per approved design etc. complete.
sft @
Amount in words :- ( Rs. sixteen Lacks thirtyseven Thousand foure Hundred Only )