You are on page 1of 3

ACCREDITATION WORK PLAN

DATE ACTIVITIES EXPECTED OUTPUT REMARKS


- Review and Analysis of the Findings and -
February Recommendations in Area VIII: Physical Plant - Matrix of findings vis a vis level of
22-26,2021 and Facilities and Area IX: Laboratories from accomplishment
last visit.

- Preparation of Plans and Strategies on the - Matrix of Plans and Strategies on the
March 8-12,
Compliance Requirement for Area VIII: Physical Compliance of Findings for Area VI:
2021
Plant and Facilities, Area IX: Laboratories/ Extension and Community Involvement
Area III: Curriculum and Instruction.

- Preparation of List of Documents to be


March 29- gathered in response to findings #1 & 2 of Area - List of Documents needed with samples.
31, 2021 VIII: Physical Plant and Facilities/ findings 1 of
Area III: Curriculum and Instruction from the
last visit.

- Preparation of List of Documents to be


April 5-8, gathered in response to findings # 3 & 4 of
- List of Documents needed with samples.
2021 Area VIII: Physical Plant and finding # 1 of Area
IX: Laboratories/ findings 2 & 3 of Area III:
Curriculum and Instruction from the last visit.

- Preparation of List of Documents to be


April 12-16, gathered in response to findings # 5 & 6 of - List of Documents needed with samples.
2021 Area VIII: Physical Plant and finding # 2 of Area
IX: Laboratories/ Findings 4 of Area III:
Curriculum and Instruction from the last visit.
- Preparation of List of Documents to be
gathered in response to findings # 7 & 8 of
April 19-23,
Area VIII: Physical Plant/ findings 1 of Area III: - List of Documents needed with samples.
2021
Curriculum and Instruction from the last visit.
- Follow-up on other documents if necessary.
- Write-up with attachment of evidence
April 26-30, - Write-up of responses on the finding issued by
supporting the responses on the
2021 the external accreditor.
compliance of findings.

May 3-7, - Write-up of responses on the finding issued by - -Write-up with attachment of evidence
2021 the external accreditor. supporting the responses on the
compliance of findings.
- Write-up with attachment of evidence
May 10-14,
- Wrap-up the work done and submit it to the supporting the responses on the
2021
internal accreditor for checking. compliance of findings.

- Gathering of additional documents required by


May 17-21, - List of Documents needed with samples.
the internal accreditor.
2021 - Finalized documents.
- Incorporated the comments and suggestion of
the internal accreditors.

- Gathering of additional documents required by


Prepared by: Recommending Approval:

Faculty OIC-Chairperson

APPROVED:

Executive Dean

You might also like