You are on page 1of 7

Assessing and Managing the Potential Environmental Risks

of Construction Projects
S. Dione1; J. Y. Ruwanpura, A.M.ASCE2; and J. P. A. Hettiaratchi3

Abstract: Policy makers make key decisions regarding economic development, but engineers are central to the implementation of these
Downloaded from ascelibrary.org by CLEMSON UNIVERSITY on 06/02/14. Copyright ASCE. For personal use only; all rights reserved.

policies. With the realization that economic development and environment are interlinked, engineers are well advised to ensure avoidance
of adverse impacts on society and environment by adopting better practices during the design and implementation of construction projects.
The objective of this paper is to present a project’s proponents and construction contractors with a framework to identify the environ-
mental risks early in a project’s life so that a proper plan could be developed to mitigate the impact of them. The paper also discusses
options currently available in Canada for environmental-type insurance and contractual liability indemnity clauses. A survey conducted
among construction companies to assess current risk-management practices in the construction industry show that although many com-
panies are concerned about the possible implications of environmental risks to their project, there still needs to be more emphasis on
identification and mitigation of these risks and the need to have a comprehensive framework to properly identify and develop an action
plan for environmental related risk issues. The current research trends to achieve these objectives are also outlined in the paper.
DOI: 10.1061/共ASCE兲1084-0680共2005兲10:4共260兲
CE Database subject headings: Construction; Environmental issues; Insurance; Liability; Canada.

Introduction mitigation of environmental risks associated with the construction


industry.
In light of current environmental regulations, proponents of In the province of Alberta in Canada, it is the proponent’s
medium- to large-scale construction projects are required to exer- responsibility to identify the requirements needed to perform a
cise an ever-increasing level of due diligence with respect to iden- detailed environmental assessment of a proposed project. Assum-
tifying potential environmental issues and associated risks. The ing that a project has been subject to this evaluation, and that an
objective of this paper is to present a project’s proponents and environmental assessment is not required under the environmental
contractors with a framework with which potential environmental regulators, the proponent can then proceed with acquiring the
risks can be identified early in a project’s life. The assumption is necessary permits to proceed with the project. However, the pro-
that screening for requirements of an environmental assessment ponent needs to be aware that even though the regulatory regime
process, under the applicable regulatory framework, has already does not require an environmental assessment, there is a possibil-
taken place and that a detailed assessment is not required. It is, ity that there may be environmental issues encountered that will
therefore, up to the project proponent or contractor to identify and need to be addressed. It is in the best interest of the project to
mitigate the potential environmental risks that the project may understand what these issues might be and how to properly ad-
pose to stakeholders or the environment. The paper also includes dress them, as early in the project’s life as possible.
a discussion of the currently available options for environmental- Depending on the project scope and schedule, the proponent or
type insurance and contractual liability indemnity clauses for contractor have two basic options for dealing with potential envi-
Canada. Results from a brief survey of construction companies to ronmental risks to the project:
assess current risk-management practices in the construction in- 1. Identify, assess, and mitigate risks early in the project’s life
dustry are presented. The survey is based on the identification and to minimize impact to the project; or
2. Insure the project from known and/or unknown environmen-
1 tal risks.
Graduate Student, Dept. of Civil Engineering, Univ. of Calgary,
Calgary AB, Canada T2N 1N4. Although the first option may be viewed as the safest alternative,
2
PQS, Director and Assistant Professor, Project Management Special- a project’s scope and schedule may not always make it the most
ization, Dept. of Civil Engineering, Univ. of Calgary, Calgary AB, feasible.
Canada T2N 1N4 共corresponding author兲. E-mail: janaka@ucalgary.ca
3
P.Eng, Professor, Dept. of Civil Engineering, Univ. of Calgary, Cal-
gary AB, Canada T2N 1N4. E-mail: jhettiar@ucalgary.ca
Note. Discussion open until April 1, 2006. Separate discussions must Construction Project Phases
be submitted for individual papers. To extend the closing date by one
month, a written request must be filed with the ASCE Managing Editor. Most medium- to large-scale projects, especially those with com-
The manuscript for this paper was submitted for review and possible
publication on August 24, 2004; approved on December 30, 2004. This
plicated engineering designs, financing and/or construction, can
paper is part of the Practice Periodical on Structural Design and Con- be divided into distinct phases. Each phase represents an impor-
struction, Vol. 10, No. 4, November 1, 2005. ©ASCE, ISSN 1084-0680/ tant milestone towards the project’s completion. The typical
2005/4-260–266/$25.00. project phases and the scope of work are as follows.

260 / PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2005

Pract. Period. Struct. Des. Constr. 2005.10:260-266.


Initiation Phase: This phase starts with the recognition of a need • Insufficient front-end planning;
for the project. The proponent may develop a proposal including • Underestimation of the project scope;
details, such as • Unrealistic project plan; and
• What outcome the project might yield; • Inability to detect problems early.
• Potential costs associated with the project; The inability to control these potential issues could result in a
• Economic justification for the project; myriad of project problems, not the least of which are environ-
• How it could be pursued; mental issues. Where, then, does the project proponent include
• Who should pursue it; environmental planning within the scope of a nonenvironmental
• Cost of the next project phase; and project? That is, where does one allow for the investigation into
• Securing of an agreement to pursue the idea through that the possible environmental issues? In a construction project fol-
phase. lowing the phases outlined previously, the most logical time to
investigate environmental risks is during the planning phase.
Construction planning, final cost estimates, and regulatory
Downloaded from ascelibrary.org by CLEMSON UNIVERSITY on 06/02/14. Copyright ASCE. For personal use only; all rights reserved.

Concept Phase: In this phase, the proponent begins the assembly


of basic data, such as compliance terms, which are finalized during the planning phase,
• The result, quantity, quality, size and location of the project; could be negatively influenced by the discovery of some unknown
• Nature of the project; and environmental issue. Construction plans may need to be changed
• Design and operating policy. to allow for the removal of contaminated soil or groundwater
This phase will outline the objectives and provide all the data 共indirect risk兲, or to alter the construction techniques to minimize
necessary for the initial scope of work to be written. Initial project noise or dust 共direct risk兲. Cost estimates may also need to be
costs and schedule will be developed at this time. The concept revised to allow for the removal of a contaminant. These costs can
phase ends with the approval and funding of the subsequent fea- range from thousands to millions of dollars. Finally, regulatory
approval to proceed with the project may be delayed pending the
sibility phase.
resolution of outstanding direct or indirect risks.
Stakeholders who understand the regulatory regime can very
Feasibility Phase: During this phase, design guidelines will be
easily delay the approval process if their concerns have not been
defined and project-specific design standards will be compiled.
satisfactorily addressed. Many proponents and contractors dis-
Critical initial design drawings will be produced, including plot
count the potential environmental risks associated with their
plans, process flow, piping, and instrumentation and utility dia-
projects, whereas others may consider these issues only when it is
grams. At this time, the proponent may also develop the prelimi- too late in the project’s schedule to turn back. To understand
nary specifications of major equipment and obtain estimates for better the methodologies required to detect potential environmen-
prices and availability of equipment. Based on this information, a tal risks, one must first understand the type of risk that the project
preliminary schedule may also be produced in conjunction with a may be exposed to.
revised cost estimate.

Planning Phase: This phase advances the work on all fronts,


Direct Environmental Risks
including
• Design;
Direct environmental risks arise from issues that emanate from
• Procurement planning;
the project or aspects of it. An analysis should be undertaken so
• Construction planning; that environmental issues specific to the project are understood,
• Definitive cost estimates; and the associated risks mitigated if possible. Many project teams
• Execution plan and schedule; and will hold brainstorming sessions, which can bring to the table
• Regulatory compliance terms. those environmental issues that may pose a risk to the project. It
The work done in this phase prepares a basis for making the final is imperative that team members understand the project to under-
decision to proceed with completion of design, procurement, stand adequately the risks involved. Table 1 lists some typical
construction, and operation. In case business conditions have risks that are associated with medium- to large-scale construction
changed, it affords the opportunity to confirm that the project projects.
should indeed be carried to completion before expenditures accel- Referring to Table 1 and the left-hand portion of Fig. 1 共direct
erate with the placement of large orders for materials and equip- risks兲, each issue can be taken through the process of determining
ment and the start of construction. its potential risk to the project. For example, if it is known that
one or more phases of the project may create excessive dust, it
Design/Implementation Phase: This phase covers all the over- should be looked at in greater detail. Is there a receptor that may
lapping phases of final design, procurement of equipment, con- be affected by excessive dust? Is there a pathway that could in-
struction, and commissioning of the project. These include troduce the dust to the receptor? If the project is undertaken in an
completion of drawings, equipment specifications, standard speci- urban center with a dense population, there is definitely a poten-
fications, operating instructions, and solving design-related prob- tial receptor present. Consequently, many proponents would con-
lems arising during construction and startup. clude that there is a potential risk to the project that is associated
Each of these project phases allows the proponent the oppor- with the creation of excessive dust.
tunity to reflect on the project details to date, understand the im- The determination of whether the issue poses a risk is consid-
plications of moving forward, and use the opportunity to make ered risk identification. If there is no risk that the particular issue
changes as necessary. However, the key to a successful project is will affect the public, wildlife, or the environment, then the
proper and complete up-front, proactive planning. The key con- project team can move on to the next potential issue or move the
tributors to budget and schedule overruns on large-scale projects project along to the next phase. However, if it has been deter-
may include the following: mined that a potential risk exists, the proponent must apply some

PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2005 / 261

Pract. Period. Struct. Des. Constr. 2005.10:260-266.


Table 1. Typical Direct Environmental Risks of Construction Projects
共Chen et al. 2000兲
Issue Source Receptor Possible mitigation
Dust Excavation Public Wet excavating
Drilling Wildlife Wet drilling
Blasting Environment Chemical breaking
Transportation Covered loads, wet loads
of aggregates
Vehicle traffic Dust suppression on roads,
restricted routes and hours,
cleaning equipment
Concrete Precast goods
Downloaded from ascelibrary.org by CLEMSON UNIVERSITY on 06/02/14. Copyright ASCE. For personal use only; all rights reserved.

mixing
Demolition Static crushing
Noise Demolition Public Static crushing
Various Wildlife Hydraulic or electric
equipment/ alternatives, restricted hours,
machinery noise barriers, prefabricated
Fig. 1. Environmental risk management flowchart
materials import
Odors Solvents, Public Solvent-free materials,
paints Wildlife powder coating, the best available technology to eliminate levels that would
prefinished materials occur in a business-as-usual case. For example, if the contractor
Welders Bolt or pressure connections declares that he or she will replace diesel-engine powered
Equipment Properly tuned engines, equipment with electric motor driven equipment 共wherever
exhaust electric motors, newer possible兲, stakeholders may be willing to accept a noise level that
equipment, emission controls will be considerably less than if the contractor had used the diesel
Asphalts/tars Reduced transport distance, engines.
in-place mixing These are, of course, only a couple of relatively simple ex-
Light Area work Public Restricted work hours, amples of direct environmental risks. Direct risks will be specific
lights spot lights rather than to each project, its stakeholders, and its location.
flood lamps
Equipment Wildlife
lights Indirect Environmental Risks
Waste Solid Public Reuse, “made to fit” rather
than off the shelf generic Indirect environmental risks are those that may be influenced by
Wildlife the project but are not necessarily a direct result of the project.
Liquid Environment Recovery/recycle, powder For example, the construction of a roadway or the excavation of
coating, water diversion soil for footings or a foundation may result in the release or
from work-site exposure of previously contaminated materials. These materials
Gas Vapor recovery were not caused by the project, but their influence to impact a
receptor 共public, wildlife or environment兲 may be a consequence
of the project. Proponents need to understand the potential indi-
form of risk management. This management can take one of two rect environmental risks that they may be liable for during the
forms: implementation phase of their project. To do so, indirect risks
1. Eliminating the risk completely, so that there is no potential should also be identified during the planning phase. In most cases,
of negatively affecting stakeholders or the costs of indirect environmental risks will be minimal in com-
2. Eliminating the risk partially, to a level that is acceptable to parison to the budgets of most medium- to large-scale projects.
stakeholders. Well-planned projects that have accounted for potential risks
As an example of completely eliminating a potential risk, if the can greatly reduce the chance of budget and schedule overruns.
project team had identified excessive construction lighting as an Conversely, projects that do not account for potential environ-
issue that could potentially affect stakeholders, they may opt to mental issues are more prone to delays and extraordinary costs. It
work only during suitable daylight hours. This choice may mean is therefore recommended that project proponents take a more
sacrificing a shorter schedule, based on the time of year and lo- proactive approach and perform assessments of the potential in-
cation of the project. However, the improved stakeholder rela- direct environmental risks that may impact their project, so that
tions, and subsequent acceptance and ease of regulatory permits, upfront planning may reduce potential catastrophes.
may offset any construction delays. The reader should reference the right-hand side 共indirect risks兲
If we use noise as an example of an issue that could impact of Fig. 1 while reviewing the following section.
stakeholders, it can be seen that option number two would be the To determine if a potential indirect environmental risk is asso-
only reasonable risk management solution. It would be all but ciated with the project, a thorough assessment of the project lands
impossible to eliminate elevated noise levels caused by drilling, and surrounding area should be undertaken. In Alberta, Canada,
excavating, blasting, or demolition equipment. However, stake- this process is known as a Phase 1 Environmental Site Assessment
holder input may reveal that they are willing to accept elevated 共Phase 1 ESA兲, and it should follow the guidelines set out by the
noise levels if it has been demonstrated that the project is using Standard Council of Canada document Z768-01 共Alberta Envi-

262 / PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2005

Pract. Period. Struct. Des. Constr. 2005.10:260-266.


ronment 2001兲. It is highly recommended that the project propo- Key factors in determining the feasibility of complete elimination
nent enlist the services of an independent third-party environmen- include
tal consulting firm that has had previous experience dealing with 1. Logistics of treatment or disposal options
large projects. • Equipment access;
During Phase 1, the investigator will perform a desktop re- • Weather contingencies;
view, a site visit, and personal interviews. The desktop review has • Location of existing infrastructure and surface improve-
three purposes: ments 共i.e., roads, buildings, city storm water or sewage
1. To obtain information about current and historical land uses lines, etc.兲; and
and activities; • Geological, hydrological and/or hydrogeological factors.
2. To identify potential sources of contamination; and 2. Feasibility of treatment or disposal options
3. To establish the framework for subsequent site investigations • Location of waste disposal site relative to project site
if necessary. 共transportation costs兲;
The desktop review typically involves the review of available • Fees associated with final disposal of material 共landfill,
Downloaded from ascelibrary.org by CLEMSON UNIVERSITY on 06/02/14. Copyright ASCE. For personal use only; all rights reserved.

records 共regulatory, landowner, and so on兲 pertaining to the site land treatment, incineration, etc.兲;
and interpretation of aerial photographs and maps. This review is • Area available for treating materials on site 共only applies to
usually followed by a site visit, which verifies the information contaminants that can be biologically, thermally or chemi-
gathered during the desktop review. Typical components of the cally treated兲;
site visit include a review of the surrounding land use, topography • Timeframe available for treatment of contaminated materi-
and vegetation; location of surface water bodies, water wells, and als; and
so on; potential sources of leaks, spills, or releases; visual evi- • Availability and cost of suitable materials to backfill the
dence of on-site and off-site contamination in addition to equip- excavation in the case of off-site disposal.
ment; and infrastructure or underground utilities that may be af- This option will have to be evaluated together with the data col-
fected during a subsurface investigation. The site visit includes, or lected from the project site. There is no template that works for all
is followed by, interviews with present and past landowners of the contaminated sites. Costs for removing contamination can range
site and the adjacent properties of the project area. from a few thousand dollars to hundreds of millions of dollars,
The outcome of Phase 1 will allow the proponent to determine depending on the extent and type of contamination present.
whether there is a potential indirect environmental risk associated
with his project. In the simplest of cases, where there is no po- Reduce the risk to an acceptable level: The proponent or con-
tential 共or it is very unlikely兲 for an indirect environmental risk, tractor could take a risk-based approach in dealing with a con-
the proponent can move to the next phase of the project. How- taminated site. The risk can be reduced to a level that is accept-
ever, where there is the potential for environmental risk, the pro- able to both the proponent and the regulator. This can be achieved
ponent should do further investigation before making any critical by managing one or more of the three components of risk:
decisions. Results of the Phase 1 ESA would naturally lead to the 1. The source of contamination;
implementation of a Phase 2 Environmental Site Assessment 2. The receptor of the contamination; and
共Phase 2 ESA兲. 3. The pathway that introduces the contamination to the recep-
The purpose of the Phase 2 ESA is to determine the presence tor. Looking at this option in more detail, the following op-
and extent of any contamination suspected as a result of the Phase tions may be available to the proponent or contractor:
1 ESA. This investigation is typically intrusive, requiring soil • Manage the contamination source;
and/or groundwater samples to be obtained and analyzed for sus- • Remove all the material;
pected contaminants at an accredited environmental laboratory. If • Remove the most heavily impacted material only;
the suspected contamination is verified to be present during the • Treat the impacted material in situ 共if feasible兲;
Phase 2 ESA, the proponent will be required to manage the po- • Leave all impacted material in place;
tential environmental risk. Investigators can usually determine an • Manage the receptor of the contamination;
estimated volume of impacted materials, the endpoints of con- • Remove the receptor 共e.g., replace a domestic water well
tamination on the site, and the likelihood of further impacts from with another alternative兲;
migration of contaminants. From this information, estimates for • Treat the receptor 共e.g., chemically treat a water body兲;
various remediation or risk alternatives can be developed. • Restrict access to a receptor site;
The proponent must evaluate the data obtained from the Phase • Do nothing with the receptor;
2 ESA and determine the potential environmental risks. If there is • Manage the pathway;
no contamination, there is no risk, and the project can move to the • Install a physical or chemical barrier around the contami-
next phase. There is also the possibility of discovering contami- nation to keep it in place 共e.g., bentonite slurry wall, bell-
nation that does not pose a potential risk, and again the project holes, or pumping culverts兲; and
can move to the next phase. If there is contamination present at • Remove the pathway 共e.g., ditches, culverts, water bodies,
levels that could potentially cause harm to a receptor, however, geologically permeable materials, and so on兲.
the proponent must manage the risks accordingly. Another way of reducing the risk associated with contamina-
Managing environmental risk is a process in which the project tion is to determine the contaminant level that is acceptable from
proponent must work together with the regulator and, where ap- a receptor standpoint. That is, reduce levels at the source so that
propriate, the stakeholders. Two options available for dealing with once the contaminant reaches the receptor, it has been reduced to
the risk from contaminated sites are the following. acceptable levels. For example, a site contaminated with high
levels of salt 共e.g., road salt storage yard兲 may have heavy chlo-
Eliminate the risk: Probably the best method for reducing future ride ion impacts within the site boundaries. However, because of
risk is to completely eliminate any contamination that is currently water flushing of the ion in the soil matrix as the ion travels
in place. However, this option may also be the most expensive. toward the receptor, those levels may be drastically reduced over

PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2005 / 263

Pract. Period. Struct. Des. Constr. 2005.10:260-266.


a short distance. In this case, the most heavily impacted material premiums cannot be determined without investigating the con-
could be removed, leaving the rest of the contamination with the tents of coverage.
expectation that it would be reduced to acceptable levels by the The following simple case studies provide further justification
time it reached the receptor. for purchasing some form of environmental insurance:
The simplest of cases will involve no indirect risks at all, and • Soon after the development of a subdivision, small sinkholes
will be most common when projects are implemented at sites began to appear around people’s homes. The sinkhole also
where very little or no development or activity has taken place in produced some unspecified debris. Fearing that the debris
the past. On the other end of the scale, projects that occur on or could also be under their homes, the owners brought a lawsuit
adjacent to existing industrial or commercial properties face the against the contractor. Because the contractor could not iden-
greatest potential of encountering indirect environmental issues. tify the owner of the debris, they were forced to clean it up at
a cost exceeding $1 million.
• A contractor in a residential area was overseeing the installa-
tion of a sewage system. The subcontractor responsible did not
Downloaded from ascelibrary.org by CLEMSON UNIVERSITY on 06/02/14. Copyright ASCE. For personal use only; all rights reserved.

Environmental Insurance
properly tie the sewage line in, resulting in the contamination
of groundwater and nearby domestic water wells. The contrac-
Whether or not the project scope entails detailed environmental tor was forced to pay over $425,000 in legal, property damage,
assessment work to uncover indirect or direct environmental and bodily injury claims.
risks, it is in the contractor’s and proponent’s best interests to • During fill operations for a subdivision project, a contractor
obtain some form of environmental insurance. Environmental li- unknowingly spread hydrocarbon-contaminated soils across
ability insurance comes in many forms and can protect all parties the project site. As the contractor was found guilty of exacer-
involved from incurring extraordinary costs that may arise from bating the clean-up effort, he was forced to pay $250,000 in
unknown, or unaccounted for, environmental risks. The following remedial and legal costs.
outlines some of the more common types of environmental insur- Though some contractors or proponents may view environmental
ance, and the benefits they may provide: insurance as a good way to finance a loss, it is always best to
• Pollution liability insurance covers the insured against third manage the exposure before loss. A highly publicized environ-
party claims such as clean-up expenses that may occur as a mental disaster can have a catastrophic impact on an organiza-
result of the insured’s work. This insurance can cover onsite tion’s reputation. While the insurance may eventually pay for the
and offsite cleanup costs and claims for cleanup, bodily injury, loss, provided proper limits of insurance were purchased, nothing
and property damage, including legal defense costs, related to will pay for the loss of an organization’s reputation 共Slivka 2002兲.
preexisting known and unknown pollution conditions and fu-
ture pollution conditions.
• Environmental errors and omissions liability insurance is typi- Risk Transfer
cally used by consulting or engineering firms to protect them-
selves from liability arising from work or recommendations Contractors and proponents can also reduce their exposure to en-
made by the insured. vironmental risk through risk transfer. This is usually in the form
• Environmental remediation insurance covers the insured of indemnification clauses within contractual agreements 共Slivka
against liability claims arising from pollution generated on 1998兲. The contractor must negotiate indemnification language
and/or migrating off property. This type of insurance usually into the contract that prevents the contractor from being held
covers investigation and remediation costs. liable for preexisting contamination. However, it is essential to
• Stop loss (cost overrun) coverage is normally used when there have a copy of an environmental assessment identifying existing
is known contamination before the insurance policy comes contamination to create this clause. To further protect a contractor
into effect. This type of insurance involves a substantial de- from identifying or discovering previously unidentified contami-
ductible that typically covers the costs of remediation plus any nation, a change in Conditions Clause could be used 共Slivka
cost overruns. At this point 共the Stop Loss amount兲, the insur- 2003兲. This contractual clause will enable the contractor to make
ance covers the remainder of costs. appropriate contract modifications in the event that contamination
• Spill liability provides coverage for bodily injury, property is discovered at a later date.
damage, and cleanup costs resulting from an incident during As contractors face potential liability as a result of subcontrac-
transportation by a carrier of the named insured’s product or tor actions, they should also give attention to contractually con-
waste 共McCaffery 1997兲. trolling this liability. Many prime contractors will carry some
The coverage and the premiums for the above insurances are form of environmental insurance, but there are usually little re-
dependent on many factors, applications and the type of the quirements for their subcontractors to do the same.
project. Applicants are required to submit their case to insurance
underwriters to evaluate the project before the insurance under-
writers determine the premiums. For example, the availability of Construction Industry Survey Results
certain hazardous materials on site may increase the risk and
thereby the premiums. In Canada, the premiums also depend on To better understand the environmental risk-management mea-
the province. A rule of thumb premium amount for Environmental sures actually employed by industry in western Canada, a brief
errors and omissions liability insurance is about $3.00 per $1,000 survey was conducted. A questionnaire was developed and dis-
coverage in Canadian dollars. Pollution liability insurance pre- tributed to 15 construction companies operating in Western
miums may vary—from $3,000–$10,000 for a coverage of Canada. Follow-up telephone calls were made, and ten companies
one million Canadian dollars depending on the nature of the provided responses. This section outlines the questions that were
coverage and the contents of the materials involved. All the other asked in the survey and summarizes the answers given by the
insurance types identified above are specific to a project and the various companies.

264 / PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2005

Pract. Period. Struct. Des. Constr. 2005.10:260-266.


Of the ten companies that provided responses, there was a spondents were unable to provide any kind of figure for this ques-
wide range of both size and services provided. Companies ranged tion. However, 30% also stated that impacts had generally been
from having approximately ten employees for a local excavation less than 1% of the overall project budget or schedule. Likewise,
company to thousands of employees for larger national compa- another 30% indicated that costs or delays to their projects had
nies. Services included excavation, road construction, residential been between 1 and 10%. One respondent stated that unforeseen
construction, commercial and industrial construction, and project environmental issues had impacted their project budget by 10–
management and engineering services. Company representatives 20%, although the exact figure had not been determined.
included project managers, safety professionals, general manag- Is there a system for tracking and closing project risks? This
ers, and engineers. The following questions were asked of each
question was directed towards finding out if companies were
company representative.
using databases or similar products to track identified environ-
Does your organization have a dedicated risk management
mental issues until they had been satisfactorily managed. Forty
group? Only 30% of respondents indicated that they have a dedi-
percent 共40%兲 of companies indicated that they do have such a
cated in-house risk management group. Surprisingly, two of the
Downloaded from ascelibrary.org by CLEMSON UNIVERSITY on 06/02/14. Copyright ASCE. For personal use only; all rights reserved.

three companies with in-house risk management are smaller, local system in place, while the other 60% stated that they do not.
companies. Others indicated that they do not have an in-house Where a tracking system has not been developed, company rep-
risk management group, and that this work is usually carried out resentatives indicated that individuals responsible for a particular
as part of the project team, or the services of a third party con- issue would track its mitigation progress using their own meth-
sultant is used when necessary. ods. These methods varied from a spreadsheet, Gantt chart, or
Do you consider the potential environmental risks or issues notepad depending on the individual and magnitude of the issue
that could occur during a project? As expected, 100% of the or project.
respondents indicated that environmental risks are considered as Are risks assigned to specific people in your organization?
part of the project. Depending on the type of issue encountered, 70% of respondents
Do you use a guiding document when determining severity of indicated that identified issues are assigned to one or more indi-
risk? Respondents were split 50/ 50 on this response, as half of viduals for management. The other 30% indicated that the project
them indicated that they do use a guiding document to rate the team, as a whole, would manage any issue that might arise. Two
severity of an identified risk, whereas the other half indicated that of the respondents indicated that issues could be managed better
they do not. Guiding documents varied from internally prepared as a team, rather than an individual.
documents to consultant-supplied guidelines. Do you carry environmental insurance as a risk-management
Is there a particular magnitude of project where these risks tool? Fifty percent 共50%兲 of respondents were unsure whether
would normally be considered (i.e. would you consider environ- their company carried a form of environmental or pollution-
mental risks only for projects such as those with large capital liability insurance. In most cases, this uncertainty was because
budgets)? Ninety percent 共90%兲 of companies indicated that they
insurance was handled by a separate legal, joint-venture, or ac-
do not have a predetermined project scope for initiating risk iden-
counting department and such matters were not discussed by the
tification. Respondents stated that any project could be subjected
project teams. Three of the respondents indicated that they do
to risk identification provided sufficient reason to warrant review.
There was one company that reviewed potential environmental carry environmental insurance of some form, but were unable to
issues only when the project’s capital budget exceeded $250k. provide details as to type of insurance carried. Two companies
Are project schedules prepared so that contingency is in- stated that subcontractors who were physically performing the
cluded? Sixty percent 共60%兲 of respondents stated that project work carried environmental insurance.
schedules did contain contingency for unaccounted environmental In summary, the following has been determined from the con-
risks. Others indicated that the subcontractors have the responsi- struction industry survey:
bility to adjust their schedules accordingly. • Most companies do not have a dedicated risk management
Are stakeholder risks included in this process of risk identifi- group in-house;
cation? Although 20% of companies indicated that they do not • The majority of companies surveyed consider environmental
consider potential risks to stakeholders, 80% of respondents and stakeholder risks;
stated that they do consider such risks. • Most companies consider these risks during the planning
At what point in the project schedule would you consider these phase of a project;
environmental/stakeholder risks? One company indicated that en- • Most have experienced cost and schedule overruns from un-
vironmental issues are only considered when they are encoun- foreseen environmental issues;
tered. In other words, there was no up-front planning involved to • There have been varying degrees of impact to the original
mitigate potential issues. Conversely, the other 90% of companies budget and schedule;
indicated that potential environmental and stakeholder risks were
• Risks are usually assigned to one person individual to mitigate
considered during the preproject planning phase.
potential impacts;
Have you experienced impacts (financial or schedule-related)
• Only half of the companies have a system to rate the severity
from unknown or unforeseen environmental issues that arose dur-
ing a particular project? Although 20% of companies have not of potential impacts to the project;
experienced budget or schedule overruns from unforeseen envi- • Almost half of the respondents do not have a contingency built
ronmental issues, 80% of respondents have dealt with them first- into their project budget or schedules;
hand. Most of the eight companies that have dealt with overruns • Over half of the companies do not have a formal system in
have experienced these issues on more than one project and with place for tracking identified issues and management options;
varying degrees of impact. and
What was the approximate cost or delay as percentage of the • Most of the companies do not carry, or do not know if they
overall project budget or schedule? Thirty percent 共30%兲 of re- carry, any form of environmental insurance.

PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2005 / 265

Pract. Period. Struct. Des. Constr. 2005.10:260-266.


Conclusions agement model as an essential deliverable that the contrac-
tors need to submit for approval before construction begins
This study shows that there is a need for the development and to optimize the resource requirements, waste minimization
implementation of an environmental risk-management frame- strategies, innovative construction practices, and to predict
work. This paper outlines some of the measures that need to be “life cycle costs and benefits.”
considered before implementation of a construction-type project. 3. Development of a mandatory contracting strategy that evalu-
Results of the survey indicated that while many companies are ates environmental needs as a new dimension in selecting
concerned about the possible implications of environmental risks successful designers and constructors considering sustainable
to their project, there still needs to be more emphasis on identifi- design and construction practices.
cation and mitigation of these risks. There are few widely ac-
cepted guidance documents or frameworks currently in place
for use by individuals or companies wishing to use information. References
Downloaded from ascelibrary.org by CLEMSON UNIVERSITY on 06/02/14. Copyright ASCE. For personal use only; all rights reserved.

Many companies have developed their own methods for de-


Alberta Environment. 共2001兲. “Phase I environmental site assessment
termining and mitigating environmental risks; nonetheless, sur-
guideline for upstream oil and gas sites.” 具http://www.3.gov.ab.
vey results indicated that project managers are still looking for ca/env/protenf/soilgrndwater/document/phaseIAssessGuideforO&Gas
a better methodology to quantity the impacts to the project’s bot- Apr01.pdf典 共April 1, 2003兲.
tom line. Chen, Z. Li, H., and Wong, C. T. C. 共2000兲. “Environmental management
It is therefore recommended that further research be conducted of urban construction projects in China.” J. Constr. Eng. Manage.,
toward the development of a universal environmental risk man- 126共4兲, 320–324.
agement framework. This research would best be conducted McCaffery, M. 共1997兲. “Emerging options in environmental insurance.”
through extensive industry surveys to determine the needs of both Pract. Period. Hazard., Toxic, Radioact. Waste Manage., 1共3兲,
the construction industry and the regulators involved. Some of the 105–106.
current initiates of the writers in this regard are: Slivka, J. M. 共1998兲. “Environmental exposure.” Civ. Eng. (N.Y.), 68共9兲,
53–55.
1. Development and validation of a comprehensive project risk
Slivka, J. M. 共2002兲. “The environmental risks of residential construc-
management framework and a user-friendly computer tool to tion.” International Risk Management Institute, 具http://www.irmi.com/
encapsulate environmental and sustainable development is- expert/articles/slivka008.asp典 共April 1, 2003兲.
sues, its impacts on the project and to develop practical ac- Slivka, J. M. 共2003兲. “Managing environmental liabilities, through con-
tion plans to mitigate impacts. tracts.” International Risk Management Institute, 具http://
2. Development and validation of a computerized waste man- www.irmi.com/expert/articles/slivka009.asp典 共April 1, 2003兲.

266 / PRACTICE PERIODICAL ON STRUCTURAL DESIGN AND CONSTRUCTION © ASCE / NOVEMBER 2005

Pract. Period. Struct. Des. Constr. 2005.10:260-266.

You might also like