BOQ for Retaining wall For Mustang

S.N. Description of works Unit Rate Quantity Amount Remarks


Site Clearance including cutting Shrubs 2
1 m 25.13 226.00 5,679.38
removing trees etc all complete
Earthwork excavation in foundation in soft and
2 hard soils including disposal upto 10m lead and m3 900.22 389.36 350,509.66
1.5m lift

Providing and filling earth material laying in 15


3 cm layer, spray water with compaction all m3 548.26 129.79 71,158.67
complete as per instruction of the site incharge

75mm thick PCC work in 1:3:6 including lead


4 m3 16,310.91 7.99 130,324.17
upto 30m
Stone Masonry work in 1:6 C/S mortar all
5 m3 13,161.84 415.17 5,464,401.11
complete
Gravel Packing Works including breaking,
6 carying and laying of gravel/stone inorder to m3 7,196.21 204.46 1,471,337.10
prevent seepage of soil
100 mm Dia. High Density Pipes covered by
7 Rm 136.73 297.90 40,731.87
Geotextile
20mm Thick Stone pointing work with 1:2 C/S
8 m2 439.76 510.60 224,541.46
all complete
Subtotal 7,758,683.42
2.5%
193,967.09
Contigency
Grand Total 7,952,650.51