DIMENSI
B
h5
Dimensi
h6
h1
h2 H = 230.00 cm
A = 25.00 cm
B = 80.00 cm
C = 70.00 cm
A h1 = 13.00 cm
H
h2 = 12.00 cm
h3 = 25.00 cm
h3 h4 = 25.00 cm
h5 = 8.00 cm
h4 h6 = 7.00 cm
C
BENTANG GIRDER
Lbr = 50 m
L = 50.8 m
Segmental/Monolith ? segmental
Composite / Non Composite Komposit
Panjang Girder L br = 50.8 m
Span Netto Clear Span Ln = 50.0 m
jarak antar girder s = 2 m
Tebal diaphragm = 20 cm
Jumlah segmen = 7
Jumlah Diaphragm = 6
MATERIALS
11/1/2017 Input 1 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
Concrete Grade
I Girder cube strength, f cu = 700 Kg/cm2
Slab cube strength, f cu = 350 Kg/cm2
Steel Grade
d< 13 mm, BJTP 24 fy = 2400 Kg/cm2
d >= 13 mm, BJTD 40 fy = 4000 Kg/cm2
Modulus of elasticity, Es = 2100000 Kg/cm2
Prestressing steel
Uncoated stress-relieved seven wire strand. Grade-270 - ASTM A416. Low-Relaxation.
Nominal diameter = 15.2 mm.
Nominal area = 138.7 mm2.
Modulus of elastisity E ps = 1970000.0 Kg/cm2
Breaking Load = 26.5 ton. 26.57492355
TEGANGAN IJIN
At transfer condition
at stressing : 100.00 % f c '. = 624.7 Kg/cm2 291.3 Kg/cm2
Compressive 0.60 f ci ' = 374.8 Kg/cm2 174.8 Kg/cm2
Tensile stress : -0.80 SQRT (f ci ' ) = -20.0 Kg/cm2 -13.7 Kg/cm2
At service condition
at service fc' = 624.7 Kg/cm2 291.3 Kg/cm2
Compressive 0.45 fc' = 281.1 Kg/cm2 131.1 Kg/cm2
Tensile stress : -1.60 SQRT ( f c ' ) = -40.0 Kg/cm2 -27.3 Kg/cm2
nc = 4.50 ( Ratio of E ps / E c )
n pi = 6.60 ( Ratio of E ps / E ci )
n = 0.68 ( Ratio of E slab / Ec )
CONCRETE PARAMETER
Precast I Komposit
b ef : 141.42 cm
h : 230.00 cm 255.00 cm
11/1/2017 Input 2 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
11/1/2017 Input 3 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
ARRANGEMENT KABEL
No tendon Dist( TtoT) space Y Dia space X END DUCT VSL n Strand
Edge Mid Sc5 - Edge Mid Dia ( "G") DEGREES 12.7 Dia("G")
Tendon 1 0.00 0.00 0.00 0.00 0.00 0.00 Sc5-3 39
Tendon 2 40.00 190.00 40.00 14.00 0.00 9.00 0.063 Sc5-7 51
Tendon 3 40.00 150.00 26.00 14.00 0.00 0.00 0.084 Sc5-12 63
Tendon 4 40.00 110.00 12.00 18.00 0.00 0.00 0.084 Sc5-19 84
Tendon 5 40.00 70.00 12.00 19.00 0.00 -15.00 0.084 Sc5-22 90
Tendon 6 30.00 30.00 12.00 19.00 0.00 15.00 0.084 Sc5-27 96
102.86 19.00 84.00 Installed = 70.00 Strand Sc5-31 105
2
PERSAMAAN X TENDON
A B C Cable length
Tendon 1 0.19 -9.76 150.00 5084.04 cm
2
Tendon 2 0.15 -7.72 110.00 5082.52 cm Y= Ax + Bx+ C
Tendon 3 0.09 -4.57 70.00 5080.88 cm
Tendon 4 0.03 -1.42 30.00 5080.09 cm
LAYOUT KABEL
Tendon 1 150.00 148.54 95.75 57.00 33.75 26.00 33.75 57.00 95.20 148.54 150.00
Tendon 2 110.00 108.85 67.13 36.50 18.13 12.00 18.13 36.50 66.69 108.85 110.00
Tendon 3 70.00 69.32 44.63 26.50 15.63 12.00 15.63 26.50 44.37 69.32 70.00
Tendon 4 30.00 29.79 22.13 16.50 13.13 12.00 13.13 16.50 22.05 29.79 30.00
x 0.00 0.15 6.35 12.70 19.05 25.40 31.75 38.10 44.38 50.65 50.80
Tendon Layout
Tendon 1
225.0
200.0
175.0
From Bottom of Girder
150.0 Tendon 2
125.0
100.0
y (cm)
75.0
50.0 Tendon 3
25.0
0.0
0.00 5.00 10.00 15.00 20.00 25.00 30.00 35.00 40.00 45.00 50.00
Tendon 4
L (cm)
PEMBEBANAN
Beban Mati
a Beban Sendiri I Girder
q sw = Ac x gc = 2.19 ton/m.
M sw = (qbs x L^2)/8 = 684.02 ton-m. at x= 350.49 ton-m.
b Beban Slab
tebal, t = 0.25 m.
q ts = s.t.gc = 1.25 ton/m.
M ts = (qtsxL^2)/8 = 390.63 ton-m. at x= 200.16 ton-m.
c. Rc Plate
tebal t = 0.07 m.
q ds = s.t.gc = 0.24 ton/m.
M ds = (qdsxL^2)/8 = 74.38 ton-m. at x= 38.11 ton-m.
d. Diafragm
Pd = 1.55 ton const.for formula = 0.75
Md = 58.28 ton m at x= 29.86 Ton m inner diaf. = 6.00
qd = 0.19 ton/m.
e Trotoar + Railing
qt = (total) = 0.00 ton/m.
Mt = (qt x L^2)/8 = 0.00 ton-m. at x= 0.00 ton-m.
Asphalt
Tebal t = 0.10 m.
g as = 2.20 Ton/m3.
q as = s x t x gas = 0.440 ton/m.
M as = (qas x L^2)/8 = 137.50 ton-m. at x= 70.45 ton-m.
Live load
11/1/2017 Loads 5 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
ANALYSIS
Prestressing force
Cg s
ep
Cg c
e
Bottom fiber:
s b = P i /A c + P i .e/W b - M sw /W b <= 374.83 ____> Pi <= 1690.73 ton. ..... (2)
From (1) dan (2) obtained Pi <= 1690.73 ton. ..... (3)
Bottom fiber:
s b = Pe/Acp + (P e .e-M sw )/W bp - (M LL +M SDL )/W bc => -39.99 ____> Pe => 1,063.46 ton. ..... (5)
From (4) and (5) obtained Pe => 1063.46 ton. ..... (6)
11/1/2017 Loads 6 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
Cara penarikan
Pi /Pe = 1.59 > 1.20 single stage.
11/1/2017 Loads 7 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
PRESTRESS LOSSES
(middle of span)
L2 = 25.400 m.
alpha = 0.073 rad.
P2 = 1567.148 ton.
(beamTitik-
end)
L3 = 50.800 m. L3
alpha = 0.146 rad. alpha
P3 = 1516.569 ton. P3
Draw-in
11/1/2017 Losses 8 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
Shrinkage
dT sh = E p .E b .k e .k h .k p
Theoritical thickness of beam = 330 mm.
From Australian Standard 1481-1978 determined;
Ep = 1.97E+06 Kg/cm2.
Eb = 4.00E-04 for humidity = 70.0 %.
ke = 0.649
kh = 0.920 for stressing after = 14.0 days
kp = 100/(100+20.r) where r = percentage of rebar.
rebar chosen, diameter 3 = 13 mm.
number = 22 nos
hence, r = 0.33 %.
kp = 0.937
dT sh = 440.8 Kg/cm2.
Creep
dTc = k c .k d .k e .k h .E p .T ci /E c
where;
kc = 1.10 for humidity = 70.0 %.
kd = 1.2 for stressing after = 14.0 days
ke = 0.649
kh = 0.919506509
Ep = 1.97E+06 Kg/cm2.
Ec = 4.37E+05 Kg/cm2.
T ci = 237.5 Kg/cm2.
dT c = 842.5 Kg/cm2.
Relaxation of strand
dT r = Fr.R.Tpi.(1-2.(dTsh+dTc)/Tpi)
Pi = 1501.120861 ton.
67.4 % UTS --> Fr = 1.8718
dT r = 482.8 Kg/cm2.
11/1/2017 Losses 9 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
P3 = 1452.474 ton.
P1 = 1243.084 ton.
P2 = 1295.351 ton. P e required = 1063.458 ton.
P3 = 1246.704 ton.
At service condition;
Slab top fiber 82.11 Kg/cm2. 131.07 Kg/cm2. OK !
Beam top fiber 211.81 Kg/cm2. 281.12 Kg/cm2. OK !
Bottom fiber 30.69 Kg/cm2. 0.00 Kg/cm2. OK !
AT SUPPORT
At service condition;
Top fiber 131.76 Kg/cm2. 281.12 Kg/cm2. OK !
Bottom fiber 131.76 Kg/cm2. 0.00 Kg/cm2. OK !
11/1/2017 Losses 10 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
fp = 19000.00 Kg/cm2.
f e min = 10669.52 Kg/cm2.
0.5*f p = 9500.00 Kg/cm2.
fe min > 0.5*fp OK!
s pu = f p *(1-k 1 *k 2 /j)
k1 = 0.4
k2 = 1/(bef*dp*fc')*{Apt*fp + (Ast - Asc)/fsy} = 0.22
C = T T = j * k ud * b ef * f c '
a = j * k ud = 48.15 cm.
a, max = 25.00 cm.
Muk > Mu and Muk > 1.2*Mcr ===> OK !!! Rebar not considered yet
SHEAR CALCULATIONS
bv = 16.10 cm.
0.8h = 184.00 cm.
bw = 25.00 cm
Shear Moment
(ton) (ton-m)
- Due to selfweight of beam 50.43 125.114
- Due to selfweight of slab 28.80 71.449
- Due to SDL 16.40 44.255
- Due to live load :
- Load P : 6.86 16.190
- Load p : 33.18 82.309
Vc = 0.2 * fc' * bv * d + Pv
11/1/2017 Losses 11 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
b1 = 1.10
b2 = 1.00
b3 = 1.00
A st = 0.00
s cp ,f = P e *e x /W b + P e /A c = 132.880 Kg/cm2.
M0 = Z * T cp,f = 868495.712 kg-m.
V 0 = M 0 /(M'/V') = 346525.887 kg.
Vc = 539240.595 kg.
Vc = Vt + Pv
Vt = 0.3*((fc')^0.5 + fpc)*bv *d = 207,017.29 kg.
Vc = Vt + Pv = 290,572.41 kg.
V c , min = 290,572.41 kg..
TRUCK LOAD = 5.00 Ton 11.25 Ton 11.25 Ton = 27.50 Ton
DLA = 0.3
4.9 11.0 11.0 (ton).
50.0 m.
12.699 Ton 14.11 Ton
11/1/2017 Losses 12 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
RESUME
Prestress force:
Pi = 1501.12 ton, or 67.44 % UTS.
Pe = 1295.35 ton, or 58.19 % UTS.
P JF = 1669.50 ton, or 75.00 % UTS.
Elongation of strand due to stressing = 358.10 mm.
ROTATION AT SUPPORT
At service condition: 1DL+1LL+1PT
R= 0.008385 rad
11/1/2017 Losses 13 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
L Bentang = 50.800 m
Bentang bersih = 50.000 m
GARIS PENGARUH LINTANG PADA GELEGAR GARIS PENGARUH MOMEN PADA GELEGAR
No. Potongan Vgdl Vqdl Vqll Vpll Vu Mgdl Mqdl Mqll Mpll Mu
Ton Ton Ton Ton Ton Ton.m Ton.m Ton.m Ton.m Ton.m
1 -0.40 0.00 0.00 0.00 0.00 0.00
2 0.00 54.72 52.86 36.00 13.72 247.59 0.00 0.00 0.00 0.00 0.00
3 2.50 49.25 47.58 32.40 13.03 224.31 129.96 125.55 85.50 32.59 588.02
4 5.00 43.78 42.29 28.80 12.35 201.04 246.25 237.88 162.00 61.74 1114.14
5 7.50 38.31 37.00 25.20 11.66 177.77 348.85 337.00 229.50 87.47 1578.36
6 10.00 32.83 31.72 21.60 10.98 154.50 437.78 422.90 288.00 109.76 1980.69
7 12.50 27.36 26.43 18.00 10.29 131.22 513.02 495.58 337.50 128.63 2321.12
8 15.00 21.89 21.14 14.40 9.60 107.95 574.58 555.05 378.00 144.06 2599.65
9 17.50 16.42 15.86 10.80 8.92 84.68 622.46 601.31 409.50 156.07 2816.29
10 20.00 10.94 10.57 7.20 8.23 61.41 656.66 634.34 432.00 164.64 2971.03
11 22.50 5.47 5.29 3.60 7.55 38.14 677.18 654.17 445.50 169.79 3063.87
12 25.00 0.00 0.00 0.00 6.86 14.86 684.02 660.78 450.00 171.50 3094.82
11/1/2017 Reinforcement 14 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
No Uraian Pot 1 Pot 2 Pot 3 Pot 4 Pot 5 Pot 6 Pot 7 Pot 8 Pot 9 Pot 10 Pot 11 Pot 12
1 Vu 0 247,586 224,313 201,041 177,769 154,497 131,225 107,952 84,680 61,408 38,136 14,863
2 Mu 0 0 588,016 1,114,136 1,578,359 1,980,686 2,321,116 2,599,650 2,816,287 2,971,028 3,063,873 3,094,821
3 dp 1.84 1.84 1.84 1.84 1.84 1.84 1.84 1.84 1.84 1.84 1.84 1.84
4 Vu*dp/Mu 1.0000 1.0000 0.7019 0.3320 0.2072 0.1435 0.1040 0.0764 0.0553 0.0380 0.0229 0.0088
5 vc 53.00 53.00 38.39 20.27 14.15 11.03 9.10 7.74 6.71 5.86 5.12 4.43
6 vc ambil 32.49 32.49 32.49 20.27 14.15 13.25 13.25 13.25 13.25 13.25 13.25 13.25
7 vu 0.00 63.32 57.37 51.42 45.47 39.51 33.56 27.61 21.66 15.71 9.75 3.80
8 vu - vc(ambil ) (32.49) 30.83 24.88 31.15 31.31 26.27 20.31 14.36 8.41 2.46 (3.49) (9.45)
9 Jarak s (13.07) 13.78 17.07 13.64 13.57 16.17 20.91 29.57 50.50 172.77 (121.58) (44.97)
10 s max 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52 1,567.52
11 s max 120.82 120.82 120.82 120.82 120.82 120.82 120.82 120.82 120.82 120.82 120.82 120.82
12 dihitung jarak (13.07) 13.78 17.07 13.64 13.57 16.17 20.91 29.57 50.50 120.82 (121.58) (44.97)
13 Dipakai jarak 10.00 10.00 10.00 15.00 15.00 15.00 20.00 25.00 25.00 25.00 25.00 25.00
Jarak Pot.( m ) -0.400 0.000 2.500 5.000 7.500 10.000 12.500 15.000 17.500 20.000 22.500 25.000
11/1/2017 Reinforcement 15 - 16
PCI h230 length 50.8 ctc 200-0-6.xlsx
TULANGAN LONGITUDINAL
Batasan yang dipakai untuk menentukan tulangan longitudinal adalah sbb :
Dimensi ' Brusting Steel ' yang dipakai : BJTD 4,000.0 Kg/cm2
As = ( F / (0.87*fy) ) = 102.03 cm2
11/1/2017 Reinforcement 16 - 16