Professional Documents
Culture Documents
techniques
Q&A
Answer the following questions and complete the projects below:
1. List three pieces of software that are available to assist in developing
a Work Breakdown Structure (WBS). Give three examples of facets of
business that a well-organised WBS can help with.
Three softwares
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
- Finish to Start
- Start to Start
- Finish to Finish
- Start to Finish
Explain what a Gantt chart
A Gantt chart, commonly used in project management, is one of the most
popular and useful ways of showing activities (tasks or events) displayed
against time. On the left of the chart is a list of the activities and along the
top is a suitable time scale. Each activity is represented by a bar; the
position and length of the bar reflects the start date, duration and end
date of the activity.
The Gantt chart is an excellent tool to graphically show the evolution of the
project, as well as being a great means of communication among the
participants of the project.
Thus, it is possible to analyze the commitment of each member in the
group, as long as they are associated with the task, as a resource
necessary to the performance of the group
3. According to https://www.pmi.org/about/learn-about-pmi/what-is-
project-management: “A project is temporary in that it has a defined
beginning and end in time, and therefore defined scope and
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
- Units Completed
- Start / Finish
- Cost Ratio
- Incremental Milestones
- Weighted or Equivalent Units
- Experience/Opinion
List at least six things that should be included in a progress
report.
Escolham 6 não na ordem para não ficar igual.
- Benefits
- Items Missed
- Budget
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
- Achievements
- Rag Status
- Dependencies
But deadlines aren’t just a way to keep the project on track. They can also
act as a metric to measure the progress of that project. By setting a
number of deadlines to meet, you have given yourself markers across the
project schedule, which can be used measure whether or not you’re
meeting your planned progress.
As work on your project progresses, you can update the plan with the
actual start and finish dates, actual work, actual and remaining duration,
and the current percent complete and percent work complete.CONTINUAR
EXEMPLO
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
Questions you should consider when you are reviewing your Project’s
perfomaces are:
Where do you feel there’s room for you to improve?This will form a
picture of how perceptive the person is at understanding what their
weaknesses are, and therefore gives you insight into how to bring
them up to snuff.
Good Answer: There really isn’t a good or bad answer, because any
answer will provide you with guidance on how to manage the person
and make them a better employee.
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
ii. project cost Cost processes include cost estimating to figure out the
needed financial commitment for all resources necessary to complete
the job. Cost budgeting creates a cost baseline. Cost control works to
manage the fluctuation of costs throughout the project. If time
management processes are performed perfectly, it will serve in the cost
plan and quality plan.
iii. project risk With time management, you become more organized
and the things you do become more habitual than panic-driven. By
making it a habit, you become more productive. You can use the same
framework as the work breakdown structure (WBS) for developing a risk
breakdown structure (RBS). A risk breakdown structure organizes
the risks that have been identified into categories using a table with
increasing levels of detail to the right.
b. Provide 1 example of either poor or excellent time
management for project resources, cost and risk.
For example, if you’re running behind schedule, you can work to reduce
the features of the project. That’s reducing scope. Then you can
dedicate more resources to moving the schedule ahead. That’s
increasing cost. You can also, if possible, change the due date to give
you more time. All these scenarios are applying the Triple Constraint for
managing the project.For a project manager, that means taking the time
to understand the Triple Constraint as it applies to the project and doing
your due diligence beforehand, so that if you must adjust, you’re doing
so from a place of knowledge.To ascertain good time management, the
defining & sequencing of activities, estimation of resources & durations,
schedule development procedure and the process of controlling
schedule must be performed painstakingly.
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
Schedule, budget and scope (also known as the project triple) are the
fundamental constraints set out at the beginning of a project and agreed
upon by all stakeholders. The business case to proceed with the project is
based on these elements. They set the expectation of what will be
delivered according to the resources allocated to the project. For this
reason, the project triple are represent important items to monitor, as they
are the major contributing factors to stakeholder satisfaction and to
meeting the business case.
13. Identify at least two tools and techniques for managing project time
and outline their particular applications in no more than 200 words
each.
Define the Activities: This step requires you to define the tasks,
milestones, and other activities needed to complete the project. Start with
a basic definition of each task and fill in the details as the project gets
fleshed out.
Sequence the Activities: Once the activities have been defined, you can
start putting the activities in order. Without worrying about dates, order
the activities in a way that makes the most sense to you. Create subtasks
as needed and organise the project in a logical manner.
14. Identify at least two techniques and in no more than 200 words each,
explain how they are used to measure, record and report the progress
of activities. You may use the internet to research your answer if
needed.
- The Units Completed lends itself well to tracking tasks that are done
repeatedly, where each iteration can easily be measured. Usually a
task that is done repeatedly tends to take about the same amount
of time, resources and effort, so tracking the units completed works
well here.
- The Cost Ratio method is usually implemented on a project that has
tasks that tend to occur over a long phase or the entire project.
Often used for Overhead costs, this technique is measured based on
the budgeted allocation of dollars vs. the labour hours of production.
This method gives the contractor the ability to earn value that is
equal to the overall percent of project completion.
15. For an actual project you are involved with or a fictitious one as
outlined to you by your assessor, create a project schedule showing
tasks, deliverable milestones, sequence, dependencies and time
estimates. Attach a copy of this schedule to your workbook.
Project schedule for a construction of a house
Duration: 1 year
Start:1st January 2019
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
Project schedule
443e8d6346a06bec490e8286e7865ae12a810f3e.doc
Assessment 2 BSBPMG410 Apply project time management
techniques
443e8d6346a06bec490e8286e7865ae12a810f3e.doc