GARCIA 2 SOLAR POWER PLANT PROJECT

Sub-con: JC ELECTROFIELDS POWER SYSTEM, INC.


Subject : THREE (3) WEEKS LOOK AHEAD SCHEDULE
### 9-Jun 16-Jun 23-Jun 30-Jun

sched
Item No. Description Unit Qty %
5/31 6/8 6/9 6/10 6/11 6/12 6/13 6/14 6/15 6/16 6/17 6/18 6/19 6/20 6/21 6/22 6/23 6/24 6/25 6/26 6/27 6/28 6/29 6/30 7/1 7/2 7/3 7/4 7/5
A MAEC SWITCHING STATION
Fab/install rebars at Gantry Footing 2,049.60 100% P 293 293 293 293 293 293 293
7 kgs.
/pedestal incl. ground rod /cables 1,171.20 57.14% A 293 293 293 293

15.91 100% P 15.9


8 Concreting of Gantry footing cu.m.
0.00 0.00% A
Fab/install forms at Gantry 81.00 100% P 27 27 27
9 sq.m.
pedestal_1st lift 0.00 0.00% A
Concreting of Gantry pedestal_1st 31.50 100% P 15.8 15.8
10 cu.m.
lift 0.00 0.00% A
113.69 100% P 28 28 28 28
11 Backfill around Gantry footinhg cu.m.
0.00 0.00% A
Laying & Compaction of subbase at 32.02 100% P 4.0 4.0 4.0 4.0 4.0 4.0 4.0 4.0
4 cu.m.
Footing (HV equipment) 0.00 0% A
8.00 100% P 4 4
6 Lean concrete at HV Eqpt. Footing cu.m.
0.00 0% A
Fab/Install forms at Footing (HV 162.96 100% P 40.74 40.74 40.74 40.74
8 sq.m.
Eqpt) 0.00 0.00% A
Fab/install rebars at HV Eqpt. 3,412.80 100% P 426.6 426.6 426.6 426.6 426.6 426.6 426.6 426.6
10 Footing /pedestal incl. ground rod & kgs.
cables 0.00 0.00% A
48.02 100% P 12.01 12.01 12.01 12.01
12 Concreting of HV Eqpt footing cu.m.
0.00 0.00% A
Fab/install forms at HV eqpt. 315.90 100% P 53 53 53 53 53 53
14 sq.m.
Pedestal & Achor bolts 0.00 0.00% A
86.91 100% P 14.49 14.49 14.49
16 Concreting of HV Eqpt pedestal cu.m.
0.00 0.00% A
Formworks at Gantry Pedestal _2nd 27.00 100% P 13.5 13.5
17 sq.m.
lift 0.00 0.00% A
Install achor bolts & concreting of 10.50 100% P 5.3 5.3
18 cu.m.
Gantry pedestal_2nd lift 0.00 0.00% A
Backfilling & compaction around 330.66 100% P 55 55 55
19 cu.m.
footing (up to Elev 3.30) 0.00 0.00% A
Note: Just unhide the rows and columns to see full sched
B NSEC TAKE-OFF SUBSTATION
7.00 100% P 3.5 3.5
6 Fab/Install forms at Footing (Gantry) sq.m.
3.50 50% A 3.5

Fab/install rebars at Gantry Footing 469.15 100% P 235 235


7 kgs.
/pedestal incl. ground rod & cables 0.00 0% A
3.75 100% P 3.8
8 Concreting of Gantry footing cu.m.
0.00 0% A
Fab/install forms at Gantry 13.50 100% P 6.8 6.8
9 sq.m.
pedestal_1st lift 0.00 0% A
Concreting of Gantry pedestal_1st 5.25 100% P 5.3
10 cu.m.
lift 0.00 0% A
50.63 100% P 25 25
11 Backfill around Gantry footinhg cu.m.
0.00 0% A
Laying & compaction of subbase at 8.58 100% P 4.3 4.3
13 cu.m.
footing of PTR Pad & HV Eqpt 0.00 0% A
Lean concrete at PTR Pad & HV Eqpt 3.44 100% P 3.4
14 cu.m.
Footing 0.00 0% A
Fab/Install forms at Footing (HV 53.60 100% P 13.4 13.4 13.4 13.4
15 sq.m.
Eqpt & PTR) 0.00 0% A
Fab/install rebars at PTR Pad & HV 1,717.64 100% P 429.4 429.4 429.4 429.4
16 kgs.
Eqpt Ftg incl. ground rod & cables 0.00 0% A
Concreting of HV Eqpt footing & PTR 23.79 50% P 11.9
17 cu.m.
Pad 0.00 0% A
Fab/install forms at HV eqpt. 81.75 67% P 27 27
18 sq.m.
Pedestal & Achor bolts 0.00 0% A
24.13 100% P 24.1
19 Concreting of HV Eqpt pedestal cu.m.
0.00 0% A
Formworks at Gantry Pedestal _2nd 4.50 100% P 4.50
20 sq.m.
lift 0.00 0% A
Install achor bolts & concreting of 1.75 100% P 1.8
21 cu.m.
Gantry pedestal_2nd lift 0.00 0% A
Note: Just unhide the rows and columns to see full sched
### 9-Jun 16-Jun 23-Jun 30-Jun

sched
Item No. Description Unit Qty %
5/31 6/8 6/9 6/10 6/11 6/12 6/13 6/14 6/15 6/16 6/17 6/18 6/19 6/20 6/21 6/22 6/23 6/24 6/25 6/26 6/27 6/28 6/29 6/30 7/1 7/2 7/3 7/4 7/5
C HV CONTROL BUILDING
Backfilling & compaction around cu.m. 1,380.21 100% P 173 173 173 173 173 173 173 173
13
footing (up to Elev 4.55) 0.00 0% A
38.77 100% P 12.9 12.9 12.9
14 Fab/install bottom forms of FTB-2 sq.m.
0.00 0% A
Fab/Install Rebars for FTB-2 incl 2,274.00 100% P 758 758 758
15 kgs.
grounding cables to col vert bars 0.00 0% A
Fab/Install FTB-2 Side forms incl 77.55 100% P 25.8 25.8 25.8
16 sq.m.
Columns 0.00 0% A
Concreting of FTB-2 incl columns 11.38 100% P 5.69 5.69
17 cu.m.
below 0.00 0% A
Fab/install bot forms Plinth Beam 11.04 100% P 3.68 3.68 3.68
18 Sq.m.
around perimeter column 0.00 0% A
Fab/install formworks at 12.87 100% P 6.4 6.4
19 Sq.m.
column_2nd lift (interion column) 0.00 0% A
0.97 100% P 1.0
20 Concreting of Col_2nd lift (interior) cu.m.
0.00 0% A
Fab/install PB rebars (perimeter 840.00 100% P 280
21 kgs.
column) 0.00 0% A

Note: Just unhide the rows and columns to see full sched upto concrete roof deck slab
D PV MAIN CONTROL BUILDING
10 Concreting of FTB-1 cu.m. 22.00 100% A 22
Fab/install formworks at 95.76 100% P 31.9 31.9 31.9
11 sq.m.
Column_1st lift 63.84 67% A 31.9 31.9
8.38 100% P 4.19 4.19
12 Concreting of Columns _1st lift cu.m.
0.00 0% A
Backfill around Columns up to FTB-2 1,704.62 100% P 142 142 142 142 142 142 142 142 142 142 142 142
13 cu.m.
(NGL) 0.00 0% A
80.85 100% P 27 27 27
14 Fab/install bottom forms of FTB-2 sq.m.
0.00 0% A
6,067.00 125% P 1517 1517 1517 1517
15 Fab/Install Rebars for FTB-2 kgs.
0.00 0% A

Note: Just unhide the rows and columns to see full sched upto concrete roof deck slab
E O&M BUILDING
22.96 100% P 7.65 7.65 7.65
4 Scaffoldings /formworks at Col Ftg sq.m.
22.96 100% A 7.65 7.65 7.65
3,126.86 100% P 782 782 782 782
5 Fab/Install Ftg & Col Rebars kgs.
1,563.43 50% A 782 782

6.79 50% P 3.4


6 Concreting of Col footing cu.m.
0.00 0% A
9.89 100% P 3.3 3.3 3.3
7 Fab/install bottom forms of FTB-1 sq.m.
0.00 0% A
2,795.63 100% P 699 699 699 699
8 Fab/install FTB-1 Rebars kgs.
0.00 0% A
35.59 100% P 8.9 8.9 8.9 8.9
9 Fab/install side forms of FTB-1 sq.m.
0.00 0% A
4.45 100% P 2.225 2.225
10 Concreting of FTB-1 cu.m.
0.00 0% A
Fab/install formworks at 47.04 100% P 15.7 15.7 15.7
11 sq.m.
Column_1st lift 0.00 0% A
4.12 100% P 2.058 2.058
12 Concreting of Columns _1st lift cu.m.
0.00 0% A
9.89 100% P 3.3 3.3
13 Fab/install bottom forms of FTB-2 sq.m.
0.00 0% A

Note: Just unhide the rows and columns to see full sched upto concrete roof deck slab