May 2022

Ref. Monthly Report-52022


Note: Feedback Form Signed By Owner

MONTHLY REPORT OF TRA VINH V1-2 WIND FARM


Feedback Form Signed By Owner
Wind Farm Monthly Availability of May 2022
o Date: 01/06/2022
Prepared Le Nhat Minh Reviewed Pham Quang Son
Wind Farm Tra Vinh V1-2 The Type of Operation Turbine/Quantity 155-4.5MW/12
Hou Donghai +84826161275
Responsible Person of Goldwind Contact Number
Tian Xiaohui +84349209516
Teetouch Suebsang +66882939510
Responsible Person of Wind Farm for Maintenance Contact Number
Pham Van Chung +84973616842

o Background
The Tra Vinh project is in the southwestern part of Vietnam, in the coastal alluvial area of Changlong Commune, a coastal town in Tra Vinh Province. It is an intertidal and offshore project. The project
is in the coastal monsoon tropical climate zone, with a tropical monsoon climate. The annual average temperature is about 26.3℃, the lowest temperature is 24.9℃, the highest temperature is
34.6℃, and the annual average humidity is about 89.46%. It is divided into two different seasons: the rainy season is from May to November, and the dry season is from December to April next year.

o Site Specification
Device name Type Device name Type
Main control system GW MCS05-CTR01 Converter system GW PCS05A-CVT01
Nacelle control system GW MCS05-NAC01 Pitch system GW PS05B-PIH02
Transformer HAINAN JINPAN SCLB11-5000/35 RMU Ormazabal CGM.3

o Report Period (Got the data from the SCADA: 00:00 01st May, 2022--- 24:00 31st May , 2022)
Amendatory Availability
Wind Farm Avg Wind Speed (m/s) Monthly Gross Production (kWh) Production Time (h) Availability (%)
(%)

Avg-Value 5.85 867,581.25 678.06 99.85 99.84

Aggregate-Value - 10,410,975.00 8,136.70 - -

o Comments(if the availability adjusted)

Downtime Availability Adjusted


WTG No. Date Description Stop Time Start time Reason
(h) (%) Availability (%)

o Opinion of owner

On behalf of Goldwind International Vietnam Co., Ltd On behalf of Tra Vinh V1-2 Wind Power Plant

By: By:

Signature: Signature:

Date: Date:
1. Operation Data of Report Period (Data from the SCADA: 00:00 01st May, 2022--- 24:00 31st May , 2022)

Ave Ave Total


Electricity Total Total Total Accumulative System Regular Manual Adjusted
Ave Wind Production Output Accumulative Annual Production Monthly Production Production Turbine Availability
WTG No. Consumption Downtime Inspection Retrofit Production OK Time Maintenance Stop Hours Availability
Speed (m/s) Wind Speed Power Production (kWh) (kWh) (kWh) Time (h) Fault (%)
(kWh) (h) Time (h) Time (h) Time (h) (h) (h) (h) (%)
(m/s) (kW) Time (h)

1 5.78 6.20 1,114.49 8,960,042 8,960,042 831,444 2,478.00 683.15 0.37 0.20 0.00 0.00 5,095.30 743.72 0.00 0.05 99.96 99.95

2 5.77 6.22 1,121.92 9,104,269 9,104,269 837,138 2,639.00 675.89 2.30 0.17 0.00 0.00 5,005.26 741.68 0.00 2.14 99.69 99.69

3 5.79 6.24 1,135.51 9,150,711 9,150,711 847,032 2,421.00 672.73 6.28 6.02 0.00 0.00 5,132.53 737.89 0.00 0.56 99.18 99.16

4 5.84 6.52 1,151.74 5,007,376 5,007,376 858,973 2,284.00 679.19 1.39 0.00 0.00 0.00 2,892.49 742.61 0.00 1.40 99.81 99.81

5 5.80 6.26 1,154.29 9,163,980 9,163,980 861,156 2,572.00 676.92 0.27 0.00 0.00 0.00 5,048.84 743.82 0.00 0.05 99.98 99.96

6 5.88 6.33 1,169.74 9,381,504 9,381,504 872,533 2,441.00 677.53 1.03 0.00 0.00 0.00 5,040.13 743.00 0.00 0.99 99.87 99.86

7 5.78 6.23 1,159.57 8,886,978 8,886,978 864,938 2,447.00 681.10 0.13 0.00 0.00 0.00 4,628.75 743.87 0.00 0.13 99.98 99.98

8 5.85 6.31 1,179.94 9,463,370 9,463,370 880,040 2,420.00 677.92 0.15 0.00 0.00 0.00 5,192.88 743.96 0.00 0.00 100.00 99.98

9 5.92 6.26 1,183.58 9,475,485 9,475,485 882,801 2,458.00 676.30 0.13 0.00 0.00 0.00 5,129.31 744.00 0.00 0.00 100.00 99.98

10 5.90 6.33 1,185.03 8,900,218 8,900,218 883,919 2,530.00 681.12 1.53 0.07 0.00 0.00 4,992.04 742.53 0.00 1.35 99.80 99.79

11 5.94 6.23 1,193.08 9,560,403 9,560,403 889,927 2,534.00 674.01 0.63 0.00 0.00 0.00 5,147.82 743.97 0.00 0.00 100.00 99.92

12 5.91 6.31 1,208.43 9,273,001 9,273,001 901,074 2,261.00 680.84 0.30 0.00 0.00 0.00 5,099.10 743.76 0.00 0.20 99.97 99.96

AVG /
5.85 6.29 1,163.11 106,327,337 106,327,337 10,410,975 29,485.00 8,136.70 14.51 6.46 0.00 0.00 67,319.26 8,921.68 0.00 6.87 99.85 99.84
SUM

Reasons for less than 97% Content


2. Power Curve (From 01st December, 2021 - 31st May, 2022)

Avg. Wind Avg. Active Power (kW)


Speed (m/s) Standard WTG01 WTG02 WTG03 WTG04 WTG05 WTG06 WTG07 WTG08 WTG09 WTG10 WTG11 WTG12
2.0 0.00 45.34
2.5 0.30 56.23 61.26 52.21 102.89 28.88 76.88 57.87 71.85 88.42 66.83 86.17 32.1
3.0 65.30 67.69 80.62 77.54 86.48 74.72 73.26 77.49 81.79 75.04 83.96 77.72 72.97
3.5 156.50 140.43 149.44 149.26 145.4 149.11 138.78 153.92 148.74 141.61 157.77 139.81 151.32
4.0 272.00 244.56 252.76 251.71 247.62 256.22 241.01 258.26 250.33 236.28 262.09 237.99 263.06
4.5 409.30 366.52 375.97 375.67 372.04 379.73 367.36 382.3 379.32 355.75 390 358.72 386.64
5.0 573.10 507.76 517.4 510.94 518.05 525.1 506.7 523.83 516.49 485.18 530.58 489.28 533.75
5.5 773.70 686.4 697.36 691.16 685.34 705.17 680.53 708.81 699.39 651.68 711.78 661.83 715.18
6.0 1012.70 911.62 926.78 913.4 898.92 931.35 893.37 937.42 911.47 858.78 928.24 871.98 936.39
6.5 1293.30 1171.81 1182.94 1160.57 1149.7 1198.56 1149.61 1199.4 1172.35 1108.6 1193.21 1123.09 1205.86
7.0 1619.30 1470.32 1485.29 1443.11 1407.46 1494.3 1438.87 1512.47 1461.78 1388.46 1494.06 1398.15 1501.4
7.5 1989.40 1814.37 1828.83 1767.63 1697.08 1849.9 1766.06 1854.17 1793.15 1696.08 1826.42 1728.15 1840.66
8.0 2401.00 2207.46 2223.81 2122.37 2013 2231.88 2139.2 2237.85 2165.46 2027.06 2203.79 2092.42 2222.44
8.5 2835.60 2597.24 2622.37 2499.11 2345.31 2626.03 2529.63 2632.23 2550 2399.98 2592.41 2487 2612.14
9.0 3280.20 3001.53 3031.67 2889.9 2710.46 3034.87 2926.08 3039.95 2947.37 2787.53 2986.27 2871.67 3014.14
9.5 3608.48 3391.51 3416.69 3289 3094.73 3428.09 3322.88 3425.21 3341.84 3180.89 3390.47 3269.76 3409.58
10.0 3866.79 3755.98 3775.34 3651.72 3441.35 3781.02 3685.77 3771.88 3712.24 3543.36 3755.02 3653.92 3771.11
10.5 3992.78 3966.17 3981.29 3915.6 3734.11 3986.76 3934.55 3979.59 3957.55 3857 3981.95 3933.52 3976.07
11.0 4000.00 4019.13 4030.18 4005.26 3941.03 4032.5 4027.77 4023.93 4024.22 3999.16 4037.13 4031.43 4018.52
11.5 4000.00 4024.75 4035.33 4018.34 4007.47 4035.75 4042.27 4027.44 4029.21 4024.63 4045.83 4044.2 4021.8
12.0 4000.00 4025.19 4035.2 4019.28 4020.6 4036.19 4042.53 4027.34 4029.15 4026.96 4046.12 4044.03 4022.01
12.5 4000.00 4025.15 4035.43 4018.88 4022.92 4036.54 4042.89 4027.21 4029.01 4026.56 4045.69 4044.29 4021.99
13.0 4000.00 4024.89 4035.81 4019.25 4022.85 4036.12 4042.98 4027.66 4029.46 4026.3 4046.05 4043.71 4022.59
13.5 4000.00 4025.61 4034.69 4019.86 4022.66 4037.31 4043.11 4027.74 4029.25 4026.44 4046.01 4044.63 4022.34
14.0 4000.00 4024.19 4035.57 4020.01 4023.09 4037.01 4043.13 4027.1 4029.28 4026.4 4046.48 4044.09 4022.74
14.5 4000.00 4024.28 4035.24 4019.87 4024.12 4036.63 4042.95 4025.82 4028.64 4026.26 4046.44 4044.04 4022.92
15.0 4000.00 4023.83 4033.86 4020.13 4024.57 4036.35 4043.05 4026.19 4028.43 4024.89 4046.83 4043.35 4023.14
15.5 4000.00 4023.74 4033.54 4019.49 4024.43 4036.14 4042.75 4024.75 4027.82 4024.69 4046.85 4042.85 4022.96
16.0 4000.00 4024.21 4033.81 4019.75 4023.64 4036.3 4042.45 4025.22 4026.98 4024.13 4046.92 4043.34 4023.02
16.5 4000.00 4024.23 4035.26 4019.5 4024.44 4036.41 4042.54 4026.6 4027.38 4024.56 4045.62 4043.12 4023.88
17.0 4000.00 4024 4035.73 4019.33 4023.41 4035.86 4042.02 4025.6 4028.5 4024.81 4046.51 4042.34 4022
17.5 4000.00 4025.86 4032 4020.23 4023.18 4036.78 4042.72 4026.38 4027.46 4024.2 4046.09 4043.41 4021.64
18.0 4000.00 4025.01 4035.75 4019.63 4024.72 4037.68 4042.46 4024.47 4026.85 4023.83 4045.35 4043.73 4023.66
18.5 4000.00 4029.47 4032.45 4019.76 4025.8 4037.22 4042.12 4028.9 4030.84 4026.13 4046.39 4043.1 4022.86
19.0 3987.00 4018.96 4023.42 4040.6 4035.65 4024.28 4046.45 4043.29 4022.28
19.5 3931.00 4026.58
3. Performance Summary
3.1. Adjusted Availability
3.1 Daily Availability
Adjusted Availability (%)
100.00
98.00
96.00
94.00
92.00
90.00
88.00
86.00
84.00
82.00
80.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Adjusted Availability (%) 100.00 99.92 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 97.21 99.93 100.00 98.41 99.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

3.2. WTG Performances


3.2 WTGs Power Generation Perfomance
1,200,000 WTGs performance 100.00

1,000,000 99.50

800,000 99.00

600,000 98.50

400,000 98.00

200,000 97.50

0 97.00
WTG01 WTG02 WTG03 WTG04 WTG05 WTG06 WTG07 WTG08 WTG09 WTG10 WTG11 WTG12
Adjusted Availability (%) 99.95 99.69 99.16 99.81 99.96 99.86 99.98 99.98 99.98 99.79 99.92 99.96
Monthly Production (kWh) 831,444 837,138 847,032 858,973 861,156 872,533 864,938 880,040 882,801 883,919 889,927 901,074

3.3. Monthly Average Wind speeds and Production


3.3 Daily Avg wind speeds and Production
Monthly Avg wind speeds and Production
1200000 12

1000000 10

800000 8

600000 6

400000 4

200000 2

0 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Production (kWh) 189932 52262 339222 279077 585354 707557 1069348 808841 571831 286795 37904 105570 212893 161634 251162 261188 41225 42691 57043 125117 229188 394096 521044 292466 465958 481471 448024 482279 414537 319899 175367
Avg Wind Speed (m/s) 5.21 3.27 5.71 5.67 7.78 8.39 11.4 8.88 7.57 6.04 3.39 4.03 5.13 4.81 5.28 5.47 3.08 2.65 3.23 4.39 5.24 6.43 7.05 5.92 6.91 7.08 6.65 7.1 6.59 5.84 5.06

3.4 Fault Analysis


No Fault description Downtimes (h) Remark

1 (32008)Heartbeat Signal Lost of 1#Pitch 5.38 The DP connector of the Topbox is damaged

2 (30109)Limit Exceeded of Deviation between Actual and Demand Position of 1#Pitch 0.64 The DP connector of the Topbox is damaged

3 (39030)Pitch(30)Pitch Web switch to pitch cotrol 0.20 Too many input control words due to network latency

4 (30733)Abnormal Condition of Bus on Lidar 0.17 Communication loss of Lidar


PCH Sensor cable shielding layer wiring loose inside of
5 (30762)Limit Exceeded of Nacelle Acceleration 0.07
Topbox.
Comment:

4. Operation and Maintenance Summary


4.1 Troubleshooting Record

NO. WTG Job title Date Stop time Start Time Downtime(h) Work content

1 1 Turbine Fault 12/05/2022 12/05/2022 19:21 12/05/2022 19:33 0.20 Remote reset
2 2 Turbine Fault 02/05/2022 02/05/2022 19:50 02/05/2022 20:00 0.17 Reset via Twincat
3 Turbine Fault 14/05/2022 14/05/2022 01:51 14/05/2022 02:13 0.36 Remote reset via TwinCAT
4 Turbine Fault 14/05/2022 14/05/2022 19:17 14/05/2022 19:46 0.48 Remote reset
5 3 Turbine Fault 14/05/2022 14/05/2022 19:48 14/05/2022 19:50 0.04 Remote reset
6 Turbine Fault 14/05/2022 14/05/2022 19:52 14/05/2022 20:27 0.60 Remote reset
Replace the DP connector from 1# pitch box to topbox - Local
7 Turbine Fault 14/05/2022 14/05/2022 20:53 15/05/2022 01:26 4.54
reset
8 10 Turbine Fault 02/05/2022 02/05/2022 04:52 02/05/2022 04:56 0.07 SCADA reset

4.2 Scheduled Maintenance


No. WTG Scheduled Maintenance Description Responsible Part Start time End time Downtime(h)

4.3 Predictive Maintenance


No. WTG Predictive Maintenance Description Responsible Part Start time End time Downtime(h)
4.4 Retrofit Record
No. WTG Retrofit Description Responsible Part Start time End time Downtime(h)

4.5. Software Updates

No. WTG Software Update Description Responsible Part Start time End time Downtime(h)

1 1 Program Updating Goldwind 11/05/2022 14:26 11/05/2022 14:36 0.17


2 2 Program Updating and Inspection Goldwind 11/05/2022 11:20 11/05/2022 13:28 2.13
3 3 Program Updating Goldwind 11/05/2022 14:03 11/05/2022 14:19 0.26
4 4 Program Updating and Inspection Goldwind 11/05/2022 15:04 11/05/2022 16:28 1.39
5 5 Program Updating Goldwind 11/05/2022 18:00 11/05/2022 18:16 0.27
6 6 Program Updating and Inspection Goldwind 11/05/2022 16:56 11/05/2022 17:58 1.03
7 7 Program Updating Goldwind 11/05/2022 18:32 11/05/2022 18:40 0.13
8 8 Program Updating Goldwind 11/05/2022 20:00 11/05/2022 20:09 0.15
9 9 Program Updating Goldwind 11/05/2022 20:13 11/05/2022 20:20 0.13
10 10 Program Updating and Inspection Goldwind 11/05/2022 19:06 11/05/2022 20:33 1.46
11 11 Program Updating Goldwind 11/05/2022 19:18 11/05/2022 19:56 0.63
12 12 Program Updating Goldwind 11/05/2022 20:48 11/05/2022 21:06 0.30

5. List of alarms and errors;


Down
No. WTG NO. Alarms or errors Start time Ending time Reason for alarm occur Brief description of handing Responsible person
time(h)

(10052)Turbine Stopped by M.C.C.


1 1 11/05/2022 14:26 11/05/2022 14:36 0.17 Push M.C.C Button on Turbine Program Updating Goldwind
Stop Button

(39030)Pitch(30)Pitch Web switch to


2 1 12/05/2022 19:21 12/05/2022 19:33 0.20 Pitch Web Switch to Pitch Control Remote reset Goldwind
pitch cotrol

DpState' of Lidar slave station is


(30733)Abnormal Condition of Bus on greater than 0 or lidar index
3 2 02/05/2022 19:50 02/05/2022 20:00 0.17 Reset via Twincat Goldwind
Lidar remains unchanged; After a 10s
delay, the fault will be triggered

(10052)Turbine Stopped by M.C.C.


4 2 11/05/2022 11:20 11/05/2022 13:28 2.13 Push M.C.C Button on Turbine Program Updating and Inspection Goldwind
Stop Button

(10052)Turbine Stopped by M.C.C.


5 3 11/05/2022 14:03 11/05/2022 14:19 0.26 Push M.C.C Button on Turbine Program Updating Goldwind
Stop Button

(32008)Heartbeat Signal Lost of 1#Pitch heartbeat signal remains


6 3 14/05/2022 01:51 14/05/2022 02:13 0.36 Remote reset via TwinCAT Goldwind
1#Pitch unchanged.

(32008)Heartbeat Signal Lost of 1#Pitch heartbeat signal remains


7 3 14/05/2022 19:17 14/05/2022 19:46 0.48 Remote reset Goldwind
1#Pitch unchanged.

In power production mode, the


(30109)Limit Exceeded of Deviation
difference between actual pitch
8 3 between Actual and Demand Position 14/05/2022 19:48 14/05/2022 19:50 0.04 Remote reset Goldwind
position and demand pitch
of 1#Pitch
position of 1#Pitch exceeds 2 deg

In power production mode, the


(30109)Limit Exceeded of Deviation
difference between actual pitch
9 3 between Actual and Demand Position 14/05/2022 19:52 14/05/2022 20:27 0.60 Remote reset Goldwind
position and demand pitch
of 1#Pitch
position of 1#Pitch exceeds 2 deg

(32008)Heartbeat Signal Lost of 1#Pitch heartbeat signal remains


10 3 14/05/2022 20:53 15/05/2022 00:00 3.11 Troubleshooting Goldwind
1#Pitch unchanged.

(32008)Heartbeat Signal Lost of 1#Pitch heartbeat signal remains Replace the DP connector from 1# pitch box
11 3 15/05/2022 00:00 15/05/2022 01:26 1.43 Goldwind
1#Pitch unchanged. to topbox - Local reset

(10052)Turbine Stopped by M.C.C.


12 4 11/05/2022 15:04 11/05/2022 16:28 1.39 Push M.C.C Button on Turbine Program Updating and Inspection Goldwind
Stop Button

13 5 (10058)Turbine Stopped by SCADA 11/05/2022 18:00 11/05/2022 18:16 0.27 Remote stop by GW Program Updating Goldwind

(10052)Turbine Stopped by M.C.C.


14 6 11/05/2022 16:56 11/05/2022 17:58 1.03 Push M.C.C Button on Turbine Program Updating and Inspection Goldwind
Stop Button

(10052)Turbine Stopped by M.C.C.


15 7 11/05/2022 18:32 11/05/2022 18:40 0.13 Push M.C.C Button on Turbine Program Updating Goldwind
Stop Button

16 8 (10058)Turbine Stopped by SCADA 11/05/2022 20:00 11/05/2022 20:09 0.15 Remote stop by GW Program Updating Goldwind

17 9 (10058)Turbine Stopped by SCADA 11/05/2022 20:13 11/05/2022 20:20 0.13 Remote stop by GW Program Updating Goldwind

The effective value of acceleration


(30762)Limit Exceeded of Nacelle
18 10 02/05/2022 04:52 02/05/2022 04:56 0.07 in yawing process is greater than or SCADA reset Goldwind
Acceleration
equal to 0.12g.

19 10 (10058)Turbine Stopped by SCADA 11/05/2022 19:06 11/05/2022 20:33 1.46 Remote stop by GW Program Updating and Inspection Goldwind

20 11 (10058)Turbine Stopped by SCADA 11/05/2022 19:18 11/05/2022 19:56 0.63 Remote stop by GW Program Updating Goldwind

21 12 (10058)Turbine Stopped by SCADA 11/05/2022 20:48 11/05/2022 21:06 0.30 Remote stop by GW Program Updating Goldwind
6. Reports
6.1. Service Report
No. WTG Service item Description Process Service time for next time Down time(h) Laborers needed

1 WTG01 Scheduled Maintenance 500 Hours Maintenance Completed Aug-2022 38.27 253.99

2 WTG02 Scheduled Maintenance 500 Hours Maintenance Completed Aug-2022 35.01 210.06

3 WTG03 Scheduled Maintenance 500 Hours Maintenance Completed Aug-2022 33.52 252.97

4 WTG04 Scheduled Maintenance 500 Hours Maintenance Completed Aug-2022 4.23 191.16

5 WTG05 Scheduled Maintenance 500 Hours Maintenance Completed Sep-2022 46.68 347.23

6 WTG06 Scheduled Maintenance 500 Hours Maintenance Completed Sep-2022 31.95 180.69

7 WTG07 Scheduled Maintenance 500 Hours Maintenance Completed Sep-2022 27.21 175.84

8 WTG08 Scheduled Maintenance 500 Hours Maintenance Completed Sep-2022 28.77 131.27

9 WTG09 Scheduled Maintenance 500 Hours Maintenance Completed Sep-2022 32.16 181.71

10 WTG10 Scheduled Maintenance 500 Hours Maintenance Completed Aug-2022 31.85 176.15

11 WTG11 Scheduled Maintenance 500 Hours Maintenance Completed Sep-2022 33.18 186.71

12 WTG12 Scheduled Maintenance 500 Hours Maintenance Completed Sep-2022 29.13 163.02

6.2. CMS alarm reports/Pending repair reports/ RCA & Other Reports
No. WTG NO. Report Name Report Description Date of Delivery Remarks

7. Parts Replacement List

No. Identification Name and Type Quantity Turbine No. Remark

The DP connector of the


1 WTG03 was Fault by Heartbeat Signal Lost of 1#Pitch 1 WTG03
Topbox is damaged

8. HSE Summary

Metrics 05/2022 2022


Recordable Injuries 0 0
First Aid Injuries 0 0
Hazards/Risks Reports 0 0
Training Completed (%) 100% 100%
Environmental Spills 0 0
Equipment/Auto Damage 0 0
Near Misses 0 0
Monthly HSE Inspections 1 5

9. Other relevant worthy mentioned information of this month and following month
Worthy mentioned work which carried out this month

1 Feedback on the technical requirements of the owner's wind power prediction system, and solution tracking
2 Submit Trouble Measure Report
3 Go to sea Troubleshooting
4 Improve the project FEMS system work order

5 Warehouse spare parts list sorting

6 Inventory warehouse tools list


7 Training Fire emergency drill
8 Tracking Power Curve Test Matters
Worthy mentioned work projected for the following month
1 Organise monthly meeting with owner
2 Inspection WTG
3 Feedback on the technical requirements of the owner's wind power prediction system, and solution tracking
4 Project regular work

10. Working Plan For Next Month


NO. Working Contents Schedule Remark
1 Organise monthly meeting with owner 15 Jun 2022

2 Inspection WTG According to plan


3 Feedback on the technical requirements of the owner's wind power prediction system, and solution tracking On tracking

4 Project regular work According to plan

5 Tracking Power Curve Test Matters According to plan


11.Turbine Monthly Availability (%)
2021 - 2022 Availability
WTG Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
01 99.95 100.00 100.00 100.00 99.78 99.74 99.95

02 100.00 100.00 100.00 99.33 99.36 99.23 99.69

03 99.96 99.97 100.00 100.00 99.36 99.58 99.16

04 N/A N/A N/A 99.28 99.32 99.98 99.81

05 100.00 100.00 98.50 100.00 99.57 99.96 99.96

06 99.97 99.98 99.63 99.98 99.98 99.98 99.86

07 99.53 100.00 100.00 99.87 100.00 99.64 99.98

08 100.00 100.00 100.00 99.97 99.29 99.17 99.98

09 100.00 99.98 100.00 99.98 99.62 99.98 99.98

10 99.99 99.98 100.00 100.00 99.63 99.61 99.79

11 100.00 100.00 100.00 99.96 99.43 99.97 99.92

12 100.00 99.65 100.00 99.97 98.54 100.00 99.96

MTD 99.95 99.96 99.83 99.86 99.49 99.74 99.84

YTD 99.95 99.96 99.91 99.90 99.81 99.80 99.81


Warranty 95.00 95.00 95.00 95.00 95.00 95.00 97.00 97.00 97.00 97.00 97.00 97.00 97.00

12.Turbine Monthly Production (kWh)


2021 - 2022 Production
WTG Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
01 810,339 1,441,170 1,767,503 1,987,735 1,205,349 916,502 831,444
02 829,146 1,481,360 1,812,554 2,016,843 1,212,328 914,900 837,138
03 852,085 1,448,845 1,857,877 2,015,669 1,209,229 919,974 847,032
04 N/A N/A N/A 2,016,188 1,205,948 926,267 858,973
05 841,545 1,555,941 1,699,758 2,057,294 1,232,126 916,160 861,156
06 884,698 1,554,257 1,889,423 2,052,258 1,192,475 935,860 872,533
07 382,439 1,556,411 1,899,078 2,049,591 1,206,766 927,755 864,938
08 895,200 1,568,642 1,912,168 2,054,152 1,219,342 933,826 880,040
09 894,770 1,573,763 1,910,810 2,053,259 1,215,592 944,490 882,801
10 904,946 1,598,759 1,901,629 1,417,042 1,243,617 950,306 883,919
11 902,803 1,599,153 1,925,757 2,065,033 1,220,088 957,642 889,927
12 904,539 1,322,134 1,928,777 2,057,076 1,233,350 926,051 901,074
MTD 9,102,510 16,700,435 20,505,334 23,842,140 14,596,210 11,169,733 10,410,975
YTD 9,102,510 25,802,945 46,308,279 70,150,419 84,746,629 95,916,362 106,327,337

On behalf of Goldwind International Vietnam Co., Ltd On behalf of Tra Vinh V1-2 Wind Power Plant

By: By:

Signature: Signature:

Date: Date: