Explanation for detail Construction Plan on Monday 10 May 2021 as below:

1. Preparation works
1.1. Site Organization Chart
1.2. Location of site office, fabrication yards, camp yard (for Roleang Chrey Sub-project and Kandal
Stung-BATI Sub-project)

2. Roleang Chrey Sub-project


2.1. Roleang Chrey Head Work
2.1.1. Temporary works
2.1.1.1. Access layout plan
2.1.1.2. Fabrication Yard: location, size,
2.1.1.3. Coffer dam (down and upstream): duration? material from? How to build?
(filling and removal 2 times)
2.1.2. Main works
2.1.2.1. Main steel gate existing: removal and disposal
2.1.2.2. Main steel gate single and double leaf and accessory: importation, fabrication,
transportation and installation
2.1.2.3. Protection works: retaining wall, slope protection, riverbed protection
2.2. Intakes
2.2.1.Andong Sla Intake
2.2.1.1. Temporary work: access road, temporary coffer dam, water diversion
2.2.1.2. Demolition existing structure
2.2.1.3. Construction new structure: concrete structure, gate
2.2.2. Wat Krouch Intake
2.2.2.1. Temporary work: access road, temporary coffer dam, water diversion
2.2.2.2. Demolition existing structure
2.2.2.3. Construction new structure: concrete structure, gate
2.3. Main Canal
2.3.1.North Main Canal:
2.3.1.1. Earth wokrs
2.3.1.1.1. Excavation and filling: how deal with water in canal? Farmer need
water, when to when?
2.3.1.1.1.1. Normal: how many team (labor, equipment)?
2.3.1.1.1.2. In the pond (NMC near spillway St.9+500 ~St.10+300): how to work with
this condition need more detail explanation to prevent future settlement?
(show us some procedure by sketch dwg)
2.3.1.2. Concrete works
2.3.1.2.1. Relate structure 44nos
2.3.1.2.2. Pumping station 2 nos (phum thmey, thmat pong)
2.3.1.2.2.1. Temporary works
2.3.1.2.2.2. Concrete structure
2.3.1.2.2.3. Pumping and accessary: import, transportation, installation
2.3.2.South Main Canal:
2.3.2.1. Earth wokrs
2.3.2.1.1. Excavation and filling: how deal with water in canal? Farmer need
water, when to when?
2.3.2.1.1.1. Normal: how many team (labor, equipment)?
2.3.2.1.1.2. In the pond (NMC near spillway St.9+550 ~St.11+150): how to work with
this condition need more detail explanation to prevent future settlement?
(show us some procedure by sketch dwg)
2.3.2.2. Concrete works
2.3.2.2.1. Relate structure
2.3.2.2.2. Pumping station 2 nos (phum thmey, thmat pong)
2.3.2.2.2.1. Temporary works
2.3.2.2.2.2. Concrete structure
2.3.2.2.2.3. Pumping and accessary: import, transportation, installation
2.3.2.2.3. Crossing Drainage (St.7+398, St.8+672):
2.3.2.2.3.1. Temporary: diversion water?
2.3.2.2.3.2. Pipe installation
2.3.2.2.4. Box Culvert at NR.4
2.3.2.2.4.1.1. Temporary works: diversion road
2.3.2.2.4.1.2. Concrete Structure
2.3.2.2.4.2. Siphon with Spillway
2.3.2.2.4.2.1. Temporary work: water diversion, coffer dam?
2.3.2.2.4.2.2. Concrete structure: box culvert
3. Kandal Stung Bati
3.1. Earth works
3.1.1.Temporary work
3.1.2.Excavation and filling
3.2. Concrete Structure
3.2.1.Weir
3.2.2.Daungkor Spillway