Professional Documents
Culture Documents
Facility Power
UTILITY CONNECTION
The data center is designed for 38 MVA maximum demand, which requires a connection to the electrical utility high voltage (HV)
sub-transmission network. Responsibility for substation construction and the point of common coupling, POCC, may vary with the
region and negotiated rate structure. The location of the utility meter is shown on the high voltage side of the transformer but may
be located on the medium voltage side of the transformer. Substation construction, equipment procurement responsibilities and
meter location are determined during the interconnection application process.
KWh KWh
52 52
38MVA 38MVA
HV HV
138kV- 138kV-
MV MV
13.8kV 13.8kV
Facility Power
SECONDARY MEDIUM VOLTAGE DISTRIBUTION
To reduce initial investment and ensure a good scalability approach, each block is independent in terms of primary and secondary
MV distribution. However, a MV back up diesel generator power plant is shared across two blocks to reduce the total cost.
Automatic transfer between main power and backup generators is built into the design.
A total of 56 HVL/cb switchgear lineups make up the secondary set of medium voltage distribution for all blocks, with distribution
switchgear rated at 15 kV, 1200 A. 12 of the HVL/cb switchgear lineups feed Type 1 blocks (two per IT room and two per cooling
system), 20 feed Type 2 blocks (four per IT room and two per cooling system), and 24 feed Type 3 blocks (four per IT room and
four per cooling system), all in a 2N architecture where half of the units provide A-side power and the other half B-side power.
The diesel generator backup power is coupled to the MV network with a LV/MV step-up 2500 kVA Power Dry II VPI cast resin
transformer with a 5.75% short circuit impedance and HVL/cb switchgear lineup rated at 15 kV with a 1200 A rated busbar.
Seven and nine 2500 kVA, 480 V generators, correspondingly, provide N+1 LV power for each pair of block types 1 and 2, while
eleven 2500 kVA generators provide N+2 power for type 3 blocks. This choice of backup generator plant configuration provides
high reliability and safety, while minimizing cost. Fuel storage and piping can also be added to the design in accordance with
regional requirements and regulations.
Secondary MV Distribution
MV Primary Dist. MV Primary Dist.
SWG A SWG B
Two Blocks
N units DESIGN OPTIONS
G N=7 Blocks 1&2 G
2500kVA N=9 Blocks 3&4 2500kVA This reference design can be modified
480V LV N=11 Blocks 5&6 LV 480V
13.8kV MV MV 13.8kV as follows without a significant effect on
5.75%Z 5.75%Z
Genset SWG
the design’s performance attributes:
1200A, 13.8 kV
Name Value
FACILITY POWER MV DISTRIBUTION ATTRIBUTES Unit
Blocks 1, 2 Blocks 3, 4 Blocks 5, 6
Number of MV secondary distribution switchgear per block 6 10 12
MV secondary distribution bus amps 1200 1200 1200 A
MV secondary distribution bus voltage 13.8 [15 kV Class] 13.8 [15 kV Class] 13.8 [15 kV Class] kV
© 2015 Schneider Electric. All rights reserved.
Facility Power
LOW VOLTAGE DISTRIBUTION
Downstream from the MV secondary distribution, each block is comprised of three parts with MV/LV transformers which serve LV
switchboards. Two of these groups are dedicated to two IT rooms and the other group to the cooling system and auxiliaries that
serve the whole block.
A total of 56 Power Dry II transformers, ranging from 1250 to 2000 kVA, are used in this design to transform power from 15 kV to 415
V with 5.75% impedance for the IT rooms and from 15 kV to 480 V with 5.75% impedance for cooling and auxiliaries, in a close-
coupling installation. The same number of LV QED 6 LV switchboards makes up the LV distribution and is distributed as follows: for
each type 1 block there are four switchboards rated at 415V, 85 kA with a 4000 A bus for IT and two switchboards rated at 480V, 85
kA with a 4000 A bus for cooling; for type 2 blocks there are eight units rated at 415V, 85 kA with a 4000 A bus for IT and two more
at 480V, 85 kA with a 4000 A bus for cooling; and, finally, for each type 3 block there are eight switchboards rated at 415V, 85 kA
with 4000 A bus for IT, and four for cooling rated at 480V, 85 kA, with 4000 A bus.
On each IT power train the QED 6 switchboards feed 2N Symmetra PX arranged for an A and B-side distribution. Downstream from
the electrical rooms to the IT space there is a combination of LV switchgear and iBusway systems with built-in intelligence for 2N
power distribution. In the mean time, the QED 6 units that make up the cooling power train provide A- and B-side distribution to
chillers, pumps, lighting, monitoring, security and automation systems, etc., while providing fault protection to cooling units in the IT
and electrical rooms.
The facility power system is designed to also support integrated peripheral devices like fire panels, access control systems, and
environmental monitoring and control devices. Power meters in the electrical path monitor power quality and allow for predictive
maintenance & diagnostics of the system. These meters as well as digital [MV & LV relays] also integrate with StruxureWare Power
Monitoring Expert.
Every component in this Reference Design is built and tested to the applicable ANSI standards. Further design details and
schematics are available in the engineering package, which can be requested at the end of this document.
DESIGN OPTIONS
This reference design can be
modified as follows without a
significant effect on the design’s
performance attributes:
Location
Type
LV critical switchboard kA 85 85 85 85 85 85 kA
2N for IT coolers 2N for IT coolers 2N for IT coolers
and pumps and pumps and pumps
UPS redundancy 2N 2N 2N
N for UPS N for UPS N for UPS
coolers coolers coolers
Total UPS capacity per
3600 288 4200 288 5400 360 kW
block
UPS runtime @ rated load 5 5 5 5 5 5 minutes
Facility Power
POWER MONITORING
Facility Cooling
This facility cooling system is meant for climates in places like
Boston, with warm summers and cold, snowy winters, though it Cooling system for Type 1 Blocks (shown as example)
can be easily adapted to work in other climates. CHWR CHWS CHWS CHWR
IT & ER IT & ER IT & ER IT & ER
The facility cooling design is made up of six stand-alone cooling
systems sized specifically to serve each type of block. Every DAS DAS
VFD
VFD
VFD
VFD
VFD
VFD
chilled water system is comprised of a dual-path piping system ET ET
in the building and direct expansion (DX) units are provisioned for
the rooms containing the generator switchgear, MV switchgear
and UPS batteries.
DESIGN OPTIONS
This design is instrumented to work with StruxureWare Building This reference design can be modified as follows without a
Operation for cooling control and monitoring. Further design ` significant effect on the design’s performance attributes:
details such as dimensions, equipment placement, temperature
set points, pipe sizing, flow rates, and pressure drops are
Add StruxureWare Building Operation
available in the engineering package.
DESIGN OPTIONS
FACILITY COOLING ATTRIBUTES
Facility
Name
Cooling This reference design can be modified as follows without a
significant effect on the design’s performance
Value Unit attributes:
Total facility cooling capacity 27 MW
This facility cooling system is meant for climates in places
Blocks 1, 2 like Blocks 3, 4 Add StruxureWare Building Operation
Blocks 5, 6
Name
Boston orSub-system
Malmö, with warm summers and cold, snowy
Value
winters,
Unit
© 2015 Schneider Electric. All rights reserved.
cooling capacity 3375 4500 5625 kW
Total facility
though it can easilycooling capacity 66 MW
Inputbevoltage adapted to work in other climates.
480 480 480 V
The facilityHeat
cooling design
rejection is made up of six stand-alone
medium Each
Chilled water block Chilled water
cooling Chilled water
Sub-system
systems sized
Number coolingto
specifically
of chillers capacity
serve each type of block. 5 5500
Every 6 kW 7
chilled water system
Input voltage is comprised
Mechanical redundancy of a dual-path piping
N+1 system
400 N+1 V N+1
with N+1 redundant air-cooled
Heat rejection medium packaged chillers with freeChilled
cooling,water
Packaged air-cooled Packaged air-cooled Packaged air-cooled
accompanied Outdoor
by heat exchange
a primary-secondary pumping scheme, withchiller with free-cooling chiller with free-cooling
chiller with free-cooling
Number of chillers 6
variable speed secondary pumps, all in an N+1 configuration.
Coolant supply
Mechanical temperature
redundancy 15 N+1 15 15 °C
Also, a redundant piping system across all the IT and electrical
Coolant return temperature 20.6 20.6 20.6 °C
distribution rooms in the block provide an alternate path for chilled
Packaged chiller with free-
Outdoor heat
Economizer exchange
type Water-side cooling Water-side Water-side
water, in case of equipment failure.
Coolant
In this cooling supply
system temperature
design, economization is achieved with 15dry °C
coolers Coolant
integrated return
Document Number RD106DS
temperature
within each chiller, to save energy 20.6
during °C Revision 0
favorable outdoor
Storage conditions. In addition, thermal storage systems
tank size per sub-system 65.6 m3
are offeredRide-through
to provide continuous
time
cooling after a power outage5 or minutes
chiller restart. These tanks would be sized accordingly for the
ramp-up timeEconomizer type and building topology.
of the chillers Water-side
[Reference Design 106] 8
IT Space
Six IT blocks are built one by one to make up the IT space of this design.
DESIGN OPTIONS
One block includes two IT rooms with 196 NetShelter racks each, so all
This reference design can be modified
rooms have a similar footprint even though they have different IT
as follows without a significant effect on
capacities. In type 1 blocks, each IT room houses racks of 8kW each, in
type 2 blocks the rack density is 10kW, and in type 3 blocks the rack the design’s performance attributes:
density is 12kW. Altogether they provide 23.52 MW of IT capacity for the
Add environmental and security
whole site.
management
In this design, each IT room is powered by redundant (2N) iBusway Change rack options
systems. Every rack has the capacity to accept dual power feed, since Tall
each is configured with redundant (2N) metered rack-mount power Wide
distribution units (PDUs) to enable remote monitoring of the units for Deep
efficiency and capacity management. Change rack power distribution options
Basic
In all rooms, heat is removed by InRow RC-HT units in an in an N+2 Metered
redundant configuration for each pair of rows. Considerations can be Switched
made with respect to return air ducting systems and/or raised floors, to Add StruxureWare Data Center Expert
improve the coolers’ performance. Redundant valves and piping are also
added to ensure continuous cooling with high reliability.
The security of the room is maintained at multiple points. At the rack
level, access is controlled by a door lock and sensor. At the room level,
security cameras are utilized for monitoring.
IT SPACE ATTRIBUTES
this design which contains the electrical one line diagrams, piping diagrams, dimensioned
floor layouts, and equipment lists.