Professional Documents
Culture Documents
Category/ Location:
Compressive testing of concrete.
1. Finding:
- Improper shape & broken edges of concrete
cubes are found often due to negligent
attitude & engagement of unskilled
manpower for important job.
Recommendation/Corrective/Preventive Actions
- Doing proper cube cast filling by skilled
manpower under strict supervision of Quality
Engineer
Remediation Timeframe:
Immediate
Corrective actions taken
The quality of cubes has improved, We hired two
skilled Lab helper for cube Casting & Quality
Engineer will also be present at the time of
casting.
1|Page
Corrective actions taken
Issue has been resolved, we shifted all
the steel on raised platform & centralized
all the steel at steel yard near plant.
Remediation Timeframe:
Immediate-
Corrective actions taken
We removed the boulders in backfilling. The video
file of removing the boulder has been attached
with QOR please find attachments.
Category/ Location:COSA- 1
4. Finding:
- Backfilling without layer
wise compaction.
Recommendation/
Corrective/Preventive Actions
- Do layer wise compaction
& testing as per
specification
Remediation Timeframe:
Immediate-
2|Page
Layer wise compaction has
been checked & jointly signed.
Category/ Location:Convention
5. Finding:Post Concrete status- Bulging
of Footing side FC523(Grid J/5)
Recommendation/Corrective/Preventive
Actions
- To use adequate & stiff formwork
with required supporting system.
- Chip out the bulged portion & make
good to the size of footing
Remediation Timeframe:
Immediate
3|Page
Category/ Location:Convention Building
6. Finding: Shrinkage Cracks on concrete
surface
Recommendation/Corrective/Preventive
Actions
- Concrete Surface should be kept
moist with gunny bags initially&
once concrete gets dry ,surface
should be ponded /poured with
water
Remediation Timeframe:
Immediate
Corrective actions taken
We covered it with gunny bags &
poured water & we definitely not
repeat this mistake in future.
Category/ Location:Cosa 1 B
7. Finding: Honey combing of RCC
column
Honeycomb observed at Column (Grid
M/25)
Recommendation/Corrective/Preventive
Actions
- No cement slurry come out of
formwork but putting form on joints
- To ensure proper vibration of
concrete with adequate size of
needle
- To chip off all loose concrete and
grout with GP-2
Remediation Timeframe:
Immediate
Corrective actions taken
We chipped of all the loose concrete
& repair it with GP-2 Material, We
assure you to do proper vibration with
adequate size of needle.
4|Page
5|Page