Safety and Emergency Equipment

Safety clothing (reflective jackets), helmets, safety boots and tools

Camp Maintenance (painting)

Maintenance of internal roads

Communication System for the Engineer

Houses

Offices

Laborers’ accommodation

Fire extinguishers at each block

Health clinics at each camp

To this end, the Employer requires up to three (3) months for the acquisition of land in rural areas

Tree removal activities for camp sites

Septic tanks

Haul and access roads …adjacent to the new road…

Assumption

The adjacent land is not farmland and grazing land

Vegetation clearing

Top soil removal

Disposal of cleared material

Stockpiling of top soil (for re instating the access road)

Selected material fill and compaction

Item 13.01 Contractor establishment

a) Fixed Cost ......................................................................................................................... Lump Sum


b) Time-related Cost ..................................................................................................................... month

Payment of the lump sum item 13.01(a) shall be made in three instalments, as follows:

• The first instalment, 50% of the lump sum, shall be paid in the first payment certificate after the
Contractor has met all his obligations under this section and has made a substantial start with the
construction in accordance with the approved programme;

• The second instalment, 30% of the lump sum, shall be paid when the value of the work done reaches
half (½) of the contract price, excluding contingencies and price adjustments in the Conditions of
Contract;

• The third and final instalment, 20% of the lump sum, shall be paid when the Works have been
completed and the Contractor has reinstated the Site in accordance with the Contract.

The Site Engineer's office;

• Laboratory facilities and working areas; and

• Camp sites for himself and his senior and junior staff, including houses, offices, labourers'
accommodation, etc.

Handing over of the Site

Engineer's office building (50 m2)

Office buildings shall have concrete floors with vinyl floor tiles.

toilets, hand wash-basins, and to the kitchen

Engineer's office building (total area = 50 m2)

Resident Engineer's Office 10 m2

General Office 1 (Pool Office for key staffs) 20 m2

Kitchen Unit 12 m2

toilets + 1 wash basin 8 m2


Laboratory

Laboratory testing area 40

Oven and soaking room 10

Sample storage 10

Store 10

Floor area for Housing Accommodation to the Engineer

Type B House (30m2)

Living 12

Bedroom 12

Bathroom 6

Maintenance of Haul and access roads

Reinstatement of Haul and access roads