Professional Documents
Culture Documents
Burchett 2017
Burchett 2017
fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
1
Abstract—A simplified voltage stability analysis method is factor loads. The maximum power transfer is achieved at the
to use a static Thévenin equivalent to represent the electrical tip of the P V curve, also known as the voltage collapse point.
connection to a load center. Assuming fixed values of the Thévenin
voltage and reactance, a power-voltage (P V ) curve analysis can
be performed to find the voltage collapse point and stability
margin. This paper proposes a method to compute the static 1.2
Thévenin equivalent voltage and reactance of a power system
using measured data. The method is validated with simulated 1 data points
Normalized Voltage, pu
PMU data and with 24-hour SCADA data at a wind hub on a
medium voltage transmission system in the US western system. 0.8
For the wind hub, the Thévenin equivalent parameters are used to
compute the maximum power transfer capability of the wind hub 0.6
as constrained by voltage stability. Then the method is extended
to online application by using short data windows and forgetting 0.4
factors.
pf = -0.9
Index Terms—Voltage stability, stability margin, Thévenin 0.2 pf = 1
equivalent, AQ bus, PV curve pf = 0.9
0
0 0.2 0.4 0.6 0.8
I. I NTRODUCTION Normalized Power, pu
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
2
noise. However, with data measured from real power systems, The large generator in System 1 is connected to the bound-
during periods where the (P, Q, V ) values are relatively con- ary bus via a transmission line of reactance 0.2 pu. The
stant, the presence of measurement and quantization noise may small generator in System 2 is connected to the boundary
result in these methods yielding rather erratic results. Figure bus via a transformer with reactance 0.15 pu. The transient
3 shows the Thévenin equivalent reactance values estimated and subtransient reactances of the generator are Xd0 = 0.42
using 5 min (P, Q, V ) data windows, over a twenty-four pu and Xd00 = 0.31 pu, respectively, and the voltage regulator
period, for the wind hub system described in Section IV. For gain is KA = 141.
a practical power system, it would be unreasonable to expect
that the equivalent reactance would vary so substantially over V 0o
such short spans of time. P + jQ
System 1 System 2
I
Boundary
bus
Fig. 4: A power system consisting of a small system (Sys-
tem 1) and a large system (System 2)
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
3
1.1 pu and Êth = 1.0804 pu. The results are consistent with
System 1 data that X̂th is the sum of the transmission line
1.05
reactance (0.2 pu) and the machine transient reactance which
1
is small when scaled by the large machine base, and Êth
0 50 100 150 200 is essentially the large generator terminal bus voltage (1.08
Time (sec) pu). As a further verification, a sequence of 2-bus power flow
Vsim solutions is obtained with the large generator bus voltage set
Eth with X th =0.3 pu at Êth = 1.0804 pu, the boundary (load) bus power set at the
Eth with X th =0.2 pu simulated (P, Q) values, and X̂th = 0.2002 pu used as the
Eth with X th =0.15 pu reactance connecting the two buses. The calculated load bus
Eth with X th =0.1 pu voltage Vcal is shown with the simulated voltage Vsim in the
Eth with X th =0.05 pu lower plot of Figure 5. The root-mean-square (RMS) error in
the Thévenin voltage approximation is 0.000532 pu.
Fig. 6: Values of Eth for various values of Xth
s
PN 1
2
k=1 (Ethi (k) − Ēthi )
εi = (3) 0
N P
Q
5) Select Ēthi with the lowest value of εi and its two adja- -1
cent neighboring points Ēth(i−1) and Ēth(i+1) . Apply
1.08
a 3-point quadratic fit algorithm in [7] to obtain the
Voltage (pu)
It should be noted that a similar estimation idea is used to Fig. 7: Values of (P, Q, V ) for the active-power step dis-
estimate Xth by iteratively computing the Thèvenin equivalent turbances
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
4
Applying the optimal estimation algorithm results in X̂th = 2 type-3 wind turbines, with a combined maximum output of
0.2018 pu and Êth = 1.0807 pu, which for practical purposes, about 600 MW. The voltage at the wind farms is supported by
are identical to those obtained in the voltage step disturbances two 28.8 MVAR shunt capacitors in the substation and a wide
for estimating the Thévenin equivalent of System 1. To verify array of shunt capacitors and reactors, and two STATCOMs
the result, again a sequence of 2-bus power flow solutions is inside the wind farms. The WH bus is connected to the west
used to obtain the load bus voltage Vcal , which is shown with by a long 160-mile line (reactance is 0.0861 pu) which is
the simulated voltage Vsim in the lower plot of Figure 7. The eventually connected back to the 500 kV system. It is also
RMS error in the Thévenin voltage approximation is 0.000530. connected to the east via a 48-mile line (reactance is 0.02732
pu) to an area with several large generators and to the 500
C. Voltage Sag Disturbances kV system. Thus the west connection is regarded as weak,
whereas the east connection is regarded as strong.
For the third case, a voltage sag disturbance is applied in The objective is to assess the voltage stability margin to
System 1 to compute the Thévenin-equivalent for System 2. ensure safe transfer of the wind energy to the west and to the
Figure 8 shows the simulated (P, Q, V ) data at the boundary east. At first glance, a voltage stability analysis would require
bus for a sequence of voltage-sag disturbances in System 1, accounting for all the status of the reactive power supply
with System 2 also responding to this disturbance. at the WH Bus, which would be quite complicated as the
statuses of the shunt capacitors/reactors at the WH Substation
1 and the wind farms are not available from the SCADA data.
However, with valid Thévenin equivalent models, the WH Bus
Power (pu)
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
5
4 1.3
Voltage (pu)
Power (pu)
2 1.2
0 1.1
P
Q
-2 1
0 4 8 12 16 20 24
1.08 Time (hours)
Voltage (pu)
Vmeas
Eth with X th =0.3 pu
1.06
Eth with X th =0.2 pu
Eth with X th =0.15 pu
1.04 Eth with X th =0.1 pu
0 4 8 12 16 20 24
Eth with X th =0.05 pu
Time (hours)
Fig. 10: 24-hour SCADA voltage at WH Bus and the Fig. 11: Calculated voltage Vth at west system using vari-
(P, Q) flow to the west system ous values of Xth
that the terminal voltages of the generators near the east system in the lower plot of Figure 13. Note that there were not enough
were adjusted during the day to accommodate load changes. (P, Q, V ) variations in the Day 8 data to compute the optimal
In particular, there is a noticeable voltage rise between Hours parameters.
7 to 8 (denoted by A in Figure 15) and a voltage drop between
Hours 21 to 22 (denoted by B). As a result, the optimal
Thévenin equivalent estimation is performed only for Hours 9 C. Voltage Stability Analysis
to 20, yielding the optimal parameters X̂th = 0.0498 pu and The AQ-bus method in [10] is used for developing the
Êth = 1.0704 pu. To verify the solution, the WH Bus voltage P V curve and computing the voltage stability margin, using
is computed using the Thévenin model and the (P, Q) flow the east and west system Thévenin model parameters. In
values. Figure 16 shows that the calculated WH Bus voltage this method, the bus that is vulnerable to voltage collapse
matches well the measured values from Hours 9 to 20. The is modeled as an AQ bus, where the bus voltage angle
RMS error of the Thévenin voltage during this Hours 9 to 20 and reactive power are specified. In the wind hub system,
period is 0.0016 pu. There is also a divergence between Hours the wind hub is selected as the AQ bus, even though it
0 to 8 and 22 to 24. is supplying power. However, with limited reactive power
The optimal parameters obtained for nine days of SCADA support, it encounters similar voltage collapse problems like a
data for the east system using Hours 9 to 20 measured data load bus. The power flow computation in the AQ-bus method
also show good consistency between Day 2 to Day 6, as shown uses a Jacobian matrix with one fewer dimension than a
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
6
in Figure 18. Note that the P V curve does not reach zero
1.075
voltage when the wind hub power is zero because of power
V
1.07 V
meas
transfers from east to west through the wind hub bus. Table
cal
I shows the maximum power transfer levels for the various
1.065 shunt compensation.
Voltage (pu)
1.06
A voltage stability analysis for the wind hub system with
the line to the East System disconnected, resulting in wind
1.055 curtailment, can be found in [11].
1.05
4
1.045
Power (pu)
2
1.04
0 4 8 12 16 20 24 0
Time (hours) P
Q
Fig. 12: Comparison of measured and west system -2
Thévenin equivalent calculated WH Bus voltage 1.08
Voltage (pu)
West 1.06
0.23 1.16
X TH (pu)
E TH (pu)
0.18 1.12
1.04
0 4 8 12 16 20 24
0.13 1.08
Time (hours)
0.08 1.04 Fig. 14: 24-hour SCADA voltage at WH Bus and the
East
0.09 1.1 (P, Q) flow to the east system
X TH (pu)
E TH (pu)
0.06 1.08
A
0 1.04 1.1
1
9
10
ay
ay
ay
ay
ay
ay
ay
ay
ay
ay
1.05
D
D
D
B
Fig. 13: Optimal Thévenin equivalent parameters ob- 1
tained from the SCADA data (∇ denotes a voltage 0 4 8 12 16 20 24
data point, and × denotes a reactance value) Time (hours)
Vmeas
Eth with X th =0.11 pu
normal Jacobian matrix, because there are two buses with E with X
th th
=0.09 pu
fixed angles, allowing it to avoid the Jacobian matrix from E with X
th th
=0.07 pu
To conduct the voltage stability analysis, the angle separa- E with X =0.03 pu
th th
tion between the wind hub (AQ bus) and the swing bus is
Fig. 15: Calculated voltage Vth at east system using various
increased to allow for the power exported by the wind hub to
values of Xth
the east and west systems. To solve for the power flow, the
split of the wind power exporting to the west and east systems
needs to be known. Here the incremental power transfer is Shunt compensation Pmax Vcrit
approximated by a linear relationship, shown in Figure 17. none 805 MW 0.879 p.u.
The east system is chosen as the swing bus because the S1 813 MW 0.890 p.u.
S1 and S2 822 MW 0.902 p.u.
power absorbed varies more than the west system. The west
system is modeled as a P V bus with its active power adjusted TABLE I: Maximum wind hub power transfer
in tandem with the east system based on the approximated
split. The voltages at these two buses are set to their Thévenin
equivalent values.
The P V -curve analysis was performed considering the two
shunt capacitors at the wind hub, which results in P V curves
for three levels of fixed shunt reactive power compensation:
no compensation, S1 only, and both S1 and S2 as shown
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
7
1.075 1.1
1.07 1
0.7
1.05
Vmeas
1.045 Vcal 0.6
1.04 0.5
0 4 8 12 16 20 24 0 2 4 6 8
Time (hours) Wind plant active power (pu)
Fig. 16: Comparison of measured and east system Fig. 18: Wind hub P V curves
Thévenin equivalent calculated WH Bus voltage
k
2 optimal Thèvenin parameter method and X̂th be the estimated
value using the forgetting factor method. Then the proposed
1.5 estimation scheme is
−1
X 0
X
1 k k k+j
X̂th = α0 Xth + αk X̂th , αk = 1, (5)
j=−n k=−n
0.5 Measured data
k k
Power flow model where X̂th is a weighted sum of the current estimate Xth
0 and n immediately past optimal Thévenin reactance values. In
0 1 2 3 4 5
East Power (p.u.) addition, the forgetting factors αk satisfy
Fig. 17: Wind hub power export to east and west systems α−n < α−(n−1) < . . . < α0 . (6)
Once X̂th has been determined, V̂th is computed using steps
V. A N O NLINE E STIMATION A LGORITHM (6)-(7) of the algorithm discussed in Section II.
In the second strategy, there are some instances that the
As noted earlier, for significant changes in power system variation in the measured data in the new data window is so
operating conditions, including line and shunt switchings, gen- small that it would be more meaningful to keep the Thévenin
erator reference voltage adjustments, and control equipment parameters from the previous data window. From Steps (4)
reaching reactive power output limits, it would be necessary and (5) of the optimal estimation algorithm, define
to re-estimate the Thèvenin equivalent parameters. In this
section, the development of online algorithms is considered. εmax = max{εi }, εmin = min{εi } (7)
i i
In contrast to the use of day-long data records to estimate
and
the average Thèvenin equivalent parameters, the objective of
δ = εmax − εmin (8)
an online algorithm is to estimate the time varying Thèvenin
parameters by means of much shorter periods of measured If δ is less than a certain tolerance, new values of Thévenin
data. Such an algorithm will repeatedly compute the Thèvenin parameters will not be calculated and the previous Thévenin
parameters at regular intervals or on demand when new parameter values will be kept.
measured data is available. The main difficulty is that the The online algorithm is demonstrated using the 2-second
measured (P, Q, V ) data may not have adequate variations to SCADA data of east WH system for the same 24-hour mea-
provide reliable results. Thus two strategies are proposed to surement period in Figure 16. The length of the data window T
improve the reliability of the results. The core of the method and the choice of n have to be chosen carefully, often based on
will incorporate the optimal Thèvenin equivalent parameter the measured data. Ideally a short data window should be used,
estimation method developed earlier. but the resulting estimation can be noisy. Also, in order to get
The first strategy is to take into account not just the new fast updates, n should not be too large. For this illustration,
data, but also incorporate the most recent data in the estimation the following parameters were used in the Thévenin equivalent
process. There are many such methods such as overlapping estimation algorithm:
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
8
1) The duration of each period is T = 5 mins of each measurement window. Figure 21 shows the improved
2) The number of previous periods used is n = 4 match with the measured data of the bus voltage throughout
3) Linear varying forgetting factors are applied with the 24-hour period.
αk = {0.06̄, 0.13̄, 0.20, 0.26̄, 0.33̄}
4) The threshold δ = 0.003 pu 1.075
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/TPWRS.2017.2776741, IEEE
Transactions on Power Systems
9
0885-8950 (c) 2017 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission. See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.