QUALITY COMPLIANCE REPORT

Project GSP Construction Site, Bhopal


Contractor MCL-SIIPL- (JV)
Date 24-07-2021
Recording no. QOR-GSP-0003
Closure Mr. Faizan ali
Verified Mr. Umakant Gupta

FINDINGS AND SUGGESTED CORRECTIVE MEASURES

Category/ Location:
Compressive testing of concrete.
1. Finding:
- Improper shape & broken edges of concrete
cubes are found often due to negligent
attitude & engagement of unskilled
manpower for important job.

Recommendation/Corrective/Preventive Actions
- Doing proper cube cast filling by skilled
manpower under strict supervision of Quality
Engineer
Remediation Timeframe:
Immediate
Corrective actions taken
The quality of cubes has improved, We hired two
skilled Lab helper for cube Casting & Quality
Engineer will also be present at the time of
casting.

Category/ Location: storing of TMT Steel


2. Finding:
- Some TMT Steel is kept on soil
directly which is never
recommended to avoid rusting due
to moisture.
Recommendation/Corrective/Preventive
Actions
- Recommended to place TMT steel
on raised platform/ centralized
concrete platform
Remediation Timeframe:
Immediate-

1|Page
Corrective actions taken
Issue has been resolved, we shifted all
the steel on raised platform & centralized
all the steel at steel yard near plant.

Category/ Location: Academics C


3. Finding:observed backfilling of soil with
boulders
Recommendation/Corrective/Preventive Actions
- Segregate and remove the boulders from
excavated earth before backfilling

Remediation Timeframe:
Immediate-
Corrective actions taken
We removed the boulders in backfilling. The video
file of removing the boulder has been attached
with QOR please find attachments.

Category/ Location:COSA- 1
4. Finding:
- Backfilling without layer
wise compaction.

Recommendation/
Corrective/Preventive Actions
- Do layer wise compaction
& testing as per
specification
Remediation Timeframe:
Immediate-

Corrective actions taken


We removed extra soil filled in
backfilling, & doing layerwise
compaction as instructed.

2|Page
Layer wise compaction has
been checked & jointly signed.

Category/ Location:Convention
5. Finding:Post Concrete status- Bulging
of Footing side FC523(Grid J/5)
Recommendation/Corrective/Preventive
Actions
- To use adequate & stiff formwork
with required supporting system.
- Chip out the bulged portion & make
good to the size of footing
Remediation Timeframe:
Immediate

Corrective Actions taken


we chipped out bulged portion & in
future we use good quality stiff formwork
for better finishing & to avoid any type of
bulging..

3|Page
Category/ Location:Convention Building
6. Finding: Shrinkage Cracks on concrete
surface

Recommendation/Corrective/Preventive
Actions
- Concrete Surface should be kept
moist with gunny bags initially&
once concrete gets dry ,surface
should be ponded /poured with
water
Remediation Timeframe:
Immediate
Corrective actions taken
We covered it with gunny bags &
poured water & we definitely not
repeat this mistake in future.

Category/ Location:Cosa 1 B
7. Finding: Honey combing of RCC
column
Honeycomb observed at Column (Grid
M/25)
Recommendation/Corrective/Preventive
Actions
- No cement slurry come out of
formwork but putting form on joints
- To ensure proper vibration of
concrete with adequate size of
needle
- To chip off all loose concrete and
grout with GP-2
Remediation Timeframe:
Immediate
Corrective actions taken
We chipped of all the loose concrete
& repair it with GP-2 Material, We
assure you to do proper vibration with
adequate size of needle.

4|Page
5|Page