Project Execution Canopy - New
Project Execution Canopy - New
Item Months
No. Major project activities Start date Finish date Nov, 2014
A Mobilization November, 19 January, 03
B Installation December, 07 February, 21
C Commissioning February, 26
4) Major Elements:
Total
Item Required
No Description Quantity Completed % Total weightRemark
(Pcs) Status (Kg)
1 Rafters 100% ###
2 Outside Columns 100% ###
3 Intermediate Columns 100% ###
4 Gable side Columns 100% ###
5 Partition Columns 100% ###
6 Purline with accessories 90% ### Drilling a hole for bracing on progress
7 Girts with accessories 90% ### Drilling a hole for bracing on progress
8 Mezzanine Elements 80% ### Stair case manufacturing on progress
9 Doors and Windows 80% ###
10 Wall cladding material with accessories 20% ### Accessories manufacturing on progress
11 Roofing materials with accessories 20% ### Accessories manufacturing on progress
###
Item
No Description Available DifferenceRemark
A Machinery
1 Arc welding machines (Heavy duty) 3 0
2 Magnetic drills (Heavy duty) 1 0
3 Self tapping drilling machines, rechargable 4 0
4 Self tapping drilling machines, electrical 6 0
5 Hand grinding machine, 180mm 3 0
6 Hand grinding machine, 120mm 5 0
7 Rivet gun 10 0
8 Tool Kit set 2 0
9 Common size wrenches, M14, 16, 20, 24 20 each 0
10 Scaffolding 4 0
11 Power distribution boxes 4 0
11 Extension cable low Voltage 4 0
12 Generator, 30 KVA 1 0
13 Double cabin pickup 1 0
14 Mobile crane (25 ton) 1 0 Property of Wanza
15 Self-loading crane (5-8 ton) 0 3 on rental basis
1) Contact Person on the client side, Cap. Kinfe Yirga, Mobile 091 075 6368 7) Communication
2) Contact Person on the consultant side,
a) Design office Fikremariam Mengistu, Mobile 091 177 6751
b) Project site Mulugeta, Mobile 092 309 8381
2) Contact Person on the KOSPI side, Client
* Project Officer
a) Project Manager Solomon Zewdie, Mobile 091 1610303
b) Project Engineer Melese Masresha 092 309 8381
3) Legal issue Construction permit secured by the client
4) Accommedation Team shall be given perdiem. Cafeteria and residence on retal basis
available around the project site KOSPI Consultant
* Project
5) Project site transportation service One own pickup vehicle shall be assigned * Project Manager Engineer
6) Safety issues All the necessary safety materials and First Aid Kit shall *Project Engineer * Site Engineer
Project Execution Plan
Project - 431
Project description: Fabrication and Installation of Engine factory Workshop Building Superstructure
Size: 51mx131m
Location: Mekele
Project value: Birr 19,569,855
Promised delivery schedule: 180 days
Terms of payment: 30% advance, 35% (50% fabrication), 14% (100% fabrication), 14% (100% installation), 7% (provisional acceptance)
Item Months
No. Major project activities Start date Finish date April, 2014 May, 2014 June, 2014 July, 2014 August, 2014
A Design April, 11 May, 08
B Procurement May, 02 May, 21
C Fabrication April, 24 August, 19
D Mobilization July, 11 August, 26
E Installation July, 24 October, 13
F Commissioning October, 13
Total
Item required
No Description no. Available Difference Remark
A Machinery
1 MIG welding machines 6 3 3 3 to be procured locally
2 Arc welding machines (Heavy duty) 3 3 0
3 Air compressor 2 1 1 1 unit to be procured locally
4 Magnetic drills (Heavy duty) 2 1 1 1 unit to be procured locally
5 Self tapping and drilling machines 10 4 6 6 to be procured locally
6 Shearing machine (Heavy duty) 1 1 0
7 Press break 1 1 0
B Vehicles and handling equipment
1 Double cabin pickup 1 1 0
2 Mobile crane (25 ton) 1 1 0 Property of Wanza
3 Self-loading crane (5-8 ton) 3 0 3 Rental
4 Forklift 1 1 0
gust, 2014 September, 2014 October, 2014
Installation
Installation Team Leader:
1) Kedir Habib
Team of erection technicians:
1) Girma Bizuneh
2) Tesfaye Abrha
3) Sitotaw Tilahun
4) Zewdu Feleke
5) Mesfin Getahun
6) Mesfin Mekonnen
7) Biruk Bekele
8)
13 Technicians & 6 Assistant
Technicians to be recruited
Remark
Remark
ocally
ed locally
ed locally `
ocally
Project Execution Plan
Project - B
Project description: Adama Micro Cluster Metal Workshop Building Super-structure
Size: 48mx60m
Location: Adama
Project value: Birr 9,511,783
Promised delivery schedule: 120 days
Terms of payment: 80% advance, 10% (100% fabrication), 10% (100% installation)
Item Months
No. Major project activities Start date Finish date April, 2014 May, 2014 June, 2014 July, 2014 August, 2014
A Design April, 14 May, 07
B Procurement April, 22 May, 20
C Fabrication April, 22 June, 24
D Mobilization June, 12 June, 25
E Installation June, 17 August, 11
F Commissioning August, 11
Total
Item required
No Description no. Available Difference Remark
A Machinery
1 MIG welding machines 3 3 0 3 to be procured locally
2 Arc welding machines (Heavy duty) 3 3 0
3 Air compressor 1 1 0 1 unit to be procured locally
4 Magnetic drills (Heavy duty) 1 1 1 1 unit to be procured locally
5 Self tapping and drilling machines 5 2 3 6 to be procured locally
6 Shearing machine (Heavy duty) 1 1 0
7 Press break 1 1 0
B Vehicles and handling equipment
1 Double cabin pickup 1 1 0
2 Mobile crane (25 ton) 1 1 0 Rental
3 Self-loading crane (5-8 ton) 1 0 3 Rental
4 Forklift 1 1 0
gust, 2014
Installation
Installation Team Leader:
1) Tilahun Gossaye
Team of erection technicians:
1) Legesse Ayalew
2) Teshome Tadesse
3) Teshome Tafesse
4) Tewodros Shimelis
5) Yismashewa
6) Gebru
7) Fasil Belay
8) Samuel H/Giorgis
Remark
Remark
ocally
ed locally
ed locally
ocally
Erection Execution Plan
MHA STADIUM, Canopy A
Project - 450
1) General
Project description: Fabrication and Installation of Stadium Canopy
Size: 29.7mx102m
Location: Woldia .
Project value: Birr 19,315,538
Promised delivery schedule: 136 days
Contract date:
Terms of payment:
2) Project execution schedule:
Item Months
No. Major project activities Start date Finish date January, 2015 February, 2015 March, 2015 April, 2015 May-15
D Mobilization January, 25 March, 4
E Installation February, 24 April, 26
F Commissioning February, 27
4) Major Elements:
Item
No Description Total Required Quantity Completed % Total Weight Remark
(Pcs) Status (Kg)
1 Front Colums 40 100% 9,878
2 Rear Columns 8 100% 13,666
3 Primary Rafters 8 100% 48,122
4 Secondary Rafters 12 100% 39,315
5 Front Girders 19 95% 10260
6 Parapet Frames Set 100% 3,760
7 Polycarbonate panels, 18mm 3560 100% 10,324
8 Purlins and Girts 491 100% 17,302
9 Gutters, trims, down pipe, etc. Set 0%
Total
Item required
No Description no. Available Difference Remark
A Machinery
1 Arc welding machines (Heavy duty) 2 2 0
2 Magnetic drills (Heavy duty) 1 0 1 1 to be procured locally
3 Hand grinding machine, 180mm 3 3 0
4 Scaffolding 2 1 1 1 Set to be rented locally
5 Power distribution boxes 2 2 0
6 Tool Kit set 1 1 0
7 Extension cable low Voltage 200m 200m 0
Common size wrenches, M14, 16, 20, 24
8 Torque wrench 2 0 2 2 to be procured locally
Months
Item No. Major project activities Start date Finish date June, 2014 July, 2014 August, 2014 September, 2014 Octobe
A Design June, 05 July, 23
B Procurement June, 18 October, 14
C Fabrication July, 31 November, 18
D Mobilization October, 14 December, 17
E Installation December, 03 January, 26
F Commissioning January, 27
Total
Item required
No Description no. Available Difference R
A Machinery
1 MIG welding machines 4 3 1 1 to be procured locall
2 Arc welding machines (Heavy duty) 3 3 0
3 Air compressor 1 1 0
4 Magnetic drills (Heavy duty) 2 1 1 1 unit to be procured l
5 Self tapping and drilling machines 10 4 6 6 to be procured locall
6 Shearing machine (Heavy duty) 1 1 0
7 Press break 1 1 0
B Vehicles and handling equipment
1 Double cabin pickup 1 1 0
2 Mobile crane (60 ton) 1 0 1 to be acquired on rent
3 Self-loading crane (5-8 ton) 1 0 1 to be acquired on rent
4 Forklift 1 1 0
October, 2014 November, 2014 December, 2014 January, 2015
Installation
Installation Team Leader:
1) Kedir Habib
Team of erection technicians:
1) Girma Bizuneh
2) Tesfaye Abrha
3) Sitotaw Tilahun
4) Zewdu Feleke
5) Mesfin Getahun
6) Mesfin Mekonnen
7) Biruk Bekele
8) 6 Assistants to be recruited
Shortage Remark
(Tons)
0
5 Available in local market
0
0
0
0
0
500 m Available in local market
0
Remark
red locally
rocured locally
red locally
d on rental basis
d on rental basis
Erection Execution Plan
1) General Project - 000
Project description: Fabrication and Installation of Engine Component Workshop Building Superstructure
Size: 40.4mx90.2m
Location: Mekele
Project value: Birr 14,178,458
Promised erection schedule: 150 days
Terms of payment: 30% advance, 35% (50% fabrication), 14% (100% fabrication), 14% (100% installation), 7% (provisional acceptance)
Item Months
No. Major project activities Start date Finish date March, 2015 April, 2015 May, 2015 June, 2015 July, 2015 August, 2015
A Design March, 01 March, 20
B Procurement March, 18 April, 01
C Fabrication April, 01 June, 15
D Mobilization May, 20 June, 30
E Installation June, 07 July, 30
F Commissioning August, 03
Total
Item required
No Description no. Available Difference Remark
A Machinery
1 Arc welding machines (Heavy duty) 3 3 0
2 Magnetic drills (Heavy duty) 1 1 0
3 Self tapping drilling machines, rechargable 4 4 0
4 Self tapping drilling machines, electrical 6 6 0
5 Hand grinding machine, 180mm 3 3 0
6 Hand grinding machine, 120mm 5 5 0
7 Rivet gun 10 10 0
8 Tool Kit set 2 2 0
9 Common size wrenches, M14, 16, 20, 24 20 each 20 each 0
10 Scaffolding 4 4 0
11 Power distribution boxes 4 4 0
11 Extension cable low Voltage 4 4 0
12 Generator, 30 KVA 1 1 0
13 Double cabin pickup 1 1 0
14 Mobile crane (25 ton) 1 1 0 Property of Wanza
15 Self-loading crane (5-8 ton) 3 0 3 on rental basis
1) Contact Person on the client side, Cap. Kinfe Yirga, Mobile 091 075 6368 7) Communication
2) Contact Person on the consultant side,
a) Design office Fikremariam Mengistu, Mobile 091 177 6751
b) Project site Mulugeta, Mobile 092 309 8381
Client
2) Contact Person on the KOSPI side, * Project Officer
a) Project Manager Solomon Zewdie, Mobile 091 1610303
b) Project Engineer Melese Masresha 092 309 8381
3) Legal issue Construction permit secured by the client
4) Accommedation Team shall be given perdiem. Cafeteria and residence on retal basis
available around the project site KOSPI Consultant
* Project Engineer
5) Project site transportation service One own pickup vehicle shall be assigned * Project Manager * Site Engineer
6) Safety issues All the necessary safety materials and First Aid Kit shall be provided *Project Engineer
Erection Execution Plan
Pharma cure NOC S/S Canopy
1) General
Project description: Fabrication and Installation of Pharmacure NOC, S/S Canopy
Location: Addis Ababa , Summit, Pharmacure NOC, S/S ( SIZE: 32.6 x16.2m) .
Project value: Birr 2,146,893.05 including VAT
Delivery schedule:
Terms of payment: 50% in advance, 30 % up on delivery of materials on the project site and the final 20% up on completion
2) Project execution schedule:
6
B Errection of External Facia Board 26-Jun-2021 2-Jul-2021 0%
6
C Errection internal Facia bord and Internal Beam Cover 3-Jul-2021 9-Jul-2021 0%
8
D Electrical Lighting system Instalation 3-Jul-2021 12-Jul-2021 0%
9
E Chack & Painting for internal & external Fcaial board 3-Jul-2021 13-Jul-2021 0%
2
F Roof Trim works 12-Jul-2021 13-Jul-2021 0%
4%
Prepared By;GetahunD Approved By:Andualem M.
N.B:- the schedule depondes on matriale supply