Item No. Description Unit Qty %
5/31 6/8 6/9 6/10 6/11 6/12 6/13 6/14 6/15 6/16 6/17 6/18 6/19 6/20 6/21 6/22 6/23 6/24 6/25 6/26 6/27 6/28 6/29 6/30 7/1 7/2 7/3 7/4 7/5
A MAEC SWITCHING STATION
Fab/install rebars at Gantry Footing 2,049.60 100% P 293 293 293 293 293 293 293
7 kgs.
/pedestal incl. ground rod /cables 1,171.20 57.14% A 293 293 293 293
sched
Item No. Description Unit Qty %
5/31 6/8 6/9 6/10 6/11 6/12 6/13 6/14 6/15 6/16 6/17 6/18 6/19 6/20 6/21 6/22 6/23 6/24 6/25 6/26 6/27 6/28 6/29 6/30 7/1 7/2 7/3 7/4 7/5
C HV CONTROL BUILDING
Backfilling & compaction around cu.m. 1,380.21 100% P 173 173 173 173 173 173 173 173
13
footing (up to Elev 4.55) 0.00 0% A
38.77 100% P 12.9 12.9 12.9
14 Fab/install bottom forms of FTB-2 sq.m.
0.00 0% A
Fab/Install Rebars for FTB-2 incl 2,274.00 100% P 758 758 758
15 kgs.
grounding cables to col vert bars 0.00 0% A
Fab/Install FTB-2 Side forms incl 77.55 100% P 25.8 25.8 25.8
16 sq.m.
Columns 0.00 0% A
Concreting of FTB-2 incl columns 11.38 100% P 5.69 5.69
17 cu.m.
below 0.00 0% A
Fab/install bot forms Plinth Beam 11.04 100% P 3.68 3.68 3.68
18 Sq.m.
around perimeter column 0.00 0% A
Fab/install formworks at 12.87 100% P 6.4 6.4
19 Sq.m.
column_2nd lift (interion column) 0.00 0% A
0.97 100% P 1.0
20 Concreting of Col_2nd lift (interior) cu.m.
0.00 0% A
Fab/install PB rebars (perimeter 840.00 100% P 280
21 kgs.
column) 0.00 0% A
Note: Just unhide the rows and columns to see full sched upto concrete roof deck slab
D PV MAIN CONTROL BUILDING
10 Concreting of FTB-1 cu.m. 22.00 100% A 22
Fab/install formworks at 95.76 100% P 31.9 31.9 31.9
11 sq.m.
Column_1st lift 63.84 67% A 31.9 31.9
8.38 100% P 4.19 4.19
12 Concreting of Columns _1st lift cu.m.
0.00 0% A
Backfill around Columns up to FTB-2 1,704.62 100% P 142 142 142 142 142 142 142 142 142 142 142 142
13 cu.m.
(NGL) 0.00 0% A
80.85 100% P 27 27 27
14 Fab/install bottom forms of FTB-2 sq.m.
0.00 0% A
6,067.00 125% P 1517 1517 1517 1517
15 Fab/Install Rebars for FTB-2 kgs.
0.00 0% A
Note: Just unhide the rows and columns to see full sched upto concrete roof deck slab
E O&M BUILDING
22.96 100% P 7.65 7.65 7.65
4 Scaffoldings /formworks at Col Ftg sq.m.
22.96 100% A 7.65 7.65 7.65
3,126.86 100% P 782 782 782 782
5 Fab/Install Ftg & Col Rebars kgs.
1,563.43 50% A 782 782
Note: Just unhide the rows and columns to see full sched upto concrete roof deck slab