Professional Documents
Culture Documents
QUANTITY IN NOS.
S.
(Approx. Drawing/
NO.
ITEMS Documents)
1 Track Slab Manufacturing Factory: Temporary Structures as per site GTI
& Hydrology
1.01 GAD, structure foundation, its arrangement, RC detail, roof sheeting plan, roof 30
framing plan, etc. for Factory shed, storage shed
1.02 Foundations, architecture, flooring, RC detail and detailed structure
arrangement for setting up of offices for Engineer's/ Employer's, L&T's, QA/ QC,
Material Testing Lab, Medical room, Staff Mess, weigh bridge, firefighting room, 62
boiler room, compressor room, maintenance workshop, labour shed, time office,
tyre washing facility, security hut, etc.
1.03 Floor plan for factory and storage area including design and arrangement of 6
trenches, steam curing pipe network, compressor network, etc.
1.04 Foundations, pedestal, RC detail and structure arrangement for mould 18
stands, inspection tables, etc.
1.05 Foundations, RC detail and structure arrangement for setting up of EOTs, 21
Flying Bucket, Gantry, Concrete Distributor, Auxiliary Track including fastenings,
etc.
1.13 Plumbing layout, Water Supply plan for entire Track Slab Manufacturing Factory 10 plumbing layout with calculation of pump selection and friction
including wastewater management plan (if required). loss and bend loss calculation
2 Track Construction Bases: Temporary Structures as per site GTI &
Hydrology
ANNEXURE‐A
QUANTITY IN NOS.
S.
(Approx. Drawing/
NO.
ITEMS Documents)
3 Foundations, RC detail and structure arrangement for Client Office, Site 30 1.Foundation desing along with its reactions from staad or etabs
Office setup along the project file along with DBR
2.RCC staad file is requested
Total: 500