To this end, the Employer requires up to three (3) months for the acquisition of land in rural areas
Septic tanks
Assumption
Vegetation clearing
Payment of the lump sum item 13.01(a) shall be made in three instalments, as follows:
• The first instalment, 50% of the lump sum, shall be paid in the first payment certificate after the
Contractor has met all his obligations under this section and has made a substantial start with the
construction in accordance with the approved programme;
• The second instalment, 30% of the lump sum, shall be paid when the value of the work done reaches
half (½) of the contract price, excluding contingencies and price adjustments in the Conditions of
Contract;
• The third and final instalment, 20% of the lump sum, shall be paid when the Works have been
completed and the Contractor has reinstated the Site in accordance with the Contract.
• Camp sites for himself and his senior and junior staff, including houses, offices, labourers'
accommodation, etc.
Office buildings shall have concrete floors with vinyl floor tiles.
Kitchen Unit 12 m2
Sample storage 10
Store 10
Living 12
Bedroom 12
Bathroom 6