VOLUME 1

FORM OF SUBCONTRACT AGREEMENT


Acid Cleaning, Supply of Mirror Target Device for Validation Blow,
Inspection and Cleaning of Non-Blown Piping Sections, Steam Blow of
Auxiliary Steam System

OROT RABIN POWER STATION


Combined Cycle Power Plant
Revision History
Rev. Revision Date Created by Checked by Approved by Brief Description

A 08.10.2020 J.-Y. Ott First Issue


A Description current Revision
First issue

Purchaser Contractor

General Electric Global Parts & Product GmbH, Switzerland


GE International Inc US
The Israel Electric Corporation Limited

Equipment Tag Numbers (KKS)

Replaces Customer Code Project Document Code


ORO-ME-CLEANING-FA
Responsible Dept. Created by Checked by Approved by Format
GE GAS C&C J. Ott DIN A4
Document Type Document Status

GE POWER - Released
Document Title Identification Number
Gas Power VOLUME 1 - FORM OF SUBCONTRACT ORO-ME-CLEANING-FA
Systems AGREEMENT Rev. Date Lang. Sheet
A 08.10.2020 en 1/4
GBM Gas Master Doc Temp (ZZZ)
© COPYRIGHT 2020 General Electric Company Confidential
All rights reserved. The information herein is Proprietary and Technically Exclusive content that is solely owned by General Electric Company and/or its
affiliates. Thus, it is being provided with the explicit expectation of restricted and privileged use. All recipients of this information shall be deemed to
have agreed not to make duplications, reproductions of any nature by any means, modifications, disclosures, or use any portion of this material; except
as is expressly authorized in writing by the General Electric Company, and/or its legitimate affiliates.
FORM OF SUBCONTRACT AGREEMENT

PO (………………………)

This Agreement made the day of 20xx

Between

General Electric International Inc (GEII), with a branch office in Israel.

(hereinafter called “the Contractor”) of the one part and

XXX

(hereinafter called “the Subcontractor”) of the other part

Whereas the Contractor is desirous that certain Works should be executed by the Subcontractor, Engineering,
Supply, and Execution of Acid Cleaning, Supply of Mirror Target Device for Validation Blow, Inspection and
Cleaning of Non-Blown Piping Sections, Steam Blow of Auxiliary Steam System, as further defined in the
technical documents and the remedying of any defects therein.

Now this Agreement witnessed as follows:

In this Agreement words and expressions shall have the same meanings as are respectively assigned to them
in the Conditions of Subcontract hereinafter referred to.

The following documents in the following order of precedence shall read and be construed as part of this
Subcontract and shall together constitute the Subcontract between the Contractor and the Subcontractor:

Volume 1: Form of Subcontract Agreement ORO-ME-CLEANING-FA Rev A


Volume 2: Subcontract Particulars ORO-ME-CLEANING-CP Rev A
Volume 3: General Conditions of Subcontract ORO-ME-CLEANING-GC Rev A
Volume 4A: Site Conditions of Subcontract ORO-ME-CLEANING-SC Rev A
Volume 4B: Environmental, Health and Safety (EHS) ORO-ME-CLEANING-EH Rev A
Volume 4C: Quality Assurance, Control and Documentation ORO-ME-CLEANING-QA Rev A
Volume 4D: Material Handling ORO-ME-CLEANING-MH Rev A
Volume 5: Technical Specifications and Work Scope ORO-ME-CLEANING-TS Rev A
Volume 6: Schedule of Rates and Prices ORO-ME-CLEANING-SP Rev A
Volume 7: Schedule of Dates ORO-ME-CLEANING-SD Rev A

GE POWER Identification Number: Rev. Date Lang. Sheet


ORO-ME-CLEANING-FA A 08.10.2020 en 2/4
Gas Power Systems
© COPYRIGHT 2020 General Electric Company Confidential
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.
The Subcontract as heretofore defined constitutes a full statement of the contractual rights and liabilities of the
Contractor and the Subcontractor in relation to the Works and no negotiations between them nor any document
agreed or signed by them prior to the date of this Agreement in relation to the Works shall hereafter be of any
contractual effect. The Contractor is not bound to any provisions, printed or otherwise made available to the
Contractor by the Subcontractor, at variance or in addition to the terms of this contractual agreement that may
appear on any Subcontractor’s acknowledgment or other document unless specially accepted by the Contractor
in writing.

In consideration of the payments to be made by the Contractor to the Subcontractor as hereinafter mentioned
the Subcontractor hereby covenants with the Contractor to execute and complete the Works and remedy any
defects therein in conformity in all respects with the provisions of the Subcontract.

For all the purposes of the Subcontract the Commencement Date shall be XXXX 20XX

The Contractor hereby covenants to pay the Subcontractor in consideration of the execution and completion of
the Works and the remedying of defects therein the Subcontract Price of;

000,000.00 (EUR)

or such other sum as may become payable under the provisions of the Subcontract at the times and in the
manner prescribed by the Subcontract.

GE POWER Identification Number: Rev. Date Lang. Sheet


ORO-ME-CLEANING-FA A 08.10.2020 en 3/4
Gas Power Systems
© COPYRIGHT 2020 General Electric Company Confidential
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.
IN WITNESS whereof the Parties hereto have caused this Agreement to be executed as a Deed the day and
year first before written.

Signed for and on behalf of the Contractor

…………………………………………… ……………………….. …………………


(Print Name) (Signature) (Date)

in the presence of:

…………………………………………… ……………………….. …………………


(Print Name of Witness) (Signature of Witness) (Date)

Signed for and on behalf of the Subcontractor

…………………………………………… ……………………….. …………………


(Print Name) (Signature) (Date)

in the presence of:

…………………………………………… ……………………….. …………………


(Print Name of Witness) (Signature of Witness) (Date)

GE POWER Identification Number: Rev. Date Lang. Sheet


ORO-ME-CLEANING-FA A 08.10.2020 en 4/4
Gas Power Systems
© COPYRIGHT 2020 General Electric Company Confidential
All rights reserved. The information herein is Proprietary and Technically Exclusive content of the General Electric Company and/or its legitimate affiliates.

You might also like