G+1 Project Start 01-Feb-22

Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

Enterprise All Initiatives


A.A 1 G+1
A7190 Start Of Project 0 0 0% 01-Feb-22
A.A 1.1 SUB-STRUCTURE
A.A 1.1.1 EXCAVATION AND EARTH WORK
A1000 Site clearing and removing the top 1 1 0% 01-Feb-22 01-Feb-22 F.Forman
200 mm thick soil
A1030 Excavation for footing to a depth not 1 1 0% 02-Feb-22 02-Feb-22 F.Forman
exceeding 1500mm in ordinary soil

A1040 Ditto but exceeding 1500mm not 1 1 0% 03-Feb-22 03-Feb-22 F.Forman


exceeding 3000mm
A1080 Fill around footing and foundation 1 1 0% 18-Mar-22 18-Mar-22 DL.Daily Laborer
columns with imported selected
materials from out side well rolled
and compacted in
A1090 Fill under hard core with imported 1 1 0% 19-Mar-22 19-Mar-22 DL.Daily Laborer
selected materials from out side well
rolled and compacted in layers not
exceeding 2
A1050 Trench excavation in ordinary soil for 2 2 0% 04-Feb-22 05-Feb-22 C.Carpenter
masonry foundation to depth of
1500 mm from reduced level.
A1060 Soft rock excavation 2 2 0% 07-Feb-22 08-Feb-22 C.Carpenter
A1070 Hard rock excavation 2 2 0% 09-Feb-22 10-Feb-22 C.Carpenter
A1100 Remove surplus excavated materials 2 2 0% 25-Apr-22 26-Apr-22 TD.Truck Driver
and deposit to a distance 5Km.

A1110 250mm thick basaltic stone hardcore 21 21 0% 31-Mar-22 23-Apr-22 M.Mason


well rolled, consolidated and blinded
with crushed stone .

Subtotal 73 73 01-Feb-22 26-Apr-22

A.A 1.1.2 CONCRETE WORK


A.A 1.1.2.1 50mm lean concrete quality C-5, 150KG
A1170 a) Under footing 1 1 0% 15-Feb-22 15-Feb-22 C.Carpenter
A1180 b) Under Grade Beam & Stone 1 1 0% 23-Feb-22 23-Feb-22 C.Carpenter
Masonary

Subtotal 8 8 15-Feb-22 23-Feb-22

A.A 1.1.2.2 Reinforced concrete quality C-25


A7150 b) To Foundation column 1 1 0% 09-Mar-22 09-Mar-22 C.Carpenter
A7170 d) To 100mm thick ground floor slab 2 2 0% 04-May-22 05-May-22 C.Carpenter

A7180 a) Footing pad 2 2 0% 21-Feb-22 22-Feb-22 C.Carpenter


A7160 c) To grade beam and steps 3 3 0% 19-Mar-22 22-Mar-22 C.Carpenter

Page 1 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

Subtotal 64 64 21-Feb-22 05-May-22

A.A 1.1.2.3 Formwork


A1280 b) Foundation column 2 2 0% 07-Mar-22 08-Mar-22 C.Carpenter
A1270 a) Footing pad 3 3 0% 11-Feb-22 14-Feb-22 C.Carpenter
A1290 c) Grade beam & steps 7 7 0% 03-Mar-22 10-Mar-22 C.Carpenter

Subtotal 24 24 11-Feb-22 10-Mar-22

A.A 1.1.2.4 Reinforcement


A.A 1.1.2.4.1 In footin bar
A1320 Dia. 12 deformed bar 4 4 0% 16-Feb-22 19-Feb-22 DL.Daily Laborer

Subtotal 4 4 16-Feb-22 19-Feb-22

A.A 1.1.2.4.2 In foundation column


A1340 Dia. 6 deformed bar 1 1 0% 05-Mar-22 05-Mar-22 DL.Daily Laborer
A1350 Dia. 14 deformed bar 1 1 0% 04-Mar-22 04-Mar-22 DL.Daily Laborer
A1360 Dia. 16 deformed bar 1 1 0% 03-Mar-22 03-Mar-22 DL.Daily Laborer

Subtotal 3 3 03-Mar-22 05-Mar-22

A.A 1.1.2.4.3 In grade beam


A1380 Dia.8 deformed bar 2 2 0% 24-Feb-22 25-Feb-22 DL.Daily Laborer
A1390 Dia.12 deformed bar 2 2 0% 26-Feb-22 28-Feb-22 DL.Daily Laborer
A1400 Dia.14 deformed bar 2 2 0% 01-Mar-22 02-Mar-22 DL.Daily Laborer

Subtotal 6 6 24-Feb-22 02-Mar-22

A.A 1.1.2.4.4 In ground slab


A1420 Dia.8 deformed bar 3 3 0% 25-Apr-22 27-Apr-22 DL.Daily Laborer

Subtotal 3 3 25-Apr-22 27-Apr-22

Subtotal 61 61 16-Feb-22 27-Apr-22

A.A 1.1.2.5 Concrete ancillaries


A1440 10mm thick 100mm deep Styrofoam 5 5 0% 28-Apr-22 03-May-22 DL.Daily Laborer
expansion joint filler.

Subtotal 5 5 28-Apr-22 03-May-22

Subtotal 72 72 11-Feb-22 05-May-22

Page 2 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A.A 1.1.6 MASONRY WORK


A1490 500 mm thick basaltic or equivalent 5 5 0% 11-Feb-22 16-Feb-22 M.Mason
type stone masonry bedded in
cement mortar(1:3) mix below
ground surface. price sha
A1500 500 mm thick basaltic or equivalent 5 5 0% 17-Feb-22 22-Feb-22 DL.Daily Laborer
type stone masonry bedded in
cement mortar(1:3) mix above
ground surface. price sha

Subtotal 10 10 11-Feb-22 22-Feb-22

Subtotal 81 81 01-Feb-22 05-May-22

A.A 1.3 SUPERSTRUCTURE


A.A 1.3.1 CONCRETE WORK
A.A 1.3.1.7 Reinforced concrete C-25
A.A 1.3.1.7.1 To elevation columns
A1580 Ground Floor 5 5 0% 03-Jun-22 08-Jun-22 C.Carpenter
A1590 Firist Floor 5 5 0% 28-Sep-22 03-Oct-22 C.Carpenter

Subtotal 105 105 03-Jun-22 03-Oct-22

A.A 1.3.1.7.2 To floor beams


A1610 Firist Floor 5 5 0% 25-Aug-22 30-Aug-22 C.Carpenter

Subtotal 5 5 25-Aug-22 30-Aug-22

A.A 1.3.1.7.3 Suspended ribbed slab


A1640 Firist Floor 5 5 0% 11-Aug-22 16-Aug-22 C.Carpenter

Subtotal 5 5 11-Aug-22 16-Aug-22

A.A 1.3.1.7.4 To 150mm thick slab


A1660 Firist Floor slab 5 5 0% 25-Aug-22 30-Aug-22 C.Carpenter
A1670 Roof slab 5 5 0% 21-Nov-22 25-Nov-22 C.Carpenter

Subtotal 80 80 25-Aug-22 25-Nov-22

A.A 1.3.1.7.5 To stair case and landingg


A1690 Ground 5 5 0% 25-Aug-22 30-Aug-22 C.Carpenter

Subtotal 5 5 25-Aug-22 30-Aug-22

Page 3 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A.A 1.3.1.7.6 To top tie beam and lintel


A1700 To top tie beam and lintel 5 5 0% 21-Nov-22 25-Nov-22 C.Carpenter

Subtotal 5 5 21-Nov-22 25-Nov-22

Subtotal 151 151 03-Jun-22 25-Nov-22

A.A 1.3.1.1 Formwork


A.A 1.3.1.1.1 To elevation columns
A1740 Ground Floor 5 5 0% 20-May-22 25-May-22 C.Carpenter
A1750 Firist Floor 5 5 0% 14-Sep-22 19-Sep-22 C.Carpenter

Subtotal 105 105 20-May-22 19-Sep-22

A.A 1.3.1.1.2 To floor beams


A1770 Firist Floor 5 5 0% 17-Jun-22 22-Jun-22 C.Carpenter

Subtotal 5 5 17-Jun-22 22-Jun-22

A.A 1.3.1.1.3 To 150mm thick slab


A1790 Firist Floor slab 5 5 0% 23-Jun-22 28-Jun-22 C.Carpenter
A1800 Roof slab 5 5 0% 26-Oct-22 31-Oct-22 C.Carpenter

Subtotal 112 112 23-Jun-22 31-Oct-22

A.A 1.3.1.1.4 To stair case and landingg


A1810 d) Staircase, landing and hall steps 5 5 0% 05-Aug-22 10-Aug-22 C.Carpenter

Subtotal 5 5 05-Aug-22 10-Aug-22

A.A 1.3.1.1.5 To top tie beam and lintel


A1820 e) To top tie beam and lintel 5 5 0% 12-Oct-22 17-Oct-22 C.Carpenter

Subtotal 5 5 12-Oct-22 17-Oct-22

Subtotal 141 141 20-May-22 31-Oct-22

A.A 1.3.1.6 Rebar


A.A 1.3.1.6.7 To elevation columns
A.A In ground floor
1.3.1.6.7.1
A1870 Dia. 6 plain bar 5 5 0% 14-May-22 19-May-22 DL.Daily Laborer

Page 4 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A1880 Dia. 14 deformed bar 5 5 0% 14-May-22 19-May-22 DL.Daily Laborer

A1890 Dia. 16 deformed bar 5 5 0% 14-May-22 19-May-22 DL.Daily Laborer

Subtotal 5 5 14-May-22 19-May-22

A.A In first floor


1.3.1.6.7.2
A1910 Dia. 6 plain bar 5 5 0% 08-Sep-22 13-Sep-22 DL.Daily Laborer
A1920 Dia. 14 deformed bar 5 5 0% 08-Sep-22 13-Sep-22 DL.Daily Laborer

A1930 Dia. 16 deformed bar 5 5 0% 08-Sep-22 13-Sep-22 DL.Daily Laborer

Subtotal 5 5 08-Sep-22 13-Sep-22

Subtotal 105 105 14-May-22 13-Sep-22

A.A 1.3.1.6.2 Floor beams


A1960 Dia. 8 deformed bar 5 5 0% 07-Jul-22 12-Jul-22 DL.Daily Laborer
A1970 Dia. 10 deformed bar 5 5 0% 29-Jun-22 04-Jul-22 DL.Daily Laborer
A1980 Dia. 12 deformed bar 5 5 0% 29-Jun-22 04-Jul-22 DL.Daily Laborer
A1990 Dia. 14 deformed bar 5 5 0% 29-Jun-22 04-Jul-22 DL.Daily Laborer

A2000 Dia. 16 deformed bar 5 5 0% 29-Jun-22 04-Jul-22 DL.Daily Laborer

A2010 Dia. 20 deformed bar 5 5 0% 29-Jun-22 04-Jul-22 DL.Daily Laborer

Subtotal 12 12 29-Jun-22 12-Jul-22

A.A 1.3.1.6.3 Ribbed slab


A2030 Dia. 6 plain bar 5 5 0% 19-Jul-22 23-Jul-22 DL.Daily Laborer
A2040 Dia. 12 deformed bar 5 5 0% 25-Jul-22 29-Jul-22 DL.Daily Laborer

A2050 Dia. 14 deformed bar 5 5 0% 30-Jul-22 04-Aug-22 DL.Daily Laborer

Subtotal 15 15 19-Jul-22 04-Aug-22

A.A 1.3.1.6.4 To 150mm thick slab


A.A First floor
1.3.1.6.4.1
A2080 Dia. 8 deformed bar 5 5 0% 13-Jul-22 18-Jul-22 DL.Daily Laborer
A2090 Dia. 10 deformed bar 5 5 0% 13-Jul-22 18-Jul-22 DL.Daily Laborer

A2100 Dia. 12 deformed bar 5 5 0% 13-Jul-22 18-Jul-22 DL.Daily Laborer

Page 5 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A2110 Dia. 16 deformed bar 5 5 0% 13-Jul-22 18-Jul-22 DL.Daily Laborer

Subtotal 5 5 13-Jul-22 18-Jul-22

A.A Roof slab


1.3.1.6.4.2
A2130 Dia. 8 deformed bar 5 5 0% 15-Nov-22 19-Nov-22 DL.Daily Laborer

Subtotal 5 5 15-Nov-22 19-Nov-22

Subtotal 112 112 13-Jul-22 19-Nov-22

A.A 1.3.1.6.5 Stair case and landingg


A2150 Dia. 8 deformed bar 5 5 0% 19-Aug-22 24-Aug-22 DL.Daily Laborer
A2160 Dia. 10 deformed bar 5 5 0% 19-Aug-22 24-Aug-22 DL.Daily Laborer

A2170 Dia. 12 deformed bar 5 5 0% 19-Aug-22 24-Aug-22 DL.Daily Laborer

A2180 Dia. 14 deformed bar 5 5 0% 19-Aug-22 24-Aug-22 DL.Daily Laborer

Subtotal 5 5 19-Aug-22 24-Aug-22

A.A 1.3.1.6.6 To top tie beam and lintel


A2200 Dia. 8 deformed bar 5 5 0% 09-Nov-22 14-Nov-22 DL.Daily Laborer
A2210 Dia. 10 deformed bar 5 5 0% 09-Nov-22 14-Nov-22 DL.Daily Laborer

A2220 Dia. 12 deformed bar 5 5 0% 09-Nov-22 14-Nov-22 DL.Daily Laborer

A2230 Dia. 14 deformed bar 5 5 0% 09-Nov-22 14-Nov-22 DL.Daily Laborer

A2240 Dia. 16 deformed bar 5 5 0% 09-Nov-22 14-Nov-22 DL.Daily Laborer

Subtotal 5 5 09-Nov-22 14-Nov-22

A.A 1.3.1.6.1 In first floor ribbed slab mesh


A2260 Dia. 6 plain bar 5 5 0% 05-Aug-22 10-Aug-22 DL.Daily Laborer

Subtotal 5 5 05-Aug-22 10-Aug-22

Subtotal 163 163 14-May-22 19-Nov-22

Subtotal 168 168 14-May-22 25-Nov-22

Page 6 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A.A 1.3.8 BLOCK WORK


A.A 1.3.8.1 20cm H.C.B wall class "B"
A2320 Ground floor 41 41 0% 14-Jan-23 02-Mar-23 DL.Daily Laborer
A2330 Firist floor 41 41 0% 30-Mar-23 17-May-23 DL.Daily Laborer

Subtotal 106 106 14-Jan-23 17-May-23

A.A 1.3.8.2 Ditto but 15cm thick


A2350 Ground floor 14 14 0% 03-Mar-23 18-Mar-23 DL.Daily Laborer
A2360 Firist floor 14 14 0% 17-May-23 02-Jun-23 DL.Daily Laborer

Subtotal 79 79 03-Mar-23 02-Jun-23

A.A 1.3.8.4 Ditto but 10cm thick


A2380 Ground floor 10 10 0% 18-Mar-23 30-Mar-23 DL.Daily Laborer
A2390 Firist floor 10 10 0% 02-Jun-23 14-Jun-23 DL.Daily Laborer

Subtotal 75 75 18-Mar-23 14-Jun-23

Subtotal 130 130 14-Jan-23 14-Jun-23

A.A 1.3.9 ROOFING


A2450 Roof cover in precoated or 4 4 0% 27-Dec-22 30-Dec-22 C.Carpenter
galvanized EGA - 400, 0.4mm thick
fixed to zigba purlins,price shall
include ridge cap, UV
A2460 G-30 Galvanized sheet metal gutter 4 4 0% 31-Dec-22 04-Jan-23 C.Carpenter
of dev. Length 1000mm.
A2470 G-30 Galvanized sheet metal 4 4 0% 05-Jan-23 09-Jan-23 C.Carpenter
copping of dev. Length 67mm.
A2480 G-30 Galvanized sheet metal 4 4 0% 10-Jan-23 13-Jan-23 C.Carpenter
Flashing of dev. Length 50mm.

Subtotal 16 16 27-Dec-22 13-Jan-23

A.A 1.3.10 DAMP PROOFING


A2530 Brush and blow out dirt,dust 1 1 0% 01-Nov-22 01-Nov-22 DL.Daily Laborer
latiance,scrapings and all other loose
material roor and water tank slab until
the reinforc
A2540 Applay 3cm thick cement screed 1 1 0% 02-Nov-22 02-Nov-22 DL.Daily Laborer
over light weight concrete in mix
proportion of 1:5
A2550 Supply and apply 4mm tthick 1 1 0% 03-Nov-22 03-Nov-22 DL.Daily Laborer
MAYAPROOF WS2 or equvalent
semi elastic water proofing material
on roof slab and wet area (

Page 7 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

Subtotal 3 3 01-Nov-22 03-Nov-22

A.A 1.3.11 CARPENTRY & JOINERY


A.A 1.3.11.1 Carpentry
A2640 Supply and fix pvc ceiling on 40x50 5 5 0% 31-Aug-23 06-Sep-23 C.Carpenter
mm wooden ceiling batten placed
600 mm c/c in both sides. Price shall
include ceil
A2650 Supply and fix gypsum board ceiling 5 5 0% 06-Sep-23 12-Sep-23 C.Carpenter
on 40x50 mm wooden ceiling batten
placed 600 mm c/c in both sides.
Price shall incl
A2660 Supply and fix sound absorbent 5 5 0% 12-Sep-23 18-Sep-23 C.Carpenter
Armstrong ceiling . Price shall include
all supporting suspensions system
and accessor

A2670 Wooden fascia board price include 12 12 0% 18-Sep-23 02-Oct-23 C.Carpenter


three coat of weather resistance paint
size 25/2.5cm.

Subtotal 27 27 31-Aug-23 02-Oct-23

A.A 1.3.11.2 Joinery


A2710 D1 size 900x2850mm 5 5 0% 11-Apr-24 17-Apr-24 C.Carpenter
A2720 D2 size 900x2750mm 5 5 0% 17-Apr-24 23-Apr-24 C.Carpenter
A2730 D3 size 800x3000mm 5 5 0% 23-Apr-24 29-Apr-24 C.Carpenter
A2740 D4 size 700x1900mm 5 5 0% 29-Apr-24 04-May-24 C.Carpenter
A2750 D5 size 1500x2750mm 5 5 0% 04-May-24 10-May-24 C.Carpenter
A2760 Supply ,cut, assemble and fix ,in 5 5 0% 10-May-24 16-May-24 C.Carpenter
class room ,steps out of steel
structure and covered with 10cm
width and 2cm thick tim
A2770 Supply and fix ,in hall,wooden 5 5 0% 16-May-24 22-May-24 C.Carpenter
cladding as shown on the detail
drawing.

Subtotal 35 35 11-Apr-24 22-May-24

Subtotal 227 227 31-Aug-23 22-May-24

A.A 1.3.12 METAL WORK


A2930 100cm hieght CHS aluminium hand 5 5 0% 22-May-24 28-May-24 Af.Alumunium Fixer
rail with all other necessary
accessories for completing the work.
All according to draw
A2940 Wall mounted CHS aluminium hand 5 5 0% 28-May-24 03-Jun-24 Af.Alumunium Fixer
rail fixed to vertical surface with all
other necessary accessories for

Page 8 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

completing the
A.A 1.3.12.1 Window
A2840 W1 Size 2980x1945mm 6 6 0% 02-Oct-23 09-Oct-23 F.Forman
A2850 W2 Size 4480x8450mm 6 6 0% 09-Oct-23 16-Oct-23 F.Forman
A2860 W3 size 4380x8450mm 6 6 0% 16-Oct-23 23-Oct-23 F.Forman
A2870 W4 Size 4480x7450mm 6 6 0% 23-Oct-23 30-Oct-23 F.Forman
A2880 W5 Size 1280x1245mm 6 6 0% 30-Oct-23 06-Nov-23 F.Forman
A2890 W6 Size 980x1570mm 6 6 0% 06-Nov-23 13-Nov-23 F.Forman
A2900 W7 Size 980x1238mm 6 6 0% 13-Nov-23 20-Nov-23 F.Forman
A2910 W8 Size 980x1860mm 6 6 0% 20-Nov-23 27-Nov-23 F.Forman

Subtotal 48 48 02-Oct-23 27-Nov-23

A.A 1.3.12.2 Corner protection


A2960 30x30x3mm perforated aluminume 5 5 0% 03-Jun-24 08-Jun-24 DL.Daily Laborer
angle iron fixed to exposed corner
plastered over and painted.lengh not
exceeding 1500mm.

Subtotal 5 5 03-Jun-24 08-Jun-24

Subtotal 215 215 02-Oct-23 08-Jun-24

A.A 1.3.13 STEEL STRUCTURE


A.A 1.3.13.1 R.H.S steel truss
A3010 80x80x3mm RHS 5 5 0% 04-Nov-22 09-Nov-22 DL.Daily Laborer
A3020 80x60x2.5mm RHS 5 5 0% 10-Nov-22 15-Nov-22 DL.Daily Laborer
A3030 40x40x2.5mmRHS 5 5 0% 16-Nov-22 21-Nov-22 DL.Daily Laborer
A3040 30x30x2.5mmRHS 5 5 0% 22-Nov-22 26-Nov-22 DL.Daily Laborer

Subtotal 20 20 04-Nov-22 26-Nov-22

A.A 1.3.13.2 R.H.S steel purlin


A3060 780x50x3mm RHS 5 5 0% 28-Nov-22 02-Dec-22 DL.Daily Laborer
A3070 Plates 200*200*5mm 5 5 0% 03-Dec-22 08-Dec-22 DL.Daily Laborer
A3080 J bolt Ø16mm, Lengh 400mm 5 5 0% 09-Dec-22 14-Dec-22 DL.Daily Laborer
A3090 J bolt Ø20mm, Lengh 400mm 5 5 0% 15-Dec-22 20-Dec-22 DL.Daily Laborer
A3100 Angle ties 30/30x30x3mm 5 5 0% 21-Dec-22 26-Dec-22 DL.Daily Laborer

Subtotal 25 25 28-Nov-22 26-Dec-22

Subtotal 45 45 04-Nov-22 26-Dec-22

Page 9 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A.A 1.3.14 FINISHING


A.A 1.3.14.1 Wall finishing
A.A 1.3.14.1.1 Two coats of plastering
A.A To internal wall surface
1.3.14.1.1.1
A3180 Ground Floor 10 10 0% 14-Jun-23 26-Jun-23 DL.Daily Laborer
A3190 First Floor 15 15 0% 10-Jul-23 27-Jul-23 DL.Daily Laborer

Subtotal 37 37 14-Jun-23 27-Jul-23

A.A To concrete ceiling and stair soffit


1.3.14.1.1.2
A3220 First Floor 5 5 0% 27-Jul-23 02-Aug-23 DL.Daily Laborer
A3210 Ground Floor 7 7 0% 26-Jun-23 04-Jul-23 DL.Daily Laborer

Subtotal 32 32 26-Jun-23 02-Aug-23

A.A To external wall surface


1.3.14.1.1.3
A3240 Ground Floor 5 5 0% 04-Jul-23 10-Jul-23 DL.Daily Laborer
A3250 First Floor 5 5 0% 02-Aug-23 08-Aug-23 DL.Daily Laborer

Subtotal 30 30 04-Jul-23 08-Aug-23

Subtotal 47 47 14-Jun-23 08-Aug-23

A.A 1.3.14.1.2 Final coat gypsum


A.A To internal wall surface
1.3.14.1.2.3
A3280 Ground Floor 5 5 0% 08-Aug-23 14-Aug-23 DL.Daily Laborer
A3290 First Floor 5 5 0% 19-Aug-23 25-Aug-23 DL.Daily Laborer

Subtotal 15 15 08-Aug-23 25-Aug-23

A.A To concrete ceiling and stair soffit


1.3.14.1.2.2
A3310 Ground Floor 5 5 0% 14-Aug-23 19-Aug-23 DL.Daily Laborer
A3320 First Floor 5 5 0% 25-Aug-23 31-Aug-23 DL.Daily Laborer

Subtotal 15 15 14-Aug-23 31-Aug-23

Subtotal 20 20 08-Aug-23 31-Aug-23

Page 10 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A.A 1.3.14.1.3 Ceramic wall tiles


A.A Klinker wall tiles
1.3.14.1.3.1
A3340 Ground Floor 1 1 0% 27-Nov-23 28-Nov-23 DL.Daily Laborer
A3350 First Floor 2 2 0% 28-Nov-23 30-Nov-23 DL.Daily Laborer

Subtotal 3 3 27-Nov-23 30-Nov-23

Subtotal 3 3 27-Nov-23 30-Nov-23

Subtotal 145 145 14-Jun-23 30-Nov-23

A.A 1.3.14.4 Floor finish


A3640 Ditto but 30cm width marble window 1 1 0% 18-Dec-23 19-Dec-23 DL.Daily Laborer
sill bedded on cement mortar (1:3)
ratio . Price shall include cement
screed , mi
A3670 40 x 40 x 5 cm cement tile pavement 1 1 0% 23-Dec-23 25-Dec-23 DL.Daily Laborer
around the bulding .it shall be laid on
compacted eart /fill and 100mm
sand/red ash
A3580 8cm high Granite skirting. 3 3 0% 05-Dec-23 08-Dec-23 DL.Daily Laborer
A3560 Granite floor tile shall be laid on 4 4 0% 30-Nov-23 05-Dec-23 DL.Daily Laborer
properly finished and cured floor
screed with approved glue in
accordance with the
A3590 3cm and 25cm wide Granait trade 4 4 0% 08-Dec-23 13-Dec-23 DL.Daily Laborer
bedded in cement mortar (1:3) ratio .
Price shall include mirror polishing
and all n
A3610 Ditto but 2cm marble riser for stair 4 4 0% 13-Dec-23 18-Dec-23 DL.Daily Laborer
bedded on cement mortar (1:3) ratio .
Price shall include cement screed ,
mirror
A3660 Ditto but 30cm width marble 4 4 0% 19-Dec-23 23-Dec-23 DL.Daily Laborer
threshold bedded on cement mortar
(1:3) ratio . Price shall include cement
screed , mirro
A.A 1.3.14.4.1 klinker floor tile
A3420 Ground Floor 5 5 0% 25-Dec-23 30-Dec-23 DL.Daily Laborer
A3430 First Floor 5 5 0% 13-Jan-24 19-Jan-24 DL.Daily Laborer

Subtotal 22 22 25-Dec-23 19-Jan-24

A.A 1.3.14.4.2 8cm high klinker skirting


A3460 Ground Floor 5 5 0% 30-Dec-23 05-Jan-24 DL.Daily Laborer
A3470 First Floor 5 5 0% 19-Jan-24 25-Jan-24 DL.Daily Laborer

Page 11 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

Subtotal 22 22 30-Dec-23 25-Jan-24

A.A 1.3.14.4.3 Roll PVC tile


A3490 Ground Floor 5 5 0% 05-Jan-24 11-Jan-24 DL.Daily Laborer
A3500 First Floor 5 5 0% 25-Jan-24 31-Jan-24 DL.Daily Laborer

Subtotal 22 22 05-Jan-24 31-Jan-24

A.A 1.3.14.4.4 8cm high Pvc tile skirting


A3530 First Floor 1 1 0% 31-Jan-24 01-Feb-24 DL.Daily Laborer
A3520 Ground Floor 2 2 0% 11-Jan-24 13-Jan-24 DL.Daily Laborer

Subtotal 18 18 11-Jan-24 01-Feb-24

Subtotal 54 54 30-Nov-23 01-Feb-24

Subtotal 199 199 14-Jun-23 01-Feb-24

A.A 1.3.5 PAINTING


A.A 1.3.5.1 To internal plasterd wall surface
A3750 First Floor 5 5 0% 30-Mar-24 05-Apr-24 DL.Daily Laborer
A3740 Ground Floor 20 20 0% 01-Feb-24 24-Feb-24 DL.Daily Laborer

Subtotal 55 55 01-Feb-24 05-Apr-24

A.A 1.3.5.2 To Rc celling


A3790 First Floor 5 5 0% 05-Apr-24 11-Apr-24 DL.Daily Laborer
A3780 Ground Floor 20 20 0% 24-Feb-24 19-Mar-24 DL.Daily Laborer

Subtotal 40 40 24-Feb-24 11-Apr-24

A.A 1.3.5.3 To gypsum board


A3820 Total sum of ground and first floor 10 10 0% 19-Mar-24 30-Mar-24 DL.Daily Laborer

Subtotal 10 10 19-Mar-24 30-Mar-24

A.A 1.3.5.4 Quartiz


A.A 1.3.5.4.1 To internal wall surface
A3850 Ground Floor 5 5 0% 08-Jun-24 14-Jun-24 DL.Daily Laborer
A3860 First Floor 5 5 0% 20-Jun-24 26-Jun-24 DL.Daily Laborer

Subtotal 15 15 08-Jun-24 26-Jun-24

Page 12 of 13
G+1 Project Start 01-Feb-22
Report Date 02-Feb-22 02:32 Project Finish 02-Jul-24

AD-01 Activity Status Report

WBS
Activity ID Activity Name Original Remaining Activity % Start Finish Primary Resource
Duration Duration Complete

A.A 1.3.5.4.2 To external wall surface


A3900 End Of Project 0 0 0% 02-Jul-24
A3880 Ground Floor 5 5 0% 14-Jun-24 20-Jun-24 DL.Daily Laborer
A3890 First Floor 5 5 0% 26-Jun-24 02-Jul-24 DL.Daily Laborer

Subtotal 15 15 14-Jun-24 02-Jul-24

Subtotal 20 20 08-Jun-24 02-Jul-24

Subtotal 130 130 01-Feb-24 02-Jul-24

Subtotal 669 669 14-May-22 02-Jul-24

Subtotal 757 757 01-Feb-22 02-Jul-24

Subtotal 757 757 01-Feb-22 02-Jul-24

Total 757 757 01-Feb-22 02-Jul-24