Fred’s Shed - Work Breakdown Structure

Task Predecessor Time Resources (people and materials


Number/ Task Description relationship (Days) required to complete the task) Costs
ID (sequence)

1 Design development NA 2 Karen $ 1,000

Fred, Construction & Building


2 Source building materials 1 2 Materials Suppliers $ 300

3 Contract signature 2 1 Fred, Mr Jones $ 200

4 Development Application and 3 1 Fred, Development Application $ 1,500


Construction Certificate Submission and Construction Certificate

5 Development Application and 4 3 Local Council $ 100


Construction Certificate Approval

Mr Jones’s final selections for colour and


6 3 1 Fred, Mr Jones $ 100
style

7 Deposit by Mr Jones 5 1 Mr Jones $ -

8 Prepare the site for construction 7 2 Fred, Employees 1, 2, 3, and 4 $ 1,500

9 Perform underground cable service 8 2 Eddie (electrician) $ 1,000


checks

10 Contracting a surveyor to locate existing 8 1 Surveyor $ 750


boundaries

11 Locate temporary facilities 8 2 Suppliers $ 1,200

12 Site set out and the formwork built 8 1 Fred, Employees 1, 2, 3, and 4 $ 1,200

13 Site excavation 12 2 Excavation Company $ 2,000

14 Book a council inspection 13 1 Fred, Council Inspection Company $ 500

15 Level the ground 14 1 Fred, Employees 1, 2, 3, and 4 $ 1,500


16 Book the concrete truck 15 1 Fred $ 400

17 Concreting 16 1 Fred, Employees 1, 2, 3, and 4 $ 1,500

18 Strip the formwork 17 1 Fred, Employees 1, 2, 3, and 4 $ 1,200

19 Invoice Mr Jones 18 1 Fred $ 100

20 Delivery and installation of the shed 19 2 Fred, Employees 1, 2, 3, and 4 $ 7,500

21 Connection of main powers 20 2 Eddie (electrician) $ 2,500

22 Connection of water and installation of 20 2 Bob (plumber) $ 2,500


the toilet

23 Installation of the windows 20 2 Gary (glazier) $ 1,500

Clear of the site (removal of any rubbish


24 20 2 Fred, Employees 1, 2, 3, and 4 $ 1,000
and the temporary site amenities)

25 Final touches 24 1 Fred, Employees 1, 2, 3, and 4 $ 750

Meet with Mr Jones to present him the


26 final bill and hand over the keys to the 25 1 Fred, Mr Jones $ -
shed

$ 31,800