You are on page 1of 9

Protection, substation automation, power quality and measurements  6.

2 Protection systems

6.2.3 Protection coordination


D
X
Typical applications and functions
X 3A
Relay operating characteristics and their settings must be C
carefully coordinated in order to achieve selectivity. The
aim is basically to switch off only the faulty component and X 2A
to leave the rest of the power system in service in order B
1 to minimize supply interruptions and to ensure stability X1A
(fig. 6.2-57).

2 Sensitivity
Protection should be as sensitive as possible in order to
detect faults at the lowest possible current level. At the
same time, however, it should remain stable under all R1A R 2A R 3A
3 permissible load, overload and through-fault conditions. A R
For more ­information: www.siemens.com / systemplanning.
The Siemens engineering programs SINCAL and SIGRADE
4 are especially designed for selective protection grading of
protection relay systems. They provide short-circuit calcula-
tions as well as international standard characteristics of
relays, fuses and circuit-breakers for easy protection Fig. 6.2-57: Operating characteristics of Siemens distance relays
5 grading with respect to motor starting, inrush phenomena,
and equipment damage curves.

6 Phase-fault overcurrent relays 12.0


The pickup values of phase overcurrent relays are normally 11.0
set 30 % above the maximum load current, provided that Rush
10.0
sufficient short-circuit current is available. This practice is N
9.0
7 recommended particularly for mechanical relays with reset 8.0
ratios of 0.8 to 0.85. Numerical relays have high reset 7.0
ratios near 0.95 and allow, therefore, about a10 % lower
6.0
8 setting. Feeders with high transformer and/or motor load
5.0
require special consideration.
4.0

Transformer feeders 3.0


9 The energizing of transformers causes inrush currents that 2.0
may last for seconds, depending on their size (fig. 6.2-58). 1.0
2 10 100 400
Selection of the pickup current and assigned time delay
10 have to be coordinated so that the inrush current decreases Rated transformer power (MVA)
below the relay overcurrent reset value before the set
operating time has elapsed. The inrush current typically Time constant of inrush current
contains only about a 50 % fundamental frequency compo- Nominal power (MVA) 0.5 … 1.0 1.0 … 10 > 10
11 nent. Numerical relays that filter out harmonics and the DC Time constant (s) 0.16 … 0.2 0.2 … 1.2 1.2 … 720
component of the inrush current can therefore be set to be
more sensitive. The inrush current peak values of Fig. 6.2-58: Peak value of inrush current

12 fig. 6.2-58 will be reduced to more than one half in this


case. Some digital relay types have an inrush detection residual-current relays in the start point connection of CTs
function that may block the trip of the overcurrent protec- cannot be used; in particular, with rated CT primary cur-
tion resulting from inrush currents. rents higher than 200 A. The pickup value of the zero-
sequence relay would be on the order of the error currents
Ground-fault protection relays of the CTs. A special core-balance CT is therefore used as
Earth-current relays enable a much more sensitive setting, the earth-current sensor. Core-balance CTs are designed for
because load currents do not have to be considered (except a ratio of 60 / 1 A. The detection of 6 A primary would then
4-wire circuits with 1-phase load). In solidly and low-resis- require a relay pickup setting of 0.1 A secondary. An even
tance earthed systems, a setting of 10 to 20 % rated load more sensitive setting is applied in isolated or Petersen coil
current can generally be applied. High-resistance earthing earthed systems where very low earth currents occur with
requires a much more sensitive setting, on the order of 1-phase-to-earth faults. Settings of 20 mA and lower may
some amperes primary. The earth-fault current of motors then be required depending on the minimum earth-fault
and generators, for example, should be limited to values current. The integrated sensitive directional earth-fault
below 10 A in order to avoid iron burning. In this case, function allows settings as low as 1 mA.

Edition 8.0  Power Engineering Guide  355


Protection, substation automation, power quality and measurements  6.2 Protection systems

Remark to ground-fault protection with cable-type current


10,000
transformers: The properties of a given cable-type current
transformer have to be observed. 1,000
Time in
seconds 100
The setting of IE> must have sufficient margin against the 10
maximum error current of the cable type CT.
1

1 Background: 0.1
Even in the case where the 3 conductors are centrally 0.01
bundled, when passing through the cable type CT, an error
0.001
2 current "I error" will arise in the secondary circuit. This error 0 1 2 3 4 5 6 7 8 9 10
current is generally proportional to load current flowing Current in multiplies of full-load amps
through the CT.
Motor starting current High set instantaneous O/C stage

3 In the case of non-bundled conductors or when the conduc-


Locked-rotor current
Overload protection
Motor thermal limit curve
Permissible locked-rotor time
tors are not in the center of the cable type CT, the error characteristic
current "I error" may be substantially larger.
4 Fig. 6.2-59: Typical motor current-time characteristics
Motor feeders
The energization of motors causes a starting current of
initially 5 to 6 times the rated current (locked rotor current).
5
A typical time-current curve for an induction motor is Time 51
shown in fig. 6.2-59.
6
In the first 100 ms, a fast-decaying asymmetrical inrush 51 51
current also appears. With conventional relays, it was
common practice to set the instantaneous overcurrent
7 stage of the short-circuit protection 20 to 30 % above the Main
0.2-0.4 seconds

locked rotor current with a short-time delay of 50 to Feeder


100 ms to override the asymmetrical inrush period. Maximum feeder fault level
Current

8
Numerical relays are able to filter out the asymmetrical Fig. 6.2-60: Coordination of inverse-time relays
current component very rapidly so that the setting of an
additional time delay is no longer applicable.
9 If the same characteristic is used for all relays, or if when
The overload protection characteristic should follow the the upstream relay has a steeper characteristic (e.g., very
thermal motor characteristic as closely as possible. The much over normal inverse), then selectivity is automatically
10 adaptation is made by setting the pickup value and the fulfilled at lower currents.
thermal time constant, using the data supplied by the
motor manufacturer. Furthermore, the locked-rotor protec- Differential relay
tion timer has to be set according to the characteristic Transformer differential relays are normally set to pickup
11 motor value. values between 20 and 30 % of the rated current. The
higher value has to be chosen when the transformer is
Time grading of overcurrent relays (51) fitted with a tap changer.
12 The selectivity of overcurrent protection is based on time
grading of the relay operating characteristics. The relay Restricted earth-fault relays and high-resistance
closer to the infeed (upstream relay) is time-delayed motor / generator differential relays are, as a rule, set to
against the relay further away from the infeed (down- about 10 % of the rated current.
stream relay). The calculation of necessary grading times is
shown in fig. 6.2-59 by an example for definite-time over- lnstantaneous overcurrent protection
current relays. This is typically applied on the final supply load or on any
protection relay with sufficient circuit impedance between
Inverse-time relays itself and the next downstream protection relay. The set-
For the time grading of inverse-time relays, in principle the ting at transformers, for example, must be chosen about
same rules apply as for the definite-time relays. The time 20 to 30 % higher than the maximum through-fault current.
grading is first calculated for the maximum fault level and The relay must remain stable during energization of the
then checked for lower current levels (fig. 6.2-60). transformer.

Edition 8.0  Power Engineering Guide  356


Protection, substation automation, power quality and measurements  6.2 Protection systems

Calculation example Load


The feeder configuration of fig. 6.2-61 and the associated A F4 B F3 C F2
13.8 kV/ Fuse: D F1
0.4 kV
load and short-circuit currents are given. Numerical over- 160 A
Load
current relays 7SJ80 with normal inverse-time characteris- 13.8 kV L.V. 75
625 kVA
tics are applied. 51 51 51 5.0 % Load
7SJ80 7SJ80 7SJ80
The relay operating times, depending on the current, can
1 be derived from the diagram or calculated with the formula Station Max. ISCC. max1 CT Ip / IN2 Iprim3 Iscc. max
I / Ip = ―――
load ratio
given in fig. 6.2-62, see next page. A A A
I prim

The Ip / IN settings shown in fig. 6.2-61 have been chosen to A 300 4,500 400 / 5 1.0 400 11.25
2
get pickup values safely above maximum load current. B 170 2,690 200 / 5 1.1 220 12.23
C 50 1,395 100 / 5 0.7 70 19.93
This current setting should be lowest for the relay farthest D – 523 – – – –
3 downstream. The relays further upstream should each have 1 ISCC. max = Maximum short-circuit current
equal or higher current settings. 2 I  / I = Relay current multiplier setting
p N
3I
prim = Primary setting current corresponding to Ip / IN

4 The time multiplier settings can now be calculated as


follows: Fig. 6.2-61: Time grading of inverse-time relays for a radial feeder

Station C:
5 •  For coordination with the fuses, the fault in location F1 is
considered.
The short-circuit current Iscc. max. related to 13.8 kV is
6 523 A.
This results in 7.47 for I / Ip at the overcurrent relay in
location C.
•  With this value and Tp = 0.05, an operating time of tA =
7 0.17 s can be derived from fig. 6.2-60.

This setting was selected for the overcurrent relay to get a


8 safe grading time over the fuse on the transformer low-
voltage side. Safety margin for the setting values for the
relay at station C are therefore:
•  Pickup current: Ip / IN = 0.7
9 •  Time multiplier: Tp = 0.05.

Station B:
10 The relay in B has a primary protection function for line B-C
and a backup function for the relay in C. The maximum
through-fault current of 1.395 A becomes effective for a
fault in location F2. For the relay in C, an operating time
11 time of 0.11 s (I / Ip = 19.93) is obtained.

It is assumed that no special requirements for short oper-


12 ating times exist, and therefore an average time grading
interval of 0.3 s can be chosen. The operating time of the
relay in B can then be calculated. The setting values for the relay at station B are:
•  Pickup current: Ip / IN = 1.1
• tB = 0.11 + 0.3 = 0.41 s •  Time multiplier Tp = 0.11
1,395 A
•  Value of Ip / IN = ―――― = 6.34 (fig. 6.2-61) Given these settings, the operating time of the relay in B
220 A for a close fault in F3 can also be checked: The short-circuit
•  W
 ith the operating time 0.41 s and Ip / IN = 6.34, current increases to 2,690 A in this case (fig. 6.2-69). The
Tp = 0.11 can be derived from fig. 6.2-70, see next page. corresponding I / Ip value is 12.23.

Edition 8.0  Power Engineering Guide  357


Protection, substation automation, power quality and measurements  6.2 Protection systems

•  W
 ith this value and the set value of Tp = 0.11, an
100
operating time of 0.3 s is obtained again (fig. 6.2-62).

Station A: t
50
•  Adding the time grading interval of 0.3 s, the desired 40
operating itme is tA = 0.3 + 0.3 = 0.6 s. 30

1 Following the same procedure as for the relay in station B,


20

the following values are obtained for the relay in station A: Tp [s]
•  Pickup current: Ip / IN = 1.0 10

2 •  Time multiplier Tp = 0.17 3.2


•  For the close-in fault at location F4, an operating time of 5
0.48 s is obtained. 4
1.6
3
3 The normal way
To prove the selectivity over the whole range of possible 2
0.8
short-circuit currents, it is normal practice to draw the set
4 of operating curves in a common diagram with double log 1
scales. These diagrams can be calculated manually and 0.4
drawn point-by-point or constructed by using templates.
0.50
0.2
5 Today, computer programs are also available for this pur-
0.4
0.3
pose. Fig. 6.2-63 shows the relay coordination diagram for
the selected example, as calculated by the Siemens pro- 0.2
0.1

6 gram SIGRADE (Siemens Grading Program).

0.1 0.05
Note:
To simplify calculations, only inverse-time characteristics
7 have been used for this example. About 0.1 s shorter 0.05
operating times could have been reached for high-current 2 4 6 8 10 20
faults by additionally applying the instantaneous zones I>>
[A]
8 of the 7SJ60 relays. p

Fig. 6.2-62: Normal inverse-time characteristic of the 7SJ60 relay

9 Setting range setting


IN
Bus-A
Ip = 0.10 – 4.00 IN Ip = 1.0 IN
10 400/5 A
Tp = 0.05 – 3.2 s
I>> = 0.1 – 25 IN
Tp = 0.17 s
I>> = ∞
52 7SJ80 Ip = 1.0 IN
Tp = 0.11 s
11 Bus-B
I>> = ∞
Ip = 0.10 – 4.00 IN
200/5 A Tp = 0.05 – 3.2 s
I>> = 0.1 – 25 IN

12 52 7SJ80

Ip = 0.7 IN
Bus-C
Tp = 0.05 s
I>> = ∞
100/5 A Ip = 0.10 – 4.00 IN
Tp = 0.05 – 3.2 s
52 7SJ80 I>> = 0.1 – 25 IN

13.8/0.4 kV
TR 625 kVA
5.0%

fuse VDE 160


HRC fuse 160 A

Fig. 6.2-63: Overcurrent-time grading diagram

Edition 8.0  Power Engineering Guide  358


Protection, substation automation, power quality and measurements  6.2 Protection systems

Coordination of overcurrent relays with fuses and low-


voltage trip devices Fault incidence BFI =
breaker failure
The procedure is similar to the above-described grading of Normal interrupting time
Current
initiation time
(intermediate
overcurrent relays. A time interval of between 0.1 and 0.2 s is detector relays, if any)
(50 BF)
usually sufficient for a safe time coordination (fig. 6.2-64). Protect. Breaker inter. reset time Margin BFT =
breaker failure
time time tripping time
Strong and extremely inverse characteristics are often more (1~) (2~) (1~) (2,5~) (auxilary relays,

1 suitable than normal inverse characteristics in this case.


[2~] [4~] [2~] [2,5~] if any)

Fig. 6.2-65 shows typical examples. 0,5~


(5~)
[8~]
0,5~
(2~)
[4~]

BFI BF timer (F) (62BF) BFT Adjacent


2 Simple distribution substations use a power fuse on the breaker
secondary side of the supply transformers (fig. 6.2-65a). Total breaker failure interrupting time int. time
(9~) [15~]

In this case, the operating characteristic of the overcurrent


3 relay at the infeed has to be coordinated with the fuse Fig. 6.2-64: Time coordination of BF time setting
curve.

4 Normalinverse
0.14 MV bus
t = ―――――― · Tp(s)
(I / Ip)0.02 – 1 Inverse-time relay
Time 51
5 Strong inverse characteristics may be used with expulsion-
type fuses (fuse cutouts), while extremely inverse versions Other Fuse
adapt better to current limiting fuses. consumers

6
In any case, the final decision should be made by plotting
n
the curves in the log-log coordination diagram. a
LV bus
7 Electronic trip devices of LV breakers have long-delay, Fuse 0.2 s
short-delay and instantaneous zones. Numerical overcur-
rent relays with one inverse-time and two definite-time Current
8 zones can closely be adapted to this (fig. 6.2-65b). a) Maximum fault available at HV bus

9 MV bus

50/51

10

11 a
n
LV bus

12

Fig. 6.2-65 a + b: Coordination of an overcurrent relay with an MV fuse


and low-voltage breaker trip device

Edition 8.0  Power Engineering Guide  359


Protection, substation automation, power quality and measurements  6.2 Protection systems

Coordination of distance relays


The distance relay setting must take into account the
limited relay accuracy, including transient overreach (5 %, Ope-
t
Z3A
rating 3
according to IEC 60255-6), the CT error (1 % for class 5P Z2A Z2B
time t 2
and 3 % for class 10P) and a security margin of about 5 %. Z1A Z1B Z1C
t1
Furthermore, the line parameters are often only calculated,
not measured. This is a further source of errors. A setting of ZL A-B ZL B-C ZLC-D
1 80 to 85 % is therefore common practice; 80 % is used for A B C D
Load Load Load
mechanical relays, while 85 % can be used for the more
accurate numerical relays.
Z1A = 0.85 · ZLA–B
2 Z2A = 0.85 · (ZLA–B + Z1B)
Where measured line or cable impedances are available,
Z2A = 0.85 · (ZLA–B + Z2B)
the protected zone setting may be extended to 90 %. The
second and third zones have to keep a safety margin of Fig. 6.2-66: Grading of distance zones
3 about 15 to 20 % to the corresponding zones of the fol-
lowing lines. The shortest following line always has to be
considered (fig. 6.2-66). Operating time
52M
4
As a general rule, the second zone should at least reach
51M
20 % over the next station to ensure backup for busbar
faults, and the third zone should cover the longest fol- 52F 52F
5 lowing line as backup for the line protection.
51F 51F
Grading of zone times 0.2-0.4
6 The first zone normally operates undelayed. For the grading Time grading
of the time delays of the second and third zones, the same Fault Fault Interruption of
rules as for overcurrent relays apply (fig. 6.2-67). For the inception detection fault current
quadrilateral characteristics (relays 7SA6 and 7SA5), only t 51F t 52F
7 the reactance values (X values) have to be considered for Set time delay
Circuit-breaker
interruption time
the protected zone setting. The setting of the R values
should cover the line resistance and possible arc or fault Overshoot*
t OS Margin tM
8 resistances. The arc resistance can be roughly estimated as
follows: t 51M
*also called overtravel or coasting time
2.5 · larc
9 RArc = ———— [Ω] Time grading
ISCC Min
trs = t51M – t51F = t52F + tOS + tM
larc = Arc length in mm Example 1 tTG =0.10 s + 0.15 s + 0.15 s = 0.40 s
10 ISCC Min = Minimum short-circuit current in kA Oil circuit-breaker t52F = 0.10 s

•  T
 ypical settings of the ratio R / X are: Mechanical relays tOS = 0.15 s
–– Short lines and cables (≤ 10 km): R / X =2 to 6 Safety margin for
11 –– Medium line lengths < 25 km: R / X =2 measuring errors, etc. tM = 0.15 s
–– Longer lines 25 to 50 km: R / X =1. Example 2 tTG = 0.08 + 0.02 + 0.10 = 0.20 s
Vacuum circuit-breaker t52F = 0.08 s
12 Shortest feeder protectable by distance relays Numerical relays tOS = 0.02 s
The shortest feeder that can be protected by underreaching
Safety margin tM = 0.10 s
distance zones without the need for signaling links depends
on the shortest settable relay reactance. Fig. 6.2-67: Time grading of overcurrent-time relays

VTratio
XPrim Min = XRelay Min · ———
CTratio

XPrim Min
lmin = ————
X’Line

The shortest setting of the numerical Siemens relays is


0.05 Ω for 1 A relays, corresponding to 0.01 Ω for 5 A
relays. This allows distance protection of distribution cables
down to the range of some 500 meters.

Edition 8.0  Power Engineering Guide  360


Protection, substation automation, power quality and measurements  6.2 Protection systems

Breaker failure protection setting


50BF
Most numerical relays in this guide provide breaker failure
(BF) protection as an integral function. The initiation of the
BF protection by the internal protection functions then
takes place via software logic. However, the BF protection 50BF
function may also be initiated externally via binary inputs A
by an alternate protection. In this case, the operating time N
1 of intermediate relays (BFI time) may have to be consid-
P1
O
D

ered. Finally, the tripping of the infeeding breakers requires R


P1: primary P 2: alternate P2
auxiliary relays, which add a small time delay (BFI) to the protection protection
2 overall fault clearing time. This is particularly the case with
one-breaker-and-a-half or ring bus arrangements where a Fig. 6.2-68: Breaker failure protection, logic circuit
separate breaker failure relay (7VK8) is used per breaker.

3 The decisive criterion of BF protection time coordination is


the reset time of the current detector (50BF), which must not •  Measuring cores
be exceeded under any condition during normal current These are normally specified with 0.2 % or 0.5 % accuracy
4 interruption. The reset times specified in the Siemens numer- (class 0.2 or class 0.5), and an rated symmetrical short-
ical relay manuals are valid for the worst-case condition: circuit current limiting factor FS of 5 or 10.
interruption of a fully offset short-circuit current and low The required output power (rated burden) should be
current pickup setting (0.1 to 0.2 times rated CT current). higher than the actually connected burden. Typical
5 values are 2.5, 5 or 10 VA. Higher values are normally
The reset time is 1 cycle for EHV relays (7SA8, 7VK8) and not necessary when only electronic meters and recorders
1.5 to 2 cycles for distribution type relays (7SJ**). are connected.
6 A typical specification could be: 0.5 FS 10, 5 VA.
Fig. 6.2-68 shows the time chart for a typical breaker •  Cores for billing values metering
failure protection scheme. The stated times in parentheses In this case, class 0.25 FS is normally required.
apply for transmission system protection and the times in •  Protection cores
7 square brackets for distribution system protection. The size of the protection core depends mainly on the
maximum short-circuit current and the total burden
CT requirements for protection relays (internal CT burden, plus burden of connected lines, plus
8 relay burden). Furthermore, a transient dimensioning
Instrument transformers factor has to be considered to cover the influence of the
Instrument transformers must comply with the applicable DC component in the short-circuit current.
IEC recommendations IEC 60044 and 60186 (PT),
9 ANSI / IEEE C57.13 or other comparable standards. The requirements for protective current transformers
(fig 6.2-69 and fig. 6.2-70, see next pages) for transient
Voltage transformers performance are specified in IEC 60044-6. In many practical
10 Voltage transformers (VT) in single-pole design for all cases, iron-core CTs cannot be designed to avoid saturation
primary voltages have typical single or dual secondary under all circumstances because of cost and space reasons,
windings of 100, 110 or 115 V / √3, with output ratings particularly with metal-enclosed switchgear.
between 10 and 50 VA suitable from most applications
11 with digital metering and protection equipment, and accu- The Siemens relays are therefore designed to tolerate
racies of 0.1 % to 6 % to suit the particular application. CT saturation to a large extent. The numerical relays pro-
Primary BIL values are selected to match those of the asso- posed in this guide are particularly stable in this case due to
12 ciated switchgear. their integrated saturation detection function. The current
transformer requirements for SIPROTEC 7UT8 transformer
Current transformers protection devices are given as an example in order to
Current transformers (CT) are usually of the single-ratio provide an overview aout how to handle CT requirements
type with wound or bar-type primaries of adequate thermal during protection calculation.
rating. Single, double or triple secondary windings of 1 or
5 A are standard. 1 A rating should, however, be preferred, For all SIPROTEC 5 devices, detailed requirement tables are
particularly in HV and EHV substations, to reduce the included in the device manuals.The latest manual version
burden of the connected lines. Output power (rated burden should be used for the CT requirement calculation.
in VA), accuracy and saturation characteristics (rated sym-
metrical short-circuit current limiting factor) of the cores More accurate dimensioning can be done by more intensive
and secondary windings must meet the requirements of the calculation with Siemens’ CTDIM (www.siemens.com/
particular application.The CT classification code of IEC is ctdim) program. Results of CTDIM are released by the relay
used in the following: manufacturer.

Edition 8.0  Power Engineering Guide  361


Protection, substation automation, power quality and measurements  6.2 Protection systems

10

11

12

Fig. 6.2-69: Requirements for current transformer

Edition 8.0  Power Engineering Guide  362


Protection, substation automation, power quality and measurements  6.2 Protection systems

10

11

12

Fig. 6.2-70: Requirements for current transformer

For further information please visit:


siemens.com/protection

Edition 8.0  Power Engineering Guide  363

You might also like