Vi-Ik-Eq - En-31-00 Ik For Build Up Raised Faced (31 - 37)

You might also like

You are on page 1of 1

No. Dok : VI-IK-EQ.

EN-31-00
WORKING INSTRUCTION FOR BUILD UP RAISED No. Rev : 00
FACED (CS-GTAW) Date : 17 Apr 2018
Hal : 1 dari 1

Welding Process: GTAW

Job Description BUILD UP Welding Code : ASME Section IX


Material Standard A105, A216 WCB or Equivalent
Material Thickness Refer Drawing Joint Design : BUILD UP
Filler Metal Standard SFA 5.18 Joint Orientation : FLAT
Filler Metal Classification ER70S-G Welding Current : DCEN
Filler Metal Tradename TGS-50 or Equivalent
Shielding Gas Argon 99.9% Flow Rate : 10 - 20 Ltr/mnt
Wire Speed N/A
Reference WPS 002/WPS/ASME/CS/OVERLAY/VI/2015

Welding Current Arc Voltage Travel Speed


Run No Electrode Size (mm) Heat Input (kJ/mm)
(Amps) (Volts) (mm/min)

1-n 2.4 60 - 150 10 - 20 90 - 120 0.30 - 2.00

L
O
Joint Detail Sketch Welding Sequence
Welding to increase surface
TR
(Based on drawing)
1. Start welding from
middle
N
O

2. Continue welding to
C

outer side until all


grey side filled
N
U

Heat Treatment: N/A (Slow Cooling)

Pre Heat: As per AS 4458 Table 10.1 (12-25mm=Ambient),(25-50mm=80°C)


(Over 50mm=125°C)
Notes:
1 Use 2.4mm thoriated tungsten
2 Close tube of welding rod after using to prevent contamination from dust and othe contaminant
3 Ensure area to be welded is free from any grease , paint , oil and other contaminants.
4 Erect baricades to ensure area is protected by draft or windy conditions to allow adequate
gas coverage where necessary.

Dibuat Oleh: Diperiksa Oleh: Diketahui Oleh:


Welding Engineer QC & Eng Manager Ops Manager General Manager Direktur

Haposan Edward Harry D.H Tunggul P. R. W. Royke Rompis Indra Cayadi

VI-IK-EQ.EN-31-00 IK FOR BUILD UP RAISED FACED ( 31 - 37)

You might also like