St.

Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique

REBAR WORKS for COLUMN


(Phase 1) – 2nd Floor

weight of longitudinal bars = N x 14.80


weight of stirrups = N x 3.70
total length
weight of #16 G.I. tie wire =
53
No. #16 G.I. Tie wire = (members in longitudinal bars) × (stirrups)

Number
Number Lengt No. of 6m
of Total length
A. MATERIALS of Units h length Weight
Member (L = u x m x l)
(u) (l) (L ÷ 6)
s (m)
COLUMN 1
20mm longitudinal 53.3 say
8m 5m 320m 799.2 kg
bar 54 pcs.
8 75.2 say
10mm stirrups 47 pcs. 1.20m 451.20m 281.2 kg
76 pcs.
#16 G.I. Tie Wire 376 ties 0.30m 902.4m 17.03 kg
COLUMN 2
20mm longitudinal 33.3 say
10m 5m 200m 488.4 kg
bar 34 pcs.
4 37.6 say
10mm stirrups 47 pcs. 1.20m 225.6m 140.6 kg
38 pcs.
#16 G.I. Tie Wire 470 ties 0.30m 564m 10.64 kg
COLUMN 3
20mm longitudinal
12m 5m 120m 20 pcs. 488.4 kg
bar
2 25.07 say
10mm stirrups 47 pcs. 1.60m 150.4m 140.6 kg
26 pcs.
#16 G.I. Tie Wire 564 ties 0.30m 338.4m 6.38 kg

TOTAL 248 bars 3012.1 kg

254
St. Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique

B. LABOR Data Unit


MH
Average Productivity Rate: 0.70
kg
Skilled Workers (Steel Men) & Laborers 20 person
105.42 hours
DURATION
14 days

Ave . Productivity Rate ×total weight 0.70 (3012.1)


= =105.42 hrs
Laborers 20

1 working day
105.42 hrs × =13.18 say 14 days
8 hrs

FORMWORKS AND SCAFFOLDING for COLUMN


(Phase 1) 2nd Floor

1
A. PLYWOOD FORM " x 4' x 8' Ordinary Plywood
4
No. of Height of No. of Plywood
shorter longer
Column Column P = 2(a + b) + .20 A=uxPxH
s (u) (H)
side (a) side (b) ( A ÷ 2.88)

12 0.30m 0.30m 1.40m 84 m2 29.2 say 30 pcs.


5.0m
2 0.40m 0.40m 1.80m 18 m2 6.25 say 7 pcs.

TOTAL 102 m2 37 pcs.

B. WOOD FRAME 2" x 2" x 12’ Wood Frame


2× 2× 12 No. of Wood
No. of Plywood Multiplier Total bd. ft.
12 Frame
274.45 say
37 pcs. 29.67 1097.79 4
275 pcs.

255
St. Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique

C. SCAFFOLDINGS
Using 2” x 3” VERTICAL SUPPORT

(Total length = No. of columns × Height)


2× 3× 12
Total length Multiplier TOTAL bd. ft. No. of Woods
12
70 7 490 6 81.67 say 82 pcs.

Using 2” x 3” HORIZONTAL SUPPORT


2× 3× 12
Total length Multiplier TOTAL bd. ft. No. of Woods
12
70 31.67 2216.90 6 369.48 say 370 pcs.

Using 2” x 3” DIAGONAL BRACES


2× 3× 12
Total length Multiplier TOTAL bd. ft. No. of Woods
12
70 17.5 1225 6 204.17 say 205 pcs.

For 3 (10d) Nails = {d} over {6} × {total bd. ft.} over {100} = {10} over {6} × {5029.69} over {100
1 kg
83.83 lbs× =38.10 say 39 kg
2.20 lb

D. LABOR Data Unit


Total Area = A1 + A2 102 m2
MH
Average Productivity Rate 2.35
m2
Laborer 2 persons
Carpenter 3 persons
47.94 hours
DURATION
6 days

Ave . Productivity Rate ×total area 2.35 (102)


= =47.94 hrs
Laborers+Carpenters 5

256
St. Anthony’s College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique

1 working day
47.94 hrs × =5.99 say 6 days
8 hrs
CONCRETE WORKS for COLUMN
(Phase 1) – 2nd Floor

Number
Height Width Length Volume
of Units
(h) (w) (l) (V = u × h × w × l)
(u)
COLUMN 1 8 0.30m 0.30m 3.60m3
COLUMN 2 4 5.0m 0.30m 0.30m 1.80m3
COLUMN 3 2 0.40m 0.40m 1.60m3
TOTAL VOLUME 7.00 m3

A. MATERIALS Volume: 7.00 m3


Concrete Proportion
Quantity
Multiplier (Class A)
Portland Cement 9.5 V x 9.5 = 66.5 67 bags
Wash Sand 0.6 V x 0.6 = 4.2 5 m3
Gravel 0.9 V x 0.9 = 6.3 7 m3

B. LABOR Data Unit


MH
Average Productivity Rate: (1 Mixing Machine) 1.80 3
m
Laborers 10 person
1.26 hour
DURATION
1 day day

Ave . Productivity Rate × volume 1.80(7.00)


= =1.26 hrs
Laborers 10

1 working day
1.26 hrs × =0.158 say 1 day
8 hrs

257