Professional Documents
Culture Documents
(C. V. J. VARMA)
Member Secretary
NEW DELHI Central Board of Irrigation and Power
(i)
,
\
(R. RAMASWAMY)
Member lD & R)
Central Water CommiSSion
CONTENTS
PAGE
F9REWORD (i)
CHAPTER 1-Introduction 1
CHAPTER 2- Definitions and Notations 16
CHAPTER 3-Investigations and Data Required 21
CHAPTER 4- Location and Alignment 27
CRAP'IER 5-Planning and Layo~t 31
CHAPTER. 6-Hydraulic Designs 65
CRAfTER 7-Structural Designs ~Q
......
..
•
CHAPTER 1
Introduction
1.0. Diversion of the river waters is achieved by the to regulate the water surface level and pattern of flow
construction of barrage or weirs across the river. The upstream. It is distinguished from a weir in that it
diversion of water may be required for purposes of is gated over its entire length and mayor may not
irtigation, hydro electric power, drinking water have a raised sill.
supply or industrIal water supply inCluding cooling
waters for thermal power stations, navigation, inter- 1.3. The diversion structures are located in the
basin transfer of water or combinatioll of any of following four regions viz., (i) the mountainous or
these. torrential (ii) the sub-mountainous (iii) the trough
and (iv) the alluvial and deltaic. Locating the
1.1. The objects of constructing a barrage or weir for structure in any of these regions has its own advan-
the required purpose are : tages and disadvantages. These are discussed
below.
(i) The water level in the canal is required to be 1.3.1. The torrential of mountainous region is suitable
at a calculated level so that it may be able to for locating a diversion structure required for hydel
command by flow a particular area to be power schemes due to the availability of high heads
irrigated or for feeding the power station, and less siltation problems. However, so far as
etc. structures required for irrigation schemes are concer-
ned, the mountainous and sub·mountainous regions
(ii) The full supply level of water required for this have both advantages and disadvantages as detailed
purpose can be obtained only if the river is in Table 1.1.
tapped at a considerable distance upstream of
the command area. To reduce the idle length 1.3.1.1. It would thus be seen that in the case of
of canal before it starts serving the area, the mountainous and sub-mountainous regions, the
water can be tapped at a lower point subject disadvantages outweigh the advantages of having a
to suitability of site by construction of a structure there. However, if it is necessary to locate
barrage or weir and having a suitable pond it in these regions only for any other reason, then the
level. structure will need to be designed and constructed
properly so that maintenance problems are reduced to
(iii) The fluctuation in the supply level in the the minimum, if not altogether eliminated.
river can be reduced.
1.3.2. While the above listed disadvantages are
(iv) Sometimes it may be necessary to store small absent in the structures located in trough, alluvial and
quantity of water for tiding over small periods deltaic regions, they have further advantages such as
of short supplies For this, storage weir uniform tlow, lesser percolation losses, more fertilising
or barrage with small storage can be had. material· in the water. etc. However, proper silt
excluding measures at the headworks will need to
(v) To have better control over silt movement be incorporated wherever necessary.
and to channelise the river to a permanent
course, diversion structures can be provided. 1.4. Whenever any diversion scheme is thought of,
the possibility of having a weir should be first consi-
1.2. Hence, a weir may be defined as an ungated dered. Only when it is proved that it is not economi-
barrier across a stream to raise the water level in the cally or otherwise not suitable. the barrag' should be
stream. Similarly, a barrage may be defined as a considered. Due to the cost of gates, etc., the cost of
barrier provided with a series of gates across the river barrage is normally more than that of a weir.
1
2
TABLE 1.1
Advantages and Disadvantages of having barrage/weir in Mountainous
and SUb-lDouDtainous Regions.
" .
Advantages Disadvantages
(i) Water will be silt free (i) There will be problems at the head works due
to shingle. Proper arrangements for excluding
shingle at the headworks will have to be
made.
(ii) Due to availability of rocky bed' at shallow (ii) Since service area will (start after some dis-
depths. less foundation problems and hence tance from the headworks, the idle length of
lesser cost. canals wilJ be more.
I'
.r (iv) Due to steep siopes in the regions; the canal
will have to be aligned with more number of
fans.
"
. (v) Due to rolling of boulders, etc., there is likeli-
hood of damages to the pier noses and wea-
ring surface of the floor.
r.4.1. While work.ing out the preference for a bar- (;) Vertical Drop Weir
rage or weir at a location the following points given (ii) Slope weir
in TABLE 1.2 in their favour need to be consi-
dered. (a) Solid masonry weir.
(b) Rockfill weir.
1.4.2, Aftet considering the advantages and dis- (e) Glacis type weir.
adyantages, the type of structure i.e., baJ[~ge or weir
may be decided. " (iii) Ogee or Parabolic type weir.
(iv) Buttress weir.
i .5. According to the u~age, the weirs can be classi- ,(v) Crib weir.
fied as diversion weir, storage- weir, waste -Weir and
pick-up weir. According to the r profile, the weirs can (vi) Syphon weir.
be divided into the following types: (vii) Trench type of weir.
3
TABLE 1.2
Barrage Weir
Advantages
(i) Due to low crest of the undersluice and (0 Where the natural banks are high enough to
spillway, the afflux created on the UIS by the contain the. affluxed water within the banks or
barrage is usually small. when only low flood protective bunds would
be necessary, a weir would be economical.
(ii) With barrage, betrer control over the river (ii) Due to the provision of gates only in the
flow can be effected by judicious operation of sluice bays, the operation would be easier
c the gates. and cost of the structure would be less. Wher-
ever needed, the pond level could be con-
veniently raised by falling shutters up to about
2 metres.
Disadvantages
(;) Cost of barrage is higher than that of a weir (i) Control over the river flow cannot be had
generally. fully as in the case of barrages.
1.5.1. A short description of the different types ill Ilcour and keeping the pond upstream in the imme-
presented below for information and their suitability diate vicinity of the weir clear of silt deposit.
or otherwise for particular conditions indicated. The
various types l indicate the development of weir 1.5.1.2. Slope Weir. In slope weir, slope is provided
sections. iJ;lvariably on the downstream of the crest and on
upstream also wberever needed. In this type of weirs,
1.5.1.1. Vertical Drop Weir. Vertical drop weir con- the jet of water remains in contact with the ,weir all
sists of a vertical masonry wall called weir or crest the way. This type of weir is best suited where
wall or body. In this type, the jet separates from the sliting of the pond is not desired and large size
weir at the crest and falls freely on the downstream pebbles and even boulders are likely to roll down the
apron. This type of weir is usually suitable in sub- weir. This can be conveniently constructed on soft
mountainous regions and particularly suitable for low sandy foundations like those in alluvial region. The
falls unless it is founded on solid rock. This is suited three different types under the general classification
for hard clay and consolidated gravel foundation. of slope weirs are discussed below.
Generally, rectangular or trapezoidal section'S are
used. The crest is given a small rising slope of say 1 1.5.1.2.1. SOLID MASONRY TYPE
in 12 (See Figure 1.1). Tbis diverts the stream leaving
the weir in lIpward direction which has a double The solid masonry weir consists of a body wall, pucca
action of creating a back roller that deposits silt on apron on the upstream. pucca sloping masonry apron
the downstream side rendering the weir safe against on the downstream and talus on both the upstream and
4
downstream. Th.is type of weir is usually constructed on required slopes on the upstream and downstream side
fioe sand foundation. In some cases, sloping aprons with a few walls across the flow which make it more
with one or more curtain walls are also provided. stable in the event of partial failure. The downstream
This type can be aGopted in all conditions except slope is generally made very flat with the object of
at sites where the vertical drop is more than 5 metres. leading the current gradually and providing sufficient
(See Figure 1.2). length of creep through the bOulders. The principles
of design of snch type of weirs are not definitely laid
1.5.1.2.2. ROCKFILL TYPE down. As the water is free to release its surplus
energy upwards in this type, uplift pressures need
After the name implies, boulders are laid to the
New puddle
1·5:1 + 170'58 Sheet pi Ie
+ 169·18 + 169-91 GUIde pile
-Flow
85
1--_
91~
_"_0__.. , f-
. o.
l~----='
2:...:...19=-.:5=--_ _.. 1
I in 10
H
1830 (All dimensions in mm
and elevations in m)
-rr.
BAITURNEE WEIR SECTION
Rubble masonry
COI>C block lets 610 x3SOx610 Khoronjo stone coarse 395 Pile casing I 2 4
tone masonry blocks 1525x610x61O Hoop iron Cement concrete blocks 1220 x610xl220
-Cement conc.blocks 1220x610x1220 Slone masonry blocks 915x510x610
fn 1370 dry brick boxing +2140 Alternate bricks and
+213- .' " . conc blocks 610x380x610
-, ~ '~' ~ ; ~ \ : ; I. :, ' : ,." =- - :;:
.. :..--:~~.--::.~~ _
~ -" r Concret~0'35 :.: Rubble in pure lime 6400 I
LBose line ofcms,' :;: .rga~'85
4575. 5795 wall 0059' pipe O·glon •• .
vertically in conc. ',:--Pure lime
of all comportments
and 1.5 m cenlre
r---- 12195 .1 1
'
2135
I 13110 ~
_I
I: 53050
77440
• \. 24390 -I
C~OSS SECTION OF RASUL WEIR SHOWING REMODELLING BAY NO.51~31l±2..46'34
, . fR'1.ln~OrCed cement conc.0·3U:2;3Z ~~~~51 ~
• . ~ordrnary cemenl cone .o.g --
Lime conc. blocks I Sdin 4 Slope- J I
+240.83 n ~ ~+241'4Ir +240." __ 11:4:7:12) n5 +792 ·10
+240·32
+217'9l)
. Curtain wall
840 D.5. pitching brick work'"
grouted stone '-Triangle
1 1220 of dry stone Nole-
Ul
.0\
~
1220
:--------27440 J 27440 •
S=/In 20
+ IR7.42
~
1220 19l5 Z';220 2:1220
1220' .
1----12 I95--clS1--9145 ,. 12195 I 42685 1
.:tJ~.1fi~~x~~5 t~~~~~~rn~~1~6~8~0~~S~=~II~n~12b==....-.:t~~2L
+ 99'39 Original river bod
Po eked sand stone rubble
I 17380 .j
~
M.R.L
1525 ,1525
.. _---.., J 25195 t J-- 19205 ... 8230., 21340---1
ron ~12 09
Second CDran
Third apron
L.oose slonll apron
Depth of stone apron is irregular
i'" 16·5
1830
..-.l
H.F.L+ 35·82
1220-. -
(1220
..l'!IRw 18290 I
+.28'96 ~.~13720----,-l
-l .....
I in IS
+28'35~EB:sa!h""JIII'1i
ROQ'~
i J ~f9QI~"kll&~
"'29'57 11,,12,5 ~
,1220'
--ol
+29'88
-4
00
/'- .FLOW
H F'L. 149 ~4
I \;.t.a.
H [ .. 0 . 46 Pond le...el-H50·0
±;F,~
-R C.C_I:~:.q tOOS Ihll:.). QV'''' 230
I:JI,O·C.C \ I~ 8 C C Blocks
over-SIDloDSS stons
H\13<29
.. 14.2-68
a(l!ia~!o.~ O,;ll!.r;IJ'l
-tJ4,2:·68·
_Cl 'tr4t"6 ~ "+14"F:lg
Re,C 12~4 lOf::ithlck G'm":~XJI.3~
, II 20l2O----" ...... ~'~1~4a ---:--l
t!3HS
-;;tJ4'~
EMERSON
C.L.ofRood\YcJy --....
.FL0W
Afflux b1=IQ4·12
Pond L + 102·9
PUNJNAD
H.E.l+ 174·39
. _ Pond le\1ol+17317
flOW.
Cr.,t R.l,+11O·73
",,\n 5
1'418
SULE IMANKI
i220'
1---1219.5 .,.j--1l940--j I-- 8310 I 21340 IA~" I •
C.C. blo"k' 1220" 1220lC840wilh RC,C,I;2:4 .305thl~k
10 jhori,s over 6101000' stone . 510"GIOx510
+205'03 nn +
'.: •. _ 0"._.1: l-;":,.:~.:".", .....
+?02'74 +201·93 , --;::If20t·83 LJf202'13 ~~9
-l I- I
152. 1 5795 ,lrf0~7315----; 7 92S --l
''+-198'78
(An di"mensions are in mm and
KALAilAGH elevation ore in metre.,
10
10
not be considered. The rockfill on the upstream required to pass the design discharge with permissible
side may become impermeable in course of time by afflux will be lesser.
the deposition of silt and sand into the voids. This
type of weir is particularly suitable to low differences Typical examples of Ogee and Parabolic shaped
of water levels between tbe upstream and downstream weirs are given in Figure 1.5.
where velocities generated by the fall may not be
excessive. It is also more suitable for mountainous 1.5.1.4. Buttress Weir: Solid ~'masonry weirs require
regions. a considerable amount of building material which acts
essentially only by its weight, whereas the strength of
The rockfil1 type of weirs constructed in India are material frequently is bardly utilised ·at all. Where it
founded on all types of foundations like sandy, clayey, is very difficult to procure these materials including
and rocky. Rockfill weirs are the oldest type in India transportation difficulties, the buttress type of weir
and are often remodelled by increasing their lengths or originated by Ambursen may be employed to advant-
introducing curtain walls upstream and/or downstream. age since consid~rably less material is required for the
The large quantities of stone required both at the same.
time of initial construction and subsequent refilling due
to sinkiog, etc, preclude their use in many cases except
where skilled labour and mortar are not available and An Ambursen weir consists of water-tight facing of
stone can be obtained economically. slabs resting on a series of triangular buttress. If a
strong sound rock foundation exists, each buttress is
From Figure 1.3, indicating typical rockfil1 founded separately. On a weaker or soft foundation,
weirs, it may be seen tbat in the case of Krishna and it may be desirable to place all buttresses on a com-
Sangam Anicuts, the body walls and curtain walls mon R.C. Slab or mattress. The buttresses of high
have well found3tions carried to a considerable depth weirs are braced with R C struts On a rocky founda-
below the river bed. It may be economical to grout tion, the seepage under the weir is prevented by means
the interstices of the body wall with concrete. How- of a concrete cu t- off I to 2 m deep at the heel of the weir
ever, this has to be done:very carefully so that uplift In loose soils, sheet piles are driven both at the heel
pressures and consequent damages are avoided. and toe to safeguard against scour and undermining.
Weep holes in the foundation slab, protected by in-
1.5.1.2.3 GLACIS TYPE verted filter at the bottom would permit the escape of
any water which may have found its way past the
Glacis type of weirs also referred to as Khosla's type, upstream sheet pile line and protect the slab against
finding adoption now with the solutions for design are uplift. The weir is either provided with a deck only
increasingly of weirs on permeable foundation propoun- on tbe upsfream side and flood waters are allowed to
ded by Dr. A.N. Kbosla and otbers. A typical section fall freely over the crest or it is constructed as a slope
of this type has upstream and downstream glaci- and weir with a downstream face. The angle of upstream
horizontal floors in continuation of the glacis. Two and deck with the horizontal is usually between 38° and
or more piles lines, one each at the upstream and 45°. Near the Crest of the weir, air holes are necessary
downstream and some intermediate piles if found neces- to destroy the partial vacuum created there.
sary are also introduced .. The floor may be of gravity
type or reinforced cement concrete raft type. Typi- The design principles of bottres.. weirs are stmilar
cal examples of Glacis type of weir are given in to buttress dams. The weight of the deck of one
Figure 1.4. bay and the water pressure on one bay are added to
the weight of the buttresses. [f the friction between
1.5. \.3. Ogee Or Parabolic Type Weir: If the sheet weir and foundation!: is insufficient to prevent sliding,
of water passing down tbe creat of the weir does not foundation slab! with ribs may be provided or sheet
adhere to the surface of the weir, the likelihood of piles driven to hold the weir securely. }
damages caused due to the partial vacuum created
between the welT surface and the lower nappe of water The material required for a buttress weir may be
is more. Hence it is always desirable to sbape the 60 percent Jess than that for a gravity weir. However,
crest and the downstream face corresponding to the tbis saving may be offset by much higher unit price of
profile of the lower nappe for the design flood. The R C.C., but the horter construction period for
shape of the falling jet over a sharp crested weir has Buttress weirs may decide the issue. Buttress weirs
become a I'tandard form called the Ogee shape. Some- are economical only for heights more than 5 m.
times, a parabolic shape IS also adopted, where
generally a bucket is provided at the toe for the
formation of hydraulic jump to dissipate the surplus Typical Buttress weir sections are indicated in
energy. These types are suitable for greater heights Figure 1.6.
of weirs on impermeable foundations like Tock or fum
clay. As the coefficient of discharge in the ca~e of 1.5.1.5. Timber Weir: Timber weir, as the name in_
Ogee type is high the lesgth of such a type of weir dicates, i.e., construeted with timber. Considering
1 - - - - - - - 19510 1
------1
I
reo' 0' roo'~'
E:.L 272'26
r 5.l. 2.59-76
M.W L 260·67
-----=:~::::::::.::::
1+-5945---1
---
Flaw
(
E L 247'56
21800---::;,.....---~/
~
#/1 o
Ol
N
4495 ':!!
I
I
1
~oo~~· ~~~
_ f-_.~~,. ~,.;v""'_-~...,"""'''':~'''~~-n-da-f;_"a~~,''''"m--
:
.. ,7; .'tK••
..... - - """",, J
\~525
-----I 10-----
1-o..__------------·46495--------------o..j..,
.I..
Flow
::r-'--_. --~-----------
o
f
o,..,
F
=-,r Tropezoldol
apron sill
-
Flow
101
Flow
-
0·10
18xlS 0·IOxQ-18
iTruss pile
Sheetpih"9
Flow
Flow
Crest cap-_~
rCapPlng p,ec~
Low water
\Hi9 h water I -!-
~Izr:* -
=-=---..g~
~. i /
I/.I,t
~.
Crest capl ~ "In II ~
/ I . "'v
L rlI .L J- VJ
,dI('I
• Sheet pit in9-r- I"
~
•
W,~ VI/'
k""~ I
·Capplng plece ~:...- ,
Sectional elevation" sheet piling ~
A Section A A
r1 E1 .J
,
I"... ~I
...... t:--:.
:~
I I
q
;J,
(j
I
I
I
-"
I
I
I
I I
, J I
I I
I
I
I I
I
A Plan
A wooden slope weir
I O.~
~ROC~k'"t~~~~
~
• -If-61..- -
t""
F,"xed weir schnalser creek (All dimensions ore In metresl
1.9. After the necessary investigations are carried out or R.C.C. -raft. A baTrage usually comprises the
and data collected, it is very important to locate the components like sheet pile or concrete cut off, pucca
diversion structucture at a satisfactory alignment. floor, piers, divide walls (provision depending on the.
Chapter 4- Location and Alignment discusses these necessity or otherwise). abutments, f1.ankwalls, .return
aspects. walls wherever necessary, .river training" works where-
ever necessary. hoist bridge and hoist, upstream and
1.10. As against different types of weirs, barrage are downstream Pucca protection and loose stone pro-
gated structures built across the rivers for diverting tection, silt excluding arrangements whenever needed.
water for various purposes as enumerated in Para 1.0. etc. Wherever necessary, road and/ot: rail bridge
Usually vertical steel gates are provided .for the opera- . would be provided over the barrage.
tion. A barrage could be constructed of stone maso-
nry or concrete and this can be either of gravity type 1.10.1. At the alignment chosen for the structure
•
14
either from the data collected and with the help of called fish pass in the form of a ladder or lock. The diffe-
preliminary model studies, the structure has to be rent types of fish pass, their location, designs, etc., have
properly laid out. This includes the location of abut- been discussed in Chapter 3, Volume II-Fish Pass.
ment, head regulator, undersluice, river sluice, divide
wall spillway, flank walls, guide bunds, protection 1.16. With Indland Navigation gaining importance
works, etc., by proper planning. A layout found satis- now, it is necessary-that the possibilities of having suit-
factory for a site may not be suitable for another site able arrangements at the barrages and weirs sh.oul j be
due to the various conditions obtaining there. Accord- explored to cater for navigation facilities wherever prac-
ing to the satisfactory hydraulic performance of ticable and potential for it exists Chapter 4, Volume II
the structure, the layout will have to be decided and Navigation Facilities deals with the details of navi-
model experiments in this regard come in as a helping gation Jocks and channels and other facilities like
band. The various considerations involved in plan- jettys, slipways for repairs, etc.
ning a proper layout are set out in Chapter 5-Planning
and Layout. 1.17. The purpose of a barrage or a weir is to divert
the required amount of water for purposes of irriga-'
1.11. As already mentioned, the designs of the struc- tion, power generation, domestic and industrial water
ture are done in two stages, viz., hydraulic and struc- supply, navigation, etc. The diverted waters are fed
tural. The various parameters calculated in the into the canals through properly designed head regu-
hydraulic designs alongwith the principles involved ]ators where regulation over the sijpply of water can
thereof are discussed in Chapter 6-Bydraulic be effected. The considerations invol '!ed in location
Designs. and design of head regulators are discussed in Chapter
5 Volume II-Head Regulators.
1.12. Once the parameters of the various com-
ponents are fixed and are confirmed by hydraulic 1.18. The control over the flow of water through the
model tests, the structural designs of the various com- barrage and head regulator is effected by properly
ponents of the barrage or weir are carried out. designed service gates. For repair and maintenance
Chapter 7-Structural Des igns deals with the princi- of the servict: gates, certain emergency measures like
ples involved in their designs. ' stop logs are required. For prevention of floating
debris getting into the canal through the head regu-
1.13. Rivers carry suspended silt and some rivers lator and causing damages to the power plants in the
carry even shingles and boulders. Unless these are case of power generation schemes, arrangements at the"
effectively excluded from the flow into the Canal head regulator like trash racks are required to exclude
through the head regulator, the canal capacity will be the floating debris. Chapter 6 Volume II-Gates,
reduced, impairing the diversion scheme. Silt carried Stop]ogs and Trash Rack describes in short the various
through the head regulator into a power canal may type3 and design cons~derations on this aspect.
affect the turbine blades of the hydel power generating
plant. Due to various reasons, the pond may get
shoaled up and unless these are effectively r~moved, 1.19. Based on certain principles and considerations
the diversion scheme may itself become unless in as would be discussed in relevant Cbapters of this
course of time. ,Hence the importance of silt and Manual, the layout of the barrage or weir is prepared
shingle excluding devices in a barrage or weir has to and designs are carried out accordingly. But there
be properly understood. These are discussed in are a number of complex factors which cannot pro-
Chapter 1 Volume II-Silt Exclusion. pelly be visualised. Hence aid of model experiments
is invariably taken now-a-days to evolve the optimum
1.14. As a component of the barrages and weirs. design which is hydraulically and structurally sound
river training works are generally needed to guide the and econonmical, ensuring a satisfactory performance
river to f1Qw axially through the barrage or weir and of the structure. The data required for laying the
to check the outflanking besides providing favourable hydraulic model before testing, the various terms of
curvature of flow at the head regulator from the point reference for the hydraulic model tests, and their
of preventing sediment entry into the canal. The river utility, etc; have been discussed briefly in Chapter 7,
training works are generally 'in the form of guide Volume II-Mode] Tests.
bunds, spurs or groynes, approach and afilux embank-
ments. Chapter 2, Volume II-River Trainiog~Works 1.20. The designs of barrages and weir are based on
deals with their layout, design considerations, etc. certain principles, both empirical and derived. How-
ever, due to various parameters involved, the designs
ITs. ' For the development of pisciculture in some @f may sometimes be oversafe or deficient in some res-
the barrages and weirs, arrangements for migratory pects. For thi~, jf tbe performances of these parameters
.fish to move from upstrem 10 downstream and vice are known tb rough some means, the desi.gns can be im-
·..er a have to be made. This is required fr<ilm environ- proved upon, both for safety and economy. Jnstrum~n
mental considerations which is necessary from the tation plays a good part in this. Chapter 8, Volume
socio-economic point of view. The arrangement is 11- Instrumentation deals briefly with the diffGrent
15
, instruments that could be conveniently installed in the selected site. The effect on the regime of the river has
diversion structures for collection of data and analysis been discussed briefly in Chapter 11, Volume II.
thereof.
I 24. In spite of the best efforts for a safe design and
1.21. The various comiderations for sound construc- g00d construction, due to unforeseen parameters like
tion ofthe diversion structure are detailed in Chapter flash flo,ods, bad or poor operation, maintenance etc.
9, Volume II-Construction. sometimes there do occur failures of barrages and
weirs. The different causes for damages and the data
required to be collected in such cases for further ana-
1.22. Even a well designed barrage or weir may pose lysis and remedial measures are discussed in Chapter
problems leading to failures if the operation and main- 12, Volum!, II-Failures of Barrages and Weirs.
tenance of the structures are not done promptly and
properly. Inspection of barrage or weir is necessary 1 25. For building a safe structure, it is also neces-
to obviate the possibility of prevention and/or exten- sary that materials', of good specifications are only used
sion of damages. Regulation of the gates before, dur- and strict quality control is maiotain~d.
ing and after monsoon has to be carefully planned and
carried out. It is also very important to keep a tiistory 1 26. Due to climatic conditions '=aud nature of the
of the headworks to .know about the behaviour and sites in which the diversion structure is located, there
overall performance, repairs carried out, etc. All might arise some special problems. These may occur
tbese aspects are discussed in Chapter 10, Volume II during construction and design stages also. Some
- Maintenance and Operation. special problepls usally faced in diversion structures
are discussed in Chapter 13< Volume II.
1.23. When a barrage or weir is constructed across
a river, it is to be understood that the natural flow of 1.27. This Manual on Barrage and Weirs is not an
the river is being interferred with and due to this, there· exhaustive one. Only the different aspects related to
will be a change in the regime of the river which is the diversion structures have been discu'>Sed in a con-
lik~ly to cause aggradation or retrogression of tbe bed cise manner. For a detailed. study of all the aspects,
aild.conseq:uences thereof, etc. Hence before; p!¥lDjng the reader is advised to refer different text books,
a barrage OT weir. it is also necessary to s.tuo.y the publications, standards, papers, etc. For convenience,
effect of tbe struoture on the regi me 0f the river ich a sbort Bibiolgra:pby on the subject which will be of
will help in designing the structure safely at a properly use to the reader is presented in Chapter 14, Volume II
."
•
..,
• f.
.. I I •
..
CHAPTER 2
2.0. Introduction itself and is constantly building its flood plain by over-
flowing.
In this Manual on Barrages and Weirs, a number of
terms relating to the di!>cipline of diversion structures 2.1.6. Apron
and also a number of notations are used. While these
have been explained in the relevant paras where they
occur, most of them have been compiled and given in A protective layer of stone or other material'
this Chapter for convenience of study. provided in the bed of the river where it is desired
to prevent erosion,
2.1. DefinitioDs
2.1.7. Backwater Curve
The various terminologies adopted in this Manual
have the following definitions. The upstream longitudinal profile of the surface
of water in a stream or conduit from a point where
2.1.1. Abutment such water surface is raised above its normal level by
a structure such as a weir/barrage or dam.
Retaining wall constructed at the end of the water-
way of barrage/weir to retain the backfill, protect the 2.1.8. Barrage
banks from erosion, support load from superstruc-
ture and confine the flow to the desired waterway A barrier provided with a series of gates across
at the structure. the river to regulate water surface level and pattern
of flow on the upstream and for other purposes,
2.1.2. Afflux distinguished from a weir in that it is gated over its
entire length and mayor may not have a raised sill.
The difference in water level between upstream
and downstream of a barrage/weir under free flow 2.1.9. Bay
condition as a result of const'Rlction of the structure
on the river. One of the main divisions of the diversion struc-
ture such as spillway, undersluice, regulator, etc., bet-
2.1.3. Afflux Bund ween two piers or a pier and abutment or a pier and
divide wall.
An embankment or dike designed to ensure that
the structure is not outflanked during flood flows 2.1.10. Bed Material
and in :iiOme cases acting as embankment to prevent
flooding of the country side due to rise in water
•
The material, the particle size of which are found
level. in appreciable quantities in the shifting portions of
2.1.4. Aggradation of Level the bed.
An increase of rise in specific levels of the bed 2.1.11. Block-outs
(the bed level at specific discharge) of a channel at
any site. Temporary recesses provided in the civil structrure
to facilitate proper embedment of steel fixtures f~r
2.1.5. Alluvial River gates. trestles. etc., and which are concreted after theIr
A river which flows through deposits created by fixing.
16
. 2.1.12. Boulder Stage of River
.17
A layer or combination of layers of graded per- A graph showing the stage, volume of flow, velo-
vious materials designed arid placed in such a manner city, sediment concentration or sediment discharge or
as to provide drainage and yet prevent the movement some other feature of flowing water with respect to
of soil particles with seepage water. time at a given place.
2.1.31. Fish Ladder/Lock 2.1.41. Looseness Factor
Device provided in tbe diversion structure to The ratio of the overall length of the weir/barrage
facilitate the passage of fish from upstream to down- provided to theoretically computed minimum stable
stream and vice versa. width of the river at the design flood obtained by us-
ing Lacey's equation.
2.1.32. Free Board
2.1.42. Meander
The vertical distance between a specified water sur-
face and top of the component of a structure under A meander in a river consists of two consecutive
consideration. loops, one flowing clockwise and the other anticlock-
wise.
2.1.33. Friction Biock
2.1.43. Modulus of Subgrade Reaction
Staggered R.C.C. blocks provided 10 the stilling
basin for energy dissipation. The load distributed on unit area of an elastic
medium which creates unit deflection.
2.1.34. Froude Number 2.1.44. Pier
The dimensionless number obtained by dividing Concrete or masonry structure constructed over the
the mean velocity by propagation velocity of an infini- waterway for supporting bridge decking, gates and
tely small surface wave (the square root of the product hoist operating mechanism.
of the depth and the acceleration of free fall).
2.1.45. Pitching
2.1.35. Glacis
A protective covering of properly packed or built-
The sloping protion of the floor upstream and in· materials on the surface of the earthern sides (side
downstream of the crest. pitching) to protect them from the action of water.
2.1 36. Gauge-Discharge Curve 2.1.46. Pond Level
The curve indicating the various stages of the The level of water immediately upstream of the
river for different values of discharge. barrage/weir required to facilitate withdrawal into the
canal or for any other purpose.
2.1.37. Guide Bund
2.1.47. Regime
A protective and training embankment constructed The condition of a stream or its channel as regards
at the side of a weir/barrage to guide the flow through their stability.
the waterway. .
2.1.48. Retrogression of Level
2.1.38. Head Regulator
The lowering of specific bed levels of a channel.
A structure built upstream of the diversion struc-
ture to divert, control and regulate water supplies from 2.1.49. River Slucies
the pond. A set of sluices similar to the undersluices located
in between the undersluice and spillway bays and se-
2.1.39. Hydraulic Jump parated from them by mean of divide walls.
The sudden and usually turbulent passage of water 2.1.50. River 'J'raining
from low level below critical depth to high level above
critical depth during which the velocity passes from Engineering works mel uding artificial plantations
supercritical to subcritical. (with or without the construction of embankment)
19
built along a river or section thereof in order to direct 2.1.60. Stone Reserve
or to lead the flow into a prescribed channel.
A quantity of stone kept as reserve on guide bunds,
2.1.51. Scour spurs or groynes for emergency use to prevent deep
scour occurring and endanger the safety of the struc-
The removal of material from the bed of a channel ture.
by flowing water.
2.1.61. Stoplogs
2.1.52. Sediment
Fabricated structural steel or wooden units utilised
Fragmental material transported by, suspended in for temporary closure of any bay of the barrage or
or deposited by a flowing channel without any regard regulator in order to facilitate repairs of the gates and
to size. other components of the bay.
A slow movement of water due to capillary action The flow in which the Froude number is less than
through pores and interstices of unsaturated packed unity and surface disturbances can travel upstream.
soil material into or out of a surface or subsurface
body of water such as river, canal, etc. 2.1.63. Super Critical Flow
The flow in which the Froude number is greater
2.1.54. Sheet Pile than unity and surface disturbances will not travel
upstream.
Steel sheet pile provided to cater for cut-off,
scours, etc. 2.1.64. Toe wall
•
20
2.2. Notations D1 = Depth of water before hydraulic jump
The notations indicated below have generally been D2=Depth of water after hydraulic jump
adopted unless mentioned otherwise: Ef1 = Energy of flow just upstream of the
point of formation of standing wave
a=semi-major axis of ellipse (See Chapter
on River Training Works). E/ 2 =Energyof flow just downstream of the
point of formation of standing wave
b = semi-minor axis of ellipse (See Chapter
on River Training Works). HL = Head loss, i.e., difference between the
upstream and downstream total energy
D=maximum anticipated scour depth line values
below water level assumed at low water
level (LWL)/Floor Va=Velocity of approach
21
•
22
area, augmentation of the river supplies from another 3.2.1. Detailed Topographical Survey
basin if necessary including ground water mpplies
and the diversion structure itself for its safety and For detailed topographical survey, the following
economy. Hydrographs at the selected site should be are required to be carried out:
prepared indicating the discharge during different
months so that the minimum and average discharge (a) An index map of the area has to be prepared.
during different months are assessed. Normal and This should show the catchment of the entire river
maximum flood discharges should also be assessed for valley upstream of the selected site and should also
the design and regulation of the barrage. show salient features like important irrigation works
in the vicinity, road and Iail way crossings, hydrologi-
3.1. 5. Assessment of Water Requirement
cal stations, wet and dry fields, gardens, temples,
It is necessary to make an assessment of the water grave-yards, villages, etc., which may come under
requirements including possible future demands for submergence if any due to the pond created. The map
irrigation, hydro power, drinking or industrial supply may preferably be drawn to a scale of 1 in 4000.
etc" 50 that the head works could be suitably designed
with the necessary feeding levels. This will also help (b) A contour plan of the site of barrage or weir
in planning for the conjun(;'tive use of surface and sub- has to be neatly prepared. The contour interval
surface water available in the service area. should not be more than O' 5 m and should cover
elevation of at least 2'5 m above the high flood level.
3.1.6. Availability or Construction Materials The contour plan shall extend to about 5 km on the
upstream and downstream of the site and upto an
The type of structure aud economics thereof at adequate distance on both the flanks upto which the
the different sites for locating the head works or diver- effect of pond is hkely to extend. The plan should
sion structure would depend on the availability and clearly indicate salient features like tributaries and
quality of the construction materials in the vicinity of their confluence with the river, firm banks, rock out-
the sites. Hence a correct assessment of the same is crops, deep channels, large shoals and islands, deed
necessary. pools. important land marks, marginal erosions, etc.
The length of survey may depend on the configura-
3.1.7. Communication to the Site of Work tion of [he river. This could be shortened or increased
While the choice of the final site fOI locating the depending on the straight reach or meandering nature
structure should be made mainly from considerations of the river. In case of meandering river, the length
of engineering aud geology, due consideration should of survey should cover at least two fully developed
also be given for communication works for easy acees- of the axison
meanders the upstream and one of the downstream
sibility apd economic transportation of materials to preferably bethedrawn
of diversion structure. The plan may
to a scale of 1 in 4000. The
the site of work. requirement of survey lengths for detailed model
studies is discussed in the chapter on Model Studies.
3.1.8. Climate of the Region
As the water availability, evaporation and cons- (c) Cross-sections of the river have to be taken at
truction techniques and period to be adopted depend the axis of the barrage or weir at the proposed site
on the climatological variations of the region in gene- and at regular intervals, both on the upstream and
ral and the work area in particular, data regarding the downstream of the axis. The interval shall be
climate of the region needs to be studied. 200 m upto at· least 600 m from the proposed
site. In addition to these, cross sections of the river
3.2. Detailed IDv~s.tigatioDs On the upstream side may be taken at 2 km intervals
up to the distance to which the back water effect of
From ·the analysis of the dada obtained during ponding is likely to extend. The intervals for taking
Preliminary Investigations, the final selection of the the cross section may be reduced if the topography
site for locating the diversion structure with its head iudicates appreciable fall in the river slope. The
regulators can be judiciously made. For collecting cross-levels in the river bed may be spaced at 10 to
the data necessary for the design of the structures at 30 m depending upon the topography of the river.
this site, detailed investigations need to be carried out. The cross-sections should generally be extended on
These should cover (i) detailed topographical survey both the banks upto about 2.5 m above the high flood
(ii) collection of hydrological, sediinent and evapora- level. It should be such that a proper layout of guide
tion data (ifi) surface and sub· surface investigations bunds aud afflux bunds, wherever necessary, could be
including laboratory tests (iv) diversion requirements planned. In billy streams, the cross-section intervals
(v) construction·materials (vi) communication system should be closer. The requirements of cross-section
and (vii) other miscellaneous studies. These are dis- and longitudinal section in respect of model studies
(;USicd in the following paras. are discussed ill the chapter on Model Studies.
23
(d) Longitudinal section of the river along the It would be useful to present the hydrological data
deep current should be' taken for a distance of about availability for various years· in the form of
5 km on tbe downstream side and about 15 km on the a histogram.
up streams side. If the back-water eHect is likely to
extend beyond 15 km longitudinal section should be 3.2.3. Sediment Data
taken upto that distance. 'The water levels observed . For planning sediment excluding and/or ejecting de-
all along-the section should be marked on the section. VIces at the headworks· and in the canal system and to
evolve a suitable gate regulation for satisfactory sedi-
3.2.2. Hydrological Data ment exclusion, it is necessary to have data on the sedi-
The success or otherwise of the diversion scheme ment load carried by the river for as such period as
depends to a great extent on the accuracy and avail- possible. It is required especially for the flood seaSOD
ability of hydrological data. These are required for when the sediment carried will be more. If DO data on
assessing tbe available weekly and monthly Iun-off sediment is available, sediment observations should be
and for computing the flood for which the structure started immediately along with gauge and discharge
has to be designed. For these purposes, it is very observations at the site to assess the quantity and
important to collect the following data for further quality of sediment carried in ttc river. The sediment
studies. sampling should be done as per standard practice. If
the quantity of sediment brought by the river is
(a) Daily rainfall data of all rainfall gauging sta- excessive, the pond levels have to be :fixed carefully
tions in the catchment area and also around taking the sediment data into account. This is
the catchment area wherever available. The especially important when the pondage is proposed to
f data should be collected for as many years as be provided to meet diurnal power fluctuations also.
possible. Data regarding storms in respect of
successive positions of the centre of the storm 3.2.4. Evaporation Data
on the catchment should be collected. Storms Evaporation is an important factor to be considered
causing peak discharges should be separated while working out the water requirements of the crops
for unit hydro graph analysis. . and hence the diversion requirement. The available
(b) For working out unit hydrogrph, flood hydro- data on evaporation by pan measurements, etc. should
graphs for isolated rain storms are to be be collected and analysed.
collected.
3.2.5. Surface and Sub-surface Investigations including
(c) If adequate :data is not available, synthetic Laboratory Tests .
hydrogral'h has to be developed. FOI this
purpose, catchment characteristics, such as For proper design of the diversion structure and
shape, slope, orientation, drainage systems its components, it is very necessary to have a
and infilteration capacity will have to be complete picture of the surface and sub-surface con-
collected. ditions. These are required both for decidine the
(d) For working out the design floods by frequency type of structure to be provided and also its mety.
analysis. peak flow data for the river for as The foundation may be of rock or alluvium and de-
many years as possible should be collected. pending on the same, the investigations may be differ-
ent. These are discussed below :
(e) Daily stage and discharge data of the river at
or near the site for as many years as possible (a) Bore holes should be driven at specified inter-
should be collected. The data should cover vals covering the entire area of the barrago or
both monsoon and non-monsoon periods. In weir and its appurten1lnt structures, and the
case the gauge and discharge data at the pro- location of these bore holes should be indica-
posed site are not available, the hydrological tad clearly in· the survey sheets. Correct log
observations at the site should be immedi- charts are to be prepared clearly. The borings
ately started so that the calculated and obser- should be generally carried out to hard rock
ved values could be correlated. Two gauges level or to a depth of about 15 to 25 m below
on the upstream, one at the axis and two on the deepest river bed level depending on the
the downstream may be set up for this pur- strata and type of structure. The bore holes
pose. All the gauges should be connected to should be at the rate of at least one in each
the nearest GTS Bench Mark and observa- bay proposed. If possible, two bore holes ill
tions carried out as per standard practice. each bay, one at the upstream cut off and
another at tbe downstream cut off, shonld be
(f) For working out a gauge· discharge curve and obtained. When the presence of clay in the
also to estimate maximum flood by slope-area foundation is detected. these are, however.
method, the flood marks in the vicinity of the ess@ntial so that the extent, depth and location
site should be re.corded by local enquiries. of the clay layer could be correctly assessed.
24
(b) If rocky strata is available at shallow depths, (i) Soil samples should be collected at suitable in-
trial pits may be excavated to determine the tervals of depth and their properties such as
depth of overburden, loose deposits, depth of classification, unit weight, angle ofinternal
weathered zone and extent of joints and fissures friction, void ratio, specific gravity, grain size
so that necessary function treatment for pre- distribution, etc., should be determined by
venting excessive seepage loss, etc., can be sieve analysis and other laboratory tests.
worked out.
(j) Wherever clayey strata is encountered, un-
disturbed samples of the clay layer should be
(c) Wherever the depth of overburden i~ large and obtained, one from the proposed foundation
comprises large size boulders and it is difficult ltvel and another 5 m below the foundation
to have ordinary boring methods, geophysical level for each bay. These samples should be
investigation needs to be carried out to 10ca1e analysed to determine the cohesion, unconflned
the rock surface. compressive strength, moisture content, dry
density and sensitivity and conl'olidation
(d) Wherever impervious layers are encountered, characteristics.
the direction of its boundary i.e., horizontal (k) Wherever clayey strata is proposed to be
or sloping up towards the downstream or treated by means of sand drains or stone
upstream should be ascertained. An imper- columns, coefficients of permeabilities and
vious boundary sloping up on the downstream consolidation should be determined in the
will cause constriction of seepage. This needs vertical as well as radial directions.
to be avoided by shifting the location of the
barrage or weir slightly upstream. (/) Observations of water table in the vicinity of
the barrage or weir sile should be carried out.
(e) If the river bed consists of boulders or is made Tbe effect of higher pond levels leading to
up of stiff soil, feasibility or otherwise of rise in water table with consequent water log-
driving sheet piles to act as cut offs must be ging in tbe adjacent areas and the attendant
invesligated properly. problems thereof should also be investigated.
(m) Field permeability tests should be carried out
(j) If .piers or abutments are to be designed with to assess the extent of seepage losses from the
reID~orced ce~ent concrete pile foundation, pond and thereby the dewatering require-
bearlDg capaCIty of the piles should be deter- ment.
mined by driving test piles before finalising
the design of the pile system, at sites where 3.2.6. Diversion Requirements
the bearing capacity of the soil is low at
shallow depth. The quantum of water that is required is to be diver-
ted through the barrage or weir has to be determined.
(g) In sandy strata, standard dynamic and static For this purpose, det~i1ed studies of th~ command area
penetration tests should be done below the cropping paltern. drarnage water reqUirements at the
position of each structure like abutments
piers, djvid~ walls, centre of each bay, etc.:
farmly outlets, any supple?Jentary source or
water, eva-
poration losses, percolatlOD l~sses, r.eqUlreme~ts .for
for eshmatlDg the beaIing pressures, likely power, drinking water snpply. LDdustnal uses, upanan
settlement and necessity of settlement joints, rights etc., have to be made. The full supply level at
etc. For boulder slrata, plate bearing tests the head regulator has to be worked out.
should be done. The depth of penetration
may be at least half the bay width of the 3.2.7. Construction Material
barrage or wefr. The interval may be decided
depending on the strata encountered. The type of structure which can .be ~c~nomica1lY built
at the site will depend on the avaIlabIlity of construc-
(h) Wherever the main floor of the structure is to tion materials in the vicinity. Hence a detailed survey of,
be designed as an R C.C. raft supported on an the materials like stone, limestone, bricks, sand, gravel
elastic medium, in situ tests for determining suitable earth etc. bas to be made with regard to both
the modulus of sub-grade reaction at the quantity and qualit~ of the same. The lead and lifts with
proposed foundation level should be conduc- necessary transport arrangements will also have to be
ted. If there is a wide variation in the pro- found out. Laboratory and field tests should be
perties of the foundation material, the length carried out for determining the quality of aggre~~tes
of the structure should be split up into suitable and earth materials. For lime stone, its bydrauhclt.y,
sections i olated from each other by means of strength and durability have to be assessed. 1.t IS
double piers and the modulus of sub-grade preferable to prepare a map indicating the quarrIes,
reaction must be determined at every section. approach roads, colonies, etc. for a proper assess
25
ment of the available construction materials. Com- bridge, data regarding the type of bridge, width of
parative estimates of the type of structure will have to roadway, foot-paths, class of loading and other facili-
be made depending on the eassy and uninterrupted ties lighting, pipe·lines, cable ducts, h~nd rails etc.,
supply of the required quantity of quality materials. should be collected. In the case of a rail bridge,
data regarding the gauge, line of traffi~, etc. need to
3.2.8. Communication System for Access to the Site be collected in consultation with the railway au-
thorities.
Investigations will have to be carried out regarding
the elristing communication facilities like railways, 3.2.9.5. Data Relating to Ice Problems. There
roadways, navigation, telecommunications etc., at the may be cases where ,barrages or weirs have to be
site of work If some of the facilities are going to be constructed in high altitlfdes where the problem
dislocated due to the proposed work, their relocation of ice formation exists. For proper safe design of tl;le
wiJl have to be thought of. Also additional facilities structure including the operation of gates where de-
required both during construction and operation will icing facilities have to be provided, it is necessary to
have to be investigated and provided for. collect data regarding the ice thickness, maximum
and minimum temperatures and rate of variation of
3.2.9. Other Miscellaneous Studies temperature.
In addition to the investigations mentioned in the 3.3. Environm.ental Considerations
foregoing paras, it is necessary to make some more im-
portant studies which win have a bearing on the designs. In addition to the various considerations discussed
Some of tbese are pond sUTvey, ush pass, log chute, rail/ in the ioreg iog paras, another important considera-
road bridge across the barrage and data relating to ice tion on environment is gaining ground now. This has
problems. It is also necessary to make a survey of also to be rightly looked into. The planning, cons-
the construction colonies and labour camps which truction and operation of irrigation, hydroelectric /
should be nearer to the site of work with easy acces· multipurpose projects have considerable impact on
sibiJity. navigation, fish culture, wild life, recreational aspects
and overall ecology of the affected regions. Some of
3.2.9.1. Pond Survey. The upstream area whicb will these aspects on the ecology of the region as well
be submerged by the normal pond and the area within as the overall environment are irreversible in
the affiux bunds which will have to be acquired due to nature. It is, therefore, neces;ary that.a careful
the construction of the barrage or weir will have to be evaluation is made of these impacts, whether good or
surveyed. Details of tbe immovable properties coming bad, before the project is undertaken. Necessary
within the same should be recorded and their values measures should be planned well in advance to miti-
assessed before the works are started so that any gate, wherever feasible, the adverse impacts. The
disputed claims arising later could be settled without minimum surveys and investigations required on these
difficulty. are indicated below.
3.2.9.2. Fish Pass. In some of the barrages or weirs, 3.3.1. Fish Culture
arrangements for migratory fish have to be made. These
are called fish passes eitber in the form of ladder or This is already disoussed under para 3.2.9.2.
lock. The type, layout etc, of tbe arrangement need to Some restrictions may also have to be imposed on
be finalisbed in consultation with the concerned Fis· fishing in tbe project areas. Owiog to the diversion
heries Department. Necessary data in this respect of water into the canals, there may be modification in
should be collected. flow patterns and quantums along the rivers/channels
and their effects on fishing downstream should also be
3.2.9.3. Log Chute. In some of the barrages or weirs, evaluated. Measures should be identified to reduce the
there may be Dfcessity of providing log chutes. To jus- quantity of the trash fish and at the same time increase
tify the necessity for the same, data regarding their num- the availability of quality fish in the affected areas.
bers, sizes, periods of handling, cost of handling and
other relevant data thereof should be collected and 3.3.2. Wild Life Habitat
analysed.
A survey plan of the areas likely to oome under
3.2.9.4. Rail/Road Bridge Across the Barrage. the pond which could be constituting as encroaoh-
Wherever communication facilities are to be ex- ment on wild life (fauna) babitat as a result of the
tended from one bank to the other, it is usually and proposed structure should be made. This may not
economically combined with a barrage. It may be a be applicable in the case of barrage/weir structure
road bridge or a rail bridge or both combined. Neces- as in the case of storage dams. However, it would
sary data regarding the same are to be collected for be worth investigating the special importance if
designing the structure and also tbe barrage itself over any to wild life in their annual/seasonal migration.
which the bridges are carried. In tbe case of a road Necessary details regarding rehabilitation if any, and
26
waterlogging problems which might affect wild life impact of flood problems, salinity of the flow in the
due to the pond should be worked out in consultation river channel and other similar ecological factors
with the appropriate department of the State Govern- should be thoroughly investigated.
ment dealing with forest and wild life. Hydraulic stmctures provide the scope for aug-
3.3.3. Historical and Cultural Repercussions menting manifold the water-based recreation facilities
including sport fishing. Development of these should
Sites of great hhtorical and cultural imporlance should be investigated.
be carefully looked for during the investigations and
where such sites cannot be avoided, a comple!e inven- 3.3.5. Water Logging Problems
tory of these should be made. The feasibility of shifting Water-legging is the phenomenon by which the
such monuments to safe areas nearby wherever this is soil of a land is affected or damaged by too much
feasible should ~lso be investigated. Damages, if any, water and due to poor drainage. rhis may be caused
likely to be caused by the pond to the outstanding by too much of irrigation also. The inflow of
scenic beauty (flora) should also be ascertained. water in the soil by infiltration from rivers causes
3.3.4. Other Ecological Factors water-logging around the headworks. Water-
logging leads to many undesirable results such as
Large hydraul ic structures will result in modifica- breading places for mosquitoes. infertility of soil, subsi-
tion in the natural flow patterns of the rivers. The re- dence of building nearby, etc. llence this aspect has
gime of the river is likely to be disturbed. Problems to be carefully considered while planning a diversion
likely to arise due to silting/scouring in the river bed. scheme.
CHAPTER 4
4.0. Introduction the one entailing the lowest cost keeping in view both
the construction and maintenance charges.
For the successful functioning of the headworks,
proper location and alignment of the barrage or weir 4.1.3. The different items discussed b~low will serve
are very important. Various considerations are in- as guidelines in selecting a satisfactory site for locat-
volved in the selection of the site for location of the ing a barrage or a weir.
diversion structure and its alignment thereat. These are
f
discussed in this chapter. 4.1.3.1. Courses 0/ the River. The best site for locating
4.1. Location a diversion structure is in a straight reach of the river
wherein the velocity of the flow should be fairly uni~
The suitability of any site for locating the barrage form and the sectional area ofthe river fairly constant.
or weir has to be analysed from the considerations for The banks should be firm, well defined and inerodible.
the components of the barrage or weir like undersluices A narrow gorge may reduce the length of the structure
spillway and the head regulators, each one having its b~t due. to greater velocity and depth of flow, hea:
own requirements to be satisfied for efficiency. An ideal VIer sections may need to be provided. On the other
site is one which satisfies the requirements of all the hand, a wider river section may induce ~iltation due
three items. But it is very difficult to find such a site to reduced velocity besides necessitating construction
in general. Hence a balance has to be struck after of longer tie bonds.
considering the merits and demerits of what are all
available at the site. However, from the consideration of silt entry into
the canal, certain amount of curvature to the river
4.1. 1. After the commanded area has been selected, course is desirable. Due to the curvature, helical flow
the location of the headworks has to be carefully is developed and the bottom layers of silt charged
selected such that besides being nearer to the service water is diverted away from the canal off-take on the
area, the height of the structure would also be reason- outer side of the curve. When the canals take off on
able. The combined cost of the construction of the both the banks, the one on the inner side of the curve
headworks and the canals upto the commencement of will draw more silt.
the service area should be as small as is consistent with
the efficiency of the works. It has also to be seen that the course of the river
has not changed for many years at the prospective site
4.1.2. The nature of the soil through which the canals of the structure. In the case of shifting rivers, proper
will have to run with a particular location of the head- measures will need to be adopted to contain the river
works and the nature of the foundation materials at in the present course. The length of the fixed course
the location of the headworks itself will be considered of the river should be at least 0.4 times the meander
in depth before deciding about the location of the length. When this much length is not available, the
headworks. The geology of the vicinity of the site is diversion structure may be located at the nodal point.
also another important factor. While fault zones, etc.,
should be avoided as far as possible, in case no other
battle site could be found, the geological findings will 4.1.3.2. Availability of Construction Materials.
indicate the foundation treatment or any appurtenant The proposed site for locating the diversion struc-
works needed to be adopted at that site. As has ture should be in proximity to the quarries supplying
already been said, a ~ite may have a number of advan- construction materials and good communication faci-
tages and disadvantages viewed on different consider- lities between the quarry site and the barrage/weir site
ations. The best site under the circumstances would be should be ensured.
27
28
4.1.3.3. Nalllre of the River Silt. One of the than the normal width. The lengths of upstream afflux
factors that could influence the choice of the site bunds and tie- bunds should be kept minimum so that
is the nature of the river sUt It is to be deter- there is no outglanking of the diversion structure and
mined whether the silt has got fertilising properties cost of training worh is also minimum. Chapter 2
and if so, upto what proportion the entry of the of Volume H-River Training Works may also be
silt could be allowed in the head regulatOr and then referred.
down the canal in the case of irrigation project. This
may govern the selection of the straight or ourved
reach for the location. The soil through which the 4.1.3.7. Foundation Conditions. If rocky strata
canal runs should be able to withstand tbe velocity of at shallow depths is available, the foundation of
flow which can carry the silt down the canal. This the diversion structure can be had relatively at a
factor will also influence the location of the head regu- lesser cost. Even if there are fissures in the rocks
lator and thus the diversion structure. at shallow depths, proper foundation treatment by
way of grouting, etc., can be done. If the foun-
dation materials are made up of sand going to
4.1.3.4. Slope of the River. If some storage is great depth , it pre ents no pr(}blems a.s the diversion
required at the diversion structure. the structure structure can be successfully designed as per the
may ne-ed td be located in a reach where .the slope principles discussed in other subgequent chapters. If
of the river is gentle. On the upstream SIde of the impervious layers are encountered in between. proper
proposed location. jf the river slope is steeper, precautions to release built up -pressures in the sub-
then the discharging capacity of the diversion struc- strata, jf any. will need to D~ taken. On the upstream
ture wQuld be higher, but the structure will have side, the cut off's could be embedded into im-perviolls
to be deSigned to withstand.higber velocities. Steeper layer to reduce seepage pressure. OIl the downstream
slopes will restrict the length on the upstream upto side such an embedment should be avoided so that
which the effect of back water would be felt. Steeper pressures are not locked up If it is not possible, proper
slopes will mean shorter lengths of flood protective drainage arrangements should be provided.
bunds and consequent reduction in cost.
However, immediately on the downstream of the 4.1.3.8. Confluence of Tributaries The location
proposed location, the slgpe of the river should be of the diversion structure should generally be below
very flat far at least a short distance. This would pro- the confluence of the main tributary of the riv~r.
vide a cushioning effect on the jet oJflow down the However, wherever it becomes n'ecessary to locate
crest of the structure, thus protecting the foundations the structure upstream of the conflueuce due to
from scour. Further downstream a steeper slope would various other considerations. the structure should
be desirable so that the flow is drained off quickly and be located as far above the confluence as possible to
submergence of irrigable area is avoided. Eeduce the cQst Of cross drainage works. The location
of the structure in the main river with a tributary flow-
4.1.3.5. Condition of the Banks. The biUlks at thd ing parallel to the maiIl river should be avoided as
proposed location should be firm and not erodible. there would be possioilities at a later date of the main
The banks should be high so that the adjoining river breaking into the tributary and o1,Jtflanking the
areas are not submerged during high floods. Other- structure, thereby rendering it infructuous.
wise costly flood protective embankments would
be necessary. If high banks are ndt available a
reach where the high flood level jf: least above the 4.1.3.9. Quantity of Floating Debris. LocatioIi
natural ground level may be chosen subject to other of the diversion structure at reaches where the quan-
aspects being satisfactory. After some length of !he tity of floating debris carried by the river is large
canals. the grQund should have a steeper down slope so sho1.j.ld be as far as possible avoided. Otherwise
that the canal cutting which is generally heavy in the preventive measures to safely remove them from enter-
head reaches gets reduced. ing into the -main canal and to pass lhem down the
river. will have to be suitably incorporated in the
structure.
4.1.3.6. Width of rhe-Rivel' Bed. The width of the
river at the proposed location should not be too
wide which induces iuegular silting forming shoals 4.1.3.10. Suitability of Site for Undersluice. If
on the upstream and c.onsequent illregular and in a. diversion structnre, there has to be provision
likely cross flows. A very nan-ow width of the river for undersluice, a site where there is a deep channel
also will reduce the waterway and induce high of the river on the side where the canal has to take
intensities of flow, which will necessitate deeper ojI, may be selected. In the case of canals on both the
cut offs and costly foundations and protective works. banks a site with deep channels on both sides and a
Hence the width of the river should be slightly less , third in the middle could be a belter location.
CHAPTERS
5.0. Introduction free board is provided for 500 years flood. Hence the
Having selected a site for locating the diversion design flood to be adopted for the structure has to be
structme, be it a barrage or a weir, planning has to be carefully decided upon. Gauge-Discharge curve upto
systematically done to decide. upon the various impor- these flood values at the site should also be worked
tant parameters of the structure which will govern out by using statistical methods by fitting proper
the designs. The layout of the structure can be fina- equations to the observed Gauge-bischarge Curve.
lised with reference to all the requirements which the For various methods of preparation of Gauge-Dis-
diversion structure has to cater for. The parameters charge curve, IS: 2914-1964-Recommedations for
have to be decided on economic and general conside- estimation of discharges by establishing stage-discharge
Tations. These are discussed in this chapter and relation in open channels. See Figure 5.1 for a
some illustrative figures of some important barrages typical Gauge-Discharge Curve.
are also incorporated. 5.1.2. Afflux
5.1. Planning As a result of the construction of the diversion
structure across the river, there will be a rise in
The requirements, for which the diversion structure the flood level on the upstream of the structure and
is required to be constructed, should be listed out and it is called the afflux. (Though it is confined in
the type of structure selected. This will help in plan- the beginning to a short reach of the river it extends
ning for the various components and appurtenant gradually very far up till the final slope of the river
works to be incorporated and e\'olving operating upstream of the structure is very much the same as it
conditions. The parameters for w.hich the barrage or was before the construction of the structure.) While
weir has to be designed are generally design floods, higher afflux can be permitted in steep reaches of the
pond level, afflux, waterway, crest levels, free board, river with bouldery or rocky bed. due to proximity of
type of cut off to be provided, etc. While planning the structure to important popUlated or industrial
the structure, the river diversion arrangements during towns in the alluvial reaches, permissible afflux will
construction should also be planned in advance. The be limited in many cases. The amount of afflux will
planning aspect does not end with deciding the para- determine the top levels of guide bunds and marginal
meters alone. It has to go side by side with the cons- bunds, their sections and length and all the top levels
1ruction, procuring materials, etc. Planning the cons- of the components of the structures like abutments,
truction programme has an important bearing on the piers, flankwalls, etc. Afflux will also govern the
layout, especially in the provision of joints between dyna mic action downstream of the work as well as the
blocks of the structure. depth and location of the hydraulic jump. By provid-
5.1.1. Design Flood ing a higher afflux, the waterway can be reduced but
the cost of training works will go up and the risk of
The diversion structure has to be designed provi- failure by OUt flanking will increase. Hence, it is very
ding sufficient waterway to pass a flood with certain important that the premissible afflux for the design
return period safely. The free board of the struc- flood is decided upon, so that designs can be carried
ture as also the foundations have to be designed out accordingly.
for a higher flood with certain return period.
Usually, in the case t>f diversion structure of 5.1.3. Free Board
minor importance. the waterway is designed to pass a Once the permissible afflux IS decided, the
flood of 1 in 50-100 years frequency and free board necessary waterway can be accordingly worked out
is provided for a flood with JOO years frequency. For and upstream water level estimated for the design
more important structures, the waterway is designed flood. Over the high flood level obtained from the
to pass safely a flood of JOO-200 years frequency and Gauge-Discharge Curve on the downstream side
31
..
32
782
~
78 I
v-- ~
1.---L.-- ~
~.I""-/v
790 "'0
~
0
0
0:
Unre~rogr8ssl!'d curve-, ~ ~i
~ V V .
~-
';;
0
778
./
~rogre"Cd
V""""
E
::: 777
/ tf1
l\l
./" curve
..
L
E V '-"V
V
./ ..-
..
c 776
V V
"'0
0
"'"o / / ~
Cl 775 ~
V 0
/
..J
774
/
V V
/ /
'773
772
I
/ v
77 I
o 20
/
40 60 80 100 120 140 160 180 200 220 . 240 260 280 300 320
Discharge In cumec.s
and estimated on the upstream side. sufficient free regulator to feed the canal with its full supply.
board has to be provided so that there is no over- The pond level bas to be carefully planned so
topping of the components like abutments, piers, that the required water can be drawn wlthout diffi-
flank walls, guide bunds, affiux bunds, etc. The free culty. Adding the losses through the head regula-
board to be provided depends on the importance of tor, and the working head to drive the required
the structure. Generally I 5 to 2 m free board above discharge through the head regulator, the
the a:fl:1uxed water level on the upstream side and pond level can be fixed. Sometinle the pond
above the high fl00d level (unretrogressed) on the level has to be fixed allowing for the diurnal variation
downstream side are provided. While deciding about ill the water level due to release from any hydel
the free-board, the likelihood of accretion of the up- stations upstream. If the river carries lot of silt, then
stream bed of the river due to excessive siJt content of there is a likelihood of encroachment into the pond
the river should also be considered. It will be rel~· level after some years. Hence to cate for the same,
vant to point out damages have occurred in quite a there might have to be a 'future' pond level also fixed
few structUTes due to inadequate provision of free in some ca es as in Kosi Project. TlIe 'future pond
board. The free board gener;ally takes care of wave Ie.vel cau also be fixed for any possible increase ~ the
splash, higber afllux caused ciue to faulty gate o"pera- service area at a later date. The structure will have
tion, variation in the coefficient of discharge assumed to be designed to be safe ag:Jinst the increased pond
for calCulations and the flood value itself The free level also. Tbe provisiun of a high. pond with a leveJ
board is provided over the aftluxed water level due to almost equal to High flood level or above the same
a flood with 5 0 year frequency. However if the bas to be planned very carefully since such a provision
pond level is higher than the watet level for 500 year is likely to induce shoaling up tream. In those cases,
flood, the free board will be provided over the pond the operation of the gates will have to be efficiently
level. Hence, it is important to decide about the formulated and the silt excluding devices have to be
allowable free board for the safety of the structure. suitably designed. As the designs of the rarts, piers.
abutments, etc. are governed in many cases by the
S.1.4. Ptlnd Level pOlld level condition discussed separately in the chap-
The pond level is the water level required in the ters on designs, fixing of a suitable pond level from
urder sluice pocket upstream of the canal bead various considerations is quite important.
29
4.1.3.11. ') lfead Repcbe~ pf the Canal.. The head- (aLThe unit discharging:capacity would be maxi-
works has to be located generally nearer to the service j mum.
area such that the idle length of canal before it
starts serving the area is minimum. However, the (b) The flow would be more or less uniform over
advantage of the site has to be considered from the the length of structure.
cost aspect also since in such cases the pond level may
have to be kept higher. So in these circumstances the (c) It is most suited for sandy and silty founda-
extra cost due to the idle length of the canal by locat- tions.
ing the diversion structure at a higher site bas to be
weighed against the cost of the structure at a lower
site. (d) It is more economical and practicable.
Upstream
Up stream
I
Vlc:ir Sloping towards the conal
Alignment-along "everallilles
..
30
4.2.2. Alignment with Reference to Geometric Shape the other two alignments. In this case also concavity
upstream is preferable. (See Figure 4.1).
The alignment of the diversion structure can be ar-
ranged in three ways, viz. (i) straight along a single 4.3. Hydraulic Model Studies
line (ii) Curved and (iii) straigbt or curved along two
or more lines. While some of the minor diversion structures can
be located and aligned at a suitable site after consider-
4.2.2.1. Straight Alignment in Single Line. This ing the merits and demerits of some selected sites
is the alignment generally followed in many of the and also by experience, in the case of major diversion
diversion structures. The flow lines on the down- structures, reCOUTlle is generally taken to select a good
stream of the structure would be parallel to the and exact location in the vicinity of some selected
banks. Feach and also to determine the satisfactory align-
ment at that particular location through the help of
4.2.2.2. Curved Alignment. The curved, alignment 3-D hydraulic model studies. Further details on the
of the diversion structure can be had with concavity model studies are discussed in Chapter 7 of Volume II-
upstream or convexity upstream, both as viewed from Model Tests.
the downstream side. (See Figure 4.1). The align-
ment with concavity upstream is suitabl~ when the 4 4. Corrective Measureli
location of the structure is proposed at a point where
the river after having widened is narrowing down to It is always very difficult to select an ideal site for
normal course. The flow would converge to the the location of the diversion structure and its regula-
centre. tors satisfying all the requirements discussed in the
earlier paras. Hence it often becomes necessary to
The alignment with convexity upstream is not select a site satisfying most of the requirements and
recommended as it diverges the current towards the for the rest, some corrective measures will have to be
banks exposing them to scour. Moreover, this type incorporated in the layout and designs. These include
of alignment is also weak structurally. properly designed guide bunds, spurs, flood protective
embankments, pilot channels, silt excluding devices,
42.2.3. Polygonal Alignment. This type of align- etc. These have been discussed elsewhere in this
ment is only a combination and modified version of manual and reference may be made to these.
33
5.1.5. Waterway value of looseness factor to be adopted unless a de-
taIled study of all these parameters is carried out in a
The limit placed on the affiux also limits the mini- scientific manner. preferably in a Research Station.
mum waterway. A likely figure to adopt for the width After the results of such studies are available and cer-
of waterway would be the minimum stable perimeter tain conclusion's and recommendatio.ns are drawn up
of Lacey for the highest flood discharge. In the case of by experts in the discipline, the issue regarding the
bouldery reach, ·the width available at the site is limited
recommendation of any optimum range of looseness
by firm banks. It is generally thought that by limiting factor with reference to discharge and river bed
the waterway, the shoal formation upstream can be eli- material could be reviewed.
minated. However, it increases the intensity of discharge
and consequently the section of the structure becomes 5.1.5.1.2 However, till such time, perhaps the loose-
heavier and cost increases though the length of the ness factor may be adopted to be near about the value
structure is reduced. There is a greater risk of out- determined on the basis of dominant flood instead of
flanking and damages due to local concentration of design flood. The available cross-section of the river
flow. Many of the existing structures have a clear also should be taken into account. It is felt that in
waterway from 10 to 2S percent mote than Lacey's any case, the value of looseness factor should not be
regime perimeter. The ratio of the waterway between lower than about 0'6 (on the basis of design flood).
abutments to the Lacey's regime perimeter is known Wherever possible, hydraulic model tests should be
as the Looseness factor. Generally. the 109seness ca;rried to study the performance with the proposed
factor varies from 1.1 to 1.5 though there are a few looseness factor.
(
cases with looseness factor less than ]. which ar,e more 5.1.6. Crest Levels
prevalent in bouldery teaches. Table 5.1 gives
a comparative statement of the varic;ms parameters Waterway to be provided, crest levels of under-
adopted in the case of different barrages in the coun- sluice and spillway and affiux permitted are all
try. Before designing any structure, the value of inter-linked. A suitable combination has to be evolv-
looseness factor which has to be adopted for the struc- ed keeping in view the limits for each. The crest level
ture has to be decided upon. This has to be arrived of the unders1uice is generally kept at average bed
at after a careful review of the permissible afflux, level or slightly raiseq by a meter or so depending on
intensity of flow, river bed and bank conditions, width the n.ature of silt materials. brought down the river
available between banks at high flood level, dewater- and silt exclusion devices proposed. The crest level
ing problems, etc. It may also be noted that in the of the spillway is generally kept about 1 to 2 m above
case of limited width of the river, and attempt to the crest level of the undersluice. However, it has to
increase the same by excavation and suitable ap- be noted that the crest levels have to be fixed finally
proaches and exit will have to be done after extensive satisfying the qonditions on afflux and waterway.
model studies since some of the additional waterway
thus created may become dormant after some time. 5. I. 7. Type of Cut off
5.1.5.1 Looseness Factor: As already stated in Another important aspect to be decided is
para 5.1.5, the values of looseness factor for a number about the type of cut off to be provided. Cut off
of barrages designed and constructed over a few may be of reinforced concrete or sheet pile or" wells
decades vary from 1.1 to 1.5. From the performance depending on the nature of foundation strata. As
of these barrages, a feeling arises that with high loose- will be seen from the chapter on Hydraulic Designs,
ness factor more than even 1, there is a tendency for upstream cut off is required for safety against scour
shoal formation in front of the barrages which causes and also to reduce the seepage pressures beneath
damages and maintenance problems. Hence. some of the floor. Downstream cut off is required for safety
the designers tend to go in for as low a looseness against scour and also safety against piping action. In
factor as possible, even to the extent of 0.5. But alJuvial strata, generally sheet pile cut offs are pro-
fixation of such arbitrary values of looseness factor vided due to the case of construction. In b-ouldery
should not be allowed. A need for certain recom- beds, reinforced concrete cut offs are provided as it is
mendations in this regard has been f~lt. difficult to drive sheet pile cut offs. By planning to
have the type of cut off after studying the bed strata,
5.J.5.L 1. It may be seen from the discussions in the the sections of the structure required could according-
varJous preceding paras that the fu::ation of the water- ly be worked out. It will also facilitate procurement
way of a barrage is closely linked '. with various para- of necessary materials for the cut otIs.
meten such as discharge, cress-section of the river at
the axis, nature of river bed materials, silt content of 5.1.8. Construction Programme
the river, crest levels of undersluices, river sluices (if
any) and spillway bays, permissible affiux permissible The construction pro.1gramme ha'S to be planned tak-
intensities of discharge. dewatering problems. economy. ing all the relevant aspects like available working sea-
etc. The prototype performance data of many: bar- son, machinery, labour, materials. target. etc., into con-
rages are also not readily available. Hence, it would sideration. T~is has got a bearing OD- the provision of
be really not desirable to recommend any particular expansion joints between blocks of bays. GeneraUy,
34
TABLE 5.1
1 2 3 4 5 6 7 8
Year of Completion 1885 1907 1922 1922 1924 ' 1925 1927 1928
1. Design Max. Flood
Discharge in
cumecs 8923'5 20340 9207 7790 12748 42493 19830 16997
2. Silt Factor 1'00 1'00 1'00 1'00 1'00 1'00 3'00
3. No of Spillway Bays 16'00 20'00 54 43 30
Undersluice 12 8 9 12 4 4
4. Width of each Bay 18'3 & 18'3 18'3 18'3 18'3 15'24
in metre Spillway 9'15
U/Sluice 6'1 18'3 18'3 18'3 18'3 15'24
5. Looseness Factor 1'70 1'98 147 I'L5 1"10 1"45 1'56 095
6, Afflux in metres 1"37 0'92 0'92 0'61 0'92 0'31 0'92
7. Intensity of Discharge 10'22 14'87 13'57 19'33 13'76 35'32 23'05 39'03
in Spillway cumec/m
U/Sluice 21 33'18 22'31 31'18 24'07 35'32 23'05 39'03 '
8. Thickness of Piers in 2'13 ~'13 ' 2'44
Metres
Glacis Upstream 5: 1 5: 1 3: 1 3 =, I 4: 1 2: 1
Slope Spillway
Downstream 9: 1 5: 1 ' 3: I 3: 1 5: 1 2: 1
9. Upstream 2: 1 5:1 2: 1
U/Sluice
Downstream - 2: 1 5: 1 2: I
Scour Upstream
Depth Spillway 1'79 R 1'73 R 1'12 R 0'90 R 1'00 R 1'23 R 1'36 R
U/Sluice 3'40R 3'39R 0'64 R 0'74 R 1'00 R 0'60 R 1'36 R
10, Downstream 0'74 R 1'70 R 1'57 R 1'17 R 1'45 R 2'82 R 1'56 R
Spillway
U/Sluice 3'74 R 1'26 R 1'55 R ' 0'96 R 1'45 R 3'64 R 2'63 R
It. Cut/off Spillway 8'02 7'32 9'15 4'57 6'71
Sheetpile Depth in
metres- V /Sluice 4'88 8'23 9'15 4'57 V/S 5'49 7'01
V/S 5'49
12. Launching V /S 2: I 2: 1 2: 1 2; 1 2: 1 2: 1
'/ Slope D/S 2: I 2: , .2: 1 2: .1 2: 1 2: 1
35
. TABLE S,l (Contd,)
9 10 11 12 13 14 15 16
1 '
48 42 22 24
14 14 9 10
9:1 5'67 : 1 4: 1 3: 1 4: 1
(OPP);' .
15 : 1 5'67: 1 4: 1 3: 1 4: 1
Level 3: 1 3:1 3:1 4: 1
• 3 :'1 3:1 2': 1 3: 1 4: 1
1'36 R 1'25 R 1: SO R 1'5 R 1R
147 R 1'15 R 1'25 R 1'50 R 1'5 R 1R
6,1 DIS' 5'79 ' D!s'7'32 DIS 2'44 DIS 6'71 U/S 4'47 4'57 8'54
;:'. : \ I' ", : DIS 2'13 DIS 6 71 DIS 6'1
- :D/~,:6'4 DIs 6'4 DIS 2'44 6'1 8'54
DIS 2'29
3:1 2'5: 1 2: 1 3:1
3: 1 2'5: 1 3: 1
36
TABLE 5'1 (Contd,)
17 18 19 20 21 22 23 24
.. DIS 9'15
2'S: 1
2'5: 1
DIS "32
2: t
2: 1
37
TABLE 5'1 (Contd,)
25 26 27 28 29 30 31 32
1967/68 1968
8499 3133 24079 16997 850 5949 8074 1190
1'0 2'50 3'00
22 18 18 60 3 6 7
10 7 12 R/S 6 17 4
18'3 12'2 18'3 14'57 18'3
18'3 6'1 18'3 2'44
1'24 0'98 1'95 1'28 1"00
3: 1 3: 1 3: 1 '3: 1
3: 1 3: 1 3:1 3:1
• 1'25 R 5 1'25 R 4 1'25 R 1'25 R
2: 1 3: 1 2: 1
2: 1 2: 1 2:1
38
the barrage is constructed in units/blocks of S to 16 depends on so many factors such as the size of the
bays separated by double piers with expansion joints. gate that can be manufactured, the cost aspects, etc.
This also depends on the nature of foundation strata. In general, the size can be anything between 8 m to
Once th~ units/blocks are planned, design of the bar- 18 m. The width of the spillway section (along the
rage floofcan be ~aken up accordingly. flow direction) and levels of the profile will be deter-
mined from considerations discussed in the chapter on
5.1.9. River Diversion during Construction Hydraulic Designs.
The strategy proposed to be adopted for river dive~ 5.2.1.1. As for the layout, the crest level can be fixed
sion during construc,tion also plays an important role 10 at average bed level or above, depending on the con-
the design of the structures. For example, it may be siderations of afflux, etc. However. it should not be
decided to close the river in parts and pass the floods kept more than 2 m {l'5 m prefeHed maximum value)
lhrdugh already constructed portions. Due to limita- above the crest level of undersluice or River-sluice.
tio.os on the aiilux, it may be necessary to have a lower
crest level of certain bays, which can be later raised to 5.2.3" ,Under$luice
the final designed level. 'The designs will have to take
care of such modifications. Hence, while planning Undersluices are a set of bays provided at the
the structure, aspects on river diversion also has to be canal end of the diversion structure to keep the river
und~f control aiming at the following :
considered carefully~
5.2. Layout (0 Maintain a clear and well defined river channel
towards the head regulator.
Layout of the diversion structure, at the site and
tbe alignment selected outlines the arrangement of the (ii) to enable the canal' to draw silt free' water
various ,components of tbe diversion structure such from surface only as much as possible.
,'.; ! '
tbat tbe hydraulic performance of the structure is quite
satisfactory under the 'given conditions. The various (iii) scour the silt deposited in front of the head
components of a diversion structure are spillway, Un- regulator.' ,
dersluice, River-sluice; Cut-off, Pier, Divide Wall,
Abutment, Flank w·all, Return wall, Guide bund, Silt (iv) , (lin case of weirs fitted with falling shutters, to
excluding devices, Affiux bund, Approach embank- pass the tI!aximum non~monsoon flood witbout
ment, Regulating arrangement, Fish pass, Navigation necessitating the dropping of weir shutters,
lock, Log chute, Bed protection, Head' Regulator, etc. 5.2.2.1. The undersluice bays may be provided on
It is not necessary that all these components must be only one flank or on both the flanks of the river de-
present in a diversion structure. Fish pass, Navigation pending on tbe number of canals taking off.
lock, Log chute, Afflux bund, River-sluice and Return
wall are some of the components which are to be 5.2.2.i;' The'1ayout of the undersluice bays should be
added only if there is a necessity for one or more of thought of on the following consideration:
these. While the arrangement of these components
for small structures can be made by experience, the (i) the dimensions and level of undersluices should
layout in major structures are generally finalised with , be suth that there is the most effective exclu-
the help of hydraulic model studies. It is important sion of silt entry into the canal.
to know about the functions of the various components (ii) the dimensions llre conducive to maintaining
so that while deciding the layout it will be easier. a cl~ar ,channel towards. the canal.
These are discussed 'in the following paras.
(iii) the capacity of undersluices is also influenced
5.2.1~ Spillway by diversion requirements during construction
or of fair weather escapage.
This is the main body of the diversion structure
over which gate, are' installed for controlling the 5.2.2.3. The dimensions of undersluices are best
discharges and to raise.,the water level to the desired determined' by the help of hydraulic model studies.
value to feed the canal i;, In the case of a barrage, However, a few general guidelines for fixing the dimen-
it is a slender structure with upstream floor, up- sions of undersluices,are as given below:
stream' glacis, crest, down stream glacis, cistern
(also called stilling pool) and end sill portions and (a) For ensuring proper scouring capacity the dis-
cut offs a1 either ends of the floor. In the case of a charging capacity of the ,UI,l'dersluice bays at
weir, all these parts would be present except that the" I pond level should Dot be less than twice the
creast portion is raised upto the desired pond level) capacity of the canal near which they are pro-
(also called operating level) or slightly below (due to vided.
provision of falling shutters if any) and it is massive.
Typical sections are given in Figures 5.2 and 5.3. The (b) While a hard and fast rule cannot be laid down
length of the spillway bay (along axis of the barrage) regarding the percentage of discharge to be
• •
}-Ax,s or Bgrragt
~
~n~ ~j~\~?:o!"'lr"'u ... ".".,O"
. '";ir-~l*f • Orluc'rOUd br'd~,
1 ! ., C +
~llJ7~,,~ E-1I0Q~ IIiiI1'J"-=
r~-l
I u=-
bl
I
t.~"'~ ILOO.UOO~~O C C. blo'kl
~O.l)oCh'~QO' C .... lIh 1S jt\Qtries 0"11' GOO
trJCKI.l .. 0.....,,. 600 II"C" ll,lc;k Iton. spawl.
=~ -?-=-5l'AAiil8;!!I8I-
i.:'""O.... P~~II;" " . . . .'k
-"'0 ,,
.,OOlh 10011 slone prol.,.hon
r~
t....!.!.!A
,,,'
I~
IHOIOI
...........1',00
~:l • 1920~ l'~ ~
~.:r~r-?!± . ~
. ~XSX38g!j''''I;'~I'''-=- l>~'"~I
,,~
.
I, ~'"
;';:1.il
'~'J\06'.; .• ', ..••.." ., , •. , l
··'·f' .. ··; . . ~.~"", •.•. ' •. ,
_ f " ; ' o , •• '
.•. ", ...... .1. ,i' . ..
18975~ 18900
.. *iII.lo
~"",",J-.o.
~P'l(IllIt p,~
:.&22.
~ .,
~l.2~.···1
, [lQ,ooo' I
".
./"~
u')
\0
;all.
o
Allllofweir
,{ 0·65
~I ~~
~.,"I">
2440
R L.40·550 I. I 914.5 I " \: .... . I.915.I
1---3465
?
t RL3B.BlO 58870 _: ..../ \
Ir/~ --_-t:..DrO/rl
915 min --.::::-_fJ'Pe
Firm rOCk J'~
Minimum 610 below firm rock
-Relief pipe
---'::....-
or R L,37·955 whichever IS lower
'-. ;;Kit.'m,....,;;..",,}~~~Uv.;r''''-ar tJ}<";;;;;"'-nxr:.<\)IAtOnH
~_ •• ~~ •• w ••••• ..,'n.-..y""...... III ; 111-~
- .......
9/5
•
42
backed strips for water-proofing. Otherwise, the joints 5.2.5.1. The piers are construoted either monolithic
can be gunited OI grouted behind the wall. with the 6.0 r (raft) or made independent with their
own foundation footings. In the latter case, seals will
5.2.4.1.2. The various sequences in the construction be provided all around to prevent leakage b;:tween the
of such R.C.C. cut-off's are shown below by sketches: fioor and the pier (See Figure No.5 6).
3. Concreting of penals. Steel 5.2.5.2.' The thickness of pier varies from 1.5 m to
stop end pipes and reinforce- 2.5 m generally. The thickness should be adequate to
ment case positioned and resist the moments oreated (discussed in more details
concrete placed through tremie in the chapter on Structural Designs) and also accom-
pipe. The bentonite is dis- modate the embedded parts for the Main gate and
.' :'1:::'::
• A 'I" .6 • placed by the concrete. stoplog grooves.
•
.
·11····
" .
:d":,L ::A<
•• _ _ •.s ••
~ ~
5.2.5.3. Wherever reinforced concrete rafts are pro-
vided; the pier extends usually from the upstream end
to the dowstream end of the 6.oor to reduce the span
length of the raft. The upstream cut-water usually
has a semicircular shape and downstream ease-water
usually has an equilateral shape with circular curves.
4. Section through com- The upstream and downstream vertical ends are some-
pleted panel showing guide times given a better of 1 in 18-20 depending on the
walls and steel. architecture. Sometimes, a few project authorities
prefer to have square ended cut-waters and ease-waters
While these may be done above the high flood levels if
aesthetic value is not disturbed, they should not be
done below the flood levels so that hydraulic efficiency
is not impaired.
MJ Under Bentonite
r~co~"""~;;l'
' . - ,, ,- __ -.. ."..--..
U
-- ..__2'... 2. .
•• •
Under Benlor,ite
5.2.5.4. The piers have to be high enough to hold the
gates clear off the maximum flood while making
ample allowance for passing the fi.oating debris under
suspension awaiting suspension awaling the gate. The height can be reduced by using double
concrete pour utilisin'iJ concrelfo pouruWis no
I wo stop end pipes single $top end pip. or triple gates. Tne height of the piers in the zones
away from gate bridge, road bridgerailway bridge and
instrumentation terminal panel location zones, can be
5. Series panels on plan illustrating uses of steel reduced if submergence of the piers is permitted.
stop-end pipes as required. However, the height of the piers should also be viewed
from any additional dead weight required while com-
Various Sequences in the construction on such
R.C.C. Cut offs puting the overall stability of the structure. The
height of the pier in the zone where gate ,4oisting
5.2.5. Pier arrangements are located is usually higher than the
other zones and is constructed with the same material
Piers are provided between each bay. The gates as the rest of the pier, i.e., concrete or masonry. But
operate through the grooves provided in the piers. in. Earthquake regions, constructing higher pJrtion of
Usually there are two grooves, tbe upstream one the pier with concrete or masonry is to be avoided so
called the stoplog groove and downstream one called that extra earthquake horizontal moments are avoid.
the main gate or service gate groove. Sometimes Instead, steel trestles of ,required heigbt Can b'e erected
there may be a third groove also for emergency pur- so tbat the moments aTe redClced due to lignt weight.
poses. In the case of head regulators, there wil1 be structure. However. this again is a qnestion of compa-
additional inclined grooves on the upstream end riSO'll of cost between tbe two alternatives. Sometimes
through which trash racks are installed wherever they for repair of the gate wheels, etc., a gallery is construe·
are required. The road bridge and/or railway bridge ted at higher levels in the pier with accesS from the
are laid from one bank to the other over the piers and road bridge over the piers.
the bearings are installed on top of the piers. The
bridge for the gate ijoisting arrangement is also taken 5.2.6. Divide wall
over the piers. Wherever necessary dummy piers are
provided in between tbe main piers to load down the The divide wall is also like a pier and is provided
raft against uplift pressure. Sometimes to reduce the between undersluice and river-sluice or undersluice and
size of the gates, dummy piers are introduced between spillway or river-sluice and spillway as the case may
the main piers. be. The following are its main fu nctions
• •
•
HOist bridge
,-000+"",00+-8500 ~
Pier cap I,Rall briDge, rRoad bridge
~oo
- I i i
t=
~lntermediate sheet pile
~'-------' 82500---1. . H
IAll d1tnentlon. In mm •• ,.vctlori In mI
Typicol section under sluice
.a:o.
w
"'"
~
Bqdge
"Ier
t...RQ9
I
~ 18fl
·R.C C Pier
9000 - 4 +22'0
I f4000 C C.blocks wjtl1 Jharries over inverted
filter and stone spowls
~.... '. m!l~
I
±..!J!:QQ oJ • • • • •
I~
1 18
.1 • _. '
..I
•• '
c:
','
End sill
+13'00 Loose stone protection
U I 5 sheet pile
,.
+9·00-:::::lrro-
R C Croft 1----21:100 ~ I 21420 -----4
Sheet pile
O/S sheet pile 1500
I' 2400 I 1=='8:100 i,~
I 82'00 .
,•
\
i I COfltr'ochcn JOints
• w,t~ ,eol,__..... ~......
i . .26-21
i m .eo •
~ -
230
~
I
~.,
i Fan""""" , 25-30 _~.'
~~
'C,"" .NO\J$ $orrl rill
",o:>."O:>Il.C C P""
SECTION C-C
I 37d,d
x- SEC OF RUSSER SEAL
C
/ 255 wlde J I829 long s'••1 plates ..............-R.CC"'ot ~
Pde cop with suitable anchor bar'S
36mrrHf6iO clc (ot'the shear key
" ,
~I
_ 1+2560 J ,+~
~ I: ;;: ~.
~ 1~~-Lk530
.... ~. ~;
...
.
Inverted filter
o
II>
(All dimensions are In mm
'and levels In rnotrUI
DETAIL"X"
ilL AN
t lnd.fieol on .ither side or pier)
rn,Jt lJ."d pi'~ cap reinforcement not shllwn
..
VI
46
(0 Its separates the turbulent flood waters from The shank and nose of divide walls should be pro-
the pocket in front of the canal head. It perly protected as per the· criteria discussed in the
also prevents heavy disturbance which would chapter on Hydraulic Designs.
otherwise result on account of the wa ter in the
two portions being at different levels and,· 5.2.7. Double Pier
(ii) It helps in checking paTallel flow which ~ould In a very long structure, double piers are intro-
be caused by the formation of deep channels duced at specified intervals. These are nothing
leading from the river to the pocket in front of but two single piers with a joint in between them
the sluices. If parallel currents stiIl form, the and also provided with seals both vertically and
divide wall keeps them away from the floor· of horizoiltally (See Figure 5'8) for typical details.
the diversion structure and upstream and Double piers are introduced for a number of reasons
downstream flexible protections. such as change in the foundation characteristics,
construction programme and length of the floor raft
5.2.6.1. The length of the divide wall on the upstream which can be conveniently and economically cast, etc.
has to be such as to keep the heavy action on the The SPlicing generally varies from 8 to 12 bays though
nose of the wall away from the upstream protection of smaller spacings are also there due to the above
the sluices and also to provide deep still water pond mentioned reasons. In a way, divide walls are only
in front of the canal had .regulator. The divide walJ extension of the double pirrs between the sluice bays
also plays an important part in the control of silt ent1:y and spillway bays.
into the canal by enclosing a pocket of neady still
water and by separating· it frQID turbulence and 5.2.8. Abutment
vagaries of the main river. Similarly on the down· The abutments fOfm the end structures of the diver-
stream side, it should be sufficiently long to guard sion structure and their layout depends on the project
against action set up by the undersluice discharge features and topography of site. The length of the abut-
damaging the spillway flexible apron on the side of ment is generally kept the same as the length of the floor.
the divide wall. Sometimes the downstream di vide The top of the abutment will be fixed with adequate free
wall can be omitted if model experiments indicate to board over the upstream and downstream water levels.
that effect. . From upstream to downstream the top of the abutment
5.2.6.2. The length of the divide wall required to be can be made slopping or stepped. The thickness of the
provided initially in the designs before testing it for abutment must be adequate. to accommodate the
its adequacy or otherwise through models bas been grooves and bridge bearings also. Due to the different
discuss.ed in the Chapter on Hydraulic Designs. intensities of loading and to avoid damages due te>
any possible differential settlement, generally the abut-
5.2.6.3. The top of the divide wall on the upstream ments are divided. into different blocks such as up-
side near the diversion structure is always kept above stream, gate bridge, road bridge, downstream blocks,
the pond level with some free board. This gives an etc. Each block is separated from the others by joints
indication of the obstruction in the pond for any and provided with seals both vertically and horizon-
crafts coming into the pond for sounding, inspection, tally! The toe slab of toe foundation of the abutment
recreation etc. Beyond some safe distance, the top of usually forms part of the raft of the end bay adjacent
divide wall can be 'owered (subject to stability require- to the abutment and separated from tbe raft by a
ments). However, !iUY decision should be based on longitudinal joint provided with seals. The founda-
the model test results. - tion of the abutments should be carried atleast to the
5.2.6.4. Due to difference in the bed levels in the same levels as those of the floor of the Main diversion
spi1lway/Riversluice/undersluice pOl1ions, it becomes structure and prefer ably a li ttle lower. The founda-
necessary to negotiate the difference in the levels over tion of the abutments should provide a boxing of the
the length of the divide wall in the upstream or down- diversion structure. Cross· cut-off or sbeet piles are
stream side. The slope usually adopted is lin 5 and continued from upstream to the downstream end of
the flexible protections are laid over this slope. Where tbe floor and well connected to the inain upstream and
the downstream divide wall has been omitted on downstream cut-offs or sheet pile lines. Typical
relevant considerations, the difference in the bed details of abutment are givel). in Figure 5.9.
levels has to be suitably negotiated. 5.2.8.1. Sometimes, in the case of small structures,
5.2.6.5. The divide walls both ,on the upstream and tbe abutments along with. tbe floor of the bays can be
?~wnstream sides, 3re separated beyond the raft by designed as a trough section. Typical layout with
]01nts nd have their own foundations. Concrete cut section is shown is Figure 5;10.
offs or sheet piles, as the cas.e may be, are driven 5.2.9. Flank Wall
aJong both the faces of the divide wall foundations
and joined up wirh the main sh~et piles. Sometimes In continuation of the abutments of the diversion
some. P?rtion of the upstream or downstream ends of structure, flank walls are provided both on the up-
the diVIde wall rest over well foundation as 'n the case stream and downstream sides on both the banks. The
of Wazirabad Barrage in Delhi. (See Figure 5'7). flank walls ensure smooth entry and exit of water
II
Pier
g!
~
~I
."',
~AII dimensions in mml
R.C.C wells
~
~
·,
00
t--.
~ IS~
----+-4500
T~
.Rn
S~
51
----"!.I-..,,-::~
16500
.' /[Capperee~+517.50~
I
I
+ 512·50
;22000
1 Iho same dra"';ng will hold good In Ihatca••
'he'water slops are 10 be o(minimum 225_
wldlh ond may be laid according to manu-
faclurers speclncohons lhe joining of the
verlicol"Ond harizon!al waler stops may be
done properl y
1-8 P LAN 3. Horizontal seals are to beproperly
brand Or banded with vertical 1001.
21002109
~+523'00
Eepansion joinl-Rrl.+ 521.50
R.C.C. Pler-!-:fILJ....O;;;;; rOd0610 long (0) 450 c/c
IAnchor bars to be welded
to lhe copp!"" seal I
l.lOOO . ~ . .u . ~
05
Eap«\.lon Jlllni ",lIfrt sial f
1250 •
~-+!lZ3'
!2!l1.f-
,.,.-+ bU. €tNf96'C)'
~I
~~AdWQ
I
li.!..U- t-'"-OQ .... 0 - -
~
510.50~
[~JO~~ ,.., Frl(hOn b'OclU /'
1~~\~\.~ t
Foe, of nanl.otJulm,,,,,
.-1";
........ .r l'Ie I E I
t § 11 U
~
~! ;
t
~ lI.
r'Ou4l1tDr ) . j ! e
lJpttr.QJn a~= ~ ~
~ I • i
.l
I
.~-
CooI.,ck
rill-r
. ~ Sf.eTION A-A SEC'TIO'N 8-8
O4.....".lr.o". o~ll1I.nt .rOch
ppr"IIQc:h ,rob or
ROOd trlC. bloc;llI
I....
Ill I ).4'00 I rOI). ""Q
., 00 ~F '--';';~ -CCE-' - P LAN I
~I .. ~Ji i~...i-~.c--............ 4fort~ r.mO .... dl •
Z
J~lnl "I'" "01 <:1. fAil Ilm,n'lon, In mm &
el,valion m mI
~
,Jl;!1ftI ....ll'h "ot
.~
....'
+".'0
"!1:2Qh ~1I'\lchleon
coner,l, ;t.~~.
L ,ao,O 0 I o~9,ncaj""r.o'6' .. C~ ---------m~m----------.ll
SECTION X~X Magn lQOW!n'HQnsutt \
~
U).
o
, . 51740
1500 1500 1:iOO 1:iOO
1_9?OO I' I 9000----f' 'j" 9000 ,I· -I . . 9.000 'I " 9bOO~
II ~Ab"m,"'Boy No. I
l/Piflr
Boy ,No.2
, Pier
Boy No.3
, Pier
Boy No"":"
"Pier Abutment"
Boy No. 5
\
-
,.- -- . _. - ~------- -- -
•
+771·00
U
---"-:- R.C. C, r ofl--e--- +669·50
-
lU~~
'Leon conc.r.eto
lU9 ' (All dimensions in rpm and
levels In metresl
,1:iOIh.com.",t COt"lc.lI~Okg/crrf'1
ISO' 'WP
Slop,', r~26'c ~OOO
C Ulc<~.
+~~
.. ~.
"c\ .
.
Ilro';/:::lI-"C'
"0_ 'J~
+=
,
AWlTlIntrocellft.t! • ,r;
1OOO"000'9~
f-c,b',ocu ..,.,if.t7.:i
jhOrrt'l 0....,. 600
;~~,,~l t:lO!lBO • __
I-oiSerb~~"~
3j
~~
:~~~(t ffiiA .0i; .u~,
OOi,)trl. CrCXJed ... 1~:i oj'
('lOA :s'it.It!:OO'llr prop-.I""
COl1lDoct!-d lIiond 'fll
~:llli.Jl:l~
000.0000.9001 ~co
ce.B1ocks wfth15
10000 I
SECTION 2-2 ~noo_ Jho"'" 0_ 6001/\ SEcnON 3-3
f~~~~'~~-~ slone spo.... h, eoQ,.
1--- :>OOO--F'i.~().oo
1~op--i --=-
r:tC C, Porl~o" DETAILcX
3330
AOoo ~. 2000
o
~
'"
o
~
.000
R.C C Lug.
750'0
-I SECTION A-A
PLAN
KEY PLAN
a feeder canal also if desired. Necessary berthing spawls or inverted filter and loose stone of adequate
facilities and repair facilities are also to be provided. thickness. On the upstream side, immediately in front
The navigation channel is generally taken out on the of the floor, cement concrete blocks over stone spawls
right or left bank, as the case may be, away from the are laid. Further upstream loose stone protection
diversion structure and sometimes it crosses the main is provided. The length. and thickness of each is deter-
canal from the diversion structure also. Layout of mined as discussed in Chapter 6 on Hydraulic Designs.
the navigation arrangement has to be done as per Usually the size of the cement COD crete block is 1500
requirement of size of craft, etc. This is discussed in x 900 mm. The thickness of stone spawls is usually
more detail in Chapter 4 of Volume II on Navigation 600 m and that of loose stone protection in wire crates
Facilities. 1500 mm on the downstream side, the total length of
c.c. block protection estimated as discussed in Chapter
5.2.17. Bed Protection 6 is provided, half over inverted filter and half over
stone spawls and separated by a curtain wall. On the
. To protect the diversion structure from damages downstream side, for the release of any pressure, 75
likely to be caused by the scouring of the river bed both rom thick jb.arries are provided between the c.c. blocks
on the upstream and downsteam due to the flow through and these are filled with bajri. Beyond c.c. block
the structure, bed protection is to be provided. This is protection, loose stone protection in wire crates are
usually in the form of cement concrete blocks over stone laid for the estimated Ie ngth.
54
- ... --
1/
- .Jo'lH
-_~!gj
~r~lf
Wit"
0
/ If'8
r
f{j.j06jo
-_ I V')
- --..; , I
Detail X r - -- -- -1-
~J-O~n~~~h-~:,--~r1 0 1
0
0
-----------~LJ I~
I
I
J
I
J
-;----.
I
':"'-Joint with seal
,
I
'j! 0 . o
o
I ~ j o
o
- --- - - - - o~ -
1
(All dimensions are In mm except
elevations whl ch a re in metres) +518·50
P LAN
CA.
VI
(Ji
Cl\
15'8.." rlO-ST..
O·'''~'8'2e.. 5-2:1
Toe wall
C L. of VIS crOll buncf
.t
i...
+
1Jt0pe 2·5'1
Le",,1 '01• • of ,"" O"'dl~nf '" ."
NSLtIIIZJ ~,
( S03f I f
;.1 152
'76
C C blocks 0 9xl 2X! 2. oller 0 6 sHne filling' 762
C C blocks 152xl52xO 9 over 0 9 slone o. Gould." FlOw.
_J Wes1ern moln ednal
lined bus'" 1046
I..!>~~-+--c C blocks I 52 ..,52.llO 9 oller 09 .Ione or boulde..
tit ~ 378·0
,I
},
.~ ~ ~'''_. rl
H
iIj
q
·III 3672
Total lenglh.: 741,2
• 120·3
• • 120·3 'jl.11
'. Barrage feature.
496~
Left under slUices 5 River 51ulce
6 .pon. of 182 each 1109 7 6 span. 01 182 each IOg'7 f Note:
5 pier. 01 213 each 106 5 plero 01 2 13 ea~h 10·6
All djmen,!ono and .1.voilO"'
20·3 Ii 2.0 3 are In metr~1
2 Let' divide wall 6 RIllI11 divide woll
OIl/Ide wall Divide wall 2. 13
.DIvide wall pier Divide wall pier 213
4.26 1426
3 Splllwa~ 7 Right under Ilule••
18 opa.1 01182 each 6 'pone 01 182. each
15 pie.. 01 ~ 13 eoch 5 pie .. 01 2'13 each
2 double pter of :3 0 each
WI.dltl "Iwe.n abulmenl.
4 DIVIde "all belween opillway
and rlyer ••utce 8 [ol'.rn gnd We&lern head regUlators
Divide ...11 8 'panl D1 76 eoch
Divide .011 pie. 7 pie .. 01 1·5 each
I •••
-2~):;- ]'
I
~. __ .r ~.33528m
~~ I .+215.80m
Divide "alll'83m
~
T211'53!!!..,f1"'1WtIT!2Q~
~~~-- ~_ ~.
::..:::L..,n,..... ... - ... -M::.r:;, ..
-If -,- ..---- .
.1tFl~'
'i!!-lin.J:18~----------------
IB!l-7
1"
tl956Bm
-1"'!j".;,'16m ~~"~~,2o'll. lin.
~~
33:lOZSm
L erat
0067
201 '17m B·84m
loaKS-;III'tO'-o3:-mJhli'fl.5.. 0ver O·6Hn araCl.d flllGr l,lr'foln ""all
c.e b IOQI(6 over GlOm 1~1 [.,V22m cLlrfOln-'w'IIorr 8'40m
Q ::
,,
R
15·Z4m I·S2m stone filling
~
1 ", I
"'
DETAILED PL AN
"
FlGURE 5.16: Wazirabad Barrage detailed La)'out Plan.
S9
.'"
~c
.c
.
't;
X
14329:5
<t
+--_-+_-1,32012.0 -l--+--;=;rn
Salient fO'ltures:
Design flood 8499 cutnees
Under sluIce - - - - -- - 10 bay ot 838!5
Spillway - - - - 22 bay 01 18295
L.nQth between obu1ment.!5!521!!5
Flaw It
Nat. :
Dlmenslon.& are In m m
5.6.2. The waterway for a barrage on clayey reach bearing pressures and (iii)· probable settlements due
may have to be provided as governed by the site con- to load conditions imposed on the strata by the struc-
ditions. A study of the cross-section at the barrage ture. In order to determine all these and have a
axis will give the necessary guidance in this respect. review, data has to be very carefully collected in the
field and analysed in the laboratory.
5.6.3. In a case of clayey foundations, it is difficult 5.6.5. Data to be Collected
to evaluate the anticipated scour depths. The resis-
tance to scour offered by the cohesion of clay would Soil samples should be carefully taken in the clayey
initially reduce the scour. However, over a long period, strata from a number of bore holes, mostly along
when this resistence is overcome, total scour could be the axis and on the up~tream and downstream cut
anticipated. Hence, generally the scour depths are off/sheet pile lines and at different depths also. The
estimated based on the soil properties overlying the laboratory analysis should indicate their engineering
clayey strata. properties such as liquid limit. plastic limit, grain-size
gradation, in-situ density, field moisture content, void
5.6.4. The factors that require careful consideration ratio, pre-con30lidation pressure. compression index,
in respect of structure on clayey strata are (i) ade- e-Iog p relationship. etc.
quacy of the structure against sliding (ii) permissible
•
$
Axis or barrage
}Jfltr.octlon Joint
.,; II
~:
e.e.blocks over 610Th,
inverted filter
,w;th seals
---------
i I DO
U
0
0
-~-~
w
-~f---vo
., U
go!! ~ uO
Flow (/
.'
"'
Y~~Hf~
In
0 :;;:
l \
~
o!i:
~
. g.e ;;:
)( ~ "'"
0t' +
lj
~
o~~
!!C~.
0:0 go§ ,,'
DO U''f
-
~ ~~ g~!.ill ~ t
Ji
8~ 0 g.0
Ql.~l;';;' c;: ~ ~
.0= 0 c'"
:
0 r:::
£l.S!
9
r::
\ .
, A' E
05
~iii +
8~
~
-r
-
_0 Q
>l:t; 0 ~ l'
~tH~; i
.s=.- '"
b~"\
~~
FIQw
•...
o
! - - - - - - <..
- ...
01
'"
<:l
~
...
..:
-~.- -.I~.-
--:;~: - -::..,;.:...
Notes;-
I. Barrage is designed to c:o\er for a moximum di.chorge of 1500 cumeca-
Z,The head regulator on'the l.tt bonk cote.., for 0 design dlschdrge of
liP cumec' and that on the r'l~' forlZcu!"8CS and for f"ture eX'pansion
No'
I. 145000 ·1 105000 ~
Pilched slope ~I
Toe willi
o~nr
/.20000.,. 90000
Curtain wall N - 't 1: ci.
CD 0 I- c
Flow
.:-
~
~
c
0 :;: ~ ~2, ~
L- I')
.:til
.c..l:0
:=: ..... W1 0
_
0Q.
t.J I _ I n. ~ .... _. V)
" 0
.. 0
~ CO
<II Ol
."
8
Toe wall--... Q..J
VI
"-
:>
Nole. :~
I ThIS drawing indicates Ihe layout plan of
Gumti Barrage across river Gumti in Tripura
2. The Barrage has been designed fur an e.timated All dimensions are in mrn and levels ore In m.tre.a.
flood dIScharge of 3340 cumec.
In case clayey strata is obtained below per.meable It is desirable to have the bottom of the pile either
(sandy) strata at a small depth, the sliding effect at embedded into the clay layer or it should be at least
that elevation should also be checke d. It is prefer- one metre above the clay layer to prevent hetrogeneous
able to use a lower value of cohesive stffngth 'e' ob- conditions of seepage (For this purpose, continuous
tained from the laboratory analysis. probing of the clayey strata along this line will be
necessary at the time of actual drIving of piles). In
5.6.6.2. BEARING PRESSURE case the pile line is embedded into the clay layer, then
the seepage flow under the raft is considerably reduced
resulling in reduced uplift pressure. In case the sheet
The design load reckoning uplift pressure into pile bottom is kept at one metre above the clay layer,
account transmitted by lbe 6tructure and also neglect- then there will be seepage flow throogh the sand
ing uplift pressure may be calculated and compared strata. It is likely that the clay layer may not be at a
with the permissible bearing capacity of the clay for- oniform elevation in which case, the sheet pile depth
mation. may have to be varied if one metre clearance between
the clayey strata and sheet pile bottom is to be ob-
5.6.6.3. SETTLEMENT tained. This may be difficult to achieve in the field
condition. In case the piles are to end in clayey
During various stages of construction and mainten- strata, no such problem will exist and it can be con-
ance. the load on the floor will be different. Maximum veniently drh'en to the design depth or slightly more
loading occurs at a time when tbe entire pit is dewatfTed to interctpt the clay layer as the ca6e may be. The
andpiers are raised to tbe full hei~ht during the COOb- latter arrangement provides depths more than enviEa-
truction stage. During operation conditions because ged and hence preferable.
of the induction of uplift pressure below tbe floor. the
net load normally gets reduced. Generally. settlement 5.6.8.2. DOWNSTREAM
caleulations may be done for this load transmitted at
the bottom of the floor. As the samples are generally In the case of downstream sheet pile, it is not a
collected at intervals of about 5 metre depths along desirable feature that the bottom of the sheet pile
the bore hole, the settlement computations are made intercepts the clay layer as this will lock up the seepage
accordingly assuming the soil to be of uniform cbarac- flow and thereby build up uplift pressures under the
ter along a depth of 5 metres. Since the top layers raft. From this consideration, it may be necessary to
of clay strata are generally removed if sandy strata raise the downstream sheet pile elevation at least by a
is met with at shallow depths before again meeting metre. The criteria of exit gradient may not be rele-
with clayey strata below the sandy strata, in those vant in respect of a condition where the upstream
cases, the top clayey strata is ignored in the settlement ~heet pile is anchored in the clay and the downstream
computations. pile line is above the sandy layer.
Hydraulic Designs
6.0. Introduction 6.1.1. Failures of Khanki and Narora weirs and Col.
Clibborn's experiment.
The designs of the diversion structures are to
be carried ont in two parts, namely hydraulic and 6.1.1.1. The law of flow of water through permeable
structural. In the hydraulic designs, overall dimen- soil was enunciated for the first time by Darcy, who
sions and profiles of the main structure and a few as a result of experiments stated that the velocity
of the components are worked out so that satisfactory varied Lirectly as the ..bead and inversely as the length
hydraulic performance of the structure can be of the path of flow. .
ensured. 10 the structural designs, the various
sections and reinforcement details wherever needed Hence v= Kh
1
are worked out. The dimensions fixed up by the
hydraulic designs are again got tested by model tests where h=head, l=length of seepage path and K=a
for their adequacy and after they are finalised based constant.
on the results of the model tests, structural designs The law is the same as the law for movement of water
are takgn up. Details are then worked out to have in capillaries enunciated by Poiseuille in 1841·42.
a structure which will be safer under any possible
and probable combination of loadings. Tn both the 6.1.1.2. Experiments were conducted by Col. Clib·
cases, the diversion structure has to be properly born in Roorkee during 1895-97 to test the validity
designed for both the surface-and SUb-surface flow of this law. The relation obtained from his experi.
conditions. The surface designs will include tbe fixing ments between velocity head and length of flow was in
up of waterway, top profile of various structures keeping with Darcy except that at high heads slight
energy dissipation arrangeme nts, protection works, departures were noticed. The experimental results
scour values. length and protection of divide walls, were then checked on the prototype at Narora weir.
alignment, levels 'and protection of guide bunds, UnfOl tunately two days after the experiments, there
afflux bunds, etc. The sub-surface designs will in- was a failure of the weir due to excessive uplift
clude .fixing of the depth and section of cut-offs, pressures.
uplift pressure calculations, exit gradient, etc. 6.1.2. Bligh's Theory
The theories involved in. the computation of these
and guide lines for their designs have all been The failures -at Narora, Khanki and Col. Clibborn's
• discussed in this chapter. Typical calculations for experiments led to the hydraulic gradient theory for
various items are presented in Appendix 6.l. weir design by Sir John Ottley and Thomas Higham.
In 1910, Bligh perfected the hydraulic gradient theory
6.1. Development or Weir Design which later on came to be universally known as
Bligh's Theory.
The principes of design of barrage and weirs
have been evolved over a number of years as a result 6.1.2.1. Bligh assumes that the hydraulic slope or
of analysis of various failures of the diversion gradient is constant throughout the length of creep.
structure constructed. The failures can be attributed (Figure 6.1.) It follows therefore, that the velo'
to four main causes, acting singly or in combination. city of filtration which must be proportional to the
They are (i) undermining through piping due to gradient is also constant, Thus, the gradient diagram
excessive exit gradient, (ii) eruption of floor caused is represented by a triangle, the base of which is
by uplift exceeding gravity forces, (iii) deep sconr equal to the "length of creep" and usually denoted
immediately upstream and/or downstream of the by the letter 'L'. It is meant to represent the length
pucca floor and (i1') miscellaneous causes like faulty of the path followed by a filtering particle of water.
regulatiClo faulty constrution etc. Bligh believes that the apron is safe against under-
65
•
66
6.1.2.4. Due to its simplicity, Bligh's theory found
general acceptance. Some works designed on the
basis of Bligh's theory failed while otbers stood,
depending on the extent to which they ignored or
took note of the importance of vertical cut offs at
the upstream and downstream ends.
6.1.2.5. The general criticism of Bligh's method is
(i) that tbe slope (Hydraulic Gradient) is considered
The length of tra,," in Q weir profile os given in the
to remain constant over the entire length of the line
figure would be L= b,+ d,+d, + b z + dz +dz + b 3
of creep. Actually, as the seepage theory developed
now shows, this gradient is varying widely at different
=bl~2di+bz+'2dz +b3
points of the seepage path, (ii) it does not give any
If H= totol head over the,weir, the loss of heod per unit weightage for creep along vertical lines and (iii) it
length of creep would be
assumes the flow to occur along the line of contact.
1_ H
C- b, t- 2dl + bz t-'2,dz + b3 6 .1.2.6. However, Bligh's theory enjoyed wide
recognition due to fundamental assumption of the
FIGURE 6.1 : Explanator" figure for Bligbs Theory existence of harmless limit for the percolation velo-
Gity and also on account of tbe simplified assumption
mining if the ratio L/H=C is not less than a certain of a sloping uplift diagram.
value given in Table 6.1. below.
TABLE 6.1
6.1.3. Lane's Theory
Minimum safe values of Bligh's ·C'. During the next 30 years, it was gradually recog-
nised that vertical tections of the line of creep con-
tributes more towards reducing the danger of piping
For fine micaceous sand in North C=15 than horizontal sections of equal length. The differ-
Indian Rivers ence is due to the nature of the flow net and would
be there even for homogeneous soils. This is further
For coarse grained sand C=12 accentuated by the fact that the sub-soil of dams is
commonly of sedimentary origin and sedimentary
For sand mixed with boulder and C=5 to 9 deposits are always much less permeable in the
gravel and for loam soil vertical direction than in the horizontal direction.
If Kn and Ko are respectively tbe coefficients of per-
meability in the horizontal and vertical directions,
The second condition of equilibrium is that the the loss in head per unit of length of vertical sections
weight of the apron must be sufficient to counter- of the line of creep is roughly equal to the ratio KnJ
balance the upward pressure. Kv times that ofnorizontal sections. The value of the
ratio ranges from 2 or 3 to almost infinity in excep-
6.1.2.2. Bligh stated that the length of the path of tional cases, depending on the details of stratification
flow had the same effectiveness' length for length in and the importance of the variations of the permeabi-
reducing uplift pressures whether it was along the
horizontal or the vertical. From the meagre data
lity in the vertical direction. :i
available at that time, Bligh evolved a simple formula 6.1.3.1. To take account of the greater efficiency of
which cannot be applied in all conditions. Following vertical sections of the line of creep, Lane modified
Buckley, Bligh assumed the percolation water to the original BJiglis procedure by the assumption that
"creep" along the contact of the base profile of the every horizontal section of the line of creep was only
weir with the sub-soil, losing head en-route, propor- one third as effective as a vertical section of the
tional to the length of its travel. same length. With reference to Figure 6.2 on this
assumption the equation,
6.1.2.3. The length of travel in a weir profile a given
in Figure 6.1 would be L=bl+dl+dl+b2+d2+d2+ba
=b 1 +2d1 +b2+2d2 +bs. If H=total head over the
weir, the loss of head per unit length of creep would be
1 H
C = bl+2dl+b2+2d2+bs was obtained. The value Ct. is known as Lane's weigh-
ted creep ratio. Lane's theory is based on his review of
This loss of head per unit length is the average the various works Wl1ich stood the test of time and also
hydraulic gradient and C is called the percolation those that had failed. Based Oll- an analysis of about 280
coefficient. If in a design C were less than the safe dam foundations of which 24 had failed, the values of
assigned value for the given sub·soil, the design was weighted creep ratio Cw were suggested as given in
considered safe. Table 6.2.
67
1-1·------ 11-------.o . ,. will meet with tess resistance than that which travels
through undisturbed soil.
6.l.3.3. Lane's theory is still popular in the USA and
less important dams of USSR are designed on its basis.
For important cases, results obtained by mathematical
approach of subsoil flow are accepted aU over.
6.1.3.4. Appraisal of Lane's theory. Lane's theory
represents an empirical approach based on long experi-
ence and one should be able to make a safe design on
the basis of Lane's theory, if he is fully familiar with
its limitations. Care should, however, be taken to
provide cut off to take care of the scour at the dis end
•.
Lanes .
w9.gt.ted creep rllloo C W:: A1 B + 11 I + 12 + 13 + 14 e IcI and also to provide necessary filter layer to take c~e
hcr
of the u:prelieved gradient at the tail. The factor of
ncr =The "malle.! head ,,' which Pipi"9 eve' "ccurAd safety of works designed on the basis of Lane's theory
would be quite uncertain and the design in some cases
FIGURE 6.2; Explanatory figure for Lane's Theory.l whould be quite wasterful.
Maximum values of Lane's weighted The modern approach to the theory of weir design
creep Ratio is that (i) seepage takes place according to the theory
of seepage flow throughtout the underling strata and
(ii) that the stability of granular particles depends on
the limiting value of hydraulic gradient at the upper
Nature of foundation C", surface of the granular material which gradient to
material satisfy the coI1llideration of equilibrium is to be smaller
than the critical gradient. The second principle was
enunciated by Terzaghi in 1925 and discovered inde-
Very fine sand 8.5 pendently by Khosla Ii few years later.
Fine sand 7.0 6.1.5. Khosla's Theory
Medium sand 6.0 The distribution of uplift pressure is not linear.
.This, of course, follows from the fact that seepage take
Coarse sand 5.0 place according to the theory of seepage .flow and is
governed 'by the Laplacian equation and appropriate
Fine gravel 4.0 boundary conditions. If the Laplacian equation could
be integrated for the given set of boundary conditions,
Medium gravel 3.5 mathematical solution of the flownet would be obtain-
• Coat'se gravel 3.0
ed for those conditions. This equation, however, is
not amenable to a direct mathematical integration
under the complex boundary conditions, particularly
Boulders and gravel 2.5 the shape of the base of the foundations presented by
an actual work.
6.1.3.2. Lane's weighted creep approach is an im- 6.1.5.1. The principle of the method of independent
provement on Bligh, but still it is purely empirical variables evolved by Dr. A.N. Khosla consists of brea-
and leads to a design with an unknown factor of king up a complex profile into a number of simple
safety. The values of C", given in Table 6.2 above profiles each of which is independently amenable to
represent maximum rather than average value and mathematical treatment. Mathematical solutions of
the values of h.r obtained by means of the above flow nets have been obtained for a number of such
given equation represent the smallest heads at which simple standard firms, the most useful of which are:
piping ever occurred. According to Lane, water may (i) A straight horizontal floor of negligible thickness
occasionally travel along the line of creep, because it with a sheet pile Bne at either end (ii) a straight hori-
is difficult to secure intimate contact between the zontal floor depressed below the bed but with no
flat surface of solid foundation and granular soil vertical cut off and (iii) a straight horizontal floor of
upon which it rests. If there is indeed lack of or poor negligible thickness with a sheet pile line at some inter-
contact, tben water percolating along the line of creep mediate position.
(i8
6.1.5.2. The results of the mathematical solutions of dete.rmined only for the face of the adjacent pile to-
these forms have been discussed in publication No. 12 of words the interfering pile. For example, in Figure 6.4,
the Central Board of Irrigation and Power titled "Design pile No. 2 will interfere with the downstream face
of Weirs on Permeable Foundations" by Rai Bahadur of ~ile No.1 and upstream face of pile No.3.
A.N. Khosla, Dr. N.K. Bose and Dr. E. Mckenzie
Taylor. The solutions are given in the forms of curves (c) Slope Correction. Due to the sloping floor, a
(Figure 6.3) from which the percentage pressures of suitable percentage correction is to be applied.
the proportion of the residual head to the total seepage The correction will be positive for down slopes
head can be determined at key points. The pressures and nega:tive for up-slopes following the direc-
at intermediate points are assumed to vary along a tion of flow The values of the correction are as
straight line, which does not introduce any appreciable below given in Table 6.3.
error.
TABLE 6.3
6.1.5.3. Dr. Khosla has shown that the percentage
pressures observed from the curves for the simple Values of Slope Correction
for s into which the profile is broken up can hold
good for the assembled profile as a whole subject to
certain corrections as given below :
Slope (V: H) Correction of % of pressure
(a) Correction for Thickness of Floor: In the
standard forms with vertical cut-off. the thick-
ness of the floor is assumed to be negligible I : 1
and hence the value observed from the curves. 11.2
refer to the top level of the floor. However, due 1:2
to the thickness of the floor provided. correc- 6.5
tions are to be applied for the points at the I:3
bottom of the raft and these are in terpolated by 4.5
assuming strai~ht line variation. The correction 1:4
may be positive or negative according to the 3.3
points of observation. 1:5 2.8
(b) Corr..ction for Mutual Interference of Sheet
piles. The correction to be applied due to the 1: 6 2.5
mutual interference of sheet piles is given by the
formula. 1:7 2.3
D d+D 1:8 2.0
C=-[/- X -b- where
Ie . '" ~ ,·r··' b
'/JC 'iiCOS(~)
'/>0--1;- COS(T)
H~ b - - - t Hi.
e I--b C
0< .11 . . 0 _. . ~b, d b To (k'ld tPE (or any "alue of d an.d Dene rQllo ~ rlad d Sheel pil" at end 0 0
0<:::;10 _ •. _ ~ .
~;zd
4Jc (or bon rollo I to:EL) for that volue of f/.. ond
20 0
70 subject (ram 100 b ~ Q
Thul fjJe for .!{; =O·d and~,s.IOO-~C (or '"1)-0.6 .aJJo<Jr~" '30
x
and d:o· ....JOO-ZO,I .. 1O·9% a.jJ:
II
To get (/)0 (0"- value or .!L leU thon 0.5
Read ¢ 0' for bote ratio I~.E! and subl;qet from 100
11-
~O
rr-
'ku. ¢o
:. 100 -do
(or
r~r
-'i;'
-r; 0·4006 ""b= 4
0.6 ond ".-:4
40
.
~
8
j =100 -44-8
=55·2
50 If)
'O~
eo
,50
a "2. Depressed floor
a 70
>< 74
~Ix
o ~-?
'& 4Q 40
'a
! t-:-:'O,.
I OE il COS"t ';2)
0',
30 00=i; COS-'l'~' I
0C,.,OO'I!lE
"I
(/lO,"OO-iIIO
0D'::.IOO-00iIO.pr....d floor I
\110=91 0 -1 I~E-101+\10.pr
• _ (;7;;1 lI\
....d f100rl
,-;1 A:;~7
~~ 2
$'
70
24
I o~-f'~-+----,
sl--+---J-=::>....Ik-....,.--T7'-=r--,---r---r--,
o I 2 3 4 5 6 7 8 9 10
Percentage correction for different slopes, Hor./1 Ver.
DEI~!~--l...------
I_
~ ~ ~~
'~~
b ....:------------·~I
latter. The frictional resistance. cohesion, etc.• of the The factor of safety has to take note of the class of
adjacent soil will have to be considered in certain material, specific weight and pore space, angle of
cases. Once the surface particles are disturbed, the repose of the sub-soil, etc. As not much correlated
resistance against upward pressure of water will be data is available, at present the values given in Table
further reduced, tending to progressive disruption of 6.4 below are in vogue.
the sub-soil. The flow gathers into a serie$ oJ pipes
in the latter and dislocation of particles is accelerated. TABLE 6.4.
The sub-soil is thus progressively undermined. Soil
erosion can also occur through natural pipes or faults Facters of Safety to Critical Values of Exit
in the sub-soil. Gradients.
C Severe bend 1.75 R FIGURE 6.5 : Explanatory Figure for CalCUlation of loose
stone apron.
D Right angled bend 2.00 R
falling apron due to scour should be 1.25 T where T
is the thickness of stone on the slope. The values of
Class A Scour is likely to occur anywhere just be- T is generally taken from the values given in Table
low the loose aprons. Class B scour is likely to occur 6.6 below.
anywhere along the aprons of guide banks in the TABLE 6.6
straight reach and classes C and D at and below the
noses of guide banks, or at the loose weir aprons, Thickness (DlDI) of Stone Pitching
should heavy swirls set in for any reason. necessary to Protect Sand
Upstream and Downstream cut offs are taken down Surfaces.
to depths such that they provide safety against certain
values of estimated scour which are discussed further
in detail in Para 6.9 Types of River slop in m/km
River bed 0.05 0.15 0.2 0.3 0.4
In addition to the cut-offs, pervious protections to materials
the pucca floor are also to be provided both on the
upstream and downstream sides beyond the floor.
These are provided in the form of cement concrete Very Coarse 400 500 550 650 700
blocks and loose stone apron. The upstream block
protection and the downstream filter area are meant to Coarse 550 650 700 800 850
be immovable. They are flexible and are supposed to
adjust themselves to slight subsidence but they are not Medium 700 800 850 950 1000
intended to fall in the same way as the loose aprons.
Whenever the protections are damaged they should be Fine 850 950 1000 1100 1150
made good at once. Their existence will be a definite
Safeguard against any damage to pucca floor. Very Fine 1000 1100 1150 1250 1300
The loose stoDe proteetien, also called the launch-
ing apron, beyond the block protection, keeps the The estimation of scour and length and thickness
Scour holes at a safe dist-'lDce from the block protec- of protections are discussed in more details in Para
tion and the pavements. The slope of the scour hole 6.9.4.
is assumed to be generally not steeper than 2 : 1 and
not flatter than 3: 1 and for rivers with very fine . Wi!h the ab~ve discussed background material.
sand or silty bed, the slope could be taken as 3 : 1 and gwdelines for fixlDg the various parameters under
for rivers in bouldery reaches, the slopes can go upto Hydraulic Designs are given in tbe succeeding paras.
72
(».2. B••ic Parameters about 0.3 m depending on the nearness to important
towns, complexes, etc. In very steep reaches of the
As already mentioned in Chapter 5 on Planning rivers with boulders of rocky bed, the afHux may
and Layout, the following basic parameters are to be safely be higher, say of the order of 2-3 metres. How-
decided upon before taking up detailed hydraulic ever, this has to be determined from considerations of
designs: economy. Refer Table 5.1 also.
(ii) Frequency analysis In the design of the diversion structure, the rating
curve, otherwise called the Gauge-Discharge Curve,
(iii) Slop Area Method plays a very important part. Hence it is very imperative
to have a gOvd rating curve of the river at the site of
(iv) trse of empirical formulae such as the structure. As already mentioned in Para 5.1.1, a
statistically analysed Gauge-Discharge curve must be
(a) Dicken's prepared. If no data is available on the Gauge- Dis-
charge values, the same may be worked out by Mann-
(b) Ryve's ing's formula. This is the unretrogressed G.D. curve
to be used for waterway and free-board calculations.
(c) Ingli's
(d) Nawab lung Bahadur's As a result of ponding up of rivers flow, relatively
silt-free water escaping over the diversion structure
(e) Creager's pick up bed silt downstream of the structure and pro-
gressive degradation or retrogession of levels takes
(I) Fuller's place. In the first few years the retrogression of levels
is rapid and progressive. It may even range between
(v) Use of flood curves such as 1.25 m to 2.25 m. This lowering of bed levels in the
early stages after commissioning of the structure, if
(a) Beale's and Whiting's not duly allowed for in the designs, may result in its
failure. The structure may be undermined by an in-
(b) Curves of the Institution of Civil Engine- crease in tbe value of the exist gradient beyond safe
ers (London). limit. The energy dissipation through hydraulic jump
may be impaired due to lowering of downstream water
For details on the various methods, standard books levels causing damages to tlie structure and the pro-
on Hydrology or ewc Publication on 'Estimation of tection works. As a result of the retrogression in
Design Flood' may be referred. bed levels, while the low water levels have been found
to drops from about 1.25 to 2.25 m, the maximum
6.2.2. Afflux flood levels have not been known to have dropped by
more than 0.3 to 0.5 m.
As already mentioned in Para 5.1.2., it is very
iIDportant to decide about the limiting values of afflux The process of recovery of downstream bed levels
to proceed with the deigns. The affiuK is generally after the initial retrogression is slow but steady, taking
limited to about 1 m for structures on alluvial rivers even 20 to 30 years The bed levels may even riSe
at highers reacbes. In lower reaches it is limited to above the original levels. Hence while fixing up the
•
retrogression, the following points are to be borne in 6.3.3.1. Total head H includes the' head of water on
mind: the upstream side over the crest and the head due to
velocity of approach. For calctifa'ting the velocity of
(i) There is more retrogression in rivers carrying approach. the discharge per unit width of the diversion
more sUt structure (total width) is divided 'by the scour depth
R below HFL calculated by the following formulae:
(ii) The finer the bed material, the more is the
possibility of retrogression.
R=0.475 ( -/
Q )1 3 when
1
looseness factor is
(iii) The steeper the slope of the river, the greater
is the retrogression. more than 1.
A retrogressed rating curve to be used in the
designs for energy dissipation, protection works, etc. R=I.35 ( }
3 )1/9
may- be obtained from the normal rating curve (unre-
trogressed) by subtracting the retrogression for various when looseness factor is less than. 1.
flood discharge which can be taken to vary in a logari-
thmic fashion between the design flood and low flood where f=Silt factor to be estimated by knowing
values. See Figure 5.1. for a typical Gauge-Discharge the average particle size mr in mm of
Curve. . soil.
As already discussed in Para 5.1.5., the watel way q=intensity of flood discharge.
of the diversion structure has to be carefully planned.
The waterway includes that of undersluice, spillway
and riversluice bays if any. In deep and confined rivers 6.3.3.2. The coefficient of discharge C depends on the
with stable banks the overall waterway between the drowning ratio obtained with different water levels as-
abutments would normally be adjusted to the actual sumed on the upstream side and estimated from the
width of the rivers at design :flood level. For shallow and unretrogressed Gauge-Discharge curve.
meandering alluvial rivers, tbe minimum stable width
can P be calculated from Lacey's formula, P=4.83 DiS W.L.-Crest Level
Ql l2 where Q is in cumecs. Where the width of the river Drowning Ratio
is very large, the width of the diversion structure is VIS W.L.-Crest Level
limited to Lacey's width x Looseness factor desired
and the balance width is blocked by Tie bunds with It may be noted that the upstream water level is
suitable river training measures. initially assumed by adding afflux to the downstream
water level.
6.3.1. With the selection of the span width of each
bay and adjustment of the number of spillway, under- The coefficient of dischllrge will need to be estima-
sluice, riversluice bays and also fish pass if any, the ted or determined from model experiments. In the
width between the abutments can be calculated by recent past, some experiments have been conducted by
adding the thickness of single and double piers in different research stations and curves have been pre-
between. This would give an idea of the lossesness pared correlating the drowning ratio with the coeffici-
factor to be adopted in the designs and the likely effects ent of discharge. These are presented in Figure 6.6.
thereof. While the conditions and parameters under which
these experiments have been carried out are not
6.3.2. The crest levels of the different bays may be fixed known, it has been observed that these curves give
up in light of the discussions in Para 5.1.6. With fairly satisfactoI-Y values of coefficient of discharge
these tentative values, the adequacy of the waterway to be used in the calculations which can be later
for passing the design flood within the permissible verified by model experiments and modified wherever
afilux needs to be checked up. Otherwise, the water- necessary.
way and crest levels will need to be readjusted in such
a way that the permissible values of alHux is not 6.3.3. .3. Substituting the various values of C, Land
exceeded. H for the initially assumed value of upstream water
level and the waterway, the value of discharge that can
6.3.3. Discharge Q=C.~.{J.3f3 where, L is the clear be passed through the structure can be worked out.
waterway, H is the total head If it is equal to or nearly equal to the design discharge,
over creast and C is the coeffici- the assumptions ate okcy; otherwise, the procedure
ent ofdiseharge. . may be repeated to get a near value.
•
74
3.2.
)-,
~O
2·g
U
..•
~ 2-
~
u
•
1; Z'7
.--
0
c
Z-
•
'il "'''"''pur ILow.r SLndh Barrage'
;;: 2-5
--•
I
0
U 2-4
2'3
z·z
Kotri Ban-age 10'" 239·0 C!l/ft rLln
2-1
2'0
I-g
"8
',1
3:5 40 45 50 55 60 65 70 75 80 85 go 9S 100
Drowning ..otio pe ..cel'ltage
6.3.3.4. Since the crest levels of spillway, undersluice 6·3.5. Typical waterway calculations are presented
and rivers-sluice bays would be. different, the dis- in Appendix 6. I.
charges passing through each wiJI have to be estima-
ted separately and totalled up. Wherever sUt excluder. 6.4. Energy Dissipation
tunnels are proposed to be provided in the undersluice
bays, the discharges through these tunnels and over
them will need to be calculated separately and added The standing wave is considered as one of the
up. For calculation of the discharge through the most effective means of killing the surplus energy in
silt excluder tunnels, it may be treated as a large verti- hydraulic structures. The elevation and length of the
cal orifice and the appropriate formula for free flow downstream cistern or pucca floor depends on the
or drowned condition or partially drowned condition position and height of the standing wave under
may be used. In some small structures with a com- various sets of conditions. The formation of standing
bination of weir and sluice bays, sometimes breast wave depends on the discharge per unit widtb,
walls are provided in the sluice bays to reduce the afHux, shape of the glacis, etc. The following points
height of the gates. Tn those cases also, for estima- are to be carefully noted in the designs for energy
tion of discharges through the sluice bays, the appro- dissipation:
priate formula of ll!Tge vertical ~Tifice may be used.
(i) On a level floor with low friction, the po~ition
6.3.4. From the above, it will be clear that the of the standing wave is unstable. For a slight
waterway, crest levels and afHux are all inter-linked change in the depth or velocity, the position
and hence various com binatioDs of these can be had of the standing-wave will vary through a·
for passing. the sarre de~ign discharge. - Thefioal wide rapge. The position of the jump 00 a
features to be adopted in tbe designs should be horizontal and smooth floor cannot, therefore,
nocsistent with economY' arid safety.' . be cJosolypredicted;
(ii) On a sloping glacis, tho position of the stan- on the structure on the basis of the gate regulation
ding wave is definite and can be closely proposed. The most severe condition would give the
predicted. lowest cistern and itl) length. These are generally
determined by the use of curves available for various
(iii) The length of the jump is approximately five discharge intensities and water depths or by analytical
times the height. While the beginning of the method. The levels and lengths of ci stern determined
jump is fairly definite, its lower end is inde- by either of these methods have to be verified by 2D-
finite. In estimating the length, the lower hydraulic model tests for their efficacy. In energy
end is taken as the place where the water dissipation calculations. retrogressed rating curve
surface becomes and remains sensibly level. should be used as this gives deeper cistern levels.
The position of this is variable and difficult to
locate. 6.4.3. Determination of Cistern Level by the use of
Curves.
6.4.1. For a structure to be safe. the standing wave
should be confined to the sloping glacis and not per-
mitted to f:lrm on the horizontal beyond the toe of For determination of cistern levels. a set of
the glacis. The main disturbance of tile standing wave curves known as Blench Curves (Figure 6.7) and
dies out at distance from the point of formation equal Montague curves (Figure 6.8) extended by Kanwar
to five times the jump or 5 (D2-Dl) where D 1 = Sain are generally used. The procedure is as follaws :
depth of water just upstream of the pomt of formation
of the wave and D 2 =depth of water just downstrem • (a) From the proposed gate regulation for various
of the point of formation of the wave. Therefore. in diseharges downstream of the river, the down-
order that filter area and the stone protection be stream water levels (Retrogressed) and the
immune from the main turbulence of the standing upstream water ·levels for passing those
wave the length of the horizontal floor should be discharges plus canal withdrawals if any can
nearly 5 (D2-D 1). be estimated. The total energy line values
both upstream and downstream can be esti-
6.4.2. The cistern level and its length have to be mated by adding the head due to velocity of
worked out for various sets of conditions imposed approach and exit.
1I1r------t--J--nr--jH---It"---rt-1'---H-t--t---tl'--t-t--r-t-rt-f-ThH-+~_{__,f_1J-+_{__,fH-I-_1f___I-_fl_____,f__+__1
u
~ u
Q)
::l
U E
::l
111 U
6
o i II
FIGURE 6.7: Bleneb Curves .
..
7.6
~
\
14
13 f-
12~
\ ij
1 f-
10f-
-
~I~ 9f-
+
~ 8f-
~
w
o
y
o L.-~'---J_----I._---'-_-"-_""""'_-:'-_-'-_--:'-----'_
2 3 4 5 6 8 9 10
(b) The difference between the upstream and ation etc., generally about 20 percent extra
downstream total energy line values is the concentration of flow is assumed in the cal-
head loss HL. This may be worked out for culations. n may be noted that 20 percent is
the various discharges under consideration. a general figure adopted though, however,
The head loss at the design flood stage is the higher values of concentration of flow have
afflux provided in the diversion structure. been reported to have been observed in orne
cases.
(c) While the upstream total enengy line is un- (e) From the known values of the intensity of
affected by retrogression, the downstream discharge with concentration of flow and
total energy line would be 10 "'ered by the the head loss, using Blench Curves (Figure
amount of retrogression already discussed in 6.7), the values of EI 2 (Energy of flow just
Para. 6.2,4. downstream of the point of formation of
the standing wave) can be read off for various
(d) The intensity of discharge through the bay discharge values.
may be estimated by dividing the total dis-
charge through the undersluice or river- (f) E'l. i.e, Energy of flow just upstream of the
sluice or spillway bays as the case may be by point of formation of the standing wave=E/~
the clear waterway available in those bays +HL. Hence, for various discharge values of
during operation. Since the flow may not the regulation chart, Ell can be calculated.
be uniform in all the bays due to various
reasons such as curvature of riveillow, stages (g) For the known values Ell and the intensity
of flow, faulty gate operation, river configur- . of discharge. using Montagu Curves (Figure
77
•
6.8), the values of D l and D2 i.e., the hyper- other. The exact values of D l and D 1 will thus
critical and sub-critical depths of water before be known.
and after the hydraulic jump can be read
out. (i) The required cistern length would be 5 (D2-
Dl )
(h) The required -cistern level would be equal to
the retrogressed water level for that discharge 6.4.4.1. It would be observed that the cistern eleva-
minus D z· The requiled cistern length would tions determined by use of curves and by analytical
be 5 (D 2 -D l ). method would vary. Hence, generally the analytical
method is preferred as it gives more accurate results.
6.4.4. Determination of Cistern Level by Analytical Use of curves would be quicker and may be used
Method for very preliminary computations.
6.4.5. Prevention of Dangerous Scour Downstream of
The various steps involved in the determination Aprons
.of cistern level by analytical method are as follows:
(a) As mentioned in Para 6.4.3 (a), the total The length of the downstream horizontal floor can
energy line values both upstream and down- be reduced with a corre!lponding saving in cost, if
stream are estimated. the Iange of turbulence of the downstream wave can
be restricted and the normal steady level of the
downstream water obtained in a distance less than
• (b) An arbitrary cistern level for the particular
discharge is initially assumed. five times the jump from the toe of the glacis. The
bed erosion on the downstrem side are caused by the
(c) Ell = Upstream T.E.L-Assumed cistern level. occurrance of vertical and negative horizontal vortices.
The former can be provided against by (i) construc-
ting suitable lengths of divide walls between spillway
(d) From the kntlwn values of Ell and q with con-
centration, D 1 can be calculated from the and sluice bays and (ii) maintaining uniform intensity
relationship, of discharge as far as possible. The negative hori-
zontal vortices can be prevented by a number of
q2 devices which are designed to give an upward bend
EI1=D1 +---
2gD 2 to the high velocity jets oC the effluent water. These
l energy dissipating devices are generally in the form
of
where g is the accelaration due to gravity.
(a) a continuous end sill or Rehbock's dell~ated
(e) Since the most important characteristic of the.
hydraulic jump is the pre-jump Proude's end sill.
number F, it may be calculated from the (b) arrows.
relationship,
(c) raised blocks
:I
F2 _ _q- (d) a roughened or toothed floor
- gD l 3
(e) a combination of two or more of these forms.
• (f) From the calculated values of D l and F, D 2
U.S.B.R. has standardised stilling basin designs for
can be calculated from the relationship,
different values of Froude numbers. For details, any
standard text books on Hydraulic Structures or publica-
tions on Energy Dissipation may be referred. One set
of blocks called Chute blocks are also provided at the
(g) The required cistern level would be equal toe of downstream glacis.
to the retrogressed water level for that dis.:
charge minus D!. While advantage can be taken of the provision of
energy dissipating devices, generally these are provided
(h) It would be seen that the initially assumed extra to take care of any unknown flow pattern. In
cistern level (Step b) and the calculated cistern any case, however, tbe proposals for eneq~y dissipa-
level (Step g) may Dot be the same which ting arrangements will need to be checked up by 2-D
indicates that the cistern level to be assumed model studies for their efficacy.
initially needs to be raised or lowered. After
assuming a modified cistern level, the various Some of the energy dissipating devices usually
steps should be repeated again till the assum~d adopted for diversion sirsctures are· indicated in
and calculated cistern levels tally with each Figures 6.9 and 6.10,
•
78
Ll
TYPE I BASIN DIMENSIONS /;
~~========='{.
LO' 2 H 3 End s:ll
Chute blocksl1'- Baffle blocks J
6.5. Upstream aDd DOWDstream Glacis 1 : 5 for the glacis are Kconsidered to be the most
suitable both for maximum dissipation of energy and
The glacis is the slope joining the crest with the economy.
floor on the upstream or dOW.Dstream side as the case
may be. From aetual observations at site and from 6 6. (~rest width
calculations, it has been found that flatter the glacis, In the- case of a broad crested weir, the crest
the more intense is the wave and the greater the range width is usually governed by the requirements for
of the trough, re"quiring heavy thickness along a much traffic during fair weather if any and height of crest
greater length of the floor. Theoretically, a stream shuntters which when lowered are to be accommodated
requires more gradual expansion than contraction. on the crest. The top width't' may be taken from
From this. it follows that the downstream glacis Bligh's empirical rule
should be flatter than that of the upstream. Where
here is cODsiderable heavy material tolling over the t=vH+Vh
crest; a flatter upstream slope would· be indicated. It where, h is the depth of water over the crest and H is
h as thus been observed that slopes' between I: 3 and the height of weir.
. ..
--
.Axi, af bartoQ'
~i"il!Wm of two Q"chor plat•• I '~50,1
~I 1- 10 bl Ilfovld.d 01 I.llobl••,oetn,
/'7511I ~75",", ~tt,"m~
.514·80 !
-I·o;!v.~ .. ·:g-'..,..~
II};", .d
I '".
3011I11I " 300 ClC.
I.
L
' ,-12':;0 .....;-1000... I.
.... lld~ to v!rHCQl enol. ~ _ ~
16111m "2,.o.--J»IOOO-;:
16111m ¢ 8 No.
"mrr\. 75m"" .-IOMM ct\OI.
~.Ided
to vedlcal angle
~Omm 0 pr'lIl.ir. rlleall pi,.
D
.-n;::,-.~75I11mx 7511I11I x 1011I11I angl.
-f
Gmm ~ 8 No>.
6Mm ~ 2 No.
-l
I+. 16mm iii 300 d/c III mm ¢ 300 C/C
,"rnrnx"'mmltIOm
t....y I.ngl'-'11<-11811III III 300 C/C
'""V 1Oq'D1~
16mmRl2NOt
~~t....:..,.'L:( , ji.:. I !ll5m.. ¢300C/C
PLAN OF FRICTION BLOCKS
OETAIL-X
\;j
80
t has a minimum value of 3h/2wi is the unit weight z5 050
of masonry.
Ratio= ~ (See Figure 6.11) 6.9. Scour Calculations and Protection Works
b=length of the barrage/weir section 6.S.I. As already discussed in Para 6.3.3.1., the value
of scour 'R' can be calculated separately for spillway
d=depth of downstream cut-off and sluice portions. 20 percent concentration factor
will also be taken into account. The upstream cut off
H=head of water. would be provided for a scour depth of R and down-
stream cut off for a scour depth of 1.25 R. The cut
Curves given in Figure 6.11 can also be used in the offs are to be extended into the banks on both sides
calculation. upto atIeast twice their depth from top of floors. 1n
the case of alluvial soils where sheet piles are provided
6.8.1. It would be observed that for &etting a safe as cut offs. the depths of sheet piles would be increased
value of the exit gradient, different combinations of b by an amount called the grip length. For calculation
and d for the same value of H can be had.' The value of the grip length, standard books on Soil Mechanics
of ~ is also governed by the requirements of safety and Foundation Engineering may be refered to. A
against SCour. Subject to this, any combination of b typical example is also presented in Appendix 6.1.
and d chosen should satisfy the considerations of
economy also, since it has been experienced that gener- 6.9.2. In addition to ~he upstream and downstream
l.a1.Iy for every 1m reduction in the depth of downstream pile/cut-off lines. in major structures. intermediate
cut off. b needs to be increased by about 10 m. This in- pile/cut·off lines are also provided. They are required
crease in the value of b has to be effected through out the neither to prevent undermining of the floor at the up·
81
• stream nor at the downstream end, nor do they materi- 0.75 D. In between, a curtain wall of depth 0'5 m
ally alter the pressure distribution to give less upli(t more than tiiat of the stone apron is provided. Since
pressures under the downstream floor. But they act as wide shallow blocks are apt to be carried away by the
important secondary lines of defence so that even if current of water.. deep blocks are to be emplo}ed
the pucea floor is damaged at either end by failure of which' get wedged 'in and!resist dislocation. The inter-
the end piles due to abnormal scour, the rest of the stices (jharries) bctweeh the bloch are filled up with
floor and the super-structure will be saved from bajri For estimation of the value of D, a scour factor
collapase by the intermediate pile/cut off line. of 1.75 to 2.25 R (mean ~.O R) may be adopted.
Generally twc intermediate pile/cnt off Jines are' pro- :
vided, one between the upstream end and the crest and Beyond tbe block protections both on the upstream
another between the downstream and the creSI, located and downstream side., ~osc stone aprons would be
under the upstream and downstream toe of the glacis. provided as discussed' ,in P aea 6.1.5.5. If D is the
While providing the intermediate pile/cut-off lines, it is depth of scour hole below the apron level, the length.
to be ensured that the bottom level of the upstream of apron over a launching slope of 2 : 1 would be
intermediate lines is not higber than that of the up-
stream end line and that of the downstream inter- .[5D. Witb a required. thickness of I metre, the sec-
mediate line is not lower than tbat of tbe dowIilstream ti~Dal area would be vi 5D. The apron as originally
end line. laid must have the same quantity of stone and hence
the sectional area. The ;length of stone protection may
vary from 1.5 D to 2.5 D (higher figure for flatter slopes
6.9.3. In big barrages, the structures are constructed of the river). Accordingly the thickness of the stone
in a number of units/blocks, each comprising about 8 apron may be calculated.. Usually it is about 1.5
to 16 spans. It is necessary to ensure independent metres. The scour' factors adopted for the upstream
stability of each unit/block. For this purpose, cross and downstream block protections hold good for the
pile/cut-off Jines need to be provided in the longitudi- loose stone apron also. The appron is provided in the
nal (flow) direction between the upstream and down- form of a wedge, with smaller thickness inside.
stream lines. These are provided below the end piers
of each unit/block which are part of tbe double piers. 6.9.4.1. It may be noted that while computing the
The bottom profile 01 the cross-pill'/cut off line may value of R no concentration (20%) need be taken in
follow the bottom profile of the pucea floor. Usually the value of q in the case of upstream and downstream
the bottom profile is in tbree portions (0 upstream por protection works.
tion having the same level as that of upstream cut off
and extending from the upstream end to the toe of up- 6.9.4.2. Typical calculations for scour and protection
stream glacis (it) downstream portion having the same works are given in Appendix 6.1.
or slightly bigber level as tbat of downstream cut off
and extending from the downstream end to the toe of 6.10. Uplift Pressure Calculations
downstream glacis and (iii) transition portion joining
the upstream and <'ownstream pOItions. These are After fixing the profile of the diversion structure
shown in Figure 6.12. including the levels of the pile/cut off lines, the thick-
ness of the pucca floor at various places like upstream
6.9.4. Protections floor, crest, glacis, downstream stilling basin, etc,.
may be suitably assumed 'and the percentage of see-
At the upstream end, a furtber protection of blo(;ks page pressure below thd floor estimated at salient
over loose stone sbould be given so as to protect the points. Necessary corrections on account of the
soil adjoining the upstream end of the pucca floor. thickness, mutul interference of piles and slope of
Tbe length of tbjs protection should be nearly equal glacis will need to be applied wherever necessary.
D' which is the depth of scour hole below the floor. After this, the required thickness of floor to be safe
The bottom level of upstream scour hole is estimated against uplift pressure has to be calculated at the
by adopting a scour factor of \.25 R to 1.75 R (mean salient points. as explained in the relevant para of
1.5 R). For calculation of R, reference may be made Chapter 7 on Structural Designs. Under Hydraulic
to Para 6.3.3.1. The thickness of this block protection' Designs, only the procedure for estimation of the
over loose stones (also called spaIJs) should be the percentage pressures is outlined. From the thickness
~ame as that of the stone apron at that end. Generally calcula.ted ..under structural Designs, the assumed
cement concrete blocks of 1. 5 m X 1.5 m X 0.9 m size thickness of the floor at various points may be suit-
over 0.6 m thick loose stone are provided on,the 1.lP- ably modified and for this final proposed profile of
stteam side for the required length . the floor, the percentage pressures may be estimated
again.
At the downstream end, there should be an area of
inverted filter of length equal to 1.5 D and depth equal 16 .10 .1.The percentage pressures at the sheet pile
to that of the downstream stone apron. T.his length is points am es~jmated from the curves given in Figure
normally made up of deep blocks laid over graded 6 3. In this Figure (a) will be used for estim !tion of
filter of length 0.75 D and over loose stones of length 'percentages at piles at the upstream and downstream
•
0Cl
t.J
.~e
·SII-I!lO
\
. I~OOO -! ~"::l.," __""""M......_,__t-a~ R.C.<;. roft
. +5D8'OO-C;=O;5c~0IT·-
II
g
~l~ ~~•
, S E C'T 10 N 1-1 - - +150·1~1<'''.I.oo cDnorele
I '0 ;1(1!5i or barrage 4
I
I
I ~j ~ I
2
I
I
1
1
3,
2?OOO
j'"
•
.
16500
~
28000
,I
I
I
t:. - ---- --
::t~~.-J +51 <l-501.. ...J S..J -lj,~
_. I,
10000L
I 15~0-- ~ P LAN 40500 I
EXPlJrt!1lol) ]olcl with
,dOl,Oble 5-eol"
....-./'---r
I __ f 'Sllh..d 1+514.80
~~
SECTION 3-3 ·SECTION 4-4 SE C T I ON 5-,5.
:i, (i) To find ,pE for any value of " and base ratio
«pc.; may be read for base ratio
value of at and subtracted from 100.
(1 ~ :1 ) f()r that
head-wor~s play an important part in deter-
mining the length of the divide wall. Thus,
if the pocket is at the outer curvature, the
length of the divide walls eoold be reduced
with advantage. Otherwise, they may do more
W) To find c/JD for values of ~l less than 0'5. the
harm than good.
6.12. Typical hydraulic calculations covering the
value of,pD for the base ratio ( 1- :1_) may be read aspects on waterway, energy dissipation, exist gradient,
scour and protections and uplift pressure percentages
and subracted from 100. for the main struGture are presented in Appendix 6.1.
84
I I .. J , 'r I I I ' ••
"
APPENDIX 6.~
Typjcal Hydraulic Calculations
Discharge Total Canal Dis. Undersluice Riversluices Dis, Spillway Dis. U,S, W,L.
in cumecs cumecs Dis, cumecs cumecs cumecs
For Spilllway, max. discharge Exit Gradient= ~:~~ XO.19=0.15= ~,7 safe
=2451 cumecs
At bottom of filter, calculating in the same way
Intensity of discharchge
2451 . Exit Gradient= 5\ safe,
q= 241'8=1014 cumecs/m
q with concentration of 20% Similar calculations for exit gradient are to be done
for under sluice and river slUIce also,
=12'17 cumecsjm
R=0'475( 7
,Q )1/3 C,C. Block and Loose Stone Protection
Spilllway-Max, intensity of discharge
=0'475 (
1'2X2451
1,
)1 1
8 =10'14 cumecs/m
With concentration q=12'17 cumecs/m
as looseness factor B> I
[Note, In case of spilllway with gate and piers,
=6'81 m. total width of spillway is to be taken for computing q
Bottom of DiS steel pile and no concentration to be taken.]
42D 42
b1/b=0'61/73' 17=0 00834 = --,;;-=. 42.68 X[10.98-( -1.22)
I-bl/b= 1-0'00834=0.99166 =12%
epc=61.8% 1
Correction for interference of 3rd,row of sheet pile
epE= 100-1 =99% OD epc.
epD = 100-26.2= 73.lt % =19 J D x d+D
bl b>
Correction for thickness of floor
D=10.98-(-4.57)=15.5S
For epc-: 73.~~~1.8 X2.134=1.79% d=10.98-.305=10.675
For
99-73.8 _ 91 =19·"" 15.55 x 10.675+15.55
epE= 1433 X2.134-3.84/0 26,22 73.17
•
88
b1 =26.22 m D=6.l-.305=5.795 m
b=73.17 m d=6.1-(-4.57)=10.67 m
!pD=2S.5%' .
89
Correction for thickness of floor d=6.1-(-4.57)=10.67 m
For 'Pc 2;·i.~ 1 x 2.134=4.98% =19
\I
'_10.6,-
29.27 x
10.67+10.61
73.• 7
37-25.5 4- ,,/
For epE= 12.8 x 2.13 -1.92 lo ht=29.21 m
.l I ('l ~.. i-
Correction for interference of 3td row of sheet 'pile ,. , 6=73.17 m
on <pE. =3.34%
=19 r bD
\I
x d+D
b '.
Corrected epc =1+4.08=5.08%
1 'Corrected' CP E =37.0-1.92-3.34
D=6.1-(-4.S7)=10.67 m =31.74%
,t .1
+1433
•
+&-23
I"
.0
.
I
26·22m
+ 8·305
-1·20
-4·57
~. OS"
31'7~
40·/ "
60·38" -
54·e2~
'1'1-09"
r-
9S·16r.
- 4$4-66"
.
'.:
UPI.IFl" PABSSUA£ P&NC.iNT G¥GA"M
:;, ..
~
' ..
I· .: t !
. "
"", ..
"
,'. :~ ....
....
~ ,..;.'" ... ..'.J,;.. _.
{n ., r " f; . .: .: ': . .: ,..
~'.:
--.-
.'
I".. •• '.,
, :; ../ ...: : ...... .- :.;
:
CHAPTER 7
.. : ; _ r ~~ : ,'. " ", ~
.... .r ... -
',I:I
t~\ "
<-j
7.0. 10 troductioo (d)< Intensity of silt charge in the river during high
..--and lowilood stages.' ':
From the various guide lines set out in t h e " "
Chapters. on Planning anct~ ....L ayout aQq J;Iydraulic,./" 'Jer Log of bQr~lrol~s t~ a dbpth of about 15 to 25
DesIgns, Jt would be possfule -to ·evofve:)ib broad .,..-- m ·below ~be. deepest .bed level at a spacing of
feat~res of the diversion stttue.ture, be it a oarrage-Gr/ . one per bay In at lea$t three rows. One row
a weIr. The various co.mp,qne;nts of the structure ha~ ~f.bore holes" may be a~ong the barrage/weir
to be very c8Tefully deSigned' for ensuring both safety aXIS, the, :second at a· dIstance of about 15 m
~d econ0":lY' Due to the different types of found.- upstream of the axis' and the third at a dis-
tlon matenals encountered. s:uch as clay, etc. som;e tance of about 30-40 m downstream of the
foundation treatments may become necessary. These axis. The location of the boreholes along
will have to be properly evolved and their effect taken the axis shall be staggered with reference to
into consideration while designing the structure. The t~ose along the upstream and downstream
type of cut~·offs proposed such a. sheet piles or R.C.C. hnes. However, these are essential wherever
Cut-oirs WIll ha~e to b~ ~.1!ifa1jly-selected depeodin~ -1>TeSenc: of clay-stratum is detected in the
on the construction difficulties and these will have to foundatIOn. The extent. depth and location
be ca!efully desigued to ensure\ c;.af#y of tbe structurd. of the clay layer should be correctly assessed.
In this ~bapter on Structural Efeslgns _Gu.i~line~ fO:r ; .
the deSign of some of the important components tif (f) In sandy strata. stapdard penetration test
t~e.main structure such as cut.offs, pucca floor. pier~-:----- --._ resu':t for a depth .qf atleast 8 to l~ m ~t a
dIVIde wall. abutment. flank wall and return welf are spacing of 40-50 m IQ the transverse direction
set .out. Though Silt excluders are also part of the (alon~ -.t?_e;--ri-v-er.'.· i~th) a!1d ~t a spacing of
mam structure. these are discossed in tbe Chapter on 30 m. In the 10ng;ltudlDal direction (along the
Sut Exclusion. 'The other cnmponents~!)~~-g; fr· 3>.~;~·:.':~:Al!?~3,;
the head regulator, fish pass~ 'navigation facilities and (g) Wherever clayey strata are encountered. un-
river training works are discussed under relevant disturbed samples of the clay layers frorn the
chapters. : . prOp~q;,f9undalion level upto 8 metres below
the foundation level for each bay. The analy-
7.1. nata Required
sed values of shear parameters. void ratio,
In addition to the data listed in Chapter 3 !l~d_ consolidation characteristics, moisture content
analysed values thereof, tbe following data are also in-SItu density, sensitivity and permeability. •
required to be collected for carrying out the Struc- (II) For sandy soil. grain size distribution curves
tural Desjgn~. There are some repetitions: However, from undisturbed samples obtained at 3 metre
these have been included for convenience. intervals from each bore hole. Dry densities,
relative densities and angle of internal
(a) High Flood level and Minimum water level friction.
in the river.
(i) Modulus of subgrade reaction at the proposed
(b) Design Pond Level foundation level. Lf the structure is long' or
if there is wide variation in tbe properties of
(c) The lowest and highest tide levels in case of tbe foundation materials, tbe value of modulus
tidal streams. of sub-grade reaction in each unit/block
90
9f
separated by double pier. If it is not fessible super-imposed dead loads consideting the portion of the
to determine' the modulus of subgrade reaction raft between joints as single unit. The gravity floor can
at site. the values given in Appendix 7.3 be of plam concrete or masonry. The top profile of
_may be adopted for design purposes, depend- the floor can be fixed up based on the guide lines set
ing on t\le type of soil met with. out under Hydraulic Designs. While the uplift pressure
percentage under the floor can be estimated as per
( j) Results of feasibility studies for driving sheet Para 6.10 and its sub-paras, the profile of the hydrau-
piles or otherwise if the river bed consists of lic jump under High Flood and Pond Level conditions
bouJders or is made up of stiff soil. can be worked out from Montague Curves (Figure. 6 8)
by finding the values of the depth of the flow over the
7.2. Design of Cut.o1fs profile of the floor.
The upstream and downstream cut-off's of the diver- 7.3.1. Gravity Floor
sion structure may be of &teel sheet piles anchored to
the pucca floor by means of R.C.C caps or of masonry The adequacy of the thickness of the floor .has to
or R.C.C. The depth of cut-offs are fixed as discussed be checked for the three conditions, viz.• (i) No flow
in Para 6.9.1. downstream which gives the maximum staticnead (in
bigh flood and (iii) flow at pond level. Under (in
'i.2.1. The sheet pile cut· offs would be designed as and (iii) hydraulic jnmp may form over tbe down-
sheet pile retaining walls anchored at top and to resist stream glacis. From the percentage pressules estimated
the worst combination of forces and moments. con- already, the levels of the hydraulic gradient lines at
sidering the possible sconr on the outer side and earth key points under different flow conditions can be
preSllure and surcharge due to floor loads on the inner worked out. Both the hydraulic gradient lines and
side differential hydrostatic pressure computed on jump profiles are to be plotted neatly.
the basis of the percentage of pressure of seepage
flow below the floor. etc. If the effect of the cut-offll 7.3.1.1. The floor thickness at any point should not
are taken into account for resistance against forward be less than the maxi mum ordinate between the sub-
sliding f the structure. they have to be designed to soil hydraulic gradient line and the water sudace
withstand the passive pressures developed. The (or !loor surface if there is no flow) divided by (G - I)
R.C.C. pile caps would be designed to transmit tbe where G is the specific gravity of the material of which
forces llnd moments actlDg on the steel sheet pile tbe floor is made of such as masonry or concrete. The
cut-offs to tbe pucca floor. . specific gravity f concrete is taken as 2.25. On the
glacis, the maximum of the ordinates under any of the
7.22. The masonry or R.C.C. cut offs al&o would three conditions would govern the floor thickness at
be designed to resist the forces and moments specified that key point. The thickness of the :floor adopted
for sheet pi!f> cut-otIs and they would he treated as for construction ~hodd be at least 10% more than
Cantilever walls fixed monolithically with the pucea the thickness required calculated as above.
flo r.
7.3.J.2. The uplift pressure in the jump cistern and the
7.2.3. The upstream intermediate cut-off usually has rt"quirt"lTIent of floor thickness are moderated to some
the same section as the upstream tmd cut-off' and tbe extent by the following factors:
downstream intermediate cut-off' same :IS lhc down-
stream end cut-off. (i) Due to a backward rolling of flow of water
into the jump cistern. it is partially filled up
7.2.4. The required sections of the sheet pile cut-off reducing the unbalanced uplift pressure.
would be worked out and the nearest section subject
to practical availability would be used for construc- (ii) The uplift due to maximum depth' of tbe
tion. cistern would operate only at the deepest f.loint
of the trough. becoming smaller on either
7.2.5. Typical example of Jesign of sheet pile cut-off side. As the floor has always got some beam
is presented in AppendIX 7.1. action. it may be designoo in small lengths (of
about ! to 2 m) for average uplift on ea\ h
7'3. Design of IlDpervious (Pucca) Floor strip. rather than for the maximum uplift at
every point As the jump is likely to travel
The impervious or pucca floor of the diversion over practically tbe entire glacis for varying
structure may he of two types. namely. gravity type diicharges this allowance for spread results in
and reinforced cement concrete raft type. In the considerable economy in the floor thickness,
gravity type, the uplift pressure is balanced by the
self-weight of the floor only considering unit length (iii) The vertical part of momentum remains un-
of the floor. In the raft type. the uplift pressute is affected at the jump and resulls in an i£llpact
b~lanced by the weigbt of the floor, piers and other on tbe herizontal floor beyo'nd the too of'
•
92
,gl~~is. ~t, th~ toe' Qf the glacis and-;for some 7.3..2.3~ "{For:'design of ,raft :tising the' theory of beams
. '. distance.aQove it, therefore, the jet would exert on elastic.fo:undation, Hentenyi's method is usually
a downward plessure equal to the rate of adopted. Appendix 7.3 is. a brief note on the
cbange of momentum in the ver,tic~l direction. Bete~yt"s theory and mentions about the procedure for
The magnitude of tbis force may be taken as analysis also. The relevant tables given in, Hetenyi's
nearly equal to 2/3rd the thickness of the jet book are to be referred wherever required.
at the toe. For determining the range of jump
formation, tbe actual positio~ of the jump on 7.3.2.4. Typical calculations of raft using Hetenyi's
a sloping glacis has been found to be upstream theory are presented in Appendix 7.4.
of the calculated position by a distance equal
to (D 2-D1 ) approximately. 7.3.2.5. The overall stability of the barrage/weir iIi
the longitudinal (flow) direction against sliding and
7.3.1.3. In the case of gravity type of floor, the abut- overturning is generally checked for pond level condi-
ments and piers are either independent of the :!loor, tion with water level on the dis side for minimum flow
separated from it by means of water tight seals or and gates of adjacent bays closed. For this purpose,
monolithic with the floor. If they are to be monolithic one span width including a pier is taken into consi-
it has to be en ~ured that the thickness of the floor is deration. All th~ stabilising forces including the self-
equal.to or more than half the length of the span so that wt. of the structure, wI. of water, wt. of road/railway
with 45° dispersion, the. need for checking for tension bridges if any, wt. of gates and hoist bridge, etc., are
does not arise. However, it is also to be noted that at to be estimated. The de-stabilising forces include
portions where the floor is failly thick, some arch uplift pressures, water pressnre on the closed gates,
action may develop if required and where it is thin, it er.rth pressures acting on the cut-offs and floor, earth-
may act as a beam to the eAteot it can stand tension quake forces, etc. While analysing, advantage of the
when called upon. .Both these factors serve as' addi- boxed earth below the floor of the barrage and passive
tional safeguard. Hence the designer ba~ to use his pressure of the cut-offs may also be considered where-
discretion in selecting the type of floor, either gravity ver applicable. Typical stability calculations are .given
or raft. Where the gravity floor is of plain concrete, in Appendix 7.5.
suitable temperature reinforcement will have to be 7.4. Design of Peir
provided.
, In the case of diversion structures, constructed of
7.3.1.4. Typical example of design of gravity floor is reinforced cement concrete, piers would be constructed
presented in Appendix 7.2. monolithic with the pucca floor. 10 the case of gravity
floor, the piers would generally be made independent
7.3.2. Reinforced Cement Concrete Raft of the floor with proper joints and sealing arrange-
ments. Sometimes, they are made monolithic with the
Generally, the design of the raft is carried out floor also as discnssed in para 7.8.1.3.
based on the theory of beams on elastic foundation
which takes into account the value of Modulus of 7.4.1. The thickness of the pier is fixed from consi-
Subgrade Reaction (K), span length, total length of deration of (il forces and moments transferred by the
raft, etc. oier to the floor/foundation (ii) minimnm thickness
7.3.2.1. However, for small spans upto 6 metres, the required at tbe block-outs for the main gate aod top-
raft can be designed :as a continuous beam resting o.n a Jog grooves and also ~iii) the weight of the pier .required
homogeneous foundjl.tion, If the abutments are made for counter-acting the nplift pressure. The thickness of
independen t from tbe raft, joints wIth water seals of R.C.C. pier generally varies from 1.5 to 2.5 m.
acceptable stanoards are to be provided. The raft has 7.4.2. In the case of raft type of floor, the piers are
to be designed for the moments caused by tbe wor t generally extended upto the fulllengtb of (he raft to
combination of the following forces: ,i) nplift (ii) soil avoid cantilever action at the ends of the floor. How-
reaction (iii) moments transferred from the abutments ever, in the case of gravity floor, the length of th,e pier
and piers and iv) seismic forces jf any. For this pur- can be restricted' according to the minimnm require.
pose, the loads transmitted by the abutment and piers ment from considerations of rod/rail bridges, hoist
are to be assumed to be distributed uniforrnl1y on the bridge, space required for housing jnstruments if any,
foundation. For the design of rafts, any standard text main gate and' sto'plog grooves, space for storage of
book on Foundation Designs and IS : 2950 (Part - 1)- stoplogs adequa.te length to prevent cross flows occur-
1973 (Code of Practice for Design and Construction of ring which may cause ~amages to the floor and beyond,
Raft Foundations: Part I - Desi!,!n) may be referred to.
etc.
7.3.2.2. For spans greater tban 6 metres, the fioor is 7.4.3. The height of the pier on the upstream side is
designed as a finite. beam resting on elastic foundation oenerally fixed such that the top is above pond level
and subjected to cuncentrated loads and moments at ~ith adequate free board. The height should be fixed
the pier and abu.tment points. . '. from consideratiQns of the requirement of the weigh t
93;"
df Hie ,pier in ~o~pteraq,ting-the uplif~ 'pressure. oh the 6;9.3.<The thicknessof'the.dotible pier with a joint in
downstream side, the .top 'qf the pier shobld ibe' above: between usually v'aries from' 3 to 5 metres; The thick-
the high flood lev~] upto about 3 m byyond the end Qr ness, length and height of double pier are governed by
the bridges and instrumentation platform if any and the same requir~ments as those of sip.gle pier explained
thereafter it can, be reduced according to low flood in paras 7.4.1., 7.4.2. end 7.4.3. Each unit of the
levels. Under the road/rail bridges, adequate free double pier (two end piers of adjacent bays) would be
board above H F L. needs to be given so that the bear- structurally independent of the other without any
ings of the bridges are not affected by the high flood. transfer of loads and moments froni one to the other.
Adequate allowance shauld also be made so that the The design principl(s for double pier are the same as
beams of the bridges are not hit by floating debris those for single pier and each unit of the double pier
during high floods. 1 he height is also governed by would be treated as acting completely independent of
the requirement of weight to counteract uplift pres· the other pier.
t;ures. While fixing the top level of the pier in tbe main
g\ite portion, it is to be ensured that the bottom of the 7.4.8. Under the bridges, properly designed pier caps
gate is atJeast 1 metre clear of the affiuxed high flood would be provided satisfying aesthetic requirements
level. As already discussed in Para 5.2.5.4., the height also. For spans upto 18 m, the thickness of the pier
of the pier in this portion has to be carefully planned cap is generally kept not less than 300 mm. The rein-
in earthquake regions. forceQJent in the pier cap would be laid distributed
both at the top and bottom in the longitudinal and
7.4.4. The design of the pier is carried out to resist transverse directions. In addition to this, two layers
of mesh reinforcement of 6 mm dia. spaced at 75 mm
.. the worst combination of the following forces and
moments: centre to centre would also be placed under the bear-
ings of the road/rail bridge beams.
(i) Deal load (ii) Live loads due to road/railway
bridges (iii) Impact and Braking effects of live loads 1.4.9. Road Bridges
(iv) Temperature forces transmitted through bridge
bearings (v) Dead and Live loads of gates, stoplogs, The road bridges over the barrages/head regalator
<:ounterweights and the hoist bridge (vi) Breaking effect (s) are to be designed for the -relevant I R.C. class of
of gantry crane (vii) Buoyancy (Viii) Differential hydro- loading as per the. requirements of the projects. The
static pressure with one side gate open and the other roadwidth including that of footpath, etc., are provided
adjacent gate closed (ix) Seismic forces and moments as per requirements. Relevant Indian Road Congress
if any and (x) Hydrodynamic forces due to seismic Codes may be referred for the details of loading and
<:onditions if any. The requirement of reinforcement other design norms, etc.
at various levels would be calculated and provided for
with suitable curtailments. The reinforcement would 7.5. Design of Divide Wall
be adequately taken into the raft/foundation slab as
the case may be and anchored properly. The functions ~nd layout of divide wall have been
explained in pal'a 5.2.6. and its sub-paras. The hy-
7.4.5. In the block-out portion, the minimum width draulic designs of the same are outlined in para 6.11.
of the pier between the blockout on either face would The upstream divide wall would be designed to resist
be 600 mm. While calculating the reinforcement in the the differential head on account of the velocity of flow
pier, the increase in the sectional area of the pier in in the pocket due to the gates adjacent to the divide
the block-out zone due to the second stage concrete is wall on either side being kept in open and closed con-
omitted. Block out-zones would be designed to with- dition. The downstream divide wall would be designed
stand the concentration of stresses due to the worst to resist the moments due to the differential head
combination of the forces and moments mentioned in caused by the closure of gate on one side and opening
para 7AA. and differential hydrostatic pressure with of gate on the other ~ide. While the range of differen-
the gate closed on one side and stoplogs dropped on tial heads for the designs would be indicated by hy-
the other adjacent side. The second stage concrete draulic model tests wherever conducted, for prelimi-
in the block out zones has to be effective ly bounded to nary desgins, usually a differential head of about 1.5 to
the main pier concrete by the provision of adequate 2 m is assumed. Under seismic conditions, differential
dowel bars and secondary reinforcement. head due to wave action is not considered as the likeli-
hood of earthquake and high wind occurring simul-
7.4.6. Typical design calculations for pier are given taneously is rather remote. Dynamic increase in water
in Appendix 7.6. pressure is calculated from the formula,
7.4.7. Tn long structures, there would be a number of p=875 ~~ v' H.y where
units/blocks depending on the construction programme
and variatioll in the foundation strata as explained in p=hydrodynamic pressure in kg/m2
para 5.2.7. These are separated by double piers with
.cross cut-off/pile line at the bottom as outlined in para Olh=design horizontal seismic coefficient
94
H=height of water surface from the level of of the coefficient of friction, determined by field
deepest scOur in metres, and investigations are t6 be used. If this is not available.
the following value~ of coefficient of friction may be
used : -
y=depth of the section below the water surface
in metres. (i) Coarse sandy soil containing no silt or clay
-0.55
Reference may be made t,o IS : l893-1975-Cri-
(ii) Coarse sandy soil containing silt-OA5.
ter.ia for Barthquake Resistant Design of Structures
(Third Revision). The divide wall will also be checked Also, wherever concrete/masonry or sheet pile cut-offs
fOI t1leir overall stability considering tbe forces and
have been provided 50 percent of the passive pressure
m.oments due to self. weight, water, ice (wherever developed below the level of the deepest scour may
applicable), uplift, earthquake, etc., acting on the wan. be comidered to the extent of the structural strength
of the cut off plovided while calculating the counter-
7.6. Design of AbutDlents acting forces against sliding.
7.6 3. Typical design calculations for one of the
The general considerations for the layout of blocks of the abutment are presented in Appendix
abutments are discuSlled in para 5.2.8. The top width 7.7.
of the abutment in each block is fixed as per the
requirements dl:\e to the loads and moments and 7.7. Design of Flank Wall
minimum width requiTed for block-outs of main
gate and stoplog grooves, bl iJge bearings, gate trestle The general considerations for the layout of flank
toundatlOn, etc. The minimum wjdth of abutments walls are discussed in para 5.2.9. The top width of
clear of the block-outs and behind bearing niches the flank wall is generally kept not less than 600 mm.
would be kept as 600 mm. GcnetaUy the minimum The top width of the flank wan made up of c.c. blocks
top width of the abutment -in the upstream and down- varies with the sIze of the c.c. blocks and generally
stream blocks iskept as 600 mm and the same in the it is 1500 mm. The flank wall is also designed as an
gate and roadjrail bridge blocks is kept as L2S0 and earth retainmg structure for the worst combination
1400 mm respectively. of the following forces and moments :--(i) Dead
loads (ii) Earth pressure, live load surcharge and
saturation pressures (iii) Uplift (iv) Seismic forces
7.6.1. While designing the various abutment blocks, and moments if any and (v) Hydrodynamic forces due
worst combination af the following forces and mo- fO seismic ~ondition if any. Just like the abutment,
ments pertaining to tbe block under (,;onsideration flank wall also has to be checked for safety against
is taken into account : (il Dead load (ii) Live load allowable be'Uing presssure, overturning and sliding.
due to moving tr~c over the bridges (iii) Impact The earth pressures acting, btbind the wall would be
and braling effect of live loads (iv) Temperature calculated by any of the standard methods avail-
forces transmitted through bridge hearings (v) Dead able.
and Live 10ad1> of gate and gate bridge (vi) Braking
effect of gantT\' crane (vii) Earth pressure, live ]oad 7.8. Design of Return Wall
surcbarge aud sllturation pressure (viii) uplift (ix)
Seismic forces and -moments if any (x) Hydro· dynamic The general considerations for the layout of
forces due to seismic conditions if any. The abutment return walls are discussed in para 5 2.10. The other
is -generally designed as a retaining wall, either as design considerations like top width, for<~es and mo-
cantilever type or counterfort type as tbe case may ments, etc., are similar to those or flank wall outlined
be. The reinf0rcement will be provjded accordingly in para 7 7 above. '
with suitable curtailment or spacing wherever
necessary.
7.9. In tbe foregoing paras, genera) guide lines for
t~e st~uotural design of the main componenU af the
7.6.2. The abutment section, desi~ned on the guide dIverSion structure have been set out. These in
lines given above, .has to be checked f01 -saf~ty against addition to the other guide lines discussed in som'e of
allowable bearing preSllure, averturning and sliding. the other Chapters on head regulator, silt exclusion
The allowable bearing pressure would be worked out navigational facilities, fish pass and river training
by £eld and Jaboratory tests foJ]o1Ving standard work.s. can be m~~fied by the designer to suit the
procedures. The factor of safety agailtst overturnjng conditIOns obtalOlDg at the site. But safety and.
should not be, les$ than 2.0 ander normal conditions economy are always to be ensured and constructional
of loading and not less than 1.5 under seismic condi. aspects should always be considered while fixing up.
·tiQns. While calculating the sliding fact-ors the value the reinforcement, piles, etc. ,
.,!. . • -
. ":,. ':-
I.
,' • .: t·" ~
,-
.'
f ,;-,.-
.'
Coeff of active earth pre~s.ure between A and B/. ,. .- .. :~.": "; ".0;
'-, ~.
T +24'50 A 130
.----""
1380
0=2'52
FIGURE 7.1
95
-96
K--
(y-Q'
1. x (Y""""a)
(y-a)
3 "iU;.
'( t, = 1970-:-130.x-}0.Sx ,0
l
- _Ki (y-a)Z .
,x2 + )2.4x=- 187.5=0
RB- 6
x ~12.4±-V154+750 =8'81
2
J
(y-a)~ ~RB =J6~~;60 =9.24 Hcnce maximum moment ;; .
Y=9.24+2.52=I1.76 ft. =1970x 8~8.-65x 8'81 -3'5 x 8'83
Allowing 20 percent extra embedment in sandy =17300-5040-2380=9880 ft. lb.
material (as suggested in Yawata sheet piling literaturc)
-118500 in. lb.
Yr'QcI=·11.76 X 1.2= 14.1 .
Assuming [-{6000 psi
Scour Lcvel :;=+ 10.70 i
118500
:. Bottom of sbect pilc=-10.7-24.1=-3.4 or say Z"Q4= 16000 7'4 in'lft run of walt
...:...3:5 of pilc linc.
<-,
to:; ,
APPENDIX 7.2
Calculations are presented for a gravity type of The levels of the hydraulic gradient lines at key
floor with the following parameters: points under different flow conditions are given ID
Table 7.1.
Pond level =328'66 m
The table 7.2 has been prepared for plotting the
HFL for an anticipated flood of 17000 cumecs hydraulic jump for the High Flood and Pond level
conditions.
=331'63 m
The thickness of the floor is determined by divi-
Rterogression at High flood=O.61 m ding the unbalanced head Igiven by the ordinate bet-
.... - - - - 4 2 0 7
1.. m---------<j.,
327 2
32064
319·21
1-_ _---"2~)_=2,;.:3m:.:..-_ _-j )1.1 dB
FIGURE 7.2:
97
..
9&
TABLE 7.1
Condition DIS WL DIS W.L. Head Ht/Elev. of Sub-soil H.G. line above datum
Datum
'/f'i ~ O:[:~3 t.
CPE qlD cpc CPEl cpD l CPCl CP E2 CP D 2 ql C 2
.
.'
• ::.=.~:!:': ~ !...:.:::-:~ -; ~t~/
No flow Height i.
Maximum 32293 328.66 5.73 5.73 4.44 4.21 3.31 2'] 238 1.9 1.52 0
Static Elevation 328.66 327.36 327.13 326.24 325.63 32538 329.13 324.45 322.93
H;~ad .. . I.' r. ~ ':', ..' , ;. ~ I I .'
~ . '\
Elevation· 332.32 332.03 33L.97 331.77 331-.63 331.56 331.45 331.37 331..02
,I ~ . ,. .
The hydraulic gradient lines in accordance with the above values have been plotted in the sketch.
r
TABLE 7.2
2 3 4 5 6 7
HFL
:---~--.
.
-
.
:
.
-
.
~
Pol.
123 78 0
Top p.rorile
1. 8.63 4.88 I
5.34 15.08 1.68 3.40 2062 2.6
5.03 I (av.)
3. 18.9 2.29 I
·2.26 I 2.2~ 225 1.73 1.83
2.21 I
j I
APPENDIX 7.3
100
•
.
Differentiating the above Expres$ion; Here>' includes the, flextural rigidity of the beam
as well as the elasticity of the supporting 'medium
(foundation soil) and is an important factor influen-
.;'.(3) cing the shape of the elastic line. For this reason the
factor A is called the 'Characteristic, of the system and
its dimension is length-l. The term 1/'.\ is frequently
Therefore from (2) and (3) referred to as the charact,eristic length. Consequently
''\x' will be an absolute number.
d'y ,
El--=--Ky+q
dx' ,
Expres9ioD (IV) represents the general solution for
This is the differential equation for the deflection the deflection line of a beam supported on Elastic
curve of a beam supported on an Elastic foundation. foundation and subjected to transverse bending force.
Along the unloaded parts of the beam, where no By succes~ive differentiati<?n, Expressions for slope of
distributed load is acting (q=O), the equation would the deflectIon curve, Bendtng moment and shearing
reduce to force can be obtained.
using
Relative Standard Penetra- Moduls of sub-
eI A:t=cos >.x+i sin Ax density tion Test Value grade reaction
e-iA:t=cos AX- i sin AX '(N) (blows for 30 K s in kgfcm t
em.) ---------
and introducing the new cons:tantil For dry For Sub-
or Moist metged
c 1 , C" Cs and C" Where S~ate State
•
102
K2 =Mpdulusof 8ubgrade ·reaction
M~dulus'~f S~bgrade R~c~ioD fo~ 'for a'square footing of side 11.
Cohesive Soils.
. .The effect of shape is negligible in the case of foot-
ing on cobesionless materfal.
Consistency Uilconfiend compres- Modulus of
sive Strength Subgrade . Loads
kg/cm2 reaction K s
in kg/cm 2 . (a) Gate, Road and Railways Bridges. These loads
Include tbe dead weight of the Bridges and tbe antici-
pated max live loads on tbe Bridges. Theie loads are
~ransrerred to tbe raft through the piers dispersing.
Stiff 1 to <2 2.7 Itself at 45 0 to the raft level.
Very Stiff 2 to <4 5.4 Due to the Braking and tractive effect of the live
loads Horizontal forces act at the bearings and are
Hard 4 and over 10.8 transferred to the raft as moments at a dispersion of
45 0 to the raft level.
The above values are based, on the assumption that In the event of Earthquake condition Inertia and
the subgrade reaction does not exceed half the ultimate impact forces are also to be considered.
bearing capacity.
(bl Dead weight ofpiers. Tbe weight of the pier
The values given above are applicable for a square is considered on the raft as a concentrated load at the
plate 30 cm X 30 em or beams 30 cm wide. For find- pier location.
ing the values of subgrade reaction K corresponding to
sizes and shapes different from those of the following Inertia force is also to be accounted in the event
relationships shall be used. of earthquake condition.
Where ,,
• t
.
j'
•
I" I'
:1
II ~". /.
, -.
~
VI ' • I
.: .,
,I -:',r; .'," r,", '0'
The pucca floor of the barrage (in the example .v: 58 48T
104
105
•
TABLE 7.4
A' A B C 0 E F
a=13'15 ()=CAa+D;\a
4A='710P =-0'1376-0'0670
>'=01775
=-0'2046
;\a=2.33
Also _1_ =1'40
. I 4;\
M=-:;u- [aCh-2() Dl.x+C;\, I a-x I ]
a
4"["=0212
where a=C;\a+2D;\a
=-0'1376+2 (-0'0670) 1t=-0'575
4A
=-0'1376-0'0134
M=O'212 CAx+O'S75 Dh+1.40 CA
==-0'1510 I a-x I (Table 7.5)
TABLE 7.5
:
S.No, A B C 0 E F
FIGURE 7.8
M=0.00475 CAx-0.166 D>.x~ 0140 C>' Multiplying the unit moments by respective loads
I x-a I v. The first table by 55.33 and second table by 58'08
and third by 57.48
Moments due to differential head is given in Figure
7.8. "
TABLE 7.6
..
A B C D E F
S.No. A B C D E F
A B E F:
FIGURE 7.9
108
Fixed end moments wJ2 0'9 x 12'12
Sagging moments =--
8 8
16'4
- w1 2 -O'9x 12'1%
MEC= -12- 12 =-11 w1 2
Moment at F due to udl on EF' =- 2
MCE=+l1 & -ll=McA
O'9x3'33S
MAC=+U 5
2
Moment at E due to udl on EF'
O'9x7'72 2
~......"...--=26'6
2 '0
= ~O·49
.
f
"
~ 20
30
JO tOl 300 C/C
c
~W ~~ I..!- ~ '0
110 -0'4\)
26.6 -110
-15·.
11·0 -11.0
-1·8 -5.26 -10·51
0
,. II c F
,
J·2 -16·26 :r Icl 3' ... 0
'".~ 30
...
:c 40 JIl @ 300 C/C
3011» 300CIC
'0 + 20 06) JOO CIC
A' F'
A • B C D E F
11.411 -i •. J \)·73 1-70 20'0 I 5.9
... \
•
APPENDIX 7,5
...... .J(}
,000 ,4000 I 6000 • 4500 ;2000 /0000 16000 21500
17'5
L"5
I-
, 10000 4500 f02! 16500 23000
FIGURE 7.12
",
109
•
110
Slope Com:etion=
4'SX4'S
56 ·0'361 %
,pH Corrected=62'003+ 1'330=63'333%
Point Distance ., Width R,L, %Pr, Uplift H . TWL~RL Total Average Uplift
Totaf 2i2'182
Total upli ft/bay= 212'182 X 12'1 xl =2567'4 say 2580 Toones allowing f9.r CJ}t-.pff width
III
rea 0 , ".
U IS cut off level = I 3'0
: .'''1
Head in metre
DIS Cut off 6'334 ' 4'500 5'417 3'5 12'1 229'41
APPENDIX 7.6
113
114
Dispersion width at R,L. 513'5 = 222 =7'17 TIm .. ,(2)
Wt/m 31
=10+(519'5-513'5)+
(521'5-516'5) Between R,L, (519'S-517'5)
-2'1 x39x2'4x2=394 T
=10+6+5=21 m
~ \: ..
N,E,Q.. Dispersion Width=39+4=43 m
V=~=S'2T/m
21
Wt/m = 394=9'IS TIm
43
...(3)
l - - - 2 I ---<~~
6·60
.
T
1'53
i.
FIGURE 7.13
L
FIGURE 7.14
=i{(6'6)S-(l'53)3 }
Hydrodynamic Moments
Uplift Pressure 2
p= -3- xO'577x6'6=2 54
=I'53x2'I+ix5'07x2'l=3'21 t
5'32 2 .'
M=2'S4X -S-X6'6=6'7 T m~
=8'53 T'
CALCULA.TION OF REINFORCEMENT
Derivation or General forDlula :
-T L
d-
T --
e
1
d
I
I -ck"
T
Id,"1
--
FIGURE 7.15
/ 11m
The pier has been designed as a column section t=Tensile Stress in tension zone.
I m x 2 'I m subjected to combined bending and direct
thrust equations used for calculations of reinforcement .!!!!l-= _n_
are given below: t d-n
Permissible Stresses (Earthquake condition)
t= me (d-n)
1=2100 kg/ems n
..1. c
= - (50 2 n)
ItTt n
-+--~----+-_-_+-_--I-+----V---
]~)1~\ C
n
C'!m-l
n-de
dt - --( - -
C' = Compressive stress in steel.
T 100 .1
11m
=14C (n-lO)_AC
n (
e+9S )= 1667 (600 n -ns+160 An-1600 A)
ll
2
1 50 n +29 An-3140 A
. C
= - (14 ACn-140 AC) (e+95) (50 n2 +29 An-3140 A)=1667 (600 n 2 -n S
n
C
+ 160 An-1600)
C+C'- -- {50 nl!+14 ACn-140 AC}
n n S +n 2 {3 (e+9S)-600}+AIl {174 (e+95)-160}
...(1)
1~ Pn
.'. equating P=Total Stress. t= - - (200-n) and
n
c= 50n~+29
-
An-3140A
P=CA +C' AC-tAt P
NC= 50 n+29 A-3140 A
=2-
n
{50 n2 +14 ACn-14 CAC} -n
_2..
n
{3000 At-IS Atn} Zone 3-3 at R,L. 513 '5
e=22S cm P=38'15
=~{50na+14 ACn+15 Atn-140AC-3000 At}
n A= 10'6 cmll i,e. 18 mm rP @240 c/c
C n8 +n2 {3(e +95)-600}+An{1'74(e+95)-160}
P=- {50 nll +29 An-3140 A} ...(3)
n
=A{l89(e+95)-1600}
Taking moments about tensile steel.
+2..
n
(14 An-140 A) 190 c _ _ _---=3:..=..81:..:..50-=--_ _~_
50x35+29XI0'6-3140 1~~
C
= - 1667 nl (600-n)
n
38150 38150
= 1750+307-950 = 1107
+..£ {2660 An-26600 A}
n
=33'7 kg/cmll
= C {10000 n2 -1667 n +2660 An
2
n 15C
t= --(200-n)
-26600 A} n
•
lIS
37420 ~74
= 15X33'7 x165
35 =-2100+493-1270 132-
, ,
t
APPENDIX 7.7
The left and right abutment of the Barrage are (j) Hydrodynamic forces due to seismic condi-
• 66'S m long each. Depending ()n tbe intens~ty of load- tion if any.
ing over the entire length of the abutment, It bas been
divided into fOUI blocks, namely (a) uls block (b) Gate The abutment has been checked for safty against
block (c) Road bridge block and (d) dis block. The allowable bearing pressure, overturning and sliding.
abutment bas been designed as a retaining wall sepa- Typical calculations for tbe uls abutment block are
rated from tbe undersluice raft by an expansion given below.
joint with seals. Each block bas been designed for
the loads and moments acting on the block under
consideration.
523·00
The top width of the abutment in each block has
been fixed as per the requirements due to loads and
moments, minimum width required for blackouts in
the main gate and stoplog grooves, bridg bearing,
hoist trestle foundation, etc. 520·00
(e) Dead and Jive loads of gate and gate bridge Uplift
5,2
5· 2 x 10 + i I x;o I
(f) Braking effect of gantry crane
(g) Earth pressure, live load surcharge and satu-
ration pressure
(h) Uplift
------1
(i) Seismic forces and moments if any FIGURE 7.17
119
}20
81. No, Item Vertical forces Horizontal forces Lever Moment Moment
arm +ve -ve
(d) Surcharge
B, Horizontalforce earth
pressure
C Uplift pressure
= 2S'lf tan 30
= ;v ( l± ~e) 95'034 X 'S765
25"11
p '95'034 ( 1 + 6 X '34 )
r 10 10 =2'18
•
Earthquake Case
81. No, Item Vertical force Horizontal force Lever Moment Moment
arm (+) ve (-) ve
6. iX'2Sx2X1'8 0'10375
7. ~~ S'79 X2 X 1'8 7'400
8, iX4'SxO'62X2 0'630
9, S'17x4'Sx2 17'2S0
10. I X S'17 X0'7 X 2 1'500
39'636
122
Earthquake Case (Contd,)
81. No, Item Vertical force Horizontal force Lever Moment Moment
arm (+> ve (-) ve
(c) Surcharge
Horizontal Force
Earth pressure
6'888 26'90
Inertia Forces
(b) Backfill
Surcharge
6'07 X l'6xO'l 0'971 S'2 7'95
-123
Calculating. tbe rilODlerifs at·, various levels. as
befoTe, max. moment at the'bo,Hom of stem
~85.400 ¥ l<g~'
At required
115.409
~0'87 x-{qOX 14()U ;><1"5
=33'4 cm!,
-.- ':.-
provide 20_ mm ~ bar,@ 15~ in.~ c/c:ln tw.o rows~'
....10 At base curtailment at differenllevels has been
.... done as per requirenwnt shown in 'the' diagram. ....
~V
= ~H tan¢> ae,.m ¢ I~C/C
20
~
_ 87"914 x "5765
-. 45'83
=1"105
=1'11 ~
o
o
eo
~ )0
~ 20mm ¢ ~OO etc
~ i'--..
....
:';,."
1048 ~
710
o
1,0 20 3-0
~
4.0 5-0
QiSlonce from the ju~ction in
10m tTl
I.. •I
FIGURE: 7.20 UIS Abutment Block: Heel Reinforcement
FIGURE 7.19 Curtail Diagram, .
124
- '-
523.5 -
522·5
\
52~ ·5
\ ..
.'
;
...
Gl
'"E 520· 5
\ 20 mm Ql 3 bo CtC
=
c
o
o
~ 519. 5
w
\ '\
5
I~ ~Omm ~ I ~O C/C
"
511. 5
~ .........
~
~
~16. 5
o 5 10 15 20 25 30
r--.-
Pressure steel reguired in sq. metre